BIM, LEAN AND ADVANCED WORK
PACKAGING
HOW DO THEY FIT TOGETHER?
ZUHAIR HADDAD
CIO – CCC/ CCT
http://www.cctintl.com/
THE INNOVATIVE PLATFORM FOR
EFFICIENT, LEAN AND TRANSPARENT
CONSTRUCTION PROCESS MANAGEMENT
ENABLING DIGITAL TRANSFORMATION OF CONSTRUCTION
 Critical path method (CPM) schedules
(primavera P6, Microsoft project and
similar) follow a top down approach
to construction project execution not
focusing on the process and mostly
neglecting the inter-relations of
multiple crews working in same
construction zones
 The result is typically obstruction of
crews rushing their way to individual
completion of tasks planned in the
schedule
WHY DO CURRENT METHODS FAIL?
THERE IS A HIGH CUSTOMER
NEED IN THE MARKET FOR
ONLINE COLLABORATION AND
DISRUPTIVE PLANNING TOOLS -
LCM DIGITAL® IS THE ONLY
ANSWER IN THE MARKET
DIGITAL CHANGES ARE MASSIVELY PUSHING THE MARKET
What we do better…
 Lean approaches are needed in the construction
industry – we use our chance
 Digital integrated construction processes help us
overcome current problems on site
 We are using the data: more data collection, data
analytics, benchmarks and machine learning
 Business Intelligence: the availability of qualified real
time data offers a high quality basis for scheduling,
design, integration, logistics and supply chain
 Integrated digital workflows: digital connection of
information leads to a very efficient and productive
communication and work results
 BIM is standard: offering data to bridge the gap
between the process and material availability as well
as online and onsite navigation
 We make mobile working happen, collaboration and
communication is redefining the way we work
together
THE MANAGEMENT PLATFORM
Plan your Strategy:
Segmentation of typical work and takt areas to define
process flow, team performance and duration
Plan your construction flow:
Use the typical takt areas to define your construction flow
(takt trains) by replication for a continuous flow and
optimal resource usage. Update your plan based on Live
Data from site and supply chain data
Production management on site:
Set your plan into action with a production management
system on site using Kanban boards and the LCM Digital
App for Live Updates.
Standard Processes
BIM Design / Engineering
Supply Chain
AI
STABILITY CRITERIA/ FRONT END LOADING
CHANGING THE WAY OF CONSTRUCTION MANAGEMENT
Consistent
process from
strategy to site
Standard
processes
Takt
planning
Easy to
use
Cloud based
collaboration
plattform
Live
update of
schedule
BIM
connected
LCM Digital®
App
Following the
plan without
deviations
Build on the
knowledge of your
team
Increase the takt
rate of your
construction project
Getting
everybody on
board to get the
job done
Easy to use on
site, everyday
Knowing what
is going on for
a better
management
Combining all digital
information for better
projects
LCM digital® offers high value during the planning process
 Built by 2 strong partners with years of experience in
construction – CCC and Drees & Sommer
 Based on construction know and IT know how
 LCM® takt planning has been proven in over 450 projects
over the past 12 years, improving project performance
with every project
 There is no other cloud-based product as
comprehensiveness and with full service as LCM digital®
 LCM digital® runs on different platforms and browsers for
PC, Mac, iPad, etc.
 We have a strong vision - the next steps implementing AI
and supply chain management are already on the way
THERE IS NO COMPARABLE TOOL WORLDWIDE
LCM DIGITAL® IS THE ONLY
CLOUD-BASED FULL SERVICE
SOFTWARE SOLUTION FOR
LEAN CONSTRUCTION
WORLDWIDE
BENEFITs FROM DIFFERENT PERSPECTIVES
OwnersProject management
and site management
Project involved
construction companies
LCM DIGITAL® WORKS
FOR DIFFERENT
CUSTOMER GROUPS
OUR ANALOG ROOTS - MAKING PROBLEMS VISIBLE AND
ELIMINATING THEM
OUR LEAN PHILOSOPHY
Many resources
are used to cover
problems.
Problems are
covered!
Create
transparency,
Reduce water.
Problems become
visible!
Problems have
been reduced or
eliminated
Causes are
permanently
eliminated!
PROBLEMS ARE
OFTEN COVERED BY
AN HEIGHTENED USE
OF RESOURCES –
LEAN PROCESS
MANAGEMENT
HELPS TO IDENTIFY
AND ELIMINATE THE
CAUSES BEHIND THIS
CIP*
*CIP = continuous improvement process
Traditional approach Lean Approach
ProblemsProblems Problems Problems
Capacity and Time
THE CONTENT & AREA DEFINITION
Daily Kanban Board
QR Code & APP
Takt Planning
Define Takt Types
Process Planning (Overall takted production schedule)
Takt AnalysisOverall Process AnalysisDefine Zone Types Define Takt Zones
Fragnet Concept
Areas with same work
sequence
(Class of Rooms)
Area type that can be
combined in a takt train
(Subclass of Rooms by
Size or minor work
difference)
Areas on site that are
combined in a takt train
sequence
(Instances per subclass)
Process Mapping and
Sequencing
Duration, Performance
& Quantities
 Construction
Flow Sequence,
 Leveling
 Resource
Optimization
 Scheduling
 Management &
Optimization
 Controlling &
Report
Daily update 3-
4 weeks
production
schedule
ZONE TYPES DEFINITION – CLASS OF ROOMS
Define Zone Types
Areas with same work
sequence
(Class of Rooms)
TAKT TYPES DEFINITION – SUB CLASS OF ROOMS
Define Takt Types
Area type that can be
combined in a takt train
(Subclass of Rooms by
Size or minor work
difference)
TAKT ZONES DEFINITION – ACTUAL INSTANCES OF
SUBCLASS
Define Takt Zones
Areas on site that are
combined in a takt train
sequence
(Instances per subclass)
OVERALL PROCESS ANALYSIS – FRAGNET DEFINITION
Takt Planning
Overall Process
Analysis
Takt Analysis
Process Planning (Overall takted production schedule)
Aim
To provide transparency,
create a common
understanding of process
steps and early identification
of problems and bottlenecks
Description
The process of creating the
optimal process sequence for
each zone type (working
area)
TAKT ANALYSIS – FRAGNET DURATIONS
Takt Planning
Overall Process
Analysis
Takt Analysis
Process Planning (Overall takted production schedule)
Aim
To prepare the overall
process analysis to transform
into an optimal process plan
populated with all the
relevant parameters
Description
The process of adding 3
dimensions namely duration,
material and manpower to
the overall process analysis
DEFINE TAKT ZONES – NAMING CONVENTION
Define Takt Zones
Areas on site that are
combined in a takt train
sequence
(Instances per subclass)
For All Selected Takt Types(
N=1;
For Takt Type(
Create Takt Zone = Area+SubArea+TaktType+N;
N= N+1;
)
)
DEFINE TAKT ZONES
TAKT PLANNING
Takt Planning
Overall Process
Analysis
Takt Analysis
Process Planning (Overall takted production schedule)
Aim
To allow for an iterative
process to find the most
efficient process plan in
terms of manhours and
quantities
Description
The process of sequencing
takt zones using takt
trains, dependencies and
time intervals
PROCESS PLANNING
Takt Planning
Overall Process
Analysis
Takt Analysis
Process Planning (Overall takted production schedule)
Aim
Have an overview/detailed
view of the schedule, front-
end loading and proactively
managing stability criteria
Description
The process of fine tuning
the takt analysis and takt
planning applied to all the
takt zones and assigning
the work of the next n
weeks to specific teams
DAILY KANBAN BOARD
Daily Kanban Board
QR Code & APP
Takt Planning
Overall Process
Analysis
Takt Analysis
Process Planning (Overall takted production schedule)
TO TAKT OR NOT TO TAKT? THAT IS THE QUESTION…
Takt planning is the process of trying to harmonize the durations for
every wagon in the train so as to keep the train moving together
If the blue wagon takes 2 times the duration of the other wagons,
the tail end of the train will fall behind every week.
We need a disruptive process to find an optimum solution.
CIFE Research in Collaboration with CCC
A Method to Quickly Generate Close-to-
optimum Look-Ahead Schedule (LAS) for
the Finishing Phase
Ning (Tony) Dong
PhD Committee:
Principle Advisor – Prof. Martin Fischer
Industrial Advisor – Mr. Zuhair Haddad
Prof. Raymond Levitt
Assist. Prof. Dongdong Ge
Why do we need a good LAS?
 A guidance to provide correct work sequence
 A shared means to prevent work conflict
 A whiteboard to provide improved awareness of resource utilization
Ultimately, a good LAS should be a way of presentation after pulling all different
data sources together to (1) facilitate coordination among various project
participants; (2) be actually used by the people from job site to guide field work
and (3) become a means of project monitor and control (i.e., progress
monitoring, crew/material forecasting, material reporting, etc.)
Why a good LAS is so important in the
finishing phase? – complex network
Activity network/fragnet for the finishing of one faculty room at CMU Qatar
Why a good LAS is so important in the
finishing phase?
GC needs to manage in the actual project:
 More than 200 rooms;
 More than 20 types of self-performed operations on average per room;
 More than 16 types of rooms (work sequence);
 More than 20 types of subs’ operations;
 More than 80 types of materials;
 More than 10 types of skilled workers/crews
Why a good LAS is so important in the
finishing phase? - constraints
Corridor Access Constraint Zone Constraint
Spatial Constraint
Why a good LAS looks like in the finishing
phase?
When
Who
What
Where
Work Days
Room ID Room-centered View of LAS
What a good LAS looks like in the finishing
phase?
Room-centered View of LAS
Install Conduit & Box  Plastering  Screed  Painting
What a good LAS looks like in the finishing
phase?
Crew ID
What
When
Who Where
Crew-centered View of LAS
Simulation Overall Description
User Input:
 Number of different types of crews
 Starting/available date of each room
 Duration of an operation when it is hard to calculate its actual length
 Corridor constraint, zone constraint, cost related inputs, etc.
Site Input:
 Composition and productivity of crews
 Fragnet (work sequence in a workspace/room)
 Quantities
System Output:
 Look-ahead schedule; crew daily work plan
 Project duration, cost, crew idle ratio, room idle ratio and other parameters.
Demo1- Schedule Random Generation
Inputs:
 6-room case
 crew availability = 1-1-1-1-1-1-1-1
 All six rooms have the same priority and the same starting date
 One corridor constraint
 One zone constraint
 Run simulation 10,000 times
Demo1- Schedule Random Generation
Six-room activity network
Demo1- Schedule Random Generation
Users can choose to
change the crew inputs
according to the availability
on site.
Random Simulation Schedule Generation Process
Find available rooms
Allocate crew
to room
Update one day’s work
& release resources
Next DAY
Next
ROOM
Zuhair Haddad’s Schedule Generation Schema
Demo1- Schedule Random Generation
Project duration ranges from 74 to 99 days.
Time spent on this
simulation: 8.7 minutes
Demo1- Schedule Random Generation
Relation between project duration and cost
The project cost ranges
from $22,900 to $28,800
The minimum project cost
found is $22,900. The
corresponding project
duration is 77 days
The shortest project duration
does not necessarily entail
minimum project cost
Demo1- Schedule Random Generation
Zone 1: The HVAC related operation
must be done simultaneously in these
three rooms.
Corridor access constraint: when the suspended ceiling
operation is on in the corridor , no access to the adjacent
rooms because of scaffolding.
The gray cells represent the days a
room is idle for the lack of crew or the
restriction of certain constraints.
Sample look-ahead schedule generated:
Resource-cost analysis:
When we keep the crews as busy as possible, we do
not necessarily get the shortest schedule.
When we keep the crews as busy as possible, we could
get the schedule with minimum cost.
Using GA to find optimized schedule
Initiation
parents
New generation
reproduction mutation
population selection
Demo2 – GA1 Fixed Crew Availability
GA Inputs:
 crew availability = 1-1-1-1-1-1-1-1;
 crossover rate = 0.4;
 mutation rate = 0.4;
 population size = 200;
 generation = 40;
Demo2 – GA1
GA Inputs:
 time spent on this simulation: 3.5 minutes
 the minimum project cost found is $22,580, the corresponding duration
is 75 days.
GA1 vs. Random – 20-room example
GA Random (10,000 runs)
Crew Avai. CPU Time
Spent
(hr.)
Min Cost
(USD)
Project
Duration
(Day)
CUP Time
Spent
(hr.)
Min Cost
(USD)
Project
Duration
(Day)
2-2-2-2-2-2-2-2 5.53 53,360 134 7.21 58,480 137
3-3-3-3-3-3-3-3 4.82 48,540 93 6.35 52,500 92
4-4-4-4-4-4-4-4 2.70 46,520 76 4.17 50,200 78
5-5-5-5-5-5-5-5 2.15 47,680 76 3.46 50,180 79
 Population Size - 360;
 Number of Generation – 360;
 Crossover rate = 0.6, mutation rate = 0.2;
Add Crew selector
 Add a new paradigm to find the optimum crew configuration (number for each
type of crew)
 Initial run assumes unlimited crews
 Result is maximum number of crews that can be utilized
 For every subsequent run of the simulator, the decider uses the random number
generator to decide number of each type of crew available
Demo3 – GA2, unknown crew availability
GA Inputs:
 Six-room case
 crossover rate = 0.2;
 mutation rate = 0.6;
 population size = 200;
 generation = 40;
Demo3 – GA2, unknown crew availability
 In around 7 minutes, GA2 found a schedule with the minimum project cost of
$22,200, the corresponding project duration is 68 days.
 Crew configuration found is: 1-2-2-2-1-1-1-1
 Note in Demo2, when the fixed crew availability is 1-1-1-1-1-1-1-1, the minimum
project cost found by GA1 is $22,580, the corresponding project duration is 75
days.
 In Demo1, when the fixed crew availability is 1-1-1-1-1-1-1-1, the minimum
project cost found by Random is $22,900, the corresponding project duration is
77 days.
 So GA2 actually can help us more to find the best crew configuration to reduce
both time and cost.
BIM Controls
3D Model
Engineering Data
Planning
Lean Construction
Advanced Work packaging
Visual Reporting
WORKFACE PLANNING
CWP
GP3-PR01-RPR-GF-CWP001
Foundations
Steel Structure
Piping
IWP – TAKT ZONE
 Electrical IWP
 Steel Structure IWP
 Foundation IWP
 Piping IWP
OPTIMIZING IWPs
 Each IWP is a takt zone.
 Each IWP has a fragnet.
 A train will pass through all homogenous IWPs (underground for all
pipe racks, etc.)
 With the lean-board/ simulator, we can optimize execution of
workface planning.
FRAGNET FOR UNDER-GROUND IWP/ TAKT ZONE
 Fragnet for Under-ground IWP
 Excavate to -2
 Foundations
 Rebar
 Concrete
 Formwork
 Under-ground piping
 Pipes
 Manholes
 Backfill to -1
 Foundations
 Etc.
BIM
C3D
Lean
Main Contractor
Contractor 1 Contractor 2 Contractor 3 Contractor N...
3D BIM Model
BOQ Library
Material Take - Off
Process Plan
Construction
StepsSubcontractor List
BOQ Cost Rates
C3D LEANBOARD
Models and MTO
Import 3D BIM Models (.IFC)
Import Material Take - Off
Import BOQ Cost Rates
A
WBS Setup
Import Process Plan
Linking Process Plan to 3D Model
Linking Construction Steps to 3D Model
Defining Subcontractors and Crews in C3D
OBS
C3D LEANBOARD
A
BOQs to Operation Assignments
Operation Quantities Calculations
Project division into parts of Construction
B
C3D LEANBOARD
C3D Planning using Leanboard
Lean Cards
Barcode Scanning
Progress Entered
in C3D Progress Reports:
• 4D Animations
• 3D Colorizations based on Progress
• PDF/Excel Reports
B
Quantity Reports Per Activity
Planned Quantities and Cost Reports
C3D LEANBOARD
FEL Methods
- Crunch
- Simulator
C3D LEANBOARD – CREW SIMULATOR
C3D’s LEAN BOARD CURRENT IMPLEMENTATION
 Suurstoffi – Switzerland (CIVIL)
 ZIRCU – ABU DHABI ZIRCU ISLAND (OIL&GAS)
 GHAZEER GAZP – OMAN (KHAZZAN BLOCK 61) (OIL&GAS)
 FGP – KAZAKHSTAN (TENGIZ)(OIL&GAS) (PENDING)
THANK YOU
ZUHAIR HADDAD
CIO – CCC/ CCT
http://www.cctintl.com/

More Related Content

What's hot

Primavera p6 18.8 planning and scheduling guide r3
Primavera p6 18.8 planning and  scheduling guide r3Primavera p6 18.8 planning and  scheduling guide r3
Primavera p6 18.8 planning and scheduling guide r3Matiwos Tsegaye
 
CAPM Exam Prep Course Preview
CAPM Exam Prep Course PreviewCAPM Exam Prep Course Preview
CAPM Exam Prep Course PreviewInvensis Learning
 
Construction management
Construction managementConstruction management
Construction managementUsama Khalid
 
Planning and Scheduling Construction Projects, Part 1: The Planning Process
Planning and Scheduling Construction Projects, Part 1: The Planning ProcessPlanning and Scheduling Construction Projects, Part 1: The Planning Process
Planning and Scheduling Construction Projects, Part 1: The Planning ProcessAlberto Sanchez
 
Agile and Lean for Construction
Agile and Lean for ConstructionAgile and Lean for Construction
Agile and Lean for ConstructionAdrian Smith
 
Modularization
ModularizationModularization
Modularizationgusgon
 
Effective Engineering Management in EPC Industry
Effective Engineering Management in EPC IndustryEffective Engineering Management in EPC Industry
Effective Engineering Management in EPC IndustryPMI Chennai Chapter
 
Chap 9.2 Estimate Activity Resource
Chap 9.2   Estimate Activity ResourceChap 9.2   Estimate Activity Resource
Chap 9.2 Estimate Activity ResourceAnand Bobade
 
project time management
 project time management project time management
project time managementHira Atiq
 
Lean Construction - Introduction
Lean Construction - IntroductionLean Construction - Introduction
Lean Construction - Introductiontabdelhamid
 
LEAN SMED TRAINING FOR SUPERVISORS AND OPERATORS
LEAN SMED TRAINING FOR SUPERVISORS AND OPERATORSLEAN SMED TRAINING FOR SUPERVISORS AND OPERATORS
LEAN SMED TRAINING FOR SUPERVISORS AND OPERATORSJulian Kalac P.Eng
 
Advanced Work Packaging (AWP) Presentation
Advanced Work Packaging (AWP) PresentationAdvanced Work Packaging (AWP) Presentation
Advanced Work Packaging (AWP) PresentationDevice Media
 
Kaizen & Small Group Activities
Kaizen & Small Group ActivitiesKaizen & Small Group Activities
Kaizen & Small Group ActivitiesDEEPAK SAHOO
 

What's hot (20)

Primavera p6 18.8 planning and scheduling guide r3
Primavera p6 18.8 planning and  scheduling guide r3Primavera p6 18.8 planning and  scheduling guide r3
Primavera p6 18.8 planning and scheduling guide r3
 
CAPM Exam Prep Course Preview
CAPM Exam Prep Course PreviewCAPM Exam Prep Course Preview
CAPM Exam Prep Course Preview
 
Construction management
Construction managementConstruction management
Construction management
 
Planning and Scheduling Construction Projects, Part 1: The Planning Process
Planning and Scheduling Construction Projects, Part 1: The Planning ProcessPlanning and Scheduling Construction Projects, Part 1: The Planning Process
Planning and Scheduling Construction Projects, Part 1: The Planning Process
 
Agile and Lean for Construction
Agile and Lean for ConstructionAgile and Lean for Construction
Agile and Lean for Construction
 
Modularization
ModularizationModularization
Modularization
 
Effective Engineering Management in EPC Industry
Effective Engineering Management in EPC IndustryEffective Engineering Management in EPC Industry
Effective Engineering Management in EPC Industry
 
Chap 9.2 Estimate Activity Resource
Chap 9.2   Estimate Activity ResourceChap 9.2   Estimate Activity Resource
Chap 9.2 Estimate Activity Resource
 
PQCDSM in Tamil
PQCDSM in TamilPQCDSM in Tamil
PQCDSM in Tamil
 
project time management
 project time management project time management
project time management
 
Advanced Work Packaging Overview
Advanced Work Packaging OverviewAdvanced Work Packaging Overview
Advanced Work Packaging Overview
 
BIM Based Project Controls
BIM Based Project ControlsBIM Based Project Controls
BIM Based Project Controls
 
Advanced Work Packaging in Construction: An Introduction
Advanced Work Packaging in Construction: An IntroductionAdvanced Work Packaging in Construction: An Introduction
Advanced Work Packaging in Construction: An Introduction
 
Lean Construction - Introduction
Lean Construction - IntroductionLean Construction - Introduction
Lean Construction - Introduction
 
Advanced Work Packaging: Applying Project Controls
Advanced Work Packaging: Applying Project ControlsAdvanced Work Packaging: Applying Project Controls
Advanced Work Packaging: Applying Project Controls
 
LEAN SMED TRAINING FOR SUPERVISORS AND OPERATORS
LEAN SMED TRAINING FOR SUPERVISORS AND OPERATORSLEAN SMED TRAINING FOR SUPERVISORS AND OPERATORS
LEAN SMED TRAINING FOR SUPERVISORS AND OPERATORS
 
Advanced Work Packaging (AWP) Presentation
Advanced Work Packaging (AWP) PresentationAdvanced Work Packaging (AWP) Presentation
Advanced Work Packaging (AWP) Presentation
 
A guide for project managers prince2
A guide for project managers prince2A guide for project managers prince2
A guide for project managers prince2
 
Project management
Project managementProject management
Project management
 
Kaizen & Small Group Activities
Kaizen & Small Group ActivitiesKaizen & Small Group Activities
Kaizen & Small Group Activities
 

Similar to BIM, Lean & Advanced Work Packaging - How do they fit together?

Fiatech 2014 - Big BIM Implementation, Zuhair Haddad
Fiatech 2014 - Big BIM Implementation, Zuhair HaddadFiatech 2014 - Big BIM Implementation, Zuhair Haddad
Fiatech 2014 - Big BIM Implementation, Zuhair HaddadCCT International
 
Manage the Digital Transformation with Machine Learning in a Reactive Microse...
Manage the Digital Transformation with Machine Learning in a Reactive Microse...Manage the Digital Transformation with Machine Learning in a Reactive Microse...
Manage the Digital Transformation with Machine Learning in a Reactive Microse...DataWorks Summit
 
vnc.pptx
vnc.pptxvnc.pptx
vnc.pptxPigPug1
 
vnc_1660543731.pptx
vnc_1660543731.pptxvnc_1660543731.pptx
vnc_1660543731.pptxPigPug1
 
Dinamikler 2017 - Alan Sharp Sunum
Dinamikler 2017 - Alan Sharp SunumDinamikler 2017 - Alan Sharp Sunum
Dinamikler 2017 - Alan Sharp Sunumdinamikler17
 
vnc.pptx
vnc.pptxvnc.pptx
vnc.pptxPigPug1
 
vnc.pptx
vnc.pptxvnc.pptx
vnc.pptxPigPug1
 
Computer Aided Process Planning Using Neutral File Step for Rotational Parts
Computer Aided Process Planning Using Neutral File Step for Rotational PartsComputer Aided Process Planning Using Neutral File Step for Rotational Parts
Computer Aided Process Planning Using Neutral File Step for Rotational PartsRSIS International
 
Evolutionary Multi-Goal Workflow Progress in Shade
Evolutionary  Multi-Goal Workflow Progress in ShadeEvolutionary  Multi-Goal Workflow Progress in Shade
Evolutionary Multi-Goal Workflow Progress in ShadeIRJET Journal
 
Transport for London - London's Operations Digital Twin
Transport for London - London's Operations Digital TwinTransport for London - London's Operations Digital Twin
Transport for London - London's Operations Digital TwinNeo4j
 
Migration Decoded
Migration DecodedMigration Decoded
Migration DecodedCognizant
 
Planning And Scheduling Construction For Decades
Planning And Scheduling Construction For DecadesPlanning And Scheduling Construction For Decades
Planning And Scheduling Construction For DecadesBeth Hall
 
Computer aided process planning
Computer aided process planningComputer aided process planning
Computer aided process planningjashid41
 
Manufacturing Production Planning AI - ERP system
Manufacturing Production Planning AI -  ERP systemManufacturing Production Planning AI -  ERP system
Manufacturing Production Planning AI - ERP systemLuis Cabrera
 

Similar to BIM, Lean & Advanced Work Packaging - How do they fit together? (20)

Fiatech 2014 - Big BIM Implementation, Zuhair Haddad
Fiatech 2014 - Big BIM Implementation, Zuhair HaddadFiatech 2014 - Big BIM Implementation, Zuhair Haddad
Fiatech 2014 - Big BIM Implementation, Zuhair Haddad
 
Manage the Digital Transformation with Machine Learning in a Reactive Microse...
Manage the Digital Transformation with Machine Learning in a Reactive Microse...Manage the Digital Transformation with Machine Learning in a Reactive Microse...
Manage the Digital Transformation with Machine Learning in a Reactive Microse...
 
vnc.pptx
vnc.pptxvnc.pptx
vnc.pptx
 
vnc_1660543731.pptx
vnc_1660543731.pptxvnc_1660543731.pptx
vnc_1660543731.pptx
 
Hakkache mohamed 202111
Hakkache mohamed 202111Hakkache mohamed 202111
Hakkache mohamed 202111
 
Dinamikler 2017 - Alan Sharp Sunum
Dinamikler 2017 - Alan Sharp SunumDinamikler 2017 - Alan Sharp Sunum
Dinamikler 2017 - Alan Sharp Sunum
 
vnc.pptx
vnc.pptxvnc.pptx
vnc.pptx
 
vnc.pptx
vnc.pptxvnc.pptx
vnc.pptx
 
Computer Aided Process Planning Using Neutral File Step for Rotational Parts
Computer Aided Process Planning Using Neutral File Step for Rotational PartsComputer Aided Process Planning Using Neutral File Step for Rotational Parts
Computer Aided Process Planning Using Neutral File Step for Rotational Parts
 
Evolutionary Multi-Goal Workflow Progress in Shade
Evolutionary  Multi-Goal Workflow Progress in ShadeEvolutionary  Multi-Goal Workflow Progress in Shade
Evolutionary Multi-Goal Workflow Progress in Shade
 
Info graphic
Info graphicInfo graphic
Info graphic
 
Decision Support System
Decision Support SystemDecision Support System
Decision Support System
 
Transport for London - London's Operations Digital Twin
Transport for London - London's Operations Digital TwinTransport for London - London's Operations Digital Twin
Transport for London - London's Operations Digital Twin
 
Case study(i)
Case study(i)Case study(i)
Case study(i)
 
Migration Decoded
Migration DecodedMigration Decoded
Migration Decoded
 
Planning And Scheduling Construction For Decades
Planning And Scheduling Construction For DecadesPlanning And Scheduling Construction For Decades
Planning And Scheduling Construction For Decades
 
Computer aided process planning
Computer aided process planningComputer aided process planning
Computer aided process planning
 
Manufacturing Production Planning AI - ERP system
Manufacturing Production Planning AI -  ERP systemManufacturing Production Planning AI -  ERP system
Manufacturing Production Planning AI - ERP system
 
CIM UNIT 1.ppt
CIM UNIT 1.pptCIM UNIT 1.ppt
CIM UNIT 1.ppt
 
A Survey and Comparison of SDN Based Traffic Management Techniques
A Survey and Comparison of SDN Based Traffic Management TechniquesA Survey and Comparison of SDN Based Traffic Management Techniques
A Survey and Comparison of SDN Based Traffic Management Techniques
 

More from CCT International

Digital Transformation of the Construction Industry
Digital Transformation of the Construction IndustryDigital Transformation of the Construction Industry
Digital Transformation of the Construction IndustryCCT International
 
6.0 CURT CII - Digital Transformation of Construction Industry
6.0 CURT CII  - Digital Transformation of Construction Industry6.0 CURT CII  - Digital Transformation of Construction Industry
6.0 CURT CII - Digital Transformation of Construction IndustryCCT International
 
Leveraging C3D® to Ensure Compliance of Site Execution Teams
Leveraging C3D® to Ensure Compliance of Site Execution TeamsLeveraging C3D® to Ensure Compliance of Site Execution Teams
Leveraging C3D® to Ensure Compliance of Site Execution TeamsCCT International
 
The Future is Now (5th BIM and Lean Conference 2017)
The Future is Now (5th BIM and Lean Conference 2017)The Future is Now (5th BIM and Lean Conference 2017)
The Future is Now (5th BIM and Lean Conference 2017)CCT International
 
O&M Challenge: BIM and Laser Scanning, a Hospital Project from the Middle East
O&M Challenge: BIM and Laser Scanning, a Hospital Project from the Middle EastO&M Challenge: BIM and Laser Scanning, a Hospital Project from the Middle East
O&M Challenge: BIM and Laser Scanning, a Hospital Project from the Middle EastCCT International
 
Roads, Infrastructure and BIM
Roads, Infrastructure and BIMRoads, Infrastructure and BIM
Roads, Infrastructure and BIMCCT International
 
Designing to Enhance Construction Planning & Monitoring
Designing to Enhance Construction Planning & MonitoringDesigning to Enhance Construction Planning & Monitoring
Designing to Enhance Construction Planning & MonitoringCCT International
 
Mandated BIM! Are you ready?
Mandated BIM! Are you ready?Mandated BIM! Are you ready?
Mandated BIM! Are you ready?CCT International
 
Fiatech 2016 - Advanced Work Packaging: from Theory to Practice
Fiatech 2016 - Advanced Work Packaging: from Theory to PracticeFiatech 2016 - Advanced Work Packaging: from Theory to Practice
Fiatech 2016 - Advanced Work Packaging: from Theory to PracticeCCT International
 
IBM Case Study of Maximo Implementation at CCC
IBM Case Study of Maximo Implementation at CCCIBM Case Study of Maximo Implementation at CCC
IBM Case Study of Maximo Implementation at CCCCCT International
 
AF-1438: Transportation MUG: CCC's Use of Maximo for Fleet Management on Infr...
AF-1438: Transportation MUG: CCC's Use of Maximo for Fleet Management on Infr...AF-1438: Transportation MUG: CCC's Use of Maximo for Fleet Management on Infr...
AF-1438: Transportation MUG: CCC's Use of Maximo for Fleet Management on Infr...CCT International
 
Computer Simulation: Quantifying and Substantiating a Claim for Extension of ...
Computer Simulation: Quantifying and Substantiating a Claim for Extension of ...Computer Simulation: Quantifying and Substantiating a Claim for Extension of ...
Computer Simulation: Quantifying and Substantiating a Claim for Extension of ...CCT International
 
Asset Management - Bridging Boundaries in Ongoing Asset Management
Asset Management - Bridging Boundaries in Ongoing Asset ManagementAsset Management - Bridging Boundaries in Ongoing Asset Management
Asset Management - Bridging Boundaries in Ongoing Asset ManagementCCT International
 
Imagine a World Without Isometric
Imagine a World Without IsometricImagine a World Without Isometric
Imagine a World Without IsometricCCT International
 
The Information Challenge Managing Construction with BIM
The Information ChallengeManaging Construction with BIMThe Information ChallengeManaging Construction with BIM
The Information Challenge Managing Construction with BIMCCT International
 

More from CCT International (20)

Digital Transformation of the Construction Industry
Digital Transformation of the Construction IndustryDigital Transformation of the Construction Industry
Digital Transformation of the Construction Industry
 
BIM In Practice Seminar
BIM In Practice Seminar BIM In Practice Seminar
BIM In Practice Seminar
 
6.0 CURT CII - Digital Transformation of Construction Industry
6.0 CURT CII  - Digital Transformation of Construction Industry6.0 CURT CII  - Digital Transformation of Construction Industry
6.0 CURT CII - Digital Transformation of Construction Industry
 
Adding Intelligence to AWP
Adding Intelligence to AWPAdding Intelligence to AWP
Adding Intelligence to AWP
 
Leveraging C3D® to Ensure Compliance of Site Execution Teams
Leveraging C3D® to Ensure Compliance of Site Execution TeamsLeveraging C3D® to Ensure Compliance of Site Execution Teams
Leveraging C3D® to Ensure Compliance of Site Execution Teams
 
The Future is Now (5th BIM and Lean Conference 2017)
The Future is Now (5th BIM and Lean Conference 2017)The Future is Now (5th BIM and Lean Conference 2017)
The Future is Now (5th BIM and Lean Conference 2017)
 
O&M Challenge: BIM and Laser Scanning, a Hospital Project from the Middle East
O&M Challenge: BIM and Laser Scanning, a Hospital Project from the Middle EastO&M Challenge: BIM and Laser Scanning, a Hospital Project from the Middle East
O&M Challenge: BIM and Laser Scanning, a Hospital Project from the Middle East
 
Roads, Infrastructure and BIM
Roads, Infrastructure and BIMRoads, Infrastructure and BIM
Roads, Infrastructure and BIM
 
Contractors: Get BIM Ready!
Contractors: Get BIM Ready!Contractors: Get BIM Ready!
Contractors: Get BIM Ready!
 
Designing to Enhance Construction Planning & Monitoring
Designing to Enhance Construction Planning & MonitoringDesigning to Enhance Construction Planning & Monitoring
Designing to Enhance Construction Planning & Monitoring
 
Mandated BIM! Are you ready?
Mandated BIM! Are you ready?Mandated BIM! Are you ready?
Mandated BIM! Are you ready?
 
Fiatech 2016 - Advanced Work Packaging: from Theory to Practice
Fiatech 2016 - Advanced Work Packaging: from Theory to PracticeFiatech 2016 - Advanced Work Packaging: from Theory to Practice
Fiatech 2016 - Advanced Work Packaging: from Theory to Practice
 
Make BIM work for you
Make BIM work for youMake BIM work for you
Make BIM work for you
 
IBM Case Study of Maximo Implementation at CCC
IBM Case Study of Maximo Implementation at CCCIBM Case Study of Maximo Implementation at CCC
IBM Case Study of Maximo Implementation at CCC
 
AF-1438: Transportation MUG: CCC's Use of Maximo for Fleet Management on Infr...
AF-1438: Transportation MUG: CCC's Use of Maximo for Fleet Management on Infr...AF-1438: Transportation MUG: CCC's Use of Maximo for Fleet Management on Infr...
AF-1438: Transportation MUG: CCC's Use of Maximo for Fleet Management on Infr...
 
Computer Simulation: Quantifying and Substantiating a Claim for Extension of ...
Computer Simulation: Quantifying and Substantiating a Claim for Extension of ...Computer Simulation: Quantifying and Substantiating a Claim for Extension of ...
Computer Simulation: Quantifying and Substantiating a Claim for Extension of ...
 
Asset Management - Bridging Boundaries in Ongoing Asset Management
Asset Management - Bridging Boundaries in Ongoing Asset ManagementAsset Management - Bridging Boundaries in Ongoing Asset Management
Asset Management - Bridging Boundaries in Ongoing Asset Management
 
Imagine a World Without Isometric
Imagine a World Without IsometricImagine a World Without Isometric
Imagine a World Without Isometric
 
Smart Construction Site
Smart Construction SiteSmart Construction Site
Smart Construction Site
 
The Information Challenge Managing Construction with BIM
The Information ChallengeManaging Construction with BIMThe Information ChallengeManaging Construction with BIM
The Information Challenge Managing Construction with BIM
 

Recently uploaded

Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxDeepakSakkari2
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSCAESB
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx959SahilShah
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort servicejennyeacort
 
Churning of Butter, Factors affecting .
Churning of Butter, Factors affecting  .Churning of Butter, Factors affecting  .
Churning of Butter, Factors affecting .Satyam Kumar
 
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxKartikeyaDwivedi3
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLDeelipZope
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerAnamika Sarkar
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.eptoze12
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learningmisbanausheenparvam
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AIabhishek36461
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...asadnawaz62
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...srsj9000
 

Recently uploaded (20)

Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptx
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentation
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx
 
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
 
Design and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdfDesign and analysis of solar grass cutter.pdf
Design and analysis of solar grass cutter.pdf
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
 
Churning of Butter, Factors affecting .
Churning of Butter, Factors affecting  .Churning of Butter, Factors affecting  .
Churning of Butter, Factors affecting .
 
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptx
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCL
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learning
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AI
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...
 
young call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Serviceyoung call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Service
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
 

BIM, Lean & Advanced Work Packaging - How do they fit together?

  • 1. BIM, LEAN AND ADVANCED WORK PACKAGING HOW DO THEY FIT TOGETHER? ZUHAIR HADDAD CIO – CCC/ CCT http://www.cctintl.com/
  • 2. THE INNOVATIVE PLATFORM FOR EFFICIENT, LEAN AND TRANSPARENT CONSTRUCTION PROCESS MANAGEMENT ENABLING DIGITAL TRANSFORMATION OF CONSTRUCTION
  • 3.  Critical path method (CPM) schedules (primavera P6, Microsoft project and similar) follow a top down approach to construction project execution not focusing on the process and mostly neglecting the inter-relations of multiple crews working in same construction zones  The result is typically obstruction of crews rushing their way to individual completion of tasks planned in the schedule WHY DO CURRENT METHODS FAIL?
  • 4. THERE IS A HIGH CUSTOMER NEED IN THE MARKET FOR ONLINE COLLABORATION AND DISRUPTIVE PLANNING TOOLS - LCM DIGITAL® IS THE ONLY ANSWER IN THE MARKET DIGITAL CHANGES ARE MASSIVELY PUSHING THE MARKET What we do better…  Lean approaches are needed in the construction industry – we use our chance  Digital integrated construction processes help us overcome current problems on site  We are using the data: more data collection, data analytics, benchmarks and machine learning  Business Intelligence: the availability of qualified real time data offers a high quality basis for scheduling, design, integration, logistics and supply chain  Integrated digital workflows: digital connection of information leads to a very efficient and productive communication and work results  BIM is standard: offering data to bridge the gap between the process and material availability as well as online and onsite navigation  We make mobile working happen, collaboration and communication is redefining the way we work together
  • 5. THE MANAGEMENT PLATFORM Plan your Strategy: Segmentation of typical work and takt areas to define process flow, team performance and duration Plan your construction flow: Use the typical takt areas to define your construction flow (takt trains) by replication for a continuous flow and optimal resource usage. Update your plan based on Live Data from site and supply chain data Production management on site: Set your plan into action with a production management system on site using Kanban boards and the LCM Digital App for Live Updates.
  • 6. Standard Processes BIM Design / Engineering Supply Chain AI STABILITY CRITERIA/ FRONT END LOADING
  • 7. CHANGING THE WAY OF CONSTRUCTION MANAGEMENT Consistent process from strategy to site Standard processes Takt planning Easy to use Cloud based collaboration plattform Live update of schedule BIM connected LCM Digital® App Following the plan without deviations Build on the knowledge of your team Increase the takt rate of your construction project Getting everybody on board to get the job done Easy to use on site, everyday Knowing what is going on for a better management Combining all digital information for better projects
  • 8. LCM digital® offers high value during the planning process  Built by 2 strong partners with years of experience in construction – CCC and Drees & Sommer  Based on construction know and IT know how  LCM® takt planning has been proven in over 450 projects over the past 12 years, improving project performance with every project  There is no other cloud-based product as comprehensiveness and with full service as LCM digital®  LCM digital® runs on different platforms and browsers for PC, Mac, iPad, etc.  We have a strong vision - the next steps implementing AI and supply chain management are already on the way THERE IS NO COMPARABLE TOOL WORLDWIDE LCM DIGITAL® IS THE ONLY CLOUD-BASED FULL SERVICE SOFTWARE SOLUTION FOR LEAN CONSTRUCTION WORLDWIDE
  • 9. BENEFITs FROM DIFFERENT PERSPECTIVES OwnersProject management and site management Project involved construction companies LCM DIGITAL® WORKS FOR DIFFERENT CUSTOMER GROUPS
  • 10. OUR ANALOG ROOTS - MAKING PROBLEMS VISIBLE AND ELIMINATING THEM
  • 11. OUR LEAN PHILOSOPHY Many resources are used to cover problems. Problems are covered! Create transparency, Reduce water. Problems become visible! Problems have been reduced or eliminated Causes are permanently eliminated! PROBLEMS ARE OFTEN COVERED BY AN HEIGHTENED USE OF RESOURCES – LEAN PROCESS MANAGEMENT HELPS TO IDENTIFY AND ELIMINATE THE CAUSES BEHIND THIS CIP* *CIP = continuous improvement process Traditional approach Lean Approach ProblemsProblems Problems Problems Capacity and Time
  • 12. THE CONTENT & AREA DEFINITION Daily Kanban Board QR Code & APP Takt Planning Define Takt Types Process Planning (Overall takted production schedule) Takt AnalysisOverall Process AnalysisDefine Zone Types Define Takt Zones Fragnet Concept Areas with same work sequence (Class of Rooms) Area type that can be combined in a takt train (Subclass of Rooms by Size or minor work difference) Areas on site that are combined in a takt train sequence (Instances per subclass) Process Mapping and Sequencing Duration, Performance & Quantities  Construction Flow Sequence,  Leveling  Resource Optimization  Scheduling  Management & Optimization  Controlling & Report Daily update 3- 4 weeks production schedule
  • 13. ZONE TYPES DEFINITION – CLASS OF ROOMS Define Zone Types Areas with same work sequence (Class of Rooms)
  • 14. TAKT TYPES DEFINITION – SUB CLASS OF ROOMS Define Takt Types Area type that can be combined in a takt train (Subclass of Rooms by Size or minor work difference)
  • 15. TAKT ZONES DEFINITION – ACTUAL INSTANCES OF SUBCLASS Define Takt Zones Areas on site that are combined in a takt train sequence (Instances per subclass)
  • 16. OVERALL PROCESS ANALYSIS – FRAGNET DEFINITION Takt Planning Overall Process Analysis Takt Analysis Process Planning (Overall takted production schedule) Aim To provide transparency, create a common understanding of process steps and early identification of problems and bottlenecks Description The process of creating the optimal process sequence for each zone type (working area)
  • 17. TAKT ANALYSIS – FRAGNET DURATIONS Takt Planning Overall Process Analysis Takt Analysis Process Planning (Overall takted production schedule) Aim To prepare the overall process analysis to transform into an optimal process plan populated with all the relevant parameters Description The process of adding 3 dimensions namely duration, material and manpower to the overall process analysis
  • 18. DEFINE TAKT ZONES – NAMING CONVENTION Define Takt Zones Areas on site that are combined in a takt train sequence (Instances per subclass) For All Selected Takt Types( N=1; For Takt Type( Create Takt Zone = Area+SubArea+TaktType+N; N= N+1; ) )
  • 20. TAKT PLANNING Takt Planning Overall Process Analysis Takt Analysis Process Planning (Overall takted production schedule) Aim To allow for an iterative process to find the most efficient process plan in terms of manhours and quantities Description The process of sequencing takt zones using takt trains, dependencies and time intervals
  • 21. PROCESS PLANNING Takt Planning Overall Process Analysis Takt Analysis Process Planning (Overall takted production schedule) Aim Have an overview/detailed view of the schedule, front- end loading and proactively managing stability criteria Description The process of fine tuning the takt analysis and takt planning applied to all the takt zones and assigning the work of the next n weeks to specific teams
  • 22. DAILY KANBAN BOARD Daily Kanban Board QR Code & APP Takt Planning Overall Process Analysis Takt Analysis Process Planning (Overall takted production schedule)
  • 23. TO TAKT OR NOT TO TAKT? THAT IS THE QUESTION… Takt planning is the process of trying to harmonize the durations for every wagon in the train so as to keep the train moving together If the blue wagon takes 2 times the duration of the other wagons, the tail end of the train will fall behind every week. We need a disruptive process to find an optimum solution.
  • 24. CIFE Research in Collaboration with CCC A Method to Quickly Generate Close-to- optimum Look-Ahead Schedule (LAS) for the Finishing Phase Ning (Tony) Dong PhD Committee: Principle Advisor – Prof. Martin Fischer Industrial Advisor – Mr. Zuhair Haddad Prof. Raymond Levitt Assist. Prof. Dongdong Ge
  • 25. Why do we need a good LAS?  A guidance to provide correct work sequence  A shared means to prevent work conflict  A whiteboard to provide improved awareness of resource utilization Ultimately, a good LAS should be a way of presentation after pulling all different data sources together to (1) facilitate coordination among various project participants; (2) be actually used by the people from job site to guide field work and (3) become a means of project monitor and control (i.e., progress monitoring, crew/material forecasting, material reporting, etc.)
  • 26. Why a good LAS is so important in the finishing phase? – complex network Activity network/fragnet for the finishing of one faculty room at CMU Qatar
  • 27. Why a good LAS is so important in the finishing phase? GC needs to manage in the actual project:  More than 200 rooms;  More than 20 types of self-performed operations on average per room;  More than 16 types of rooms (work sequence);  More than 20 types of subs’ operations;  More than 80 types of materials;  More than 10 types of skilled workers/crews
  • 28. Why a good LAS is so important in the finishing phase? - constraints Corridor Access Constraint Zone Constraint Spatial Constraint
  • 29. Why a good LAS looks like in the finishing phase? When Who What Where Work Days Room ID Room-centered View of LAS
  • 30. What a good LAS looks like in the finishing phase? Room-centered View of LAS Install Conduit & Box  Plastering  Screed  Painting
  • 31. What a good LAS looks like in the finishing phase? Crew ID What When Who Where Crew-centered View of LAS
  • 32. Simulation Overall Description User Input:  Number of different types of crews  Starting/available date of each room  Duration of an operation when it is hard to calculate its actual length  Corridor constraint, zone constraint, cost related inputs, etc. Site Input:  Composition and productivity of crews  Fragnet (work sequence in a workspace/room)  Quantities System Output:  Look-ahead schedule; crew daily work plan  Project duration, cost, crew idle ratio, room idle ratio and other parameters.
  • 33. Demo1- Schedule Random Generation Inputs:  6-room case  crew availability = 1-1-1-1-1-1-1-1  All six rooms have the same priority and the same starting date  One corridor constraint  One zone constraint  Run simulation 10,000 times
  • 34. Demo1- Schedule Random Generation Six-room activity network
  • 35. Demo1- Schedule Random Generation Users can choose to change the crew inputs according to the availability on site.
  • 36. Random Simulation Schedule Generation Process Find available rooms Allocate crew to room Update one day’s work & release resources Next DAY Next ROOM Zuhair Haddad’s Schedule Generation Schema
  • 37. Demo1- Schedule Random Generation Project duration ranges from 74 to 99 days. Time spent on this simulation: 8.7 minutes
  • 38. Demo1- Schedule Random Generation Relation between project duration and cost The project cost ranges from $22,900 to $28,800 The minimum project cost found is $22,900. The corresponding project duration is 77 days The shortest project duration does not necessarily entail minimum project cost
  • 39. Demo1- Schedule Random Generation Zone 1: The HVAC related operation must be done simultaneously in these three rooms. Corridor access constraint: when the suspended ceiling operation is on in the corridor , no access to the adjacent rooms because of scaffolding. The gray cells represent the days a room is idle for the lack of crew or the restriction of certain constraints. Sample look-ahead schedule generated: Resource-cost analysis: When we keep the crews as busy as possible, we do not necessarily get the shortest schedule. When we keep the crews as busy as possible, we could get the schedule with minimum cost.
  • 40. Using GA to find optimized schedule Initiation parents New generation reproduction mutation population selection
  • 41. Demo2 – GA1 Fixed Crew Availability GA Inputs:  crew availability = 1-1-1-1-1-1-1-1;  crossover rate = 0.4;  mutation rate = 0.4;  population size = 200;  generation = 40;
  • 42. Demo2 – GA1 GA Inputs:  time spent on this simulation: 3.5 minutes  the minimum project cost found is $22,580, the corresponding duration is 75 days.
  • 43. GA1 vs. Random – 20-room example GA Random (10,000 runs) Crew Avai. CPU Time Spent (hr.) Min Cost (USD) Project Duration (Day) CUP Time Spent (hr.) Min Cost (USD) Project Duration (Day) 2-2-2-2-2-2-2-2 5.53 53,360 134 7.21 58,480 137 3-3-3-3-3-3-3-3 4.82 48,540 93 6.35 52,500 92 4-4-4-4-4-4-4-4 2.70 46,520 76 4.17 50,200 78 5-5-5-5-5-5-5-5 2.15 47,680 76 3.46 50,180 79  Population Size - 360;  Number of Generation – 360;  Crossover rate = 0.6, mutation rate = 0.2;
  • 44. Add Crew selector  Add a new paradigm to find the optimum crew configuration (number for each type of crew)  Initial run assumes unlimited crews  Result is maximum number of crews that can be utilized  For every subsequent run of the simulator, the decider uses the random number generator to decide number of each type of crew available
  • 45. Demo3 – GA2, unknown crew availability GA Inputs:  Six-room case  crossover rate = 0.2;  mutation rate = 0.6;  population size = 200;  generation = 40;
  • 46. Demo3 – GA2, unknown crew availability  In around 7 minutes, GA2 found a schedule with the minimum project cost of $22,200, the corresponding project duration is 68 days.  Crew configuration found is: 1-2-2-2-1-1-1-1  Note in Demo2, when the fixed crew availability is 1-1-1-1-1-1-1-1, the minimum project cost found by GA1 is $22,580, the corresponding project duration is 75 days.  In Demo1, when the fixed crew availability is 1-1-1-1-1-1-1-1, the minimum project cost found by Random is $22,900, the corresponding project duration is 77 days.  So GA2 actually can help us more to find the best crew configuration to reduce both time and cost.
  • 47. BIM Controls 3D Model Engineering Data Planning Lean Construction Advanced Work packaging Visual Reporting WORKFACE PLANNING
  • 49. IWP – TAKT ZONE  Electrical IWP  Steel Structure IWP  Foundation IWP  Piping IWP
  • 50. OPTIMIZING IWPs  Each IWP is a takt zone.  Each IWP has a fragnet.  A train will pass through all homogenous IWPs (underground for all pipe racks, etc.)  With the lean-board/ simulator, we can optimize execution of workface planning.
  • 51. FRAGNET FOR UNDER-GROUND IWP/ TAKT ZONE  Fragnet for Under-ground IWP  Excavate to -2  Foundations  Rebar  Concrete  Formwork  Under-ground piping  Pipes  Manholes  Backfill to -1  Foundations  Etc.
  • 52. BIM C3D Lean Main Contractor Contractor 1 Contractor 2 Contractor 3 Contractor N... 3D BIM Model BOQ Library Material Take - Off Process Plan Construction StepsSubcontractor List BOQ Cost Rates C3D LEANBOARD
  • 53. Models and MTO Import 3D BIM Models (.IFC) Import Material Take - Off Import BOQ Cost Rates A WBS Setup Import Process Plan Linking Process Plan to 3D Model Linking Construction Steps to 3D Model Defining Subcontractors and Crews in C3D OBS C3D LEANBOARD
  • 54. A BOQs to Operation Assignments Operation Quantities Calculations Project division into parts of Construction B C3D LEANBOARD
  • 55. C3D Planning using Leanboard Lean Cards Barcode Scanning Progress Entered in C3D Progress Reports: • 4D Animations • 3D Colorizations based on Progress • PDF/Excel Reports B Quantity Reports Per Activity Planned Quantities and Cost Reports C3D LEANBOARD FEL Methods - Crunch - Simulator
  • 56. C3D LEANBOARD – CREW SIMULATOR
  • 57. C3D’s LEAN BOARD CURRENT IMPLEMENTATION  Suurstoffi – Switzerland (CIVIL)  ZIRCU – ABU DHABI ZIRCU ISLAND (OIL&GAS)  GHAZEER GAZP – OMAN (KHAZZAN BLOCK 61) (OIL&GAS)  FGP – KAZAKHSTAN (TENGIZ)(OIL&GAS) (PENDING)
  • 58. THANK YOU ZUHAIR HADDAD CIO – CCC/ CCT http://www.cctintl.com/