SlideShare a Scribd company logo
1 of 16
RAJEEV INSTITUTE OF TECHNOLOGY
HASSAN
Department of Civil Engineering
TECHNICAL SEMINAR
on
“CASE STUDY ON SIGNATURE BRIDGE”
Under the guidance of
Mrs. RASHMI A S
Assistant Professor
Presented by:
TEJAS D A
4RA16CV107
1
2
CONTENTS
1. INTRODUCTION
2. COMPONENTS OF SIGNATURE BRIDGE
3. ASSESMENTS AND ERRECTION
4. CONCLUSION
3
Introduction
Signature bridge:
• The Signature Bridge is a cantilever spar cable-stayed bridge. It
spans the Yamuna river at Wazirabad section, connecting Wazirabad
to East Delhi.
• It is India's first asymmetrical cable-stayed bridge.
• The pylon of the Signature bridge is the tallest structure in Delhi
and is double the height of Qutb Minar with its 154-metre high
viewing box, which acts as selfie points for visitors. It shortens the
travel time between north and northeast Delhi.
• This bridge is self-anchored bridge in which cables are anchored at
the deck level. Main advantage of this self-anchored bridge is that it
allow transmission of forces from backstays to deck with rendering
the deck self-equilibrated in the longitudinal direction.
4
Signature bridge
Areal view of Signature bridge
Detail of the bridge
• Structural Design Firm: Schlaich Bergermann Partner
• Contractor: Joint Venture Gammon India[6][13] and Tensa India
Construtora Cidade
• Main span: 251 m
• Height of pylon: 165 m above ground
• Total length of infrastructure project: 6 km (approx.)
• Lanes: 2 x 4
• Deck surface: 25,000 m2
• Total length of bridge: 675 m (incl. 100 m west extension)
• Side spans: 36 m
• Structural steel pylon: 5800 tonne
• Structural steel deck: 7400 tonne
• Open foundation: 6 nos.
• Closed foundation: 16 nos.
5
Components of signature bridge
6
Detail of components
Foundation:
The final structure concluded for 23 foundation Out of which 16 wells of 8-9
m diameter sunk up to the level 500 mm above the highest rock level with
sixteen 1.20 m diameter piles inserted through the walls of the well embedded
up to 6m into rock on each wells, a combined tie beam of 4.5 m deep and 42 m
x 17.5 m sizes on top of the well connecting the wells, piles and piers
constructed on top of the same.
7
Bearings:
There are 20 free spherical bearings, two large fixed bearings under
pylon legs of the capacity of 17,000t, two numbers of longitudinally
guided spherical bearings at the location of expansion joimts to
enable reversible momvement of 270mm and rock bearing under
backstay anchor foundation, which can tranfere the tensile faorce of
6,380t within main cable stay system. The two inclined pillars merge
at half height of the pylon. Above that point, the backstay cables and
the inclined cables lead into the pylon.
.
Deck:
Two carriage way, typically 14m wide and separated by a concrete crash barriers as
well as two lateral emergency pathways, from the deck of the bridge that total 35.2m in
width. Each of the carriage way accommodates four traffic lanes. The deck is formed of
outer I-shaped longitudinal main girders at 4.5m intervals. A third central nain girder is
placed to distribute heavy truck loads onto the several cross girders. All structural steel
is grade S355. Shop welding and site splices with high strength friction grip bolts will
be used. The deck is transversally supported on both ends of the bridge and at the
pylon. The only longitudinal movement of the deck at its western end is 250mm
approximately.
Cables:
The deck is supported by two cable planes. The cables are directly anchored to
the webs of the outer main girders at 13.5 meter distances with their dead end,
and are stressed with in the stressing chamber at the top of the pylon. The
cables will be made up of bundles of parallel 0.6'' strands grsde 1770.
depending on the location the number of strands per cable varies from 55 to
123 no. at the main span end is 127no. for each of the backstays. corrosion
protection will be international practice i.e., with hot dip galvanized wires and
individually coated strands that are covered by an PEpipe. In the backstay area
the lower part of the cables will be covered with steel tubes for fire protection.
10
Fabrication
• Construction of the super structure involved fabrication and erection of about
14,500Mt of structural steel for permanent structure. The pylon with its harp shaped
body , leaning backwards, would be the most unstable structure during construction
stage.
• Pylon is complex structure having inclination in all directions. It is made up of
irregular pannels wleded out of varying steel plates of different grades. To
thoroughly understand the complexities of the structure , dimensional weights of
the elements to be fabricated, transported and erected, a true-to-scale digital model
of the bridge was prepared in Tekla.
• Some of the major challenges involved as using plat thickness ranging from 2.5 to
250mm including Z quality steel and drilling almost 8,50,000 holes for HSFG bolts
ranging from 12mm to 36mm in plates upto 120mm thick.
• To ensure fabrication accuracy many test were carried out like Dye penetration test,
ultrasonic test etc.
11
• Two methods for drilling of holes were specially devised. Pre-drilled holes on web
plate of the connection during panel fabrication and post-drilling for other holes
which are marked and drilled with template after fit-up, welding, rectification and
milling of segments.
• All the compression joints were designed to transfer load through bearing contact
surface along with the splice connection.
• The pylon included three parts; steel segments, main body , pylon head segments.
• Steel leg was divided into 11 large segments, main body was divided into 5 large
segments, front cable pylon was divide into 5 large segments.
• The fabrication of pylon included base fabrication, leg fabrication, main body
fabrication band back body segments fabrication.
• Fabrication and erection of segments were divided into 3 parts: panelling
fabrication, shop assembly and trial assembly bon site into large blocks for erection,
erection and bolt connection on site.
12
Erection
• The pylon is composed of two legs,box girders, inclined backwards and inward and
connected at a level of 63m by a main body that is vertical shaft with variable cross
section which hosts the top anchorages for the stay cables. The legs have
rectangular box girder with a constant width of 2.50m and height varying from 7.20
to 9.60m.
• The pylon was divided into segment with weights varying from 40t to 250t. The
joints between the segments were flanged bolted joints with machined flnages.
• After working out several alternative, it was proposed to erect pylon using 1,250t
crawler crane, while the pylon would be supported with a specially designed
temporary struts until the system is stable after installation of permanent cables.
Segments weighting more than 40t to 250t were required to be erected.
• Pre-cast deck panels were erected over girders using the Goliath gantry for deck
erection towards the river side .
• For correct positioning, with double inclination, of pylon segments was achieved by
a specially designed turn table.
13
• Structural geometry was checked at installation of every element and daily survey
procedure started at the beginning of stay caboe stressing.
• While monitoring the effect of construction lodings, element loadings and cable
stressing on deformation of pylon and decks, the following correction factors of the
environmental effects had to be applied. The pylon position changed rapidly during
the day, with movements around 20mm in the longitudinal and vertical direction
and upto 40mm in transverse direction.
• Stay cable consists of 19 pairs of cables with varying number of stands minimum
being 55 to maximun 127 of 15.70 mm dia with GUTS of 1,770Mpa.
• Stay cable strands preparation consists of pulling out the strand from coil drum,
laying on the bench , uncoating, cutting and marking for identification.
• Strands in the cables were tensioned using iso-elongation method. This method
utilise Moni strand jack attached with a load cell, hydraulic pump, dynamometer for
calibration of pump-jack system.
• A topographic survey of the bridge during each stressing phase was provided. After
reaching 80% of the stressing force in each phase, new elongation to be applied to
the strand had to be provided considering the actual load registered and the data
collected from the topographic survey.
14
Inference
It symbolises the standard for iconism in India.
3-dimensionally varying pylons being attempted
first time and over comes many other complex
issues by proper construction engineering.
15
16
THANK
YOU

More Related Content

What's hot

Non destructive test on concrete
Non destructive test on concreteNon destructive test on concrete
Non destructive test on concreteAglaia Connect
 
Inspection,Repair and Strengthening of PSC Bridge.
Inspection,Repair and Strengthening of PSC  Bridge.Inspection,Repair and Strengthening of PSC  Bridge.
Inspection,Repair and Strengthening of PSC Bridge.Mohammad Furqan
 
A project report on flyover internship bihar rajya pul nirman nigam limited p...
A project report on flyover internship bihar rajya pul nirman nigam limited p...A project report on flyover internship bihar rajya pul nirman nigam limited p...
A project report on flyover internship bihar rajya pul nirman nigam limited p...Prashant Shaurabh
 
Fibre reinforced concrete
Fibre reinforced concreteFibre reinforced concrete
Fibre reinforced concreteMOHIT PANCHAL
 
AN INTERNSHIP REPORT ON RESIDENTIAL BUILDING CONSTRUCTION
AN INTERNSHIP  REPORT  ON  RESIDENTIAL  BUILDING  CONSTRUCTIONAN INTERNSHIP  REPORT  ON  RESIDENTIAL  BUILDING  CONSTRUCTION
AN INTERNSHIP REPORT ON RESIDENTIAL BUILDING CONSTRUCTIONAbhishek Singh
 
Bar bending schedule(by akhil)
Bar bending schedule(by akhil)Bar bending schedule(by akhil)
Bar bending schedule(by akhil)Lamdade Akhil
 
Prestressing ppt
Prestressing pptPrestressing ppt
Prestressing pptSudhan Sathe
 
Tunnels ppt
Tunnels pptTunnels ppt
Tunnels ppt1971995
 
Presentation on Suspension Bridge
Presentation on Suspension BridgePresentation on Suspension Bridge
Presentation on Suspension Bridgemantukr4ever
 
INDUSTRIAL TRAINING OF FLYOVER CONSTRUCTION
INDUSTRIAL TRAINING OF FLYOVER CONSTRUCTIONINDUSTRIAL TRAINING OF FLYOVER CONSTRUCTION
INDUSTRIAL TRAINING OF FLYOVER CONSTRUCTIONBhavek Sharma
 
Concrete Road Pavement
Concrete Road Pavement Concrete Road Pavement
Concrete Road Pavement Awinash Tiwari
 
Polymer concrete and it's types
Polymer concrete and it's typesPolymer concrete and it's types
Polymer concrete and it's typesMONISHA K Y
 
PRESENTATION ON CASTING YARD OF LUCKNOW METRO
PRESENTATION ON CASTING YARD OF LUCKNOW METRO PRESENTATION ON CASTING YARD OF LUCKNOW METRO
PRESENTATION ON CASTING YARD OF LUCKNOW METRO Akanksha Priya
 
Design of Reinforced Concrete Structure (IS 456:2000)
Design of Reinforced Concrete Structure (IS 456:2000)Design of Reinforced Concrete Structure (IS 456:2000)
Design of Reinforced Concrete Structure (IS 456:2000)MachenLink
 
Creep of Rails.pdf
Creep of Rails.pdfCreep of Rails.pdf
Creep of Rails.pdfTVijayaGowri
 
Design of flexible pavement
Design of flexible pavementDesign of flexible pavement
Design of flexible pavementBhavik A Shah
 

What's hot (20)

PRE STRESSING
PRE STRESSINGPRE STRESSING
PRE STRESSING
 
Non destructive test on concrete
Non destructive test on concreteNon destructive test on concrete
Non destructive test on concrete
 
Inspection,Repair and Strengthening of PSC Bridge.
Inspection,Repair and Strengthening of PSC  Bridge.Inspection,Repair and Strengthening of PSC  Bridge.
Inspection,Repair and Strengthening of PSC Bridge.
 
A project report on flyover internship bihar rajya pul nirman nigam limited p...
A project report on flyover internship bihar rajya pul nirman nigam limited p...A project report on flyover internship bihar rajya pul nirman nigam limited p...
A project report on flyover internship bihar rajya pul nirman nigam limited p...
 
Fibre reinforced concrete
Fibre reinforced concreteFibre reinforced concrete
Fibre reinforced concrete
 
AN INTERNSHIP REPORT ON RESIDENTIAL BUILDING CONSTRUCTION
AN INTERNSHIP  REPORT  ON  RESIDENTIAL  BUILDING  CONSTRUCTIONAN INTERNSHIP  REPORT  ON  RESIDENTIAL  BUILDING  CONSTRUCTION
AN INTERNSHIP REPORT ON RESIDENTIAL BUILDING CONSTRUCTION
 
GGBS
GGBSGGBS
GGBS
 
4. wbm roads 10 sep
4. wbm roads 10 sep4. wbm roads 10 sep
4. wbm roads 10 sep
 
Bar bending schedule(by akhil)
Bar bending schedule(by akhil)Bar bending schedule(by akhil)
Bar bending schedule(by akhil)
 
Prestressing ppt
Prestressing pptPrestressing ppt
Prestressing ppt
 
Tunnels ppt
Tunnels pptTunnels ppt
Tunnels ppt
 
Presentation on Suspension Bridge
Presentation on Suspension BridgePresentation on Suspension Bridge
Presentation on Suspension Bridge
 
INDUSTRIAL TRAINING OF FLYOVER CONSTRUCTION
INDUSTRIAL TRAINING OF FLYOVER CONSTRUCTIONINDUSTRIAL TRAINING OF FLYOVER CONSTRUCTION
INDUSTRIAL TRAINING OF FLYOVER CONSTRUCTION
 
Concrete Road Pavement
Concrete Road Pavement Concrete Road Pavement
Concrete Road Pavement
 
Polymer concrete and it's types
Polymer concrete and it's typesPolymer concrete and it's types
Polymer concrete and it's types
 
PRESENTATION ON CASTING YARD OF LUCKNOW METRO
PRESENTATION ON CASTING YARD OF LUCKNOW METRO PRESENTATION ON CASTING YARD OF LUCKNOW METRO
PRESENTATION ON CASTING YARD OF LUCKNOW METRO
 
Design of Reinforced Concrete Structure (IS 456:2000)
Design of Reinforced Concrete Structure (IS 456:2000)Design of Reinforced Concrete Structure (IS 456:2000)
Design of Reinforced Concrete Structure (IS 456:2000)
 
Creep of Rails.pdf
Creep of Rails.pdfCreep of Rails.pdf
Creep of Rails.pdf
 
Design of flexible pavement
Design of flexible pavementDesign of flexible pavement
Design of flexible pavement
 
hot and cold weather concreting
hot and cold weather concretinghot and cold weather concreting
hot and cold weather concreting
 

Similar to Case study on signature bridge ppt (1)

Millau via duct presentation full analysis
Millau via duct presentation full analysisMillau via duct presentation full analysis
Millau via duct presentation full analysisMohammad Ali
 
Presentation on construction of cable stay bridge - a modern technique for su...
Presentation on construction of cable stay bridge - a modern technique for su...Presentation on construction of cable stay bridge - a modern technique for su...
Presentation on construction of cable stay bridge - a modern technique for su...Rajesh Prasad
 
Millau viaduct
Millau viaductMillau viaduct
Millau viaductPaurin Shah
 
Bandra Worli sea link
Bandra Worli sea linkBandra Worli sea link
Bandra Worli sea linkKAVYA H
 
Calculation note suez canal cable stayed bridge
Calculation note suez canal cable stayed bridgeCalculation note suez canal cable stayed bridge
Calculation note suez canal cable stayed bridgeMohammed Abdelkawy
 
Calculation Note Final
Calculation Note FinalCalculation Note Final
Calculation Note FinalMohamed Elfike
 
Nhpc training report civil engineerimg_bit_mesra_ISHANT GAUTAM
Nhpc training report civil engineerimg_bit_mesra_ISHANT GAUTAMNhpc training report civil engineerimg_bit_mesra_ISHANT GAUTAM
Nhpc training report civil engineerimg_bit_mesra_ISHANT GAUTAMIshant Gautam.
 
stress ribbon bridge.pptx
stress ribbon bridge.pptxstress ribbon bridge.pptx
stress ribbon bridge.pptxSauravShahane
 
Experimental study of precast portal frame
Experimental study of precast portal frameExperimental study of precast portal frame
Experimental study of precast portal frameSatish Kambaliya
 
BALANCED CANTILEVER BRIDGE
BALANCED CANTILEVER BRIDGEBALANCED CANTILEVER BRIDGE
BALANCED CANTILEVER BRIDGEsrinivas cnu
 
well foundation of six lane new ganga bridge near kacchi dargah in district P...
well foundation of six lane new ganga bridge near kacchi dargah in district P...well foundation of six lane new ganga bridge near kacchi dargah in district P...
well foundation of six lane new ganga bridge near kacchi dargah in district P...Arman Hashmi
 
Busan geoje fixed link
Busan   geoje fixed linkBusan   geoje fixed link
Busan geoje fixed linkVicky Matwan
 
Cable anchoring and grouting for cable tensioning
Cable anchoring and grouting for cable tensioningCable anchoring and grouting for cable tensioning
Cable anchoring and grouting for cable tensioningChinnuNinan
 
Bandra worli sealink pdf
Bandra worli sealink pdfBandra worli sealink pdf
Bandra worli sealink pdfDesireddy Manasa
 
Chenab Bridge.pdf
Chenab Bridge.pdfChenab Bridge.pdf
Chenab Bridge.pdfPpt Creater
 

Similar to Case study on signature bridge ppt (1) (20)

Millau via duct presentation full analysis
Millau via duct presentation full analysisMillau via duct presentation full analysis
Millau via duct presentation full analysis
 
THE CONSTRUCTION PROCEDURE AND ADVANTAGE OF THE RAIL CABLE-LIFTING CONSTRUCTI...
THE CONSTRUCTION PROCEDURE AND ADVANTAGE OF THE RAIL CABLE-LIFTING CONSTRUCTI...THE CONSTRUCTION PROCEDURE AND ADVANTAGE OF THE RAIL CABLE-LIFTING CONSTRUCTI...
THE CONSTRUCTION PROCEDURE AND ADVANTAGE OF THE RAIL CABLE-LIFTING CONSTRUCTI...
 
the millau viaduct
the millau viaductthe millau viaduct
the millau viaduct
 
Presentation on construction of cable stay bridge - a modern technique for su...
Presentation on construction of cable stay bridge - a modern technique for su...Presentation on construction of cable stay bridge - a modern technique for su...
Presentation on construction of cable stay bridge - a modern technique for su...
 
Millau viaduct
Millau viaductMillau viaduct
Millau viaduct
 
Bandra Worli sea link
Bandra Worli sea linkBandra Worli sea link
Bandra Worli sea link
 
Calculation note suez canal cable stayed bridge
Calculation note suez canal cable stayed bridgeCalculation note suez canal cable stayed bridge
Calculation note suez canal cable stayed bridge
 
Calculation Note Final
Calculation Note FinalCalculation Note Final
Calculation Note Final
 
Nhpc training report civil engineerimg_bit_mesra_ISHANT GAUTAM
Nhpc training report civil engineerimg_bit_mesra_ISHANT GAUTAMNhpc training report civil engineerimg_bit_mesra_ISHANT GAUTAM
Nhpc training report civil engineerimg_bit_mesra_ISHANT GAUTAM
 
stress ribbon bridge.pptx
stress ribbon bridge.pptxstress ribbon bridge.pptx
stress ribbon bridge.pptx
 
Cable stayed bridge
Cable stayed bridgeCable stayed bridge
Cable stayed bridge
 
Segmental bridge construction
Segmental bridge constructionSegmental bridge construction
Segmental bridge construction
 
Experimental study of precast portal frame
Experimental study of precast portal frameExperimental study of precast portal frame
Experimental study of precast portal frame
 
BALANCED CANTILEVER BRIDGE
BALANCED CANTILEVER BRIDGEBALANCED CANTILEVER BRIDGE
BALANCED CANTILEVER BRIDGE
 
Bridge-SIT-01.pptx
Bridge-SIT-01.pptxBridge-SIT-01.pptx
Bridge-SIT-01.pptx
 
well foundation of six lane new ganga bridge near kacchi dargah in district P...
well foundation of six lane new ganga bridge near kacchi dargah in district P...well foundation of six lane new ganga bridge near kacchi dargah in district P...
well foundation of six lane new ganga bridge near kacchi dargah in district P...
 
Busan geoje fixed link
Busan   geoje fixed linkBusan   geoje fixed link
Busan geoje fixed link
 
Cable anchoring and grouting for cable tensioning
Cable anchoring and grouting for cable tensioningCable anchoring and grouting for cable tensioning
Cable anchoring and grouting for cable tensioning
 
Bandra worli sealink pdf
Bandra worli sealink pdfBandra worli sealink pdf
Bandra worli sealink pdf
 
Chenab Bridge.pdf
Chenab Bridge.pdfChenab Bridge.pdf
Chenab Bridge.pdf
 

More from varun km

accelerated bridge construction(ABC)
accelerated bridge construction(ABC)accelerated bridge construction(ABC)
accelerated bridge construction(ABC)varun km
 
smart village report
smart village reportsmart village report
smart village reportvarun km
 
3 d printed building technology report
 3 d printed building technology report 3 d printed building technology report
3 d printed building technology reportvarun km
 
Accelerated Bridge Construction( ABC)
Accelerated Bridge  Construction( ABC)Accelerated Bridge  Construction( ABC)
Accelerated Bridge Construction( ABC)varun km
 
POLYETHYLENE CONCRETE
POLYETHYLENE CONCRETEPOLYETHYLENE CONCRETE
POLYETHYLENE CONCRETEvarun km
 
3d printed building technology
3d printed building technology3d printed building technology
3d printed building technologyvarun km
 

More from varun km (6)

accelerated bridge construction(ABC)
accelerated bridge construction(ABC)accelerated bridge construction(ABC)
accelerated bridge construction(ABC)
 
smart village report
smart village reportsmart village report
smart village report
 
3 d printed building technology report
 3 d printed building technology report 3 d printed building technology report
3 d printed building technology report
 
Accelerated Bridge Construction( ABC)
Accelerated Bridge  Construction( ABC)Accelerated Bridge  Construction( ABC)
Accelerated Bridge Construction( ABC)
 
POLYETHYLENE CONCRETE
POLYETHYLENE CONCRETEPOLYETHYLENE CONCRETE
POLYETHYLENE CONCRETE
 
3d printed building technology
3d printed building technology3d printed building technology
3d printed building technology
 

Recently uploaded

CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfAsst.prof M.Gokilavani
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...VICTOR MAESTRE RAMIREZ
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile servicerehmti665
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionDr.Costas Sachpazis
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxPoojaBan
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSCAESB
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AIabhishek36461
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx959SahilShah
 
microprocessor 8085 and its interfacing
microprocessor 8085  and its interfacingmicroprocessor 8085  and its interfacing
microprocessor 8085 and its interfacingjaychoudhary37
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort servicejennyeacort
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...srsj9000
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxDeepakSakkari2
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2RajaP95
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 

Recently uploaded (20)

CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptx
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
 
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Serviceyoung call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentation
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AI
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx
 
microprocessor 8085 and its interfacing
microprocessor 8085  and its interfacingmicroprocessor 8085  and its interfacing
microprocessor 8085 and its interfacing
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptx
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 

Case study on signature bridge ppt (1)

  • 1. RAJEEV INSTITUTE OF TECHNOLOGY HASSAN Department of Civil Engineering TECHNICAL SEMINAR on “CASE STUDY ON SIGNATURE BRIDGE” Under the guidance of Mrs. RASHMI A S Assistant Professor Presented by: TEJAS D A 4RA16CV107 1
  • 2. 2 CONTENTS 1. INTRODUCTION 2. COMPONENTS OF SIGNATURE BRIDGE 3. ASSESMENTS AND ERRECTION 4. CONCLUSION
  • 3. 3 Introduction Signature bridge: • The Signature Bridge is a cantilever spar cable-stayed bridge. It spans the Yamuna river at Wazirabad section, connecting Wazirabad to East Delhi. • It is India's first asymmetrical cable-stayed bridge. • The pylon of the Signature bridge is the tallest structure in Delhi and is double the height of Qutb Minar with its 154-metre high viewing box, which acts as selfie points for visitors. It shortens the travel time between north and northeast Delhi. • This bridge is self-anchored bridge in which cables are anchored at the deck level. Main advantage of this self-anchored bridge is that it allow transmission of forces from backstays to deck with rendering the deck self-equilibrated in the longitudinal direction.
  • 4. 4 Signature bridge Areal view of Signature bridge
  • 5. Detail of the bridge • Structural Design Firm: Schlaich Bergermann Partner • Contractor: Joint Venture Gammon India[6][13] and Tensa India Construtora Cidade • Main span: 251 m • Height of pylon: 165 m above ground • Total length of infrastructure project: 6 km (approx.) • Lanes: 2 x 4 • Deck surface: 25,000 m2 • Total length of bridge: 675 m (incl. 100 m west extension) • Side spans: 36 m • Structural steel pylon: 5800 tonne • Structural steel deck: 7400 tonne • Open foundation: 6 nos. • Closed foundation: 16 nos. 5
  • 7. Detail of components Foundation: The final structure concluded for 23 foundation Out of which 16 wells of 8-9 m diameter sunk up to the level 500 mm above the highest rock level with sixteen 1.20 m diameter piles inserted through the walls of the well embedded up to 6m into rock on each wells, a combined tie beam of 4.5 m deep and 42 m x 17.5 m sizes on top of the well connecting the wells, piles and piers constructed on top of the same. 7
  • 8. Bearings: There are 20 free spherical bearings, two large fixed bearings under pylon legs of the capacity of 17,000t, two numbers of longitudinally guided spherical bearings at the location of expansion joimts to enable reversible momvement of 270mm and rock bearing under backstay anchor foundation, which can tranfere the tensile faorce of 6,380t within main cable stay system. The two inclined pillars merge at half height of the pylon. Above that point, the backstay cables and the inclined cables lead into the pylon.
  • 9. . Deck: Two carriage way, typically 14m wide and separated by a concrete crash barriers as well as two lateral emergency pathways, from the deck of the bridge that total 35.2m in width. Each of the carriage way accommodates four traffic lanes. The deck is formed of outer I-shaped longitudinal main girders at 4.5m intervals. A third central nain girder is placed to distribute heavy truck loads onto the several cross girders. All structural steel is grade S355. Shop welding and site splices with high strength friction grip bolts will be used. The deck is transversally supported on both ends of the bridge and at the pylon. The only longitudinal movement of the deck at its western end is 250mm approximately.
  • 10. Cables: The deck is supported by two cable planes. The cables are directly anchored to the webs of the outer main girders at 13.5 meter distances with their dead end, and are stressed with in the stressing chamber at the top of the pylon. The cables will be made up of bundles of parallel 0.6'' strands grsde 1770. depending on the location the number of strands per cable varies from 55 to 123 no. at the main span end is 127no. for each of the backstays. corrosion protection will be international practice i.e., with hot dip galvanized wires and individually coated strands that are covered by an PEpipe. In the backstay area the lower part of the cables will be covered with steel tubes for fire protection. 10
  • 11. Fabrication • Construction of the super structure involved fabrication and erection of about 14,500Mt of structural steel for permanent structure. The pylon with its harp shaped body , leaning backwards, would be the most unstable structure during construction stage. • Pylon is complex structure having inclination in all directions. It is made up of irregular pannels wleded out of varying steel plates of different grades. To thoroughly understand the complexities of the structure , dimensional weights of the elements to be fabricated, transported and erected, a true-to-scale digital model of the bridge was prepared in Tekla. • Some of the major challenges involved as using plat thickness ranging from 2.5 to 250mm including Z quality steel and drilling almost 8,50,000 holes for HSFG bolts ranging from 12mm to 36mm in plates upto 120mm thick. • To ensure fabrication accuracy many test were carried out like Dye penetration test, ultrasonic test etc. 11
  • 12. • Two methods for drilling of holes were specially devised. Pre-drilled holes on web plate of the connection during panel fabrication and post-drilling for other holes which are marked and drilled with template after fit-up, welding, rectification and milling of segments. • All the compression joints were designed to transfer load through bearing contact surface along with the splice connection. • The pylon included three parts; steel segments, main body , pylon head segments. • Steel leg was divided into 11 large segments, main body was divided into 5 large segments, front cable pylon was divide into 5 large segments. • The fabrication of pylon included base fabrication, leg fabrication, main body fabrication band back body segments fabrication. • Fabrication and erection of segments were divided into 3 parts: panelling fabrication, shop assembly and trial assembly bon site into large blocks for erection, erection and bolt connection on site. 12
  • 13. Erection • The pylon is composed of two legs,box girders, inclined backwards and inward and connected at a level of 63m by a main body that is vertical shaft with variable cross section which hosts the top anchorages for the stay cables. The legs have rectangular box girder with a constant width of 2.50m and height varying from 7.20 to 9.60m. • The pylon was divided into segment with weights varying from 40t to 250t. The joints between the segments were flanged bolted joints with machined flnages. • After working out several alternative, it was proposed to erect pylon using 1,250t crawler crane, while the pylon would be supported with a specially designed temporary struts until the system is stable after installation of permanent cables. Segments weighting more than 40t to 250t were required to be erected. • Pre-cast deck panels were erected over girders using the Goliath gantry for deck erection towards the river side . • For correct positioning, with double inclination, of pylon segments was achieved by a specially designed turn table. 13
  • 14. • Structural geometry was checked at installation of every element and daily survey procedure started at the beginning of stay caboe stressing. • While monitoring the effect of construction lodings, element loadings and cable stressing on deformation of pylon and decks, the following correction factors of the environmental effects had to be applied. The pylon position changed rapidly during the day, with movements around 20mm in the longitudinal and vertical direction and upto 40mm in transverse direction. • Stay cable consists of 19 pairs of cables with varying number of stands minimum being 55 to maximun 127 of 15.70 mm dia with GUTS of 1,770Mpa. • Stay cable strands preparation consists of pulling out the strand from coil drum, laying on the bench , uncoating, cutting and marking for identification. • Strands in the cables were tensioned using iso-elongation method. This method utilise Moni strand jack attached with a load cell, hydraulic pump, dynamometer for calibration of pump-jack system. • A topographic survey of the bridge during each stressing phase was provided. After reaching 80% of the stressing force in each phase, new elongation to be applied to the strand had to be provided considering the actual load registered and the data collected from the topographic survey. 14
  • 15. Inference It symbolises the standard for iconism in India. 3-dimensionally varying pylons being attempted first time and over comes many other complex issues by proper construction engineering. 15