SlideShare a Scribd company logo
1 of 19
Download to read offline
TRUSS FINAL
PROJECT
Group 3: Arman Yosal, Josia Tannos,
Maya Goldman, Savannah Brooks
Completed Bridge
Introduction
-Concept
-Design Methods
-Construction Techniques
-Testing and Performance
-Post Test Evaluation
-Conclusion
Concept
● Warren Truss design
● Hand Calculations and SAP2000
Analysis
● Seven triangle design most
efficient
● Safety Factor of 2
Design Methods
● Warren Truss design
● 69 Total Members
○ 27 on each side of truss
○ 15 connecting the two sides
● Deflection decreases with increased cross-sectional area
Cross Sectional Size Number of Members Pieces Laminated
1/4" x 1/4" 38 4 x (1/8" balsa wood)
1/8" x 1/8" 8 4 x (1/16" balsa wood)
3/8" x 3/8" 4 4 x (3/16" balsa wood)
1/4" x 1/8" 4 2 x (1/8" balsa wood)
Construction techniques (1) - Cutting
● Materials used: X-Acto blades, T-squares or metal rulers
● Followed table to keep track of amounts, lengths, sizes
● Rounded up for consistency
Construction techniques (2) - Laminating
● Super glue used to form members with larger cross-sectional areas and
greater strength
○ Ex. using ⅛” wood pieces, four were laminated together to create a ¼”X¼” member
● Extra pieces added to small members at connection joints so heights were
equal
Construction techniques (3) Building Frame
Comparison of hand and CAD templates; second frame built on top of first
Construction techniques (4) Second Frame
Second frame build on top of first
Construction techniques (5) Lateral Bracing
● Tongue depressor and screw system to align
frames
● Gusset plates added on small members
● Cross-bracing cut and placed one at a time at
the end
Testing/Performance (1)
Testing Method
● Metal bar laid on platform at
top center of bridge
● Chain hung over bar then
attached beneath bucket
● Began at ten pounds then
weight was added until failure
Testing/Performance (2)
The bridge met all design requirements
● Minimum 36” span with no more than ½” at
each support
● Minimum height 5”, width 4” for truck to pass
● Less than 0.25” deflection
● Did not exceed 30% over-order
Weight of
load at failure
53.5 lb
Length 40”
Height 6”
Width 4”
Weight of
bridge
135.6 g
Testing/Performance (3)
https://youtu.be/X-wvcwi89wY
Video of testing
Post Test Evaluation (1)
Bridge main failure points
Post Test Evaluation (2)
Gusset plate and member shear failures
Post Test Evaluation (3)
Length 40”
Height 6”
Width 4”
Weight of bridge 135.6 g
Weight of load at
failure
53.5 lb
Post Test Evaluation (4)
● More efficient design can be achieved
○ Underestimation of elastic modulus
Trial Length
(cm)
Width
(cm)
Moment of
Inertia
(cm4
)
Load
(N)
Length
(cm)
Deflection
(cm)
Elastic
Modulus
(GPa)
1 0.318 0.318 8.468E-04 0.196 25.000 1.800 6.704
2 0.318 0.318 8.468E-04 0.196 25.000 2.200 5.485
3 0.159 0.159 5.293E-05 0.098 10.000 1.000 6.178
4 0.159 0.159 5.293E-05 0.098 10.000 1.500 4.119
Our data (left), researched data (right)
Conclusions
- The bridge met all design requirements
- The bridge was over designed
- What we would improve
● Use larger gusset plate
● Take into account the thickness of each member
● Measure the actual elastic modulus of the material
Questions?

More Related Content

What's hot

What's hot (20)

Column base plates_prof_thomas_murray
Column base plates_prof_thomas_murrayColumn base plates_prof_thomas_murray
Column base plates_prof_thomas_murray
 
Connections
Connections Connections
Connections
 
Bridge project
Bridge projectBridge project
Bridge project
 
Precast pretensioned concrete girders
Precast pretensioned concrete girdersPrecast pretensioned concrete girders
Precast pretensioned concrete girders
 
Bar bending schedule(by akhil)
Bar bending schedule(by akhil)Bar bending schedule(by akhil)
Bar bending schedule(by akhil)
 
Reinforced column design
Reinforced column design Reinforced column design
Reinforced column design
 
How to calculate quantity of steel in slab
How to calculate quantity of steel in slabHow to calculate quantity of steel in slab
How to calculate quantity of steel in slab
 
PELAT LANTAI JEMBATAN.pdf
PELAT LANTAI JEMBATAN.pdfPELAT LANTAI JEMBATAN.pdf
PELAT LANTAI JEMBATAN.pdf
 
CFST
CFSTCFST
CFST
 
Building Structure Project 1
Building Structure Project 1Building Structure Project 1
Building Structure Project 1
 
Bar bending schedule
Bar bending scheduleBar bending schedule
Bar bending schedule
 
Center line method 4
Center line method 4Center line method 4
Center line method 4
 
Multi Storey Steel Structures
Multi Storey Steel StructuresMulti Storey Steel Structures
Multi Storey Steel Structures
 
Beam and slab design
Beam and slab designBeam and slab design
Beam and slab design
 
Bolted connections
Bolted connectionsBolted connections
Bolted connections
 
Perencanaan struktur kolom komposit
Perencanaan struktur kolom kompositPerencanaan struktur kolom komposit
Perencanaan struktur kolom komposit
 
Steel connections
Steel connectionsSteel connections
Steel connections
 
Rcc structure design by etabs (acecoms)
Rcc structure design by etabs (acecoms)Rcc structure design by etabs (acecoms)
Rcc structure design by etabs (acecoms)
 
Design steps of foot bridge , stringer and cross girder
Design steps of foot bridge , stringer and cross girderDesign steps of foot bridge , stringer and cross girder
Design steps of foot bridge , stringer and cross girder
 
Rail and Road Over Rail Bridge
Rail and Road Over Rail BridgeRail and Road Over Rail Bridge
Rail and Road Over Rail Bridge
 

Viewers also liked

Bridge engineering
Bridge engineeringBridge engineering
Bridge engineeringHalcrow
 
Truss Bridge Report
Truss Bridge ReportTruss Bridge Report
Truss Bridge ReportYvonne Chin
 
Truss bridge final presentation
Truss bridge final presentationTruss bridge final presentation
Truss bridge final presentationkaiumbhai
 
Building Structure Project 1 Fettuccine Bridge
Building Structure Project 1 Fettuccine BridgeBuilding Structure Project 1 Fettuccine Bridge
Building Structure Project 1 Fettuccine BridgeDexter Ng
 
3D Analysis Of Truss Bridges
3D Analysis Of Truss Bridges3D Analysis Of Truss Bridges
3D Analysis Of Truss Bridgesblovelace
 
ASE Conference Presentation
ASE Conference PresentationASE Conference Presentation
ASE Conference PresentationAndrew Kenyon
 
Bridge Design Exchange Brochure
Bridge Design Exchange BrochureBridge Design Exchange Brochure
Bridge Design Exchange BrochureIQPCExchanges
 
Widening of the Huey P. Long Bridge
Widening of the Huey P. Long BridgeWidening of the Huey P. Long Bridge
Widening of the Huey P. Long BridgeDavid Kanger, P.E.
 
KwaNogawu village Pedestrian Bridge Proposal
KwaNogawu village Pedestrian Bridge ProposalKwaNogawu village Pedestrian Bridge Proposal
KwaNogawu village Pedestrian Bridge ProposalAyandiswa Msane
 
Application of the trusses
Application of the trussesApplication of the trusses
Application of the trussesumar642642
 
PROJECT REPORT - SUPER GROUP
PROJECT REPORT - SUPER GROUPPROJECT REPORT - SUPER GROUP
PROJECT REPORT - SUPER GROUPShobhit Shekhar
 
Building Construction II: Project One
Building Construction II: Project OneBuilding Construction II: Project One
Building Construction II: Project OneEuxuan Ong
 
Training Report on Bridge Construction
Training Report on Bridge ConstructionTraining Report on Bridge Construction
Training Report on Bridge ConstructionMAHAVIR MEENA
 
Fink truss (w type)
Fink truss (w type)Fink truss (w type)
Fink truss (w type)mnauth
 
Waste Recycling Project Final
Waste  Recycling  Project   FinalWaste  Recycling  Project   Final
Waste Recycling Project FinalMUSATTI
 
Training report done on Bridge Construction
Training report done on Bridge ConstructionTraining report done on Bridge Construction
Training report done on Bridge ConstructionSukhdeep Jat
 
Bridge Presentation
Bridge PresentationBridge Presentation
Bridge Presentationdysalot
 

Viewers also liked (20)

Bridge engineering
Bridge engineeringBridge engineering
Bridge engineering
 
Truss Bridge Report
Truss Bridge ReportTruss Bridge Report
Truss Bridge Report
 
Truss bridge final presentation
Truss bridge final presentationTruss bridge final presentation
Truss bridge final presentation
 
Building Structure Project 1 Fettuccine Bridge
Building Structure Project 1 Fettuccine BridgeBuilding Structure Project 1 Fettuccine Bridge
Building Structure Project 1 Fettuccine Bridge
 
3D Analysis Of Truss Bridges
3D Analysis Of Truss Bridges3D Analysis Of Truss Bridges
3D Analysis Of Truss Bridges
 
Steel roof trusses
Steel roof trussesSteel roof trusses
Steel roof trusses
 
ASE Conference Presentation
ASE Conference PresentationASE Conference Presentation
ASE Conference Presentation
 
Bridge Design Exchange Brochure
Bridge Design Exchange BrochureBridge Design Exchange Brochure
Bridge Design Exchange Brochure
 
Widening of the Huey P. Long Bridge
Widening of the Huey P. Long BridgeWidening of the Huey P. Long Bridge
Widening of the Huey P. Long Bridge
 
KwaNogawu village Pedestrian Bridge Proposal
KwaNogawu village Pedestrian Bridge ProposalKwaNogawu village Pedestrian Bridge Proposal
KwaNogawu village Pedestrian Bridge Proposal
 
Fettucine Bridge Report
Fettucine Bridge ReportFettucine Bridge Report
Fettucine Bridge Report
 
Application of the trusses
Application of the trussesApplication of the trusses
Application of the trusses
 
PROJECT REPORT - SUPER GROUP
PROJECT REPORT - SUPER GROUPPROJECT REPORT - SUPER GROUP
PROJECT REPORT - SUPER GROUP
 
Building Construction II: Project One
Building Construction II: Project OneBuilding Construction II: Project One
Building Construction II: Project One
 
Training Report on Bridge Construction
Training Report on Bridge ConstructionTraining Report on Bridge Construction
Training Report on Bridge Construction
 
Fink truss (w type)
Fink truss (w type)Fink truss (w type)
Fink truss (w type)
 
Waste Recycling Project Final
Waste  Recycling  Project   FinalWaste  Recycling  Project   Final
Waste Recycling Project Final
 
Training report done on Bridge Construction
Training report done on Bridge ConstructionTraining report done on Bridge Construction
Training report done on Bridge Construction
 
Roof trusses
Roof trussesRoof trusses
Roof trusses
 
Bridge Presentation
Bridge PresentationBridge Presentation
Bridge Presentation
 

Similar to Final Presentation (Balsa Wood Bridge Design)

Mire End-Quarter Design Review
Mire End-Quarter Design ReviewMire End-Quarter Design Review
Mire End-Quarter Design ReviewRobert Auer
 
Texas A&M Transportation Institute’s Experience and Observations on Manual fo...
Texas A&M Transportation Institute’s Experience and Observations on Manual fo...Texas A&M Transportation Institute’s Experience and Observations on Manual fo...
Texas A&M Transportation Institute’s Experience and Observations on Manual fo...Texas A&M Transportation Institute
 
Bridge-Plate & Multi-Plate Applications and Case Studies (Randy McDonald, P.E...
Bridge-Plate & Multi-Plate Applications and Case Studies (Randy McDonald, P.E...Bridge-Plate & Multi-Plate Applications and Case Studies (Randy McDonald, P.E...
Bridge-Plate & Multi-Plate Applications and Case Studies (Randy McDonald, P.E...Communications Branding
 
Aggregates types and test as per Indian Standard
Aggregates   types and test as per Indian StandardAggregates   types and test as per Indian Standard
Aggregates types and test as per Indian StandardPrabakaran Ellappan
 
Testing to failure of the Ruytenschildt Bridge
Testing to failure of the Ruytenschildt BridgeTesting to failure of the Ruytenschildt Bridge
Testing to failure of the Ruytenschildt BridgeEva Lantsoght
 
KTU CE 204 Construction Technology - Module 2
KTU CE 204 Construction Technology - Module 2KTU CE 204 Construction Technology - Module 2
KTU CE 204 Construction Technology - Module 2Bennet Kuriakose, PhD
 
Julianna Ricci Portfolio 2016
Julianna Ricci Portfolio 2016Julianna Ricci Portfolio 2016
Julianna Ricci Portfolio 2016Julianna Ricci
 
Tire Testing Applications & Solutions
Tire Testing Applications & SolutionsTire Testing Applications & Solutions
Tire Testing Applications & SolutionsInstron
 
TAMS Industries fact sheet
TAMS Industries fact sheetTAMS Industries fact sheet
TAMS Industries fact sheetOmar Gonzalez
 
Rockwell Hardness Testing Machine
Rockwell Hardness Testing MachineRockwell Hardness Testing Machine
Rockwell Hardness Testing MachineUmer Azeem
 
Armtec - Introduction to Soil Steel Structures & End Treatments
Armtec - Introduction to Soil Steel Structures & End TreatmentsArmtec - Introduction to Soil Steel Structures & End Treatments
Armtec - Introduction to Soil Steel Structures & End TreatmentsCommunications Branding
 
Titan Rover CDR Presentation
Titan Rover CDR PresentationTitan Rover CDR Presentation
Titan Rover CDR PresentationKristopherKerames
 
Tampere Wear Center & Research equipment 2014
Tampere Wear Center & Research equipment 2014Tampere Wear Center & Research equipment 2014
Tampere Wear Center & Research equipment 2014Kati Valtonen
 
Midterm presentation rough
Midterm presentation   rough Midterm presentation   rough
Midterm presentation rough supermanu22
 
Tampere Wear Center activities and research equipment 2015
Tampere Wear Center activities and research equipment 2015Tampere Wear Center activities and research equipment 2015
Tampere Wear Center activities and research equipment 2015Kati Valtonen
 
bolted connections.pptx
bolted connections.pptxbolted connections.pptx
bolted connections.pptxmayur280524
 

Similar to Final Presentation (Balsa Wood Bridge Design) (20)

Mire End-Quarter Design Review
Mire End-Quarter Design ReviewMire End-Quarter Design Review
Mire End-Quarter Design Review
 
Texas A&M Transportation Institute’s Experience and Observations on Manual fo...
Texas A&M Transportation Institute’s Experience and Observations on Manual fo...Texas A&M Transportation Institute’s Experience and Observations on Manual fo...
Texas A&M Transportation Institute’s Experience and Observations on Manual fo...
 
Bridge-Plate & Multi-Plate Applications and Case Studies (Randy McDonald, P.E...
Bridge-Plate & Multi-Plate Applications and Case Studies (Randy McDonald, P.E...Bridge-Plate & Multi-Plate Applications and Case Studies (Randy McDonald, P.E...
Bridge-Plate & Multi-Plate Applications and Case Studies (Randy McDonald, P.E...
 
Aggregates types and test as per Indian Standard
Aggregates   types and test as per Indian StandardAggregates   types and test as per Indian Standard
Aggregates types and test as per Indian Standard
 
Testing to failure of the Ruytenschildt Bridge
Testing to failure of the Ruytenschildt BridgeTesting to failure of the Ruytenschildt Bridge
Testing to failure of the Ruytenschildt Bridge
 
KTU CE 204 Construction Technology - Module 2
KTU CE 204 Construction Technology - Module 2KTU CE 204 Construction Technology - Module 2
KTU CE 204 Construction Technology - Module 2
 
CHE :- 6 form work (MODULE 3)
CHE :- 6 form work (MODULE 3)CHE :- 6 form work (MODULE 3)
CHE :- 6 form work (MODULE 3)
 
Julianna Ricci Portfolio 2016
Julianna Ricci Portfolio 2016Julianna Ricci Portfolio 2016
Julianna Ricci Portfolio 2016
 
Tire Testing Applications & Solutions
Tire Testing Applications & SolutionsTire Testing Applications & Solutions
Tire Testing Applications & Solutions
 
TAMS Industries fact sheet
TAMS Industries fact sheetTAMS Industries fact sheet
TAMS Industries fact sheet
 
Rockwell Hardness Testing Machine
Rockwell Hardness Testing MachineRockwell Hardness Testing Machine
Rockwell Hardness Testing Machine
 
New Roadside Hardware Improvements
New Roadside Hardware ImprovementsNew Roadside Hardware Improvements
New Roadside Hardware Improvements
 
Armtec - Introduction to Soil Steel Structures & End Treatments
Armtec - Introduction to Soil Steel Structures & End TreatmentsArmtec - Introduction to Soil Steel Structures & End Treatments
Armtec - Introduction to Soil Steel Structures & End Treatments
 
Titan Rover CDR Presentation
Titan Rover CDR PresentationTitan Rover CDR Presentation
Titan Rover CDR Presentation
 
ME8700_project
ME8700_projectME8700_project
ME8700_project
 
Tampere Wear Center & Research equipment 2014
Tampere Wear Center & Research equipment 2014Tampere Wear Center & Research equipment 2014
Tampere Wear Center & Research equipment 2014
 
Midterm presentation rough
Midterm presentation   rough Midterm presentation   rough
Midterm presentation rough
 
Tampere Wear Center activities and research equipment 2015
Tampere Wear Center activities and research equipment 2015Tampere Wear Center activities and research equipment 2015
Tampere Wear Center activities and research equipment 2015
 
FYP presentation
FYP presentationFYP presentation
FYP presentation
 
bolted connections.pptx
bolted connections.pptxbolted connections.pptx
bolted connections.pptx
 

More from Josia Tannos, EIT

Final Report (XL Keystone Pipeline Project)
Final Report (XL Keystone Pipeline Project)Final Report (XL Keystone Pipeline Project)
Final Report (XL Keystone Pipeline Project)Josia Tannos, EIT
 
Final Presentation (XL Keystone Pipeline Project)
Final Presentation (XL Keystone Pipeline Project)Final Presentation (XL Keystone Pipeline Project)
Final Presentation (XL Keystone Pipeline Project)Josia Tannos, EIT
 
Final Presentation (Intersection Improvement Project)
Final Presentation (Intersection Improvement Project)Final Presentation (Intersection Improvement Project)
Final Presentation (Intersection Improvement Project)Josia Tannos, EIT
 
Final Report (Intersection Improvement Project)
Final Report (Intersection Improvement Project)Final Report (Intersection Improvement Project)
Final Report (Intersection Improvement Project)Josia Tannos, EIT
 
AutoCAD Drawing (Transportation Planning and Design)
AutoCAD Drawing (Transportation Planning and Design)AutoCAD Drawing (Transportation Planning and Design)
AutoCAD Drawing (Transportation Planning and Design)Josia Tannos, EIT
 
Final Report (Transportation Planning & Design)
Final Report (Transportation Planning & Design)Final Report (Transportation Planning & Design)
Final Report (Transportation Planning & Design)Josia Tannos, EIT
 
Final Presentation (Transportation Planning & Design)
Final Presentation (Transportation Planning & Design)Final Presentation (Transportation Planning & Design)
Final Presentation (Transportation Planning & Design)Josia Tannos, EIT
 

More from Josia Tannos, EIT (7)

Final Report (XL Keystone Pipeline Project)
Final Report (XL Keystone Pipeline Project)Final Report (XL Keystone Pipeline Project)
Final Report (XL Keystone Pipeline Project)
 
Final Presentation (XL Keystone Pipeline Project)
Final Presentation (XL Keystone Pipeline Project)Final Presentation (XL Keystone Pipeline Project)
Final Presentation (XL Keystone Pipeline Project)
 
Final Presentation (Intersection Improvement Project)
Final Presentation (Intersection Improvement Project)Final Presentation (Intersection Improvement Project)
Final Presentation (Intersection Improvement Project)
 
Final Report (Intersection Improvement Project)
Final Report (Intersection Improvement Project)Final Report (Intersection Improvement Project)
Final Report (Intersection Improvement Project)
 
AutoCAD Drawing (Transportation Planning and Design)
AutoCAD Drawing (Transportation Planning and Design)AutoCAD Drawing (Transportation Planning and Design)
AutoCAD Drawing (Transportation Planning and Design)
 
Final Report (Transportation Planning & Design)
Final Report (Transportation Planning & Design)Final Report (Transportation Planning & Design)
Final Report (Transportation Planning & Design)
 
Final Presentation (Transportation Planning & Design)
Final Presentation (Transportation Planning & Design)Final Presentation (Transportation Planning & Design)
Final Presentation (Transportation Planning & Design)
 

Final Presentation (Balsa Wood Bridge Design)

  • 1. TRUSS FINAL PROJECT Group 3: Arman Yosal, Josia Tannos, Maya Goldman, Savannah Brooks
  • 3. Introduction -Concept -Design Methods -Construction Techniques -Testing and Performance -Post Test Evaluation -Conclusion
  • 4. Concept ● Warren Truss design ● Hand Calculations and SAP2000 Analysis ● Seven triangle design most efficient ● Safety Factor of 2
  • 5. Design Methods ● Warren Truss design ● 69 Total Members ○ 27 on each side of truss ○ 15 connecting the two sides ● Deflection decreases with increased cross-sectional area Cross Sectional Size Number of Members Pieces Laminated 1/4" x 1/4" 38 4 x (1/8" balsa wood) 1/8" x 1/8" 8 4 x (1/16" balsa wood) 3/8" x 3/8" 4 4 x (3/16" balsa wood) 1/4" x 1/8" 4 2 x (1/8" balsa wood)
  • 6. Construction techniques (1) - Cutting ● Materials used: X-Acto blades, T-squares or metal rulers ● Followed table to keep track of amounts, lengths, sizes ● Rounded up for consistency
  • 7. Construction techniques (2) - Laminating ● Super glue used to form members with larger cross-sectional areas and greater strength ○ Ex. using ⅛” wood pieces, four were laminated together to create a ¼”X¼” member ● Extra pieces added to small members at connection joints so heights were equal
  • 8. Construction techniques (3) Building Frame Comparison of hand and CAD templates; second frame built on top of first
  • 9. Construction techniques (4) Second Frame Second frame build on top of first
  • 10. Construction techniques (5) Lateral Bracing ● Tongue depressor and screw system to align frames ● Gusset plates added on small members ● Cross-bracing cut and placed one at a time at the end
  • 11. Testing/Performance (1) Testing Method ● Metal bar laid on platform at top center of bridge ● Chain hung over bar then attached beneath bucket ● Began at ten pounds then weight was added until failure
  • 12. Testing/Performance (2) The bridge met all design requirements ● Minimum 36” span with no more than ½” at each support ● Minimum height 5”, width 4” for truck to pass ● Less than 0.25” deflection ● Did not exceed 30% over-order Weight of load at failure 53.5 lb Length 40” Height 6” Width 4” Weight of bridge 135.6 g
  • 14. Post Test Evaluation (1) Bridge main failure points
  • 15. Post Test Evaluation (2) Gusset plate and member shear failures
  • 16. Post Test Evaluation (3) Length 40” Height 6” Width 4” Weight of bridge 135.6 g Weight of load at failure 53.5 lb
  • 17. Post Test Evaluation (4) ● More efficient design can be achieved ○ Underestimation of elastic modulus Trial Length (cm) Width (cm) Moment of Inertia (cm4 ) Load (N) Length (cm) Deflection (cm) Elastic Modulus (GPa) 1 0.318 0.318 8.468E-04 0.196 25.000 1.800 6.704 2 0.318 0.318 8.468E-04 0.196 25.000 2.200 5.485 3 0.159 0.159 5.293E-05 0.098 10.000 1.000 6.178 4 0.159 0.159 5.293E-05 0.098 10.000 1.500 4.119 Our data (left), researched data (right)
  • 18. Conclusions - The bridge met all design requirements - The bridge was over designed - What we would improve ● Use larger gusset plate ● Take into account the thickness of each member ● Measure the actual elastic modulus of the material