SlideShare a Scribd company logo
1 of 15
SUBMITTED BY :- PROJECT GUIDE :-
SOURAV GOSWAMI Mr. S.C MITRA
MVJ COLLEGE OF ENGINEERING, BANGALORE MANAGER –(PROJECT)
(02.01.2016 to 09.01.2016) RVNL - KOLKATA
ACKNOWLEDGEMENT
I would like to express my special thanks of gratitude to
Mr. Amit Kumar Roy (CPM/LINE, RVNL Kolkata),
Mr. Avijit Roy (GM/P, RVNL KOLKATA),
Mr. S.C.Mitra (MANAGER, PROJECT, RVNL KOLKATA), Staffs and
Supervisors of RVNL and GAMMON INDIA LIMITED who gave me
the golden opportunity to do this wonderful project on the topic
CONSTRUCTION OF METRO RAIL BRIDGE, which also helped me in
doing a lot of Research and I came to know about so many new things. I
am really thankful to them.
Lastly, I would also like to thank my parents who helped me a lot in
finalizing this project within the limited time frame.
SOURAV GOSWAMI
(PROJECT INTERN)
SUMMARY
The following project focuses on the viaduct and its various parts, describing
their individual characteristics as well as the methods being used for its
construction. The project was done in a brief span of seven days. The topics
discussed here were the subjects of my inspection. The Project was done as
summer internship under Rail Vikas Nigam Limited (RVNL), in association
with Gammon India Limited.
This internship has helped me gather practical knowledge of the onsite
activities that takes place while constructing a viaduct/bridge.
SOURAV GOSWAMI
( PROJECT INTERN )
CONTENT
1. BRIDGE
2. PILE
3. PILING ACTIVITY
4. PILE CAP
5. PIER
6. PIER CAP
7. BEARING
8. SEGMENT
9. SEISMIC RESTRAINER
10. CASH BARRIER
BRIDGE
A bridge is a structure built to span physical obstacles without closing the way
underneath such as a body of water, valley, or road, for the purpose of providing
passage over the obstacle. There are many different designs that all serve unique
purposes and apply to different situations. Designs of bridges vary depending on the
function of the bridge, the nature of the terrain where the bridge is constructed and
anchored, the material used to make it, and the funds available to build it. During
the design process, every bridge can be divided broadly into three parts:
-Superstructure.
-Substructure.
-Foundation.
MAJOR PARTS OF A BRIDGE
The major parts of a bridge are as follows:
- Pile.
- Pile Cap.
- Pier.
- Pier Cap.
- Bearing.
- Segment.
- Seismic Restrainer.
- Crash Barrier.
PILE
 There are three types of pile foundations according to their construction methods:
1.Driven piles, 2.Cast-in-situ piles, and 3.Driven and cast-in-situ piles.
 Pile foundation selection depends on the soil data received from soil exploration
bore holes at different depths.
 Selection of pile foundation types and length depends on following conditions:
-Soil conditions
-Loads from structures
-Nature of loads
-Number of piles to be used
-Cost of construction
 There are three types of pile foundation based on load transfer mechanism:
-End bearing piles
-Friction bearing piles
-Combination of end bearing and friction bearing piles.
 The purpose of pile foundations is:
– To transmit the buildings loads to the foundations and the ground soil layers
whether these loads vertical or inclined
– To install loose cohesion less soil through displacement and vibration.
– To control the settlements; which can be accompanied by surface foundations.
– To increase the factor of safety for heavy loads buildings.
PILING ACTIVITY
 SITE CLEARING AND PLACING BARRICADING.
 SURVEYING WORK.
 CASING AND DRIVING.
 BORING.
 CHECKING FOR FOUNDING LEVEL.
 MAKING AND LOWERING OF REINFORCEMENT CAGE.
 LOWERING OF TREMMIE PIPE.
 FLUSHING.
 CONCRETING.
PILE CAP
 A pile cap is a thick concrete mat that rests on concrete or timber piles that have
been driven into soft or unstable ground to provide a suitable stable foundation. It
usually forms part of the foundation of a building, typically a multi-story building,
structure or support base for heavy equipment. The cast concrete pile cap
distributes the load of the building into the piles. A similar structure to a pile cap is
a "raft", which is a concrete foundation floor resting directly onto soft soil which
may be liable to subsidence.
 The mat is made of concrete which is an aggregate of small rocks and cement. This
mixture has to be supported by a framework to avoid sagging and fracture whilst
setting. This process is known as shuttering and reinforcing. The materials used are
long twisted steel bars between the piles held in shape by thinner tie wires. Once
this steel mat is laid, timber is attached around the perimeter to contain the wet
concrete mixture. Once poured, (usually as a series of small loads), the concrete is
stirred to remove any air pockets that might weaken the structure when set. The
concrete undergoes a chemical change as it hardens and this produces a lot of heat.
Sometimes, if the mass of concrete is very large, pipes
carrying refrigerant coolant are used in the mass to assist the setting process to
prevent the concrete from cracking.
PIER
 A pier is a raised structure typically supported by well-
spaced piles or pillars. Bridges, buildings, and walkways may all be
supported by piers. Their open structure allows tides and currents to
flow relatively unhindered, whereas the more solid foundations of
a quay or the closely spaced piles of a wharf can act as a breakwater,
and are consequently more liable to silting. Piers can range in size and
complexity from a simple lightweight wooden structure to major
structures extended over 1600 meters.
PIER CAP
The upper or bearing part of a bridge pier, usually
made of concrete or hard stone.
It is designed to distribute concentrated loads evenly
over the area of the pier.
BEARING
 A bridge bearing is a component of a bridge which typically provides a resting
surface between bridge piers and the bridge deck. The purpose of a bearing is
to allow controlled movement and thereby reduce the stresses involved.
Movement could be thermal expansion or contraction, or movement from
other sources such as seismic activity. There are several different types of bridge
bearings which are used depending on a number of different factors including
the bridge span. The oldest form of bridge bearing is simply two plates resting
on top of each other. A common form of modern bridge bearing is
the elastomeric bridge bearing. Another type of bridge bearing is the
mechanical bridge bearing. There are several types of mechanical bridge
bearing, such as the pinned bearing, which in turn includes specific types such
as the rocker bearing, and the roller bearing. Another type of mechanical
bearing is the fixed bearing, which allows rotation, but not other forms of
movement.
 The purpose of a bridge bearing is to support the superstructure at a constant
elevation, to carry all forces from the superstructure into the substructure and
to allow necessary superstructure motions to take place. Forces to be applied to
bridge bearings can come from any of the loads associated with the bridges.
SEGMENT
 A segment is a bridge built in short sections (called segments), i.e., one piece at a
time, as opposed to traditional methods that build a bridge in very large sections.
The bridge is made of concrete that is either cast-in-place (constructed fully in its
final location) or precast concrete (built at another location and then transported to
their final location for placement in the full structure).
 These bridges are very economical for a span of 28m or so.
 For example, the span of 28m is divided into segments (FS1, FS2, FS3, FS4, FS5,
RS1,RS2,RS3,RS4,RS5) where the first and last segments are of 2m and the rest are of
3m.
 In cast-in-place bridges, the falsework is connected to the previously installed
concrete and allowed to cantilever freely. Next, the permanent reinforcing steel and
supports are installed. Finally, the concrete is placed and cured, freeing the
falsework to be moved.
 In pre-cast bridges, the concrete segment is constructed on the ground, and then
transported and hoisted into place. As the new segment is suspended in place by
the crane, workers install steel reinforcing that attaches the new segment to
preceding segments. Each segment of the bridge designed to accept connections
from both preceding and succeeding segments.
SEISMIC RESTRAINER
 Most bridges have movement joints to accommodate thermal
expansion an contraction without inducing large forces in the bridge.
During an earthquake, the joints pose a hazard. If the relative
displacement of adjacent frames or girders exceeds the available seat
width, the span will collapse.
 The seismic restrainer is provided at the bridge construction to prevent
or minimize the relative displacement caused due to the seismic waves
induced by earthquake or tsunami.
CRASH BARRIER
 A wall is cast around the pier around the road level, which
is known as Crash Barrier.
 The gap of 25mm is maintained between pier and crash
barrier.
 Crash Barriers are generally provided to protect the pier
from damages by the road accidents caused by the vehicles
when it gets crashed with the pier.
THANK
YOU

More Related Content

What's hot

Bridge Engineering
Bridge EngineeringBridge Engineering
Bridge EngineeringKHUSHBU SHAH
 
Bituminous road construction
Bituminous road constructionBituminous road construction
Bituminous road constructionAnitha Jacob
 
Training Report on Bridge Construction
Training Report on Bridge ConstructionTraining Report on Bridge Construction
Training Report on Bridge ConstructionMAHAVIR MEENA
 
Principles and design concepts of reinforced soil walls
Principles and design concepts of reinforced soil wallsPrinciples and design concepts of reinforced soil walls
Principles and design concepts of reinforced soil wallsPrakash Ravindran
 
ROAD CONSTRUCTION(BITUMEN) SUMMER TRAINING REPORT
ROAD CONSTRUCTION(BITUMEN) SUMMER TRAINING REPORTROAD CONSTRUCTION(BITUMEN) SUMMER TRAINING REPORT
ROAD CONSTRUCTION(BITUMEN) SUMMER TRAINING REPORTssuser5fea8f
 
Construction of rigid pavement
Construction of rigid pavementConstruction of rigid pavement
Construction of rigid pavementpradip dangar
 
Study of design of the flexible pavements ppt
Study of design of the flexible pavements pptStudy of design of the flexible pavements ppt
Study of design of the flexible pavements pptShaik Asif Ahmed
 
Training project report NHAI by Amit Kumar
Training project report NHAI by Amit KumarTraining project report NHAI by Amit Kumar
Training project report NHAI by Amit KumarAmitKumar7069
 
Bridge inspection,maintenance and repair
Bridge inspection,maintenance and repairBridge inspection,maintenance and repair
Bridge inspection,maintenance and repairKartikSuryawanshi2
 
Delhi metro(underground system) ppt
Delhi metro(underground system) pptDelhi metro(underground system) ppt
Delhi metro(underground system) pptGurudutt Bagha
 
PWD CC ROAD CONSTRUCTION WORK TRAINING REPORT
PWD CC ROAD CONSTRUCTION WORK TRAINING REPORTPWD CC ROAD CONSTRUCTION WORK TRAINING REPORT
PWD CC ROAD CONSTRUCTION WORK TRAINING REPORTSatyam Anand
 
Types of joints in rigid pavement
Types of joints in rigid pavementTypes of joints in rigid pavement
Types of joints in rigid pavementBhavya Jaiswal
 
6. BRIDGE ENGINEERING (RBT) 2160603 GTU
6. BRIDGE ENGINEERING (RBT) 2160603 GTU6. BRIDGE ENGINEERING (RBT) 2160603 GTU
6. BRIDGE ENGINEERING (RBT) 2160603 GTUVATSAL PATEL
 
Road Construction
Road ConstructionRoad Construction
Road ConstructionDanish Mohd
 

What's hot (20)

Bridge Engineering
Bridge EngineeringBridge Engineering
Bridge Engineering
 
Bituminous road construction
Bituminous road constructionBituminous road construction
Bituminous road construction
 
Training Report on Bridge Construction
Training Report on Bridge ConstructionTraining Report on Bridge Construction
Training Report on Bridge Construction
 
Principles and design concepts of reinforced soil walls
Principles and design concepts of reinforced soil wallsPrinciples and design concepts of reinforced soil walls
Principles and design concepts of reinforced soil walls
 
Bridge report
Bridge reportBridge report
Bridge report
 
SUMMER TRAINING FROM PWD
SUMMER TRAINING FROM PWDSUMMER TRAINING FROM PWD
SUMMER TRAINING FROM PWD
 
ROAD CONSTRUCTION(BITUMEN) SUMMER TRAINING REPORT
ROAD CONSTRUCTION(BITUMEN) SUMMER TRAINING REPORTROAD CONSTRUCTION(BITUMEN) SUMMER TRAINING REPORT
ROAD CONSTRUCTION(BITUMEN) SUMMER TRAINING REPORT
 
Roads & bridges
Roads & bridgesRoads & bridges
Roads & bridges
 
Construction of rigid pavement
Construction of rigid pavementConstruction of rigid pavement
Construction of rigid pavement
 
Study of design of the flexible pavements ppt
Study of design of the flexible pavements pptStudy of design of the flexible pavements ppt
Study of design of the flexible pavements ppt
 
Introduction to bridges
Introduction to bridgesIntroduction to bridges
Introduction to bridges
 
Training project report NHAI by Amit Kumar
Training project report NHAI by Amit KumarTraining project report NHAI by Amit Kumar
Training project report NHAI by Amit Kumar
 
Bridge inspection,maintenance and repair
Bridge inspection,maintenance and repairBridge inspection,maintenance and repair
Bridge inspection,maintenance and repair
 
Delhi metro(underground system) ppt
Delhi metro(underground system) pptDelhi metro(underground system) ppt
Delhi metro(underground system) ppt
 
PWD CC ROAD CONSTRUCTION WORK TRAINING REPORT
PWD CC ROAD CONSTRUCTION WORK TRAINING REPORTPWD CC ROAD CONSTRUCTION WORK TRAINING REPORT
PWD CC ROAD CONSTRUCTION WORK TRAINING REPORT
 
Classification of bridges
Classification of bridgesClassification of bridges
Classification of bridges
 
Road construction ppt
Road construction pptRoad construction ppt
Road construction ppt
 
Types of joints in rigid pavement
Types of joints in rigid pavementTypes of joints in rigid pavement
Types of joints in rigid pavement
 
6. BRIDGE ENGINEERING (RBT) 2160603 GTU
6. BRIDGE ENGINEERING (RBT) 2160603 GTU6. BRIDGE ENGINEERING (RBT) 2160603 GTU
6. BRIDGE ENGINEERING (RBT) 2160603 GTU
 
Road Construction
Road ConstructionRoad Construction
Road Construction
 

Similar to Construction of Metro Rail Bridge

Training project report BSRDCL by Amit Kumar
Training project report BSRDCL by Amit KumarTraining project report BSRDCL by Amit Kumar
Training project report BSRDCL by Amit KumarAmitKumar7069
 
Prestressed Concrete Bridge.pptx
Prestressed Concrete Bridge.pptxPrestressed Concrete Bridge.pptx
Prestressed Concrete Bridge.pptxRajeshKumar25548
 
report-on-emmar.docx13
report-on-emmar.docx13report-on-emmar.docx13
report-on-emmar.docx13Minhal Haider
 
Running Head BRIDGE DESIGN1BRIDGE DESIGN31.docx
Running Head BRIDGE DESIGN1BRIDGE DESIGN31.docxRunning Head BRIDGE DESIGN1BRIDGE DESIGN31.docx
Running Head BRIDGE DESIGN1BRIDGE DESIGN31.docxtoddr4
 
challanges made for construction of bridge in hilly areas
challanges made for construction of bridge in hilly areaschallanges made for construction of bridge in hilly areas
challanges made for construction of bridge in hilly areasSwapnali Kunjir
 
High rise building design
High rise building design High rise building design
High rise building design Somesh Siddharth
 
stress ribbon bridge.pptx
stress ribbon bridge.pptxstress ribbon bridge.pptx
stress ribbon bridge.pptxSauravShahane
 
introductiontobridges07-08-090507223401-phpapp02.ppt
introductiontobridges07-08-090507223401-phpapp02.pptintroductiontobridges07-08-090507223401-phpapp02.ppt
introductiontobridges07-08-090507223401-phpapp02.pptJoeBankerS1
 
introductiontobridges07-08-090507223401-phpapp02.ppt
introductiontobridges07-08-090507223401-phpapp02.pptintroductiontobridges07-08-090507223401-phpapp02.ppt
introductiontobridges07-08-090507223401-phpapp02.pptJoeBankerS1
 
PRE-CAST-CONSTRUCTION.pptx
PRE-CAST-CONSTRUCTION.pptxPRE-CAST-CONSTRUCTION.pptx
PRE-CAST-CONSTRUCTION.pptxLokeswarSaha1
 
High-rise structural systems
High-rise structural systemsHigh-rise structural systems
High-rise structural systemsAkshay Revekar
 
Finalppthighrise 130504010636-phpapp02
Finalppthighrise 130504010636-phpapp02Finalppthighrise 130504010636-phpapp02
Finalppthighrise 130504010636-phpapp02satwik345
 
introductiontobridges07-08-090507223401-phpapp02.pdf
introductiontobridges07-08-090507223401-phpapp02.pdfintroductiontobridges07-08-090507223401-phpapp02.pdf
introductiontobridges07-08-090507223401-phpapp02.pdfabhinavbharat9
 
High rise structure
High rise structureHigh rise structure
High rise structureAnuj Singhal
 
PRE-CAST-CONSTRUCTION.pptx
PRE-CAST-CONSTRUCTION.pptxPRE-CAST-CONSTRUCTION.pptx
PRE-CAST-CONSTRUCTION.pptxVinayak247538
 
Ishfaq Rashid.pptx
Ishfaq Rashid.pptxIshfaq Rashid.pptx
Ishfaq Rashid.pptxlovish34
 

Similar to Construction of Metro Rail Bridge (20)

Training project report BSRDCL by Amit Kumar
Training project report BSRDCL by Amit KumarTraining project report BSRDCL by Amit Kumar
Training project report BSRDCL by Amit Kumar
 
Prestressed Concrete Bridge.pptx
Prestressed Concrete Bridge.pptxPrestressed Concrete Bridge.pptx
Prestressed Concrete Bridge.pptx
 
report-on-emmar.docx13
report-on-emmar.docx13report-on-emmar.docx13
report-on-emmar.docx13
 
Bridges Functionality and Aesthetics
Bridges Functionality and AestheticsBridges Functionality and Aesthetics
Bridges Functionality and Aesthetics
 
Running Head BRIDGE DESIGN1BRIDGE DESIGN31.docx
Running Head BRIDGE DESIGN1BRIDGE DESIGN31.docxRunning Head BRIDGE DESIGN1BRIDGE DESIGN31.docx
Running Head BRIDGE DESIGN1BRIDGE DESIGN31.docx
 
challanges made for construction of bridge in hilly areas
challanges made for construction of bridge in hilly areaschallanges made for construction of bridge in hilly areas
challanges made for construction of bridge in hilly areas
 
Acm Unit 1
Acm Unit 1Acm Unit 1
Acm Unit 1
 
STRESS RIBBON BRIDGE
STRESS RIBBON BRIDGESTRESS RIBBON BRIDGE
STRESS RIBBON BRIDGE
 
High rise building design
High rise building design High rise building design
High rise building design
 
stress ribbon bridge.pptx
stress ribbon bridge.pptxstress ribbon bridge.pptx
stress ribbon bridge.pptx
 
introductiontobridges07-08-090507223401-phpapp02.ppt
introductiontobridges07-08-090507223401-phpapp02.pptintroductiontobridges07-08-090507223401-phpapp02.ppt
introductiontobridges07-08-090507223401-phpapp02.ppt
 
introductiontobridges07-08-090507223401-phpapp02.ppt
introductiontobridges07-08-090507223401-phpapp02.pptintroductiontobridges07-08-090507223401-phpapp02.ppt
introductiontobridges07-08-090507223401-phpapp02.ppt
 
PRE-CAST-CONSTRUCTION.pptx
PRE-CAST-CONSTRUCTION.pptxPRE-CAST-CONSTRUCTION.pptx
PRE-CAST-CONSTRUCTION.pptx
 
High-rise structural systems
High-rise structural systemsHigh-rise structural systems
High-rise structural systems
 
Finalppthighrise 130504010636-phpapp02
Finalppthighrise 130504010636-phpapp02Finalppthighrise 130504010636-phpapp02
Finalppthighrise 130504010636-phpapp02
 
high rise building
high rise buildinghigh rise building
high rise building
 
introductiontobridges07-08-090507223401-phpapp02.pdf
introductiontobridges07-08-090507223401-phpapp02.pdfintroductiontobridges07-08-090507223401-phpapp02.pdf
introductiontobridges07-08-090507223401-phpapp02.pdf
 
High rise structure
High rise structureHigh rise structure
High rise structure
 
PRE-CAST-CONSTRUCTION.pptx
PRE-CAST-CONSTRUCTION.pptxPRE-CAST-CONSTRUCTION.pptx
PRE-CAST-CONSTRUCTION.pptx
 
Ishfaq Rashid.pptx
Ishfaq Rashid.pptxIshfaq Rashid.pptx
Ishfaq Rashid.pptx
 

Recently uploaded

HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSRajkumarAkumalla
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxupamatechverse
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxupamatechverse
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...ranjana rawat
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...ranjana rawat
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidNikhilNagaraju
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝soniya singh
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...srsj9000
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingrakeshbaidya232001
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINESIVASHANKAR N
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Christo Ananth
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoão Esperancinha
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 

Recently uploaded (20)

HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptx
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfid
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writing
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINEDJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 

Construction of Metro Rail Bridge

  • 1. SUBMITTED BY :- PROJECT GUIDE :- SOURAV GOSWAMI Mr. S.C MITRA MVJ COLLEGE OF ENGINEERING, BANGALORE MANAGER –(PROJECT) (02.01.2016 to 09.01.2016) RVNL - KOLKATA
  • 2. ACKNOWLEDGEMENT I would like to express my special thanks of gratitude to Mr. Amit Kumar Roy (CPM/LINE, RVNL Kolkata), Mr. Avijit Roy (GM/P, RVNL KOLKATA), Mr. S.C.Mitra (MANAGER, PROJECT, RVNL KOLKATA), Staffs and Supervisors of RVNL and GAMMON INDIA LIMITED who gave me the golden opportunity to do this wonderful project on the topic CONSTRUCTION OF METRO RAIL BRIDGE, which also helped me in doing a lot of Research and I came to know about so many new things. I am really thankful to them. Lastly, I would also like to thank my parents who helped me a lot in finalizing this project within the limited time frame. SOURAV GOSWAMI (PROJECT INTERN)
  • 3. SUMMARY The following project focuses on the viaduct and its various parts, describing their individual characteristics as well as the methods being used for its construction. The project was done in a brief span of seven days. The topics discussed here were the subjects of my inspection. The Project was done as summer internship under Rail Vikas Nigam Limited (RVNL), in association with Gammon India Limited. This internship has helped me gather practical knowledge of the onsite activities that takes place while constructing a viaduct/bridge. SOURAV GOSWAMI ( PROJECT INTERN )
  • 4. CONTENT 1. BRIDGE 2. PILE 3. PILING ACTIVITY 4. PILE CAP 5. PIER 6. PIER CAP 7. BEARING 8. SEGMENT 9. SEISMIC RESTRAINER 10. CASH BARRIER
  • 5. BRIDGE A bridge is a structure built to span physical obstacles without closing the way underneath such as a body of water, valley, or road, for the purpose of providing passage over the obstacle. There are many different designs that all serve unique purposes and apply to different situations. Designs of bridges vary depending on the function of the bridge, the nature of the terrain where the bridge is constructed and anchored, the material used to make it, and the funds available to build it. During the design process, every bridge can be divided broadly into three parts: -Superstructure. -Substructure. -Foundation. MAJOR PARTS OF A BRIDGE The major parts of a bridge are as follows: - Pile. - Pile Cap. - Pier. - Pier Cap. - Bearing. - Segment. - Seismic Restrainer. - Crash Barrier.
  • 6. PILE  There are three types of pile foundations according to their construction methods: 1.Driven piles, 2.Cast-in-situ piles, and 3.Driven and cast-in-situ piles.  Pile foundation selection depends on the soil data received from soil exploration bore holes at different depths.  Selection of pile foundation types and length depends on following conditions: -Soil conditions -Loads from structures -Nature of loads -Number of piles to be used -Cost of construction  There are three types of pile foundation based on load transfer mechanism: -End bearing piles -Friction bearing piles -Combination of end bearing and friction bearing piles.  The purpose of pile foundations is: – To transmit the buildings loads to the foundations and the ground soil layers whether these loads vertical or inclined – To install loose cohesion less soil through displacement and vibration. – To control the settlements; which can be accompanied by surface foundations. – To increase the factor of safety for heavy loads buildings.
  • 7. PILING ACTIVITY  SITE CLEARING AND PLACING BARRICADING.  SURVEYING WORK.  CASING AND DRIVING.  BORING.  CHECKING FOR FOUNDING LEVEL.  MAKING AND LOWERING OF REINFORCEMENT CAGE.  LOWERING OF TREMMIE PIPE.  FLUSHING.  CONCRETING.
  • 8. PILE CAP  A pile cap is a thick concrete mat that rests on concrete or timber piles that have been driven into soft or unstable ground to provide a suitable stable foundation. It usually forms part of the foundation of a building, typically a multi-story building, structure or support base for heavy equipment. The cast concrete pile cap distributes the load of the building into the piles. A similar structure to a pile cap is a "raft", which is a concrete foundation floor resting directly onto soft soil which may be liable to subsidence.  The mat is made of concrete which is an aggregate of small rocks and cement. This mixture has to be supported by a framework to avoid sagging and fracture whilst setting. This process is known as shuttering and reinforcing. The materials used are long twisted steel bars between the piles held in shape by thinner tie wires. Once this steel mat is laid, timber is attached around the perimeter to contain the wet concrete mixture. Once poured, (usually as a series of small loads), the concrete is stirred to remove any air pockets that might weaken the structure when set. The concrete undergoes a chemical change as it hardens and this produces a lot of heat. Sometimes, if the mass of concrete is very large, pipes carrying refrigerant coolant are used in the mass to assist the setting process to prevent the concrete from cracking.
  • 9. PIER  A pier is a raised structure typically supported by well- spaced piles or pillars. Bridges, buildings, and walkways may all be supported by piers. Their open structure allows tides and currents to flow relatively unhindered, whereas the more solid foundations of a quay or the closely spaced piles of a wharf can act as a breakwater, and are consequently more liable to silting. Piers can range in size and complexity from a simple lightweight wooden structure to major structures extended over 1600 meters.
  • 10. PIER CAP The upper or bearing part of a bridge pier, usually made of concrete or hard stone. It is designed to distribute concentrated loads evenly over the area of the pier.
  • 11. BEARING  A bridge bearing is a component of a bridge which typically provides a resting surface between bridge piers and the bridge deck. The purpose of a bearing is to allow controlled movement and thereby reduce the stresses involved. Movement could be thermal expansion or contraction, or movement from other sources such as seismic activity. There are several different types of bridge bearings which are used depending on a number of different factors including the bridge span. The oldest form of bridge bearing is simply two plates resting on top of each other. A common form of modern bridge bearing is the elastomeric bridge bearing. Another type of bridge bearing is the mechanical bridge bearing. There are several types of mechanical bridge bearing, such as the pinned bearing, which in turn includes specific types such as the rocker bearing, and the roller bearing. Another type of mechanical bearing is the fixed bearing, which allows rotation, but not other forms of movement.  The purpose of a bridge bearing is to support the superstructure at a constant elevation, to carry all forces from the superstructure into the substructure and to allow necessary superstructure motions to take place. Forces to be applied to bridge bearings can come from any of the loads associated with the bridges.
  • 12. SEGMENT  A segment is a bridge built in short sections (called segments), i.e., one piece at a time, as opposed to traditional methods that build a bridge in very large sections. The bridge is made of concrete that is either cast-in-place (constructed fully in its final location) or precast concrete (built at another location and then transported to their final location for placement in the full structure).  These bridges are very economical for a span of 28m or so.  For example, the span of 28m is divided into segments (FS1, FS2, FS3, FS4, FS5, RS1,RS2,RS3,RS4,RS5) where the first and last segments are of 2m and the rest are of 3m.  In cast-in-place bridges, the falsework is connected to the previously installed concrete and allowed to cantilever freely. Next, the permanent reinforcing steel and supports are installed. Finally, the concrete is placed and cured, freeing the falsework to be moved.  In pre-cast bridges, the concrete segment is constructed on the ground, and then transported and hoisted into place. As the new segment is suspended in place by the crane, workers install steel reinforcing that attaches the new segment to preceding segments. Each segment of the bridge designed to accept connections from both preceding and succeeding segments.
  • 13. SEISMIC RESTRAINER  Most bridges have movement joints to accommodate thermal expansion an contraction without inducing large forces in the bridge. During an earthquake, the joints pose a hazard. If the relative displacement of adjacent frames or girders exceeds the available seat width, the span will collapse.  The seismic restrainer is provided at the bridge construction to prevent or minimize the relative displacement caused due to the seismic waves induced by earthquake or tsunami.
  • 14. CRASH BARRIER  A wall is cast around the pier around the road level, which is known as Crash Barrier.  The gap of 25mm is maintained between pier and crash barrier.  Crash Barriers are generally provided to protect the pier from damages by the road accidents caused by the vehicles when it gets crashed with the pier.