SlideShare a Scribd company logo
Earned Value Analysis
By Er. NikhilRaj
BAC BUDGETED AT COMPLETION PV PLANNED VALUE EV
EARNED VALUE
SV SCHEDULE VARIANCE CV COST VARIANCE SPI SCHEDULE
PERFORMANCE INDEX
CPI COST PERFORMANCE INDEX EAC ESTIMATE AT COMPLETION ETC
ESTIMATE TO COMPLETION
VAC VARIANCE AT
COMPLETION
1/21/2016
1all rights reserved to www.tutomaash.com | any queries can be mailed to tutomaash@gmail.com
Performance measuring system | Forecasting system
Contents
• What is earned value?
• Why earned value?
• EVM practiced industries
• Application example
• Application of same example in primavera p6
• Generation of financial s-curve
1/21/2016
2
Definition
Earned value management (EVM) is a methodology that combines scope,
schedule, and resource measurements to assess project performance and
progress.
It is a commonly used method of performance measurement for projects.
It integrates the scope baseline with the cost baseline, along with the
schedule baseline, to form the performance baseline, which helps the
project management team assess and measure project performance and
progress
- PMBOK 5th Edition Pg.217
1/21/2016
3
Why EVM?
Quantify and measure program/contract performance,
Provide an early warning system for deviation from a baseline,
Mitigate risks associated with cost and schedule overruns,
Provide a means to forecast final cost and schedule outcomes
1/21/2016
4
EVM practiced industries
Department of Defense (DoD)
The Federal government
Construction
IT sector
Commercial sector
R&D
Aerospace
1/21/2016
5
Example
2 weeks into the project
Ms Ann completed 35MILES
Also spent $15500
“Calculate the
Performance”
Imagine Ms Ann is the project manager of 100 miles road work
She must finish the project in 5 weeks
She can spent $10000/week
PLANNED
ACTUAL
2W
4W
3W
2W
1W
5W
1/21/2016
6
PLANNED VS ACTUAL
TOTAL PROJECT BUDGET=$50000
PLAN
(TIME)
W1
W2
W3
W4
W5
PLAN
(COST)
$10000
$20000
PV
$30000
$40000
$50000
BAC
PLAN
(%COMPLETE)
20%
20MILES
40%
40 MILES
60%
60 MILES
80%
80 MILES
100%
100 MILES
ACTUAL
(TIME)
W1
W2
W3
W4
W5
ACTUAL
(COST)
$15500
AC
ACTUAL
(%COMPLETE)
35%
35 MILES
1/21/2016
7
NAME DEFINITION EQUATION
VALUE
2nd week
INTERPRETATION
BAC | BUDGETED AT
COMPLETION
The value of total planned work, the project cost baseline $50000
PV | PLANNED VALUE
COST
The value of the work planned to be completed to a point in
time, usually the data date, or project completion $20000
EV | EARNED VALUE
COST
The planned value of all the work completed (earned) to a
point in time, usually the data date, without reference to actual
costs
$17500
AC | ACTUAL COST The actual cost of all the work completed to a point in time,
usually the data date $15500
CV | COST VARIANCE
The difference between the value of work completed to a point
in time, usually the data date, and the actual costs to the same
point in time
CV = EV –
AC $2000
Positive = Under planned cost
Neutral = On planned cost
Negative = Over planned cost
SV | SCHEDULE
VARIANCE
The difference between the work completed to a point in time,
and the work planned to be completed to the same point in
time.
SV = EV –
PV -$2500
Positive = Ahead of Schedule
Neutral = On schedule
Negative = Behind Schedule
CPI | COST
PERFORMANCE INDEX
A measure of the cost efficiency of budgeted resources
expressed as the ratio of earned value to actual cost. CPI = EV/AC 1.129
>1.0 = Under planned cost
Exactly 1.0 = On planned cost
<1.0 = Over planned cost
SPI | SCHEDULE
PERFORMANCE INDEX
A measure of schedule efficiency expressed as the ratio of
earned value to planned value
SPI = EV/PV 0.875
>1.0 = Ahead of schedule
Exactly 1.0 = On schedule
<1.0 = Behind schedule
VALUESCALCULATED
USINGEQUATION
VALUES
FROM
ACTUAL
VALUES
FROM
PLAN
1/21/2016
8
Project forecast
2WBAC= $50000 (Planned budget)
EAC= $44287 (Forecasted Budget calculated Based On 2nd week actual values)
ETC= EAC-AC
=$28786 (money to finish project)AC= $15500
1/21/2016
9
NAME DEFINITION EQUATION
VALUE
2nd week
EAC | ESTIMATE AT
COMPLETION
If the CPI is expected to be the same for the remainder of the
project, EAC can be calculated using EAC = BAC/CPI $44286.979
If future work will be accomplished at the planned rate, use: EAC = AC + BAC – EV $48000
If the initial plan is no longer valid, use: EAC = AC + Bottom-up ETC
If both the CPI and SPI influence the remaining work, use EAC = AC + [(BAC – EV)/(CPI x SPI)] $48398.899
ETC | ESTIMATE TO
COMPLETION
Assuming work is proceeding on plan, the cost of completing the
remaining authorized work can be calculated using:
ETC = EAC – AC $28786
Reestimate the remaining work from the bottom up ETC = Reestimate
VAC | VARIANCE AT
COMPLETION
The estimated difference in cost at the completion of the project.
Positive = Under planned cost
Neutral = On planned cost
Negative = Over planned cost
VAC = BAC – EAC $5713.021
1/21/2016
10
FORECASTEDVALUES
See Mix
in Action!
https://mix.office.com/watch/1otxpj7hz6kbx
(Copy the link and paste into your browser.
Or, when in a slide show, click the photo.)
1/21/2016
11
Get the add-in
Office Mix
Learn more at http://aka.ms/officemix
1/21/2016

More Related Content

What's hot

Earned value management (EVM)
Earned value management (EVM)Earned value management (EVM)
Earned value management (EVM)
Joshua Render
 
Earned value management for Beginners
Earned value management for Beginners Earned value management for Beginners
Earned value management for Beginners Shenin Hassan
 
Earned Value Analysis - Basic Concepts
Earned Value Analysis  - Basic ConceptsEarned Value Analysis  - Basic Concepts
Earned Value Analysis - Basic Concepts
Ricardo Viana Vargas
 
Earned Value Management
Earned Value ManagementEarned Value Management
Earned Value Management
Mansoor Shoaib
 
project control using earned value analysis - Part 01
project control using earned value analysis - Part 01 project control using earned value analysis - Part 01
project control using earned value analysis - Part 01
waleed hamdy
 
7.4 Earned Value Analysis
7.4 Earned Value Analysis7.4 Earned Value Analysis
7.4 Earned Value Analysis
DavidMcLachlan1
 
Project cost & control
Project cost & controlProject cost & control
Project cost & control
AMARAYYA
 
A simple example of Earned Value Management (EVM) in action
A simple example of Earned Value Management (EVM) in actionA simple example of Earned Value Management (EVM) in action
A simple example of Earned Value Management (EVM) in action
Planisware
 
Construction Cost Control
Construction Cost ControlConstruction Cost Control
Construction Cost Control
Sunayana Miglani
 
EVM of Project Management...
EVM of Project Management...EVM of Project Management...
EVM of Project Management...Fahad Ali
 
Introduction to Earned Value Management
Introduction to Earned Value ManagementIntroduction to Earned Value Management
Introduction to Earned Value Management
Unanet
 
Project Cost Management - PMBOK6
Project Cost Management - PMBOK6Project Cost Management - PMBOK6
Project Cost Management - PMBOK6
Agus Suhanto
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost Management
Hayat Denzi
 
Project Control
Project ControlProject Control
Project Control
Martin Sillaots
 
Back to basics - Earned Value Management for beginners webinar
Back to basics - Earned Value Management for beginners webinarBack to basics - Earned Value Management for beginners webinar
Back to basics - Earned Value Management for beginners webinar
Association for Project Management
 

What's hot (20)

Earned value management (EVM)
Earned value management (EVM)Earned value management (EVM)
Earned value management (EVM)
 
Earned Value Analysis
Earned Value AnalysisEarned Value Analysis
Earned Value Analysis
 
Earned value management for Beginners
Earned value management for Beginners Earned value management for Beginners
Earned value management for Beginners
 
Earned Value Analysis - Basic Concepts
Earned Value Analysis  - Basic ConceptsEarned Value Analysis  - Basic Concepts
Earned Value Analysis - Basic Concepts
 
Earned Value Management
Earned Value ManagementEarned Value Management
Earned Value Management
 
project control using earned value analysis - Part 01
project control using earned value analysis - Part 01 project control using earned value analysis - Part 01
project control using earned value analysis - Part 01
 
7.4 Earned Value Analysis
7.4 Earned Value Analysis7.4 Earned Value Analysis
7.4 Earned Value Analysis
 
Project cost & control
Project cost & controlProject cost & control
Project cost & control
 
A simple example of Earned Value Management (EVM) in action
A simple example of Earned Value Management (EVM) in actionA simple example of Earned Value Management (EVM) in action
A simple example of Earned Value Management (EVM) in action
 
Construction Cost Control
Construction Cost ControlConstruction Cost Control
Construction Cost Control
 
EVM of Project Management...
EVM of Project Management...EVM of Project Management...
EVM of Project Management...
 
Project cost management-slides
Project cost management-slidesProject cost management-slides
Project cost management-slides
 
07 project cost management
07 project cost management07 project cost management
07 project cost management
 
Introduction to Earned Value Management
Introduction to Earned Value ManagementIntroduction to Earned Value Management
Introduction to Earned Value Management
 
Project scheduling
Project schedulingProject scheduling
Project scheduling
 
Project Cost Management - PMBOK6
Project Cost Management - PMBOK6Project Cost Management - PMBOK6
Project Cost Management - PMBOK6
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost Management
 
Project Control
Project ControlProject Control
Project Control
 
Cost Management
Cost ManagementCost Management
Cost Management
 
Back to basics - Earned Value Management for beginners webinar
Back to basics - Earned Value Management for beginners webinarBack to basics - Earned Value Management for beginners webinar
Back to basics - Earned Value Management for beginners webinar
 

Viewers also liked

Earned Value Analysis - EVA
Earned Value Analysis - EVAEarned Value Analysis - EVA
Earned Value Analysis - EVAAhmed Bamasdoos
 
Agile and earned value management
Agile and earned value management  Agile and earned value management
Agile and earned value management
Dr Ezzat Mansour
 
Performance Analaysis - Earned Value Analysis
Performance Analaysis - Earned Value AnalysisPerformance Analaysis - Earned Value Analysis
Performance Analaysis - Earned Value AnalysisDeborah Obasogie
 
Earned Value Analysis in the Control of Projects
Earned Value Analysis in the Control of ProjectsEarned Value Analysis in the Control of Projects
Earned Value Analysis in the Control of Projects
Ricardo Viana Vargas
 
Earned value management in action - A Webinar by Vivek Prakash, pmwares
Earned value management in action - A Webinar by Vivek Prakash, pmwares Earned value management in action - A Webinar by Vivek Prakash, pmwares
Earned value management in action - A Webinar by Vivek Prakash, pmwares Vivek Prakash
 
Calendar in Primavera P6 R15.2
Calendar in Primavera P6 R15.2Calendar in Primavera P6 R15.2
Calendar in Primavera P6 R15.2
Nikhil Raj
 
Primavera P6 R8.3,8.4, R15 HD Training videos + Support For Working Professio...
Primavera P6 R8.3,8.4, R15 HD Training videos + Support For Working Professio...Primavera P6 R8.3,8.4, R15 HD Training videos + Support For Working Professio...
Primavera P6 R8.3,8.4, R15 HD Training videos + Support For Working Professio...
Nikhil Raj
 
Résistance des matériaux
Résistance des  matériaux Résistance des  matériaux
Résistance des matériaux
El Hassasna Riadh
 
Enterprise Project Structure (EPS)
Enterprise Project Structure (EPS)Enterprise Project Structure (EPS)
Enterprise Project Structure (EPS)
Nikhil Raj
 
Activity Types and Relationships in Primavera p6
Activity Types and Relationships in Primavera p6 Activity Types and Relationships in Primavera p6
Activity Types and Relationships in Primavera p6
Nikhil Raj
 
Robot 2010 patie3
Robot 2010 patie3Robot 2010 patie3
Robot 2010 patie3
El Hassasna Riadh
 
Robot 2010 patie2
Robot 2010 patie2Robot 2010 patie2
Robot 2010 patie2
El Hassasna Riadh
 
Critical path method (CPM)
Critical path method (CPM)Critical path method (CPM)
Critical path method (CPM)
Nikhil Raj
 
Robot 2010 patie4
Robot 2010 patie4Robot 2010 patie4
Robot 2010 patie4
El Hassasna Riadh
 
organizational breakdown structure (OBS)
organizational breakdown structure (OBS)organizational breakdown structure (OBS)
organizational breakdown structure (OBS)
Nikhil Raj
 
Formation Robo2010 patie1
Formation Robo2010 patie1Formation Robo2010 patie1
Formation Robo2010 patie1
El Hassasna Riadh
 
Human aspect of project management
Human aspect of project managementHuman aspect of project management
Human aspect of project managementKinshook Chaturvedi
 
Travailler en securite
Travailler en securiteTravailler en securite
Travailler en securite
Anis Souissi
 
Catalogue formation Autodesk Robot Structural Analysis
Catalogue formation Autodesk Robot Structural AnalysisCatalogue formation Autodesk Robot Structural Analysis
Catalogue formation Autodesk Robot Structural Analysis
Francois PEDEBOSCQ
 

Viewers also liked (20)

Earned Value Analysis - EVA
Earned Value Analysis - EVAEarned Value Analysis - EVA
Earned Value Analysis - EVA
 
Agile and earned value management
Agile and earned value management  Agile and earned value management
Agile and earned value management
 
Performance Analaysis - Earned Value Analysis
Performance Analaysis - Earned Value AnalysisPerformance Analaysis - Earned Value Analysis
Performance Analaysis - Earned Value Analysis
 
Earned Value Analysis in the Control of Projects
Earned Value Analysis in the Control of ProjectsEarned Value Analysis in the Control of Projects
Earned Value Analysis in the Control of Projects
 
S-Curve Presentation- 20130529
S-Curve Presentation- 20130529S-Curve Presentation- 20130529
S-Curve Presentation- 20130529
 
Earned value management in action - A Webinar by Vivek Prakash, pmwares
Earned value management in action - A Webinar by Vivek Prakash, pmwares Earned value management in action - A Webinar by Vivek Prakash, pmwares
Earned value management in action - A Webinar by Vivek Prakash, pmwares
 
Calendar in Primavera P6 R15.2
Calendar in Primavera P6 R15.2Calendar in Primavera P6 R15.2
Calendar in Primavera P6 R15.2
 
Primavera P6 R8.3,8.4, R15 HD Training videos + Support For Working Professio...
Primavera P6 R8.3,8.4, R15 HD Training videos + Support For Working Professio...Primavera P6 R8.3,8.4, R15 HD Training videos + Support For Working Professio...
Primavera P6 R8.3,8.4, R15 HD Training videos + Support For Working Professio...
 
Résistance des matériaux
Résistance des  matériaux Résistance des  matériaux
Résistance des matériaux
 
Enterprise Project Structure (EPS)
Enterprise Project Structure (EPS)Enterprise Project Structure (EPS)
Enterprise Project Structure (EPS)
 
Activity Types and Relationships in Primavera p6
Activity Types and Relationships in Primavera p6 Activity Types and Relationships in Primavera p6
Activity Types and Relationships in Primavera p6
 
Robot 2010 patie3
Robot 2010 patie3Robot 2010 patie3
Robot 2010 patie3
 
Robot 2010 patie2
Robot 2010 patie2Robot 2010 patie2
Robot 2010 patie2
 
Critical path method (CPM)
Critical path method (CPM)Critical path method (CPM)
Critical path method (CPM)
 
Robot 2010 patie4
Robot 2010 patie4Robot 2010 patie4
Robot 2010 patie4
 
organizational breakdown structure (OBS)
organizational breakdown structure (OBS)organizational breakdown structure (OBS)
organizational breakdown structure (OBS)
 
Formation Robo2010 patie1
Formation Robo2010 patie1Formation Robo2010 patie1
Formation Robo2010 patie1
 
Human aspect of project management
Human aspect of project managementHuman aspect of project management
Human aspect of project management
 
Travailler en securite
Travailler en securiteTravailler en securite
Travailler en securite
 
Catalogue formation Autodesk Robot Structural Analysis
Catalogue formation Autodesk Robot Structural AnalysisCatalogue formation Autodesk Robot Structural Analysis
Catalogue formation Autodesk Robot Structural Analysis
 

Similar to Earned value analysis

5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
ProfDrAnbalaganChinn
 
Project Management EVM & SCBA
Project Management EVM & SCBAProject Management EVM & SCBA
PMP COST FORMULAE
PMP COST FORMULAEPMP COST FORMULAE
PMP COST FORMULAE
Bhaskara Reddy Sannapureddy
 
Project monitoring & Earned Value Analysis
Project monitoring & Earned Value AnalysisProject monitoring & Earned Value Analysis
Project monitoring & Earned Value Analysis
BECM, RUET, Bangladesh
 
Project Cost Management - PMP preparation course
Project Cost Management - PMP preparation courseProject Cost Management - PMP preparation course
Project Cost Management - PMP preparation course
Vladimir Vujovic
 
EVA - Metrics.ppt
EVA - Metrics.pptEVA - Metrics.ppt
EVA - Metrics.ppt
NivethaSampath3
 
Cost Controlling And Forecasting of Project.pdf
Cost Controlling And Forecasting of Project.pdfCost Controlling And Forecasting of Project.pdf
Cost Controlling And Forecasting of Project.pdf
Nabeel Ahmad
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost ManagementSerdar Temiz
 
Basics of EVM.pdf
Basics of  EVM.pdfBasics of  EVM.pdf
Basics of EVM.pdf
sajidkhan82714
 
PM - EVM - Dr Najam Abbas - OHT 1.pdf
PM - EVM - Dr Najam Abbas - OHT 1.pdfPM - EVM - Dr Najam Abbas - OHT 1.pdf
PM - EVM - Dr Najam Abbas - OHT 1.pdf
Najm Naqvi
 
Pmp cost chapter 7
Pmp cost chapter 7Pmp cost chapter 7
Pmp cost chapter 7
Ahmed Elshaboury,PMP,LEED GA
 
Earned Value Analysis in Project Management — an Easy Cheat Sheet 🡆 http://b...
Earned Value Analysis in Project Management — an Easy Cheat Sheet  🡆 http://b...Earned Value Analysis in Project Management — an Easy Cheat Sheet  🡆 http://b...
Earned Value Analysis in Project Management — an Easy Cheat Sheet 🡆 http://b...
Tipsographic . com
 
Earned Value AnalysisTracking Project ProgressWh.docx
Earned Value AnalysisTracking Project ProgressWh.docxEarned Value AnalysisTracking Project ProgressWh.docx
Earned Value AnalysisTracking Project ProgressWh.docx
sagarlesley
 
Track Project Performance - Earned Value Management
Track Project Performance - Earned Value ManagementTrack Project Performance - Earned Value Management
Track Project Performance - Earned Value Management
Baroness PM
 
Evm.calculations.Summary sheet
Evm.calculations.Summary sheetEvm.calculations.Summary sheet
Evm.calculations.Summary sheet
Essam Lotffy, PMP®, CCP®
 
Project Management: Cost Management Knowledge Area
Project Management: Cost Management Knowledge AreaProject Management: Cost Management Knowledge Area
Project Management: Cost Management Knowledge Area
Joshua Render
 
COST MANAGEMENT REPORT
COST MANAGEMENT REPORT COST MANAGEMENT REPORT
COST MANAGEMENT REPORT
Jo Balucanag - Bitonio
 
An introduction to project accounting
An introduction to project accountingAn introduction to project accounting
An introduction to project accounting
Association for Project Management
 
cost-managementtttttttttttttttttttttttttttttt.ppt
cost-managementtttttttttttttttttttttttttttttt.pptcost-managementtttttttttttttttttttttttttttttt.ppt
cost-managementtttttttttttttttttttttttttttttt.ppt
RedhaElhuni
 
Projects Control Using Earned Value Techniques - Part One
Projects Control Using Earned Value Techniques - Part OneProjects Control Using Earned Value Techniques - Part One
Projects Control Using Earned Value Techniques - Part One
Waleed Hamdy Albana
 

Similar to Earned value analysis (20)

5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
5. PAE AcFn621 Ch-5 Execution and Monitoring.ppt
 
Project Management EVM & SCBA
Project Management EVM & SCBAProject Management EVM & SCBA
Project Management EVM & SCBA
 
PMP COST FORMULAE
PMP COST FORMULAEPMP COST FORMULAE
PMP COST FORMULAE
 
Project monitoring & Earned Value Analysis
Project monitoring & Earned Value AnalysisProject monitoring & Earned Value Analysis
Project monitoring & Earned Value Analysis
 
Project Cost Management - PMP preparation course
Project Cost Management - PMP preparation courseProject Cost Management - PMP preparation course
Project Cost Management - PMP preparation course
 
EVA - Metrics.ppt
EVA - Metrics.pptEVA - Metrics.ppt
EVA - Metrics.ppt
 
Cost Controlling And Forecasting of Project.pdf
Cost Controlling And Forecasting of Project.pdfCost Controlling And Forecasting of Project.pdf
Cost Controlling And Forecasting of Project.pdf
 
Project Cost Management
Project Cost ManagementProject Cost Management
Project Cost Management
 
Basics of EVM.pdf
Basics of  EVM.pdfBasics of  EVM.pdf
Basics of EVM.pdf
 
PM - EVM - Dr Najam Abbas - OHT 1.pdf
PM - EVM - Dr Najam Abbas - OHT 1.pdfPM - EVM - Dr Najam Abbas - OHT 1.pdf
PM - EVM - Dr Najam Abbas - OHT 1.pdf
 
Pmp cost chapter 7
Pmp cost chapter 7Pmp cost chapter 7
Pmp cost chapter 7
 
Earned Value Analysis in Project Management — an Easy Cheat Sheet 🡆 http://b...
Earned Value Analysis in Project Management — an Easy Cheat Sheet  🡆 http://b...Earned Value Analysis in Project Management — an Easy Cheat Sheet  🡆 http://b...
Earned Value Analysis in Project Management — an Easy Cheat Sheet 🡆 http://b...
 
Earned Value AnalysisTracking Project ProgressWh.docx
Earned Value AnalysisTracking Project ProgressWh.docxEarned Value AnalysisTracking Project ProgressWh.docx
Earned Value AnalysisTracking Project ProgressWh.docx
 
Track Project Performance - Earned Value Management
Track Project Performance - Earned Value ManagementTrack Project Performance - Earned Value Management
Track Project Performance - Earned Value Management
 
Evm.calculations.Summary sheet
Evm.calculations.Summary sheetEvm.calculations.Summary sheet
Evm.calculations.Summary sheet
 
Project Management: Cost Management Knowledge Area
Project Management: Cost Management Knowledge AreaProject Management: Cost Management Knowledge Area
Project Management: Cost Management Knowledge Area
 
COST MANAGEMENT REPORT
COST MANAGEMENT REPORT COST MANAGEMENT REPORT
COST MANAGEMENT REPORT
 
An introduction to project accounting
An introduction to project accountingAn introduction to project accounting
An introduction to project accounting
 
cost-managementtttttttttttttttttttttttttttttt.ppt
cost-managementtttttttttttttttttttttttttttttt.pptcost-managementtttttttttttttttttttttttttttttt.ppt
cost-managementtttttttttttttttttttttttttttttt.ppt
 
Projects Control Using Earned Value Techniques - Part One
Projects Control Using Earned Value Techniques - Part OneProjects Control Using Earned Value Techniques - Part One
Projects Control Using Earned Value Techniques - Part One
 

Recently uploaded

COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdfCOLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
Kamal Acharya
 
TECHNICAL TRAINING MANUAL GENERAL FAMILIARIZATION COURSE
TECHNICAL TRAINING MANUAL   GENERAL FAMILIARIZATION COURSETECHNICAL TRAINING MANUAL   GENERAL FAMILIARIZATION COURSE
TECHNICAL TRAINING MANUAL GENERAL FAMILIARIZATION COURSE
DuvanRamosGarzon1
 
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
H.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdfH.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdf
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
MLILAB
 
road safety engineering r s e unit 3.pdf
road safety engineering  r s e unit 3.pdfroad safety engineering  r s e unit 3.pdf
road safety engineering r s e unit 3.pdf
VENKATESHvenky89705
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
TeeVichai
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
Neometrix_Engineering_Pvt_Ltd
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
Kamal Acharya
 
ASME IX(9) 2007 Full Version .pdf
ASME IX(9)  2007 Full Version       .pdfASME IX(9)  2007 Full Version       .pdf
ASME IX(9) 2007 Full Version .pdf
AhmedHussein950959
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
SamSarthak3
 
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxCFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
R&R Consult
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
seandesed
 
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
MdTanvirMahtab2
 
ethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.pptethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.ppt
Jayaprasanna4
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
Massimo Talia
 
Quality defects in TMT Bars, Possible causes and Potential Solutions.
Quality defects in TMT Bars, Possible causes and Potential Solutions.Quality defects in TMT Bars, Possible causes and Potential Solutions.
Quality defects in TMT Bars, Possible causes and Potential Solutions.
PrashantGoswami42
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
obonagu
 
Courier management system project report.pdf
Courier management system project report.pdfCourier management system project report.pdf
Courier management system project report.pdf
Kamal Acharya
 
The Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdfThe Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdf
Pipe Restoration Solutions
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Sreedhar Chowdam
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
bakpo1
 

Recently uploaded (20)

COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdfCOLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
 
TECHNICAL TRAINING MANUAL GENERAL FAMILIARIZATION COURSE
TECHNICAL TRAINING MANUAL   GENERAL FAMILIARIZATION COURSETECHNICAL TRAINING MANUAL   GENERAL FAMILIARIZATION COURSE
TECHNICAL TRAINING MANUAL GENERAL FAMILIARIZATION COURSE
 
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
H.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdfH.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdf
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
 
road safety engineering r s e unit 3.pdf
road safety engineering  r s e unit 3.pdfroad safety engineering  r s e unit 3.pdf
road safety engineering r s e unit 3.pdf
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
 
ASME IX(9) 2007 Full Version .pdf
ASME IX(9)  2007 Full Version       .pdfASME IX(9)  2007 Full Version       .pdf
ASME IX(9) 2007 Full Version .pdf
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
 
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptxCFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
CFD Simulation of By-pass Flow in a HRSG module by R&R Consult.pptx
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
 
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
Industrial Training at Shahjalal Fertilizer Company Limited (SFCL)
 
ethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.pptethical hacking-mobile hacking methods.ppt
ethical hacking-mobile hacking methods.ppt
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
 
Quality defects in TMT Bars, Possible causes and Potential Solutions.
Quality defects in TMT Bars, Possible causes and Potential Solutions.Quality defects in TMT Bars, Possible causes and Potential Solutions.
Quality defects in TMT Bars, Possible causes and Potential Solutions.
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
 
Courier management system project report.pdf
Courier management system project report.pdfCourier management system project report.pdf
Courier management system project report.pdf
 
The Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdfThe Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdf
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
 

Earned value analysis

  • 1. Earned Value Analysis By Er. NikhilRaj BAC BUDGETED AT COMPLETION PV PLANNED VALUE EV EARNED VALUE SV SCHEDULE VARIANCE CV COST VARIANCE SPI SCHEDULE PERFORMANCE INDEX CPI COST PERFORMANCE INDEX EAC ESTIMATE AT COMPLETION ETC ESTIMATE TO COMPLETION VAC VARIANCE AT COMPLETION 1/21/2016 1all rights reserved to www.tutomaash.com | any queries can be mailed to tutomaash@gmail.com Performance measuring system | Forecasting system
  • 2. Contents • What is earned value? • Why earned value? • EVM practiced industries • Application example • Application of same example in primavera p6 • Generation of financial s-curve 1/21/2016 2
  • 3. Definition Earned value management (EVM) is a methodology that combines scope, schedule, and resource measurements to assess project performance and progress. It is a commonly used method of performance measurement for projects. It integrates the scope baseline with the cost baseline, along with the schedule baseline, to form the performance baseline, which helps the project management team assess and measure project performance and progress - PMBOK 5th Edition Pg.217 1/21/2016 3
  • 4. Why EVM? Quantify and measure program/contract performance, Provide an early warning system for deviation from a baseline, Mitigate risks associated with cost and schedule overruns, Provide a means to forecast final cost and schedule outcomes 1/21/2016 4
  • 5. EVM practiced industries Department of Defense (DoD) The Federal government Construction IT sector Commercial sector R&D Aerospace 1/21/2016 5
  • 6. Example 2 weeks into the project Ms Ann completed 35MILES Also spent $15500 “Calculate the Performance” Imagine Ms Ann is the project manager of 100 miles road work She must finish the project in 5 weeks She can spent $10000/week PLANNED ACTUAL 2W 4W 3W 2W 1W 5W 1/21/2016 6
  • 7. PLANNED VS ACTUAL TOTAL PROJECT BUDGET=$50000 PLAN (TIME) W1 W2 W3 W4 W5 PLAN (COST) $10000 $20000 PV $30000 $40000 $50000 BAC PLAN (%COMPLETE) 20% 20MILES 40% 40 MILES 60% 60 MILES 80% 80 MILES 100% 100 MILES ACTUAL (TIME) W1 W2 W3 W4 W5 ACTUAL (COST) $15500 AC ACTUAL (%COMPLETE) 35% 35 MILES 1/21/2016 7
  • 8. NAME DEFINITION EQUATION VALUE 2nd week INTERPRETATION BAC | BUDGETED AT COMPLETION The value of total planned work, the project cost baseline $50000 PV | PLANNED VALUE COST The value of the work planned to be completed to a point in time, usually the data date, or project completion $20000 EV | EARNED VALUE COST The planned value of all the work completed (earned) to a point in time, usually the data date, without reference to actual costs $17500 AC | ACTUAL COST The actual cost of all the work completed to a point in time, usually the data date $15500 CV | COST VARIANCE The difference between the value of work completed to a point in time, usually the data date, and the actual costs to the same point in time CV = EV – AC $2000 Positive = Under planned cost Neutral = On planned cost Negative = Over planned cost SV | SCHEDULE VARIANCE The difference between the work completed to a point in time, and the work planned to be completed to the same point in time. SV = EV – PV -$2500 Positive = Ahead of Schedule Neutral = On schedule Negative = Behind Schedule CPI | COST PERFORMANCE INDEX A measure of the cost efficiency of budgeted resources expressed as the ratio of earned value to actual cost. CPI = EV/AC 1.129 >1.0 = Under planned cost Exactly 1.0 = On planned cost <1.0 = Over planned cost SPI | SCHEDULE PERFORMANCE INDEX A measure of schedule efficiency expressed as the ratio of earned value to planned value SPI = EV/PV 0.875 >1.0 = Ahead of schedule Exactly 1.0 = On schedule <1.0 = Behind schedule VALUESCALCULATED USINGEQUATION VALUES FROM ACTUAL VALUES FROM PLAN 1/21/2016 8
  • 9. Project forecast 2WBAC= $50000 (Planned budget) EAC= $44287 (Forecasted Budget calculated Based On 2nd week actual values) ETC= EAC-AC =$28786 (money to finish project)AC= $15500 1/21/2016 9
  • 10. NAME DEFINITION EQUATION VALUE 2nd week EAC | ESTIMATE AT COMPLETION If the CPI is expected to be the same for the remainder of the project, EAC can be calculated using EAC = BAC/CPI $44286.979 If future work will be accomplished at the planned rate, use: EAC = AC + BAC – EV $48000 If the initial plan is no longer valid, use: EAC = AC + Bottom-up ETC If both the CPI and SPI influence the remaining work, use EAC = AC + [(BAC – EV)/(CPI x SPI)] $48398.899 ETC | ESTIMATE TO COMPLETION Assuming work is proceeding on plan, the cost of completing the remaining authorized work can be calculated using: ETC = EAC – AC $28786 Reestimate the remaining work from the bottom up ETC = Reestimate VAC | VARIANCE AT COMPLETION The estimated difference in cost at the completion of the project. Positive = Under planned cost Neutral = On planned cost Negative = Over planned cost VAC = BAC – EAC $5713.021 1/21/2016 10 FORECASTEDVALUES
  • 11. See Mix in Action! https://mix.office.com/watch/1otxpj7hz6kbx (Copy the link and paste into your browser. Or, when in a slide show, click the photo.) 1/21/2016 11
  • 12. Get the add-in Office Mix Learn more at http://aka.ms/officemix 1/21/2016