SlideShare a Scribd company logo
TrussBridge​ ​Optimization
May​ ​2,​ ​2015
By​ ​Ralph​ ​Gemade,​ ​Alphonse​ ​Mugisha,​ ​Mathew​ ​Quirong,​ ​Johann​ ​Ortiz-Franco
Abstract:
In​ ​this​ ​project,​ ​we​ ​were​ ​instructed​ ​to​ ​make​ ​three​ ​iterations​ ​of​ ​a​ ​truss​ ​bridge​ ​given
multiple​ ​constraints​ ​to​ ​work​ ​with.​ ​The​ ​goal​ ​was​ ​to​ ​build​ ​the​ ​truss​ ​bridge​ ​and​ ​improve​ ​upon​ ​it,
each​ ​time​ ​reducing​ ​the​ ​weight​ ​of​ ​the​ ​bridge​ ​while​ ​it​ ​still​ ​met​ ​the​ ​required​ ​standards.​ ​Upon
completing​ ​our​ ​fully​ ​optimized​ ​truss​ ​bridge,​ ​it​ ​weighed​ ​15.28kN.​ ​This​ ​was​ ​a​ ​significant
improvement​ ​from​ ​our​ ​initial​ ​truss​ ​which​ ​weighed​ ​28.35kN.
Introduction:
The​ ​goal​ ​of​ ​this​ ​project​ ​is​ ​for​ ​our​ ​group​ ​to​ ​design​ ​and​ ​optimize​ ​a​ ​bridge​ ​consisting​ ​of​ ​6
modules,​ ​each​ ​spanning​ ​52​ ​meters​ ​in​ ​length.​ ​It​ ​must​ ​fit​ ​within​ ​a​ ​9​ ​meter​ ​height​ ​and​ ​support​ ​a
deck​ ​at​ ​a​ ​height​ ​of​ ​4.5​ ​meters​ ​above​ ​the​ ​pier.​ ​With​ ​the​ ​use​ ​of​ ​Dr.​ ​Frame,​ ​we​ ​were​ ​able​ ​to​ ​design
half​ ​of​ ​a​ ​module​ ​as​ ​each​ ​module​ ​is​ ​vertically​ ​symmetrical​ ​at​ ​the​ ​center​ ​point​ ​between​ ​two​ ​piers
and​ ​again​ ​along​ ​the​ ​middle​ ​of​ ​the​ ​pier​ ​itself.​ ​To​ ​accounts​ ​for​ ​the​ ​presence​ ​of​ ​the​ ​rest​ ​of​ ​the
structure,​ ​we​ ​utilized​ ​the​ ​software​ ​by​ ​positioning​ ​rollers​ ​along​ ​those​ ​lines​ ​of​ ​symmetry​ ​in​ ​order
to​ ​constrain​ ​the​ ​movement​ ​of​ ​the​ ​structure​ ​as​ ​if​ ​the​ ​rest​ ​of​ ​the​ ​structure​ ​was​ ​present.​ ​In​ ​designing
the​ ​bridge,we​ ​had​ ​multiple​ ​constraints​ ​that​ ​we​ ​had​ ​to​ ​follow,​ ​and​ ​these​ ​included​ ​the​ ​geometrical
constraints​ ​of​ ​the​ ​bridge​ ​as​ ​well​ ​as​ ​the​ ​type​ ​of​ ​material​ ​we​ ​could​ ​use​ ​in​ ​the​ ​construction​ ​of​ ​our
truss​ ​bridge​ ​and​ ​the​ ​support​ ​conditions​ ​of​ ​the​ ​bridge.​ ​One​ ​of​ ​these​ ​constraints​ ​was​ ​the​ ​joints
resting​ ​on​ ​the​ ​pier​ ​that​ ​had​ ​to​ ​be​ ​pin​ ​connected.​ ​This​ ​means​ ​that​ ​the​ ​joints​ ​are​ ​not​ ​allowed​ ​to
translate​ ​in​ ​either​ ​vertical​ ​or​ ​horizontal​ ​direction;​ ​they​ ​can​ ​only​ ​rotate.​ ​Members​ ​along​ ​the
symmetry​ ​lines​ ​​ ​must​ ​be​ ​free​ ​to​ ​move​ ​​ ​along​ ​the​ ​line​ ​of​ ​symmetry​ ​and​ ​constrained​ ​in​ ​the
direction​ ​perpendicular​ ​to​ ​the​ ​symmetry​ ​line.​ ​Not​ ​only​ ​this,​ ​but​ ​the​ ​members​ ​can​ ​be​ ​no​ ​more
than​ ​10m​ ​in​ ​length.​ ​The​ ​material​ ​used​ ​in​ ​the​ ​truss​ ​are​ ​straight​ ​bars​ ​of​ ​pine​ ​timber​ ​and​ ​the​ ​cross
sections​ ​available​ ​for​ ​construction​ ​of​ ​the​ ​bridge​ ​are,​ ​5x5​ ​cm,​ ​10x10cm,​ ​20x20​ ​cm,​ ​30x30​ ​cm,
and​ ​40x40cm.​ ​We’re​ ​allowed​ ​to​ ​use​ ​different​ ​cross​ ​section​ ​dimensions​ ​in​ ​the​ ​same​ ​truss​ ​design.
The​ ​mechanical​ ​properties​ ​of​ ​pine​ ​are,​ ​elastic​ ​modulus,​ ​E=​ ​10​ ​GPa,​ ​strength​ ​in​ ​tension,​ ​σst​ ​=100
MPa,​ ​strength​ ​in​ ​compression,​ ​σcr​ ​=27​ ​MPa,​ ​and​ ​density​ ​of​ ​the​ ​wood,​ ​ρ​ ​=​ ​350​ ​kg/m​3​
.
For​ ​the​ ​live​ ​load​ ​acting​ ​on​ ​the​ ​truss​ ​due​ ​to​ ​traffic​ ​and​ ​the​ ​deck​ ​weight​ ​itself,​ ​we​ ​have
4.9kN​ ​for​ ​every​ ​meter​ ​of​ ​the​ ​road​ ​deck.​ ​Thus​ ​we​ ​have​ ​that​ ​the​ ​total​ ​live​ ​is​ ​127.4​ ​kN.​ ​Apart​ ​from
all​ ​of​ ​this,​ ​the​ ​imperial​ ​building​ ​code​ ​requires​ ​that​ ​as​ ​we​ ​construct​ ​our​ ​bridge,​ ​we​ ​use​ ​a​ ​factor​ ​of
safety​ ​of
5​ ​to​ ​ensure​ ​that​ ​the​ ​structure​ ​is​ ​very​ ​safe​ ​for​ ​use​ ​by​ ​the​ ​public.With​ ​this​ ​safety​ ​factor​ ​we​ ​have
that​ ​allowed​ ​stress​ ​in​ ​tension​ ​is​ ​20MPa​ ​and​ ​allowed​ ​stress​ ​in​ ​compression​ ​is​ ​5.4MPa.
Truss​ ​Design:
In​ ​designing​ ​our​ ​truss,​ ​we​ ​began​ ​with​ ​a​ ​simple​ ​design​ ​that​ ​would​ ​not​ ​fail​ ​under​ ​the
different​ ​tests​ ​that​ ​it​ ​had​ ​to​ ​pass,​ ​which​ ​meant​ ​that​ ​the​ ​stresses​ ​in​ ​the​ ​elements​ ​had​ ​to​ ​be​ ​less​ ​that
what​ ​was​ ​allowed,​ ​and​ ​this​ ​was​ ​5.4MPa​ ​for​ ​the​ ​elements​ ​in​ ​compression​ ​and​ ​20MPa​ ​for​ ​those​ ​in
tension.​ ​The​ ​objective​ ​of​ ​the​ ​initial​ ​design​ ​was​ ​to​ ​find​ ​a​ ​truss​ ​that​ ​worked​ ​the​ ​different
constraints​ ​given.​ ​Once​ ​the​ ​truss​ ​design​ ​was​ ​determined,​ ​the​ ​goal​ ​from​ ​there​ ​was​ ​to​ ​optimize​ ​it​ ​to
the​ ​best​ ​of​ ​our​ ​ability.​ ​The​ ​initial​ ​step​ ​taken​ ​toward​ ​optimization​ ​of​ ​our​ ​truss​ ​was​ ​to​ ​remove​ ​the
members​ ​which​ ​we​ ​considered​ ​unnecessary.​ ​These​ ​included​ ​members​ ​that​ ​carried​ ​very​ ​little
force​ ​without​ ​helping​ ​to​ ​reduce​ ​the​ ​force​ ​of​ ​the​ ​other​ ​members.​ ​Although​ ​this​ ​reduced​ ​the​ ​weight
of​ ​the​ ​truss​ ​by​ ​a​ ​good​ ​amount,​ ​more​ ​changes​ ​could​ ​be​ ​made​ ​to​ ​reduce​ ​the​ ​weight​ ​even​ ​further.
To​ ​do​ ​so,​ ​we​ ​began​ ​by​ ​decreasing​ ​the​ ​cross​ ​sectional​ ​areas​ ​of​ ​the​ ​members​ ​that​ ​carried​ ​little
forces​ ​as​ ​well​ ​as​ ​those​ ​in​ ​tension​ ​for​ ​they​ ​had​ ​a​ ​higher​ ​allowable​ ​stress​ ​and​ ​making​ ​sure​ ​that​ ​the
stress​ ​in​ ​these​ ​members​ ​was​ ​less​ ​than​ ​the​ ​allowable​ ​stress.​ ​For​ ​this​ ​reason​ ​the​ ​truss​ ​could​ ​be​ ​light
and​ ​still​ ​be​ ​able​ ​to​ ​carry​ ​the​ ​desired​ ​loads.
Figure​ ​1:​ ​Truss​ ​Geometry
​ ​Figure​ ​2:​ ​Live​ ​Loads
Figure​ ​3:​ ​Dead​ ​Loads
Element Side​ ​[m] area​ ​[m^2]
2nd​ ​area
mom.​ ​[m^4] length​ ​[m]
Dead​ ​Load
[kN]
Live​ ​Load
[kN]
AB 0.3 0.09 0.000675 4.50 1.3906
AC 0.3 0.09 0.000675 6.50 2.0086 31.85
AD 0.3 0.09 0.000675 7.90 2.4412
CD 0.3 0.09 0.000675 4.50 1.3906
CF 0.3 0.09 0.000675 6.50 2.0086 31.85
CG 0.3 0.09 0.000675 7.90 2.4412
EG 0.4 0.16 0.002133333 4.20 2.3073
FG 0.3 0.09 0.000675 4.50 1.3906
FH 0.3 0.09 0.000675 6.50 2.0086 31.85
FI 0.3 0.09 0.000675 7.00 2.1631
GI 0.3 0.09 0.000675 6.80 2.1013
HI 0.3 0.09 0.000675 2.50 0.7725
HJ 0.3 0.09 0.000675 6.50 2.0086 31.85
HK 0.3 0.09 0.000675 7.00 2.1631
IK 0.3 0.09 0.000675 6.50 2.0086
JK 0.3 0.09 0.000675 2.50 0.7725
Table​ ​1:​ ​Element​ ​cross​ ​sectional​ ​area,​ ​dead​ ​loads,​ ​and​ ​live​ ​loads

More Related Content

What's hot

200 questions answers
200 questions answers200 questions answers
200 questions answers
Abhilash Chandra Dey
 
Modeling and Analysis of Retrofitted Exterior RC Beam Column connection
Modeling and Analysis of Retrofitted Exterior RC Beam Column connectionModeling and Analysis of Retrofitted Exterior RC Beam Column connection
Modeling and Analysis of Retrofitted Exterior RC Beam Column connection
maged salama
 
Ch8 Truss Bridges (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Metwally ...
Ch8 Truss Bridges (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Metwally ...Ch8 Truss Bridges (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Metwally ...
Ch8 Truss Bridges (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Metwally ...
Hossam Shafiq II
 
Ppt for tensigrity
 Ppt for tensigrity Ppt for tensigrity
Ppt for tensigrity
Vívék Sâí
 
Tensegrity
TensegrityTensegrity
Tensegrity
Mahindra Venkat
 
IRJET- Review Paper of Tensegrity Structure
IRJET- Review Paper of Tensegrity StructureIRJET- Review Paper of Tensegrity Structure
IRJET- Review Paper of Tensegrity Structure
IRJET Journal
 
Design of pile cap
Design of  pile capDesign of  pile cap
Design of pile cap
Puspendu Ray
 
Ch1 Introduction (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Metwally A...
Ch1 Introduction (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Metwally A...Ch1 Introduction (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Metwally A...
Ch1 Introduction (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Metwally A...
Hossam Shafiq II
 
Design of Prestressed Concrete - <topic>
Design of Prestressed Concrete  - <topic>Design of Prestressed Concrete  - <topic>
Design of Prestressed Concrete - <topic>
S M Rahat Rahman
 
Top civil engineering Interview questions and Answers
Top civil engineering Interview questions and AnswersTop civil engineering Interview questions and Answers
Top civil engineering Interview questions and Answers
Ram N
 
Ch4 Bridge Floors (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Metwally ...
Ch4 Bridge Floors (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Metwally ...Ch4 Bridge Floors (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Metwally ...
Ch4 Bridge Floors (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Metwally ...
Hossam Shafiq II
 
Mechanism of load transfored...PRC-I
Mechanism of load transfored...PRC-IMechanism of load transfored...PRC-I
Mechanism of load transfored...PRC-I
Irfan Malik
 
Design of Beam- RCC Singly Reinforced Beam
Design of Beam- RCC Singly Reinforced BeamDesign of Beam- RCC Singly Reinforced Beam
Design of Beam- RCC Singly Reinforced Beam
SHAZEBALIKHAN1
 
Modeling and Analysis of Retrofitted Exterior RC Beam Column Joint
 Modeling and Analysis of Retrofitted Exterior RC Beam Column Joint Modeling and Analysis of Retrofitted Exterior RC Beam Column Joint
Modeling and Analysis of Retrofitted Exterior RC Beam Column Joint
maged salama
 
Design of beams
Design of beamsDesign of beams
Design of beams
Sabna Thilakan
 
Comparison Of Square And Raft Footing For A Multistory Building Under Static ...
Comparison Of Square And Raft Footing For A Multistory Building Under Static ...Comparison Of Square And Raft Footing For A Multistory Building Under Static ...
Comparison Of Square And Raft Footing For A Multistory Building Under Static ...
Lovneesh Modi
 
Shear connector 081281000409
Shear connector 081281000409Shear connector 081281000409
Shear connector 081281000409
shear connector
 
IJERD (www.ijerd.com) International Journal of Engineering Research and Devel...
IJERD (www.ijerd.com) International Journal of Engineering Research and Devel...IJERD (www.ijerd.com) International Journal of Engineering Research and Devel...
IJERD (www.ijerd.com) International Journal of Engineering Research and Devel...IJERD Editor
 

What's hot (20)

final404report
final404reportfinal404report
final404report
 
200 questions answers
200 questions answers200 questions answers
200 questions answers
 
Modeling and Analysis of Retrofitted Exterior RC Beam Column connection
Modeling and Analysis of Retrofitted Exterior RC Beam Column connectionModeling and Analysis of Retrofitted Exterior RC Beam Column connection
Modeling and Analysis of Retrofitted Exterior RC Beam Column connection
 
Ch8 Truss Bridges (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Metwally ...
Ch8 Truss Bridges (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Metwally ...Ch8 Truss Bridges (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Metwally ...
Ch8 Truss Bridges (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Metwally ...
 
Ppt for tensigrity
 Ppt for tensigrity Ppt for tensigrity
Ppt for tensigrity
 
Tensegrity
TensegrityTensegrity
Tensegrity
 
IRJET- Review Paper of Tensegrity Structure
IRJET- Review Paper of Tensegrity StructureIRJET- Review Paper of Tensegrity Structure
IRJET- Review Paper of Tensegrity Structure
 
Design of pile cap
Design of  pile capDesign of  pile cap
Design of pile cap
 
Ch1 Introduction (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Metwally A...
Ch1 Introduction (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Metwally A...Ch1 Introduction (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Metwally A...
Ch1 Introduction (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Metwally A...
 
Design of Prestressed Concrete - <topic>
Design of Prestressed Concrete  - <topic>Design of Prestressed Concrete  - <topic>
Design of Prestressed Concrete - <topic>
 
Top civil engineering Interview questions and Answers
Top civil engineering Interview questions and AnswersTop civil engineering Interview questions and Answers
Top civil engineering Interview questions and Answers
 
Ch4 Bridge Floors (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Metwally ...
Ch4 Bridge Floors (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Metwally ...Ch4 Bridge Floors (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Metwally ...
Ch4 Bridge Floors (Steel Bridges تصميم الكباري المعدنية & Prof. Dr. Metwally ...
 
Mechanism of load transfored...PRC-I
Mechanism of load transfored...PRC-IMechanism of load transfored...PRC-I
Mechanism of load transfored...PRC-I
 
Design of Beam- RCC Singly Reinforced Beam
Design of Beam- RCC Singly Reinforced BeamDesign of Beam- RCC Singly Reinforced Beam
Design of Beam- RCC Singly Reinforced Beam
 
Modeling and Analysis of Retrofitted Exterior RC Beam Column Joint
 Modeling and Analysis of Retrofitted Exterior RC Beam Column Joint Modeling and Analysis of Retrofitted Exterior RC Beam Column Joint
Modeling and Analysis of Retrofitted Exterior RC Beam Column Joint
 
Design of beams
Design of beamsDesign of beams
Design of beams
 
Comparison Of Square And Raft Footing For A Multistory Building Under Static ...
Comparison Of Square And Raft Footing For A Multistory Building Under Static ...Comparison Of Square And Raft Footing For A Multistory Building Under Static ...
Comparison Of Square And Raft Footing For A Multistory Building Under Static ...
 
Shear connector 081281000409
Shear connector 081281000409Shear connector 081281000409
Shear connector 081281000409
 
IJERD (www.ijerd.com) International Journal of Engineering Research and Devel...
IJERD (www.ijerd.com) International Journal of Engineering Research and Devel...IJERD (www.ijerd.com) International Journal of Engineering Research and Devel...
IJERD (www.ijerd.com) International Journal of Engineering Research and Devel...
 
Losses in prestress
Losses in prestressLosses in prestress
Losses in prestress
 

Similar to Final project mec e 3

Building Structure Project 1 Report
Building Structure Project 1 ReportBuilding Structure Project 1 Report
Building Structure Project 1 Report
kimberleyee95
 
bridge report
bridge reportbridge report
bridge report
abc def
 
Building Structure Project 1 Fettuccine Bridge
Building Structure Project 1 Fettuccine BridgeBuilding Structure Project 1 Fettuccine Bridge
Building Structure Project 1 Fettuccine Bridge
Colby Hooi
 
Paper Bridge - Design, FEA & Construction
Paper Bridge - Design, FEA & ConstructionPaper Bridge - Design, FEA & Construction
Paper Bridge - Design, FEA & Construction
Dibyajyoti Laha
 
Building Structure Project 1
Building Structure Project 1Building Structure Project 1
Building Structure Project 1
Pinkie95
 
BUILDING STRUCTURES PROJECT 1 FETTUCCINE TRUSS BRIDGE
BUILDING STRUCTURES PROJECT 1 FETTUCCINE TRUSS BRIDGEBUILDING STRUCTURES PROJECT 1 FETTUCCINE TRUSS BRIDGE
BUILDING STRUCTURES PROJECT 1 FETTUCCINE TRUSS BRIDGE
Patricia Kong
 
Building structure report xoxoxo
Building structure report xoxoxoBuilding structure report xoxoxo
Building structure report xoxoxo
Jason Juen
 
Building structure report xoxoxo
Building structure report xoxoxoBuilding structure report xoxoxo
Building structure report xoxoxo
Anthony Chew
 
Building structure report xoxoxo
Building structure report xoxoxoBuilding structure report xoxoxo
Building structure report xoxoxo
Jason Juen
 
Final Report (Balsa Wood Bridge Design)
Final Report (Balsa Wood Bridge Design)Final Report (Balsa Wood Bridge Design)
Final Report (Balsa Wood Bridge Design)Josia Tannos, EIT
 
Design and analysis of stress ribbon bridges
Design and analysis of stress ribbon bridgesDesign and analysis of stress ribbon bridges
Design and analysis of stress ribbon bridges
eSAT Journals
 
Design and analysis of stress ribbon bridges
Design and analysis of stress ribbon bridgesDesign and analysis of stress ribbon bridges
Design and analysis of stress ribbon bridges
eSAT Journals
 
Building structure report
Building structure reportBuilding structure report
Building structure report
Chenyi Teo
 
FETTICCINE BRIDGE
FETTICCINE BRIDGEFETTICCINE BRIDGE
FETTICCINE BRIDGE
Pengeneee Peng
 
Fettucine
FettucineFettucine
Ijsea04031013
Ijsea04031013Ijsea04031013
Ijsea04031013
Editor IJCATR
 
Sub.ass.2
Sub.ass.2Sub.ass.2
Sub.ass.2
RajaVIGNESHPATHI
 
BUILDING STRUCTURE ASSIGNMENT 1
BUILDING STRUCTURE ASSIGNMENT 1BUILDING STRUCTURE ASSIGNMENT 1
BUILDING STRUCTURE ASSIGNMENT 1
Nur Zaas
 
Building Structures - Fettucine Bridge
Building Structures - Fettucine BridgeBuilding Structures - Fettucine Bridge
Building Structures - Fettucine Bridgenadiacbass
 
IRJET- Cost Analysis of Two-Way Slab and Post Tension Slab
IRJET-  	  Cost Analysis of Two-Way Slab and Post Tension SlabIRJET-  	  Cost Analysis of Two-Way Slab and Post Tension Slab
IRJET- Cost Analysis of Two-Way Slab and Post Tension Slab
IRJET Journal
 

Similar to Final project mec e 3 (20)

Building Structure Project 1 Report
Building Structure Project 1 ReportBuilding Structure Project 1 Report
Building Structure Project 1 Report
 
bridge report
bridge reportbridge report
bridge report
 
Building Structure Project 1 Fettuccine Bridge
Building Structure Project 1 Fettuccine BridgeBuilding Structure Project 1 Fettuccine Bridge
Building Structure Project 1 Fettuccine Bridge
 
Paper Bridge - Design, FEA & Construction
Paper Bridge - Design, FEA & ConstructionPaper Bridge - Design, FEA & Construction
Paper Bridge - Design, FEA & Construction
 
Building Structure Project 1
Building Structure Project 1Building Structure Project 1
Building Structure Project 1
 
BUILDING STRUCTURES PROJECT 1 FETTUCCINE TRUSS BRIDGE
BUILDING STRUCTURES PROJECT 1 FETTUCCINE TRUSS BRIDGEBUILDING STRUCTURES PROJECT 1 FETTUCCINE TRUSS BRIDGE
BUILDING STRUCTURES PROJECT 1 FETTUCCINE TRUSS BRIDGE
 
Building structure report xoxoxo
Building structure report xoxoxoBuilding structure report xoxoxo
Building structure report xoxoxo
 
Building structure report xoxoxo
Building structure report xoxoxoBuilding structure report xoxoxo
Building structure report xoxoxo
 
Building structure report xoxoxo
Building structure report xoxoxoBuilding structure report xoxoxo
Building structure report xoxoxo
 
Final Report (Balsa Wood Bridge Design)
Final Report (Balsa Wood Bridge Design)Final Report (Balsa Wood Bridge Design)
Final Report (Balsa Wood Bridge Design)
 
Design and analysis of stress ribbon bridges
Design and analysis of stress ribbon bridgesDesign and analysis of stress ribbon bridges
Design and analysis of stress ribbon bridges
 
Design and analysis of stress ribbon bridges
Design and analysis of stress ribbon bridgesDesign and analysis of stress ribbon bridges
Design and analysis of stress ribbon bridges
 
Building structure report
Building structure reportBuilding structure report
Building structure report
 
FETTICCINE BRIDGE
FETTICCINE BRIDGEFETTICCINE BRIDGE
FETTICCINE BRIDGE
 
Fettucine
FettucineFettucine
Fettucine
 
Ijsea04031013
Ijsea04031013Ijsea04031013
Ijsea04031013
 
Sub.ass.2
Sub.ass.2Sub.ass.2
Sub.ass.2
 
BUILDING STRUCTURE ASSIGNMENT 1
BUILDING STRUCTURE ASSIGNMENT 1BUILDING STRUCTURE ASSIGNMENT 1
BUILDING STRUCTURE ASSIGNMENT 1
 
Building Structures - Fettucine Bridge
Building Structures - Fettucine BridgeBuilding Structures - Fettucine Bridge
Building Structures - Fettucine Bridge
 
IRJET- Cost Analysis of Two-Way Slab and Post Tension Slab
IRJET-  	  Cost Analysis of Two-Way Slab and Post Tension SlabIRJET-  	  Cost Analysis of Two-Way Slab and Post Tension Slab
IRJET- Cost Analysis of Two-Way Slab and Post Tension Slab
 

Recently uploaded

HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
Robbie Edward Sayers
 
Courier management system project report.pdf
Courier management system project report.pdfCourier management system project report.pdf
Courier management system project report.pdf
Kamal Acharya
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Teleport Manpower Consultant
 
Forklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella PartsForklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella Parts
Intella Parts
 
Halogenation process of chemical process industries
Halogenation process of chemical process industriesHalogenation process of chemical process industries
Halogenation process of chemical process industries
MuhammadTufail242431
 
TECHNICAL TRAINING MANUAL GENERAL FAMILIARIZATION COURSE
TECHNICAL TRAINING MANUAL   GENERAL FAMILIARIZATION COURSETECHNICAL TRAINING MANUAL   GENERAL FAMILIARIZATION COURSE
TECHNICAL TRAINING MANUAL GENERAL FAMILIARIZATION COURSE
DuvanRamosGarzon1
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
gdsczhcet
 
Event Management System Vb Net Project Report.pdf
Event Management System Vb Net  Project Report.pdfEvent Management System Vb Net  Project Report.pdf
Event Management System Vb Net Project Report.pdf
Kamal Acharya
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation & Control
 
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxCFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
R&R Consult
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
obonagu
 
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang,  ICLR 2024, MLILAB, KAIST AI.pdfJ.Yang,  ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
MLILAB
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
Kamal Acharya
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Sreedhar Chowdam
 
LIGA(E)11111111111111111111111111111111111111111.ppt
LIGA(E)11111111111111111111111111111111111111111.pptLIGA(E)11111111111111111111111111111111111111111.ppt
LIGA(E)11111111111111111111111111111111111111111.ppt
ssuser9bd3ba
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
Amil Baba Dawood bangali
 
WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
AafreenAbuthahir2
 
DESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docxDESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docx
FluxPrime1
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
Divya Somashekar
 
Vaccine management system project report documentation..pdf
Vaccine management system project report documentation..pdfVaccine management system project report documentation..pdf
Vaccine management system project report documentation..pdf
Kamal Acharya
 

Recently uploaded (20)

HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
 
Courier management system project report.pdf
Courier management system project report.pdfCourier management system project report.pdf
Courier management system project report.pdf
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
 
Forklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella PartsForklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella Parts
 
Halogenation process of chemical process industries
Halogenation process of chemical process industriesHalogenation process of chemical process industries
Halogenation process of chemical process industries
 
TECHNICAL TRAINING MANUAL GENERAL FAMILIARIZATION COURSE
TECHNICAL TRAINING MANUAL   GENERAL FAMILIARIZATION COURSETECHNICAL TRAINING MANUAL   GENERAL FAMILIARIZATION COURSE
TECHNICAL TRAINING MANUAL GENERAL FAMILIARIZATION COURSE
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
 
Event Management System Vb Net Project Report.pdf
Event Management System Vb Net  Project Report.pdfEvent Management System Vb Net  Project Report.pdf
Event Management System Vb Net Project Report.pdf
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
 
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxCFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
 
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang,  ICLR 2024, MLILAB, KAIST AI.pdfJ.Yang,  ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
 
LIGA(E)11111111111111111111111111111111111111111.ppt
LIGA(E)11111111111111111111111111111111111111111.pptLIGA(E)11111111111111111111111111111111111111111.ppt
LIGA(E)11111111111111111111111111111111111111111.ppt
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
 
WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
 
DESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docxDESIGN A COTTON SEED SEPARATION MACHINE.docx
DESIGN A COTTON SEED SEPARATION MACHINE.docx
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
 
Vaccine management system project report documentation..pdf
Vaccine management system project report documentation..pdfVaccine management system project report documentation..pdf
Vaccine management system project report documentation..pdf
 

Final project mec e 3

  • 1. TrussBridge​ ​Optimization May​ ​2,​ ​2015 By​ ​Ralph​ ​Gemade,​ ​Alphonse​ ​Mugisha,​ ​Mathew​ ​Quirong,​ ​Johann​ ​Ortiz-Franco
  • 2. Abstract: In​ ​this​ ​project,​ ​we​ ​were​ ​instructed​ ​to​ ​make​ ​three​ ​iterations​ ​of​ ​a​ ​truss​ ​bridge​ ​given multiple​ ​constraints​ ​to​ ​work​ ​with.​ ​The​ ​goal​ ​was​ ​to​ ​build​ ​the​ ​truss​ ​bridge​ ​and​ ​improve​ ​upon​ ​it, each​ ​time​ ​reducing​ ​the​ ​weight​ ​of​ ​the​ ​bridge​ ​while​ ​it​ ​still​ ​met​ ​the​ ​required​ ​standards.​ ​Upon completing​ ​our​ ​fully​ ​optimized​ ​truss​ ​bridge,​ ​it​ ​weighed​ ​15.28kN.​ ​This​ ​was​ ​a​ ​significant improvement​ ​from​ ​our​ ​initial​ ​truss​ ​which​ ​weighed​ ​28.35kN. Introduction: The​ ​goal​ ​of​ ​this​ ​project​ ​is​ ​for​ ​our​ ​group​ ​to​ ​design​ ​and​ ​optimize​ ​a​ ​bridge​ ​consisting​ ​of​ ​6 modules,​ ​each​ ​spanning​ ​52​ ​meters​ ​in​ ​length.​ ​It​ ​must​ ​fit​ ​within​ ​a​ ​9​ ​meter​ ​height​ ​and​ ​support​ ​a deck​ ​at​ ​a​ ​height​ ​of​ ​4.5​ ​meters​ ​above​ ​the​ ​pier.​ ​With​ ​the​ ​use​ ​of​ ​Dr.​ ​Frame,​ ​we​ ​were​ ​able​ ​to​ ​design half​ ​of​ ​a​ ​module​ ​as​ ​each​ ​module​ ​is​ ​vertically​ ​symmetrical​ ​at​ ​the​ ​center​ ​point​ ​between​ ​two​ ​piers and​ ​again​ ​along​ ​the​ ​middle​ ​of​ ​the​ ​pier​ ​itself.​ ​To​ ​accounts​ ​for​ ​the​ ​presence​ ​of​ ​the​ ​rest​ ​of​ ​the structure,​ ​we​ ​utilized​ ​the​ ​software​ ​by​ ​positioning​ ​rollers​ ​along​ ​those​ ​lines​ ​of​ ​symmetry​ ​in​ ​order to​ ​constrain​ ​the​ ​movement​ ​of​ ​the​ ​structure​ ​as​ ​if​ ​the​ ​rest​ ​of​ ​the​ ​structure​ ​was​ ​present.​ ​In​ ​designing the​ ​bridge,we​ ​had​ ​multiple​ ​constraints​ ​that​ ​we​ ​had​ ​to​ ​follow,​ ​and​ ​these​ ​included​ ​the​ ​geometrical constraints​ ​of​ ​the​ ​bridge​ ​as​ ​well​ ​as​ ​the​ ​type​ ​of​ ​material​ ​we​ ​could​ ​use​ ​in​ ​the​ ​construction​ ​of​ ​our truss​ ​bridge​ ​and​ ​the​ ​support​ ​conditions​ ​of​ ​the​ ​bridge.​ ​One​ ​of​ ​these​ ​constraints​ ​was​ ​the​ ​joints resting​ ​on​ ​the​ ​pier​ ​that​ ​had​ ​to​ ​be​ ​pin​ ​connected.​ ​This​ ​means​ ​that​ ​the​ ​joints​ ​are​ ​not​ ​allowed​ ​to translate​ ​in​ ​either​ ​vertical​ ​or​ ​horizontal​ ​direction;​ ​they​ ​can​ ​only​ ​rotate.​ ​Members​ ​along​ ​the symmetry​ ​lines​ ​​ ​must​ ​be​ ​free​ ​to​ ​move​ ​​ ​along​ ​the​ ​line​ ​of​ ​symmetry​ ​and​ ​constrained​ ​in​ ​the direction​ ​perpendicular​ ​to​ ​the​ ​symmetry​ ​line.​ ​Not​ ​only​ ​this,​ ​but​ ​the​ ​members​ ​can​ ​be​ ​no​ ​more than​ ​10m​ ​in​ ​length.​ ​The​ ​material​ ​used​ ​in​ ​the​ ​truss​ ​are​ ​straight​ ​bars​ ​of​ ​pine​ ​timber​ ​and​ ​the​ ​cross sections​ ​available​ ​for​ ​construction​ ​of​ ​the​ ​bridge​ ​are,​ ​5x5​ ​cm,​ ​10x10cm,​ ​20x20​ ​cm,​ ​30x30​ ​cm, and​ ​40x40cm.​ ​We’re​ ​allowed​ ​to​ ​use​ ​different​ ​cross​ ​section​ ​dimensions​ ​in​ ​the​ ​same​ ​truss​ ​design. The​ ​mechanical​ ​properties​ ​of​ ​pine​ ​are,​ ​elastic​ ​modulus,​ ​E=​ ​10​ ​GPa,​ ​strength​ ​in​ ​tension,​ ​σst​ ​=100 MPa,​ ​strength​ ​in​ ​compression,​ ​σcr​ ​=27​ ​MPa,​ ​and​ ​density​ ​of​ ​the​ ​wood,​ ​ρ​ ​=​ ​350​ ​kg/m​3​ . For​ ​the​ ​live​ ​load​ ​acting​ ​on​ ​the​ ​truss​ ​due​ ​to​ ​traffic​ ​and​ ​the​ ​deck​ ​weight​ ​itself,​ ​we​ ​have 4.9kN​ ​for​ ​every​ ​meter​ ​of​ ​the​ ​road​ ​deck.​ ​Thus​ ​we​ ​have​ ​that​ ​the​ ​total​ ​live​ ​is​ ​127.4​ ​kN.​ ​Apart​ ​from
  • 3. all​ ​of​ ​this,​ ​the​ ​imperial​ ​building​ ​code​ ​requires​ ​that​ ​as​ ​we​ ​construct​ ​our​ ​bridge,​ ​we​ ​use​ ​a​ ​factor​ ​of safety​ ​of 5​ ​to​ ​ensure​ ​that​ ​the​ ​structure​ ​is​ ​very​ ​safe​ ​for​ ​use​ ​by​ ​the​ ​public.With​ ​this​ ​safety​ ​factor​ ​we​ ​have that​ ​allowed​ ​stress​ ​in​ ​tension​ ​is​ ​20MPa​ ​and​ ​allowed​ ​stress​ ​in​ ​compression​ ​is​ ​5.4MPa. Truss​ ​Design: In​ ​designing​ ​our​ ​truss,​ ​we​ ​began​ ​with​ ​a​ ​simple​ ​design​ ​that​ ​would​ ​not​ ​fail​ ​under​ ​the different​ ​tests​ ​that​ ​it​ ​had​ ​to​ ​pass,​ ​which​ ​meant​ ​that​ ​the​ ​stresses​ ​in​ ​the​ ​elements​ ​had​ ​to​ ​be​ ​less​ ​that what​ ​was​ ​allowed,​ ​and​ ​this​ ​was​ ​5.4MPa​ ​for​ ​the​ ​elements​ ​in​ ​compression​ ​and​ ​20MPa​ ​for​ ​those​ ​in tension.​ ​The​ ​objective​ ​of​ ​the​ ​initial​ ​design​ ​was​ ​to​ ​find​ ​a​ ​truss​ ​that​ ​worked​ ​the​ ​different constraints​ ​given.​ ​Once​ ​the​ ​truss​ ​design​ ​was​ ​determined,​ ​the​ ​goal​ ​from​ ​there​ ​was​ ​to​ ​optimize​ ​it​ ​to the​ ​best​ ​of​ ​our​ ​ability.​ ​The​ ​initial​ ​step​ ​taken​ ​toward​ ​optimization​ ​of​ ​our​ ​truss​ ​was​ ​to​ ​remove​ ​the members​ ​which​ ​we​ ​considered​ ​unnecessary.​ ​These​ ​included​ ​members​ ​that​ ​carried​ ​very​ ​little force​ ​without​ ​helping​ ​to​ ​reduce​ ​the​ ​force​ ​of​ ​the​ ​other​ ​members.​ ​Although​ ​this​ ​reduced​ ​the​ ​weight of​ ​the​ ​truss​ ​by​ ​a​ ​good​ ​amount,​ ​more​ ​changes​ ​could​ ​be​ ​made​ ​to​ ​reduce​ ​the​ ​weight​ ​even​ ​further. To​ ​do​ ​so,​ ​we​ ​began​ ​by​ ​decreasing​ ​the​ ​cross​ ​sectional​ ​areas​ ​of​ ​the​ ​members​ ​that​ ​carried​ ​little forces​ ​as​ ​well​ ​as​ ​those​ ​in​ ​tension​ ​for​ ​they​ ​had​ ​a​ ​higher​ ​allowable​ ​stress​ ​and​ ​making​ ​sure​ ​that​ ​the stress​ ​in​ ​these​ ​members​ ​was​ ​less​ ​than​ ​the​ ​allowable​ ​stress.​ ​For​ ​this​ ​reason​ ​the​ ​truss​ ​could​ ​be​ ​light and​ ​still​ ​be​ ​able​ ​to​ ​carry​ ​the​ ​desired​ ​loads. Figure​ ​1:​ ​Truss​ ​Geometry
  • 4. ​ ​Figure​ ​2:​ ​Live​ ​Loads Figure​ ​3:​ ​Dead​ ​Loads
  • 5. Element Side​ ​[m] area​ ​[m^2] 2nd​ ​area mom.​ ​[m^4] length​ ​[m] Dead​ ​Load [kN] Live​ ​Load [kN] AB 0.3 0.09 0.000675 4.50 1.3906 AC 0.3 0.09 0.000675 6.50 2.0086 31.85 AD 0.3 0.09 0.000675 7.90 2.4412 CD 0.3 0.09 0.000675 4.50 1.3906 CF 0.3 0.09 0.000675 6.50 2.0086 31.85 CG 0.3 0.09 0.000675 7.90 2.4412 EG 0.4 0.16 0.002133333 4.20 2.3073 FG 0.3 0.09 0.000675 4.50 1.3906 FH 0.3 0.09 0.000675 6.50 2.0086 31.85 FI 0.3 0.09 0.000675 7.00 2.1631 GI 0.3 0.09 0.000675 6.80 2.1013 HI 0.3 0.09 0.000675 2.50 0.7725 HJ 0.3 0.09 0.000675 6.50 2.0086 31.85 HK 0.3 0.09 0.000675 7.00 2.1631 IK 0.3 0.09 0.000675 6.50 2.0086 JK 0.3 0.09 0.000675 2.50 0.7725 Table​ ​1:​ ​Element​ ​cross​ ​sectional​ ​area,​ ​dead​ ​loads,​ ​and​ ​live​ ​loads