SlideShare a Scribd company logo
© 2015, Fiatech
AWP: From Theory To
PracticeCompelling
Image Here
(If Possible)
© 2015, Fiatech
OpportunitiesBeingAddressed
AWP in Oil and Gas Plant
• Client standing between EP and C
• Submission of IWP’s prior to work
execution at site
• Front end loading and job cards using DP
Compelling
Image Here
(If Possible)
© 2015, Fiatech
OpportunitiesBeingAddressed
AWP a contractual requirement
© 2015, Fiatech
PresentationTakeaways
Tools and Methods for applying AWP
• Systems used
• C3D Planner
• VBC
• Talisman
• Solinas
• Timesheet
• Atlas
• Data preparation/Integration
• Workflow
Compelling
Image Here
(If Possible)
© 2015, Fiatech
BIM Controls
3D Model
Engineering Data
Planning
Lean Construction
Advanced Work packaging
Visual Reporting
PresentationTakeaways
© 2015, Fiatech
AWP roles distribution
• Engaging all members of
the project
• Having a fully tagged 3D model
• Getting the MTO at early stage
Constraints&Barriers
© 2015, Fiatech
Case Scenario: Rabab Harweel Integrated Project
(RHIP, Oman)
Compelling
Image Here
 Production of Oil and Gas from the
Harweel oil reservoirs via miscible gas
injection (MGI)
 Production of gas/condensate from the
Rabab reservoir through partial recycle of
sour gas
 Export of Sweet Gas to the Salalah gas
pipeline (SGL)
 Contract Value 500 M$
Approach&BenefitsRealized
HARWEEL
© 2015, Fiatech
RHIP – Major Commodities
Sl. No. Item Description Unit Estimated
1 Concrete – (Structural + Building work) Cu. Mt. 71,800
2 Building - Block Works Built up area Sq. Mt. 14,616
3 Structural Steel Fabrication Tons 21,300
4 Structural Steel Erection Tons 30,118
5 Equipment Installation Tons 20,000
6 Equipment Installation Nos. 386
7 Pipe Support Fabrication Tons 1,639
8 U/G Piping Installation (PVC + UPVC) Lm 50,700
9 A/G Piping Fabrication & Erection Inch Dia. 516,805
10 Electrical Cable Pulling m 2,735,065
11 Lighting & Small Power (Eqpt. + Fixture) Sets 5,291
12 Instrumentation Cable Pulling m 524,860
13 Instrument Installation Nos. 4,875
14 Insulation Sq. Mt. 141,339
15 Painting Sq. Mt. 141,339
© 2015, Fiatech
Compelling
Image Here
Approach&BenefitsRealized
AWP workflow at RHIP
© 2015, Fiatech
Results
 More than 500 IWP’s submitted and items closed before planned start date.
 Log register per IWP for pending items from EP. (Claim purposes)
 A better forecast of required manpower.
 Improved crew productivity
FutureWork&IndustryAdoptionApproach&BenefitsRealized
© 2015, Fiatech
RHIP – Plot PlanApproach&BenefitsRealized
© 2015, Fiatech
AWP at RHIP
12
PAR 2A
Approach&BenefitsRealized
© 2015, Fiatech
Work Fronts Aggregation
Approach&BenefitsRealized
© 2015, Fiatech
Work Front
 Work Front Definition in C3D
 2D Maps  Volumes
Approach&BenefitsRealized
© 2015, Fiatech
Work Front
Work Front (Construction work Package):
Logical Boundaries
Aligned with general execution plan
Measureable and Trackable Unit
Each Work Front is given a unique identification tag
Work front TAG identifies the location and scope
5270-01-RPR-01A-WF01
PBS Scope Sequence No.
RPR – Regular Pipe Rack
01A – Pipe Rack 1A
Approach&BenefitsRealized
© 2015, Fiatech
Work Front
 Logical Work Front Definition
 Steel Structure – Module wise  Electrical Trench – Entire Trench as one WF
5270-01-RPR-01A-WF01 6321-01-ECT-02A-WF01
Approach&BenefitsRealized
© 2015, Fiatech
Installation Work Package
Work Package (Installation work Package):
Single Discipline
Specific Engineering and Procurement Deliverables
Measureable and Trackable Unit
Each IWP is given a unique identification tag
IWP TAG identifies the type of work. (discipline/sub discipline)
6327-01-RPR-01A-WF01-CX-FDN-0001
5270-01-RPR-01A-WF01-CS-HVY-0002
PARENT WF NAME DISCIPLINE CODE SEQUENCE NO. CX – CIVIL DISCIPLINE
FDN – FOUNDATIONS
CS – STRUCTURES
HVY – HEAVY STEEL STRUCTURE
Approach&BenefitsRealized
© 2015, Fiatech
Installation Work Package
 Foundation Work Package  Steel Structure Work Package
Approach&BenefitsRealized
© 2015, Fiatech
Approach&BenefitsRealized
Installation Work Package (2)
© 2015, Fiatech
Object Categorization
Approach&BenefitsRealized
© 2015, Fiatech
Linking IWP with WBSApproach&BenefitsRealized
© 2015, Fiatech
Front End Loading
Is the process of checking and preparing the execution elements that are required to consider a work
front as an open front through a check list.(HSE, PMV, Material, Drawings/Docs, Accessibility,
Manpower, etc..)
 FEL Template is created per work front type Ex: Regular pipe racks, Preassembles Pipe racks,
Equipment, cable laying.
 List of all deliverables required to consider a package as open front
 Template prepared in consultation with discipline heads and customized as per project scenarios
 FEL Template Loaded to VBC
 C3D Connects to VBC and generates checklist for each WF / IWP created
 FEL checklist is extracted per IWP and submitted to client
Approach&BenefitsRealized
© 2015, Fiatech
Front End Loading – FEL TemplateApproach&BenefitsRealized
© 2015, Fiatech
Work Packages for next 3 MonthsApproach&BenefitsRealized
© 2015, Fiatech
FEL- Linked DocumentsApproach&BenefitsRealized
© 2015, Fiatech
Approach&BenefitsRealized FEL- Linked Documents (2)
© 2015, Fiatech
Approach&BenefitsRealized
© 2015, Fiatech
Work
Order
s
Open
Fronts
S-Curve
Sequence
Of Work
Crew
Capacity
Approach&BenefitsRealized
© 2015, Fiatech
Approach&BenefitsRealized
Specify work in sequence
© 2015, Fiatech
Digital
pen form
Approach&BenefitsRealized
© 2015, Fiatech
Digital Pen based Work Orders
Approach&BenefitsRealized
© 2015, Fiatech
AWP in Future projects
Compelling
Image Here
• Grand Opera (Civil Project)– Dubai
• YKP – Oman ( Awarded based on RHIP)
• Subcontractor Coordination
FutureWork&IndustryAdoption
© 2015, Fiatech
Thank You… Are There Any Questions?
Name: Abdelghani Sinno
Title: Sr. VDC Consultant
Company: Consolidated Contractors Company
Email: asinno@ccc.net
Links: www.c3d.com
Photo
Contact&MoreInformation
AWP: From Theory to
Practice

More Related Content

What's hot

Epc for module mm1 mm2 baseline schedule level 3
Epc for module mm1  mm2  baseline schedule level 3Epc for module mm1  mm2  baseline schedule level 3
Epc for module mm1 mm2 baseline schedule level 3
robotbietcuoi
 
Advanced Work Packaging Overview
Advanced Work Packaging OverviewAdvanced Work Packaging Overview
Advanced Work Packaging Overview
The Advanced Work Packaging Institute
 
Advanced Work Packaging - Real Life Implementation
Advanced Work Packaging - Real Life ImplementationAdvanced Work Packaging - Real Life Implementation
Advanced Work Packaging - Real Life Implementation
CCT International
 
Second edition epc project rule of credit and progress measurement promo
Second edition epc project rule of credit and progress measurement promoSecond edition epc project rule of credit and progress measurement promo
Second edition epc project rule of credit and progress measurement promo
ignitetribes
 
30 60 90 percent ifc engineering what is the project progress - Oracle Prim...
30 60 90 percent ifc engineering   what is the project progress - Oracle Prim...30 60 90 percent ifc engineering   what is the project progress - Oracle Prim...
30 60 90 percent ifc engineering what is the project progress - Oracle Prim...
p6academy
 
Epc project interdepency and Work Flow- promo
Epc project interdepency and Work Flow- promoEpc project interdepency and Work Flow- promo
Epc project interdepency and Work Flow- promo
ignitetribes
 
AWP-Education-Primer.pdf
AWP-Education-Primer.pdfAWP-Education-Primer.pdf
AWP-Education-Primer.pdf
My own
 
Promo_Epc project rule of credit and progress measurement
Promo_Epc project rule of credit and progress measurement Promo_Epc project rule of credit and progress measurement
Promo_Epc project rule of credit and progress measurement
ignitetribes
 
WSP USA Overview
WSP USA OverviewWSP USA Overview
WSP USA Overview
WSP USA
 
Primavera P6 Tips and Tricks
Primavera P6 Tips and TricksPrimavera P6 Tips and Tricks
Primavera P6 Tips and Tricks
p6academy
 
Project control plan_draft
Project control plan_draftProject control plan_draft
Project control plan_draft
ignitetribes
 
Milestone checklist
Milestone checklist   Milestone checklist
oil gas engineering-41-phpapp02
oil gas engineering-41-phpapp02oil gas engineering-41-phpapp02
oil gas engineering-41-phpapp02Mario Fonseca
 
WORKFLOW
WORKFLOW WORKFLOW
WORKFLOW TW Carl
 
Project Schedule Management
Project Schedule ManagementProject Schedule Management
Project Schedule Management
M Maged Hegazy, LLM, MBA, CCP, P3O
 
Avoiding unrealistic schedules
Avoiding unrealistic schedulesAvoiding unrealistic schedules
Avoiding unrealistic schedules
Hatem Hegazi
 
Advanced Work Packaging
Advanced Work Packaging Advanced Work Packaging
Advanced Work Packaging
The Advanced Work Packaging Institute
 
Planning and Scheduling Construction Projects, Part 1: The Planning Process
Planning and Scheduling Construction Projects, Part 1: The Planning ProcessPlanning and Scheduling Construction Projects, Part 1: The Planning Process
Planning and Scheduling Construction Projects, Part 1: The Planning Process
Alberto Sanchez
 
Primavera p6 advanced project planning
Primavera p6 advanced project planningPrimavera p6 advanced project planning
Primavera p6 advanced project planning
Amit Kumar Senapati, PMP®
 

What's hot (20)

Epc for module mm1 mm2 baseline schedule level 3
Epc for module mm1  mm2  baseline schedule level 3Epc for module mm1  mm2  baseline schedule level 3
Epc for module mm1 mm2 baseline schedule level 3
 
Advanced Work Packaging Overview
Advanced Work Packaging OverviewAdvanced Work Packaging Overview
Advanced Work Packaging Overview
 
Advanced Work Packaging - Real Life Implementation
Advanced Work Packaging - Real Life ImplementationAdvanced Work Packaging - Real Life Implementation
Advanced Work Packaging - Real Life Implementation
 
Second edition epc project rule of credit and progress measurement promo
Second edition epc project rule of credit and progress measurement promoSecond edition epc project rule of credit and progress measurement promo
Second edition epc project rule of credit and progress measurement promo
 
30 60 90 percent ifc engineering what is the project progress - Oracle Prim...
30 60 90 percent ifc engineering   what is the project progress - Oracle Prim...30 60 90 percent ifc engineering   what is the project progress - Oracle Prim...
30 60 90 percent ifc engineering what is the project progress - Oracle Prim...
 
Epc project interdepency and Work Flow- promo
Epc project interdepency and Work Flow- promoEpc project interdepency and Work Flow- promo
Epc project interdepency and Work Flow- promo
 
Epc presentation robert foxpresentation
Epc presentation robert foxpresentationEpc presentation robert foxpresentation
Epc presentation robert foxpresentation
 
AWP-Education-Primer.pdf
AWP-Education-Primer.pdfAWP-Education-Primer.pdf
AWP-Education-Primer.pdf
 
Promo_Epc project rule of credit and progress measurement
Promo_Epc project rule of credit and progress measurement Promo_Epc project rule of credit and progress measurement
Promo_Epc project rule of credit and progress measurement
 
WSP USA Overview
WSP USA OverviewWSP USA Overview
WSP USA Overview
 
Primavera P6 Tips and Tricks
Primavera P6 Tips and TricksPrimavera P6 Tips and Tricks
Primavera P6 Tips and Tricks
 
Project control plan_draft
Project control plan_draftProject control plan_draft
Project control plan_draft
 
Milestone checklist
Milestone checklist   Milestone checklist
Milestone checklist
 
oil gas engineering-41-phpapp02
oil gas engineering-41-phpapp02oil gas engineering-41-phpapp02
oil gas engineering-41-phpapp02
 
WORKFLOW
WORKFLOW WORKFLOW
WORKFLOW
 
Project Schedule Management
Project Schedule ManagementProject Schedule Management
Project Schedule Management
 
Avoiding unrealistic schedules
Avoiding unrealistic schedulesAvoiding unrealistic schedules
Avoiding unrealistic schedules
 
Advanced Work Packaging
Advanced Work Packaging Advanced Work Packaging
Advanced Work Packaging
 
Planning and Scheduling Construction Projects, Part 1: The Planning Process
Planning and Scheduling Construction Projects, Part 1: The Planning ProcessPlanning and Scheduling Construction Projects, Part 1: The Planning Process
Planning and Scheduling Construction Projects, Part 1: The Planning Process
 
Primavera p6 advanced project planning
Primavera p6 advanced project planningPrimavera p6 advanced project planning
Primavera p6 advanced project planning
 

Viewers also liked

Interview with Olfa Hamdi - PM World Journal July 2016
Interview with Olfa Hamdi - PM World Journal July 2016Interview with Olfa Hamdi - PM World Journal July 2016
Interview with Olfa Hamdi - PM World Journal July 2016
The Advanced Work Packaging Institute
 
Integration
IntegrationIntegration
Integration
IFS
 
Fiatech2014__Berkoe_Rev_6b
Fiatech2014__Berkoe_Rev_6bFiatech2014__Berkoe_Rev_6b
Fiatech2014__Berkoe_Rev_6bJon Berkoe
 
Fiatech Presentation Berkoe_Crosby_Final
Fiatech Presentation Berkoe_Crosby_FinalFiatech Presentation Berkoe_Crosby_Final
Fiatech Presentation Berkoe_Crosby_FinalJon Berkoe
 
AACE_Western_Outline_Berkoe_Draft_3_5_Rev_2_no_video
AACE_Western_Outline_Berkoe_Draft_3_5_Rev_2_no_videoAACE_Western_Outline_Berkoe_Draft_3_5_Rev_2_no_video
AACE_Western_Outline_Berkoe_Draft_3_5_Rev_2_no_videoJon Berkoe
 
AVEVA ProCon Complete Contract Control
AVEVA ProCon Complete Contract ControlAVEVA ProCon Complete Contract Control
AVEVA ProCon Complete Contract Control
AVEVA ProCon
 
Hazardous Area Equipment Certification - ATEX (Zone 1 Zone 2), IEC Ex, NEMA (...
Hazardous Area Equipment Certification - ATEX (Zone 1 Zone 2), IEC Ex, NEMA (...Hazardous Area Equipment Certification - ATEX (Zone 1 Zone 2), IEC Ex, NEMA (...
Hazardous Area Equipment Certification - ATEX (Zone 1 Zone 2), IEC Ex, NEMA (...
Thorne & Derrick International
 
AVEVA ProCon: The 4P's for Building a Successful Capital Asset
AVEVA ProCon: The 4P's for Building a Successful Capital AssetAVEVA ProCon: The 4P's for Building a Successful Capital Asset
AVEVA ProCon: The 4P's for Building a Successful Capital Asset
AVEVA ProCon
 
AVEVA ProCon fiatech-shell-case-study-slideshare 2016
AVEVA ProCon fiatech-shell-case-study-slideshare 2016AVEVA ProCon fiatech-shell-case-study-slideshare 2016
AVEVA ProCon fiatech-shell-case-study-slideshare 2016
AVEVA ProCon
 
FIATECH 2011 - Reducing Costs and Increasing ROI: Project Management in the C...
FIATECH 2011 - Reducing Costs and Increasing ROI: Project Management in the C...FIATECH 2011 - Reducing Costs and Increasing ROI: Project Management in the C...
FIATECH 2011 - Reducing Costs and Increasing ROI: Project Management in the C...
Aconex
 
AVEVA ProCon FPSO Europe Congress 2016
AVEVA ProCon FPSO Europe Congress 2016AVEVA ProCon FPSO Europe Congress 2016
AVEVA ProCon FPSO Europe Congress 2016
AVEVA ProCon
 
Classification and Regulatory Standards used in Novel Design Concepts for Dee...
Classification and Regulatory Standards used in Novel Design Concepts for Dee...Classification and Regulatory Standards used in Novel Design Concepts for Dee...
Classification and Regulatory Standards used in Novel Design Concepts for Dee...
IQPC
 

Viewers also liked (12)

Interview with Olfa Hamdi - PM World Journal July 2016
Interview with Olfa Hamdi - PM World Journal July 2016Interview with Olfa Hamdi - PM World Journal July 2016
Interview with Olfa Hamdi - PM World Journal July 2016
 
Integration
IntegrationIntegration
Integration
 
Fiatech2014__Berkoe_Rev_6b
Fiatech2014__Berkoe_Rev_6bFiatech2014__Berkoe_Rev_6b
Fiatech2014__Berkoe_Rev_6b
 
Fiatech Presentation Berkoe_Crosby_Final
Fiatech Presentation Berkoe_Crosby_FinalFiatech Presentation Berkoe_Crosby_Final
Fiatech Presentation Berkoe_Crosby_Final
 
AACE_Western_Outline_Berkoe_Draft_3_5_Rev_2_no_video
AACE_Western_Outline_Berkoe_Draft_3_5_Rev_2_no_videoAACE_Western_Outline_Berkoe_Draft_3_5_Rev_2_no_video
AACE_Western_Outline_Berkoe_Draft_3_5_Rev_2_no_video
 
AVEVA ProCon Complete Contract Control
AVEVA ProCon Complete Contract ControlAVEVA ProCon Complete Contract Control
AVEVA ProCon Complete Contract Control
 
Hazardous Area Equipment Certification - ATEX (Zone 1 Zone 2), IEC Ex, NEMA (...
Hazardous Area Equipment Certification - ATEX (Zone 1 Zone 2), IEC Ex, NEMA (...Hazardous Area Equipment Certification - ATEX (Zone 1 Zone 2), IEC Ex, NEMA (...
Hazardous Area Equipment Certification - ATEX (Zone 1 Zone 2), IEC Ex, NEMA (...
 
AVEVA ProCon: The 4P's for Building a Successful Capital Asset
AVEVA ProCon: The 4P's for Building a Successful Capital AssetAVEVA ProCon: The 4P's for Building a Successful Capital Asset
AVEVA ProCon: The 4P's for Building a Successful Capital Asset
 
AVEVA ProCon fiatech-shell-case-study-slideshare 2016
AVEVA ProCon fiatech-shell-case-study-slideshare 2016AVEVA ProCon fiatech-shell-case-study-slideshare 2016
AVEVA ProCon fiatech-shell-case-study-slideshare 2016
 
FIATECH 2011 - Reducing Costs and Increasing ROI: Project Management in the C...
FIATECH 2011 - Reducing Costs and Increasing ROI: Project Management in the C...FIATECH 2011 - Reducing Costs and Increasing ROI: Project Management in the C...
FIATECH 2011 - Reducing Costs and Increasing ROI: Project Management in the C...
 
AVEVA ProCon FPSO Europe Congress 2016
AVEVA ProCon FPSO Europe Congress 2016AVEVA ProCon FPSO Europe Congress 2016
AVEVA ProCon FPSO Europe Congress 2016
 
Classification and Regulatory Standards used in Novel Design Concepts for Dee...
Classification and Regulatory Standards used in Novel Design Concepts for Dee...Classification and Regulatory Standards used in Novel Design Concepts for Dee...
Classification and Regulatory Standards used in Novel Design Concepts for Dee...
 

Similar to Fiatech 2016 - Advanced Work Packaging: from Theory to Practice

Pivotal microservices spring_pcf_skillsmatter.pptx
Pivotal microservices spring_pcf_skillsmatter.pptxPivotal microservices spring_pcf_skillsmatter.pptx
Pivotal microservices spring_pcf_skillsmatter.pptx
Sufyaan Kazi
 
To Microservices and Beyond
To Microservices and BeyondTo Microservices and Beyond
To Microservices and Beyond
Matt Stine
 
Removing Crucial Dependencies to Enable KPN as a Virtual Telecom Provider
Removing Crucial Dependencies to Enable KPN as a Virtual Telecom ProviderRemoving Crucial Dependencies to Enable KPN as a Virtual Telecom Provider
Removing Crucial Dependencies to Enable KPN as a Virtual Telecom Provider
CA Technologies
 
Concevoir et déployer vos applications a base de microservices sur Cloud Foundry
Concevoir et déployer vos applications a base de microservices sur Cloud FoundryConcevoir et déployer vos applications a base de microservices sur Cloud Foundry
Concevoir et déployer vos applications a base de microservices sur Cloud Foundry
VMware Tanzu
 
Lean Kanban India 2015 | Boring Flow Metrics! Having fun with them to make or...
Lean Kanban India 2015 | Boring Flow Metrics! Having fun with them to make or...Lean Kanban India 2015 | Boring Flow Metrics! Having fun with them to make or...
Lean Kanban India 2015 | Boring Flow Metrics! Having fun with them to make or...
LeanKanbanIndia
 
3983 cics java real life projects
3983   cics java real life projects3983   cics java real life projects
3983 cics java real life projects
nick_garrod
 
Project design considerations for integration of oem skid equipment with plan...
Project design considerations for integration of oem skid equipment with plan...Project design considerations for integration of oem skid equipment with plan...
Project design considerations for integration of oem skid equipment with plan...
IntelligentManufacturingInstitute
 
Automated Project Management Across Departments at Oi
Automated Project Management Across Departments at OiAutomated Project Management Across Departments at Oi
Automated Project Management Across Departments at Oi
CA Technologies
 
SW360 Update Tooling Telco
SW360 Update Tooling TelcoSW360 Update Tooling Telco
SW360 Update Tooling Telco
Shane Coughlan
 
See It Live - Single Pane of Glass Enterprise Monitoring with CA Unified Infr...
See It Live - Single Pane of Glass Enterprise Monitoring with CA Unified Infr...See It Live - Single Pane of Glass Enterprise Monitoring with CA Unified Infr...
See It Live - Single Pane of Glass Enterprise Monitoring with CA Unified Infr...
CA Technologies
 
[2015-11월 정기 세미나] Cloud Native Platform - Pivotal
[2015-11월 정기 세미나] Cloud Native Platform - Pivotal[2015-11월 정기 세미나] Cloud Native Platform - Pivotal
[2015-11월 정기 세미나] Cloud Native Platform - Pivotal
OpenStack Korea Community
 
Enterprise DevOps Transformation
Enterprise DevOps TransformationEnterprise DevOps Transformation
Enterprise DevOps Transformation
Bart Driscoll
 
Practical Reporting for Effective Analytical Data Intelligence with CA Worklo...
Practical Reporting for Effective Analytical Data Intelligence with CA Worklo...Practical Reporting for Effective Analytical Data Intelligence with CA Worklo...
Practical Reporting for Effective Analytical Data Intelligence with CA Worklo...
CA Technologies
 
Fmea alignment aiag_and_vda_-_eng
Fmea alignment aiag_and_vda_-_engFmea alignment aiag_and_vda_-_eng
Fmea alignment aiag_and_vda_-_eng
erkinguler
 
Nazeer Yusuff PLM-CAD -Profile
Nazeer Yusuff PLM-CAD -Profile Nazeer Yusuff PLM-CAD -Profile
Nazeer Yusuff PLM-CAD -Profile nazeer yusuff
 
I4MS Elaphe - Luka Ambrozick
I4MS Elaphe - Luka AmbrozickI4MS Elaphe - Luka Ambrozick
I4MS Elaphe - Luka Ambrozick
Laura Argilés Martínez
 
How NBCUniversal Adopted DevOps
How NBCUniversal Adopted DevOpsHow NBCUniversal Adopted DevOps
How NBCUniversal Adopted DevOps
Sanjeev Sharma
 
Deep dive into unifiers cash flow management - Oracle Primavera P6 Collaborat...
Deep dive into unifiers cash flow management - Oracle Primavera P6 Collaborat...Deep dive into unifiers cash flow management - Oracle Primavera P6 Collaborat...
Deep dive into unifiers cash flow management - Oracle Primavera P6 Collaborat...
p6academy
 
Realizing Traceability for Safety and Certainty
Realizing Traceability for Safety and CertaintyRealizing Traceability for Safety and Certainty
Realizing Traceability for Safety and Certainty
Steven Vettermann
 

Similar to Fiatech 2016 - Advanced Work Packaging: from Theory to Practice (20)

Pivotal microservices spring_pcf_skillsmatter.pptx
Pivotal microservices spring_pcf_skillsmatter.pptxPivotal microservices spring_pcf_skillsmatter.pptx
Pivotal microservices spring_pcf_skillsmatter.pptx
 
To Microservices and Beyond
To Microservices and BeyondTo Microservices and Beyond
To Microservices and Beyond
 
Removing Crucial Dependencies to Enable KPN as a Virtual Telecom Provider
Removing Crucial Dependencies to Enable KPN as a Virtual Telecom ProviderRemoving Crucial Dependencies to Enable KPN as a Virtual Telecom Provider
Removing Crucial Dependencies to Enable KPN as a Virtual Telecom Provider
 
Concevoir et déployer vos applications a base de microservices sur Cloud Foundry
Concevoir et déployer vos applications a base de microservices sur Cloud FoundryConcevoir et déployer vos applications a base de microservices sur Cloud Foundry
Concevoir et déployer vos applications a base de microservices sur Cloud Foundry
 
Lean Kanban India 2015 | Boring Flow Metrics! Having fun with them to make or...
Lean Kanban India 2015 | Boring Flow Metrics! Having fun with them to make or...Lean Kanban India 2015 | Boring Flow Metrics! Having fun with them to make or...
Lean Kanban India 2015 | Boring Flow Metrics! Having fun with them to make or...
 
Ayyadevara Rangadham 1203
Ayyadevara Rangadham 1203Ayyadevara Rangadham 1203
Ayyadevara Rangadham 1203
 
3983 cics java real life projects
3983   cics java real life projects3983   cics java real life projects
3983 cics java real life projects
 
Project design considerations for integration of oem skid equipment with plan...
Project design considerations for integration of oem skid equipment with plan...Project design considerations for integration of oem skid equipment with plan...
Project design considerations for integration of oem skid equipment with plan...
 
Automated Project Management Across Departments at Oi
Automated Project Management Across Departments at OiAutomated Project Management Across Departments at Oi
Automated Project Management Across Departments at Oi
 
SW360 Update Tooling Telco
SW360 Update Tooling TelcoSW360 Update Tooling Telco
SW360 Update Tooling Telco
 
See It Live - Single Pane of Glass Enterprise Monitoring with CA Unified Infr...
See It Live - Single Pane of Glass Enterprise Monitoring with CA Unified Infr...See It Live - Single Pane of Glass Enterprise Monitoring with CA Unified Infr...
See It Live - Single Pane of Glass Enterprise Monitoring with CA Unified Infr...
 
[2015-11월 정기 세미나] Cloud Native Platform - Pivotal
[2015-11월 정기 세미나] Cloud Native Platform - Pivotal[2015-11월 정기 세미나] Cloud Native Platform - Pivotal
[2015-11월 정기 세미나] Cloud Native Platform - Pivotal
 
Enterprise DevOps Transformation
Enterprise DevOps TransformationEnterprise DevOps Transformation
Enterprise DevOps Transformation
 
Practical Reporting for Effective Analytical Data Intelligence with CA Worklo...
Practical Reporting for Effective Analytical Data Intelligence with CA Worklo...Practical Reporting for Effective Analytical Data Intelligence with CA Worklo...
Practical Reporting for Effective Analytical Data Intelligence with CA Worklo...
 
Fmea alignment aiag_and_vda_-_eng
Fmea alignment aiag_and_vda_-_engFmea alignment aiag_and_vda_-_eng
Fmea alignment aiag_and_vda_-_eng
 
Nazeer Yusuff PLM-CAD -Profile
Nazeer Yusuff PLM-CAD -Profile Nazeer Yusuff PLM-CAD -Profile
Nazeer Yusuff PLM-CAD -Profile
 
I4MS Elaphe - Luka Ambrozick
I4MS Elaphe - Luka AmbrozickI4MS Elaphe - Luka Ambrozick
I4MS Elaphe - Luka Ambrozick
 
How NBCUniversal Adopted DevOps
How NBCUniversal Adopted DevOpsHow NBCUniversal Adopted DevOps
How NBCUniversal Adopted DevOps
 
Deep dive into unifiers cash flow management - Oracle Primavera P6 Collaborat...
Deep dive into unifiers cash flow management - Oracle Primavera P6 Collaborat...Deep dive into unifiers cash flow management - Oracle Primavera P6 Collaborat...
Deep dive into unifiers cash flow management - Oracle Primavera P6 Collaborat...
 
Realizing Traceability for Safety and Certainty
Realizing Traceability for Safety and CertaintyRealizing Traceability for Safety and Certainty
Realizing Traceability for Safety and Certainty
 

More from CCT International

BIM, Lean & Advanced Work Packaging - How do they fit together?
BIM, Lean & Advanced Work Packaging - How do they fit together? BIM, Lean & Advanced Work Packaging - How do they fit together?
BIM, Lean & Advanced Work Packaging - How do they fit together?
CCT International
 
Digital Transformation of the Construction Industry
Digital Transformation of the Construction IndustryDigital Transformation of the Construction Industry
Digital Transformation of the Construction Industry
CCT International
 
BIM In Practice Seminar
BIM In Practice Seminar BIM In Practice Seminar
BIM In Practice Seminar
CCT International
 
6.0 CURT CII - Digital Transformation of Construction Industry
6.0 CURT CII  - Digital Transformation of Construction Industry6.0 CURT CII  - Digital Transformation of Construction Industry
6.0 CURT CII - Digital Transformation of Construction Industry
CCT International
 
Adding Intelligence to AWP
Adding Intelligence to AWPAdding Intelligence to AWP
Adding Intelligence to AWP
CCT International
 
BIM Based Project Controls
BIM Based Project ControlsBIM Based Project Controls
BIM Based Project Controls
CCT International
 
Leveraging C3D® to Ensure Compliance of Site Execution Teams
Leveraging C3D® to Ensure Compliance of Site Execution TeamsLeveraging C3D® to Ensure Compliance of Site Execution Teams
Leveraging C3D® to Ensure Compliance of Site Execution Teams
CCT International
 
The Future is Now (5th BIM and Lean Conference 2017)
The Future is Now (5th BIM and Lean Conference 2017)The Future is Now (5th BIM and Lean Conference 2017)
The Future is Now (5th BIM and Lean Conference 2017)
CCT International
 
O&M Challenge: BIM and Laser Scanning, a Hospital Project from the Middle East
O&M Challenge: BIM and Laser Scanning, a Hospital Project from the Middle EastO&M Challenge: BIM and Laser Scanning, a Hospital Project from the Middle East
O&M Challenge: BIM and Laser Scanning, a Hospital Project from the Middle East
CCT International
 
Roads, Infrastructure and BIM
Roads, Infrastructure and BIMRoads, Infrastructure and BIM
Roads, Infrastructure and BIM
CCT International
 
Contractors: Get BIM Ready!
Contractors: Get BIM Ready!Contractors: Get BIM Ready!
Contractors: Get BIM Ready!
CCT International
 
Designing to Enhance Construction Planning & Monitoring
Designing to Enhance Construction Planning & MonitoringDesigning to Enhance Construction Planning & Monitoring
Designing to Enhance Construction Planning & Monitoring
CCT International
 
Mandated BIM! Are you ready?
Mandated BIM! Are you ready?Mandated BIM! Are you ready?
Mandated BIM! Are you ready?
CCT International
 
Integrating BIM and LEAN for Project Delivery - Construction of a Major Hospi...
Integrating BIM and LEAN for Project Delivery - Construction of a Major Hospi...Integrating BIM and LEAN for Project Delivery - Construction of a Major Hospi...
Integrating BIM and LEAN for Project Delivery - Construction of a Major Hospi...
CCT International
 
Make BIM work for you
Make BIM work for youMake BIM work for you
Make BIM work for you
CCT International
 
IBM Case Study of Maximo Implementation at CCC
IBM Case Study of Maximo Implementation at CCCIBM Case Study of Maximo Implementation at CCC
IBM Case Study of Maximo Implementation at CCC
CCT International
 
AF-1438: Transportation MUG: CCC's Use of Maximo for Fleet Management on Infr...
AF-1438: Transportation MUG: CCC's Use of Maximo for Fleet Management on Infr...AF-1438: Transportation MUG: CCC's Use of Maximo for Fleet Management on Infr...
AF-1438: Transportation MUG: CCC's Use of Maximo for Fleet Management on Infr...
CCT International
 
Computer Simulation: Quantifying and Substantiating a Claim for Extension of ...
Computer Simulation: Quantifying and Substantiating a Claim for Extension of ...Computer Simulation: Quantifying and Substantiating a Claim for Extension of ...
Computer Simulation: Quantifying and Substantiating a Claim for Extension of ...
CCT International
 
Asset Management - Bridging Boundaries in Ongoing Asset Management
Asset Management - Bridging Boundaries in Ongoing Asset ManagementAsset Management - Bridging Boundaries in Ongoing Asset Management
Asset Management - Bridging Boundaries in Ongoing Asset Management
CCT International
 
Imagine a World Without Isometric
Imagine a World Without IsometricImagine a World Without Isometric
Imagine a World Without Isometric
CCT International
 

More from CCT International (20)

BIM, Lean & Advanced Work Packaging - How do they fit together?
BIM, Lean & Advanced Work Packaging - How do they fit together? BIM, Lean & Advanced Work Packaging - How do they fit together?
BIM, Lean & Advanced Work Packaging - How do they fit together?
 
Digital Transformation of the Construction Industry
Digital Transformation of the Construction IndustryDigital Transformation of the Construction Industry
Digital Transformation of the Construction Industry
 
BIM In Practice Seminar
BIM In Practice Seminar BIM In Practice Seminar
BIM In Practice Seminar
 
6.0 CURT CII - Digital Transformation of Construction Industry
6.0 CURT CII  - Digital Transformation of Construction Industry6.0 CURT CII  - Digital Transformation of Construction Industry
6.0 CURT CII - Digital Transformation of Construction Industry
 
Adding Intelligence to AWP
Adding Intelligence to AWPAdding Intelligence to AWP
Adding Intelligence to AWP
 
BIM Based Project Controls
BIM Based Project ControlsBIM Based Project Controls
BIM Based Project Controls
 
Leveraging C3D® to Ensure Compliance of Site Execution Teams
Leveraging C3D® to Ensure Compliance of Site Execution TeamsLeveraging C3D® to Ensure Compliance of Site Execution Teams
Leveraging C3D® to Ensure Compliance of Site Execution Teams
 
The Future is Now (5th BIM and Lean Conference 2017)
The Future is Now (5th BIM and Lean Conference 2017)The Future is Now (5th BIM and Lean Conference 2017)
The Future is Now (5th BIM and Lean Conference 2017)
 
O&M Challenge: BIM and Laser Scanning, a Hospital Project from the Middle East
O&M Challenge: BIM and Laser Scanning, a Hospital Project from the Middle EastO&M Challenge: BIM and Laser Scanning, a Hospital Project from the Middle East
O&M Challenge: BIM and Laser Scanning, a Hospital Project from the Middle East
 
Roads, Infrastructure and BIM
Roads, Infrastructure and BIMRoads, Infrastructure and BIM
Roads, Infrastructure and BIM
 
Contractors: Get BIM Ready!
Contractors: Get BIM Ready!Contractors: Get BIM Ready!
Contractors: Get BIM Ready!
 
Designing to Enhance Construction Planning & Monitoring
Designing to Enhance Construction Planning & MonitoringDesigning to Enhance Construction Planning & Monitoring
Designing to Enhance Construction Planning & Monitoring
 
Mandated BIM! Are you ready?
Mandated BIM! Are you ready?Mandated BIM! Are you ready?
Mandated BIM! Are you ready?
 
Integrating BIM and LEAN for Project Delivery - Construction of a Major Hospi...
Integrating BIM and LEAN for Project Delivery - Construction of a Major Hospi...Integrating BIM and LEAN for Project Delivery - Construction of a Major Hospi...
Integrating BIM and LEAN for Project Delivery - Construction of a Major Hospi...
 
Make BIM work for you
Make BIM work for youMake BIM work for you
Make BIM work for you
 
IBM Case Study of Maximo Implementation at CCC
IBM Case Study of Maximo Implementation at CCCIBM Case Study of Maximo Implementation at CCC
IBM Case Study of Maximo Implementation at CCC
 
AF-1438: Transportation MUG: CCC's Use of Maximo for Fleet Management on Infr...
AF-1438: Transportation MUG: CCC's Use of Maximo for Fleet Management on Infr...AF-1438: Transportation MUG: CCC's Use of Maximo for Fleet Management on Infr...
AF-1438: Transportation MUG: CCC's Use of Maximo for Fleet Management on Infr...
 
Computer Simulation: Quantifying and Substantiating a Claim for Extension of ...
Computer Simulation: Quantifying and Substantiating a Claim for Extension of ...Computer Simulation: Quantifying and Substantiating a Claim for Extension of ...
Computer Simulation: Quantifying and Substantiating a Claim for Extension of ...
 
Asset Management - Bridging Boundaries in Ongoing Asset Management
Asset Management - Bridging Boundaries in Ongoing Asset ManagementAsset Management - Bridging Boundaries in Ongoing Asset Management
Asset Management - Bridging Boundaries in Ongoing Asset Management
 
Imagine a World Without Isometric
Imagine a World Without IsometricImagine a World Without Isometric
Imagine a World Without Isometric
 

Recently uploaded

CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxCFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
R&R Consult
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
thanhdowork
 
space technology lecture notes on satellite
space technology lecture notes on satellitespace technology lecture notes on satellite
space technology lecture notes on satellite
ongomchris
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Sreedhar Chowdam
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
obonagu
 
WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
AafreenAbuthahir2
 
AP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specificAP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specific
BrazilAccount1
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Teleport Manpower Consultant
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
Robbie Edward Sayers
 
Runway Orientation Based on the Wind Rose Diagram.pptx
Runway Orientation Based on the Wind Rose Diagram.pptxRunway Orientation Based on the Wind Rose Diagram.pptx
Runway Orientation Based on the Wind Rose Diagram.pptx
SupreethSP4
 
power quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptxpower quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptx
ViniHema
 
ethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.pptethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.ppt
Jayaprasanna4
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
SamSarthak3
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
bakpo1
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
gerogepatton
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Dr.Costas Sachpazis
 
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
zwunae
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
Kamal Acharya
 
MCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdfMCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdf
Osamah Alsalih
 
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang,  ICLR 2024, MLILAB, KAIST AI.pdfJ.Yang,  ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
MLILAB
 

Recently uploaded (20)

CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxCFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
 
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
RAT: Retrieval Augmented Thoughts Elicit Context-Aware Reasoning in Long-Hori...
 
space technology lecture notes on satellite
space technology lecture notes on satellitespace technology lecture notes on satellite
space technology lecture notes on satellite
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
 
WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
 
AP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specificAP LAB PPT.pdf ap lab ppt no title specific
AP LAB PPT.pdf ap lab ppt no title specific
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
 
Runway Orientation Based on the Wind Rose Diagram.pptx
Runway Orientation Based on the Wind Rose Diagram.pptxRunway Orientation Based on the Wind Rose Diagram.pptx
Runway Orientation Based on the Wind Rose Diagram.pptx
 
power quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptxpower quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptx
 
ethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.pptethical hacking in wireless-hacking1.ppt
ethical hacking in wireless-hacking1.ppt
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
 
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
一比一原版(IIT毕业证)伊利诺伊理工大学毕业证成绩单专业办理
 
Cosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdfCosmetic shop management system project report.pdf
Cosmetic shop management system project report.pdf
 
MCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdfMCQ Soil mechanics questions (Soil shear strength).pdf
MCQ Soil mechanics questions (Soil shear strength).pdf
 
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang,  ICLR 2024, MLILAB, KAIST AI.pdfJ.Yang,  ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
 

Fiatech 2016 - Advanced Work Packaging: from Theory to Practice

  • 1. © 2015, Fiatech AWP: From Theory To PracticeCompelling Image Here (If Possible)
  • 2. © 2015, Fiatech OpportunitiesBeingAddressed AWP in Oil and Gas Plant • Client standing between EP and C • Submission of IWP’s prior to work execution at site • Front end loading and job cards using DP Compelling Image Here (If Possible)
  • 4. © 2015, Fiatech PresentationTakeaways Tools and Methods for applying AWP • Systems used • C3D Planner • VBC • Talisman • Solinas • Timesheet • Atlas • Data preparation/Integration • Workflow Compelling Image Here (If Possible)
  • 5. © 2015, Fiatech BIM Controls 3D Model Engineering Data Planning Lean Construction Advanced Work packaging Visual Reporting PresentationTakeaways
  • 6. © 2015, Fiatech AWP roles distribution • Engaging all members of the project • Having a fully tagged 3D model • Getting the MTO at early stage Constraints&Barriers
  • 7. © 2015, Fiatech Case Scenario: Rabab Harweel Integrated Project (RHIP, Oman) Compelling Image Here  Production of Oil and Gas from the Harweel oil reservoirs via miscible gas injection (MGI)  Production of gas/condensate from the Rabab reservoir through partial recycle of sour gas  Export of Sweet Gas to the Salalah gas pipeline (SGL)  Contract Value 500 M$ Approach&BenefitsRealized HARWEEL
  • 8. © 2015, Fiatech RHIP – Major Commodities Sl. No. Item Description Unit Estimated 1 Concrete – (Structural + Building work) Cu. Mt. 71,800 2 Building - Block Works Built up area Sq. Mt. 14,616 3 Structural Steel Fabrication Tons 21,300 4 Structural Steel Erection Tons 30,118 5 Equipment Installation Tons 20,000 6 Equipment Installation Nos. 386 7 Pipe Support Fabrication Tons 1,639 8 U/G Piping Installation (PVC + UPVC) Lm 50,700 9 A/G Piping Fabrication & Erection Inch Dia. 516,805 10 Electrical Cable Pulling m 2,735,065 11 Lighting & Small Power (Eqpt. + Fixture) Sets 5,291 12 Instrumentation Cable Pulling m 524,860 13 Instrument Installation Nos. 4,875 14 Insulation Sq. Mt. 141,339 15 Painting Sq. Mt. 141,339
  • 9. © 2015, Fiatech Compelling Image Here Approach&BenefitsRealized AWP workflow at RHIP
  • 10. © 2015, Fiatech Results  More than 500 IWP’s submitted and items closed before planned start date.  Log register per IWP for pending items from EP. (Claim purposes)  A better forecast of required manpower.  Improved crew productivity FutureWork&IndustryAdoptionApproach&BenefitsRealized
  • 11. © 2015, Fiatech RHIP – Plot PlanApproach&BenefitsRealized
  • 12. © 2015, Fiatech AWP at RHIP 12 PAR 2A Approach&BenefitsRealized
  • 13. © 2015, Fiatech Work Fronts Aggregation Approach&BenefitsRealized
  • 14. © 2015, Fiatech Work Front  Work Front Definition in C3D  2D Maps  Volumes Approach&BenefitsRealized
  • 15. © 2015, Fiatech Work Front Work Front (Construction work Package): Logical Boundaries Aligned with general execution plan Measureable and Trackable Unit Each Work Front is given a unique identification tag Work front TAG identifies the location and scope 5270-01-RPR-01A-WF01 PBS Scope Sequence No. RPR – Regular Pipe Rack 01A – Pipe Rack 1A Approach&BenefitsRealized
  • 16. © 2015, Fiatech Work Front  Logical Work Front Definition  Steel Structure – Module wise  Electrical Trench – Entire Trench as one WF 5270-01-RPR-01A-WF01 6321-01-ECT-02A-WF01 Approach&BenefitsRealized
  • 17. © 2015, Fiatech Installation Work Package Work Package (Installation work Package): Single Discipline Specific Engineering and Procurement Deliverables Measureable and Trackable Unit Each IWP is given a unique identification tag IWP TAG identifies the type of work. (discipline/sub discipline) 6327-01-RPR-01A-WF01-CX-FDN-0001 5270-01-RPR-01A-WF01-CS-HVY-0002 PARENT WF NAME DISCIPLINE CODE SEQUENCE NO. CX – CIVIL DISCIPLINE FDN – FOUNDATIONS CS – STRUCTURES HVY – HEAVY STEEL STRUCTURE Approach&BenefitsRealized
  • 18. © 2015, Fiatech Installation Work Package  Foundation Work Package  Steel Structure Work Package Approach&BenefitsRealized
  • 20. © 2015, Fiatech Object Categorization Approach&BenefitsRealized
  • 21. © 2015, Fiatech Linking IWP with WBSApproach&BenefitsRealized
  • 22. © 2015, Fiatech Front End Loading Is the process of checking and preparing the execution elements that are required to consider a work front as an open front through a check list.(HSE, PMV, Material, Drawings/Docs, Accessibility, Manpower, etc..)  FEL Template is created per work front type Ex: Regular pipe racks, Preassembles Pipe racks, Equipment, cable laying.  List of all deliverables required to consider a package as open front  Template prepared in consultation with discipline heads and customized as per project scenarios  FEL Template Loaded to VBC  C3D Connects to VBC and generates checklist for each WF / IWP created  FEL checklist is extracted per IWP and submitted to client Approach&BenefitsRealized
  • 23. © 2015, Fiatech Front End Loading – FEL TemplateApproach&BenefitsRealized
  • 24. © 2015, Fiatech Work Packages for next 3 MonthsApproach&BenefitsRealized
  • 25. © 2015, Fiatech FEL- Linked DocumentsApproach&BenefitsRealized
  • 26. © 2015, Fiatech Approach&BenefitsRealized FEL- Linked Documents (2)
  • 28. © 2015, Fiatech Work Order s Open Fronts S-Curve Sequence Of Work Crew Capacity Approach&BenefitsRealized
  • 30. © 2015, Fiatech Digital pen form Approach&BenefitsRealized
  • 31. © 2015, Fiatech Digital Pen based Work Orders Approach&BenefitsRealized
  • 32. © 2015, Fiatech AWP in Future projects Compelling Image Here • Grand Opera (Civil Project)– Dubai • YKP – Oman ( Awarded based on RHIP) • Subcontractor Coordination FutureWork&IndustryAdoption
  • 33. © 2015, Fiatech Thank You… Are There Any Questions? Name: Abdelghani Sinno Title: Sr. VDC Consultant Company: Consolidated Contractors Company Email: asinno@ccc.net Links: www.c3d.com Photo Contact&MoreInformation AWP: From Theory to Practice

Editor's Notes

  1. Guideline Please read this… Your breakout session presentation CAN NOT exceed 30min. In consideration and courtesy to other presenters there will be no exceptions You should never have to read from your slides… bullet points should act as a reminder for what you would like to say This presentation template is structured to provide continuity and consistency in flow (slide 2) which should not be changed Each subsequent slide has a banner (on the left) to convey the purpose of the slide. If you can adhere to the 30min constraint feel free to add additional slides; be sure to use the correct banner Use images as much as possible to convey your points Please note this presentation is in 16:9 format so you may need to rework some of your slides if importing from 4:3 format You should never have complex unreadable images or text Tables, documents with additional details and other resources can be added to the conference app for the attendees to access during the presentation Please keep audience in mind always… do not use acronyms or any terminology that is not already being used by a large cross-section of the industry Do not market your company Develop options for providing follow up information such as links or documents, all can be connected to your speaker profile in the conference app Do not assume you presentation is clear, concise and efficient, conduct presentation dry runs to verify message and time Do not procrastinate make sure your presentation is complete and turned in by February 15, 2016; changes at the conference cannot be accepted Provide your contact information on the last slide in your deck Allow for Q&A to occur via questions provided via the conference app, which can be answered during or after the presentation.