Cross Border Road Network Improvement Project (CBRNIP), Package-B
Financed by
Client:
Roads and Highways Department (RHD)
Joint Venture of
Oriental Consultants Global Co. Ltd- Lead,
Oriental Consultants co. Ltd
PADECO Co. Ltd
BCL Associates Ltd.
Main Project Feature:
Reconstruction of 8 numbers 2-lane PC-I Girder Bridges and 7 numbers Box Culverts along with the approach roads
on Baraiyarhat-Heako-Ramgarh road including installation of axle load control station at Ramgarh
In Association with
SMEC International Pty. Ltd.,
Japan Bridge and Structure Institute Inc.,
ACE Consultants Ltd.,
Development Design Consultants,
BCL Associates Ltd.
Consultants:
Contractor:
Project Location Map
Brief Presentation on Bridge
Construction Under CBRNIP,
Package-B
Part-1
Presented By: Md. Zakirul Islam
Quality Control Manager, CPCL
Prepared By: Sk Mosaddek Haque Reyad
Planning Engineer, CPCL
1. Sub-Structure Work
a) Sub-Soil investigation
b) Pile Construction
c) Pile Cap
d) Abutment wall/Pier Column
e) Abutment Head/Pier Head
2. Super-Structure Work
a) Girder/Beam
b) Deck Slab
c) Kerb, Parapet & Footway slab
3. Misc. Work
a) Approach Slab
b) Slope Protection
Step of Bridge Construction Work:
Elevation of a Bridge
Sub-Soil investigation
Sub-soil Investigation (1) Sub-soil Investigation (2)
Test on Pile
Pile Construction
• Temporary Casing Setting for Boring
• Wash Boring of Pile by Percussion Method
• Wash With Bentonite Slurry
• Drilling Pipe Pulling-out
• Rebar Cage Lowering
• Tremie Pipe Lowering
• Concreting of Pile Through Tremie Pipe
• Static Load Test on Pile
• Dynamic Load Test on Pile
• Pile Integrity Test
• Cross Hole Sonic Logging Test
Pile Construction
Wash Boring by Percussion Method Rebar Cage Lowering
Test On Pile
Hydraulic Jack & Meter gauge for SLT on Pile Static Load Test on Pile is ongoing
Test On Pile
PDA Test Cross Hole Sonic Logging Test
Pile Cap
• Temporary Protection Work for Pile Cap e.g. Sheet Pile/Timber Pile/Steel Pile
• Structural Excavation
• Pile Head Breaking
• Bottom Seal by Lean Concrete
• Rebar Fabrication Work
• Form Work for Pile Cap
• Concreting Work
• Form Work Removing
• Abutment Wall/Pier Shaft Casting Above Present Water Level
• Dismantling All Temporary Protective Work
• Backfilling of Structure By Suitable Material
Pile Cap
Pile Head Breaking Cleaning after Pile Head Breaking
Pile Cap
Rebar Fabrication of Pile Cap Concreting Work of Pile Cap
Abutment Wall/Pier Column
Abutment Wall Pier Shaft
Abutment/Pier Head
Pier Head Stagging Work Pier Head/Cap
PCI Girder/Beam
• Temporary Stagging/Sand Filling Bed for Girder
• Bottom Shutter Placing
• Rebar Fabrication
• Duct Profile Placing
• Installation of HT Wire
• Side Form Work Setting
• Concreting
• Post Tensioning
• Grouting
• Shifting
• Cross Girder Casting
PCI Girder/Beam
Temporary Stagging for PCI Girder Casting Temporary Sand Filling Bed for PCI Girder
PCI Girder/Beam
Duct Profile & Rebar Fabrication Work for PCI Girder Form Work Support for PCI Girder
PCI Girder/Beam
PCI Girder Concreting Work Preparation for Post Tensioning of PCI Girder
PCI Girder/Beam
Post Tensioning Work of PCI Girder ongoing (1) Post Tensioning Work of PCI Girder ongoing (2)
PCI Girder/Beam
PCI Girder Grouting Work PCI Girder Shifting Work by Hydraulic Jack
Cross Girder/Beam
Dowel Bar Between Abutment & Cross Beam Cross Girder/Beam Form Work
Deck Slab
Deck Slab Rebar Fabrication Deck Slab Concreting
Deck Slab
Expansion Joint Rebar Fabrication Expansion Joint Concreting
Deck Slab
Wearing Course Over Bridge Deck
Water Proofing Membrane Over Bridge Deck
Kerb, Parapet & Footway slab
Parapet Rebar Fabrication Parapet, Kerb & Footpath
Approach Slab
Approach Slab Rebar Approach Slab Concreting
Slope Protection Work
Precast CC Block Concreting Slope/Canal Protection Work
Brief Presentation on Road
Construction Work Under CBRNIP,
Package-B
Part-2
Prepared By: Sk Mosaddek Haque Reyad
Planning Engineer, CPCL
Presented By: Md. Zakirul Islam
Quality Control Manager, CPCL
1. Embankment Work
a) Clearing Grubbing
b) Soft Soil Treatment
c) Excavation
d) Embankment Filling with sand/soil
e) Sub-Grade
f) Improved Sub-Grade
2. Pavement Work
a) Sub-Base
b) Base-(II)
c) Base-(I)
d) Prime Coat
e) Binder Course
f) Tack Coat
g) Wearing Course
3. Misc. Work
a) Thermoplastic Road Marking
b) W Beam Guard Rail
c) Drainage Work
Step of Flexible Road Construction Work:
Typical Cross Section of Flexible Pavement:
Clearing Grubbing:
Clearing Grubbing Work by Excavator
Excavation
Excavation Work
Embankment Filling
Embankment Filling Work
ISG
ISG Bed Compaction Work
Sub-Base
Sub-Base
Base Course-(II)
FDD Test for Base Course-(II)
Prime Coat
Prime Coat Laying Prime Coat
Binder Course
Binder Course by Paver Binder Course Compaction Work by Tandem & Pneumatic Roller
Thermoplastic Road marking
Yellow Colour Reflective Thermoplastic Road Marking

Bridge & Road Construction .pptx