International)
 The pricing of coal was controlled by the Central Government since 1945 under Colliery Control
Order of 1945 under section 4 .
 The price notification had been amended in December 1995, January 1996 and April 1996 to
enhance the differential between run of mine, steam and slack coal, to meet the increase in
transportation charges .
 Following the recommendations of Bureau of Industrial Costs and Prices (BICP), a decision was
taken by the Government to deregulate the prices of all grades of coking coal and A, B, & C
grades of non-coking coal and this decision was implemented with effect from 22.3.96.
 In March,1996,the Government gradually deregulate
the price of the various types and grades of coal.
 Later in 2000, the coal pricing was totally
deregulated after the Colliery Control Order, 2000
and was decided by Coal India Limited.
 Under the Colliery Control Order, 2000 the Central
Government has no power to fix the prices of coal.
Coal Pricing History
Date Category of Coal Prices
Deregulated
March
22,1996
‱ Non-coking Grades: A,B&C
‱ Coking Coal & Semi/Weekly
Coking Coal
March
12,1997
‱ Non-coking Grades: D
‱ Hard Coke & Soft Coke
‱ CIL is allowed to revise the price
of the non-coking coal every 6
months.
January
01,2000
‱ CIL free to decide the price of
coal.
De-regulation Stages of Coal pricing
Source: CIL
 The price of the coal depend on the input cost, mining cost, inflation and other factor.
 Since complete deregulation of pricing with effect from January 1, 2000, there have been five
revisions in notified coal prices: (i)January 31, 2001, (ii) June 15, 2004, (iii) December 12, 2007,
(iv) October 16, 2009, and (v) February 27, 2011.
 The average price increase was approximately 8.5%, 16.2%, 10.0% and 11.0%, respectively.
 On an annualized basis, the increase in the price of coal from January 2000 to March 31, 2010 was
4.9% which is lower than average inflation rates in India in this period.
 The pricing of the coal is done on useful heat value (UHV) basis till Dec,2011 and from Jan,2012, the
pricing mechanism changed to the Gross Calorific value(GCV).
 The Price regulation has obvious ramifications to competitiveness in the sector.
 However, the Ministry of Power has been writing to the Department of Coal that in the absence of a
regulatory mechanism, the prevailing monopoly situation in the coal market will lead to arbitrary
increase in price levels affecting adversely the cost of generation and thereby electricity tariff which
has direct impact on the national economy.
 The Ministry of Power has been pressing for appointing an independent regulatory body for price
determination. Several State Governments and State Electricity Boards/ Undertakings have also
raised the issue.
 In view of the above, the Tariff Commission is being involved in pricing of coal for the Power Sector
and to suggest modalities for pricing of coal for other sectors.
Coal Pricing History
 Coal Pricing ,at present , is fixed by coal ministry in consultation with Coal India Ltd.
( CIL ) & Singareni Collieries Company ( SCCL ) . The price are determined on the
basis of cost incurred in Coal Production from different mines.
Coal Pricing
 The expert committee on Integrated Energy Policy headed by Kirit Parikh,
has recommended setting up of an independent Coal Regulator to replace
government committees for determine coal prices for different user
industries.
STEP-I: An weighted average price (WAP) calculation for all
mines (UG/OC) together, as applicable.
WAP is calculated by taking sample opencast and
underground mines in a certain ratio and taking average
cost for opencast mine and corresponding cost for
underground mines
Guidelines of BICP to determine Coal Price
STEP II: Addition of other cost elements to WAP.
Other cost elements are Interest on Working
capital, Interest on Term Loan; and post tax return
on equity. These element are calculated on the Net
Block Per Tone basis.
STEP III: Summation of I & II above and Distribution of the
average price among various grades.
Guidelines of BICP to determine Coal Price
STEP-IV: Normative correction of the costs based on norms
to derive fair prices developed by BICP(Bureau of
Industrial Costs and Prices ) or CMPDIL (Central
Mine Planning & Design Institute Limited).
 To achieve uniformity of prices among different mines of
same Coal Companies, BICP used norms for price
finalizations (its own norms as also CMPDI norms)
 For this purpose Normative levels of production, Stripping
Ratio, Annual Capacity, Interest, Power consumption,
Consumption of explosives and detonators, Requirement
of Working capital etc were prescribed.
Guidelines of BICP to determine Coal Price
STEP V: Grade wise distribution of cost & price fixation
for different Grades of Coal and Classes of
Mines.
Guidelines of BICP to determine Coal Price
Example for Indian Coal pricing
447 476 507 520
2254
2584
2660
2796
660 715 738 745
FY08 FY09 FY10 FY11
Open Cast Under Ground Over All
Under ground mining is 5 times costlier than
open cast mining.
Given that 90% of coal production is open-cast
only & the rest from under-ground.
The average unit cost of coal production for
CIL comes out to be Rs.745.06(app) per tonne
in FY11.
This is just an example and while calculation
other factors are also been considered as
explained earlier in the presentation.
The flaw in the calculation here is that
assumption made here of 10% from
underground mining is normally lower than
that.
This shows that the maximum difference
between assumed and actual underground
mining is the extra profit of CIL.
Cost of Coal Production by CIL (in Rs./Tonne)
Source: CIL & Infraline Research
The price of coal delivered shall be –
A. Basic Price
+
B. Other Charges
+
C. Statutory Charges
Typical Price Clause of Coal Supply Agreement
I. EXISTING PRICING STRUCTURE
Under price notifications
OR
II. COAL PRICE UNDER DE-CONTROL REGIME
with price escalation provision
A. Basic Price of Coal
i. Transportation Charges
+
ii. Sizing/Crushing Charges
+
iii. Rapid Loading Charge
+
iv . Washing Charges
B. Other Charges
 Where coal is transported by the Seller beyond the distance of 3 Kms from the pit-
head to the delivery/unloading point.
 The Purchaser shall pay transportation charges as applicable from time to time.
 Coal is classified in the (sub-section 150) of the freight charges of the Indian
railways. The charges for the coal transportation as per the distance is as shown
below:
1. Transportation Charges
Distance (KM) Class 150 (Rs/Ton)
1-100 150.20
101-125 177.20
126-150 206.00
151-175 230.90
501-550 631.20
551-600 685.10
1001-1100 1214.30
1101-1200 1320.20
3001-3500 2902.70
Source: Ministry of Railways
 Where the coal is crushed by mechanical means for limiting the top size to
200mm – 250mm.- depending on Coal Agreement.
 The Purchaser shall pay sizing/crushing charges as applicable from time to
time.
 Sizing charges of Rs. 35/- per tonne for limiting the top size of coal to 250 mm
by mechanical or manual means, are included in the run of mine price.
 However, if top sizes further limited to smaller size e.g. 100/50 mm, then Rs.
55/- per tonne may be levied.
2. Sizing/Crushing Charges
 Where coal is loaded through Rapid Loading System either into Indian
Railways system or into the Purchaser’s own MGR.
 Purchaser shall pay Rapid Loading charges as applicable from time to time.
 The price of Rapid Loading of coal is determined by mutual agreement
between the two party. (Coal producer and Coal consumer).
 Where coal is loaded, either into Indian Railways system or into the
purchasers’ own system of transport, through high capacity loading system
with a nominal capacity of 3500 tonnes per hour or more, additional charge of
Rs.20.00 per tonne shall be levied for such loading.
3. Rapid Loading Charges
4. Washing Charges
 It is the process of cleaning of coal prior to it’s use.
 It includes sizing, removal of rock originating from mining roof, removal of ash
and sulfur minerals, drying to remove surface moisture and blending of different
coals to achieve desired physical and chemical properties.
 The cost of washing of coal varies from one playersto other player.
the approx cost of coal washing is around
Rs. 120/ton.
 The “Statutory Charges” shall comprise-
 royalties; (A+B*Run of Mine Price)
Where A =70 and B= 5% of run of mine price of coal
 National Clean Energy Cess; (Rs 50 Fixed)
 Stowing Exercise Duties (SED); for developing of abandoned mines ; (Rs. 20 Fixed)
 CST ;(@ 4% of ROM Price of coal);
Exercise Duty; (@5% of ROM coal);
 levies etc., if any,
 It shall be payable by the Purchaser Subject to :
Provisions of relevant statute ;
not included in the basic price
STATUTORY CHARGES
Yearly Escalated Price of coal in terms of Rs /tonne may be determined by the following
formula:
Let P0 = Price of Coal on a mutually agreed date to be termed as “Base Date” (from which
date price escalation to be calculated for the first time or any subsequent times)
P1= Escalated price of Coal to be calculated annually on the date of revision.
P1 = P0  dP1  dP2
where
dP1 = Price escalation Part-1
Applicable on components of cost of Coal comprising : Salaries & Wages, Explosives,
Power, Other items including Stores & Spares which are linked to published indices/
SEB tariff notifications
dP2 = Price escalation Part –2
Applicable on components of cost of Coal comprising : Depreciation, Interest and Pre-
tax return which are based on Net Block per tonne of Coal and are related to the
capacity
FORMULA FOR COAL PRICE ESCALATION
Component Symbol Rs/ tonne
(effective
from 1.4.
1997)
Rs/ tonne
(effective
from
1.4.200
1)
Rs/ tonne
(effective
from
01.01.2
012)
Basic Raw coal Price (BP)
+ Crushing Charges (CR)
PR 332
20
431
20
600
55
Statutory Charges on Raw Coal (Ro)
=Royalty
+ (SE)= SED
PSr 50
3.50
50
3.50
70
10
Add: Adjustment due to Yield
Factor (Yc)
Extra 83.78 154.97
-
Total Raw Coal Component Price  489.28 659.47 From CIL,SCCL
Washing charges =
+ Wage Revision Adjustment
PW 225.72 268.48
+2.04
-
Total Price of Washed Coal (P) 715.00 930.00
-
COAL PRICING METHODOLOGY
Pricing effective from Jan 2012 (1/2)
Grade GCV Bands(Kcal/Kg)
Power utilities (including
IPPs),fertilizers,Defense
sector (Rs./Te)
Sector other than Power
utilities (including IPPs ),
fertilizers,Defense
sector(Rs./Te)
G1 Exceeding 7000 * *
G2 Exceeding 6700 and not exceeding
7000
4870 4870
G3 Exceeding 6400 and not exceeding
6700
4420 4420
G4 Exceeding 6100 and not exceeding
6400
3970 3970
G5 Exceeding 5800 and not exceeding
6100
2800 2800
G6 Exceeding 5500 and not exceeding
5800
1450 1960
G7 Exceeding 5200 and not exceeding
5500
1270 1720
Pit head Run On Mine non-coking Coal Prices as per CIL effective from Jan 1,2012 Based on GCV
Note *:1.For GCV exceeding 7000 Kcal/Kg, the price shall be increase by Rs.150/-per tonne over & above price for GCV
band (6700-7000) Kcal/Kg, for increase in GCV by every 100 Kcal/Kg.
2.For WCL,there shall be 10% add on over & above price mentioned for GCV bands not exceeding 5800Kcal/Kg
and below. Source: CIL
Switching to GCV mechanism would characterize coal in more efficient manner
Grade GCV Bands(Kcal/Kg)
Power utilities (including
IPPs),fertilizers,Defence
sector(Rs./Te)
Sector other than Power
utilities (including
IPPs),fertilizers,Defence
sector(Rs./Te)
G8 Exceeding 4900 and not exceeding
5200
1140 1540
G9 Exceeding 4600 and not exceeding
4900
880 1180
G10 Exceeding 4300 and not exceeding
4600
780 1050
G11 Exceeding 4000 and not exceeding
4300
640 870
G12 Exceeding 3700 and not exceeding
4000
600 810
G13 Exceeding 3400 and not exceeding
3700
550 740
G14 Exceeding 3100 and not exceeding
3400
500 680
G15 Exceeding 2800 and not exceeding
3100
460 620
G16 Exceeding 2500 and not exceeding
2800
410 550
G17 Exceeding 2200 and not exceeding
2500
360 490
Pricing effective from Jan 2012 (2/2)
RAIL MODE - ZSNT PRICES W.E.F.15.06.2012
CHP
BASI
C
SIZI
NG
BASI
C
TOTA
L
Prem
ium
ROYA
LTY
ON
BASIC
ROM
PRICE
SED
ROYAL
TY ON
PREMI
UM
ENGI
NE
SHNT
G
CHGS
+
ADDL.
CR
FLS
STC
FORE
ST
PERM
IT
FEE
PWBFSC
CLEA
N
ENE
RGY
CES
S
ED
TAXAB
LAE
AMOU
NT
VAT
5%
TOTA
L
PRIC
E
WITH
VAT
5%
CST
2%
TOTA
L
PRIC
E
WITH
CST
2%
RCHP
G7
CRR
1,840.
00
60.0
0
1,900.
00 570 257.6 10 79.8 15 15 83 10 0 48 50
179.
30
3,217.7
0
160.
89
3,378
.59
64.3
5
3,282.
06
RCHP
G13
CRR 690
60.0
0
750.0
0 300 96.6 10 42 15 15 83 10 0 48 50
82.1
8
1,501.7
8
75.0
9
1,576
.86
30.0
4
1,531.
81
YLD
CHP
G13
CRR 690
60.0
0
750.0
0 300 96.6 10 42 15 15 96 10 0 48 50
82.9
6
1,515.5
6
75.7
8
1,591
.33
30.3
1
1,545.
87
Coal Transportation from WCL Site(A Screenshot)
INTERNATIONAL COAL PRICING
 Quite Deregulated Market across the world.
 Various Coal Price Indices are used across the world to
benchmark their cost of production and thereby making it
competitive with the other prominent markets across the
world.
Market Structure
Demand
EU 25
Eastern Europe
Mediterranean area
North, Central and
South America
Major suppliers
Colombia
SA
Russia
Poland
Venezuela
USA
Major suppliers
Australia
Indonesia
China
Russia
Vietnam
Demand
Japan
South Korea
Taiwan
India
China
Price Formation
Market leaders
‱SA
‱Colombia
‱Russia
Marginal suppliers
‱Poland
‱USA
‱Australia
FOB prices
Freight Rates
Currency relations
Buyer and seller’s market
Market leaders
‱Australia
‱Indonesia
‱China
Marginal suppliers
‱SA
‱Russia
Atlantic market Pacific market
Coal Transportation across the Globe
INTERNATIONAL COAL INDICES
API 2 Index (an average of the Argus cif Rotterdam assessment and
McCloskey’s northwest European steam coal marker)-imported into
northwest Europe
API 4 Index (an average of the Argus fob Richards Bay assessment and McCloskey’s fob
Richards Bay marker.) - exported out of Richards Bay, South Africa.
API 5 Index(an average of the Argus fob Newcastle 5,500 kcal/kg assessment
and the equivalent from IHS McCloskey.)-exports of 5,500 kcal/kg NAR (net as
received), high-ash coal from Australia
API 6 Index (an average of the Argus fob Newcastle 6,000 kcal/kg assessment and the
equivalent from IHS McCloskey.) -
API 8 Index (an average of the Argus 5,500 kcal/kg cfr south China price
assessment, and the IHS McCloskey/Xinhua Infolink south China marker) -
price for 5,500 kcal/kg NAR coal delivered to south China.
The ICI (Indonesian Coal Index) reflects the spot price of five key grades of Indonesian
coal — 6,500, 5,800, 5,000, 4,200 and 3,400 kcal/kg GAR
 Ensure price revisions.
 Suggest measures for Setting Coal prices.
 Regulate trading margins.
 Ensure that price discovery through e- auctions is free of distortions.
 Ensure coal supply to the power sectors under commercially driven
Long – term Fuel Supply & Transport Agreements ( FSTAs)
Functions or Need of Regulators
 To deliver a sustained growth of 8% through 2031, India
would, in the very least, need to grow its primary energy supply
by 3 to 4 times and electricity supply by 5 to 7 times of today’s
consumption.
 By 2031-32 power generation capacities would have to increase
to 778095 MW and annual coal requirement would be 2040
MT
Future Prospects of Coal in India
PRICE DIFFERENTIAL BETWEEN INDIAN AND INTERNATIONAL COAL
Coal pricing(Domestic and International)

More Related Content

What's hot

Coal production and washing in india
Coal production and washing in india Coal production and washing in india
Coal production and washing in india INDRANEELA1
 
Coal India Limited-An Overview
Coal India Limited-An OverviewCoal India Limited-An Overview
Coal India Limited-An OverviewPranavkumar Jain
 
Coal industry
Coal industryCoal industry
Coal industrykamleshnpl
 
Transportation of coal ppt
Transportation of coal pptTransportation of coal ppt
Transportation of coal pptNaina Rajput
 
Doing Business With Coal India
Doing Business With Coal IndiaDoing Business With Coal India
Doing Business With Coal Indiapartha247
 
Northern Coalfields Limited Training report on Heavy Earth Moving And Mining ...
Northern Coalfields Limited Training report on Heavy Earth Moving And Mining ...Northern Coalfields Limited Training report on Heavy Earth Moving And Mining ...
Northern Coalfields Limited Training report on Heavy Earth Moving And Mining ...Saurabh Tripathi
 
Coal India limited .ppt
Coal India limited .pptCoal India limited .ppt
Coal India limited .pptProlaydey
 
Coal industry
Coal industryCoal industry
Coal industrykamleshnpl
 
PROJECT REPORT TATA STEEL- Rahul
PROJECT REPORT TATA STEEL- RahulPROJECT REPORT TATA STEEL- Rahul
PROJECT REPORT TATA STEEL- RahulRahul Singh
 
COAL INDIA
COAL INDIA COAL INDIA
COAL INDIA Akash Gupta
 
Coal India Limited case study - radhika lalit
Coal India Limited case study - radhika lalitCoal India Limited case study - radhika lalit
Coal India Limited case study - radhika lalitRadhika Kapoor Lalit
 
Oil & gas industry in india
Oil & gas industry in indiaOil & gas industry in india
Oil & gas industry in indiasuyash gunjal
 
Reasons for change in crude oil price
Reasons for change in crude oil price Reasons for change in crude oil price
Reasons for change in crude oil price Gurjit Kaur Kaler
 
Coal india limited_-_the_biggest_energy_provider_in_india
Coal india limited_-_the_biggest_energy_provider_in_indiaCoal india limited_-_the_biggest_energy_provider_in_india
Coal india limited_-_the_biggest_energy_provider_in_indiahapina
 
SWOT Analysis of Coal India
SWOT Analysis of Coal IndiaSWOT Analysis of Coal India
SWOT Analysis of Coal IndiaHimanshu Jain
 
Fuel supply agreement
Fuel supply agreementFuel supply agreement
Fuel supply agreement1ks06me005
 
Ia final presentation
Ia final presentationIa final presentation
Ia final presentationRAJESH KUMAR
 
Thar Coal, A Black Treasure OF Pakistan ( Series of Presentations, (No. 2/17)
Thar Coal, A Black Treasure OF Pakistan ( Series of Presentations, (No. 2/17)Thar Coal, A Black Treasure OF Pakistan ( Series of Presentations, (No. 2/17)
Thar Coal, A Black Treasure OF Pakistan ( Series of Presentations, (No. 2/17)Malik Tariq Sarwar Awan
 
Oil and gas industry ppt
Oil and gas industry pptOil and gas industry ppt
Oil and gas industry pptshalini ilavarapu
 

What's hot (20)

Coal production and washing in india
Coal production and washing in india Coal production and washing in india
Coal production and washing in india
 
Coal India Limited-An Overview
Coal India Limited-An OverviewCoal India Limited-An Overview
Coal India Limited-An Overview
 
Coal industry
Coal industryCoal industry
Coal industry
 
Transportation of coal ppt
Transportation of coal pptTransportation of coal ppt
Transportation of coal ppt
 
Doing Business With Coal India
Doing Business With Coal IndiaDoing Business With Coal India
Doing Business With Coal India
 
Northern Coalfields Limited Training report on Heavy Earth Moving And Mining ...
Northern Coalfields Limited Training report on Heavy Earth Moving And Mining ...Northern Coalfields Limited Training report on Heavy Earth Moving And Mining ...
Northern Coalfields Limited Training report on Heavy Earth Moving And Mining ...
 
Coal India limited .ppt
Coal India limited .pptCoal India limited .ppt
Coal India limited .ppt
 
Coal industry
Coal industryCoal industry
Coal industry
 
PROJECT REPORT TATA STEEL- Rahul
PROJECT REPORT TATA STEEL- RahulPROJECT REPORT TATA STEEL- Rahul
PROJECT REPORT TATA STEEL- Rahul
 
COAL INDIA
COAL INDIA COAL INDIA
COAL INDIA
 
Coal India Limited case study - radhika lalit
Coal India Limited case study - radhika lalitCoal India Limited case study - radhika lalit
Coal India Limited case study - radhika lalit
 
Oil & gas industry in india
Oil & gas industry in indiaOil & gas industry in india
Oil & gas industry in india
 
Reasons for change in crude oil price
Reasons for change in crude oil price Reasons for change in crude oil price
Reasons for change in crude oil price
 
Coal india limited_-_the_biggest_energy_provider_in_india
Coal india limited_-_the_biggest_energy_provider_in_indiaCoal india limited_-_the_biggest_energy_provider_in_india
Coal india limited_-_the_biggest_energy_provider_in_india
 
SWOT Analysis of Coal India
SWOT Analysis of Coal IndiaSWOT Analysis of Coal India
SWOT Analysis of Coal India
 
Fuel supply agreement
Fuel supply agreementFuel supply agreement
Fuel supply agreement
 
Coal major trading ports & routes
Coal major trading ports & routesCoal major trading ports & routes
Coal major trading ports & routes
 
Ia final presentation
Ia final presentationIa final presentation
Ia final presentation
 
Thar Coal, A Black Treasure OF Pakistan ( Series of Presentations, (No. 2/17)
Thar Coal, A Black Treasure OF Pakistan ( Series of Presentations, (No. 2/17)Thar Coal, A Black Treasure OF Pakistan ( Series of Presentations, (No. 2/17)
Thar Coal, A Black Treasure OF Pakistan ( Series of Presentations, (No. 2/17)
 
Oil and gas industry ppt
Oil and gas industry pptOil and gas industry ppt
Oil and gas industry ppt
 

Viewers also liked

Coal Supply Chain Example
Coal Supply Chain ExampleCoal Supply Chain Example
Coal Supply Chain ExampleEMBS2007
 
Coal Transportation Methods
Coal Transportation Methods Coal Transportation Methods
Coal Transportation Methods Shoniza Irfan
 
Asian Coal Benchmarks and Risk Management Report
Asian Coal Benchmarks and Risk Management ReportAsian Coal Benchmarks and Risk Management Report
Asian Coal Benchmarks and Risk Management Reportkasper1
 
Formation, Occurrence, Extraction and Refining of coal and petroleum.
Formation, Occurrence, Extraction and Refining of coal and petroleum.Formation, Occurrence, Extraction and Refining of coal and petroleum.
Formation, Occurrence, Extraction and Refining of coal and petroleum.Satya Patra
 
Coal n petroleum
Coal n petroleumCoal n petroleum
Coal n petroleumTamannac
 
20.06.2013 Coal pricing outlook: Key trends for Mongolia, William Wang
 20.06.2013 Coal pricing outlook: Key trends for Mongolia, William Wang 20.06.2013 Coal pricing outlook: Key trends for Mongolia, William Wang
20.06.2013 Coal pricing outlook: Key trends for Mongolia, William WangThe Business Council of Mongolia
 
Coal presentation
Coal presentationCoal presentation
Coal presentationchartprophet
 
Preparing Detailed Project Report and Presenting Business Plan to Investors
Preparing Detailed Project Report  and Presenting Business Plan to InvestorsPreparing Detailed Project Report  and Presenting Business Plan to Investors
Preparing Detailed Project Report and Presenting Business Plan to InvestorsRahul Sharma
 
Coal and Ash Handling
Coal and Ash HandlingCoal and Ash Handling
Coal and Ash HandlingVanita Thakkar
 

Viewers also liked (15)

Coal Supply Chain Example
Coal Supply Chain ExampleCoal Supply Chain Example
Coal Supply Chain Example
 
Coal Transportation Methods
Coal Transportation Methods Coal Transportation Methods
Coal Transportation Methods
 
Asian Coal Benchmarks and Risk Management Report
Asian Coal Benchmarks and Risk Management ReportAsian Coal Benchmarks and Risk Management Report
Asian Coal Benchmarks and Risk Management Report
 
Svalbard Coal
Svalbard CoalSvalbard Coal
Svalbard Coal
 
Carbon uptake
Carbon uptakeCarbon uptake
Carbon uptake
 
Formation, Occurrence, Extraction and Refining of coal and petroleum.
Formation, Occurrence, Extraction and Refining of coal and petroleum.Formation, Occurrence, Extraction and Refining of coal and petroleum.
Formation, Occurrence, Extraction and Refining of coal and petroleum.
 
Coal n petroleum
Coal n petroleumCoal n petroleum
Coal n petroleum
 
Coal
CoalCoal
Coal
 
20.06.2013 Coal pricing outlook: Key trends for Mongolia, William Wang
 20.06.2013 Coal pricing outlook: Key trends for Mongolia, William Wang 20.06.2013 Coal pricing outlook: Key trends for Mongolia, William Wang
20.06.2013 Coal pricing outlook: Key trends for Mongolia, William Wang
 
Coal presentation
Coal presentationCoal presentation
Coal presentation
 
HEDGING
HEDGINGHEDGING
HEDGING
 
Preparing Detailed Project Report and Presenting Business Plan to Investors
Preparing Detailed Project Report  and Presenting Business Plan to InvestorsPreparing Detailed Project Report  and Presenting Business Plan to Investors
Preparing Detailed Project Report and Presenting Business Plan to Investors
 
Strabismus
StrabismusStrabismus
Strabismus
 
Coal and Ash Handling
Coal and Ash HandlingCoal and Ash Handling
Coal and Ash Handling
 
Coal classification
Coal classificationCoal classification
Coal classification
 

Similar to Coal pricing(Domestic and International)

Coal Block Auction- A Boon for Consumer or Just a Boom
Coal Block Auction- A Boon for Consumer or Just a BoomCoal Block Auction- A Boon for Consumer or Just a Boom
Coal Block Auction- A Boon for Consumer or Just a BoomSoumya Ranjan Parida
 
SVCE Initiation of Coverage
SVCE Initiation of CoverageSVCE Initiation of Coverage
SVCE Initiation of CoverageMohab Yamany, CMA
 
Coal_Gasification_Overview_1712844563.pdf
Coal_Gasification_Overview_1712844563.pdfCoal_Gasification_Overview_1712844563.pdf
Coal_Gasification_Overview_1712844563.pdfVenkatsubramanian84
 
Business Prospects of Floating LNG
Business Prospects of Floating LNGBusiness Prospects of Floating LNG
Business Prospects of Floating LNGRonak Sani
 
ARCC initiation of coverage
ARCC initiation of coverageARCC initiation of coverage
ARCC initiation of coverageMohab Yamany, CMA
 
Satyamurty_Coal_Beneficiation_21_8_07.pdf
Satyamurty_Coal_Beneficiation_21_8_07.pdfSatyamurty_Coal_Beneficiation_21_8_07.pdf
Satyamurty_Coal_Beneficiation_21_8_07.pdfBhawnaRighteous
 
Review of Indian coal sector
Review of Indian coal sectorReview of Indian coal sector
Review of Indian coal sectorManoj Jhawar
 
Presentation coal oil and gas scenario in the context of power sector-by-rake...
Presentation coal oil and gas scenario in the context of power sector-by-rake...Presentation coal oil and gas scenario in the context of power sector-by-rake...
Presentation coal oil and gas scenario in the context of power sector-by-rake...Prashantkarhade72
 
Coal in india 2015
Coal in india 2015Coal in india 2015
Coal in india 2015Angel Dass
 
PCI update May 2012 Ross Stainlay
PCI update May 2012  Ross Stainlay PCI update May 2012  Ross Stainlay
PCI update May 2012 Ross Stainlay Ross Stainlay
 
Managing fuel supply & uncertainty in India
Managing fuel supply & uncertainty in IndiaManaging fuel supply & uncertainty in India
Managing fuel supply & uncertainty in IndiaIPPAI
 
Coal linkages auctioning release v 7.0
Coal linkages auctioning release v 7.0Coal linkages auctioning release v 7.0
Coal linkages auctioning release v 7.0Ajay Katekhaye
 
Report on Natural Gas- Distribution and Pricing.pdf
Report on Natural Gas- Distribution and Pricing.pdfReport on Natural Gas- Distribution and Pricing.pdf
Report on Natural Gas- Distribution and Pricing.pdfASHISH GOEL
 
Understanding the Coal Conundrum?
Understanding the Coal Conundrum?Understanding the Coal Conundrum?
Understanding the Coal Conundrum?Yogesh Upadhyaya
 
21.02.1013 Current state of coal sector of Mongolia and it's future trends, D...
21.02.1013 Current state of coal sector of Mongolia and it's future trends, D...21.02.1013 Current state of coal sector of Mongolia and it's future trends, D...
21.02.1013 Current state of coal sector of Mongolia and it's future trends, D...The Business Council of Mongolia
 
Rational of fixed charge capping as per the DBFOO document
Rational of fixed charge capping as per the DBFOO documentRational of fixed charge capping as per the DBFOO document
Rational of fixed charge capping as per the DBFOO documentSoumya Ranjan Parida
 

Similar to Coal pricing(Domestic and International) (20)

Coal Block Auction- A Boon for Consumer or Just a Boom
Coal Block Auction- A Boon for Consumer or Just a BoomCoal Block Auction- A Boon for Consumer or Just a Boom
Coal Block Auction- A Boon for Consumer or Just a Boom
 
FAQ’s Sl. No. 2 : Regarding Power Procurement Costs
FAQ’s Sl. No. 2 : Regarding Power Procurement CostsFAQ’s Sl. No. 2 : Regarding Power Procurement Costs
FAQ’s Sl. No. 2 : Regarding Power Procurement Costs
 
SVCE Initiation of Coverage
SVCE Initiation of CoverageSVCE Initiation of Coverage
SVCE Initiation of Coverage
 
Black is Back
Black is BackBlack is Back
Black is Back
 
Coal policy
Coal policyCoal policy
Coal policy
 
Coal_Gasification_Overview_1712844563.pdf
Coal_Gasification_Overview_1712844563.pdfCoal_Gasification_Overview_1712844563.pdf
Coal_Gasification_Overview_1712844563.pdf
 
Business Prospects of Floating LNG
Business Prospects of Floating LNGBusiness Prospects of Floating LNG
Business Prospects of Floating LNG
 
pmicg-jp.pdf
pmicg-jp.pdfpmicg-jp.pdf
pmicg-jp.pdf
 
ARCC initiation of coverage
ARCC initiation of coverageARCC initiation of coverage
ARCC initiation of coverage
 
Satyamurty_Coal_Beneficiation_21_8_07.pdf
Satyamurty_Coal_Beneficiation_21_8_07.pdfSatyamurty_Coal_Beneficiation_21_8_07.pdf
Satyamurty_Coal_Beneficiation_21_8_07.pdf
 
Review of Indian coal sector
Review of Indian coal sectorReview of Indian coal sector
Review of Indian coal sector
 
Presentation coal oil and gas scenario in the context of power sector-by-rake...
Presentation coal oil and gas scenario in the context of power sector-by-rake...Presentation coal oil and gas scenario in the context of power sector-by-rake...
Presentation coal oil and gas scenario in the context of power sector-by-rake...
 
Coal in india 2015
Coal in india 2015Coal in india 2015
Coal in india 2015
 
PCI update May 2012 Ross Stainlay
PCI update May 2012  Ross Stainlay PCI update May 2012  Ross Stainlay
PCI update May 2012 Ross Stainlay
 
Managing fuel supply & uncertainty in India
Managing fuel supply & uncertainty in IndiaManaging fuel supply & uncertainty in India
Managing fuel supply & uncertainty in India
 
Coal linkages auctioning release v 7.0
Coal linkages auctioning release v 7.0Coal linkages auctioning release v 7.0
Coal linkages auctioning release v 7.0
 
Report on Natural Gas- Distribution and Pricing.pdf
Report on Natural Gas- Distribution and Pricing.pdfReport on Natural Gas- Distribution and Pricing.pdf
Report on Natural Gas- Distribution and Pricing.pdf
 
Understanding the Coal Conundrum?
Understanding the Coal Conundrum?Understanding the Coal Conundrum?
Understanding the Coal Conundrum?
 
21.02.1013 Current state of coal sector of Mongolia and it's future trends, D...
21.02.1013 Current state of coal sector of Mongolia and it's future trends, D...21.02.1013 Current state of coal sector of Mongolia and it's future trends, D...
21.02.1013 Current state of coal sector of Mongolia and it's future trends, D...
 
Rational of fixed charge capping as per the DBFOO document
Rational of fixed charge capping as per the DBFOO documentRational of fixed charge capping as per the DBFOO document
Rational of fixed charge capping as per the DBFOO document
 

More from Rahul Sharma

Latest Mergers and Acquisitions
Latest Mergers and AcquisitionsLatest Mergers and Acquisitions
Latest Mergers and AcquisitionsRahul Sharma
 
Consumer protection Act
Consumer protection ActConsumer protection Act
Consumer protection ActRahul Sharma
 
Companies act 1956
Companies act 1956Companies act 1956
Companies act 1956Rahul Sharma
 
JSW Steel Ltd.
JSW Steel Ltd.JSW Steel Ltd.
JSW Steel Ltd.Rahul Sharma
 
Need of Power?
Need of Power?Need of Power?
Need of Power?Rahul Sharma
 
Unit trust of india
Unit trust of indiaUnit trust of india
Unit trust of indiaRahul Sharma
 
Growth of indian money market
Growth of indian money marketGrowth of indian money market
Growth of indian money marketRahul Sharma
 
Managing IT security and Business Ethics
Managing IT security and Business EthicsManaging IT security and Business Ethics
Managing IT security and Business EthicsRahul Sharma
 
Strategic Fit
Strategic FitStrategic Fit
Strategic FitRahul Sharma
 
Group 7 load forecasting&harmonics final ppt
Group   7 load forecasting&harmonics final pptGroup   7 load forecasting&harmonics final ppt
Group 7 load forecasting&harmonics final pptRahul Sharma
 

More from Rahul Sharma (10)

Latest Mergers and Acquisitions
Latest Mergers and AcquisitionsLatest Mergers and Acquisitions
Latest Mergers and Acquisitions
 
Consumer protection Act
Consumer protection ActConsumer protection Act
Consumer protection Act
 
Companies act 1956
Companies act 1956Companies act 1956
Companies act 1956
 
JSW Steel Ltd.
JSW Steel Ltd.JSW Steel Ltd.
JSW Steel Ltd.
 
Need of Power?
Need of Power?Need of Power?
Need of Power?
 
Unit trust of india
Unit trust of indiaUnit trust of india
Unit trust of india
 
Growth of indian money market
Growth of indian money marketGrowth of indian money market
Growth of indian money market
 
Managing IT security and Business Ethics
Managing IT security and Business EthicsManaging IT security and Business Ethics
Managing IT security and Business Ethics
 
Strategic Fit
Strategic FitStrategic Fit
Strategic Fit
 
Group 7 load forecasting&harmonics final ppt
Group   7 load forecasting&harmonics final pptGroup   7 load forecasting&harmonics final ppt
Group 7 load forecasting&harmonics final ppt
 

Recently uploaded

Benefits and Challenges of Using Open Educational Resources
Benefits and Challenges of Using Open Educational ResourcesBenefits and Challenges of Using Open Educational Resources
Benefits and Challenges of Using Open Educational Resourcesdimpy50
 
Solid waste management & Types of Basic civil Engineering notes by DJ Sir.pptx
Solid waste management & Types of Basic civil Engineering notes by DJ Sir.pptxSolid waste management & Types of Basic civil Engineering notes by DJ Sir.pptx
Solid waste management & Types of Basic civil Engineering notes by DJ Sir.pptxDenish Jangid
 
Synthetic Fiber Construction in lab .pptx
Synthetic Fiber Construction in lab .pptxSynthetic Fiber Construction in lab .pptx
Synthetic Fiber Construction in lab .pptxPavel ( NSTU)
 
Matatag-Curriculum and the 21st Century Skills Presentation.pptx
Matatag-Curriculum and the 21st Century Skills Presentation.pptxMatatag-Curriculum and the 21st Century Skills Presentation.pptx
Matatag-Curriculum and the 21st Century Skills Presentation.pptxJenilouCasareno
 
PART A. Introduction to Costumer Service
PART A. Introduction to Costumer ServicePART A. Introduction to Costumer Service
PART A. Introduction to Costumer ServicePedroFerreira53928
 
Students, digital devices and success - Andreas Schleicher - 27 May 2024..pptx
Students, digital devices and success - Andreas Schleicher - 27 May 2024..pptxStudents, digital devices and success - Andreas Schleicher - 27 May 2024..pptx
Students, digital devices and success - Andreas Schleicher - 27 May 2024..pptxEduSkills OECD
 
Sectors of the Indian Economy - Class 10 Study Notes pdf
Sectors of the Indian Economy - Class 10 Study Notes pdfSectors of the Indian Economy - Class 10 Study Notes pdf
Sectors of the Indian Economy - Class 10 Study Notes pdfVivekanand Anglo Vedic Academy
 
Basic Civil Engineering Notes of Chapter-6, Topic- Ecosystem, Biodiversity G...
Basic Civil Engineering Notes of Chapter-6,  Topic- Ecosystem, Biodiversity G...Basic Civil Engineering Notes of Chapter-6,  Topic- Ecosystem, Biodiversity G...
Basic Civil Engineering Notes of Chapter-6, Topic- Ecosystem, Biodiversity G...Denish Jangid
 
Jose-Rizal-and-Philippine-Nationalism-National-Symbol-2.pptx
Jose-Rizal-and-Philippine-Nationalism-National-Symbol-2.pptxJose-Rizal-and-Philippine-Nationalism-National-Symbol-2.pptx
Jose-Rizal-and-Philippine-Nationalism-National-Symbol-2.pptxricssacare
 
678020731-Sumas-y-Restas-Para-Colorear.pdf
678020731-Sumas-y-Restas-Para-Colorear.pdf678020731-Sumas-y-Restas-Para-Colorear.pdf
678020731-Sumas-y-Restas-Para-Colorear.pdfCarlosHernanMontoyab2
 
50 ĐỀ LUYỆN THI IOE LỚP 9 - NĂM HỌC 2022-2023 (CÓ LINK HÌNH, FILE AUDIO VÀ ĐÁ...
50 ĐỀ LUYỆN THI IOE LỚP 9 - NĂM HỌC 2022-2023 (CÓ LINK HÌNH, FILE AUDIO VÀ ĐÁ...50 ĐỀ LUYỆN THI IOE LỚP 9 - NĂM HỌC 2022-2023 (CÓ LINK HÌNH, FILE AUDIO VÀ ĐÁ...
50 ĐỀ LUYỆN THI IOE LỚP 9 - NĂM HỌC 2022-2023 (CÓ LINK HÌNH, FILE AUDIO VÀ ĐÁ...Nguyen Thanh Tu Collection
 
How to Create Map Views in the Odoo 17 ERP
How to Create Map Views in the Odoo 17 ERPHow to Create Map Views in the Odoo 17 ERP
How to Create Map Views in the Odoo 17 ERPCeline George
 
Salient features of Environment protection Act 1986.pptx
Salient features of Environment protection Act 1986.pptxSalient features of Environment protection Act 1986.pptx
Salient features of Environment protection Act 1986.pptxakshayaramakrishnan21
 
B.ed spl. HI pdusu exam paper-2023-24.pdf
B.ed spl. HI pdusu exam paper-2023-24.pdfB.ed spl. HI pdusu exam paper-2023-24.pdf
B.ed spl. HI pdusu exam paper-2023-24.pdfSpecial education needs
 
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaasiemaillard
 
How to Break the cycle of negative Thoughts
How to Break the cycle of negative ThoughtsHow to Break the cycle of negative Thoughts
How to Break the cycle of negative ThoughtsCol Mukteshwar Prasad
 
The Roman Empire A Historical Colossus.pdf
The Roman Empire A Historical Colossus.pdfThe Roman Empire A Historical Colossus.pdf
The Roman Empire A Historical Colossus.pdfkaushalkr1407
 
Overview on Edible Vaccine: Pros & Cons with Mechanism
Overview on Edible Vaccine: Pros & Cons with MechanismOverview on Edible Vaccine: Pros & Cons with Mechanism
Overview on Edible Vaccine: Pros & Cons with MechanismDeeptiGupta154
 
How libraries can support authors with open access requirements for UKRI fund...
How libraries can support authors with open access requirements for UKRI fund...How libraries can support authors with open access requirements for UKRI fund...
How libraries can support authors with open access requirements for UKRI fund...Jisc
 
UNIT – IV_PCI Complaints: Complaints and evaluation of complaints, Handling o...
UNIT – IV_PCI Complaints: Complaints and evaluation of complaints, Handling o...UNIT – IV_PCI Complaints: Complaints and evaluation of complaints, Handling o...
UNIT – IV_PCI Complaints: Complaints and evaluation of complaints, Handling o...Sayali Powar
 

Recently uploaded (20)

Benefits and Challenges of Using Open Educational Resources
Benefits and Challenges of Using Open Educational ResourcesBenefits and Challenges of Using Open Educational Resources
Benefits and Challenges of Using Open Educational Resources
 
Solid waste management & Types of Basic civil Engineering notes by DJ Sir.pptx
Solid waste management & Types of Basic civil Engineering notes by DJ Sir.pptxSolid waste management & Types of Basic civil Engineering notes by DJ Sir.pptx
Solid waste management & Types of Basic civil Engineering notes by DJ Sir.pptx
 
Synthetic Fiber Construction in lab .pptx
Synthetic Fiber Construction in lab .pptxSynthetic Fiber Construction in lab .pptx
Synthetic Fiber Construction in lab .pptx
 
Matatag-Curriculum and the 21st Century Skills Presentation.pptx
Matatag-Curriculum and the 21st Century Skills Presentation.pptxMatatag-Curriculum and the 21st Century Skills Presentation.pptx
Matatag-Curriculum and the 21st Century Skills Presentation.pptx
 
PART A. Introduction to Costumer Service
PART A. Introduction to Costumer ServicePART A. Introduction to Costumer Service
PART A. Introduction to Costumer Service
 
Students, digital devices and success - Andreas Schleicher - 27 May 2024..pptx
Students, digital devices and success - Andreas Schleicher - 27 May 2024..pptxStudents, digital devices and success - Andreas Schleicher - 27 May 2024..pptx
Students, digital devices and success - Andreas Schleicher - 27 May 2024..pptx
 
Sectors of the Indian Economy - Class 10 Study Notes pdf
Sectors of the Indian Economy - Class 10 Study Notes pdfSectors of the Indian Economy - Class 10 Study Notes pdf
Sectors of the Indian Economy - Class 10 Study Notes pdf
 
Basic Civil Engineering Notes of Chapter-6, Topic- Ecosystem, Biodiversity G...
Basic Civil Engineering Notes of Chapter-6,  Topic- Ecosystem, Biodiversity G...Basic Civil Engineering Notes of Chapter-6,  Topic- Ecosystem, Biodiversity G...
Basic Civil Engineering Notes of Chapter-6, Topic- Ecosystem, Biodiversity G...
 
Jose-Rizal-and-Philippine-Nationalism-National-Symbol-2.pptx
Jose-Rizal-and-Philippine-Nationalism-National-Symbol-2.pptxJose-Rizal-and-Philippine-Nationalism-National-Symbol-2.pptx
Jose-Rizal-and-Philippine-Nationalism-National-Symbol-2.pptx
 
678020731-Sumas-y-Restas-Para-Colorear.pdf
678020731-Sumas-y-Restas-Para-Colorear.pdf678020731-Sumas-y-Restas-Para-Colorear.pdf
678020731-Sumas-y-Restas-Para-Colorear.pdf
 
50 ĐỀ LUYỆN THI IOE LỚP 9 - NĂM HỌC 2022-2023 (CÓ LINK HÌNH, FILE AUDIO VÀ ĐÁ...
50 ĐỀ LUYỆN THI IOE LỚP 9 - NĂM HỌC 2022-2023 (CÓ LINK HÌNH, FILE AUDIO VÀ ĐÁ...50 ĐỀ LUYỆN THI IOE LỚP 9 - NĂM HỌC 2022-2023 (CÓ LINK HÌNH, FILE AUDIO VÀ ĐÁ...
50 ĐỀ LUYỆN THI IOE LỚP 9 - NĂM HỌC 2022-2023 (CÓ LINK HÌNH, FILE AUDIO VÀ ĐÁ...
 
How to Create Map Views in the Odoo 17 ERP
How to Create Map Views in the Odoo 17 ERPHow to Create Map Views in the Odoo 17 ERP
How to Create Map Views in the Odoo 17 ERP
 
Salient features of Environment protection Act 1986.pptx
Salient features of Environment protection Act 1986.pptxSalient features of Environment protection Act 1986.pptx
Salient features of Environment protection Act 1986.pptx
 
B.ed spl. HI pdusu exam paper-2023-24.pdf
B.ed spl. HI pdusu exam paper-2023-24.pdfB.ed spl. HI pdusu exam paper-2023-24.pdf
B.ed spl. HI pdusu exam paper-2023-24.pdf
 
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
 
How to Break the cycle of negative Thoughts
How to Break the cycle of negative ThoughtsHow to Break the cycle of negative Thoughts
How to Break the cycle of negative Thoughts
 
The Roman Empire A Historical Colossus.pdf
The Roman Empire A Historical Colossus.pdfThe Roman Empire A Historical Colossus.pdf
The Roman Empire A Historical Colossus.pdf
 
Overview on Edible Vaccine: Pros & Cons with Mechanism
Overview on Edible Vaccine: Pros & Cons with MechanismOverview on Edible Vaccine: Pros & Cons with Mechanism
Overview on Edible Vaccine: Pros & Cons with Mechanism
 
How libraries can support authors with open access requirements for UKRI fund...
How libraries can support authors with open access requirements for UKRI fund...How libraries can support authors with open access requirements for UKRI fund...
How libraries can support authors with open access requirements for UKRI fund...
 
UNIT – IV_PCI Complaints: Complaints and evaluation of complaints, Handling o...
UNIT – IV_PCI Complaints: Complaints and evaluation of complaints, Handling o...UNIT – IV_PCI Complaints: Complaints and evaluation of complaints, Handling o...
UNIT – IV_PCI Complaints: Complaints and evaluation of complaints, Handling o...
 

Coal pricing(Domestic and International)

  • 1. Presented By- Anil Kumar Rahul Sharma Himanshu Aggarwal Md. Imtiaz COAL PRICING (Domestic & International)
  • 2.  The pricing of coal was controlled by the Central Government since 1945 under Colliery Control Order of 1945 under section 4 .  The price notification had been amended in December 1995, January 1996 and April 1996 to enhance the differential between run of mine, steam and slack coal, to meet the increase in transportation charges .  Following the recommendations of Bureau of Industrial Costs and Prices (BICP), a decision was taken by the Government to deregulate the prices of all grades of coking coal and A, B, & C grades of non-coking coal and this decision was implemented with effect from 22.3.96.  In March,1996,the Government gradually deregulate the price of the various types and grades of coal.  Later in 2000, the coal pricing was totally deregulated after the Colliery Control Order, 2000 and was decided by Coal India Limited.  Under the Colliery Control Order, 2000 the Central Government has no power to fix the prices of coal. Coal Pricing History Date Category of Coal Prices Deregulated March 22,1996 ‱ Non-coking Grades: A,B&C ‱ Coking Coal & Semi/Weekly Coking Coal March 12,1997 ‱ Non-coking Grades: D ‱ Hard Coke & Soft Coke ‱ CIL is allowed to revise the price of the non-coking coal every 6 months. January 01,2000 ‱ CIL free to decide the price of coal. De-regulation Stages of Coal pricing Source: CIL
  • 3.  The price of the coal depend on the input cost, mining cost, inflation and other factor.  Since complete deregulation of pricing with effect from January 1, 2000, there have been five revisions in notified coal prices: (i)January 31, 2001, (ii) June 15, 2004, (iii) December 12, 2007, (iv) October 16, 2009, and (v) February 27, 2011.  The average price increase was approximately 8.5%, 16.2%, 10.0% and 11.0%, respectively.  On an annualized basis, the increase in the price of coal from January 2000 to March 31, 2010 was 4.9% which is lower than average inflation rates in India in this period.  The pricing of the coal is done on useful heat value (UHV) basis till Dec,2011 and from Jan,2012, the pricing mechanism changed to the Gross Calorific value(GCV).  The Price regulation has obvious ramifications to competitiveness in the sector.  However, the Ministry of Power has been writing to the Department of Coal that in the absence of a regulatory mechanism, the prevailing monopoly situation in the coal market will lead to arbitrary increase in price levels affecting adversely the cost of generation and thereby electricity tariff which has direct impact on the national economy.  The Ministry of Power has been pressing for appointing an independent regulatory body for price determination. Several State Governments and State Electricity Boards/ Undertakings have also raised the issue.  In view of the above, the Tariff Commission is being involved in pricing of coal for the Power Sector and to suggest modalities for pricing of coal for other sectors. Coal Pricing History
  • 4.  Coal Pricing ,at present , is fixed by coal ministry in consultation with Coal India Ltd. ( CIL ) & Singareni Collieries Company ( SCCL ) . The price are determined on the basis of cost incurred in Coal Production from different mines. Coal Pricing
  • 5.  The expert committee on Integrated Energy Policy headed by Kirit Parikh, has recommended setting up of an independent Coal Regulator to replace government committees for determine coal prices for different user industries.
  • 6. STEP-I: An weighted average price (WAP) calculation for all mines (UG/OC) together, as applicable. WAP is calculated by taking sample opencast and underground mines in a certain ratio and taking average cost for opencast mine and corresponding cost for underground mines Guidelines of BICP to determine Coal Price
  • 7. STEP II: Addition of other cost elements to WAP. Other cost elements are Interest on Working capital, Interest on Term Loan; and post tax return on equity. These element are calculated on the Net Block Per Tone basis. STEP III: Summation of I & II above and Distribution of the average price among various grades. Guidelines of BICP to determine Coal Price
  • 8. STEP-IV: Normative correction of the costs based on norms to derive fair prices developed by BICP(Bureau of Industrial Costs and Prices ) or CMPDIL (Central Mine Planning & Design Institute Limited).  To achieve uniformity of prices among different mines of same Coal Companies, BICP used norms for price finalizations (its own norms as also CMPDI norms)  For this purpose Normative levels of production, Stripping Ratio, Annual Capacity, Interest, Power consumption, Consumption of explosives and detonators, Requirement of Working capital etc were prescribed. Guidelines of BICP to determine Coal Price
  • 9. STEP V: Grade wise distribution of cost & price fixation for different Grades of Coal and Classes of Mines. Guidelines of BICP to determine Coal Price
  • 10. Example for Indian Coal pricing 447 476 507 520 2254 2584 2660 2796 660 715 738 745 FY08 FY09 FY10 FY11 Open Cast Under Ground Over All Under ground mining is 5 times costlier than open cast mining. Given that 90% of coal production is open-cast only & the rest from under-ground. The average unit cost of coal production for CIL comes out to be Rs.745.06(app) per tonne in FY11. This is just an example and while calculation other factors are also been considered as explained earlier in the presentation. The flaw in the calculation here is that assumption made here of 10% from underground mining is normally lower than that. This shows that the maximum difference between assumed and actual underground mining is the extra profit of CIL. Cost of Coal Production by CIL (in Rs./Tonne) Source: CIL & Infraline Research
  • 11. The price of coal delivered shall be – A. Basic Price + B. Other Charges + C. Statutory Charges Typical Price Clause of Coal Supply Agreement
  • 12. I. EXISTING PRICING STRUCTURE Under price notifications OR II. COAL PRICE UNDER DE-CONTROL REGIME with price escalation provision A. Basic Price of Coal
  • 13. i. Transportation Charges + ii. Sizing/Crushing Charges + iii. Rapid Loading Charge + iv . Washing Charges B. Other Charges
  • 14.  Where coal is transported by the Seller beyond the distance of 3 Kms from the pit- head to the delivery/unloading point.  The Purchaser shall pay transportation charges as applicable from time to time.  Coal is classified in the (sub-section 150) of the freight charges of the Indian railways. The charges for the coal transportation as per the distance is as shown below: 1. Transportation Charges Distance (KM) Class 150 (Rs/Ton) 1-100 150.20 101-125 177.20 126-150 206.00 151-175 230.90 501-550 631.20 551-600 685.10 1001-1100 1214.30 1101-1200 1320.20 3001-3500 2902.70 Source: Ministry of Railways
  • 15.  Where the coal is crushed by mechanical means for limiting the top size to 200mm – 250mm.- depending on Coal Agreement.  The Purchaser shall pay sizing/crushing charges as applicable from time to time.  Sizing charges of Rs. 35/- per tonne for limiting the top size of coal to 250 mm by mechanical or manual means, are included in the run of mine price.  However, if top sizes further limited to smaller size e.g. 100/50 mm, then Rs. 55/- per tonne may be levied. 2. Sizing/Crushing Charges
  • 16.  Where coal is loaded through Rapid Loading System either into Indian Railways system or into the Purchaser’s own MGR.  Purchaser shall pay Rapid Loading charges as applicable from time to time.  The price of Rapid Loading of coal is determined by mutual agreement between the two party. (Coal producer and Coal consumer).  Where coal is loaded, either into Indian Railways system or into the purchasers’ own system of transport, through high capacity loading system with a nominal capacity of 3500 tonnes per hour or more, additional charge of Rs.20.00 per tonne shall be levied for such loading. 3. Rapid Loading Charges
  • 17. 4. Washing Charges  It is the process of cleaning of coal prior to it’s use.  It includes sizing, removal of rock originating from mining roof, removal of ash and sulfur minerals, drying to remove surface moisture and blending of different coals to achieve desired physical and chemical properties.  The cost of washing of coal varies from one playersto other player. the approx cost of coal washing is around Rs. 120/ton.
  • 18.  The “Statutory Charges” shall comprise-  royalties; (A+B*Run of Mine Price) Where A =70 and B= 5% of run of mine price of coal  National Clean Energy Cess; (Rs 50 Fixed)  Stowing Exercise Duties (SED); for developing of abandoned mines ; (Rs. 20 Fixed)  CST ;(@ 4% of ROM Price of coal); Exercise Duty; (@5% of ROM coal);  levies etc., if any,  It shall be payable by the Purchaser Subject to : Provisions of relevant statute ; not included in the basic price STATUTORY CHARGES
  • 19. Yearly Escalated Price of coal in terms of Rs /tonne may be determined by the following formula: Let P0 = Price of Coal on a mutually agreed date to be termed as “Base Date” (from which date price escalation to be calculated for the first time or any subsequent times) P1= Escalated price of Coal to be calculated annually on the date of revision. P1 = P0  dP1  dP2 where dP1 = Price escalation Part-1 Applicable on components of cost of Coal comprising : Salaries & Wages, Explosives, Power, Other items including Stores & Spares which are linked to published indices/ SEB tariff notifications dP2 = Price escalation Part –2 Applicable on components of cost of Coal comprising : Depreciation, Interest and Pre- tax return which are based on Net Block per tonne of Coal and are related to the capacity FORMULA FOR COAL PRICE ESCALATION
  • 20. Component Symbol Rs/ tonne (effective from 1.4. 1997) Rs/ tonne (effective from 1.4.200 1) Rs/ tonne (effective from 01.01.2 012) Basic Raw coal Price (BP) + Crushing Charges (CR) PR 332 20 431 20 600 55 Statutory Charges on Raw Coal (Ro) =Royalty + (SE)= SED PSr 50 3.50 50 3.50 70 10 Add: Adjustment due to Yield Factor (Yc) Extra 83.78 154.97 - Total Raw Coal Component Price  489.28 659.47 From CIL,SCCL Washing charges = + Wage Revision Adjustment PW 225.72 268.48 +2.04 - Total Price of Washed Coal (P) 715.00 930.00 - COAL PRICING METHODOLOGY
  • 21. Pricing effective from Jan 2012 (1/2) Grade GCV Bands(Kcal/Kg) Power utilities (including IPPs),fertilizers,Defense sector (Rs./Te) Sector other than Power utilities (including IPPs ), fertilizers,Defense sector(Rs./Te) G1 Exceeding 7000 * * G2 Exceeding 6700 and not exceeding 7000 4870 4870 G3 Exceeding 6400 and not exceeding 6700 4420 4420 G4 Exceeding 6100 and not exceeding 6400 3970 3970 G5 Exceeding 5800 and not exceeding 6100 2800 2800 G6 Exceeding 5500 and not exceeding 5800 1450 1960 G7 Exceeding 5200 and not exceeding 5500 1270 1720 Pit head Run On Mine non-coking Coal Prices as per CIL effective from Jan 1,2012 Based on GCV Note *:1.For GCV exceeding 7000 Kcal/Kg, the price shall be increase by Rs.150/-per tonne over & above price for GCV band (6700-7000) Kcal/Kg, for increase in GCV by every 100 Kcal/Kg. 2.For WCL,there shall be 10% add on over & above price mentioned for GCV bands not exceeding 5800Kcal/Kg and below. Source: CIL Switching to GCV mechanism would characterize coal in more efficient manner
  • 22. Grade GCV Bands(Kcal/Kg) Power utilities (including IPPs),fertilizers,Defence sector(Rs./Te) Sector other than Power utilities (including IPPs),fertilizers,Defence sector(Rs./Te) G8 Exceeding 4900 and not exceeding 5200 1140 1540 G9 Exceeding 4600 and not exceeding 4900 880 1180 G10 Exceeding 4300 and not exceeding 4600 780 1050 G11 Exceeding 4000 and not exceeding 4300 640 870 G12 Exceeding 3700 and not exceeding 4000 600 810 G13 Exceeding 3400 and not exceeding 3700 550 740 G14 Exceeding 3100 and not exceeding 3400 500 680 G15 Exceeding 2800 and not exceeding 3100 460 620 G16 Exceeding 2500 and not exceeding 2800 410 550 G17 Exceeding 2200 and not exceeding 2500 360 490 Pricing effective from Jan 2012 (2/2)
  • 23. RAIL MODE - ZSNT PRICES W.E.F.15.06.2012 CHP BASI C SIZI NG BASI C TOTA L Prem ium ROYA LTY ON BASIC ROM PRICE SED ROYAL TY ON PREMI UM ENGI NE SHNT G CHGS + ADDL. CR FLS STC FORE ST PERM IT FEE PWBFSC CLEA N ENE RGY CES S ED TAXAB LAE AMOU NT VAT 5% TOTA L PRIC E WITH VAT 5% CST 2% TOTA L PRIC E WITH CST 2% RCHP G7 CRR 1,840. 00 60.0 0 1,900. 00 570 257.6 10 79.8 15 15 83 10 0 48 50 179. 30 3,217.7 0 160. 89 3,378 .59 64.3 5 3,282. 06 RCHP G13 CRR 690 60.0 0 750.0 0 300 96.6 10 42 15 15 83 10 0 48 50 82.1 8 1,501.7 8 75.0 9 1,576 .86 30.0 4 1,531. 81 YLD CHP G13 CRR 690 60.0 0 750.0 0 300 96.6 10 42 15 15 96 10 0 48 50 82.9 6 1,515.5 6 75.7 8 1,591 .33 30.3 1 1,545. 87 Coal Transportation from WCL Site(A Screenshot)
  • 24. INTERNATIONAL COAL PRICING  Quite Deregulated Market across the world.  Various Coal Price Indices are used across the world to benchmark their cost of production and thereby making it competitive with the other prominent markets across the world.
  • 25. Market Structure Demand EU 25 Eastern Europe Mediterranean area North, Central and South America Major suppliers Colombia SA Russia Poland Venezuela USA Major suppliers Australia Indonesia China Russia Vietnam Demand Japan South Korea Taiwan India China Price Formation Market leaders ‱SA ‱Colombia ‱Russia Marginal suppliers ‱Poland ‱USA ‱Australia FOB prices Freight Rates Currency relations Buyer and seller’s market Market leaders ‱Australia ‱Indonesia ‱China Marginal suppliers ‱SA ‱Russia Atlantic market Pacific market Coal Transportation across the Globe
  • 26. INTERNATIONAL COAL INDICES API 2 Index (an average of the Argus cif Rotterdam assessment and McCloskey’s northwest European steam coal marker)-imported into northwest Europe API 4 Index (an average of the Argus fob Richards Bay assessment and McCloskey’s fob Richards Bay marker.) - exported out of Richards Bay, South Africa. API 5 Index(an average of the Argus fob Newcastle 5,500 kcal/kg assessment and the equivalent from IHS McCloskey.)-exports of 5,500 kcal/kg NAR (net as received), high-ash coal from Australia API 6 Index (an average of the Argus fob Newcastle 6,000 kcal/kg assessment and the equivalent from IHS McCloskey.) - API 8 Index (an average of the Argus 5,500 kcal/kg cfr south China price assessment, and the IHS McCloskey/Xinhua Infolink south China marker) - price for 5,500 kcal/kg NAR coal delivered to south China. The ICI (Indonesian Coal Index) reflects the spot price of five key grades of Indonesian coal — 6,500, 5,800, 5,000, 4,200 and 3,400 kcal/kg GAR
  • 27.  Ensure price revisions.  Suggest measures for Setting Coal prices.  Regulate trading margins.  Ensure that price discovery through e- auctions is free of distortions.  Ensure coal supply to the power sectors under commercially driven Long – term Fuel Supply & Transport Agreements ( FSTAs) Functions or Need of Regulators
  • 28.  To deliver a sustained growth of 8% through 2031, India would, in the very least, need to grow its primary energy supply by 3 to 4 times and electricity supply by 5 to 7 times of today’s consumption.  By 2031-32 power generation capacities would have to increase to 778095 MW and annual coal requirement would be 2040 MT Future Prospects of Coal in India
  • 29. PRICE DIFFERENTIAL BETWEEN INDIAN AND INTERNATIONAL COAL