Advanced Work Packaging (AWP) 
and Integrated Materials 
Management (IMM) 
Ray Topping 
Fiatech
Advanced Work Packaging Information 
Mapping (AIM) – Raising Project Performance 
Ray Topping, PE 
Fiatech Director
Agenda 
Advanced Work Packaging 
AIM Purpose 
AIM Deliverables 
AIM Implementation Guide 
Questions & Discussion
Examples of Capital Projects 
Industry Work Packaging 
Engineering 
Work 
Packages 
Construction 
Work 
Packages 
Installation 
Work 
Packages 
System 
Commissioning 
Packages 
System 
Turnover 
Packages 
Test 
Packages 
Fabrication 
Packages 
Procurement 
Packages 
Initial Project 
Focus Area
IWP an Example of AWP Motivation 
• Construction Industry Institute (CII) studies* have shown that 25% to 40% of the construction 
installed costs is from direct labor and IWP promises the benefit of up to 25% improvement in field 
productivity, and a 4-10% reduction in total installed project costs. 
Personal Typical workday (8hr) 
0 0.5 1 1.5 2 2.5 
Material Handling 
Preparatory Work 
Waiting 
Travel 
Tools and Equipment 
Direct Work 
consumption of time 
Hours * IR 252-2A, 2010
AIM - Advanced Workface Packaging 
Information Management 
CII Identified AWP Potential 
• Up to 25% increase in productivity 
• Reduction in TIC of 4-10% 
• Increased Predictability / Visibility 
• Safety Benefits 
Identified Barrier 
Data Provisioning 
CII RT 272 
Fiatech AIM Project
Martin Swaine – Shell 
Mark Shively – Shell 
Terry Erhart – Hatch 
Bill O’Brien – U of Texas, Austin 
Ted Blackmon – Construct-X 
Reg Hunter – FIATECH 
Jen Rizzo – AVEVA 
Moussa Konate - AVEVA 
Mike Mosley – Zachry 
John Corzo – Zachry 
Todd Sutton – Zachry 
Dan Slade – Jacobs 
Adam Carlson – Jacobs 
Dale Adcox – Jacobs 
Deborah McNeil – Dow 
T.A. Madhivanan – Dow 
Lawrence Dowe – Chevron 
Angela Spadafino – Chevron 
Eric Crivella – Bentley 
Robin Mikaelsson – Bentley 
Don Gibson – Black & Veatch 
Dan Macek – Black & Veatch 
Judy Veatch – Black & Veatch 
John Fish – Ford, Bacon 
&Davis 
Kathryn Lust – Mustang 
Lorna Shipp – Mustang 
Russ Parkin – HAL, Inc. 
Stephane Levesque – Hatch 
Saquib Haroon – Hatch 
Fiatech AIM 
Project 
Participants
AIM Project Background
AIM Deliverables 
• Information Workflows for AWP 
• Example ‘Next-Gen’ Work Pack 
• Approach for BOM Consolidation / Validation 
• Landscape of Software Tools to Support AWP 
• Library of AWP Data Exchanges 
• Relevant Industry Data Standards and Initiatives 
• Contractual Recommendations for Data 
Deliverables 
• AIM Implementation Guide
AIM Workflows 
Level 1 – 
Conceptual Diagram
AIM Workflows 
Level 2 Swim Lane Diagram 
Stake-holders 
Engineering 
Procurement & Materials 
Vendors / Fabricators 
Project Controls 
Construction 
Completions 
Owner-Operator 1 
Project Stages 
Preliminary Planning & 
Design 
Detailed Engineering 
Construction 
Completions 
Operations & Maintenance 1 
1. Latest draft diagram needs updated to further extend into Operations
AIM Workflows 
Level 3 
Swim Lane 
Diagrams 
Engineering 
Procurement 
/ Materials 
Management Project 
Controls 
Module Fab / 
Site 
Installation Completions 
Legend 
Deferred 
Starting 
In Progress 
Complete
BOM Consolidation & Validation Approach
Landscape of Software Tools to Support AWP
Library of AWP Data Exchanges 
Information 
Consumed 
Information 
Produced
Library of AWP Data Exchanges 
Construction Drawing Release Log 
Consolidated and Validated BOM 
CWP Release Plan 
Pipe Spool Isometric Details 
Structural Steel Details 
Engineering Lists and Component Registers 
Fabrication Progress Tracking 
Module Fabrication Tracking & Carry-over Work 
IWP Scope Definition 
IWP Release Plan 
Materials Allocation & Issue by IWP 
Crew Resource Availability 
Field Progress and Status of IWP Execution 
Progress Roll-Up from Field Execution of IWPs 
System and Test Pack Scope Definitions 
System Turnover Plan 
Required Data for Turnover into Operations
Relevant Industry Data Standards and Initiatives
Contractual Recommendations for Data Deliverables 
11 
Key Assumptions 
15 
Key Recommendations
AIM Implementation Guide – Jump Start 
CII – RT 272 Vol I 
Form a 
Leadership 
Team for the 
AWP Project 
Effort
AIM Implementation Guide – Early Planning 
CII – RT 272 Vol I 
Align with 
Material 
Responsibility 
Matrix 
Define IT 
Systems 
Architecture to 
Support Target 
AWP Scope 
Specify 
Project Data 
Deliverables to 
Support AWP 
Include Project 
Data Deliverables 
for AWP into 
Contracts
AIM Implementation Guide – Detailed Engineering 
CII – RT 272 Vol I 
Conduct Bench 
Tests of AWP 
Automation 
Systems 
Establish 
Process for 
Validation of 
BOM/MTO and 
other Data 
On-board New 
Stakeholders 
into AWP 
Environment
Copyright 2014. All rights reserved. 
Purpose 
• Provide methodology for identifying and 
organizing information to enable Advanced Work 
Packaging (AWP) 
• AIM Phase 2 will strengthen linkages to Material 
Flows 
Maturity/Readiness 
Development POC/Demo Adopt/Deploy 
Industry Relevance/Impact 
• Supported by Shell, Chevron, Dow, Hatch, 
Zachry and more than 20 other organizations 
• Enables realization of CII/COAA AWP providing 
benefits of up to 25% productivity improvement 
Advanced Work Packaging 
Information Mapping (AIM) 
 Advanced Work Packaging Information 
Mapping Overview/Guide (FRS-AIM-1) 
 Information Management Framework 
for Advanced Work Packaging (FIR-AIM- 
1) 
 Industry Software Platforms and 
Functions (FIR-AIM-2) 
 Contract Language Information 
Mapping Recommendations to Enable 
Advanced Work Packaging (FIR-AIM-3) 
Drafts complete, release Q1/2015 
Summary
Questions & Discussion 
AIM Deliverables 
• Information Workflows for AWP 
• Example ‘Next-Gen’ Work Pack 
• Approach for BOM Consolidation / Validation 
• Landscape of Software Tools to Support AWP 
• Library of AWP Data Exchanges 
• Relevant Industry Data Standards and Initiatives 
• Contractual Recommendations for Data 
Deliverables 
• AIM Implementation Guide
Integrated Materials Management 
Community of Interest (IMM-CoI) 
Ray Topping, PE 
Fiatech Director
Fiatech	members	have	set	Integrated	Automated	Procurement	 
&	Materials	Management	as	a	Strategic	Priority	 
Comparison	 
Materials	Management		 
&	Control	Costs	 
Manufacturing	 
Industry	 
1%		 
	 
Construc on	 
Industry	 
0.15%		 
	 
Marsh	 
Capital	Project	 
Total	Cost	 
Materials	&		 
Equipment		 
50	to	60%		 
Capital	Project	Schedule	 
Influencers	 
Materials	&		 
Equipment		 
Control		 
80%	 
CII
Integrated Materials Management 
Community of Interest (IMM-CoI) 
Monitoring & 
Controlling 
End$to$End'Interoperability'(ISO'15926'&'BIM)'Informa?on'Sharing' 
End-to-End ISO-15926 Enabled Information Gathering, Conditioning & Sharing 
Complete,	Real-Time,	Ac onable	Informa on	-	Feed	Forward	&	Backward	 
Fabrication 
& Assembly 
Lessons Learning 
Copyright 2014. All rights reserved. 
Ongoing 
Operations 
Construction 
Site 
Logistics 
In-Transit 
Logistics 
Planning & 
Organizing 
Designing Acquiring Maintaining 
Materials, Modules, Equipment, 
Subsystems, Work Packages, Spares, etc. 
FEED' 
Detailed' 
Design' 
Procurement' Logis?cs' Construc?on' Startup' Opera?ons' 
Opportunity'' 
Iden?fica?on' 
Capital'Project'Life'Cycles' 
It is All About: Visibility, Predictability, Accountability, and Control
Advanced Work Packaging 
Information Mapping (AIM)
Potential IMM Future-State Realization 
Contractors Use Their Internal Systems to Achieve Maximum Productivity and Value 
Purchasing 
Documents 
Status Rpts 
Drawings 
& Data 
3D Models 
Progress 
Reports 
RFIs FCOs 
Change 
Orders QA/QC 
Collaboration / Integration System 
Owner Lifecycle Systems 
ERP Asset 
Mgmt 
Instrument 
Control 
Maintenanc 
e/Reliability 
Warehouse 
Spare Parts 
Document 
Control 
MOC 
Mtls Mgmt 
Lifecycle 3D 
Model 
Progress Information 
Available Real-Time for 
Owner 
End of Project Download into 
Owner Lifecycle Systems 
Engineering 
Contractor1 
Engineering 
Contractor2 
Engineering 
Contractor3 
Engineering 
Contractor4 
Construction 
Contractor1 
Construction 
Contractor2 
Construction 
Contractor3 
Construction 
Contractor4
Industry 
Outreach & 
Engagement 
Portfolio of 
Use Case 
Priorities 
Enabling Fiatech 
Projects Use 
Case Slices 
Use Case Based 
Consensus 
Building 
Webinar Sharing of 
Advancements & 
Innovative Practices
Potential IMM COI Sponsored Webinars 
1) Enabling Advance Work Packaging — Linking the WorkFace Planners with Enabling Information 
Resources and Materials Visibility (Construct X) 
2) Industry Challenges to Effective WorkFace Planning (Aveva & Bentley) 
3) Proven Methods in Capturing, Converting, Managing and Global Sharing Product Information 
(Thomas) 
4) Predictive Performance Indicators — Enabling Management With Certainty (UT, Shell) 
5) Overcoming Roadblocks to Materials Identification, Selection and Procurement (FBD) 
6) Positive Materials Identification — Confronting the Counterfeiting Threat (intro Philips66, Thomas, 
Hal, Neway Valves) 
7) Increasing Construction Site Materials Visibility and Control (Atlas RFID, Inteliwave) 
8) Materials Risk Mitigation — Building a Framework to Identify and Resolve Disruptions to Material 
Flows (DevonWay) 
9) Maximizing In-Transit Materials Visibility, Predictability and Control (HAL) 
10) Advances in RFID technologies and use cases (OMNI-ID) 
11) Other?
E2open Company Overview
Boeing 787: Global Orchestration for Streamlined Assembly
Boeing 787: Coordination of Global Partner Operations 
About Boeing: 
• Dreamliner 787 Program 
oSupply Planning 
oForecast/Commits 
oLogistics Visibility 
• Over $80B Corp Revenue 
• Very complex, global Supply Chain footprint 
• Each Program has several unique suppliers / partners 
Suppliers 
Sub 
Upstream Assemblies 
Suppliers 
Inventory 
Hubs 
Benefits: 
• Eliminate latency across multiple partners 
• Automate delivery schedules & order changes 
• Ensure continuity of supply, minimize supply 
disruptions 
• Improved cash flow for business partners via 
managed inventory programs 
• Improved on-time delivery: minimizing logistics 
costs 
• Improve process management : reporting and 
About Boeing: 
• Dreamliner 787 Program 
oSupply Planning 
oForecast/Commits 
oLogistics Visibility 
• Over $80B Corp Revenue 
• Very complex, global Supply Chain footprint 
• Each Program has several unique suppliers / partners 
Revolutionary Approach to Partner Based Programs 
Focus: 
• Entire 787 mission critical supply chain managed 
with E2open 
• Achieved near real-time visibility for in transit 
packages 
• Solution scalable for all business partners 
irrespective of their technological sophistication
Use-Case Methodology, Summarized 
Keep it 
simple by 
telling stories 
Understand 
the big 
picture 
Focus on 
Value 
Build the 
system in 
slices 
Adapt to 
meet the 
team’s needs 
Deliver the 
system in 
increments 
Requirements 
Systems 
Tests 
Stories 
Use Cases 
Use Case 
Slices 
Source: http://www.ivarjacobson.com/uploadedFiles/Pages/Knowledge_Centre/Resources/White_Paper/Resources/IJI_Use- 
Case2_0.pdf
Use-Case Concept Map 
A use case is all the ways of using a 
system to achieve a particular goal for 
a particular user. 
To make the value easy to quantify, 
identify and deliver you need to 
structure the use-case narrative. 
A use-case slice is one or more stories 
selected from a use case to form a 
work item that is of clear value to 
stakeholders. 
Source: http://www.ivarjacobson.com/uploadedFiles/Pages/Knowledge_Centre/Resources/White_Paper/Resources/IJI_Use- 
Case2_0.pdf
Why Use-Case Methodology? 
• Action-oriented methodology, progressing from identification of needs to their 
fulfillment, allowing Fiatech CoIs to act as Change Agents 
Use Case 
(as-is) 
Identification 
of Need/ 
Problem 
Resolution 
Strategies 
Use Case 
(to-be) 
Use Case 
Slices 
System 
Realization 
Use Case Cycle 
Use Case Slice Cycle 
Work Packages driving Fiatech Projects
Call for Action – Collecting Stories 
• Identify stakeholder roles within your own organization 
• Identify needs and problems in current environment 
• Collect anecdotes, develop into comprehensive stories 
• Develop shared understanding of to-be state 
• Collaborate with Fiatech CoI to organize stories into Use 
Cases 
• Develop Use Case Slices 
• Initiate Fiatech Projects

#FiaComit - Advanced Works Packaging & Integrated Materials Management

  • 1.
    Advanced Work Packaging(AWP) and Integrated Materials Management (IMM) Ray Topping Fiatech
  • 2.
    Advanced Work PackagingInformation Mapping (AIM) – Raising Project Performance Ray Topping, PE Fiatech Director
  • 3.
    Agenda Advanced WorkPackaging AIM Purpose AIM Deliverables AIM Implementation Guide Questions & Discussion
  • 4.
    Examples of CapitalProjects Industry Work Packaging Engineering Work Packages Construction Work Packages Installation Work Packages System Commissioning Packages System Turnover Packages Test Packages Fabrication Packages Procurement Packages Initial Project Focus Area
  • 5.
    IWP an Exampleof AWP Motivation • Construction Industry Institute (CII) studies* have shown that 25% to 40% of the construction installed costs is from direct labor and IWP promises the benefit of up to 25% improvement in field productivity, and a 4-10% reduction in total installed project costs. Personal Typical workday (8hr) 0 0.5 1 1.5 2 2.5 Material Handling Preparatory Work Waiting Travel Tools and Equipment Direct Work consumption of time Hours * IR 252-2A, 2010
  • 6.
    AIM - AdvancedWorkface Packaging Information Management CII Identified AWP Potential • Up to 25% increase in productivity • Reduction in TIC of 4-10% • Increased Predictability / Visibility • Safety Benefits Identified Barrier Data Provisioning CII RT 272 Fiatech AIM Project
  • 7.
    Martin Swaine –Shell Mark Shively – Shell Terry Erhart – Hatch Bill O’Brien – U of Texas, Austin Ted Blackmon – Construct-X Reg Hunter – FIATECH Jen Rizzo – AVEVA Moussa Konate - AVEVA Mike Mosley – Zachry John Corzo – Zachry Todd Sutton – Zachry Dan Slade – Jacobs Adam Carlson – Jacobs Dale Adcox – Jacobs Deborah McNeil – Dow T.A. Madhivanan – Dow Lawrence Dowe – Chevron Angela Spadafino – Chevron Eric Crivella – Bentley Robin Mikaelsson – Bentley Don Gibson – Black & Veatch Dan Macek – Black & Veatch Judy Veatch – Black & Veatch John Fish – Ford, Bacon &Davis Kathryn Lust – Mustang Lorna Shipp – Mustang Russ Parkin – HAL, Inc. Stephane Levesque – Hatch Saquib Haroon – Hatch Fiatech AIM Project Participants
  • 8.
  • 9.
    AIM Deliverables •Information Workflows for AWP • Example ‘Next-Gen’ Work Pack • Approach for BOM Consolidation / Validation • Landscape of Software Tools to Support AWP • Library of AWP Data Exchanges • Relevant Industry Data Standards and Initiatives • Contractual Recommendations for Data Deliverables • AIM Implementation Guide
  • 10.
    AIM Workflows Level1 – Conceptual Diagram
  • 11.
    AIM Workflows Level2 Swim Lane Diagram Stake-holders Engineering Procurement & Materials Vendors / Fabricators Project Controls Construction Completions Owner-Operator 1 Project Stages Preliminary Planning & Design Detailed Engineering Construction Completions Operations & Maintenance 1 1. Latest draft diagram needs updated to further extend into Operations
  • 12.
    AIM Workflows Level3 Swim Lane Diagrams Engineering Procurement / Materials Management Project Controls Module Fab / Site Installation Completions Legend Deferred Starting In Progress Complete
  • 13.
    BOM Consolidation &Validation Approach
  • 14.
    Landscape of SoftwareTools to Support AWP
  • 15.
    Library of AWPData Exchanges Information Consumed Information Produced
  • 16.
    Library of AWPData Exchanges Construction Drawing Release Log Consolidated and Validated BOM CWP Release Plan Pipe Spool Isometric Details Structural Steel Details Engineering Lists and Component Registers Fabrication Progress Tracking Module Fabrication Tracking & Carry-over Work IWP Scope Definition IWP Release Plan Materials Allocation & Issue by IWP Crew Resource Availability Field Progress and Status of IWP Execution Progress Roll-Up from Field Execution of IWPs System and Test Pack Scope Definitions System Turnover Plan Required Data for Turnover into Operations
  • 17.
    Relevant Industry DataStandards and Initiatives
  • 18.
    Contractual Recommendations forData Deliverables 11 Key Assumptions 15 Key Recommendations
  • 19.
    AIM Implementation Guide– Jump Start CII – RT 272 Vol I Form a Leadership Team for the AWP Project Effort
  • 20.
    AIM Implementation Guide– Early Planning CII – RT 272 Vol I Align with Material Responsibility Matrix Define IT Systems Architecture to Support Target AWP Scope Specify Project Data Deliverables to Support AWP Include Project Data Deliverables for AWP into Contracts
  • 21.
    AIM Implementation Guide– Detailed Engineering CII – RT 272 Vol I Conduct Bench Tests of AWP Automation Systems Establish Process for Validation of BOM/MTO and other Data On-board New Stakeholders into AWP Environment
  • 22.
    Copyright 2014. Allrights reserved. Purpose • Provide methodology for identifying and organizing information to enable Advanced Work Packaging (AWP) • AIM Phase 2 will strengthen linkages to Material Flows Maturity/Readiness Development POC/Demo Adopt/Deploy Industry Relevance/Impact • Supported by Shell, Chevron, Dow, Hatch, Zachry and more than 20 other organizations • Enables realization of CII/COAA AWP providing benefits of up to 25% productivity improvement Advanced Work Packaging Information Mapping (AIM)  Advanced Work Packaging Information Mapping Overview/Guide (FRS-AIM-1)  Information Management Framework for Advanced Work Packaging (FIR-AIM- 1)  Industry Software Platforms and Functions (FIR-AIM-2)  Contract Language Information Mapping Recommendations to Enable Advanced Work Packaging (FIR-AIM-3) Drafts complete, release Q1/2015 Summary
  • 23.
    Questions & Discussion AIM Deliverables • Information Workflows for AWP • Example ‘Next-Gen’ Work Pack • Approach for BOM Consolidation / Validation • Landscape of Software Tools to Support AWP • Library of AWP Data Exchanges • Relevant Industry Data Standards and Initiatives • Contractual Recommendations for Data Deliverables • AIM Implementation Guide
  • 24.
    Integrated Materials Management Community of Interest (IMM-CoI) Ray Topping, PE Fiatech Director
  • 25.
    Fiatech members have set Integrated Automated Procurement & Materials Management as a Strategic Priority Comparison Materials Management & Control Costs Manufacturing Industry 1% Construc on Industry 0.15% Marsh Capital Project Total Cost Materials & Equipment 50 to 60% Capital Project Schedule Influencers Materials & Equipment Control 80% CII
  • 26.
    Integrated Materials Management Community of Interest (IMM-CoI) Monitoring & Controlling End$to$End'Interoperability'(ISO'15926'&'BIM)'Informa?on'Sharing' End-to-End ISO-15926 Enabled Information Gathering, Conditioning & Sharing Complete, Real-Time, Ac onable Informa on - Feed Forward & Backward Fabrication & Assembly Lessons Learning Copyright 2014. All rights reserved. Ongoing Operations Construction Site Logistics In-Transit Logistics Planning & Organizing Designing Acquiring Maintaining Materials, Modules, Equipment, Subsystems, Work Packages, Spares, etc. FEED' Detailed' Design' Procurement' Logis?cs' Construc?on' Startup' Opera?ons' Opportunity'' Iden?fica?on' Capital'Project'Life'Cycles' It is All About: Visibility, Predictability, Accountability, and Control
  • 27.
    Advanced Work Packaging Information Mapping (AIM)
  • 28.
    Potential IMM Future-StateRealization Contractors Use Their Internal Systems to Achieve Maximum Productivity and Value Purchasing Documents Status Rpts Drawings & Data 3D Models Progress Reports RFIs FCOs Change Orders QA/QC Collaboration / Integration System Owner Lifecycle Systems ERP Asset Mgmt Instrument Control Maintenanc e/Reliability Warehouse Spare Parts Document Control MOC Mtls Mgmt Lifecycle 3D Model Progress Information Available Real-Time for Owner End of Project Download into Owner Lifecycle Systems Engineering Contractor1 Engineering Contractor2 Engineering Contractor3 Engineering Contractor4 Construction Contractor1 Construction Contractor2 Construction Contractor3 Construction Contractor4
  • 29.
    Industry Outreach & Engagement Portfolio of Use Case Priorities Enabling Fiatech Projects Use Case Slices Use Case Based Consensus Building Webinar Sharing of Advancements & Innovative Practices
  • 30.
    Potential IMM COISponsored Webinars 1) Enabling Advance Work Packaging — Linking the WorkFace Planners with Enabling Information Resources and Materials Visibility (Construct X) 2) Industry Challenges to Effective WorkFace Planning (Aveva & Bentley) 3) Proven Methods in Capturing, Converting, Managing and Global Sharing Product Information (Thomas) 4) Predictive Performance Indicators — Enabling Management With Certainty (UT, Shell) 5) Overcoming Roadblocks to Materials Identification, Selection and Procurement (FBD) 6) Positive Materials Identification — Confronting the Counterfeiting Threat (intro Philips66, Thomas, Hal, Neway Valves) 7) Increasing Construction Site Materials Visibility and Control (Atlas RFID, Inteliwave) 8) Materials Risk Mitigation — Building a Framework to Identify and Resolve Disruptions to Material Flows (DevonWay) 9) Maximizing In-Transit Materials Visibility, Predictability and Control (HAL) 10) Advances in RFID technologies and use cases (OMNI-ID) 11) Other?
  • 31.
  • 32.
    Boeing 787: GlobalOrchestration for Streamlined Assembly
  • 33.
    Boeing 787: Coordinationof Global Partner Operations About Boeing: • Dreamliner 787 Program oSupply Planning oForecast/Commits oLogistics Visibility • Over $80B Corp Revenue • Very complex, global Supply Chain footprint • Each Program has several unique suppliers / partners Suppliers Sub Upstream Assemblies Suppliers Inventory Hubs Benefits: • Eliminate latency across multiple partners • Automate delivery schedules & order changes • Ensure continuity of supply, minimize supply disruptions • Improved cash flow for business partners via managed inventory programs • Improved on-time delivery: minimizing logistics costs • Improve process management : reporting and About Boeing: • Dreamliner 787 Program oSupply Planning oForecast/Commits oLogistics Visibility • Over $80B Corp Revenue • Very complex, global Supply Chain footprint • Each Program has several unique suppliers / partners Revolutionary Approach to Partner Based Programs Focus: • Entire 787 mission critical supply chain managed with E2open • Achieved near real-time visibility for in transit packages • Solution scalable for all business partners irrespective of their technological sophistication
  • 34.
    Use-Case Methodology, Summarized Keep it simple by telling stories Understand the big picture Focus on Value Build the system in slices Adapt to meet the team’s needs Deliver the system in increments Requirements Systems Tests Stories Use Cases Use Case Slices Source: http://www.ivarjacobson.com/uploadedFiles/Pages/Knowledge_Centre/Resources/White_Paper/Resources/IJI_Use- Case2_0.pdf
  • 35.
    Use-Case Concept Map A use case is all the ways of using a system to achieve a particular goal for a particular user. To make the value easy to quantify, identify and deliver you need to structure the use-case narrative. A use-case slice is one or more stories selected from a use case to form a work item that is of clear value to stakeholders. Source: http://www.ivarjacobson.com/uploadedFiles/Pages/Knowledge_Centre/Resources/White_Paper/Resources/IJI_Use- Case2_0.pdf
  • 36.
    Why Use-Case Methodology? • Action-oriented methodology, progressing from identification of needs to their fulfillment, allowing Fiatech CoIs to act as Change Agents Use Case (as-is) Identification of Need/ Problem Resolution Strategies Use Case (to-be) Use Case Slices System Realization Use Case Cycle Use Case Slice Cycle Work Packages driving Fiatech Projects
  • 37.
    Call for Action– Collecting Stories • Identify stakeholder roles within your own organization • Identify needs and problems in current environment • Collect anecdotes, develop into comprehensive stories • Develop shared understanding of to-be state • Collaborate with Fiatech CoI to organize stories into Use Cases • Develop Use Case Slices • Initiate Fiatech Projects

Editor's Notes

  • #7 As adoption of work packaging grows across the industry, and as the practices and principles around the topic continue to mature, we’re seeing a convergence of information, materials, documentation, plans, schedule, etc. as well as an increasingly significant amount of anecdotal information coming forward from other companies that are using these tools. The result is a coalescing of a body of knowledge as well as a de facto collection of best practices, tools, templates, etc. In order to be successful at this we need to have some standardization of procedures, information exchange formats, and protocols. One of the advantages we get from FIATECH is access to a body of domain expertise and access to a group that is interested in defining these best practices and publishing recommendations, best practices, and guidelines. Today that effort is through an active FIATECH project called Advanced Work Packaging Information Management, or AIM for short. AIM is continuation of the great work done by CII’s RT-272 They stated that one of the primary barriers to implementation of work packaging in the industry is information management and standardization of workflows and processes. The presentation so far has focused on “refined to best practice” addressing how Advanced Workface Planning is implemented. In line with CII’s findings, we think that the ability to visualize project data with numerous disparate systems and data point is crucial and will provide significant benefits toward the predictability of our project execution. We also believe that as the tools improve they innately improve our ability to support the internal initiatives of engineering for construction safety. We anticipate a 10% growth in productivity; however, while this is noticeably less than the 25% figure put forward by the RT-272 study, this is largely due to the fact that Zachry has been doing workface planning in some shape or form for quite some time. Based upon what we have seen with the case study project, and as the AIM project continues to push forward with their mandate, we will continue to pull those artifacts into our SOP and the innate byproduct of doing so is improved project execution, improved vendor engagement, and ultimately, reductions in schedule. What I consider the most significant expected benefit is in regards to Total Installed Cost. As productivity increases, vendor performance improves, and schedule pressures are reduced we anticipate a notable reduction of TIC in the neighborhood of 5-7% .
  • #33 Transition from vertically integrated to global partner model Maintained contractual relationships with Tier-2 suppliers Enable Boeing to integrate with and orchestrate its business processes in a distributed supply network of 135 partners in 12 countries Synchronize demand/supply, order, and inventory information across all supply partners Improve on-time delivery and ship-to-commit date with end customer Provide global visibility to all partners involved in the delivery of the completed assemblies Buy-Side – Inventory Mgmt, Order Management, Multi-Enterprise Integration Coordinated events to ensure final assembly and delivery takes place in 9 days Improved cash flow for business partners via managed inventory programs Improved on-time delivery while minimizing logistics costs Improve process management through reporting and analysis
  • #34 Transition from vertically integrated to global partner model Maintained contractual relationships with Tier-2 suppliers Enable Boeing to integrate with and orchestrate its business processes in a distributed supply network of 135 partners in 12 countries Synchronize demand/supply, order, and inventory information across all supply partners Improve on-time delivery and ship-to-commit date with end customer Provide global visibility to all partners involved in the delivery of the completed assemblies Buy-Side – Inventory Mgmt, Order Management, Multi-Enterprise Integration Coordinated events to ensure final assembly and delivery takes place in 9 days Improved cash flow for business partners via managed inventory programs Improved on-time delivery while minimizing logistics costs Improve process management through reporting and analysis