The document discusses environmental impact assessments (EIA) in Malaysia. It describes the purpose and legal requirements of EIAs, which were introduced in 1987 to identify and mitigate environmental impacts of development projects. The key aspects of the EIA process in Malaysia are:
1) Projects are screened to determine if an EIA is required based on their potential environmental impacts.
2) The scoping process identifies which issues and impacts the EIA will address.
3) EIAs involve assessing alternatives, environmental baselines, impacts, and mitigation measures.
4) Completed EIA reports are submitted for review and must include opportunities for public consultation.
a general term that can reflect various types of evaluations intended to identify environmental compliance and management system implementation gaps, along with related corrective actions.
In this way they perform an analogous (similar) function to financial audits.
Developing Guidelines for Public Participation on Environmental Impact Assess...Ethical Sector
On 24 February 2016, MCRB and PACT MPE (Mekong Partnership for Environment) co-organised a discussion in Yangon of public participation in EIA with the objectives of sharing experience which could be used to guide development of regional guidelines on public participation in EIA for the Mekong region (Cambodia, Laos, Myanmar, Thailand, and Vietnam) as well as planned public participation guidelines for the implementation of Myanmar’s new EIA procedures.
U Than Aye, (Yangon office of ECD, MOECAF) gave a presentation on the public participation provisions of the Myanmar government’s EIA Procedures which were adopted on 29 December 2015, highlighting the requirements for consultation and disclosure at different stages of the EIA and Initial Environmental Examination (IEE) processes; and the resource constraints and faced by MOECAF.
a general term that can reflect various types of evaluations intended to identify environmental compliance and management system implementation gaps, along with related corrective actions.
In this way they perform an analogous (similar) function to financial audits.
Developing Guidelines for Public Participation on Environmental Impact Assess...Ethical Sector
On 24 February 2016, MCRB and PACT MPE (Mekong Partnership for Environment) co-organised a discussion in Yangon of public participation in EIA with the objectives of sharing experience which could be used to guide development of regional guidelines on public participation in EIA for the Mekong region (Cambodia, Laos, Myanmar, Thailand, and Vietnam) as well as planned public participation guidelines for the implementation of Myanmar’s new EIA procedures.
U Than Aye, (Yangon office of ECD, MOECAF) gave a presentation on the public participation provisions of the Myanmar government’s EIA Procedures which were adopted on 29 December 2015, highlighting the requirements for consultation and disclosure at different stages of the EIA and Initial Environmental Examination (IEE) processes; and the resource constraints and faced by MOECAF.
presentation on a paper of EIA given by Richard K. Morgan. The paper includes the growth of EIA around the world in last 40 years and also includes the effectiveness of EIA.
Environmental Impact Assessment (EIA) in Project ManagementJoy Bhattacharjee
Environmental Impact Assessment is a systematic process by which we can identify what will be the future consequences of a projected or recent actions.
National Environmental Policy Act (NEPA) Writing Environmental Assessments (...rshimoda2014
Helen Clough - Department of the Interior, U.S. Fish and Wildlife Service, retired, Judith Kurtzman - Utah State University
Writing clear Environmental Assessments (EAs) as required by the National Environmental Policy Act (NEPA) is critical to successful implementation of the law and more importantly good decisions. The NEPA process must be well documented in clear language so that the proposals, alternatives and the environmental effects of proposals and alternatives are clearing explained. Often the NEPA analysis is not well documented resulting in costly delays in projects as appeals and litigation occur regarding the NEPA analysis.
This training session is a continuation of the materials presented in Writing Environmental Assessments, Parts 1 and 2. Resource-specific analysis (for examples, effects on wildlife, effects on recreation, effects on water quality) and cumulative impact analysis (effects of past, present, and “reasonably foreseeable” future actions) will be explored. Mitigation and monitoring will be addressed. As with the other NEPA sessions examples relevant to river management will be explored and critiqued. Ample time is allotted for discussion and questions from participants.
National Environmental Policy Act (NEPA) Writing Environmental Assessments (...rshimoda2014
Clough, Helen - Department of the Interior, U.S. Fish and Wildlife Service, retired
This session follows Part 1 and will continue training on the EA process. Part 2 will address development of alternatives and description of the affected environment. Part 2 will end with a discussion of environmental consequences. Discussion of environmental consequences will carry over into Part 3.
While environmental impact statements (EISs) and environmental assessments (EAs) have been prepared for federal and federally funded actions for over 40 years, developing a reasonable range of alternatives, identifying the affected environment and the actual analysis of the likely environmental effects of a proposed action is often poorly understood.
The presenters will draw upon their over 50 years of experience with NEPA to describe alternatives, the affected environment and impact analysis focused on topics relevant to river management. Examples relevant to both river planning and river management will be explored and critiqued. Resource-specific analysis (for examples, effects on wildlife, effects on recreation, effects on water quality) and cumulative impact analysis (effects of past, present, and “reasonably foreseeable” future actions) will be explored. Sources of additional information and training on the subject will also be shared. Hands-on exercises will help participants expand knowledge and skill in impact assessment.
These slides could be helpful to those who want to know about the screening process in EIA. Also, these slides give brief information about the initial environmental examination(IEE).
presentation on a paper of EIA given by Richard K. Morgan. The paper includes the growth of EIA around the world in last 40 years and also includes the effectiveness of EIA.
Environmental Impact Assessment (EIA) in Project ManagementJoy Bhattacharjee
Environmental Impact Assessment is a systematic process by which we can identify what will be the future consequences of a projected or recent actions.
National Environmental Policy Act (NEPA) Writing Environmental Assessments (...rshimoda2014
Helen Clough - Department of the Interior, U.S. Fish and Wildlife Service, retired, Judith Kurtzman - Utah State University
Writing clear Environmental Assessments (EAs) as required by the National Environmental Policy Act (NEPA) is critical to successful implementation of the law and more importantly good decisions. The NEPA process must be well documented in clear language so that the proposals, alternatives and the environmental effects of proposals and alternatives are clearing explained. Often the NEPA analysis is not well documented resulting in costly delays in projects as appeals and litigation occur regarding the NEPA analysis.
This training session is a continuation of the materials presented in Writing Environmental Assessments, Parts 1 and 2. Resource-specific analysis (for examples, effects on wildlife, effects on recreation, effects on water quality) and cumulative impact analysis (effects of past, present, and “reasonably foreseeable” future actions) will be explored. Mitigation and monitoring will be addressed. As with the other NEPA sessions examples relevant to river management will be explored and critiqued. Ample time is allotted for discussion and questions from participants.
National Environmental Policy Act (NEPA) Writing Environmental Assessments (...rshimoda2014
Clough, Helen - Department of the Interior, U.S. Fish and Wildlife Service, retired
This session follows Part 1 and will continue training on the EA process. Part 2 will address development of alternatives and description of the affected environment. Part 2 will end with a discussion of environmental consequences. Discussion of environmental consequences will carry over into Part 3.
While environmental impact statements (EISs) and environmental assessments (EAs) have been prepared for federal and federally funded actions for over 40 years, developing a reasonable range of alternatives, identifying the affected environment and the actual analysis of the likely environmental effects of a proposed action is often poorly understood.
The presenters will draw upon their over 50 years of experience with NEPA to describe alternatives, the affected environment and impact analysis focused on topics relevant to river management. Examples relevant to both river planning and river management will be explored and critiqued. Resource-specific analysis (for examples, effects on wildlife, effects on recreation, effects on water quality) and cumulative impact analysis (effects of past, present, and “reasonably foreseeable” future actions) will be explored. Sources of additional information and training on the subject will also be shared. Hands-on exercises will help participants expand knowledge and skill in impact assessment.
These slides could be helpful to those who want to know about the screening process in EIA. Also, these slides give brief information about the initial environmental examination(IEE).
Philippine Envaironmental Impact System System. This my presentation in one of my subject Mining 103.. i tried my best just to finish this.. although this report did not cover all the sections in the PEISS.
Environment impact Assessment (EIA) in Ugandakayondo alex
The definition of an EIA, its purpose, The lead agency involved, the various stages undertaken and where or not EIA is needed. the presentation summarizes the EIA process in Uganda.
EIA is an important tool to make sure the healthy of our environment. It helps us to sustain our environment healthy for long run as well as benifit for our human as much as possible
Micro RNA genes and their likely influence in rice (Oryza sativa L.) dynamic ...Open Access Research Paper
Micro RNAs (miRNAs) are small non-coding RNAs molecules having approximately 18-25 nucleotides, they are present in both plants and animals genomes. MiRNAs have diverse spatial expression patterns and regulate various developmental metabolisms, stress responses and other physiological processes. The dynamic gene expression playing major roles in phenotypic differences in organisms are believed to be controlled by miRNAs. Mutations in regions of regulatory factors, such as miRNA genes or transcription factors (TF) necessitated by dynamic environmental factors or pathogen infections, have tremendous effects on structure and expression of genes. The resultant novel gene products presents potential explanations for constant evolving desirable traits that have long been bred using conventional means, biotechnology or genetic engineering. Rice grain quality, yield, disease tolerance, climate-resilience and palatability properties are not exceptional to miRN Asmutations effects. There are new insights courtesy of high-throughput sequencing and improved proteomic techniques that organisms’ complexity and adaptations are highly contributed by miRNAs containing regulatory networks. This article aims to expound on how rice miRNAs could be driving evolution of traits and highlight the latest miRNA research progress. Moreover, the review accentuates miRNAs grey areas to be addressed and gives recommendations for further studies.
Characterization and the Kinetics of drying at the drying oven and with micro...Open Access Research Paper
The objective of this work is to contribute to valorization de Nephelium lappaceum by the characterization of kinetics of drying of seeds of Nephelium lappaceum. The seeds were dehydrated until a constant mass respectively in a drying oven and a microwawe oven. The temperatures and the powers of drying are respectively: 50, 60 and 70°C and 140, 280 and 420 W. The results show that the curves of drying of seeds of Nephelium lappaceum do not present a phase of constant kinetics. The coefficients of diffusion vary between 2.09.10-8 to 2.98. 10-8m-2/s in the interval of 50°C at 70°C and between 4.83×10-07 at 9.04×10-07 m-8/s for the powers going of 140 W with 420 W the relation between Arrhenius and a value of energy of activation of 16.49 kJ. mol-1 expressed the effect of the temperature on effective diffusivity.
WRI’s brand new “Food Service Playbook for Promoting Sustainable Food Choices” gives food service operators the very latest strategies for creating dining environments that empower consumers to choose sustainable, plant-rich dishes. This research builds off our first guide for food service, now with industry experience and insights from nearly 350 academic trials.
"Understanding the Carbon Cycle: Processes, Human Impacts, and Strategies for...MMariSelvam4
The carbon cycle is a critical component of Earth's environmental system, governing the movement and transformation of carbon through various reservoirs, including the atmosphere, oceans, soil, and living organisms. This complex cycle involves several key processes such as photosynthesis, respiration, decomposition, and carbon sequestration, each contributing to the regulation of carbon levels on the planet.
Human activities, particularly fossil fuel combustion and deforestation, have significantly altered the natural carbon cycle, leading to increased atmospheric carbon dioxide concentrations and driving climate change. Understanding the intricacies of the carbon cycle is essential for assessing the impacts of these changes and developing effective mitigation strategies.
By studying the carbon cycle, scientists can identify carbon sources and sinks, measure carbon fluxes, and predict future trends. This knowledge is crucial for crafting policies aimed at reducing carbon emissions, enhancing carbon storage, and promoting sustainable practices. The carbon cycle's interplay with climate systems, ecosystems, and human activities underscores its importance in maintaining a stable and healthy planet.
In-depth exploration of the carbon cycle reveals the delicate balance required to sustain life and the urgent need to address anthropogenic influences. Through research, education, and policy, we can work towards restoring equilibrium in the carbon cycle and ensuring a sustainable future for generations to come.
Willie Nelson Net Worth: A Journey Through Music, Movies, and Business Venturesgreendigital
Willie Nelson is a name that resonates within the world of music and entertainment. Known for his unique voice, and masterful guitar skills. and an extraordinary career spanning several decades. Nelson has become a legend in the country music scene. But, his influence extends far beyond the realm of music. with ventures in acting, writing, activism, and business. This comprehensive article delves into Willie Nelson net worth. exploring the various facets of his career that have contributed to his large fortune.
Follow us on: Pinterest
Introduction
Willie Nelson net worth is a testament to his enduring influence and success in many fields. Born on April 29, 1933, in Abbott, Texas. Nelson's journey from a humble beginning to becoming one of the most iconic figures in American music is nothing short of inspirational. His net worth, which estimated to be around $25 million as of 2024. reflects a career that is as diverse as it is prolific.
Early Life and Musical Beginnings
Humble Origins
Willie Hugh Nelson was born during the Great Depression. a time of significant economic hardship in the United States. Raised by his grandparents. Nelson found solace and inspiration in music from an early age. His grandmother taught him to play the guitar. setting the stage for what would become an illustrious career.
First Steps in Music
Nelson's initial foray into the music industry was fraught with challenges. He moved to Nashville, Tennessee, to pursue his dreams, but success did not come . Working as a songwriter, Nelson penned hits for other artists. which helped him gain a foothold in the competitive music scene. His songwriting skills contributed to his early earnings. laying the foundation for his net worth.
Rise to Stardom
Breakthrough Albums
The 1970s marked a turning point in Willie Nelson's career. His albums "Shotgun Willie" (1973), "Red Headed Stranger" (1975). and "Stardust" (1978) received critical acclaim and commercial success. These albums not only solidified his position in the country music genre. but also introduced his music to a broader audience. The success of these albums played a crucial role in boosting Willie Nelson net worth.
Iconic Songs
Willie Nelson net worth is also attributed to his extensive catalog of hit songs. Tracks like "Blue Eyes Crying in the Rain," "On the Road Again," and "Always on My Mind" have become timeless classics. These songs have not only earned Nelson large royalties but have also ensured his continued relevance in the music industry.
Acting and Film Career
Hollywood Ventures
In addition to his music career, Willie Nelson has also made a mark in Hollywood. His distinctive personality and on-screen presence have landed him roles in several films and television shows. Notable appearances include roles in "The Electric Horseman" (1979), "Honeysuckle Rose" (1980), and "Barbarosa" (1982). These acting gigs have added a significant amount to Willie Nelson net worth.
Television Appearances
Nelson's char
Natural farming @ Dr. Siddhartha S. Jena.pptxsidjena70
A brief about organic farming/ Natural farming/ Zero budget natural farming/ Subash Palekar Natural farming which keeps us and environment safe and healthy. Next gen Agricultural practices of chemical free farming.
2. LEARNING OUTCOME
•Describe the purpose and role of EIA in the decision-making
process;
•understand the strengths of EIA in regard to environmental
management;
•understand the technical and social/political limitations of EIA;
•understand the scoping process and how it is applied;
•know the format of an EIA Report
4. EIA :INTRODUCTION
•DOE was formed as a result of the section 34A:EQA
1974
•The emphasis was on control of pollution and
taking remedial action
•1970’s and 1980’s: agro based: palm oil and rubber
wastes
•1987:EIA was introduced for preventive control
5. WHAT IS EIA?
EIA is a study to identify, predict, evaluate and
communicate information about the impacts
on the environment of a proposed project and to
detail out the mitigating measures prior to project
approval and implementation.( DOE,Malaysia)
6. LEGAL REQUIREMENT IN MALAYSIA
•In Malaysia, EIA is required under section 34A, Environmental Quality Act, 1974 ,
which specifies the legal requirements in respect of EIA for Prescribed Activities.
•It empowers the Minister of Natural Resources and Environment after due
consultation, to prescribe any activity which may have significant environmental
impact as a Prescribed Activity.
•The section further requires the Project Proponent of a Prescribed Activity to
submit a report (the EIA) to the Director General of Environmental Quality before
approval for the proposed activity is granted by the relevant approving authority.
•The EIA report must be in accordance with the guidelines issued by the DOE
contain an assessment of the impact of the Prescribed Activity on the
environment; and detail the proposed measures that shall be instituted to prevent,
reduce or control adverse impacts on the environment
7. WHO CAN CONDUCT EIA STUDY?
•An EIA Study has to be conducted by
competent individuals who are registered with
the Department of Environment under the EIA
Consultant Registration Scheme.
8. How To Conduct EIA?
•In the preparation of EIA reports, project proponents
and EIA consultants may refer to A Handbook of
Environmental Impact Assessment Guidelines
(fourth edition) 2007 and EIA Guidelines for specific
activities published by the Department of Environment
and other relevant guidelines published by other
agencies
9. WHY DO WE NEED EIA?
•EIA is essentially a planning mechanism for preventing
environmental problems due to an action.
•It ensures that the potential problems are foreseen and addressed
at an early stage in the project planning and design.
•Thus this will avoid costly mistakes in project implementation, either
because of the environmental damages that are likely to arise
during project implementation, or because of modifications that may
be required subsequently in order to make the action
environmentally acceptable
•EIA when integrated into the existing planning and decision-making
structure, provides additional information towards a better decision-
making.
10. GENERIC LIMITATION OF EIA
•EIA occurs at the project level, not the policy program level
•EIA is typically done after feasibility studies and preliminary
decisions are made.
•The EIA is then and ‘add-on’ to meet legal requirements, and
serves largely to suggest mitigation measures for a project
already selected, rather than an opportunity to come up with
optimal project.
11. •Environmental values which have not or cannot be monetized
may fall through the cracks
•Consultation with public does not necessarily require a full
inclusion of all relevant stake-holders
•Social equity considerations are typically outside the scope of
EIA
•Although EIA occur before the project decision, they should also
be used AFTER the decision to help ensure robust
environmental monitoring and management throughout project
life but this id not done.
12. EIA:SCOPE
•Before initiating environmental studies, an agency determines
scopes of issues to be addressed in the EIS.
•If preliminary studies determines that significant environment
impacts are likely, the appropriate agency must prepare the EIS.
•Agency identifies individual citizens, interest groups, institutions
likely to be interested.
•Scoping also involves synchronizing environmental studies and
decision making time table.
13. EIA: COMPONENTS
•Statement of purpose
•Scoping
•Alternatives, including proposed action
•Environmental impact of each alternative
•Mitigation measures
•Consultation and coordination
•List of papers
14. EIA:AIM
•To assess the overall impact on the
environment of development projects proposed
by the public and private sectors.
15. EIA:OBJECTIVES
•To examine and select the best from the project options
available
•To identify and incorporate into the project plan appropriate
abatement and mitigating measures.
•To predict significant residual environmental impacts
•To determine the significant residual environmental impacts
predicted, and to identify the environmental costs and benefits of
the project to the community.
16. THE EIA DIRECTIVE
•The EIA should identify, describe and assess the
direct and indirect effects of a project on the following
factors:
o human beings, fauna and flora
o soil, water, air, climate and the landscape
o material assets and cultural heritage
o the interaction between the above factors
•EIA should therefore have a strong social dimension
17. Screening (does the project
require EIA?)
Scoping (what issues and
impacts should the EIA address?)
Baseline studies (establish the
environmental baseline)
Alternatives (consider the
different approaches)
Mitigation (what can be done to
alleviate negative impacts?)
EIS preparation/review
(document the EIA findings)
Public consultation (consult
general public and NGOs)
Monitoring (monitor impacts of
project)
Impact prediction (forecast
the environmental impacts)
Impact assessment
(interpreting the impacts)
18. SCREENING
•Is an EIA needed?
•A screening mechanism seeks to identify those
projects with potentially significant adverse
environmental effects
19. SCOPING
•The scope of an EIA is the issues and impacts it addresses
•Scoping is the process of deciding which of a project’s
possible alternatives and impacts should be addressed in
the EIA
•An EIA should focus only on the significant issues and
impacts
20. SCOPING
•Scoping is carried out in discussions between the
developer, the competent authority, relevant agencies
and, ideally, the public
•Effective scoping enables limited resources to be
allocated to best effect (i.e. through investigation of
only the most significant impacts)
•Scoping is not mandatory under the EIA Directive
21. BASELINE STUDIES
•Following the scoping phase, it is essential to
assemble all the relevant information on the current
status of the environment
•The baseline study should anticipate the future state of
the environment assuming the project is not
undertaken - the ‘no action alternative’
•This provides the ‘baseline’ against which future
impacts can be assessed
22. BASELINE STUDIES
•Baseline studies should be undertaken for each
alternative site so that the relative severity of the
impacts for each alternative can be assessed
•New field work may necessary (e.g. ecological survey)
if relevant data is not already available
23. ALTERNATIVES
•EIA is ideally undertaken for a project and its alternatives (e.g.
different locations, scales, designs)
•Alternatives are the ‘raw material’ of EIA
•The US Council on Environmental Quality (CEQ) has described
the discussion of alternatives as the ‘heart’ of the EIS
•Many EISs fail to consider alternatives
24. IMPACT ASSESSMENT
•Impact assessment involves evaluating the significance of the
impacts identified
•Significance can be determined through professional judgment,
reference to regulations etc.
•Potential for bias in determining what is significant
•The conclusions of the impact assessment can ultimately be
used by decision-makers when determining the fate of the
project application
25. MITIGATION
•Negative impacts on the environment identified during the EIA
can be alleviated through mitigation measures
•The mitigation hierarchy: Avoid - Reduce - Remedy -
Compensate - Enhance
•Impacts remaining after mitigation are known as residual
impacts
•The legislation obstructs the proper process of design
development
26. EIS PREPARATION / REVIEW
•The Environmental Impact Statement (EIS) is a formal
document which includes information on the development and
information relating to screening, scoping, baseline studies,
alternatives etc.
•Common requirement to include a non-technical summary
27. EIS PREPARATION / REVIEW
•Once complete, the EIS is submitted to the competent authority
(along with the planning application)
•The EIS is often reviewed (either formally or informally)
•The review enables the competent authority to decide whether
the EIA is adequate, accurate and unbiased
28. PUBLIC CONSULTATION
•The EIA Directive provides for public consultation on
the application for development and the EIS
29. POST-PROJECT MONITORING
•Monitoring should determine:
o the accuracy of the original predictions
o the degree of deviation from the predictions
o the possible reasons for any deviations
o the extent to which mitigation measures have achieved their
objectives
30. MALAYSIA EIA PROCEDURE
•The EIA procedure in Malaysia has been designed to follow the
integrated project planning concept so that EIA is carried out at
the pre-feasibility and feasibility stages.
•Comparable to the National Environmental Policy Act
1969(NEPA) model in US
32. EIA: PROCEDURES
•Preliminary assessments of all prescribed activities
•Detailed assessments of those prescribed activities for
which significant residual environmental impacts have
been predicted in the preliminary assessments
•Review of assessment reports
33. EIA: Steps- Preliminary Assessments
•Objectives
To examine and select the best from the project
options available
To identify and incorporate into the project plan
appropiate abatement and mitigating measures
To identify significant residual environmental
impacts
34. EIA: STEPS-DETAILED ASSESSMENTS
•Objectives
To describe the significant residual environmental
impacts predicted from the final project plan
To specify mitigating and abatement measures in
the final project plan
To identify the environmental costs and benefits of
the project to the community
35. AIR QUALITY
•Looking for
oOxides of nitrogen (NOx)
oOxides of sulphur (SOx)
oOzone O3
oParticulates PM10 and now
PM2.5
oDioxins and Furans for
Incinerators
oParticulates (dust)
oOdour
36. AIR QUALITY
•No legal standards
•Most projects have very limited impact
•Dioxins and Furans have become significant concerns
since the extremely low levels could be measured
37. FORESTRY AND AGRICULTURE
•Classification of land (Grade 1, 2, 3)
•Severance and viability
•Orphaning of land parcels
•Isolating buildings from fields etc
•Opportunities for landscaping on isolated pieces of land
39. LANDSCAPE AND VISUAL
AMENITY
•Visual assessment
•Site categorisation ( Conservation area)
•Inter visibility plots
•Landscape description
•Landscape value
•Opportunities for landscaping
40. HERITAGE AND ARCHAEOLOGY
•Site categorization (World Heritage
Site, Conservation Area)
•Locally important buildings without
designation
•English Heritage
•National Trust
•County Archaeologist
41. ECOLOGY
•Assessment of ecological value
•Site categorisation
•Inventory of flora and fauna
•Rare species
•Protected species
•Impact of severance, disruption etc
•English Nature, Wildlife Trusts etc
47. EIA: ISSUES AND PROBLEM
•Lack of awareness of the strength of EIA as a planning tool.
Many still perceive EIA as a stumbling block to development.
•Perception that carrying out EIA would delay project approval
and implementation
•EIA not carried out prior to final project design, so that issues
such as sitting and technology are not considered.
•Lack of baseline data on environmental quality
•Poor prediction of impacts
•Limitation public participation
48. EIA:CASE STUDY- BERIS DAM,KEDAH
•Title: Dam Project: Environmental Impacts and
mitigation Measures: A case of Beris Dam,
Kedah,Malaysia
•Purpose: To alleviate water shortage problems meting
the demands for the agricultural, domestic and
industrial needs
49. EIA:CASE STUDY-PRE-CONSTRUCTION
•There are various steps necessary to be taken during the
planning and site preparation.
•This include: providing sufficient buffer zones between a road
reserves and the project area and maintaining as far as possible
the natural topography of the project area.
•In an EIA report, it is required at this stage to prepare scheduled
earthworks in such a way that rainy seasons are avoided.
•Detailed earthworks plan shall be paved before the start of any
construction
50. •For site preparation prior to actual construction, any cleared
areas must be turned immediately. Cutting of trees should be
reduced to a minimum and only areas designated for
construction of building, roads or any other infrastructures shall
be cleared.
•Temporary sanitary facilities shall ne provided in the worker’s
camp.
•The ground conditions as described in the EIA is usually very
brief and further investigations are required to ascertain the sites
especially if the land use of the areas are known as former
industrial area or dumping sites.
•Studies on the state of the health of the site should be carried
out.
51. EIA:CASE STUDY-DURING CONSTRUCTION
•During construction, the disposal of construction wastes must be
removed within the project area and the open burning should not
be carried out.
•Noise level at the boundary of the construction site shall be
controlled as not exceed 55 dBA at night and 65 dBA during the
day.
•Silt trap shall be followed to minimized the impacts to river
quality.
•Vehicles and machineries used for transportation of construction
materials shall be cleaned before leaving the construction sites.
52. EIA:CASE STUDY- POST-CONSTRUCTION
•The period just before handing over and years beyond
require certain aspects of environmental management.
•The construction wastes and debris have to be
disposed at approved sites.
•Monitoring for river quality downstream of the site has
to be carried out if stated by the EIA report.