This document provides an overview of environmental impact assessment (EIA). It discusses what an EIA is, the key steps in the EIA process like screening, scoping, baseline data collection and impact prediction, and tools used like modeling and alternatives analysis. It also outlines aspects like mitigation measures, monitoring, auditing and public consultation. Examples are provided of strategic environmental assessment (SEA) and how it differs from project-based EIA in considering longer-term and cumulative impacts of policies and plans.
PACT's Mekong Partnership for the Environment gave this presentation on whether meaningful public participation in Environmental Impact Assessment is possible in the Mekong Region. Case studies in other countries and domains were looked at.
PACT's Mekong Partnership for the Environment gave this presentation on whether meaningful public participation in Environmental Impact Assessment is possible in the Mekong Region. Case studies in other countries and domains were looked at.
A Short introduction over what EIA is , its objectives , its process , advantages and challenges in india.
Also two case studies, one where EIA is implented, and other where it isnt, have been included along with the references.
Presentation by Dr A Qayyum, Comprehensive Disaster Management Programme, Bangladesh at the CCAFS Workshop on Institutions and Policies to Scale out Climate Smart Agriculture held between 2-5 December 2013 in Colombo, Sri Lanka.
A Short introduction over what EIA is , its objectives , its process , advantages and challenges in india.
Also two case studies, one where EIA is implented, and other where it isnt, have been included along with the references.
Presentation by Dr A Qayyum, Comprehensive Disaster Management Programme, Bangladesh at the CCAFS Workshop on Institutions and Policies to Scale out Climate Smart Agriculture held between 2-5 December 2013 in Colombo, Sri Lanka.
Philippine Envaironmental Impact System System. This my presentation in one of my subject Mining 103.. i tried my best just to finish this.. although this report did not cover all the sections in the PEISS.
The Art of the Pitch: WordPress Relationships and SalesLaura Byrne
Clients don’t know what they don’t know. What web solutions are right for them? How does WordPress come into the picture? How do you make sure you understand scope and timeline? What do you do if sometime changes?
All these questions and more will be explored as we talk about matching clients’ needs with what your agency offers without pulling teeth or pulling your hair out. Practical tips, and strategies for successful relationship building that leads to closing the deal.
PHP Frameworks: I want to break free (IPC Berlin 2024)Ralf Eggert
In this presentation, we examine the challenges and limitations of relying too heavily on PHP frameworks in web development. We discuss the history of PHP and its frameworks to understand how this dependence has evolved. The focus will be on providing concrete tips and strategies to reduce reliance on these frameworks, based on real-world examples and practical considerations. The goal is to equip developers with the skills and knowledge to create more flexible and future-proof web applications. We'll explore the importance of maintaining autonomy in a rapidly changing tech landscape and how to make informed decisions in PHP development.
This talk is aimed at encouraging a more independent approach to using PHP frameworks, moving towards a more flexible and future-proof approach to PHP development.
Smart TV Buyer Insights Survey 2024 by 91mobiles.pdf91mobiles
91mobiles recently conducted a Smart TV Buyer Insights Survey in which we asked over 3,000 respondents about the TV they own, aspects they look at on a new TV, and their TV buying preferences.
Alt. GDG Cloud Southlake #33: Boule & Rebala: Effective AppSec in SDLC using ...James Anderson
Effective Application Security in Software Delivery lifecycle using Deployment Firewall and DBOM
The modern software delivery process (or the CI/CD process) includes many tools, distributed teams, open-source code, and cloud platforms. Constant focus on speed to release software to market, along with the traditional slow and manual security checks has caused gaps in continuous security as an important piece in the software supply chain. Today organizations feel more susceptible to external and internal cyber threats due to the vast attack surface in their applications supply chain and the lack of end-to-end governance and risk management.
The software team must secure its software delivery process to avoid vulnerability and security breaches. This needs to be achieved with existing tool chains and without extensive rework of the delivery processes. This talk will present strategies and techniques for providing visibility into the true risk of the existing vulnerabilities, preventing the introduction of security issues in the software, resolving vulnerabilities in production environments quickly, and capturing the deployment bill of materials (DBOM).
Speakers:
Bob Boule
Robert Boule is a technology enthusiast with PASSION for technology and making things work along with a knack for helping others understand how things work. He comes with around 20 years of solution engineering experience in application security, software continuous delivery, and SaaS platforms. He is known for his dynamic presentations in CI/CD and application security integrated in software delivery lifecycle.
Gopinath Rebala
Gopinath Rebala is the CTO of OpsMx, where he has overall responsibility for the machine learning and data processing architectures for Secure Software Delivery. Gopi also has a strong connection with our customers, leading design and architecture for strategic implementations. Gopi is a frequent speaker and well-known leader in continuous delivery and integrating security into software delivery.
Enhancing Performance with Globus and the Science DMZGlobus
ESnet has led the way in helping national facilities—and many other institutions in the research community—configure Science DMZs and troubleshoot network issues to maximize data transfer performance. In this talk we will present a summary of approaches and tips for getting the most out of your network infrastructure using Globus Connect Server.
SAP Sapphire 2024 - ASUG301 building better apps with SAP Fiori.pdfPeter Spielvogel
Building better applications for business users with SAP Fiori.
• What is SAP Fiori and why it matters to you
• How a better user experience drives measurable business benefits
• How to get started with SAP Fiori today
• How SAP Fiori elements accelerates application development
• How SAP Build Code includes SAP Fiori tools and other generative artificial intelligence capabilities
• How SAP Fiori paves the way for using AI in SAP apps
Dev Dives: Train smarter, not harder – active learning and UiPath LLMs for do...UiPathCommunity
💥 Speed, accuracy, and scaling – discover the superpowers of GenAI in action with UiPath Document Understanding and Communications Mining™:
See how to accelerate model training and optimize model performance with active learning
Learn about the latest enhancements to out-of-the-box document processing – with little to no training required
Get an exclusive demo of the new family of UiPath LLMs – GenAI models specialized for processing different types of documents and messages
This is a hands-on session specifically designed for automation developers and AI enthusiasts seeking to enhance their knowledge in leveraging the latest intelligent document processing capabilities offered by UiPath.
Speakers:
👨🏫 Andras Palfi, Senior Product Manager, UiPath
👩🏫 Lenka Dulovicova, Product Program Manager, UiPath
The Metaverse and AI: how can decision-makers harness the Metaverse for their...Jen Stirrup
The Metaverse is popularized in science fiction, and now it is becoming closer to being a part of our daily lives through the use of social media and shopping companies. How can businesses survive in a world where Artificial Intelligence is becoming the present as well as the future of technology, and how does the Metaverse fit into business strategy when futurist ideas are developing into reality at accelerated rates? How do we do this when our data isn't up to scratch? How can we move towards success with our data so we are set up for the Metaverse when it arrives?
How can you help your company evolve, adapt, and succeed using Artificial Intelligence and the Metaverse to stay ahead of the competition? What are the potential issues, complications, and benefits that these technologies could bring to us and our organizations? In this session, Jen Stirrup will explain how to start thinking about these technologies as an organisation.
DevOps and Testing slides at DASA ConnectKari Kakkonen
My and Rik Marselis slides at 30.5.2024 DASA Connect conference. We discuss about what is testing, then what is agile testing and finally what is Testing in DevOps. Finally we had lovely workshop with the participants trying to find out different ways to think about quality and testing in different parts of the DevOps infinity loop.
Accelerate your Kubernetes clusters with Varnish CachingThijs Feryn
A presentation about the usage and availability of Varnish on Kubernetes. This talk explores the capabilities of Varnish caching and shows how to use the Varnish Helm chart to deploy it to Kubernetes.
This presentation was delivered at K8SUG Singapore. See https://feryn.eu/presentations/accelerate-your-kubernetes-clusters-with-varnish-caching-k8sug-singapore-28-2024 for more details.
A tale of scale & speed: How the US Navy is enabling software delivery from l...sonjaschweigert1
Rapid and secure feature delivery is a goal across every application team and every branch of the DoD. The Navy’s DevSecOps platform, Party Barge, has achieved:
- Reduction in onboarding time from 5 weeks to 1 day
- Improved developer experience and productivity through actionable findings and reduction of false positives
- Maintenance of superior security standards and inherent policy enforcement with Authorization to Operate (ATO)
Development teams can ship efficiently and ensure applications are cyber ready for Navy Authorizing Officials (AOs). In this webinar, Sigma Defense and Anchore will give attendees a look behind the scenes and demo secure pipeline automation and security artifacts that speed up application ATO and time to production.
We will cover:
- How to remove silos in DevSecOps
- How to build efficient development pipeline roles and component templates
- How to deliver security artifacts that matter for ATO’s (SBOMs, vulnerability reports, and policy evidence)
- How to streamline operations with automated policy checks on container images
zkStudyClub - Reef: Fast Succinct Non-Interactive Zero-Knowledge Regex ProofsAlex Pruden
This paper presents Reef, a system for generating publicly verifiable succinct non-interactive zero-knowledge proofs that a committed document matches or does not match a regular expression. We describe applications such as proving the strength of passwords, the provenance of email despite redactions, the validity of oblivious DNS queries, and the existence of mutations in DNA. Reef supports the Perl Compatible Regular Expression syntax, including wildcards, alternation, ranges, capture groups, Kleene star, negations, and lookarounds. Reef introduces a new type of automata, Skipping Alternating Finite Automata (SAFA), that skips irrelevant parts of a document when producing proofs without undermining soundness, and instantiates SAFA with a lookup argument. Our experimental evaluation confirms that Reef can generate proofs for documents with 32M characters; the proofs are small and cheap to verify (under a second).
Paper: https://eprint.iacr.org/2023/1886
Removing Uninteresting Bytes in Software FuzzingAftab Hussain
Imagine a world where software fuzzing, the process of mutating bytes in test seeds to uncover hidden and erroneous program behaviors, becomes faster and more effective. A lot depends on the initial seeds, which can significantly dictate the trajectory of a fuzzing campaign, particularly in terms of how long it takes to uncover interesting behaviour in your code. We introduce DIAR, a technique designed to speedup fuzzing campaigns by pinpointing and eliminating those uninteresting bytes in the seeds. Picture this: instead of wasting valuable resources on meaningless mutations in large, bloated seeds, DIAR removes the unnecessary bytes, streamlining the entire process.
In this work, we equipped AFL, a popular fuzzer, with DIAR and examined two critical Linux libraries -- Libxml's xmllint, a tool for parsing xml documents, and Binutil's readelf, an essential debugging and security analysis command-line tool used to display detailed information about ELF (Executable and Linkable Format). Our preliminary results show that AFL+DIAR does not only discover new paths more quickly but also achieves higher coverage overall. This work thus showcases how starting with lean and optimized seeds can lead to faster, more comprehensive fuzzing campaigns -- and DIAR helps you find such seeds.
- These are slides of the talk given at IEEE International Conference on Software Testing Verification and Validation Workshop, ICSTW 2022.
Securing your Kubernetes cluster_ a step-by-step guide to success !KatiaHIMEUR1
Today, after several years of existence, an extremely active community and an ultra-dynamic ecosystem, Kubernetes has established itself as the de facto standard in container orchestration. Thanks to a wide range of managed services, it has never been so easy to set up a ready-to-use Kubernetes cluster.
However, this ease of use means that the subject of security in Kubernetes is often left for later, or even neglected. This exposes companies to significant risks.
In this talk, I'll show you step-by-step how to secure your Kubernetes cluster for greater peace of mind and reliability.
2. Thought of the Day
The Living in the
Moment Concept
Environmental Impact Assessment 2
3. DOMAINS OF ENVIRONMENT
Physical
• Air
• Water
• Land
Ecological
• Flora
• Fauna
Socio-economic
• Social
• Economic
• Cultural
Environmental Impact Assessment 3
4. Environmental Impact Assessment
EIA
WHAT IS EIA?
An important procedure for
ensuring that the likely
effects of new development
on the environment are fully
understood and taken into
account before the
development is allowed to
go ahead
Environmental Impact Assessment 4
5. What EIA can do?
• Modify and improve design
• Ensure efficient resource use
• Enhance social aspects
• Identify measures for monitoring and
managing impacts
• Inform decision-making
• Provide justification for a proposal
Environmental Impact Assessment 5
6. Origin of EIA in Pakistan
• The EIA process was strengthened under
Section 12 of Pakistan Environment Protection
Act (PEPA), 1997
• Guidelines were prepared with a thorough
consultative process with the stakeholders
• Initial Environmental Examination IEE/EIA
Regulations, 2000 notified.
Environmental Impact Assessment 6
7. Pakistan Environmental Protection Act
1997
• Penalties
• Upto One Million Rupees (Rs 10,00,000) with
a daily penalty of Rs 100,000
• Environmental Tribunals
• Judge
• National Environmental Quality Standards
(NEQS)
• Arrest Warrants
Environmental Impact Assessment 7
8. List of Projects Requiring IEE/EIA
• Agriculture, livestock and fisheries, etc.
• Energy
• Manufacturing and processing
• Mining and mineral processing
• Transport
• Water management, dams, irrigation and flood
protection
• Waste Disposal
• Urban development and tourism
• Environmentally sensitive areas
Environmental Impact Assessment 8
10. Description of a Project
• Type of project
• Need for project
• Location (use maps showing general location, specific location, project boundary
and project site layout)
• Size or magnitude of operation including any associated activities required by or
for the project
• Proposed schedule for approval and implementation
• Description of the project including drawings showing project layout, components
of project, etc. This information should be of the same type and extent as is
included in feasibility reports for proposed projects, in order to give a clear picture
of the project and its operations.
Environmental Impact Assessment 10
11. EIA processes in sequences of
application
• Project Screening
• Scoping
• Baseline Data Collection
• Identification of
Environmental Impacts
• Impact Prediction
Comparison of Alternatives
• Comparison of Alternatives
• Mitigation Measures
• Public Consultation and
Participation
• Environmental Monitoring
• Environmental Auditing
Environmental Impact Assessment 11
12. Screening
• important to establish
mechanisms by
identifying projects
which requires EIA, and
this process of selection
of project is referred to
as "Screening“
Environmental Impact Assessment 12
13. Project Scoping
• Scoping is to determine
what should be the
coverage or scope of the
EIA study for a project
proposal as having
potentially significant
environmental impacts.
Environmental Impact Assessment 13
14. Baseline Data Collection
• Baseline information is
important reference point for
conducting EIA.
• The term "baseline" refers to
the collection of background
information on the
biophysical, social and
economic settings proposed
project area.
Baseline data are collected for
two main purposes:
• to provide a description of the
status and trends of
environmental factors (e.g., air
pollutant concentrations)
against which predicted
changes can be compared and
evaluated in terms of
importance, and
• to provide a means of
detecting actual change by
monitoring once a project has
been initiated
Environmental Impact Assessment 14
15. Identification of Environmental
Impacts
• Biological and Physio-
chemical Impacts
• Social Impact
• demographic impacts, socio-
economic impacts, institutional
impacts, gender impact
• Cultural Impacts
• Health Impact
• Economic Impact
• labor force requirements, size of
investment, likely demographic
changes
Environmental Impact Assessment 15
16. Impact Prediction Comparison of
Alternatives
Considerations for Impact
Prediction
• Magnitude of Impact
• Extent of Impact
• Duration of Impact
Uncertainty in Impact
Prediction
Environmental Impact Assessment 16
20. Lahore Sports City
(Site Screening Criteria)
• Accessibility
• Land use and Land availability
• Aesthetics
• Water Availability
• Potential of Infrastructure Development
• Environmental and Social Issues
Environmental Impact Assessment 20
22. Key elements for assessing impact
significance
• Ecological
• effects on plant and animal
habitat
• rare and endangered species
• ecosystem resilience, sensitivity,
bio-diversity and carrying
capacity
• viability of local species
populations
• Environmental
Standards
• Social and Economical
• effects on human health and
safety
• potential loss of species with
current or potential value, or
commercially available
production (farmland)
• recreational or aesthetic value
• demands on public resources
such as social service
• demands on transportation and
other infrastructures
• demographic effects
Environmental Impact Assessment 22
23. Mitigation Measures
• recommended actions
to reduce, avoid or
offset the potential
adverse environmental
consequences of
development activities
• maximize project
benefits
• minimize undesirable
impacts
Environmental Impact Assessment 23
24. Mitigation Measures
• Mitigation measures
requires funding
• Mitigation measures
should be integrated in
the project design
• Mitigation measures is
not limited to one point
in the EIA process
• Link between mitigation
and monitoring
Environmental Impact Assessment 24
25. Public Consultation and Participation
• Local people
• Project beneficiaries
• NGOs
• Voluntary organizations
• Private sector
• National/local
governments
• Scientist/experts
• Private sector
Environmental Impact Assessment 25
26. Methods for stakeholder involvement
• Public meetings
• Advisory panels
• Public information
centers
• Interviews
• Questionnaires
• Participatory Appraisal
techniques
Environmental Impact Assessment 26
27. Environmental Monitoring
• an activity undertaken to
provide specific information
on the characteristics and
functions of environmental
and social variables in space
and time
Environmental monitoring is
therefore one of the most
important components of an EIA
• ensuring that impacts do not
exceed the legal standards
• checking the implementation
of mitigation measures in the
manner described in the EIA
report
• providing early warning of
potential environmental
damages
Environmental Impact Assessment 27
28. Principles of Monitoring
• Determine the indicators to be
used in monitoring activities
• Collection of meaningful and
relevant information
• Application of
measurable criteria in relation to
chosen indicators
• Reviewing objective judgments
on the information collected
• Draw tangible conclusions based
on the processing of information
• Making rational decision based
on the conclusion drawn
• Recommendation of improved
mitigation measures to be
undertaken
Environmental Impact Assessment 28
29. Types of Monitoring
• Baseline Monitoring
• pre-audit study
• Impact Monitoring
• Compliance Monitoring
Environmental Impact Assessment 29
30. Environmental Auditing
• an audit assess the actual
environmental impact
• the accuracy of prediction
• the effectiveness of
environmental impact
mitigation
• enhancement measures
• the functioning of
monitoring mechanisms
Environmental Impact Assessment 30
32. Environmental Auditing Plan
• condition of
natural/social/economical
resources prior to project
implementation
• mitigation measures
implemented are effective
to control adverse impact
• degraded landscape have
been restored into original
condition
• effect on the local economy
of project implementation
Environmental Impact Assessment 32
33. Public Hearing
Public Hearing of Environmental Impact
Assessment of 225 MW Thermal Power
RFO Fired Power Plant Near Sheikhupura
Public Hearing of Zero Point Interchange
Environmental Impact Assessment 33
34. Public Hearing
Public Hearing of Benazir Bhutto International
Airport
Public Consultation for Mirani Dam
Project
Environmental Impact Assessment 34
37. Mangla Dam Raising Project
• A population of about 50,000
persons is being affected
• About 8000 houses and other
buildings are being affected
• A total of 6,388 hectares of land
(residential, agriculture and barren)
is to be acquired
• 28 brick kilns will be abandoned
• An unprecedented and very
attractive compensation package
for the affectees has been provided
• Pakistan Resettlement Policy is
being followed for the resettlement
and compensation process
Environmental Impact Assessment 37
40. Strategic Environmental Assessment
SEA
• Social Impact
Assessment (SIA)
• Cumulative Impact
Assessment (CIA)
• Environmental and
Social Impact
Assessment (ESIA)
Environmental Impact Assessment 40
41. EIA SEA
Applied to specific and relatively short-term (life-
cycle) projects and their specifications
Applied to policies, plans and programs with broad,
long-term strategic perspective
Takes place at early stage of project planning once
parameters are set
Ideally, takes place at an early stage in strategic
planning
Considers limited range of project alternatives Considers a broad range of alternative scenarios
Usually prepared and/or funded by the project
proponents
Conducted independently of any specific project
proponent
Focus on obtaining project permission, and rarely
with feedback
to policy, plan or program consideration
Focus on decision on policy, plan and program
implications
for future lower-level decisions
Well-defined, linear process with clear beginning and
end
Multi-stage, iterative process with feedback loops
Preparation of an EIA document with prescribed
format and contents
is usually mandatory. This document provides a
baseline reference
for monitoring
May not be formally documented
Limited review of cumulative impacts, often limited
to phases of a specific project. Does not cover
regional-scale developments
or multiple projects
Inherently incorporates consideration of cumulative
impacts
Environmental Impact Assessment 41
42. Tools for predicting environmental and
socio-economic effects
• Modeling or forecasting
of direct environmental
effects
• Matrices and network
analysis
• Participatory or
consultative techniques
• Geographical information
systems as a tool to
analyze, organize and
present information
Environmental Impact Assessment 42
43. Tools for analyzing and comparing
options
• Scenario analysis and
multi-criteria analysis
• Risk analysis or
assessment
• Cost benefit analysis
• Opinion surveys to
identify priorities
Environmental Impact Assessment 43
44. A continuum of SEA application
Environmental Impact Assessment 44
45. SEA benefits at a glance
1. Supporting the integration of
environment and
development
2. Providing environmental-
based evidence to support
informed decisions
3. Improving the identification
of new opportunities
4. Preventing costly mistakes
5. Building public engagement
in decision making for
improved governance
6. Facilitating transboundary
co-operation
Environmental Impact Assessment 45
46. Thermal Power Generation Policy, Pakistan: an
early SEA would have helped
• In the mid 1990s, rapidly expanding industrial
activity, increasing population
• Pakistan’s Government decided to stimulate
increased power generation
• Independent Power Plants Policy (IPPs) provided
incentives for investments in thermal power
generation
• No SEA was made; instead investors had to submit
an EIA without considering potential cumulative
effects
• Investors given freedom to choose the
site, technology and the fuel
• plants were installed with little or no pollution
control devices
• Leading energy experts and the WAPDA raised
objections to the policy but were ignored
• EIA used down-stream decision making approach
• individual projects, especially after deciding the
site, technology and fuel
• thermal power stations using high-sulphur furnace
oil became clustered in one city and added to the
already polluted air
• Alternatively, they were developed in a scattered
way in remote places, which made it difficult to
connect them with the national grid system
Key costs
• Increased pollution
• Relocation of plants –
following public
pressure and lobbying –
at considerable cost
• Delayed delivery of
energy
Environmental Impact Assessment 46
47. The Circular Debt of Pakistan
• According to USAID report on the
Causes and Impacts of Power Sector
Circular Debt in Pakistan
• in 2008, the circular debt was Rs
161.21 billion
• increased to Rs 235.65 billion in 2009
• circular debt in 2010 increased to Rs
365.66 billion
• in 2011, this amount swelled to Rs
537.53 billion
• During the current fiscal year circular
debt increased to Rs 872.41 billion
Environmental Impact Assessment 47