SlideShare a Scribd company logo
1
PREPARED BY : ASST. PROF. VATSAL D. PATEL
MAHATMA GANDHI INSTITUTE OF
TECHNICAL EDUCATION &
RESEARCH CENTRE, NAVSARI.
• Dewatering means removal of excess water from saturated
soil.
• it comes to
when the
Dewatering is a necessary process when many construction
projects, particularly construction is for underground
projects.
• Factors such as the type of soil and the nature of the construction site will all influence
which dewatering method will be best suited to the project.
6. Cement Grouting
7. Chemical Process
8. Freezing Process
9. Electro-Osmosis Method
1. Sumps And Ditches
2. Shallow Well System
3. Deep Well System
4. Well Point System
5. Vacuum Method
• It is the simplest and most commonly used
form of dewatering.
• In this method, shallow pits, called sumps are dug along
the periphery of the area and connected by drains of
semicircular in shape and 20 cm diameter.
• The water from the slopes
gravityand iscollected in
flows under
sumps from
which it is pumped out.
 A hole of 30 cm diameter or more is bored into the ground to a depth not more than 10 m
below the pump level. A strainer tube of 15 cm diameter is lowered in the bore hole having a
casing tube.
 A gravel filter is formed around the strainer tube by gradually removing the casing tube and
simultaneously pouring the filter well so formed.

The suction pipe from a number of such wells may be connected to one common header
connected to the pumping unit.
[A typical layout of a shallow well system]
This system is more suitable when the depth of excavation is more than the 16m or where
artesian water is present.
In this, 15 to 16 cm diameter hole is bored and a casing with a large screen is provided. A row
of well points is frequently installed at the toe of the side slope of the deep excavation.
A submersible pump is installed at the bottom of the well, of which the casing generally has a
minimum diameter of 150 mm. The discharge pipes from the submersible pumps of a number
of adjacent wells are connected to a common delivery main. The water is raised from the well
by a multi-staged pump.
[A typical layout of a deep well system]
• The main components of a well-point system are:
1. well points
2. Riser pipe
3. Swinger arm
4. Header pipe
5. pumps
• The well point is perforated pipe 5 to 8 CM in dia & 1m long
covered by cylindrical wire gauge screen known as strainer.
Pipes are jetted in the ground 1 to 2mt a part.
Well point → riser pipe → swinger arm → header.
It is suitable for lowering water table by 5 to 6 m in soil.
13
14
Multi-stage well point system is suitable for excavations up to 15 m.
When water table is greater than 6 m this method willuse.
In this method 2 or more rows of well point are installed at different elevation.
In this method wells are installed in 2 stages.
In 1st stage water table lowered by 5 m.
If required, then 3rd stage of well point can also be installed for further lower water table.
This method useful for up to 15 m. For up to 15th m deep well system will use.
17
is very rapid. The equipment is reasonably Simple
Advantages:
•Installation
and cheap.
•As water is filtered while removing from the ground, soil particles are not washed
away. Hence, there is no danger of subsidence of the surrounding ground.
•As the water is drawn away by well points from the excavation, the sides of
excavation are stabilized and steeper side slopes can be permitted.
Disadvantages:
•Single stage well point system is suitable for lowering water table by 5 to 6 m only. For
deeper excavations, where water table is to be lowered for a depth greater than 6 m, multi-
stage well point system is required.
•It is essential to continue pumping once it has been started until the excavation is
complete. If it is stopped in between, it may prove to be disastrous.
•In case of the ground consisting of stiff clay, gravel or boulders, well points are
installed in drilled holes, which increases the installation cost.
When draining is required for silt or clay which have size less than
0.05mm. That time vacuum pump system will require.
The process is as follows:
The well-points are driven and 25 CM dia is provided around the well point.
Installed in the ground by forcing a jet of water under sufficient pressure.
The sand of medium to coarse size is then forced into
this hole as rapidly as possible. This sand forms the filter medium.
In the upper most 600 mm to 900 mm, an impervious material such as clay is tamped to
form the seal the upper portion.
The pumping is then carried out by means of equipment capable of maintaining a vacuum
in the well-points and the surrounding filter.
In this way, the pressure around the well-points is reduced to a small fraction of the
atmospheric pressure. The ground is acted upon by the atmospheric pressure. Thus the soil
becomes consolidated under a pressure which is very nearly equal to the atmospheric.
In highly permeable cohesionless soil, the safety of the side slopes may be endangered
through the application of severe pumping. In such cases, especially if control of the
groundwater is required permanently, the methods of grouting can be used.
The main idea is to insert fine materials or chemicals around the excavation in order to
reduce the hydraulic conductivity of the surrounding soil to a minimum.
In other words, the grouting process creates an almost impervious curtain around the
excavation. The grouting is conducted using movable pipes with holes. The grout material
is injected under pressure as it flows outside the pipes through the holes to fill the voids of
the surrounding soil.
The material used for grouting may be clay, cement or special chemical compounds.
• The material commonly used for grout include:
1) Cement And Water
2) Cement, Rock Flour and Water
3) Cement, Clay and Water
4) Cement, Clay, Sand and Water
5) Asphalt
6) Clay And Water
7) Chemicals
• The desirable properties of chemical grouts:
1)It must be able to modify the properties of soil as desired
2)It may either increase the strength or decrease the permeability of soil
3)It must be cheap, non-toxic, non-explosive
4)It must be in the form of a liquid with low viscosity so that it can be readily placed
in the soil
5)It must be non-corrosive, so that it can be handled with common pumps and
piping
6)It must be possible to control the gel time by suitable means.
• Inorganic chemicals
Sodium silicate
Calcium chloride
Ligno-chrome
Ligno sulphate
They are called silicate grouts
They are cheaper
• Organic chemicals
Epoxy resins
Polyester resins
They are also called resin grouts
They possess advantage of low viscosity, precise control of gel time and high
strength
Soils that will not drain using conventional methods Typically a ground freezing system
consists of an array of freeze pipes.
That are installed into the ground around the perimeter of the excavation, usually in a
circular pattern.
A supermodel brine solution is pump through to freeze the pipes, which freezes the water
bearing soils around the pipes to create a frozen wall. Extreme care must be taken to make
sure that the freeze is complete because any groundwater seepage though the wall or from
below the excavation depth will have a sliding effect.
34
 The procedure:
A refrigeration plant of required installed near the site of work.
The large pipes of 100 mm to 150 mm diameter.
The distance between the pipes is about 1 m to 1.50 m.
The pipes are closed at the bottom.
The small pipes of 25mm to 50mm diametre are inserted into the large pipes open at the
bottom.
The cold liquid at a temperature of about -23°C to -30°C is then circulated through the
circuit.
The liquid comes through the small pipe and goes up through the large pipe.
This causes the ground to freeze around the pipes.
• This method is used for fine grained cohesive soils (such as clay), which can be drained or
stabilized using electric current. The method was developed by
L. Casagrande (1952).
• If direct current is passed between two electrodes driven into natural soil mass, the soil water
will travel` from the positive electrode (anode) to the negative electrode (cathode). The
cathode is made in the form of well point or metal tube for pumping out the seeping form of
well point or a metal tube for pumping out the seeping water.
• A steel rod, a pipe or steel piling of excavation can serve as the cathode. The arrangement of
electrodes is done in such a way that the natural direction of flow of water is reversed away
from the excavation, thereby increasing the strength of the soil and stability of the slope. The
potentials generally used in the process are from 40 to 180 volts, with electrode spacing of 4
to 5 meters.
The vibroflot is inserted into the ground and typically can be used to improve soil up to depths
of 150 feet. Vibroflotation utilizes water and the mechanical vibrations of the vibroflot to move
the particles into a denser state. Typical radial distances affected range from 5 to 15 feet (Bauer
Maschinen GmbH, 2012).
The vibroflot is suspended from a crane and seats on the surface of the ground that is to be
improved. To penetrate the material, the bottom jet is activated and the vibration begins. The
water saturates the material to create a “quick sand” condition (i.e. temporarily liquefying the
material), which allows the vibroflot to sink to the desired depth of improvement.
At that point, the bottom jet is stopped and the water is transferred to the upper jet. This is
done to create a saturated environment surrounding the vibroflot, thereby enhancing the
compaction of the material. The vibroflot remains at the desired depth of improvement until
the material reaches adequate density.
The density of the soil is measured by using the power input (via the electric current or
hydraulic pressure) as an index. As the material densifies, the vibroflot requires more
power to continue vibrating at which point pressure gauge displays a peak in required
power.
Once this point is reached, the vibroflot is raised one lift (generally ranging from 1 to 3
feet) and compaction ensues until the peak amperage or hydraulic pressure is reached once
again.
The vibroflotation process can offer the following benefits:
•When the process is done properly, it will reduce the possibility of differential settlements
that will improve the foundation condition of the proposed structure.
•It is the fastest and easiest way to improve soil when bottom layers of soil will not provide
good load bearing capacity.
•It is a great technology to improve harbor bottoms.
•On a cost-related standpoint, it helps improve thousands of cubic meters per day. It is
faster than piling.
•It can be done around existing structures without damaging them .
•It does not harm the environment. It improves the soil strata using its own characteristic
•No excavations are needed, reducing the hazards, contamination of soils and hauling
material out from the site.
METHOD CONDITIONS FOR SUITABILITY
1. Sumps and Ditches For shallow excavations in coarse
grained soils.
2. Well point system Suitable for lowering water table by 5-6 m
in soils
3. Bored well system For coarse grained soils and depth of
excavation more than 16 m
4. Vacuum method Draining silty sands and fine sands
5. Cement grouting For coarse materials or rocks with
cracks
6. Freezing process Suitable for excavations in water logged
soils
7. Electro-osmosis process Suitable for fine grained cohesive soils
such as clays
41

More Related Content

What's hot

Presentation edited final
Presentation edited finalPresentation edited final
Presentation edited final
Hikmat Ullah Amini
 
Presentation on well point system
Presentation on well point systemPresentation on well point system
Presentation on well point systemAnshuman Tyagi
 
Dewatering methods for excavations at construction sites
Dewatering methods for excavations at construction sitesDewatering methods for excavations at construction sites
Dewatering methods for excavations at construction sites
Abhay Shrivastava
 
Dewatering System
Dewatering SystemDewatering System
Dewatering System
nik kin
 
Civil Engineering-Dewatering
Civil Engineering-DewateringCivil Engineering-Dewatering
Civil Engineering-DewateringMoe Abadla
 
BCT Module 5 ground water excavation PART 4
BCT Module 5 ground water excavation PART 4BCT Module 5 ground water excavation PART 4
BCT Module 5 ground water excavation PART 4
Shree Swami atmanand saraswati inst. of technology, surat
 
Dewatering
DewateringDewatering
Dewatering
PrabhanjanThorat
 
Dewatering process and control in building projects
Dewatering process and control in building projectsDewatering process and control in building projects
Dewatering process and control in building projects
Umar Faruk
 
Groundwater Control Techniques for Tunnelling and Shaft Sinking
Groundwater Control Techniques for Tunnelling and Shaft SinkingGroundwater Control Techniques for Tunnelling and Shaft Sinking
Groundwater Control Techniques for Tunnelling and Shaft Sinking
Martin Preene
 
Construction dewatering
Construction dewateringConstruction dewatering
Construction dewatering
Shubham Parab
 
The Best Thing about Ground Freezing Technique
The Best Thing about Ground Freezing TechniqueThe Best Thing about Ground Freezing Technique
The Best Thing about Ground Freezing Technique
Darwin Jayson Mariano
 
Dewatering techniques
Dewatering techniquesDewatering techniques
Dewatering techniques
jamali husain
 
De watering-ppt
De watering-pptDe watering-ppt
De watering-ppt
Ghulam Mehdi Sahito
 
Study of Prefabricated Vertical Drains
Study of Prefabricated Vertical DrainsStudy of Prefabricated Vertical Drains
Study of Prefabricated Vertical Drains
NatarajaSaiCharan1
 
Methods of Dewatering
Methods of DewateringMethods of Dewatering
Methods of Dewatering
ajinkya gaikwad
 
Ground freezing
Ground freezing Ground freezing
Ground freezing
Mahesh Sharma
 
Construction dewatering technology data sheet
Construction dewatering technology data sheetConstruction dewatering technology data sheet
Construction dewatering technology data sheet
Groundwater Engineering Ltd
 
Collection and Conveyance of Water
Collection and Conveyance of WaterCollection and Conveyance of Water
Collection and Conveyance of Water
GAURAV. H .TANDON
 

What's hot (20)

Presentation edited final
Presentation edited finalPresentation edited final
Presentation edited final
 
Methods of Dewatering
Methods of DewateringMethods of Dewatering
Methods of Dewatering
 
Presentation on well point system
Presentation on well point systemPresentation on well point system
Presentation on well point system
 
Ground freezing..ll
Ground freezing..llGround freezing..ll
Ground freezing..ll
 
Dewatering methods for excavations at construction sites
Dewatering methods for excavations at construction sitesDewatering methods for excavations at construction sites
Dewatering methods for excavations at construction sites
 
Dewatering System
Dewatering SystemDewatering System
Dewatering System
 
Civil Engineering-Dewatering
Civil Engineering-DewateringCivil Engineering-Dewatering
Civil Engineering-Dewatering
 
BCT Module 5 ground water excavation PART 4
BCT Module 5 ground water excavation PART 4BCT Module 5 ground water excavation PART 4
BCT Module 5 ground water excavation PART 4
 
Dewatering
DewateringDewatering
Dewatering
 
Dewatering process and control in building projects
Dewatering process and control in building projectsDewatering process and control in building projects
Dewatering process and control in building projects
 
Groundwater Control Techniques for Tunnelling and Shaft Sinking
Groundwater Control Techniques for Tunnelling and Shaft SinkingGroundwater Control Techniques for Tunnelling and Shaft Sinking
Groundwater Control Techniques for Tunnelling and Shaft Sinking
 
Construction dewatering
Construction dewateringConstruction dewatering
Construction dewatering
 
The Best Thing about Ground Freezing Technique
The Best Thing about Ground Freezing TechniqueThe Best Thing about Ground Freezing Technique
The Best Thing about Ground Freezing Technique
 
Dewatering techniques
Dewatering techniquesDewatering techniques
Dewatering techniques
 
De watering-ppt
De watering-pptDe watering-ppt
De watering-ppt
 
Study of Prefabricated Vertical Drains
Study of Prefabricated Vertical DrainsStudy of Prefabricated Vertical Drains
Study of Prefabricated Vertical Drains
 
Methods of Dewatering
Methods of DewateringMethods of Dewatering
Methods of Dewatering
 
Ground freezing
Ground freezing Ground freezing
Ground freezing
 
Construction dewatering technology data sheet
Construction dewatering technology data sheetConstruction dewatering technology data sheet
Construction dewatering technology data sheet
 
Collection and Conveyance of Water
Collection and Conveyance of WaterCollection and Conveyance of Water
Collection and Conveyance of Water
 

Similar to 5. CONTROL OF GROUND WATER IN EXCAVATION (ACE) 2160601 GTU

Excavation and Ground water control1.pptx
Excavation and Ground water control1.pptxExcavation and Ground water control1.pptx
Excavation and Ground water control1.pptx
ssusercbae26
 
dewateringtechniques 2.pptx
dewateringtechniques 2.pptxdewateringtechniques 2.pptx
dewateringtechniques 2.pptx
CarolTumaneng
 
Subsurface drainage
Subsurface drainageSubsurface drainage
Subsurface drainage
Chethan B J
 
DEWATERING METHODS IN DIFFERENT SOIL CONDITIONS
DEWATERING METHODS IN DIFFERENT SOIL CONDITIONSDEWATERING METHODS IN DIFFERENT SOIL CONDITIONS
DEWATERING METHODS IN DIFFERENT SOIL CONDITIONS
TejaswiniNarayane
 
Design, layout and installation of drip and fertigation in precision farming
Design, layout and installation of drip and fertigation in precision farmingDesign, layout and installation of drip and fertigation in precision farming
Design, layout and installation of drip and fertigation in precision farming
Dr. M. Kumaresan Hort.
 
Special Concreting Techniques
Special Concreting Techniques Special Concreting Techniques
Special Concreting Techniques
GAURAV. H .TANDON
 
Geotechnical engineering II
Geotechnical engineering IIGeotechnical engineering II
Geotechnical engineering II
Gaurang Kakadiya
 
Special Methods of Sub Surface Drainage: Agricultural Draining Engineering
Special Methods of Sub Surface Drainage: Agricultural Draining EngineeringSpecial Methods of Sub Surface Drainage: Agricultural Draining Engineering
Special Methods of Sub Surface Drainage: Agricultural Draining Engineering
Venkata Sai Kari
 
Week 01 Preliminaries Works, Soil Investigate & Ground Water Control
Week 01 Preliminaries Works, Soil Investigate & Ground Water ControlWeek 01 Preliminaries Works, Soil Investigate & Ground Water Control
Week 01 Preliminaries Works, Soil Investigate & Ground Water Controlnik kin
 
Gwe paper material
Gwe paper materialGwe paper material
Gwe paper material
keyur pansara
 
Methods of boring ppt
Methods of boring  pptMethods of boring  ppt
Methods of boring ppt
Rakesh Ahirwar
 
sm-1_chap._6_geotechnical_investigation.pptx
sm-1_chap._6_geotechnical_investigation.pptxsm-1_chap._6_geotechnical_investigation.pptx
sm-1_chap._6_geotechnical_investigation.pptx
pavuluri2014
 
Tube-Wells and their Designs
Tube-Wells and their DesignsTube-Wells and their Designs
Tube-Wells and their Designs
Anand Kumar
 
Sewer joints of pipes, sewer appurtenances, storm water drainage.pptx
Sewer joints of pipes, sewer appurtenances, storm water drainage.pptxSewer joints of pipes, sewer appurtenances, storm water drainage.pptx
Sewer joints of pipes, sewer appurtenances, storm water drainage.pptx
PriyaTalwar8
 
Dewatering
DewateringDewatering
Dewatering
JNTUK
 
water wells.ppt
water wells.pptwater wells.ppt
water wells.ppt
Ali Al-naqa
 
Tube wells and their design
Tube wells and their designTube wells and their design
Tube wells and their design
Moudud Hasan
 
Bc.ppt METHOD OF IMPROVING SOIL BEARING CAPPACITY
Bc.ppt METHOD OF IMPROVING SOIL BEARING CAPPACITYBc.ppt METHOD OF IMPROVING SOIL BEARING CAPPACITY
Bc.ppt METHOD OF IMPROVING SOIL BEARING CAPPACITY
Sukhvinder Singh
 
Management & mitigation of groundwater infiltration within underground excava...
Management & mitigation of groundwater infiltration within underground excava...Management & mitigation of groundwater infiltration within underground excava...
Management & mitigation of groundwater infiltration within underground excava...
Angelo Indelicato
 

Similar to 5. CONTROL OF GROUND WATER IN EXCAVATION (ACE) 2160601 GTU (20)

Excavation and Ground water control1.pptx
Excavation and Ground water control1.pptxExcavation and Ground water control1.pptx
Excavation and Ground water control1.pptx
 
dewateringtechniques 2.pptx
dewateringtechniques 2.pptxdewateringtechniques 2.pptx
dewateringtechniques 2.pptx
 
Subsurface drainage
Subsurface drainageSubsurface drainage
Subsurface drainage
 
DEWATERING METHODS IN DIFFERENT SOIL CONDITIONS
DEWATERING METHODS IN DIFFERENT SOIL CONDITIONSDEWATERING METHODS IN DIFFERENT SOIL CONDITIONS
DEWATERING METHODS IN DIFFERENT SOIL CONDITIONS
 
Design, layout and installation of drip and fertigation in precision farming
Design, layout and installation of drip and fertigation in precision farmingDesign, layout and installation of drip and fertigation in precision farming
Design, layout and installation of drip and fertigation in precision farming
 
Special Concreting Techniques
Special Concreting Techniques Special Concreting Techniques
Special Concreting Techniques
 
Geotechnical engineering II
Geotechnical engineering IIGeotechnical engineering II
Geotechnical engineering II
 
Special Methods of Sub Surface Drainage: Agricultural Draining Engineering
Special Methods of Sub Surface Drainage: Agricultural Draining EngineeringSpecial Methods of Sub Surface Drainage: Agricultural Draining Engineering
Special Methods of Sub Surface Drainage: Agricultural Draining Engineering
 
Week 01 Preliminaries Works, Soil Investigate & Ground Water Control
Week 01 Preliminaries Works, Soil Investigate & Ground Water ControlWeek 01 Preliminaries Works, Soil Investigate & Ground Water Control
Week 01 Preliminaries Works, Soil Investigate & Ground Water Control
 
Gwe paper material
Gwe paper materialGwe paper material
Gwe paper material
 
Methods of boring ppt
Methods of boring  pptMethods of boring  ppt
Methods of boring ppt
 
sm-1_chap._6_geotechnical_investigation.pptx
sm-1_chap._6_geotechnical_investigation.pptxsm-1_chap._6_geotechnical_investigation.pptx
sm-1_chap._6_geotechnical_investigation.pptx
 
Tube-Wells and their Designs
Tube-Wells and their DesignsTube-Wells and their Designs
Tube-Wells and their Designs
 
Sewer joints of pipes, sewer appurtenances, storm water drainage.pptx
Sewer joints of pipes, sewer appurtenances, storm water drainage.pptxSewer joints of pipes, sewer appurtenances, storm water drainage.pptx
Sewer joints of pipes, sewer appurtenances, storm water drainage.pptx
 
Dewatering
DewateringDewatering
Dewatering
 
water wells.ppt
water wells.pptwater wells.ppt
water wells.ppt
 
Tube wells and their design
Tube wells and their designTube wells and their design
Tube wells and their design
 
Bc.ppt METHOD OF IMPROVING SOIL BEARING CAPPACITY
Bc.ppt METHOD OF IMPROVING SOIL BEARING CAPPACITYBc.ppt METHOD OF IMPROVING SOIL BEARING CAPPACITY
Bc.ppt METHOD OF IMPROVING SOIL BEARING CAPPACITY
 
Drainage
DrainageDrainage
Drainage
 
Management & mitigation of groundwater infiltration within underground excava...
Management & mitigation of groundwater infiltration within underground excava...Management & mitigation of groundwater infiltration within underground excava...
Management & mitigation of groundwater infiltration within underground excava...
 

More from VATSAL PATEL

5. AIR TRANSPORTATION (TRE) GTU 3150611
5. AIR TRANSPORTATION (TRE) GTU 31506115. AIR TRANSPORTATION (TRE) GTU 3150611
5. AIR TRANSPORTATION (TRE) GTU 3150611
VATSAL PATEL
 
3. RAIL TRANSPORTATION (TRE) GTU 3150611
3. RAIL TRANSPORTATION (TRE) GTU 31506113. RAIL TRANSPORTATION (TRE) GTU 3150611
3. RAIL TRANSPORTATION (TRE) GTU 3150611
VATSAL PATEL
 
2.7 HIGHWAY TRANSPORTATION : TRAFFIC ENGINEERING (TRE) 3150611 GTU
2.7 HIGHWAY TRANSPORTATION : TRAFFIC ENGINEERING (TRE) 3150611 GTU2.7 HIGHWAY TRANSPORTATION : TRAFFIC ENGINEERING (TRE) 3150611 GTU
2.7 HIGHWAY TRANSPORTATION : TRAFFIC ENGINEERING (TRE) 3150611 GTU
VATSAL PATEL
 
2.6 HIGHWAY TRANSPORTATION : HIGHWAY DRAINAGE, ARBORICULTURE AND LIGHTING (TR...
2.6 HIGHWAY TRANSPORTATION : HIGHWAY DRAINAGE, ARBORICULTURE AND LIGHTING (TR...2.6 HIGHWAY TRANSPORTATION : HIGHWAY DRAINAGE, ARBORICULTURE AND LIGHTING (TR...
2.6 HIGHWAY TRANSPORTATION : HIGHWAY DRAINAGE, ARBORICULTURE AND LIGHTING (TR...
VATSAL PATEL
 
2.5 HIGHWAY TRANSPORTATION : PAVEMENT MAINTENANCE (TRE) 3150611 GTU
2.5 HIGHWAY TRANSPORTATION : PAVEMENT MAINTENANCE (TRE) 3150611 GTU2.5 HIGHWAY TRANSPORTATION : PAVEMENT MAINTENANCE (TRE) 3150611 GTU
2.5 HIGHWAY TRANSPORTATION : PAVEMENT MAINTENANCE (TRE) 3150611 GTU
VATSAL PATEL
 
2.4 HIGHWAY TRANSPORTATION : DESIGN AND CONSTRUCTION OF PAVEMENT (TRE) 315061...
2.4 HIGHWAY TRANSPORTATION : DESIGN AND CONSTRUCTION OF PAVEMENT (TRE) 315061...2.4 HIGHWAY TRANSPORTATION : DESIGN AND CONSTRUCTION OF PAVEMENT (TRE) 315061...
2.4 HIGHWAY TRANSPORTATION : DESIGN AND CONSTRUCTION OF PAVEMENT (TRE) 315061...
VATSAL PATEL
 
2. PORT PLANNING (PHE) GTU 3170623
2. PORT PLANNING (PHE) GTU 31706232. PORT PLANNING (PHE) GTU 3170623
2. PORT PLANNING (PHE) GTU 3170623
VATSAL PATEL
 
4. WATER TRANSPORTATION (TRE) GTU 3150611
4. WATER TRANSPORTATION (TRE) GTU 31506114. WATER TRANSPORTATION (TRE) GTU 3150611
4. WATER TRANSPORTATION (TRE) GTU 3150611
VATSAL PATEL
 
8. IMPACT ANALYSIS (PHE) GTU 3170623
8. IMPACT ANALYSIS (PHE) GTU 31706238. IMPACT ANALYSIS (PHE) GTU 3170623
8. IMPACT ANALYSIS (PHE) GTU 3170623
VATSAL PATEL
 
2.3 HIGHWAY TRANSPORTATION : HIGHWAY MATERIALS (TRE) 3150611 GTU
2.3 HIGHWAY TRANSPORTATION : HIGHWAY MATERIALS (TRE) 3150611 GTU2.3 HIGHWAY TRANSPORTATION : HIGHWAY MATERIALS (TRE) 3150611 GTU
2.3 HIGHWAY TRANSPORTATION : HIGHWAY MATERIALS (TRE) 3150611 GTU
VATSAL PATEL
 
7. SEAPORT MAINTENANCE (PHE) GTU 3170623
7. SEAPORT MAINTENANCE (PHE) GTU 31706237. SEAPORT MAINTENANCE (PHE) GTU 3170623
7. SEAPORT MAINTENANCE (PHE) GTU 3170623
VATSAL PATEL
 
6. NAVIGATIONAL AIDS (PHE) GTU 3170623
6. NAVIGATIONAL AIDS (PHE) GTU 31706236. NAVIGATIONAL AIDS (PHE) GTU 3170623
6. NAVIGATIONAL AIDS (PHE) GTU 3170623
VATSAL PATEL
 
5. PORT AMENITIES & OPERATIONS (PHE) GTU 3170623
5. PORT AMENITIES & OPERATIONS (PHE) GTU 31706235. PORT AMENITIES & OPERATIONS (PHE) GTU 3170623
5. PORT AMENITIES & OPERATIONS (PHE) GTU 3170623
VATSAL PATEL
 
4. HARBOUR INFRASTRUCTURES (PHE) GTU 3170623
4. HARBOUR INFRASTRUCTURES (PHE) GTU 31706234. HARBOUR INFRASTRUCTURES (PHE) GTU 3170623
4. HARBOUR INFRASTRUCTURES (PHE) GTU 3170623
VATSAL PATEL
 
3. NATURAL PHENOMENA (PHE) GTU 3170623
3. NATURAL PHENOMENA (PHE) GTU 31706233. NATURAL PHENOMENA (PHE) GTU 3170623
3. NATURAL PHENOMENA (PHE) GTU 3170623
VATSAL PATEL
 
2.2 HIGHWAY TRANSPORTATION : HIGHWAY GEOMETRIC DESIGN (TRE) 3150611 GTU
2.2 HIGHWAY TRANSPORTATION : HIGHWAY GEOMETRIC DESIGN (TRE) 3150611 GTU2.2 HIGHWAY TRANSPORTATION : HIGHWAY GEOMETRIC DESIGN (TRE) 3150611 GTU
2.2 HIGHWAY TRANSPORTATION : HIGHWAY GEOMETRIC DESIGN (TRE) 3150611 GTU
VATSAL PATEL
 
1. INTRODUCTION TO WATER TRANSPORTATION (PHE) GTU 3170623
1. INTRODUCTION  TO WATER TRANSPORTATION (PHE) GTU 31706231. INTRODUCTION  TO WATER TRANSPORTATION (PHE) GTU 3170623
1. INTRODUCTION TO WATER TRANSPORTATION (PHE) GTU 3170623
VATSAL PATEL
 
2.1 HIGHWAY TRANSPORTATION : HIGHWAY PLANNING AND DEVELOPMENT (TRE) 3150611 GTU
2.1 HIGHWAY TRANSPORTATION : HIGHWAY PLANNING AND DEVELOPMENT (TRE) 3150611 GTU2.1 HIGHWAY TRANSPORTATION : HIGHWAY PLANNING AND DEVELOPMENT (TRE) 3150611 GTU
2.1 HIGHWAY TRANSPORTATION : HIGHWAY PLANNING AND DEVELOPMENT (TRE) 3150611 GTU
VATSAL PATEL
 
1. INTRODUCTION (TRE) 3150611 GTU
1. INTRODUCTION (TRE) 3150611 GTU1. INTRODUCTION (TRE) 3150611 GTU
1. INTRODUCTION (TRE) 3150611 GTU
VATSAL PATEL
 
9. MORDAN SURVEYING INSTRUMENTS (SUR) 3140601 GTU
9. MORDAN SURVEYING INSTRUMENTS (SUR) 3140601 GTU9. MORDAN SURVEYING INSTRUMENTS (SUR) 3140601 GTU
9. MORDAN SURVEYING INSTRUMENTS (SUR) 3140601 GTU
VATSAL PATEL
 

More from VATSAL PATEL (20)

5. AIR TRANSPORTATION (TRE) GTU 3150611
5. AIR TRANSPORTATION (TRE) GTU 31506115. AIR TRANSPORTATION (TRE) GTU 3150611
5. AIR TRANSPORTATION (TRE) GTU 3150611
 
3. RAIL TRANSPORTATION (TRE) GTU 3150611
3. RAIL TRANSPORTATION (TRE) GTU 31506113. RAIL TRANSPORTATION (TRE) GTU 3150611
3. RAIL TRANSPORTATION (TRE) GTU 3150611
 
2.7 HIGHWAY TRANSPORTATION : TRAFFIC ENGINEERING (TRE) 3150611 GTU
2.7 HIGHWAY TRANSPORTATION : TRAFFIC ENGINEERING (TRE) 3150611 GTU2.7 HIGHWAY TRANSPORTATION : TRAFFIC ENGINEERING (TRE) 3150611 GTU
2.7 HIGHWAY TRANSPORTATION : TRAFFIC ENGINEERING (TRE) 3150611 GTU
 
2.6 HIGHWAY TRANSPORTATION : HIGHWAY DRAINAGE, ARBORICULTURE AND LIGHTING (TR...
2.6 HIGHWAY TRANSPORTATION : HIGHWAY DRAINAGE, ARBORICULTURE AND LIGHTING (TR...2.6 HIGHWAY TRANSPORTATION : HIGHWAY DRAINAGE, ARBORICULTURE AND LIGHTING (TR...
2.6 HIGHWAY TRANSPORTATION : HIGHWAY DRAINAGE, ARBORICULTURE AND LIGHTING (TR...
 
2.5 HIGHWAY TRANSPORTATION : PAVEMENT MAINTENANCE (TRE) 3150611 GTU
2.5 HIGHWAY TRANSPORTATION : PAVEMENT MAINTENANCE (TRE) 3150611 GTU2.5 HIGHWAY TRANSPORTATION : PAVEMENT MAINTENANCE (TRE) 3150611 GTU
2.5 HIGHWAY TRANSPORTATION : PAVEMENT MAINTENANCE (TRE) 3150611 GTU
 
2.4 HIGHWAY TRANSPORTATION : DESIGN AND CONSTRUCTION OF PAVEMENT (TRE) 315061...
2.4 HIGHWAY TRANSPORTATION : DESIGN AND CONSTRUCTION OF PAVEMENT (TRE) 315061...2.4 HIGHWAY TRANSPORTATION : DESIGN AND CONSTRUCTION OF PAVEMENT (TRE) 315061...
2.4 HIGHWAY TRANSPORTATION : DESIGN AND CONSTRUCTION OF PAVEMENT (TRE) 315061...
 
2. PORT PLANNING (PHE) GTU 3170623
2. PORT PLANNING (PHE) GTU 31706232. PORT PLANNING (PHE) GTU 3170623
2. PORT PLANNING (PHE) GTU 3170623
 
4. WATER TRANSPORTATION (TRE) GTU 3150611
4. WATER TRANSPORTATION (TRE) GTU 31506114. WATER TRANSPORTATION (TRE) GTU 3150611
4. WATER TRANSPORTATION (TRE) GTU 3150611
 
8. IMPACT ANALYSIS (PHE) GTU 3170623
8. IMPACT ANALYSIS (PHE) GTU 31706238. IMPACT ANALYSIS (PHE) GTU 3170623
8. IMPACT ANALYSIS (PHE) GTU 3170623
 
2.3 HIGHWAY TRANSPORTATION : HIGHWAY MATERIALS (TRE) 3150611 GTU
2.3 HIGHWAY TRANSPORTATION : HIGHWAY MATERIALS (TRE) 3150611 GTU2.3 HIGHWAY TRANSPORTATION : HIGHWAY MATERIALS (TRE) 3150611 GTU
2.3 HIGHWAY TRANSPORTATION : HIGHWAY MATERIALS (TRE) 3150611 GTU
 
7. SEAPORT MAINTENANCE (PHE) GTU 3170623
7. SEAPORT MAINTENANCE (PHE) GTU 31706237. SEAPORT MAINTENANCE (PHE) GTU 3170623
7. SEAPORT MAINTENANCE (PHE) GTU 3170623
 
6. NAVIGATIONAL AIDS (PHE) GTU 3170623
6. NAVIGATIONAL AIDS (PHE) GTU 31706236. NAVIGATIONAL AIDS (PHE) GTU 3170623
6. NAVIGATIONAL AIDS (PHE) GTU 3170623
 
5. PORT AMENITIES & OPERATIONS (PHE) GTU 3170623
5. PORT AMENITIES & OPERATIONS (PHE) GTU 31706235. PORT AMENITIES & OPERATIONS (PHE) GTU 3170623
5. PORT AMENITIES & OPERATIONS (PHE) GTU 3170623
 
4. HARBOUR INFRASTRUCTURES (PHE) GTU 3170623
4. HARBOUR INFRASTRUCTURES (PHE) GTU 31706234. HARBOUR INFRASTRUCTURES (PHE) GTU 3170623
4. HARBOUR INFRASTRUCTURES (PHE) GTU 3170623
 
3. NATURAL PHENOMENA (PHE) GTU 3170623
3. NATURAL PHENOMENA (PHE) GTU 31706233. NATURAL PHENOMENA (PHE) GTU 3170623
3. NATURAL PHENOMENA (PHE) GTU 3170623
 
2.2 HIGHWAY TRANSPORTATION : HIGHWAY GEOMETRIC DESIGN (TRE) 3150611 GTU
2.2 HIGHWAY TRANSPORTATION : HIGHWAY GEOMETRIC DESIGN (TRE) 3150611 GTU2.2 HIGHWAY TRANSPORTATION : HIGHWAY GEOMETRIC DESIGN (TRE) 3150611 GTU
2.2 HIGHWAY TRANSPORTATION : HIGHWAY GEOMETRIC DESIGN (TRE) 3150611 GTU
 
1. INTRODUCTION TO WATER TRANSPORTATION (PHE) GTU 3170623
1. INTRODUCTION  TO WATER TRANSPORTATION (PHE) GTU 31706231. INTRODUCTION  TO WATER TRANSPORTATION (PHE) GTU 3170623
1. INTRODUCTION TO WATER TRANSPORTATION (PHE) GTU 3170623
 
2.1 HIGHWAY TRANSPORTATION : HIGHWAY PLANNING AND DEVELOPMENT (TRE) 3150611 GTU
2.1 HIGHWAY TRANSPORTATION : HIGHWAY PLANNING AND DEVELOPMENT (TRE) 3150611 GTU2.1 HIGHWAY TRANSPORTATION : HIGHWAY PLANNING AND DEVELOPMENT (TRE) 3150611 GTU
2.1 HIGHWAY TRANSPORTATION : HIGHWAY PLANNING AND DEVELOPMENT (TRE) 3150611 GTU
 
1. INTRODUCTION (TRE) 3150611 GTU
1. INTRODUCTION (TRE) 3150611 GTU1. INTRODUCTION (TRE) 3150611 GTU
1. INTRODUCTION (TRE) 3150611 GTU
 
9. MORDAN SURVEYING INSTRUMENTS (SUR) 3140601 GTU
9. MORDAN SURVEYING INSTRUMENTS (SUR) 3140601 GTU9. MORDAN SURVEYING INSTRUMENTS (SUR) 3140601 GTU
9. MORDAN SURVEYING INSTRUMENTS (SUR) 3140601 GTU
 

Recently uploaded

Forklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella PartsForklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella Parts
Intella Parts
 
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdfCOLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
Kamal Acharya
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
gerogepatton
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
AJAYKUMARPUND1
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
Kamal Acharya
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
SamSarthak3
 
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang,  ICLR 2024, MLILAB, KAIST AI.pdfJ.Yang,  ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
MLILAB
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
Neometrix_Engineering_Pvt_Ltd
 
weather web application report.pdf
weather web application report.pdfweather web application report.pdf
weather web application report.pdf
Pratik Pawar
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Sreedhar Chowdam
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Dr.Costas Sachpazis
 
Event Management System Vb Net Project Report.pdf
Event Management System Vb Net  Project Report.pdfEvent Management System Vb Net  Project Report.pdf
Event Management System Vb Net Project Report.pdf
Kamal Acharya
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
Massimo Talia
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
Amil Baba Dawood bangali
 
TECHNICAL TRAINING MANUAL GENERAL FAMILIARIZATION COURSE
TECHNICAL TRAINING MANUAL   GENERAL FAMILIARIZATION COURSETECHNICAL TRAINING MANUAL   GENERAL FAMILIARIZATION COURSE
TECHNICAL TRAINING MANUAL GENERAL FAMILIARIZATION COURSE
DuvanRamosGarzon1
 
LIGA(E)11111111111111111111111111111111111111111.ppt
LIGA(E)11111111111111111111111111111111111111111.pptLIGA(E)11111111111111111111111111111111111111111.ppt
LIGA(E)11111111111111111111111111111111111111111.ppt
ssuser9bd3ba
 
Automobile Management System Project Report.pdf
Automobile Management System Project Report.pdfAutomobile Management System Project Report.pdf
Automobile Management System Project Report.pdf
Kamal Acharya
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
Divya Somashekar
 
power quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptxpower quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptx
ViniHema
 
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
H.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdfH.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdf
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
MLILAB
 

Recently uploaded (20)

Forklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella PartsForklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella Parts
 
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdfCOLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
COLLEGE BUS MANAGEMENT SYSTEM PROJECT REPORT.pdf
 
Immunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary AttacksImmunizing Image Classifiers Against Localized Adversary Attacks
Immunizing Image Classifiers Against Localized Adversary Attacks
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
 
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang,  ICLR 2024, MLILAB, KAIST AI.pdfJ.Yang,  ICLR 2024, MLILAB, KAIST AI.pdf
J.Yang, ICLR 2024, MLILAB, KAIST AI.pdf
 
Standard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - NeometrixStandard Reomte Control Interface - Neometrix
Standard Reomte Control Interface - Neometrix
 
weather web application report.pdf
weather web application report.pdfweather web application report.pdf
weather web application report.pdf
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
 
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
Sachpazis:Terzaghi Bearing Capacity Estimation in simple terms with Calculati...
 
Event Management System Vb Net Project Report.pdf
Event Management System Vb Net  Project Report.pdfEvent Management System Vb Net  Project Report.pdf
Event Management System Vb Net Project Report.pdf
 
Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024Nuclear Power Economics and Structuring 2024
Nuclear Power Economics and Structuring 2024
 
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
NO1 Uk best vashikaran specialist in delhi vashikaran baba near me online vas...
 
TECHNICAL TRAINING MANUAL GENERAL FAMILIARIZATION COURSE
TECHNICAL TRAINING MANUAL   GENERAL FAMILIARIZATION COURSETECHNICAL TRAINING MANUAL   GENERAL FAMILIARIZATION COURSE
TECHNICAL TRAINING MANUAL GENERAL FAMILIARIZATION COURSE
 
LIGA(E)11111111111111111111111111111111111111111.ppt
LIGA(E)11111111111111111111111111111111111111111.pptLIGA(E)11111111111111111111111111111111111111111.ppt
LIGA(E)11111111111111111111111111111111111111111.ppt
 
Automobile Management System Project Report.pdf
Automobile Management System Project Report.pdfAutomobile Management System Project Report.pdf
Automobile Management System Project Report.pdf
 
block diagram and signal flow graph representation
block diagram and signal flow graph representationblock diagram and signal flow graph representation
block diagram and signal flow graph representation
 
power quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptxpower quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptx
 
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
H.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdfH.Seo,  ICLR 2024, MLILAB,  KAIST AI.pdf
H.Seo, ICLR 2024, MLILAB, KAIST AI.pdf
 

5. CONTROL OF GROUND WATER IN EXCAVATION (ACE) 2160601 GTU

  • 1. 1 PREPARED BY : ASST. PROF. VATSAL D. PATEL MAHATMA GANDHI INSTITUTE OF TECHNICAL EDUCATION & RESEARCH CENTRE, NAVSARI.
  • 2. • Dewatering means removal of excess water from saturated soil. • it comes to when the Dewatering is a necessary process when many construction projects, particularly construction is for underground projects.
  • 3. • Factors such as the type of soil and the nature of the construction site will all influence which dewatering method will be best suited to the project. 6. Cement Grouting 7. Chemical Process 8. Freezing Process 9. Electro-Osmosis Method 1. Sumps And Ditches 2. Shallow Well System 3. Deep Well System 4. Well Point System 5. Vacuum Method
  • 4. • It is the simplest and most commonly used form of dewatering. • In this method, shallow pits, called sumps are dug along the periphery of the area and connected by drains of semicircular in shape and 20 cm diameter. • The water from the slopes gravityand iscollected in flows under sumps from which it is pumped out.
  • 5.  A hole of 30 cm diameter or more is bored into the ground to a depth not more than 10 m below the pump level. A strainer tube of 15 cm diameter is lowered in the bore hole having a casing tube.  A gravel filter is formed around the strainer tube by gradually removing the casing tube and simultaneously pouring the filter well so formed.  The suction pipe from a number of such wells may be connected to one common header connected to the pumping unit.
  • 6. [A typical layout of a shallow well system]
  • 7. This system is more suitable when the depth of excavation is more than the 16m or where artesian water is present. In this, 15 to 16 cm diameter hole is bored and a casing with a large screen is provided. A row of well points is frequently installed at the toe of the side slope of the deep excavation. A submersible pump is installed at the bottom of the well, of which the casing generally has a minimum diameter of 150 mm. The discharge pipes from the submersible pumps of a number of adjacent wells are connected to a common delivery main. The water is raised from the well by a multi-staged pump.
  • 8. [A typical layout of a deep well system]
  • 9.
  • 10. • The main components of a well-point system are: 1. well points 2. Riser pipe 3. Swinger arm 4. Header pipe 5. pumps
  • 11. • The well point is perforated pipe 5 to 8 CM in dia & 1m long covered by cylindrical wire gauge screen known as strainer. Pipes are jetted in the ground 1 to 2mt a part. Well point → riser pipe → swinger arm → header. It is suitable for lowering water table by 5 to 6 m in soil.
  • 12. 13
  • 13. 14
  • 14. Multi-stage well point system is suitable for excavations up to 15 m.
  • 15. When water table is greater than 6 m this method willuse. In this method 2 or more rows of well point are installed at different elevation. In this method wells are installed in 2 stages. In 1st stage water table lowered by 5 m. If required, then 3rd stage of well point can also be installed for further lower water table. This method useful for up to 15 m. For up to 15th m deep well system will use.
  • 16. 17
  • 17. is very rapid. The equipment is reasonably Simple Advantages: •Installation and cheap. •As water is filtered while removing from the ground, soil particles are not washed away. Hence, there is no danger of subsidence of the surrounding ground. •As the water is drawn away by well points from the excavation, the sides of excavation are stabilized and steeper side slopes can be permitted.
  • 18. Disadvantages: •Single stage well point system is suitable for lowering water table by 5 to 6 m only. For deeper excavations, where water table is to be lowered for a depth greater than 6 m, multi- stage well point system is required. •It is essential to continue pumping once it has been started until the excavation is complete. If it is stopped in between, it may prove to be disastrous. •In case of the ground consisting of stiff clay, gravel or boulders, well points are installed in drilled holes, which increases the installation cost.
  • 19.
  • 20. When draining is required for silt or clay which have size less than 0.05mm. That time vacuum pump system will require. The process is as follows: The well-points are driven and 25 CM dia is provided around the well point. Installed in the ground by forcing a jet of water under sufficient pressure. The sand of medium to coarse size is then forced into this hole as rapidly as possible. This sand forms the filter medium.
  • 21. In the upper most 600 mm to 900 mm, an impervious material such as clay is tamped to form the seal the upper portion. The pumping is then carried out by means of equipment capable of maintaining a vacuum in the well-points and the surrounding filter. In this way, the pressure around the well-points is reduced to a small fraction of the atmospheric pressure. The ground is acted upon by the atmospheric pressure. Thus the soil becomes consolidated under a pressure which is very nearly equal to the atmospheric.
  • 22. In highly permeable cohesionless soil, the safety of the side slopes may be endangered through the application of severe pumping. In such cases, especially if control of the groundwater is required permanently, the methods of grouting can be used. The main idea is to insert fine materials or chemicals around the excavation in order to reduce the hydraulic conductivity of the surrounding soil to a minimum. In other words, the grouting process creates an almost impervious curtain around the excavation. The grouting is conducted using movable pipes with holes. The grout material is injected under pressure as it flows outside the pipes through the holes to fill the voids of the surrounding soil. The material used for grouting may be clay, cement or special chemical compounds.
  • 23.
  • 24.
  • 25.
  • 26. • The material commonly used for grout include: 1) Cement And Water 2) Cement, Rock Flour and Water 3) Cement, Clay and Water 4) Cement, Clay, Sand and Water 5) Asphalt 6) Clay And Water 7) Chemicals
  • 27. • The desirable properties of chemical grouts: 1)It must be able to modify the properties of soil as desired 2)It may either increase the strength or decrease the permeability of soil 3)It must be cheap, non-toxic, non-explosive 4)It must be in the form of a liquid with low viscosity so that it can be readily placed in the soil 5)It must be non-corrosive, so that it can be handled with common pumps and piping 6)It must be possible to control the gel time by suitable means.
  • 28.
  • 29. • Inorganic chemicals Sodium silicate Calcium chloride Ligno-chrome Ligno sulphate They are called silicate grouts They are cheaper • Organic chemicals Epoxy resins Polyester resins They are also called resin grouts They possess advantage of low viscosity, precise control of gel time and high strength
  • 30. Soils that will not drain using conventional methods Typically a ground freezing system consists of an array of freeze pipes. That are installed into the ground around the perimeter of the excavation, usually in a circular pattern. A supermodel brine solution is pump through to freeze the pipes, which freezes the water bearing soils around the pipes to create a frozen wall. Extreme care must be taken to make sure that the freeze is complete because any groundwater seepage though the wall or from below the excavation depth will have a sliding effect.
  • 31.
  • 32. 34
  • 33.  The procedure: A refrigeration plant of required installed near the site of work. The large pipes of 100 mm to 150 mm diameter. The distance between the pipes is about 1 m to 1.50 m. The pipes are closed at the bottom. The small pipes of 25mm to 50mm diametre are inserted into the large pipes open at the bottom. The cold liquid at a temperature of about -23°C to -30°C is then circulated through the circuit. The liquid comes through the small pipe and goes up through the large pipe. This causes the ground to freeze around the pipes.
  • 34.
  • 35. • This method is used for fine grained cohesive soils (such as clay), which can be drained or stabilized using electric current. The method was developed by L. Casagrande (1952). • If direct current is passed between two electrodes driven into natural soil mass, the soil water will travel` from the positive electrode (anode) to the negative electrode (cathode). The cathode is made in the form of well point or metal tube for pumping out the seeping form of well point or a metal tube for pumping out the seeping water. • A steel rod, a pipe or steel piling of excavation can serve as the cathode. The arrangement of electrodes is done in such a way that the natural direction of flow of water is reversed away from the excavation, thereby increasing the strength of the soil and stability of the slope. The potentials generally used in the process are from 40 to 180 volts, with electrode spacing of 4 to 5 meters.
  • 36. The vibroflot is inserted into the ground and typically can be used to improve soil up to depths of 150 feet. Vibroflotation utilizes water and the mechanical vibrations of the vibroflot to move the particles into a denser state. Typical radial distances affected range from 5 to 15 feet (Bauer Maschinen GmbH, 2012). The vibroflot is suspended from a crane and seats on the surface of the ground that is to be improved. To penetrate the material, the bottom jet is activated and the vibration begins. The water saturates the material to create a “quick sand” condition (i.e. temporarily liquefying the material), which allows the vibroflot to sink to the desired depth of improvement. At that point, the bottom jet is stopped and the water is transferred to the upper jet. This is done to create a saturated environment surrounding the vibroflot, thereby enhancing the compaction of the material. The vibroflot remains at the desired depth of improvement until the material reaches adequate density.
  • 37. The density of the soil is measured by using the power input (via the electric current or hydraulic pressure) as an index. As the material densifies, the vibroflot requires more power to continue vibrating at which point pressure gauge displays a peak in required power. Once this point is reached, the vibroflot is raised one lift (generally ranging from 1 to 3 feet) and compaction ensues until the peak amperage or hydraulic pressure is reached once again.
  • 38.
  • 39. The vibroflotation process can offer the following benefits: •When the process is done properly, it will reduce the possibility of differential settlements that will improve the foundation condition of the proposed structure. •It is the fastest and easiest way to improve soil when bottom layers of soil will not provide good load bearing capacity. •It is a great technology to improve harbor bottoms. •On a cost-related standpoint, it helps improve thousands of cubic meters per day. It is faster than piling. •It can be done around existing structures without damaging them . •It does not harm the environment. It improves the soil strata using its own characteristic •No excavations are needed, reducing the hazards, contamination of soils and hauling material out from the site.
  • 40. METHOD CONDITIONS FOR SUITABILITY 1. Sumps and Ditches For shallow excavations in coarse grained soils. 2. Well point system Suitable for lowering water table by 5-6 m in soils 3. Bored well system For coarse grained soils and depth of excavation more than 16 m 4. Vacuum method Draining silty sands and fine sands 5. Cement grouting For coarse materials or rocks with cracks 6. Freezing process Suitable for excavations in water logged soils 7. Electro-osmosis process Suitable for fine grained cohesive soils such as clays
  • 41. 41