MAKERERE UNIVERSITY
COLLEGE OF ENGINEERING, DESIGN ART &
TECHNOLOGY
DEPARTMENT OF CIVIL ENGINEERING
SCHOOL OF ENGINEERING
THIRD YEAR INDUSTRIAL TRAINING REPORT
(6TH
JUNE TO 29TH
JULY 2016)
NAME: KAGANZI KENBERT
REG NUMBER: 13/U/298
STD NUMBER: 213000715
DEPT SUPERVISOR: FIELD SUPERVISOR:
NAME: DR. TUMWESIGYE EMMANUEL NAME: DR. MWESIGE GODFREY
SIGNATURE……………………. SIGNATURE:………………………..
i
DECLARATION
I KAGANZI KENBERT declare that this report is personally prepared and compiled by me, and
that the contents contained within this report have not been duplicated or published anywhere or
submitted to any university for any degree program by a student or any other person, unless
indicated. I have personally compiled it based on the experience and training I had under UB
consulting engineers Ltd, on the Seguku-Kasenge-Buddo road rebuilding project.
NAME: KAGANZI KENBERT
REG NO: 13/U/298
STUDENT NO: 213000715
SIGN ……………………………………….
DATE ………………………………………
ii
ACKNOWLEDGEMENTS
I would like to thank the management and staff of UB Consulting Engineers Limited for the
opportunity they offered me to do undertake training with them
I would like to thank the management and staff of Abubaker Technical Services and General
Supplies Limited for the opportunity they offered me to do undertake training with them, on top
of which they tolerated my mistakes and too many questions as well as the facilitation offered in
term of meals.
I would like to thank my internship supervisor Dr. Tumwesigye Emmanuel for taking on the
responsibility to supervise me during my internship training
I would like to thank my parents for their unconditional willingness to meet all of my needs and
requirements as per the industrial training period, in terms of funding, advice and personal
guidance.
Finally, I would like to thank the Almighty God for the knowledge, wisdom, good health, safety
and ability he granted because without these, the success of this industrial training would not have
been possible.
iii
Table of Contents
DECLARATION............................................................................................................................. i
ACKNOWLEDGEMENTS............................................................................................................ii
LIST OF FIGURES ....................................................................................................................... vi
LIST OF TABLES........................................................................................................................vii
ABBREVIATIONS .....................................................................................................................viii
ABSTRACT................................................................................................................................... ix
CHAPTER ONE: INTRODUCTION............................................................................................. 1
1.1 Background........................................................................................................................... 1
1.2 Objectives ............................................................................................................................. 1
1.3 Project Setting....................................................................................................................... 2
1.3.1 Consultant’s Background............................................................................................... 3
1.3.2 Contractor’s Background............................................................................................... 4
1.4 Road design specifications.................................................................................................... 5
1.5 Scope of works...................................................................................................................... 5
CHAPTER TWO: LITERATURE REVIEW................................................................................. 7
2.1 Pavement............................................................................................................................... 7
2.1.1 Flexible Pavement.......................................................................................................... 8
2.1.2 Perpetual Pavement........................................................................................................ 9
2.1.3 Rigid Pavement............................................................................................................ 10
2.1.5 Rigid and Flexible Pavement Characteristics .............................................................. 11
2.2 Pavement Materials:............................................................................................................ 12
2.2.1 Soil............................................................................................................................... 12
2.2.2 Aggregates: .................................................................................................................. 13
2.3 Earthworks.......................................................................................................................... 14
2.3.1 Site Investigation ......................................................................................................... 14
2.3.2 Clearing and grubbing.................................................................................................. 14
2.3.3 Excavation.................................................................................................................... 15
2.3.4 Cut and fill ................................................................................................................... 15
2.3.5 Embankments............................................................................................................... 15
2.4 Asphalt Concrete Works..................................................................................................... 16
iv
2.4.1 Terms used................................................................................................................... 16
2.4.2 Pavement Surface Preparation ..................................................................................... 17
2.4.3 Mix Transport .............................................................................................................. 19
2.4.4 Mix placement ............................................................................................................. 19
2.4.5 Compaction.................................................................................................................. 22
2.4 Field Inspection................................................................................................................... 25
2.5 Drainage Structures............................................................................................................. 26
2.5.1 Objective of Drainage.................................................................................................. 26
2.5.2 Hydraulic Structures .................................................................................................... 26
2.5.3 Terms used................................................................................................................... 26
2.5.5 Culverts........................................................................................................................ 28
2.5.6 Culvert installation....................................................................................................... 28
2.5.7 Sub-surface drainage.................................................................................................... 30
2.6 Surveying............................................................................................................................ 31
2.6.1 Major survey operations .............................................................................................. 32
2.6.2 Surveying terms ........................................................................................................... 34
CHAPTER THREE: PRACTICAL WORKS............................................................................... 35
3.1 FIELD SURVEY OPERATIONS ...................................................................................... 35
3.1.1 Setting out Road centerline.......................................................................................... 35
3.1.2 Setting out subgrade transverse dimensions ................................................................ 36
3.1.3 Road chaining .............................................................................................................. 36
3.1.4 Setting out levels on offset pegs for construction of a road layer................................ 37
3.1.5 Checking levels on pegs............................................................................................... 38
3.1.6 Checking ground levels for finished road layers ......................................................... 39
3.1.7 Setting out the centerline on a finished road layer....................................................... 40
3.2 Earthworks.......................................................................................................................... 41
3.2.1 Grubbing ...................................................................................................................... 41
3.2.2 Cutting.......................................................................................................................... 41
3.2.3 Filling........................................................................................................................... 42
3.2.4 Laying the subbase layer.............................................................................................. 44
3.2.5 Preparing of stone base layer ....................................................................................... 45
v
3.2.6 Checking depth of constructed pavement layers ......................................................... 48
3.3 Insitu Geotechnical tests ..................................................................................................... 48
3.3.1 Dynamic Cone Penetrometer test (DCP)..................................................................... 48
3.3.2 Field density test by sand replacement method ........................................................... 50
3.4 Asphalt Concrete works...................................................................................................... 53
3.4.1 Cleaning....................................................................................................................... 53
3.4.2 Priming process............................................................................................................ 54
3.4.3 Tack coating................................................................................................................. 57
3.4.4 Laying of asphalt concrete surfacing ........................................................................... 59
3.4.5 Checking level of compaction of wearing course........................................................ 61
3.5 DRAINAGE........................................................................................................................ 63
3.5.1 Introduction.................................................................................................................. 63
3.5.2 Drainage Features ........................................................................................................ 64
3.5.3 Cumber (cross slopes).................................................................................................. 64
3.5.4 Roadside ditches .......................................................................................................... 64
CHAPTER FOUR: OBSERVATIONS, CONCLUSIONS AND RECOMMENDATIONS....... 68
4.1 Achievements from the industrial training ......................................................................... 68
4.2 Challenges faced and suggested solutions;......................................................................... 69
4.2.1 By the internship trainee.............................................................................................. 69
4.2.2 By the contractor.......................................................................................................... 69
4.3 Conclusion .......................................................................................................................... 72
CHAPTER FIVE: REFERENCES ............................................................................................... 73
vi
LIST OF FIGURES
Figure 1: Project stakeholder set-up ............................................................................................... 3
Figure 2: Main features of a pavement (Ref: http://visualdictionary.com/) ................................... 7
Figure 3: Components of flexible pavement (Ref: E-info Wiki; Civil and Environmental
Engineering portal) ......................................................................................................................... 9
Figure 4: Generalized perpetual pavement design (Ref: onlinemanuals.txdot.gov)....................... 9
Figure 5: Typical structure of rigid pavement (Ref: Highway Engineering class notes 2015) .... 10
Figure 6: Load transfer mechanism in flexible and rigid pavement (Ref: Handbook for highway
engineering, T.F. Fwa).................................................................................................................. 12
Figure 7: Land clearing and grubbing along the Lubowa Hill View road by 140H Motor grader14
Figure 8: Push roller and truck hitch............................................................................................. 20
Figure 9: Hopper on asphalt paving tractor .................................................................................. 21
Figure 10: Auger distributing HMA ............................................................................................. 21
Figure 11: 8tonne, 1500mm drum width Tandem steel wheel vibratory roller............................ 23
Figure 12: 3 Front, 4 Rear wheel Dynapac Static Pneumatic tyred roller .................................... 24
Figure 13: Humboldt HS-5001EZ Troxler Nuclear Density Gauge............................................. 25
Figure 14: Culvert cross-section................................................................................................... 29
Figure 15: Culvert outlet/inlet....................................................................................................... 30
Figure 16: Setting out involving horizontal control...................................................................... 33
Figure 17: Illustration of dipping along road section.................................................................... 34
Figure 18: Using GPS to locate centerline of existing road.......................................................... 35
Figure 19: Labelling chainages along road................................................................................... 37
Figure 20: A cut section reduced to the designed road formation ................................................ 41
Figure 21: Excavation and removal of unwanted material for dumping ...................................... 42
Figure 22: Filling and compaction during road bed preparation. ................................................. 43
Figure 23: Rock filling at the swamp............................................................................................ 44
Figure 24: Laying of subbase at CH 4+200.................................................................................. 45
Figure 25: Grading stone base and obtaining cross slopes ........................................................... 47
Figure 26: Laying of base layer .................................................................................................... 47
Figure 27: Casing for DCP test equipment................................................................................... 49
Figure 28: Section of constructed base tested for density at CH 2+200 LHS .............................. 51
Figure 29: Excavating hole for testing.......................................................................................... 52
Figure 30: Sand replacement in excavated hole ........................................................................... 52
Figure 31: Cleaning surface in preparation for asphalt paving..................................................... 54
Figure 32: Calibrating primer distributor truck ............................................................................ 55
Figure 33: Precautions to block roads from traffic to avoid work interruptions .......................... 56
Figure 34: Applying primer to the clean base surface .................................................................. 56
Figure 35: Spreading quarry dust on primed surface at section CH 0+300 – CH 1+200............. 57
Figure 36: Cleaning quarry dust off primed surface..................................................................... 57
Figure 37: Marking off longitudinal road dimensions for paving works...................................... 58
vii
Figure 38: Applying tack coat to primed surface.......................................................................... 58
Figure 39: Determining temperature of premix on truck.............................................................. 59
Figure 40: Placing of asphalt concrete.......................................................................................... 60
Figure 41: Taking temperature measurements of placed asphalt concrete using thermocouple .. 61
Figure 42: Testing level of compaction using Troxler moisture density gauge ........................... 62
Figure 43: Drainage features along cross-section......................................................................... 64
Figure 44: Finishing of the Stone pitching of the line drain......................................................... 65
Figure 45: Setting out drainage channel/ trench ........................................................................... 66
Figure 46: Excavation of roadside ditches.................................................................................... 66
Figure 47: Stone pitched trench at CH 0+800 .............................................................................. 67
Figure 48: Site work disruptions and delays from heavy rains flooding excavated trenches and
carry rubbish to the road surface................................................................................................... 70
Figure 49: Some of the disturbances that caused delays along the road....................................... 71
LIST OF TABLES
Table 2: Factors affecting compaction.......................................................................................... 22
Table 3: Pros and Cons of pneumatic tyred rollers (Ref: Russel W. Lenz 2011)......................... 24
Table 4: Specification of Dumping Murrum for the Subbase....................................................... 44
Table 5: Specifications of stone base laying on site ..................................................................... 46
Table 6: The average results obtained CH 0+300 to CH 0+500................................................... 63
viii
ABBREVIATIONS
DCP Dynamic Cone Penetrometer
MoWT Ministry of Works and Transport
GPS Global Positioning System
RTK Real Time Kinematic
BM Benchmark
TBM Temporary Benchmark
PBM Permanent Benchmark
HOC Height of Collimation
CH Chainage
CL Center Line
LHS Left Hand Side
RHS Right Hand Side
RL Reduced Level
E Eastings
N Northings
Z Elevation/ Vertical height from datum
BS Back Sight
FS Fore Sight
IS Intermediate Sight
PPE Personal Protective Equipment
CBR California Bearing Ratio
CRR Crushed Run Rock
HMA Hot Mix Asphalt
MDD Maximum Dry Density
OMC Optimum Moisture Content
MC Medium Cutback
ix
ABSTRACT
A successful industrial training is necessary for the award of a degree of a Bachelor of Science in
Civil engineering. The main aim of the training program was to expose students to a more practical
approach of theoretical concepts learnt at the university
This report depicts the activities carried out during my eight weeks, during the internship period
from 6th
/June to 29th
/August 2015 on the Seguku-Kasenge-Buddo (10 km) road redesign and build
project under Wakiso District Local Government (client). The project was contracted by Abubaker
Technical Services and General Supplies Limited and supervised by UB Consulting Engineers
Limited.
This report involves details of all the activities I was involved in during the internship period.
These have been separated into various sections namely; Introduction, Literature review, and
methodology.
The introduction is made up of objectives of training, brief background on the contractor and
consultant, a project setting layout, a summary of road design specifications as well as the scope
of works
Literature review was compiled on most of the aspects of the site works, from textbooks, internet
and published articles to describe some literal concepts of the works done on site and the theory
underlying most of the field practices carried out during the training. It is made up of pavement
types and properties, materials, theory behind earthworks, pavement layer construction, asphalt
concrete placement and compaction activities, drainage works and field surveying operations
Methodology including Field survey operations, Earthworks, Pavement layer construction,
asphalt works and drainage works
Field surveys involve setting out of road centerline and cross section on formation level, road
chaining, setting up pegs to assist in checking levels on constructed road and final validation works
and checks on finished layers
Earthworks are made up of the processes involved in preparing the subgrade (>95% CBR, 12m
width) for the overlying pavement layers such as grubbing, cutting and filling, rock filling at the
section in the swamp.
x
The process of pavement layer construction and asphalt concrete laying is then described as
required following the design specifications from the subbase (11m width, 170mm depth), base
(9.5m width, 150mm depth) to the wearing course (9m width, 30mm depth).
A description of several field tests carried out such DCP to determine subgrade strength (CBR
value) and bearing capacity, field density test by sand replacement method on compacted layers to
determine level of compaction of base and subbase, and nuclear density gauge tests to determine
level of compaction of asphalt concrete layer.
Drainage works involve the drainage features on site, setting out process, excavation, levelling and
finally stone pitching of the drain surfaces
1
CHAPTER ONE: INTRODUCTION
This report includes a theoretical and technical account of the activities I participated in during my
eight week long industrial training from 6th
June to 29th
July 2016. The information in this report
is based on my personal observations, experience during participation in site activities,
consultation and the theoretical background obtained from the lecture rooms.
1.1 Background
Industrial training is an important part of training to students especially the engineering student
since it prepares the student for real work in the field.
This course introduces students to various technological skills in industries and provides on-the-
job training and exposure. It’s through this kind of training that the student is exposed to the real
application of the theoretical knowledge from the classroom to the field.
1.2 Objectives
 Expose students to practical aspects of engineering and construction activities
 Provide an opportunity to students to relate the knowledge obtained during lectures to
actual field operations
 Create an understanding of the roles played by different project personnel during project
execution
 Enable students learn how to work in a team (casual workers, technicians, engineers, etc).
 Teach students different engineering ethics necessary for career building
 Enhance problem solving capacity of the students using available appropriate technology
and surrounding condition
 Enable students to have a hands-on with tools and equipment not readily available in the
University laboratories and are of great importance in the engineering field
 Enable students appreciate various challenges faced in the field and critical areas
necessitating further research studies.
2
 Create a more imaginative understanding, to students, of concepts taught in lecture rooms,
making the job of a lecturer much easier to carry out
 Equip students with a feel of the work environment away from school, which may in turn
assist them during later decision making concerning aspects of study, work, and life
generally
1.3 Project Setting
The ongoing project is the “DESIGN AND BUILD OF SEGUKU-KASENGE-BUDDO
(10KM) AND LUBOWA (QUALITY SUPERMARKET) HILL VIEW ROAD (2.1KM)
WAKISO DISTRICT LOCAL GOVERNMENT LOT 1”:
CONTRACT NO. WAK1555/WRKS/2015-2016/00002
The contract agreement was made between the Wakiso District local government and Abubaker
Technical Services and General Supplies Limited (Main contractor), to carry out the project of
reconstruction /upgrading and periodic maintenance of Lubowa Quality Supermarket Hill view
Road (2.1 km) and Seguku Busawula Kasenge Buddo Road (10.0 km) LOT 1;
The project was contracted with an assigned duration of 18 months, with an expected starting date
of 26TH/03/2016 and last till 25TH/09/2017.
This project was overall estimated to cost Ushs. 15,188,224,517 ($4,467,125) fully funded by
Government of the Republic of Uganda as a rehabilitation grant.
The Figure 1 below depicts the structure of the stakeholders involved in the ongoing project, which
was deployed as the project sign board:
3
Figure 1: Project stakeholder set-up
1.3.1 Consultant’s Background
The consultants to the project are UB Consulting Engineers Ltd, established in Uganda in 2011
and is operated by indigenous Ugandans. UB Consulting Engineers Ltd. is a leading consultancy
service provider to both private and public sectors in the fields of engineering, management,
computing, architecture and surveying in East Africa, specializing in Materials and Geotechnical
4
Engineering, Structural & Bridge Engineering, Highways Engineering, Hydrology and
Hydraulics, Sociology.
Physical address:
P. O. Box 22509, Kampala | Plot 3, Nasuuna lane, Masanafu, Lugala – Rubaga division
Tel.: +256 200908255 or +256 414-581938
Email: ub@ubconsulting.co.ug | www.ubconsulting.co.ug
1.3.2 Contractor’s Background
The main contractor to whom the project was awarded is Abubaker Technical Services and General
Supplies Limited, commended for its highly qualified and experienced team able to implement
complicated projects and meet the most challenging requirements.
The contractor has also been involved in some of the following projects as part of the company’s
experience:
 Maintenance of Nakivubo channel section (From Jan 2008 to Dec 2009 worth Ushs.867M)
 Periodic Maintenance of Nsambya and Hanlon Roads in Makindye Division (From Aug
2012 to Jan 2013 worth Ushs.3.7Bn)
 Construction of Access Road to Petroleum Directorate Head Office Building in Entebbe
(March 2016 worth Ushs.1.7Bn)
 Construction of Selected Infrastructure sub-projects in Mbarara Municipality (From March
2016 worth Ushs.18Bn)
And over 50 other projects have been contracted successfully by the indigenous company over the
years since 2005.
Physical address:
P.O. Box 29087 Kampala, Uganda
Telephone: +256-392-949990
Email: abutech2002@yahoo.com
The site offices of the contractor were located at CH 2+300, offset 10m on the RHS.
5
Aims of the Project
The major aim of this project is to upgrade the existing gravel road which was ravaged by poor
drainage and has narrow sections to bituminous standards. This is owing to the considerable
increase in the volume of traffic. This will be achieved by;
 Increasing the width of the road.
 Implementing the geometric design for the new road, providing extra widening in corners,
super elevation and busy centers such as towns and trading centers.
 Improving drainage especially in swampy areas through use of rock fill and providing
drainage conduits for example culverts, stone pitched trenches.
1.4 Road design specifications
The following design specifications shown in Table 1 below were adopted in the implementation
of the road construction for the Seguku-Kasenge-Buddo road project
PARAMETER REMARKS
Chainage 0+000 - 10+000
Location Seguku-Kasenge-Buddo
Lane Width 3.5 m
Number of lanes 2
Shoulder Width 1.0 m
Design Speed 50 km/hr
Design Life 10 years
Normal Camber (cross slope) 2.50%
1.5 Scope of works
My training on the Seguku-Kasenge-Buddo road project lasted from 7th
June 2016 to 29th
July
2016. I carried out my training affiliated to the consultant of the project, UB consulting engineers
Ltd.
During the 8-week internship period, I was involved in four major activities, namely:
 Surveying and road setting out
6
 Pavement layer construction and asphalt works
 Insitu pavement layer tests
 Drainage works
7
CHAPTER TWO: LITERATURE REVIEW
2.1 Pavement
A pavement is a structure made up of carefully selected and well-proportioned materials in
different layers designed to transfer loads applied to the surface so that the underlying subgrade
is not overstressed.
The major aims of pavement design are:
 Structure - Provide a structure that has adequate strength to distribute the wheel
loads to the soil without undue deflection, compaction or consolidation.
 Surface - Provide a surface that is adequately stable so as to not deform under traffic load,
is weather resistant, has adequate skid resistance, is adequately smooth and is
sufficiently wear resistant.
The Figure 2 below shows some of the main features of pavement
Figure 2: Main features of a pavement (Ref: http://visualdictionary.com/)
Centerline: Axis along the middle of the road
Lane: Strip of roadway intended to accommodate a single line of moving vehicles
Shoulder: Part of the road outside the carriageway, but at substantially the same level, for
accommodation of stopped vehicles for emergency use, and for lateral support of the
carriageway. It is the unpaved width at edge of road section
Side Drain: A longitudinal drain offset from, and parallel to, the carriageway
Footway: Portion of a road reserved exclusively for pedestrians
8
Subgrade: Is the formation or foundation layer, the structure that must eventually support all
loads that cone onto the pavement
Subbase: Is made up of granular material or stabilized material and it may be used in areas
where frost action is severe, where the subgrade soil is extremely weak, or where construction
working table is needed
Base: This is a layer or layers of very high stability and density. Its principal purpose is to
distribute or spread the stresses created by wheel loads acting on the wearing surface so that
the stresses transmitted to the subgrade will not result in excessive deformation foundation
layer
Road camber: The slope from a high point (typically at the center line of a road) across the
lanes of a highway. It is also called cross fall/cross slope.
Carriageway: Part of the roadway including the various traffic lanes and auxiliary lanes but
excluding shoulders
Roadway: Part of the road comprising the carriageway, shoulders and median
2.1.1 Flexible Pavement
A flexible pavement structure is typically composed of several layers of material with better
quality materials on top where the intensity of stress from traffic loads is high and lower quality
materials at the bottom where the stress intensity is low. Flexible pavements can be analyzed
as a multilayer system under loading.
When hot mix asphalt (HMA) is used as the surface course, it is the stiffest and may contribute
to the pavement strength. The underlying layers are less stiff but are still important to pavement
strength as well as drainage and frost protection (Russel W. Lenz 2011).
When a seal coat is used as the surface course, the base generally is the layer that contributes
most to the structural stiffness. Figure 3 below shows a typical section for a flexible pavement.
9
Figure 3: Components of flexible pavement (Ref: E-info Wiki; Civil and Environmental Engineering portal)
2.1.2 Perpetual Pavement
Perpetual pavement is a term used to describe a long-life structural design. It uses premium
HMA mixtures, appropriate construction techniques and occasional maintenance to renew the
surface. Close attention must be paid to proper construction techniques to avoid problems with
permeability, trapping moisture, segregation with depth, and variability of density with depth.
A perpetual pavement can last 30 years or more if properly maintained.
Figure 4: Generalized perpetual pavement design (Ref: onlinemanuals.txdot.gov)
10
Structural deterioration typically occurs due to either classical bottom-up fatigue cracking,
rutting of the HMA layers, or rutting of the subgrade. Perpetual pavement is designed to
withstand almost infinite number of axle loads without structural deterioration by limiting the
level of load-induced strain at the bottom of the HMA layers and top of the subgrade and using
deformation resistant HMA mixtures (Russel W. Lenz 2011).
2.1.3 Rigid Pavement
A rigid pavement structure is composed of a hydraulic cement concrete surface course and
underlying base and subbase courses. The surface course (concrete slab) is the stiffest layer
and provides the majority of strength. The base or subbase layers are orders of magnitude less
stiff than the PCC surface but still make important contributions to pavement drainage and
provide a working platform for construction equipment (Russel W. Lenz 2011).
A typical structure of a rigid pavement is as shown in the Figure 5 below
Rigid pavements are substantially stiffer than flexible pavements resulting in very low
deflections under loading.
Figure 5: Typical structure of rigid pavement (Ref: Highway Engineering class notes 2015)
2.1.3.1 Jointed Reinforced Concrete Pavement (JRCP)
JRCP uses contraction joints and reinforcing steel to control cracking. Transverse joint spacing
is longer than that for concrete pavement contraction design (CPCD). This rigid pavement
11
design option is no longer widely endorsed because of past difficulties in selecting effective
rehabilitation strategies (Russel W. Lenz 2011).
2.1.3.2 Concrete Pavement Contraction Design (CPCD)
Also known as the Joint Unreinforced Concrete Pavement (JUCP), CPCD uses contraction
joints to control cracking and does not use any reinforcing steel. Transverse joint spacing is
selected such that temperature and moisture stresses do not produce intermediate cracking
between joints (Russel W. Lenz 2011).
2.1.3.3 Continuously Reinforced Concrete Pavement
CRCP provides joint-free design. The formation of transverse cracks at relatively close
intervals is a distinctive characteristic of CRCP. These cracks are held tightly by the
reinforcement and should be of no concern as long as the cracks are uniformly spaced, do not
spall excessively, and a uniform non-erosive base is provided (Russel W. Lenz 2011).
2.1.4 Composite Pavement
A composite pavement is composed of both hot mix asphalt (HMA) and hydraulic cement
concrete. Typically, composite pavements are asphalt overlays on top of concrete pavements.
The HMA overlay may have been placed as the final stage of initial construction, or as part of
a rehabilitation or safety treatment. Composite pavement behavior under traffic loading is
essentially the same as rigid pavement (T.F. Fwa 2006)
2.1.5 Rigid and Flexible Pavement Characteristics
The primary structural difference between a rigid and flexible pavement is the manner in which
each type of pavement distributes traffic loads over the subgrade. A rigid pavement has a very
high stiffness and distributes loads over a relatively wide area of subgrade – a major portion
of the structural capacity is contributed by the slab itself as shown in Figure 6(b) below.
The load carrying capacity of a true flexible pavement is derived from the load-distributing
characteristics of a layered system (Yoder and Witczak, 1975) as shown in Figure 6(a) below.
12
Figure 6: Load transfer mechanism in flexible and rigid pavement (Ref: Handbook for highway engineering,
T.F. Fwa)
2.2 Pavement Materials:
2.2.1 Soil
Soil is any un-cemented or weakly cemented accumulation of mineral particles formed by the
weathering of rocks, the void space between the particles containing water and/or air. (Craig,
2004). Soil is a most important part of the road structure. It is the soil that provides support to
the road from below and therefore it should possess sufficient strength and stability under most
adverse loading and climatic conditions.
Soil used in embankments should be incompressible. This will prevent differential settlement
in the sub-grade, to achieve this incompressibility the soil should be compacted and stabilized
adequately. (Singh, 2004).
Soil index properties
Types of soils vary from place to place and area to area. The index properties of soil are as
follows
Grain size distribution is in coarse grained soils and is determined by sieve analysis. For the
fine grained soils grain size distribution can be analyzed by sedimentation.
Sieve analysis process is sieving a soil sample through the set of sieves kept one over the other,
the largest sieve being at the top and the smallest at the bottom. The soil retained on each sieve
is weighed and expressed as a percentage of the total weight of the sample.
For consistency limits, atterberg’s tests are carried out to determine the consistency and plastic
behavior of the fine soils.
13
Liquid limit: It is the minimum moisture content at which the soil will flow under its own
weight when tapped 25 times in Casegrande apparatus device. This indicates the limit where
soil changes from plastic to liquid state. At this limit of moisture, the effect of cohesion and
internal friction becomes practically zero
Plastic limit: this indicates the percentage of moisture at which the soil sample changes with
decreasing wetness from a plastic to a semi-solid state. It is the maximum water content at
which soils can be rolled into threads approximately 3mm diameter without breaking.
Plastic index: the range of consistency within which soil exhibits plastic properties is called
the plastic range and it is indicated by the plastic index. Plastic index is the numerical
difference between liquid limit and plastic limit.
Shrinkage limit: it is the moisture content expressed as a percentage at which volume change
ceases.
After obtaining the soil limits, the soil is classified using Unified Soil Classification System
(USCS).
2.2.2 Aggregates:
Stone aggregate is a principle material used in pavement construction. In bituminous
pavements, aggregates constitute about 90% of the construction materials. This is the material
primarily responsible for bearing stress occurring on the road and also to resist wear due to
abrasive action of the traffic.
The aggregates are obtained from natural rock. There are soft and hard aggregates. Hard
aggregates are used to resist crushing effects and adverse weather conditions while soft
aggregates are used in gravel roads. Aggregates are specified according to their grain size,
shape, texture and gradation.
Favorable properties of aggregates
 Strength
 Hardness
 Toughness
 Soundness
 Shape of aggregate
 Surface texture and angularity
14
2.3 Earthworks
This refers to all soils material placed below the formation level including improved subgrade
layers, fill and prepared roadbed. It involves site investigation, clearing and grubbing,
excavation, and construction of the embankments, compaction and finishing operations.
(MWHC, 2005). The different classifications of earthworks are described below:
2.3.1 Site Investigation
A site investigation is required to determine the classification and the bearing strength of the
subgrade. The susceptibility of the subgrade to frost heave and the position of the water table
are also required. (Fwa, 2006).
Methods of investigations
 Boring and probing – Involves the determination of the nature of the ground in a geological
structure and recovery of undisturbed samples for laboratory examination.
 Geophysical techniques
2.3.2 Clearing and grubbing
Clearing and grubbing involves the removal of trees, stumps, roots, debris from the area of
excavation and embankment.
Clearing refers the removal of material above the existing ground surface.
Grubbing is the removal of objects to nominal depth below the surface. (MWHC, 2005)
Figure 7: Land clearing and grubbing along the Lubowa Hill View road by 140H Motor grader
15
2.3.3 Excavation
Excavation is the process of loosening and removing rock or earth from its original position
and transporting it to a fill or waste deposit. Excavation involves; road and drainage
excavation, excavation for structures and borrow excavation. (MWHC, 2005)
2.3.4 Cut and fill
A cut is a section of the road where the formation level is below the original ground level
requiring excavations before the construction of the pavement layers as shown in figure 9.
A fill is a portion of a road prism consisting of approved material, which lies on the road bed
and is bounded by embankment side slopes and on which the subgrade is placed as shown
below.
2.3.5 Embankments
Embankments are used in road construction when the vertical alignment of the road has to be
raised above the level of the existing ground to satisfy the design standards, or prevent damage
from surface or ground water. Many embankments are only 0.5-1.5m high, but heights of 5m
may be used on major highways.
Embankment and Pavement Structure
The road embankment and pavement design for the Seguku-Kasenge-Buddo roadway is as
given below:
Table showing the road embankment and Pavement Structure for the project road carriage and
shoulders.
Surfacing 30mm single seal
Base 150mm of Granular Base Course (CRS) compacted to 98% of BS-Heavy
Sub-base 170mm gravel material (Natural Gravel Class G30) compacted to 95%
of BS-Heavy
Improved
Subgrade
250mm improved sub-grade constructed with material of a minimum
quality of G15 Class gravel compacted to 95% of BS-Heavy
Fills Fills constructed with material of a minimum quality of G7 Class gravel
compacted to 93% of BS-Heavy
16
Roadbed 150mm depth after clearing, grubbing and removal of topsoil and/or
other unsuitable material compacted to 93% of BS-Heavy.
2.4 Asphalt Concrete Works
Asphalt concrete mixes are made up of mixtures of aggregate and asphalt cement binder about
95% aggregate by weight, about 75% aggregate by volume ideally, 3-5% air voids
HMA mix designs are carried out to develop an economical blend of aggregates and asphalt
that meet design requirements using the Marshall or Hveem test
Required properties:
 Flexibility due to high binder content of low viscosity
 Short-term loadings elastic properties of binder-aggregate matrix
 Long-term durability
 Sufficient workability: Ease in which material is handled and laid and compacted
 Sufficient strength and stability under traffic loads
 Sufficient air voids
-Upper limit to prevent excessive environmental damage
-Lower limit to allow room for initial densification due to traffic
2.4.1 Terms used
Asphalt is the cementitious material being added as bituminous binder
Asphalt concrete is the asphalt mix in place on the road including levelling and surface courses
during and after spreading and compacting.
Asphalt Mix is the mix after the asphalt mix aggregate and asphalt have been blended together.
Asphalt Mix Design is the laboratory determination of the precise proportions of asphalt,
reclaimed asphalt concrete, additives, and all virgin aggregates to be blended together to meet
the specified properties for the asphalt mix.
Job Mix Formula is the field determination of the precise proportions of asphalt, reclaimed
asphalt concrete, additives, and all virgin aggregates to be blended together to meet the
specified properties for the asphalt mix as produced at the plant (MoWT 2010)
17
2.4.2 Pavement Surface Preparation
2.4.2.1 Surface Condition
The performance of a flexible pavement under traffic is directly related to the condition of the
surface on which the pavement layers are placed. For a full-depth asphalt pavement, if the
condition of the subgrade soil is poor, the ultimate durability of the roadway may be reduced.
For hot mix asphalt (HMA) layers placed on top of a new, untreated granular base course, the
base material should not be distorted by the trucks carrying the mix to the paver. For HMA
placed as an overlay on top of an existing HMA layer, the surface should be free of major
distresses, smooth and clean.
2.4.2.2 Prime Coat - Flexible Pavements
For flexible pavements, the graded subgrade or the top granular base layer may be prepared
with a prime coat. A prime coat is a sprayed application of a cutback (MC-30 or MC-70) or
emulsion asphalt applied to the surface of untreated subgrade or base layers. The prime coat
serves several purposes:
 fills the surface voids and protect the base from weather
 stabilizes the fines and preserve the base material
 promotes bonding to the subsequent pavement layers.
2.4.2.3 Underseals
Existing Surface Preparation for Overlays includes an under seal which is a sprayed application
of asphalt binder (emulsion or hot applied asphalt binder) immediately covered by a layer of
one-sized aggregate. The underseal provides several benefits, such as waterproofing the
surface, sealing small cracks and protecting the underneath surface from solar radiations
2.4.2.4 Existing Surface Preparation for Overlays
The degree of surface preparation for an overlay is dependent on the condition and type of the
existing pavement. Generally, the existing pavement should be structurally sound, level, clean
and capable of bonding to the overlay. To meet these prerequisites, the existing pavement is
usually repaired, leveled, cleaned and then coated with a binding agent. This subsection covers:
 repair
 tack coats.
A tack coat material is an emulsion layer applied between HMA pavement lifts to promote
adequate bonding. If adjacent layers do not bond to one another they essentially behave as
18
multiple independent thin layers - none of which are designed to accommodate the anticipated
traffic-imposed bending stresses. Inadequate bonding between layers can result in
delamination (de-bonding) followed by longitudinal wheel path cracking, alligator cracking,
potholes, and other distresses such as rutting that greatly reduce pavement life.
Application
Tack coats should be applied uniformly across the entire pavement surface and result in more
than about 90% surface coverage. In order for this uniformity to be consistently achieved, all
aspects of the application must be considered and carefully controlled. Specific aspects are:
 the condition of the pavement surface receiving the tack coat
 the application rate
 type of tack coat according to specified standards
Condition of the Pavement Surface Receiving the Tack Coat
The pavement surface receiving the tack coat should be clean and dry to promote maximum
bonding. Emulsified tack coat materials may be applied to cool and/or damp pavement
Since existing and milled pavements can be quite dirty and dusty, their surfaces should be
cleaned off by sweeping, washing or high pressure compressor blowing before any tack coat
is placed, otherwise the tack coat material may bond to the dirt and dust rather than the adjacent
pavement layers. This can result in excessive tracking of the tack coat material. Construction
vehicles and equipment pick up the tack-dirt mixture on their tires and leave the existing
roadway with little or no tack coat in the wheel paths
Application Rate
Tack coat application should result in a thin, uniform coating of tack coat material covering
approximately 90% of the pavement surface (Flexible Pavements of Ohio, 2001).
Too little tack coat can result in inadequate bonding between layers. Too much tack coat can
create a lubricated slippage plane between layers, or can cause the tack coat material to be
drawn into an overlay, negatively affecting mix properties and even creating a potential for
bleeding in thin overlays
Factors considered include:
 Roughness of the pavement surface receiving the tack coat. Rough surfaces require more
tack coat than smooth surfaces.
19
 Distributor vehicle. Several vehicle-related adjustments and settings are critical to
achieving uniform tack coat placement. Essentially the nozzle patterns, spray bar height
and distribution pressure must work together to produce uniform tack coat application.
Other Tack Coat Aspects considered include
 Timing: Generally, a tack coat should be allowed enough time to break and set (emulsion)
before applying the next layer of hot mix asphalt (HMA).
 Tracking: Tracking is the pick-up of tack coat material by vehicle tires. Tracking deposits
tack coat material on adjacent pavement surfaces. In extreme cases, tracking may deposit
enough tack coat material to distort pavement surfaces or hinder a driver's ability to
navigate (Flexible Pavements of Ohio, 2001).
 Traffic on Tack Coats: Generally, traffic should not be allowed on tack coats. When a
tacked road surface is exposed to traffic, the potential exists for reduced skid resistance,
especially during wet weather (Flexible Pavements of Ohio, 2001). When tack coat
surfaces must be opened to traffic, they should be covered with stone-dust/sand to provide
friction and prevent pick-up
2.4.3 Mix Transport
Mix transport can have a large impact on flexible pavement construction quality and efficiency.
Mix characteristics such as laydown temperature, aggregate segregation and temperature (120-
150o
C) differentials are largely determined by transport practices. Key considerations in mix
transport are:
 truck bed cleanliness and lubrication
 proper mix loading techniques in order to prevent aggregate segregation
 haul distance and mix temperature
 timely mix unloading and unloading of the correct mix.
If properly managed, mix transport can successfully move HMA from the production facility
to the paving site with little or no change in mix characteristics
2.4.4 Mix placement
Mix placement involves any equipment or procedures used to place the delivered HMA on the
desired surface at the desired thickness. The basic concept of the asphalt paving involves:
 HMA is loaded in the front,
20
 carried to the rear by a set of flight feeders (conveyor belts),
 spread out by a set of augers,
 then leveled and compacted by a screed.
This set of functions can be divided into two main systems; the tractor (or material feed system
and the screed.
Tractor (Material Feed System)
The tractor contains the material feed system, which accepts the HMA at the front of the paver,
moves it to the rear and spreads it out to the desired width in preparation for screed leveling
and compaction. The basic tractor components are
 Push Roller and Truck Hitch. The push roller is the portion of the paver that contacts the
transport vehicle and the truck hitch holds the transport vehicle in contact with the paver
as shown in Figure 8 below. They are located on the front of the hopper.
Figure 8: Push roller and truck hitch
 Hopper. The hopper is used as a temporary storage area for HMA delivered by the transport
vehicle shown in Figure 9 below
21
Figure 9: Hopper on asphalt paving tractor
 Conveyor. The conveyor mechanism carries the HMA from the hopper to the augers
 Auger. The auger receives HMA from the conveyor and spreads it out evenly over the
width to be paved as in Figure 10 below. There is one auger for each side of the paver and
they can be operated independently
Figure 10: Auger distributing HMA
Screed
The most critical feature of the paver is the self-leveling screed unit, which determines the
profile of the HMA being placed (Roberts et al., 1996). The screed takes the head of HMA
from the material delivery system, strikes it off at the correct thickness and provides initial mat
compaction.
22
2.4.5 Compaction
Compaction is the process by which the volume of air in an HMA mixture is reduced by using
external forces to reorient the constituent aggregate particles into a more closely spaced
arrangement. This reduction of air volume in a mixture produces a corresponding increase in
HMA unit weight, or density (Roberts et al., 1996).
Inadequate compaction results in a pavement with decreased stiffness, reduced fatigue life,
accelerated aging/decreased durability, rutting, raveling, and moisture damage (Hughes, 1989)
Table 1: Factors affecting compaction
ENVIRONMENTAL
FACTORS
MIX PROPERTY
FACTORS
CONSTRUCTION
FACTORS
Temperature Aggregate Rollers
 Ground temperature
 Air temperature
 Wind speed
 Solar flux
 Gradation
 Size
 Shape
 Fractured faces
 Volume
 Type
 Number
 Speed and timing
 Number of passes
 Lift thickness
Asphalt binder Other
 Chemical properties
 Physical properties
 Amount
 HMA production
temperature
 Haul distance
 Haul distance
 Foundation support
2.4.5.1 Compaction Equipment
There are two basic pieces of equipment available for HMA compaction on the Seguku-
Kasenge-Buddo road:
 the steel wheeled roller
 the pneumatic tire roller.
Each piece of equipment compacts the HMA by two principal means:
 By applying its weight to the HMA surface and compressing the material underneath the
ground contact area. Since this compression will be greater for longer periods of contact,
lower equipment speeds will produce more compression.
23
 By creating a shear stress between the compressed material underneath the ground contact
area and the adjacent uncompressed material. When combined with equipment speed, this
produces a shear rate. Lowering equipment speed can decrease the shear rate, which
increases the shearing stress. Higher shearing stresses are more capable of rearranging
aggregate into denser configurations.
Steel Wheel Rollers
Steel wheel rollers are self-propelled compaction devices that use steel drums to compress the
underlying HMA. They can have one, two or even three drums, although tandem (2 drum)
rollers are most often used. The drums can be either static or vibratory
Since asphalt cement binder sticks to steel wheels, most steel wheel rollers spray water on the
drums to prevent HMA from sticking, and are equipped with a transverse bar on each drum to
wipe off HMA. This water will however cool the HMA and can reduce the time available for
compaction. A tandem wheel roller used in the compaction of the asphalt concrete layer as
well as the base and subbase layers is shown in the Figure 11 below.
Figure 11: 8tonne, 1500mm drum width Tandem steel wheel vibratory roller
Some steel wheel rollers are equipped with vibratory drums. Drum vibration adds a dynamic
load to the static roller weight to create a greater total compactive effort. Drum vibration also
reduces friction and aggregate interlock during compaction, which allows aggregate particles
to move into final positions that produce greater friction and interlock than could be achieved
without vibration
Pneumatic Tire Rollers
The pneumatic tire roller is a self-propelled compaction device that uses pneumatic tires to
compact the underlying HMA. Pneumatic tire rollers employ a set of smooth (no tread) tires
24
on each axle. Figure 12 below shows one of the pneumatic rollers used in the compaction of
the wearing course
Asphalt binder tends to stick to cold pneumatic tires but not too hot pneumatic tires. A release
agent (like water) can be used to minimize this sticking
Figure 12: 3 Front, 4 Rear wheel Dynapac Static Pneumatic tyred roller
In addition to a static compressive force, pneumatic tire rollers also develop a kneading action
between the tires that tends to realign aggregate within the HMA. This results in both
advantages and disadvantages when compared to steel wheel rollers
Table 2: Pros and Cons of pneumatic tyred rollers (Ref: Russel W. Lenz 2011)
Advantages Disadvantages
 They provide a more uniform degree of
compaction than steel wheel rollers.
 They provide a tighter, denser surface thus
decreasing permeability of the layer.
 They provide increased density that many
times cannot be obtained with steel
wheeled rollers.
 They compact the mixture without causing
checking (hairline surface cracks) and they
help to remove any checking that is caused
with steel wheeled rollers.
 The individual tire arrangement may cause
deformations in the mat that are difficult or
impossible to remove with further rolling.
Thus, they should not be used for finish
rolling.
 If the HMA binder contains a rubber
modifier, HMA pickup (mix sticking to the
tires) may be so severe as to warrant
discontinuing use of the roller.
25
2.4.5.2 Compaction measurement
Compaction reduces the volume of air in HMA. Therefore, the characteristic of concern is the
volume of air within the compacted pavement. This volume is typically quantified as a
percentage of air voids by volume and expressed as “percent air voids done on a core sample
of the compacted asphalt pavement
These procedures require a small pavement core, which is extracted from the compacted HMA.
Since core extraction is time consuming and expensive, air voids are often measured indirectly
using a portable density-measuring device such as a nuclear density gauge
Figure 13: Humboldt HS-5001EZ Troxler Nuclear Density Gauge
2.4 Field Inspection
Inspection refers to the act of taking keen observations at works in progress and those
completed and making a proper judgment about your observations after which instructions you
give instructions. It is done to ensure the works are of the expected quality through good
workmanship. Look outs include;
 Presence of deleterious materials
 Suitability of the material being used
 Checking compaction
 Checking levels for the different pavement layers
 Checking to find out if the right equipment is used for a particular type of work.
26
2.5 Drainage Structures
Drainage is very important both in relation to road pavement construction and maintenance.
This is the provision made for protecting the road from surface water or sub surface water. If
water is allowed to enter the structure of the road, the pavement will be weakened and will be
much susceptible to damage by traffic
2.5.1 Objective of Drainage
The main objective of drainage is to protect the project road and the adjacent lands against
potential damage from storm water and sub-surface water.
A good drainage system, properly maintained, is vital to the successful operation of a road. It
serves the following purpose;
 To convey storm water from the surface of the carriageway to outfalls;
 To control the level of the water table in the sub-grade beneath the carriageway;
 To intercept ground and surface water flowing towards the road.
2.5.2 Hydraulic Structures
Hydraulic structures in roads include; bridges, box and pipe culverts, side drains, and catch
water drains.
A culvert is a specific type of stream crossing, used generally to convey water flow through
the road prism base. These usually consists of concrete, PVC or steel pipes, or a reinforced
concrete box, placed under the road within an embankment to provide suitable means of
conveying streams, or the contents of side drains under the road with no restrictions on traffic.
The most common shape used is circular, rectangular or square.
On this project, the bigger percentage of the culverts to be used was made of concrete diameter
of 900 mm.
2.5.3 Terms used
 Culvert entrance: The downstream end of a culvert through which water enter to pass
upstream.
 Culvert Exit: The upstream end of a culvert through which water exit to pass upstream
 Culvert Inlet: The upstream end of a culvert through which stream flow enters.
 Culvert Outlet: The downstream end of a culvert through which stream flow discharges.
 Culvert End Structures
27
The Culvert End Structures includes; Head and Wing walls, Aprons, Catch basins and Drop
Inlets. The details of these structures are given below;
Headwall is a concrete, gabion, masonry, or timber wall built around the inlet or outlet of a
drainage pipe or structure to increase inlet flow capacity, reduce risk of debris damage, retain
the fill material and minimize scour around the structure.
Wing wall is a masonry or concrete structures built onto the side of culvert inlet and outlet
headwalls, designed to retain the roadway fill and direct water into and out of the drainage
structure while protecting the road and fill from erosion.
Apron is an extension of the head wall structure built at ground or stream level and designed
to protect the stream bottom from high flow velocities and to safely move water away from the
drainage structure.
Catch Basin - The excavated or constructed basin at the inlet of a culvert cross-drain pipe,
used to store water and direct it into the culvert pipe.
Drop Inlet - Masonry or concrete basin, or a vertical riser on a metal culvert inlet, usually of
the same diameter as the culvert, and often slotted, to allow water to flow into the culvert as
water flow rises around the outside. Drop inlets are often used on ditch relief culverts where
sediment or debris would plug the pipe. A drop inlet also helps control the elevation
2.5.4 Drainage of a Pavement
This is the process of interception and removal of water from over, under and the vicinity of
the pavement. Pavement performance and integrity often depends on the removal of water from
above and below the pavement surface. The principle function of highway drainage is to
remove surface water as rapidly and efficiently as possible from impermeable surfaces. (Fwa,
2006)
Drainage of the pavement has two main components namely:
 Surface drainage,
 Sub-surface drainage.
Surface water can enter the pavement construction through the porous surface, through cracks
that develop as the pavement ages and at the end of the carriage way if it cannot find its way
off the pavement. The following provisions ensure satisfactory surface drainage such that the
service life of the road is not reduced by the damage that can be inflicted by poor drainage on
the road;
28
 Camber (Cross slope): This is a gradient in the cross section of the roadway surface that
makes it possible for water to flow easily across the surface into the side drains or drop
inlets.
 Side slopes: These effects the movement of water from the vicinity of the road into the
roadside ditches.
 Side drains /Roadside ditches: The runoff is allowed to sheet flow across the roadway
surface (affected by the camber) into the roadside ditches from where it can be conveyed
through culverts to a natural stream.
 Curbs, gutters and inlets: The roadside ditches may not always be possible or cost
effective due to right of way restrictions, therefore curbs, gutters and drop inlets are used
to intercept water from the pavement to drains below the surface.
 Culverts and storm drains: These are open end conduits used to convey water from one
side of the roadway through the embankment to the other side of the roadway. A network
or system of conduits used to carry storm water intercepted by inlets is referred to as a
storm drain system.
2.5.5 Culverts
Culverts are closed conduits for passage of runoff from one open channel to another, made
from several types of materials including concrete, plastic, aluminum, and corrugated steel.
Culverts come in several commonly used shapes including circular, box, elliptical, pipe arch,
and arch. Shape selection is based on construction costs, limitations on upstream water surface
elevation, roadway embankment height, and hydraulic performance (FHWA 1985)
Culverts are usually located in existing channel beds. This is generally the cheapest placement
since it involves the least earthwork and re-routing of the water.
2.5.6 Culvert installation
Culvert installation involves excavation, bedding placement, culvert placement, back filling
and finishing. Finishing involves construction of outlet and inlet structures such as head wall,
wing wall, and apron. These end structures are mostly made out of masonry
Culvert cross-section
Figure 2.20 below can show how to determine the design parameters of the cross-section of a
culvert
29
Figure 14: Culvert cross-section
Calculating design parameters
𝑉𝑜𝑙𝑢𝑚𝑒 𝑜𝑓 𝐸𝑥𝑐𝑎𝑣𝑎𝑡𝑖𝑜𝑛 = 𝐷𝑒𝑝𝑡ℎ 𝑜𝑓 𝑒𝑥𝑐𝑎𝑣𝑎𝑡𝑖𝑜𝑛 × 𝑊𝑖𝑑𝑡ℎ × 𝐿𝑒𝑛𝑔𝑡ℎ 𝑜𝑓 𝑐𝑢𝑙𝑣𝑒𝑟𝑡
𝑉𝑜𝑙𝑢𝑚𝑒 𝑜𝑓 𝐵𝑒𝑑𝑑𝑖𝑛𝑔 𝑚𝑎𝑡𝑒𝑟𝑖𝑎𝑙 = 𝐷𝑒𝑝𝑡ℎ 𝑜𝑓 𝑏𝑒𝑑𝑑𝑖𝑛𝑔 × 𝑊𝑖𝑑𝑡ℎ × 𝐿𝑒𝑛𝑔𝑡ℎ 𝑜𝑓 𝐶𝑢𝑙𝑣𝑒𝑟𝑡
𝑋𝑠𝑒𝑐𝑡𝑖𝑜𝑛𝑎𝑙 𝑎𝑟𝑒𝑎 𝑜𝑓 𝑏𝑎𝑐𝑘𝑓𝑖𝑙𝑙 = 𝑋𝑠𝑒𝑐𝑡𝑖𝑜𝑛𝑎𝑙 𝑎𝑟𝑒𝑎 𝑜𝑓 𝑒𝑥𝑐𝑎𝑣𝑎𝑡𝑖𝑜𝑛 − 𝐴𝑟𝑒𝑎 𝑜𝑓 𝑐𝑢𝑙𝑣𝑒𝑟𝑡
𝐴𝑟𝑒𝑎 𝑜𝑓 𝑐𝑢𝑙𝑣𝑒𝑟𝑡 =
𝜋𝐷2
4
𝑤ℎ𝑒𝑟𝑒 𝐷 − 𝐷𝑖𝑎𝑚𝑒𝑡𝑒𝑟 𝑜𝑓 𝑐𝑢𝑙𝑣𝑒𝑟𝑡
𝑉𝑜𝑙𝑢𝑚𝑒 𝑜𝑓 𝑏𝑎𝑐𝑘𝑓𝑖𝑙𝑙 = 𝑋𝑠𝑒𝑐𝑡𝑖𝑜𝑛𝑎𝑙 𝑎𝑟𝑒𝑎 𝑜𝑓 𝑏𝑎𝑐𝑘𝑓𝑖𝑙𝑙 × 𝐿𝑒𝑛𝑔𝑡ℎ 𝑜𝑓 𝐶𝑢𝑙𝑣𝑒𝑟𝑡
Culvert inlet/outlet
Figure 2.21 below shows how to determine the design parameters of the culvert outlet
30
Figure 15: Culvert outlet/inlet
Calculating design parameters
𝑉𝑜𝑙𝑢𝑚𝑒 𝑜𝑓 𝐻𝑒𝑎𝑑 𝑊𝑎𝑙𝑙 = ((𝐴 × 𝐵) − 𝐴𝑟𝑒𝑎 𝑜𝑓 𝐶𝑢𝑙𝑣𝑒𝑟𝑡) × 𝐻𝑒𝑎𝑑 𝑊𝑎𝑙𝑙 𝑇ℎ𝑖𝑐𝑘𝑛𝑒𝑠𝑠
𝑉𝑜𝑙𝑢𝑚𝑒 𝑜𝑓 𝑊𝑖𝑛𝑔 𝑊𝑎𝑙𝑙 = ((
𝐶 + 𝐷
2
) × 𝐸) × 𝑊𝑖𝑛𝑔 𝑊𝑎𝑙𝑙 𝑇ℎ𝑖𝑐𝑘𝑛𝑒𝑠𝑠
𝑉𝑜𝑙𝑢𝑚𝑒 𝑜𝑓 𝐴𝑝𝑟𝑜𝑛 = ((
𝐹 + 𝐺
2
) × 𝐻) × 𝐴𝑝𝑟𝑜𝑛 𝑇ℎ𝑖𝑐𝑘𝑛𝑒𝑠𝑠
2.5.7 Sub-surface drainage
This involves the interception and removal of water from within the pavement.
 Sources of sub-surface water include;
 Shallow water table
 Infiltration through surface cracks
 Capillary rise
 Seepage from the sides of the pavement
 Evaporation and cooling
Ground water will rise beneath any pavement through cuttings or where the water table is near
the surface. Sidelong ground can lead to saturation from surface and sub-soil water flow,
therefore under these circumstances sub- soil drainage should be provided.
31
Traffic loads can create serious problems in the road foundation if it becomes saturated, which
include;
 Reduction in strength of the subgrade, capping layer and unbound sub-base as pore water
pressures are generated and particle interlock is lost.
 Movement of fines within the capping layer and unbound sub-base leading to further loss
of aggregate interlock, loss of strength and possible risk of frost damage.
 Degradation of unbound aggregate generating even more fines.
 Friction between the sub-base and structural layers is reduced, lowering the strength of the
total construction.
 The base of the asphalt layer may be subjected to scouring by water stripping the bitumen,
creating voids and reducing strength. Water can also be forced into micro-cracks leading
to rapid failure.
If the water table is well below the formation level and both the capping layer material and
sub-base have adequate permeability to carry away surface water, it is possible that sub-surface
drainage is not necessary otherwise it should be provided for.
The measures undertaken to provide for sub-surface drainage include;
 Installation of drainage beds in the pavement. These are made of high permeability material
such as sand. During water flows, the water may come with fine materials which gradually
clog the sand layer, impairing its functionality. Therefore, filter layers such as geo-
membranes are installed at the top and bottom of the drainage bed to prevent this.
 Use of transverse perforated drains embedded within the drainage bed
 Use of sand drains to lower the water table.
 Longitudinal French drains.
2.6 Surveying
Surveying may be defined as the art of making measurements of the relative positions of
natural and manmade features on the earth’s surface and presentation of this information either
graphically or numerically (Surveying II class notes 2014).
To most engineers, Surveying is the process of measuring lengths; height differences and
angles on site either for the preparation of large scale plans or in order that engineering works
can be located in their correct positions on ground.
32
Land surveys can also be classified by purpose as follows:
a) Topographic surveys: Used to establish the position and shape of natural and manmade
features over a given area usually for purposes of producing a map of an area
Such surveys are normally classified according to the scale of the final map. Typical scales
are: 1:1000000, 1:50000, 1:10000, 1:1000, 1:500 etc.
b) Cadastral surveys: Undertaken to produce plans of property boundaries for legal purposes.
For instance, in many countries the registration of land ownership is based on cadastral
surveys/plans
c) Engineering surveys: Embrace all the survey work required before, during and after any
engineering works.
d) Hydrographic surveying: Carried out on water bodies like lakes, rivers and oceans. They
involve measuring water depth and investigating the nature of the sea bed in order to
produce navigational charts for mariners. Other uses of hydrographic surveys include:
offshore oil exploration and production, design, construction and maintenance of harbors
and inland water routes, scientific studies etc.
2.6.1 Major survey operations
i) Setting out – This describes the process of establishing on paper designs on ground.
Involves making an alignment for the proposed road using survey equipment. It comprises
pegging out the route, and establishing the width and level of the road.
Setting out involving horizontal control
The process used in establishing horizontal control is one of working from the whole to the
part. This involves starting with a small number of very accurately measured control points
(primary control), which enclose the area in question and then using this to establish
secondary control points from which the design is set out
33
Figure 16: Setting out involving horizontal control
Once established and coordinated, control points can be used with a positioning technique to
set out E, N coordinates of the design points of the proposed structure. They are generally used
following the road centerline as the baseline.
Setting out involving vertical control
To provide a basis for vertical control, all levels on site will normally be reduced to a nearby
Benchmark (BM). The actual BM used is normally agreed upon by the engineer and the
contractor and is termed as the Master Benchmark (MBM). This is used for two main
purposes;
 To establish points of known reduced level near to and on the elements of the
proposed scheme i.e. Temporary Bench marks (TBMs).
 Used to check the reduced level of any nearby BMs and in case of any
discrepancy, their amended values are used.
When coordinated points are set out for horizontal control, the points are often leveled with
reference to either the MBM or TBM to provide vertical control
ii) Leveling – Involves determining the relative difference in elevation between two or more
points by measuring from the ground level to the line of collimation.
iii) Tape and offsetting – Often referred to as chain surveying deriving its name from the fact
that the principal item of equipment traditionally was a measuring chain which has been
replaced by an accurate steel band. (Bannister and Raymond 1998)
34
2.6.2 Surveying terms
Offset: A distance measured perpendicular from the main line of measurement/ a side shoot
measured from the centerline
Benchmark: A height reference point or mark of known level
Line of collimation: Optical axis of a telescope: also the line of sight through an instrument
when set horizontal
Datum: Horizontal, vertical or 3-dimensional coordinate reference definition
Formation level: Excavation level (height) on which permanent works constructed
Profile: A site marker delineating the shape/level etc of a construction element at that location
Total station: A combined distance and angle (electronic) measuring survey instrument
Dipping: This refers to the process of adding a specified magnitude to a given measurement,
to provide room for setting out that measurement on ground or for inspection of setout
measurements
The dipping height for this project is 20cm (0.2m) and it is used to determine the up and down
reduced levels which are then marked off on the two opposite offset pegs at every checkpoint.
Figure 17: Illustration of dipping along road section
Major Survey apparatus used include:
Total station, GPS-RTK, Dumpy level, staff, tape measure, theodolite, travelers, wooden pegs,
tripod stands, hammer and chisel
35
CHAPTER THREE: PRACTICAL WORKS
3.1 FIELD SURVEY OPERATIONS
3.1.1 Setting out Road centerline
The road centerline points, horizontal position and vertical profile design specifications were
provided by the consultant and would be the first feature of the pavement to be set out and act
as a baseline/reference for other activities during the pavement construction
Equipment
 GPS-RTK machine
 Tape measure
 Nails
 Hammer
Procedure
The base station receiver for the GPS machine was set up at known TBM by the chief surveyor,
and switched on
Figure 18: Using GPS to locate centerline of existing road
Coordinates were initially installed in GPS memory as recorded from design documentations
The rover rod, which was now positioned in a global coordinate framework was then carried
off and used to establish known coordinates of the road centerline as read off from the
geometric designs provided initially by the consultant.
36
Along the movement of the rover rod, a known point was traced on the ground, located with
position by accurately horizontally adjusting the rover, until fairly accurate focus was
achieved, with the aid of variable tones of the sounding alarm.
At this centerline point, a nail was hammered into the ground to mark the location of the point
Referring to the same BM location of the base station receiver, points along the entire road
centerline were established at 20m intervals as provided in the geometric designs
3.1.2 Setting out subgrade transverse dimensions
The subgrade cross section, was obtained by use of the marked out centerline and section
details from the provided geometric designs. This was to help determine the cross dimensions
to be cut and levelled for subgrade construction
Equipment
 Wooden pegs
 Tape measure
 Hammer
 Chisel
Procedure
Using a tape measure, a distance of 6m was offset from the initially established centerline
points, measured perpendicular to the longitudinal centerline outline, on both the LHS and
RHS to obtain a 12m wide subgrade section
At each of these offsets, a wooden peg was driven into the ground to demarcate the transverse
dimensions of the road section. A chisel was used to create a hole in the ground in cases where
the ground was too hard to be penetrated by wooden peg alone
3.1.3 Road chaining
This involved writing out chainage numbers along road length as established in the initial
surveying activities. This was done with the main aim of providing labels along the road length,
which would in turn ease locating specified points along the road in the field, most especially
during inspection and further surveys.
Equipment
 Weather resistant, visually clear paint (white)
 Tape measure
37
 Paint brush
Procedure
Along the road length, from the start, the road was labelled with respect to the chainage
distances to the end point
From the first nail, labelled CH0+000, the chainages were written on fairly permanent
structures on the road side that were anticipated to last quite as long as the road design life, in
order to provide them to be used at a later time in case of road maintenance works or repairs
Chainages were written on walls of houses, trees, fences, etc, located outside the road reserve
in the most practically visible places, for easy spotting appropriate depending on the location
Figure 19: Labelling chainages along road
3.1.4 Setting out levels on offset pegs for construction of a road layer
Equipment
 Automatic level
 Tripod stand
 Staff
 Tape measure
 Marker
 Change point
38
Procedure
The automatic level was setup on the tripod stand at a convenient height, centered, leveled and
focused.
A BS reading was taken on a known nearby BM and the height of collimation (HOC)
calculated.
𝐻𝑂𝐶 = 𝐵𝑆 + 𝑅𝐿 𝑜𝑓 𝐵𝑒𝑛𝑐ℎ𝑚𝑎𝑟𝑘
The required down and up staff readings (including 0.2m for dipping) were calculated from;
𝑅𝑒𝑞𝑢𝑖𝑟𝑒𝑑 𝑢𝑝 𝑜𝑟 𝑑𝑜𝑤𝑛 𝑠𝑡𝑎𝑓𝑓𝑟𝑒𝑎𝑑𝑖𝑛𝑔
= 𝐻𝑂𝐶 − 𝐷𝑒𝑠𝑖𝑔𝑛 𝑢𝑝 𝑜𝑟 𝑑𝑜𝑤𝑛 𝑅𝐿 (𝑖𝑛𝑐𝑙𝑢𝑑𝑖𝑛𝑔 20𝑐𝑚 𝑑𝑖𝑝𝑝𝑖𝑛𝑔)
The staff was then held by the chainman on top of the peg, and then oriented vertically along
the length of the peg until the required staff reading was observed through the automatic level
The point at the bottom of the staff was then marked on the two pegs at each chainage using a
marker.
Change points were made after every appropriate distance, approximately 30m to ensure
intervisibility between points of sight
A foresight (FS) was then taken on a nearby benchmark as a check at the end of the survey, to
check for the margin of error.
3.1.5 Checking levels on pegs
Equipment
 Automatic level,
 Tripod
 Calibrated staff
Procedure
The instrument (automatic level) was setup at a convenient height, centered, leveled and
focused.
A back sight (BS) reading was taken on a leveling staff held vertically at a benchmark (known
reduced level) and the height of the height of collimation (H.O.C) calculated from,
𝐻𝑂𝐶 = 𝐵𝑆 + 𝑅𝐿 𝑜𝑓 𝐵𝑒𝑛𝑐ℎ𝑚𝑎𝑟𝑘
The required upper and down staff readings (including 0.2m for dipping) to be checked for
were calculated from,
39
𝑅𝑒𝑞𝑢𝑖𝑟𝑒𝑑 𝑢𝑝 𝑜𝑟 𝑑𝑜𝑤𝑛 𝑠𝑡𝑎𝑓𝑓𝑟𝑒𝑎𝑑𝑖𝑛𝑔
= 𝐻𝑂𝐶 − 𝐷𝑒𝑠𝑖𝑔𝑛 𝑢𝑝 𝑜𝑟 𝑑𝑜𝑤𝑛 𝑅𝐿 (𝑖𝑛𝑐𝑙𝑢𝑑𝑖𝑛𝑔 20𝑐𝑚 𝑑𝑖𝑝𝑝𝑖𝑛𝑔)
Intermediate sights (IS) were taken on the already marked up and down levels on the pegs on
both the Left Hand Side (L.H.S) and Right Hand Side (R.H.S) of each marked peg checkpoint
to check whether they corresponded with the calculated required up/down staff readings and
the necessary corrections made using a marker.
The leveling staff would be held in contact with face of the peg and the chainman would be
directed by the surveyor to move the staff up and down until the calculated staff readings were
in focus at the cross hairs.
A foresight (FS) reading was taken on a nearby benchmark as a check that is,
𝑅𝑒𝑑𝑢𝑐𝑒𝑑 𝑙𝑒𝑣𝑒𝑙 𝑜𝑓 𝑏𝑒𝑛𝑐ℎ𝑚𝑎𝑟𝑘 = 𝐻𝑂𝐶 − 𝐹𝑆
3.1.6 Checking ground levels for finished road layers
This was done to ensure that the levels achieved during construction of the road layer
corresponded to those provided in the designs provided by the consultant.
Equipment
 Automatic level
 Tripod
 Leveling staff
 Fiber tape measure,
 Change point (CP)
 Nails.
Procedure
The instrument was setup on a tripod stand at a convenient height, centered, leveled and
focused.
A back sight (BS) reading was taken to a leveling staff held vertically at a nearby benchmark
and the height of collimation (H.O.C) calculated.
𝐻𝑂𝐶 = 𝐵𝑆 + 𝑅𝐿 𝑜𝑓 𝐵𝑒𝑛𝑐ℎ𝑚𝑎𝑟𝑘
Intermediate sights (IS) were taken along each chainage on the L.H.S and R.H.S at points
defining the end of the carriageway and shoulder as well as the centerline.
The reduced levels of these five points were calculated for every chainage from,
40
𝑅𝑒𝑑𝑢𝑐𝑒𝑑 𝑙𝑒𝑣𝑒𝑙 = 𝐻𝑂𝐶 − 𝐼𝑆
These measured reduced levels were compared with the design values for these five points
along each chainage and the discrepancy/error between the corresponding readings calculated
from,
𝐸𝑟𝑟𝑜𝑟 = 𝐷𝑒𝑠𝑖𝑔𝑛 𝑅𝐿 − 𝑀𝑒𝑎𝑠𝑢𝑟𝑒𝑑 𝑅𝐿
Therefore, a positive error indicates a fill (material should be brought and compacted in that
section to make up for the difference) and a negative difference indicates a cut (material should
be cut away from the section).
Requirements
The allowable difference was +/-20mm (0.02m)
3.1.7 Setting out the centerline on a finished road layer
The purpose of setting out centers on a finished road layer is to enable the placement of offset
pegs for construction of the next layer and they are also used in taking cross-sections/layouts
along chainage.
Equipment
 Total station,
 Rod with reflector prism,
 Steel tape,
 Tripod, nails,
 Metallic hammer
Procedure
The total station was set up on the tripod stand at a convenient height, centered, leveled and
focused. The instrument was traversed on the nearby benchmark as a check.
For each chainage, the horizontal angle was set to 0°00’00’’ and the instrument fixed.
The rod with reflector prism was then moved to and fro in the road way by a chainman directed
by the surveyor looking through the telescope until the horizontal distance reading on the
screen of the instrument was 0.00m.
These points were marked on ground using nails and these were the points forming the
centerline of the road way between chainages under investigation.
The instrument was then traversed on a nearby benchmark (FS) as a check.
41
Note: The coordinates of all the benchmarks and center points were initially already stored in
the total station.
3.2 Earthworks
These involved all the work done right from bush clearing and grubbing to the finishing of the
subgrade layer. It involved site investigation, excavation, compaction and finishing work as
well as cuts and fills, road bed and removal to spoil of unsuitable or surplus material
3.2.1 Grubbing
Grubbing was done to a depth of 150-200mm. the machines used included bull dozers,
excavators, wheel loaders, dumper trucks and excavator hammers. It was carried out mainly
 To prepare the surface for top soil stripping and excavation.
 Create working space for the equipment
 Remove harmful insects and animals to the workforce.
3.2.2 Cutting
It is the process by which a raised section in the designed road width was reduced to attain the
formation level for the pavement. Prior to cutting, levels were set by the surveyors on the pegs
defining the slope on the design. Cutting began from the top slopping down using the bulldozer
and finishes on the slope were done using the grader with its blade set to the required slopes.
Figure 20: A cut section reduced to the designed road formation
42
Cut to Spoil: Any material with a CBR less than 7% was considered unsuitable for use in the
construction processes so it was permanently removed and dumped away from the pavement
width.
Figure 21: Excavation and removal of unwanted material for dumping
3.2.3 Filling
Filling is the process by which the road bed was raised in a low lying area to flash with the
formation level or the existing road bed. It involved the use of natural gravel material of
minimum California Bearing Ratio (CBR) of 7% (G7 materials) from the existing ground level
or imported material being compacted to refusal density in layers of not greater 200mm.
43
Figure 22: Filling and compaction during road bed preparation.
Fill /Bed road treatment
Since Seguku-Kasenge-Buddo area are raised areas their water table are low and have less
underground streams, the process of bed road treatments was needed in a few valleys order to
make the water move easily horizontal below the yet to be laid pavement, this is done by
establishing French drains and rock fills and the following was done;
 Locate areas along the road that have underground springs and then dig up any loose soils
to a depth of 4.5m manually using pick axe, spades, and hoes. The ditch is made in regular
shape for example a cubical ditch
 Boulders and rocks are placed in this ditch until it is almost full, it then blinded with small
rocks and seal off with coarse sand on top. a steel drum roller is pass over the coarse sand
layer to partially compact the rocks and consequently the coarse sand layer
 A dump proof membrane (polythene paper) of gauge thickness 1000µm is placed on
partially compacted layer, murram is poured over the DPC, spread, and water is sprinkled
and mixed to attain optimal moisture content and finally compacted using a hand roller.
44
Figure 23: Rock filling at the swamp
3.2.4 Laying the subbase layer
Gravel/murrum to be used was first tested in the laboratory for moisture content, MDD&OMC,
through the proctor test, as well as sieve analysis and approved from a given borrow pit.
Borrow pits with soil found to have the desired qualities were then excavated to obtain the
gravel required in bulk quantities, and transported to the project site to be applied in the laying
of the subbase.
Murrum was heaped at specific distances apart depending on calibrated intervals from relation
between the volume of the dumping trucks and layer thickness, for the subbase
Table 3: Specification of Dumping Murrum for the Subbase
Vol. of
truck
Thickness of
layer
Width of layer/lane Distance between 4m3
heaps
8m3
170mm 5.5m 4m
The murrum was then spread along the road cross section using the blade of the grader
45
Levels are then taken using an automatic level and the pegs are put on either sides of the road
bearing marks for the sub grade level, the camber level and deep.
Then a process of dipping was carried out with the help of a string and a steel tape, this helps
to establish road cross slope and also checks regions that need a cut or a fill
Dipping height used was 200mm. If the string placed on either pegs and the string was above
the 200mm height mark that region needed a fill, if the string is below the 200mm mark that
region needed a cut
Using the blade of the grader again a cut and a fill could be done until the required thickness
and slope of the road camber could be achieved.
Water was then sprinkled along the road using a water bowser at a specified rate, which
depends on the discharge at the sprinkling bar and the speed of the water bowser which were
0.01m3
/s and 15km/h in order to achieve Optimal Moisture Content (OMC).
Finally, the moist murram was heavily compacted using the tandem drum roller following
monitored number of passes over layer to achieve Maximum Dry Density (MDD).
Figure 24: Laying of subbase at CH 4+200
3.2.5 Preparing of stone base layer
Gravel soils in the base layer were stabilized using crushed rock containing 40% CRR content
and 60% gravel soil to form a highly rigid, strong and stable base layer.
46
The process of stabilization is always carried out to make the base coarse strong and durable
by binding the crushed rock (CRR) and gravel particles together. The mixture is bound firmly
forming a solid matrix when compacted well.
Table 4: Specifications of stone base laying on site
Vol
of
heaps
Thickness
of CRR
Thickness
of gravel
Base
thickness
Width of
base/lane
Intervals
between
CRR
Intervals
between
gravel
4m3
90mm 60mm 150mm 4.75m 5m 9m
Heaps of components of the base layer were placed independently. Heaps of CRR were
positioned to the finished subbase, spread out with the grader blade to provide a temporarily
motorable surface for delivery trucks and then gravel was then delivered and heaps piled as
shown in the table above
The grader first spread the crushed rock to a depth of 90mm along the road, another layer of
murram is spread at a depth of 60mm using a grader. The road was then scarified using the
back forks of the grader to mix the placed crushed stone and murram.
Water was the sprinkled along the road using a water bowser and the mixed thoroughly until
the base is uniform.
The dipping process was then carried out to find out regions that need a cut or fill, also road
cambers are established at the same time using a grader to obtain a road thickness of 150mm.
47
Figure 25: Grading stone base and obtaining cross slopes
More water was sprinkled using a water bowser until the stabilized base is has achieved optimal
moisture content, and finally heavily compacted using a tandem steel drum roller to achieve
MDD as determined in the laboratory.
Figure 26: Laying of base layer
(a) The grader plate spreading CRR (b) Blended layer of CRR and gravel (c) Spreading of gravel material (d)
Water pump spraying water in blended mixture to be compacted
48
3.2.6 Checking depth of constructed pavement layers
The depth of constructed pavement layers was checked manually along 100m intervals by a
shallow excavation/ coring process where a section along the road length was cored using a
pick axe, making an excavation of 𝐷𝑖𝑎𝑚𝑒𝑡𝑒𝑟 ≈ 50𝑚𝑚
The hole was dug to a 𝐷𝑒𝑝𝑡ℎ ≥ 350𝑚𝑚 and with the help of a steel tape, the depth of each
layer was observed and noted, as a validation check to determine whether the depth of each
layer conforms to the standards
3.3 Insitu Geotechnical tests
3.3.1 Dynamic Cone Penetrometer test (DCP)
The DCP test was carried out on Insitu soils to establish the strength of the existing subgrade,
and its ability to support traffic loads without risk of failing under bearing capacity or
settlement
Objective
To determine the mechanical properties of existing pavement layers for use in structural
pavement design and to provide a measure of a material’s insitu resistance to penetration.
Principle
The underlying principle of the DCP is that the rate of penetration of the cone, when driven by
a standard force, is inversely proportional to the strength of the material for example in the
CBR test. Where the pavement layers have different strengths, the boundaries between the
layers can be identified and the thickness of the layers determined
Reference
BS 5930:1999
Equipment
 DCP machine
Bottom rod, top rod (hammer shaft), falling hammer (8kgs falling through 575mm), meter rule,
60° cone.
Refer to figure 3.20 for DCP apparatus.
 Road safety wear and equipment for traffic control
49
Figure 27: Casing for DCP test equipment
The DCP machine was assembled appropriately with the cone firmly screwed to the bottom
rod with a spanner, and clamp ring was fastened using alley keys, the meter rule placed in
position and set up at the position where test was required
The initial meter rule reading was recorded, the weight lifted till it touches the handle, and left
to fall freely along the hammer shaft onto the coupling to make the first blow
The depth achieved after a number of blows was read off the meter rule was recorded
10 or 5 blows were normally satisfactory for good quality strong layers
1 or 2 blows were appropriate on meeting fairly weaker subbase and subgrade layers
Analysis of results
DCP results were analysed using the UK DCP version 3.1 software. Raw data was entered into
the program and analysis done; this program was chosen because it automatically generates
the thickness of layers with uniform strength. A change in gradient indicates a point of change
from one layer to another. The graphs were used to ascertain the depth of layers with uniform
strengths by noting uniformity in gradient
CBR values were evaluated using DCP results using the expression (Ref: http://civilblog.org)
log10 𝐶𝐵𝑅 = 2.48 − 1.057 log10(𝐷𝐶𝑃 𝑣𝑎𝑙𝑢𝑒)
50
3.3.2 Field density test by sand replacement method
Introduction
The dry density of compacted soil or pavement material is a common measure of the amount
of the compaction achieved. Knowing the field density and field moisture content, the dry
density is calculated.
It is one of the several methods to determine field density, as well as core cutter method, sand
replacement, rubber balloon, heavy oil method, etc.
The sand replacement procedure was carried out on at intervals along the road length, where
the base layer had been finished.
Objective
To determine the field density of compacted base layer by sand replacement method
References
IS: 2720- PART-28
Principle
The basic principle is to measure the insitu volume of a hole from which the material was
excavated from the weight of sand with known density filling the hole. The insitu density of
the material is given by the weight of the excavated material divided by the insitu volume
Required equipment
 Sand pouring cylinder
Large capacity 16.5litres, 200mm diameter, 610mm length
Medium: Capacity 150mm diameter, length 450mm
 Leveling, excavating and scooping tools; Hand tools like scraper, hammer and chisel
 Metal trays, some intact and with holes in middle 150mm diameter
 Sand
 Test sieves; 600mm and 300mm and 75µm aperture
 Balance 30kgs, accuracy 1g
 Air tight bags
 Glass plate
Test procedure
Sand calibration
51
Sand to be used in the test is obtained from a borrow pit and washed on a 75µm sieve to
eliminate silt sized particles, then spread out on a clean surface to sundry for 36 hours
The sand is then sieved through a setup of 600mm and 300mm sieves, and material retained
on the 300mm sieve was transferred to a metal pan and the rest discarded
A mass of 16kgs of sand is poured into the sand pouring cylinder with a cone of known capacity
placed on a glass plate, and the shutter opened
The shutter is then opened, sand left to pour into the cone of known volume and the remaining
sand in the cylinder is weighed
𝑀𝑎𝑠𝑠 𝑜𝑓 𝑠𝑎𝑛𝑑 𝑖𝑛 𝑐𝑜𝑛𝑒 = 𝑀𝑎𝑠𝑠 𝑝𝑜𝑢𝑟𝑒𝑑 − 𝑀𝑎𝑠𝑠 𝑙𝑒𝑓𝑡 𝑖𝑛 𝑡ℎ𝑒 𝑐𝑦𝑙𝑖𝑛𝑑𝑒𝑟 𝑎𝑓𝑡𝑒𝑟 𝑝𝑜𝑢𝑟𝑖𝑛𝑔
𝐷𝑒𝑛𝑠𝑖𝑡𝑦 𝑜𝑓 𝑠𝑎𝑛𝑑 =
𝑀𝑎𝑠𝑠 𝑜𝑓 𝑠𝑎𝑛𝑑 𝑖𝑛 𝑐𝑜𝑛𝑒
𝑉𝑜𝑙𝑢𝑚𝑒 𝑜𝑓 𝑡ℎ𝑒 𝑐𝑜𝑛𝑒
The procedure is repeated using different sized sand pouring cylinders, and the average density
from the different tests is determined
Measurement of field density
An area was leveled and cleared in the open field and a tray was placed on the levelled surface
Figure 28: Section of constructed base tested for density at CH 2+200 LHS
52
A circular hole of approximately 15cm diameter (size of the tray hole) was excavated 20cm
deep (depth of calibrating container) and all the excavated soil was collected in an airtight bag.
Figure 29: Excavating hole for testing
The weight of the excavated soil was recorded
The sand pouring cylinder was refilled, weighed, the tray removed and the sand pouring
cylinder placed over the hole.
The shutter was opened and the sand left to run out into the hole.
The shutter of the cylinder was closed when no further movement was seen.
The cylinder was removed and the mass of the sand pouring cylinder with the remaining sand
was determined
Figure 30: Sand replacement in excavated hole
A representative sample of the excavated material was kept for moisture content determination
Analysis of results
The field density of the insitu pavement layer was determined from the expressions below
53
𝐷𝑒𝑛𝑠𝑖𝑡𝑦 𝑜𝑓 𝑠𝑎𝑛𝑑 =
𝑊𝑒𝑖𝑔ℎ𝑡 𝑜𝑓 𝑠𝑎𝑛𝑑 𝑖𝑛 𝑐𝑜𝑛𝑒
𝑉𝑜𝑙𝑢𝑚𝑒 𝑜𝑓 𝑐𝑜𝑛𝑒
(𝑔/𝑐𝑚3
)
𝐹𝑖𝑒𝑙𝑑 𝑑𝑒𝑛𝑠𝑖𝑡𝑦 𝑜𝑓 𝑒𝑥𝑐𝑎𝑣𝑎𝑡𝑒𝑑 𝑠𝑜𝑖𝑙 =
𝑊𝑒𝑖𝑔ℎ𝑡 𝑜𝑓 𝑠𝑜𝑖𝑙 𝑒𝑥𝑐𝑎𝑣𝑎𝑡𝑒𝑑 𝑓𝑟𝑜𝑚 𝑠𝑜𝑖𝑙
𝑉𝑜𝑙𝑢𝑚𝑒 𝑜𝑓 𝑠𝑎𝑛𝑑 𝑓𝑖𝑙𝑙𝑖𝑛𝑔 𝑒𝑥𝑐𝑎𝑣𝑎𝑡𝑒𝑑 ℎ𝑜𝑙𝑒
(𝑔/𝑐𝑚3
)
Where
𝑉𝑜𝑙𝑢𝑚𝑒 𝑜𝑓 𝑠𝑎𝑛𝑑 𝑓𝑖𝑙𝑙𝑖𝑛𝑔 ℎ𝑜𝑙𝑒 =
𝑊𝑒𝑖𝑔ℎ𝑡 𝑜𝑓 𝑆𝑎𝑛𝑑 𝑖𝑛 ℎ𝑜𝑙𝑒
𝐷𝑒𝑛𝑠𝑖𝑡𝑦 𝑜𝑓 𝑠𝑎𝑛𝑑
(𝑐𝑚3
)
This density was then compared to the specifications for the compaction of that particular layer.
The required compactions for each particular layer for the road project, for tests carried out at
CH2+100 were as follows:
 Road bed – 93%
 Subgrade – 95%
 Sub base – 95%
 Base – 98%
In case the field values did not meet the required values then the Ministry of Works and
Transport reserved the right to instruct the contractor to repeat the compaction work.
3.4 Asphalt Concrete works
The laying of the wearing course layer with premix was done following the following procedures:
 Cleaning of the surface
 Priming
 Tack Coating
 Paving of Bituminous mix/Spreading
 Quality testing
 Compacting
3.4.1 Cleaning
Immediately before priming, loose stones were removed, dust and foreign material from the
base surface. It was done using a mechanical broom and high-pressure air jet from compressor.
It was done manually by workers using brooms in some instances where the sweeper truck was
not reliable. Traffic was then kept off the cleaned surface.
54
Figure 31: Cleaning surface in preparation for asphalt paving
3.4.2 Priming process
This is the process of spraying a mixture of bitumen and paraffin along the stabilized base in
order seal off the base or protect the base from being affected by water. The primer used for
the project was grade MC30 (minimum kinematic velocity 30poise at 140o
F). The priming
process involved calibration of the distributor, and spreading of the primer
3.4.2.1 Calibration of priming machine (Marine truck)
Primer is applied onto finished base so as to seal the surface and prevent penetration of water
to the road layers beneath. However, the spray rate needs to be within certain limits so as to
avoid application of excess primer which would cause bleeding or too little primer that would
leave some surface sections exposed. The specified range for this project was (0.8 - 0.9) kg/m2
Equipment
 Metallic trays (30cm by 30cm)
 Weighing scale
 Calculator
Procedure
The weight of the empty trays was measured and recorded.
The trays were placed along the finished base at different positions such that the primer could
be collected from the spray bar of the distributor truck as it drove along.
Each tray and its contents was weighed again and the masses recorded.
2016 internship report
2016 internship report
2016 internship report
2016 internship report
2016 internship report
2016 internship report
2016 internship report
2016 internship report
2016 internship report
2016 internship report
2016 internship report
2016 internship report
2016 internship report
2016 internship report
2016 internship report
2016 internship report
2016 internship report
2016 internship report
2016 internship report

More Related Content

What's hot

ROAD CONSTRUCTION(BITUMEN) SUMMER TRAINING REPORT
ROAD CONSTRUCTION(BITUMEN) SUMMER TRAINING REPORTROAD CONSTRUCTION(BITUMEN) SUMMER TRAINING REPORT
ROAD CONSTRUCTION(BITUMEN) SUMMER TRAINING REPORTssuser5fea8f
 
Highway construction or Road work report
Highway construction or Road work reportHighway construction or Road work report
Highway construction or Road work reportAbdul rahman kureshi
 
SUMMER TRAINING REPORT ON BUILDING CONSTRUCTION
SUMMER TRAINING REPORT ON BUILDING CONSTRUCTIONSUMMER TRAINING REPORT ON BUILDING CONSTRUCTION
SUMMER TRAINING REPORT ON BUILDING CONSTRUCTIONVed Jangid
 
Summer Training Report On Bituminous (Asphalt) Road
Summer Training Report On Bituminous (Asphalt) RoadSummer Training Report On Bituminous (Asphalt) Road
Summer Training Report On Bituminous (Asphalt) Roadshashanksingh593
 
TRAINING REPORT A PROJECT ON ROAD WIDENI...
                       TRAINING REPORT              A PROJECT  ON ROAD WIDENI...                       TRAINING REPORT              A PROJECT  ON ROAD WIDENI...
TRAINING REPORT A PROJECT ON ROAD WIDENI...Pradeep Yadav
 
Industrial Training Report of Construction Site in Civil Engineering
Industrial Training Report of Construction Site in Civil EngineeringIndustrial Training Report of Construction Site in Civil Engineering
Industrial Training Report of Construction Site in Civil EngineeringRAVI KUMAR
 
Traning report on pwd cement concrete road pavement
Traning report on pwd cement concrete road pavementTraning report on pwd cement concrete road pavement
Traning report on pwd cement concrete road pavementNIWASHISH VISWAS
 
Design & Analysis of G+2 Residential Building Using STAAD Pro
Design & Analysis of G+2 Residential Building Using STAAD ProDesign & Analysis of G+2 Residential Building Using STAAD Pro
Design & Analysis of G+2 Residential Building Using STAAD ProPARAS TANEJA
 
REPORT ON SUMMER TRAINING AT PWD(FLEXIBLE PAVEMENTS CONSTRUCTION)
REPORT ON SUMMER TRAINING AT PWD(FLEXIBLE PAVEMENTS CONSTRUCTION)REPORT ON SUMMER TRAINING AT PWD(FLEXIBLE PAVEMENTS CONSTRUCTION)
REPORT ON SUMMER TRAINING AT PWD(FLEXIBLE PAVEMENTS CONSTRUCTION)Ratnesh Kushwaha
 
Summer Internship Report of Civil Engineering in Construction Site
Summer Internship Report of Civil Engineering in Construction SiteSummer Internship Report of Civil Engineering in Construction Site
Summer Internship Report of Civil Engineering in Construction SiteRAVI KUMAR
 
Industrial report for civil engg. training
Industrial report for civil engg. trainingIndustrial report for civil engg. training
Industrial report for civil engg. trainingRam1239
 
Civil engineering internship report
Civil engineering internship reportCivil engineering internship report
Civil engineering internship reportMd Mohsin Mohsin
 
AN INTERNSHIP REPORT ON RESIDENTIAL BUILDING CONSTRUCTION
AN INTERNSHIP  REPORT  ON  RESIDENTIAL  BUILDING  CONSTRUCTIONAN INTERNSHIP  REPORT  ON  RESIDENTIAL  BUILDING  CONSTRUCTION
AN INTERNSHIP REPORT ON RESIDENTIAL BUILDING CONSTRUCTIONAbhishek Singh
 
Industrial Summer Training Report at Construction Site of CPWD
Industrial Summer Training Report at Construction Site of CPWD Industrial Summer Training Report at Construction Site of CPWD
Industrial Summer Training Report at Construction Site of CPWD Alok Mishra
 
Summer internship report on soil testing,Bitumen & aggregate
Summer internship report on soil testing,Bitumen & aggregateSummer internship report on soil testing,Bitumen & aggregate
Summer internship report on soil testing,Bitumen & aggregateAnup singh
 
PROJECT REPORT ON ROAD CONSTRUCTION
PROJECT REPORT ON ROAD CONSTRUCTIONPROJECT REPORT ON ROAD CONSTRUCTION
PROJECT REPORT ON ROAD CONSTRUCTIONGLA University
 
final year civil engineering training report
final year civil engineering training report final year civil engineering training report
final year civil engineering training report Poojan Patel
 
project final year civil
project final year civilproject final year civil
project final year civilAlankar jaiswal
 
Construction of residential building summer training ppt
 Construction of residential building summer training ppt Construction of residential building summer training ppt
Construction of residential building summer training pptSumit Singh
 

What's hot (20)

ROAD CONSTRUCTION(BITUMEN) SUMMER TRAINING REPORT
ROAD CONSTRUCTION(BITUMEN) SUMMER TRAINING REPORTROAD CONSTRUCTION(BITUMEN) SUMMER TRAINING REPORT
ROAD CONSTRUCTION(BITUMEN) SUMMER TRAINING REPORT
 
Highway construction or Road work report
Highway construction or Road work reportHighway construction or Road work report
Highway construction or Road work report
 
SUMMER TRAINING REPORT ON BUILDING CONSTRUCTION
SUMMER TRAINING REPORT ON BUILDING CONSTRUCTIONSUMMER TRAINING REPORT ON BUILDING CONSTRUCTION
SUMMER TRAINING REPORT ON BUILDING CONSTRUCTION
 
Summer Training Report On Bituminous (Asphalt) Road
Summer Training Report On Bituminous (Asphalt) RoadSummer Training Report On Bituminous (Asphalt) Road
Summer Training Report On Bituminous (Asphalt) Road
 
TRAINING REPORT A PROJECT ON ROAD WIDENI...
                       TRAINING REPORT              A PROJECT  ON ROAD WIDENI...                       TRAINING REPORT              A PROJECT  ON ROAD WIDENI...
TRAINING REPORT A PROJECT ON ROAD WIDENI...
 
Industrial Training Report of Construction Site in Civil Engineering
Industrial Training Report of Construction Site in Civil EngineeringIndustrial Training Report of Construction Site in Civil Engineering
Industrial Training Report of Construction Site in Civil Engineering
 
Traning report on pwd cement concrete road pavement
Traning report on pwd cement concrete road pavementTraning report on pwd cement concrete road pavement
Traning report on pwd cement concrete road pavement
 
Design & Analysis of G+2 Residential Building Using STAAD Pro
Design & Analysis of G+2 Residential Building Using STAAD ProDesign & Analysis of G+2 Residential Building Using STAAD Pro
Design & Analysis of G+2 Residential Building Using STAAD Pro
 
REPORT ON SUMMER TRAINING AT PWD(FLEXIBLE PAVEMENTS CONSTRUCTION)
REPORT ON SUMMER TRAINING AT PWD(FLEXIBLE PAVEMENTS CONSTRUCTION)REPORT ON SUMMER TRAINING AT PWD(FLEXIBLE PAVEMENTS CONSTRUCTION)
REPORT ON SUMMER TRAINING AT PWD(FLEXIBLE PAVEMENTS CONSTRUCTION)
 
Summer Internship Report of Civil Engineering in Construction Site
Summer Internship Report of Civil Engineering in Construction SiteSummer Internship Report of Civil Engineering in Construction Site
Summer Internship Report of Civil Engineering in Construction Site
 
Industrial report for civil engg. training
Industrial report for civil engg. trainingIndustrial report for civil engg. training
Industrial report for civil engg. training
 
Civil engineering internship report
Civil engineering internship reportCivil engineering internship report
Civil engineering internship report
 
AN INTERNSHIP REPORT ON RESIDENTIAL BUILDING CONSTRUCTION
AN INTERNSHIP  REPORT  ON  RESIDENTIAL  BUILDING  CONSTRUCTIONAN INTERNSHIP  REPORT  ON  RESIDENTIAL  BUILDING  CONSTRUCTION
AN INTERNSHIP REPORT ON RESIDENTIAL BUILDING CONSTRUCTION
 
Industrial Summer Training Report at Construction Site of CPWD
Industrial Summer Training Report at Construction Site of CPWD Industrial Summer Training Report at Construction Site of CPWD
Industrial Summer Training Report at Construction Site of CPWD
 
Summer internship report on soil testing,Bitumen & aggregate
Summer internship report on soil testing,Bitumen & aggregateSummer internship report on soil testing,Bitumen & aggregate
Summer internship report on soil testing,Bitumen & aggregate
 
PROJECT REPORT ON ROAD CONSTRUCTION
PROJECT REPORT ON ROAD CONSTRUCTIONPROJECT REPORT ON ROAD CONSTRUCTION
PROJECT REPORT ON ROAD CONSTRUCTION
 
final year civil engineering training report
final year civil engineering training report final year civil engineering training report
final year civil engineering training report
 
Internship review (Civil Engineering)
Internship review (Civil Engineering)Internship review (Civil Engineering)
Internship review (Civil Engineering)
 
project final year civil
project final year civilproject final year civil
project final year civil
 
Construction of residential building summer training ppt
 Construction of residential building summer training ppt Construction of residential building summer training ppt
Construction of residential building summer training ppt
 

Similar to 2016 internship report

derrick ampiire intern report with ozone group ltd
derrick ampiire intern report with ozone group ltdderrick ampiire intern report with ozone group ltd
derrick ampiire intern report with ozone group ltdDerrick Ampiire
 
Abshir nur mohamed for print
Abshir  nur mohamed for print Abshir  nur mohamed for print
Abshir nur mohamed for print Avv Inshar
 
ARTIFICIALLY INTELLIGENT FACE DETECTION AND INVESTIGATION SYSTEM BASED ON OPE...
ARTIFICIALLY INTELLIGENT FACE DETECTION AND INVESTIGATION SYSTEM BASED ON OPE...ARTIFICIALLY INTELLIGENT FACE DETECTION AND INVESTIGATION SYSTEM BASED ON OPE...
ARTIFICIALLY INTELLIGENT FACE DETECTION AND INVESTIGATION SYSTEM BASED ON OPE...Valerie Felton
 
INTEGRATED FINANCIAL MANAGEMENT INFORMATION SYSTEM AND FINANCIAL REPORTING EF...
INTEGRATED FINANCIAL MANAGEMENT INFORMATION SYSTEM AND FINANCIAL REPORTING EF...INTEGRATED FINANCIAL MANAGEMENT INFORMATION SYSTEM AND FINANCIAL REPORTING EF...
INTEGRATED FINANCIAL MANAGEMENT INFORMATION SYSTEM AND FINANCIAL REPORTING EF...Kyambogo University, Kampala-Uganda
 
INTEGRATED FINANCIAL MANAGEMENT INFORMATION SYSTEM AND FINANCIAL REPORTING EF...
INTEGRATED FINANCIAL MANAGEMENT INFORMATION SYSTEM AND FINANCIAL REPORTING EF...INTEGRATED FINANCIAL MANAGEMENT INFORMATION SYSTEM AND FINANCIAL REPORTING EF...
INTEGRATED FINANCIAL MANAGEMENT INFORMATION SYSTEM AND FINANCIAL REPORTING EF...Kyambogo University, Kampala-Uganda
 
Work place safety_in_india_research_report_deepgoel
Work place safety_in_india_research_report_deepgoelWork place safety_in_india_research_report_deepgoel
Work place safety_in_india_research_report_deepgoelDeep Goel
 
Aman Tex Industrial Report By Farzana.pdf
Aman Tex Industrial Report By Farzana.pdfAman Tex Industrial Report By Farzana.pdf
Aman Tex Industrial Report By Farzana.pdfFarzana Akter
 
COSMAS turyasingurFINALLS - Copy - Copy.doc
COSMAS turyasingurFINALLS - Copy - Copy.docCOSMAS turyasingurFINALLS - Copy - Copy.doc
COSMAS turyasingurFINALLS - Copy - Copy.docAmanyaSylus
 
ARMLESS CYCLE FOR A PERSON WITHOUT HAND PROJECT REPORT
ARMLESS CYCLE FOR A PERSON WITHOUT HAND PROJECT REPORTARMLESS CYCLE FOR A PERSON WITHOUT HAND PROJECT REPORT
ARMLESS CYCLE FOR A PERSON WITHOUT HAND PROJECT REPORTVanchhitrawat
 
Effectiveness of using Facebook on increasing the brand awareness;
Effectiveness of using Facebook on increasing the brand awareness; Effectiveness of using Facebook on increasing the brand awareness;
Effectiveness of using Facebook on increasing the brand awareness; Tharushika Ruwangi
 
rigid and flexiable pavement of highway Project bbjr report
rigid and flexiable pavement of highway Project bbjr reportrigid and flexiable pavement of highway Project bbjr report
rigid and flexiable pavement of highway Project bbjr reportrakeshchoudhary129
 
A Comparison Between Pre and Post Covid-19 Recruitment Strategies in Tata Con...
A Comparison Between Pre and Post Covid-19 Recruitment Strategies in Tata Con...A Comparison Between Pre and Post Covid-19 Recruitment Strategies in Tata Con...
A Comparison Between Pre and Post Covid-19 Recruitment Strategies in Tata Con...Home
 
Student's Work Experience Program (SWEP) by IGINA PAUL
Student's Work Experience Program (SWEP) by IGINA PAUL Student's Work Experience Program (SWEP) by IGINA PAUL
Student's Work Experience Program (SWEP) by IGINA PAUL iginapaul
 
Internship report
Internship report Internship report
Internship report DiribaEjersa
 

Similar to 2016 internship report (20)

derrick ampiire intern report with ozone group ltd
derrick ampiire intern report with ozone group ltdderrick ampiire intern report with ozone group ltd
derrick ampiire intern report with ozone group ltd
 
4th year final research report
4th year final research report4th year final research report
4th year final research report
 
Abshir nur mohamed for print
Abshir  nur mohamed for print Abshir  nur mohamed for print
Abshir nur mohamed for print
 
ARTIFICIALLY INTELLIGENT FACE DETECTION AND INVESTIGATION SYSTEM BASED ON OPE...
ARTIFICIALLY INTELLIGENT FACE DETECTION AND INVESTIGATION SYSTEM BASED ON OPE...ARTIFICIALLY INTELLIGENT FACE DETECTION AND INVESTIGATION SYSTEM BASED ON OPE...
ARTIFICIALLY INTELLIGENT FACE DETECTION AND INVESTIGATION SYSTEM BASED ON OPE...
 
Connie
ConnieConnie
Connie
 
Diriba Ejersa
Diriba EjersaDiriba Ejersa
Diriba Ejersa
 
Schedule overruns plagia
Schedule overruns plagiaSchedule overruns plagia
Schedule overruns plagia
 
INTEGRATED FINANCIAL MANAGEMENT INFORMATION SYSTEM AND FINANCIAL REPORTING EF...
INTEGRATED FINANCIAL MANAGEMENT INFORMATION SYSTEM AND FINANCIAL REPORTING EF...INTEGRATED FINANCIAL MANAGEMENT INFORMATION SYSTEM AND FINANCIAL REPORTING EF...
INTEGRATED FINANCIAL MANAGEMENT INFORMATION SYSTEM AND FINANCIAL REPORTING EF...
 
INTEGRATED FINANCIAL MANAGEMENT INFORMATION SYSTEM AND FINANCIAL REPORTING EF...
INTEGRATED FINANCIAL MANAGEMENT INFORMATION SYSTEM AND FINANCIAL REPORTING EF...INTEGRATED FINANCIAL MANAGEMENT INFORMATION SYSTEM AND FINANCIAL REPORTING EF...
INTEGRATED FINANCIAL MANAGEMENT INFORMATION SYSTEM AND FINANCIAL REPORTING EF...
 
Work place safety_in_india_research_report_deepgoel
Work place safety_in_india_research_report_deepgoelWork place safety_in_india_research_report_deepgoel
Work place safety_in_india_research_report_deepgoel
 
Aman Tex Industrial Report By Farzana.pdf
Aman Tex Industrial Report By Farzana.pdfAman Tex Industrial Report By Farzana.pdf
Aman Tex Industrial Report By Farzana.pdf
 
COSMAS turyasingurFINALLS - Copy - Copy.doc
COSMAS turyasingurFINALLS - Copy - Copy.docCOSMAS turyasingurFINALLS - Copy - Copy.doc
COSMAS turyasingurFINALLS - Copy - Copy.doc
 
Research Project
Research ProjectResearch Project
Research Project
 
ARMLESS CYCLE FOR A PERSON WITHOUT HAND PROJECT REPORT
ARMLESS CYCLE FOR A PERSON WITHOUT HAND PROJECT REPORTARMLESS CYCLE FOR A PERSON WITHOUT HAND PROJECT REPORT
ARMLESS CYCLE FOR A PERSON WITHOUT HAND PROJECT REPORT
 
Effectiveness of using Facebook on increasing the brand awareness;
Effectiveness of using Facebook on increasing the brand awareness; Effectiveness of using Facebook on increasing the brand awareness;
Effectiveness of using Facebook on increasing the brand awareness;
 
rigid and flexiable pavement of highway Project bbjr report
rigid and flexiable pavement of highway Project bbjr reportrigid and flexiable pavement of highway Project bbjr report
rigid and flexiable pavement of highway Project bbjr report
 
A Comparison Between Pre and Post Covid-19 Recruitment Strategies in Tata Con...
A Comparison Between Pre and Post Covid-19 Recruitment Strategies in Tata Con...A Comparison Between Pre and Post Covid-19 Recruitment Strategies in Tata Con...
A Comparison Between Pre and Post Covid-19 Recruitment Strategies in Tata Con...
 
1st Report at Nikini Automation1
1st Report at Nikini Automation11st Report at Nikini Automation1
1st Report at Nikini Automation1
 
Student's Work Experience Program (SWEP) by IGINA PAUL
Student's Work Experience Program (SWEP) by IGINA PAUL Student's Work Experience Program (SWEP) by IGINA PAUL
Student's Work Experience Program (SWEP) by IGINA PAUL
 
Internship report
Internship report Internship report
Internship report
 

2016 internship report

  • 1. MAKERERE UNIVERSITY COLLEGE OF ENGINEERING, DESIGN ART & TECHNOLOGY DEPARTMENT OF CIVIL ENGINEERING SCHOOL OF ENGINEERING THIRD YEAR INDUSTRIAL TRAINING REPORT (6TH JUNE TO 29TH JULY 2016) NAME: KAGANZI KENBERT REG NUMBER: 13/U/298 STD NUMBER: 213000715 DEPT SUPERVISOR: FIELD SUPERVISOR: NAME: DR. TUMWESIGYE EMMANUEL NAME: DR. MWESIGE GODFREY SIGNATURE……………………. SIGNATURE:………………………..
  • 2. i DECLARATION I KAGANZI KENBERT declare that this report is personally prepared and compiled by me, and that the contents contained within this report have not been duplicated or published anywhere or submitted to any university for any degree program by a student or any other person, unless indicated. I have personally compiled it based on the experience and training I had under UB consulting engineers Ltd, on the Seguku-Kasenge-Buddo road rebuilding project. NAME: KAGANZI KENBERT REG NO: 13/U/298 STUDENT NO: 213000715 SIGN ………………………………………. DATE ………………………………………
  • 3. ii ACKNOWLEDGEMENTS I would like to thank the management and staff of UB Consulting Engineers Limited for the opportunity they offered me to do undertake training with them I would like to thank the management and staff of Abubaker Technical Services and General Supplies Limited for the opportunity they offered me to do undertake training with them, on top of which they tolerated my mistakes and too many questions as well as the facilitation offered in term of meals. I would like to thank my internship supervisor Dr. Tumwesigye Emmanuel for taking on the responsibility to supervise me during my internship training I would like to thank my parents for their unconditional willingness to meet all of my needs and requirements as per the industrial training period, in terms of funding, advice and personal guidance. Finally, I would like to thank the Almighty God for the knowledge, wisdom, good health, safety and ability he granted because without these, the success of this industrial training would not have been possible.
  • 4. iii Table of Contents DECLARATION............................................................................................................................. i ACKNOWLEDGEMENTS............................................................................................................ii LIST OF FIGURES ....................................................................................................................... vi LIST OF TABLES........................................................................................................................vii ABBREVIATIONS .....................................................................................................................viii ABSTRACT................................................................................................................................... ix CHAPTER ONE: INTRODUCTION............................................................................................. 1 1.1 Background........................................................................................................................... 1 1.2 Objectives ............................................................................................................................. 1 1.3 Project Setting....................................................................................................................... 2 1.3.1 Consultant’s Background............................................................................................... 3 1.3.2 Contractor’s Background............................................................................................... 4 1.4 Road design specifications.................................................................................................... 5 1.5 Scope of works...................................................................................................................... 5 CHAPTER TWO: LITERATURE REVIEW................................................................................. 7 2.1 Pavement............................................................................................................................... 7 2.1.1 Flexible Pavement.......................................................................................................... 8 2.1.2 Perpetual Pavement........................................................................................................ 9 2.1.3 Rigid Pavement............................................................................................................ 10 2.1.5 Rigid and Flexible Pavement Characteristics .............................................................. 11 2.2 Pavement Materials:............................................................................................................ 12 2.2.1 Soil............................................................................................................................... 12 2.2.2 Aggregates: .................................................................................................................. 13 2.3 Earthworks.......................................................................................................................... 14 2.3.1 Site Investigation ......................................................................................................... 14 2.3.2 Clearing and grubbing.................................................................................................. 14 2.3.3 Excavation.................................................................................................................... 15 2.3.4 Cut and fill ................................................................................................................... 15 2.3.5 Embankments............................................................................................................... 15 2.4 Asphalt Concrete Works..................................................................................................... 16
  • 5. iv 2.4.1 Terms used................................................................................................................... 16 2.4.2 Pavement Surface Preparation ..................................................................................... 17 2.4.3 Mix Transport .............................................................................................................. 19 2.4.4 Mix placement ............................................................................................................. 19 2.4.5 Compaction.................................................................................................................. 22 2.4 Field Inspection................................................................................................................... 25 2.5 Drainage Structures............................................................................................................. 26 2.5.1 Objective of Drainage.................................................................................................. 26 2.5.2 Hydraulic Structures .................................................................................................... 26 2.5.3 Terms used................................................................................................................... 26 2.5.5 Culverts........................................................................................................................ 28 2.5.6 Culvert installation....................................................................................................... 28 2.5.7 Sub-surface drainage.................................................................................................... 30 2.6 Surveying............................................................................................................................ 31 2.6.1 Major survey operations .............................................................................................. 32 2.6.2 Surveying terms ........................................................................................................... 34 CHAPTER THREE: PRACTICAL WORKS............................................................................... 35 3.1 FIELD SURVEY OPERATIONS ...................................................................................... 35 3.1.1 Setting out Road centerline.......................................................................................... 35 3.1.2 Setting out subgrade transverse dimensions ................................................................ 36 3.1.3 Road chaining .............................................................................................................. 36 3.1.4 Setting out levels on offset pegs for construction of a road layer................................ 37 3.1.5 Checking levels on pegs............................................................................................... 38 3.1.6 Checking ground levels for finished road layers ......................................................... 39 3.1.7 Setting out the centerline on a finished road layer....................................................... 40 3.2 Earthworks.......................................................................................................................... 41 3.2.1 Grubbing ...................................................................................................................... 41 3.2.2 Cutting.......................................................................................................................... 41 3.2.3 Filling........................................................................................................................... 42 3.2.4 Laying the subbase layer.............................................................................................. 44 3.2.5 Preparing of stone base layer ....................................................................................... 45
  • 6. v 3.2.6 Checking depth of constructed pavement layers ......................................................... 48 3.3 Insitu Geotechnical tests ..................................................................................................... 48 3.3.1 Dynamic Cone Penetrometer test (DCP)..................................................................... 48 3.3.2 Field density test by sand replacement method ........................................................... 50 3.4 Asphalt Concrete works...................................................................................................... 53 3.4.1 Cleaning....................................................................................................................... 53 3.4.2 Priming process............................................................................................................ 54 3.4.3 Tack coating................................................................................................................. 57 3.4.4 Laying of asphalt concrete surfacing ........................................................................... 59 3.4.5 Checking level of compaction of wearing course........................................................ 61 3.5 DRAINAGE........................................................................................................................ 63 3.5.1 Introduction.................................................................................................................. 63 3.5.2 Drainage Features ........................................................................................................ 64 3.5.3 Cumber (cross slopes).................................................................................................. 64 3.5.4 Roadside ditches .......................................................................................................... 64 CHAPTER FOUR: OBSERVATIONS, CONCLUSIONS AND RECOMMENDATIONS....... 68 4.1 Achievements from the industrial training ......................................................................... 68 4.2 Challenges faced and suggested solutions;......................................................................... 69 4.2.1 By the internship trainee.............................................................................................. 69 4.2.2 By the contractor.......................................................................................................... 69 4.3 Conclusion .......................................................................................................................... 72 CHAPTER FIVE: REFERENCES ............................................................................................... 73
  • 7. vi LIST OF FIGURES Figure 1: Project stakeholder set-up ............................................................................................... 3 Figure 2: Main features of a pavement (Ref: http://visualdictionary.com/) ................................... 7 Figure 3: Components of flexible pavement (Ref: E-info Wiki; Civil and Environmental Engineering portal) ......................................................................................................................... 9 Figure 4: Generalized perpetual pavement design (Ref: onlinemanuals.txdot.gov)....................... 9 Figure 5: Typical structure of rigid pavement (Ref: Highway Engineering class notes 2015) .... 10 Figure 6: Load transfer mechanism in flexible and rigid pavement (Ref: Handbook for highway engineering, T.F. Fwa).................................................................................................................. 12 Figure 7: Land clearing and grubbing along the Lubowa Hill View road by 140H Motor grader14 Figure 8: Push roller and truck hitch............................................................................................. 20 Figure 9: Hopper on asphalt paving tractor .................................................................................. 21 Figure 10: Auger distributing HMA ............................................................................................. 21 Figure 11: 8tonne, 1500mm drum width Tandem steel wheel vibratory roller............................ 23 Figure 12: 3 Front, 4 Rear wheel Dynapac Static Pneumatic tyred roller .................................... 24 Figure 13: Humboldt HS-5001EZ Troxler Nuclear Density Gauge............................................. 25 Figure 14: Culvert cross-section................................................................................................... 29 Figure 15: Culvert outlet/inlet....................................................................................................... 30 Figure 16: Setting out involving horizontal control...................................................................... 33 Figure 17: Illustration of dipping along road section.................................................................... 34 Figure 18: Using GPS to locate centerline of existing road.......................................................... 35 Figure 19: Labelling chainages along road................................................................................... 37 Figure 20: A cut section reduced to the designed road formation ................................................ 41 Figure 21: Excavation and removal of unwanted material for dumping ...................................... 42 Figure 22: Filling and compaction during road bed preparation. ................................................. 43 Figure 23: Rock filling at the swamp............................................................................................ 44 Figure 24: Laying of subbase at CH 4+200.................................................................................. 45 Figure 25: Grading stone base and obtaining cross slopes ........................................................... 47 Figure 26: Laying of base layer .................................................................................................... 47 Figure 27: Casing for DCP test equipment................................................................................... 49 Figure 28: Section of constructed base tested for density at CH 2+200 LHS .............................. 51 Figure 29: Excavating hole for testing.......................................................................................... 52 Figure 30: Sand replacement in excavated hole ........................................................................... 52 Figure 31: Cleaning surface in preparation for asphalt paving..................................................... 54 Figure 32: Calibrating primer distributor truck ............................................................................ 55 Figure 33: Precautions to block roads from traffic to avoid work interruptions .......................... 56 Figure 34: Applying primer to the clean base surface .................................................................. 56 Figure 35: Spreading quarry dust on primed surface at section CH 0+300 – CH 1+200............. 57 Figure 36: Cleaning quarry dust off primed surface..................................................................... 57 Figure 37: Marking off longitudinal road dimensions for paving works...................................... 58
  • 8. vii Figure 38: Applying tack coat to primed surface.......................................................................... 58 Figure 39: Determining temperature of premix on truck.............................................................. 59 Figure 40: Placing of asphalt concrete.......................................................................................... 60 Figure 41: Taking temperature measurements of placed asphalt concrete using thermocouple .. 61 Figure 42: Testing level of compaction using Troxler moisture density gauge ........................... 62 Figure 43: Drainage features along cross-section......................................................................... 64 Figure 44: Finishing of the Stone pitching of the line drain......................................................... 65 Figure 45: Setting out drainage channel/ trench ........................................................................... 66 Figure 46: Excavation of roadside ditches.................................................................................... 66 Figure 47: Stone pitched trench at CH 0+800 .............................................................................. 67 Figure 48: Site work disruptions and delays from heavy rains flooding excavated trenches and carry rubbish to the road surface................................................................................................... 70 Figure 49: Some of the disturbances that caused delays along the road....................................... 71 LIST OF TABLES Table 2: Factors affecting compaction.......................................................................................... 22 Table 3: Pros and Cons of pneumatic tyred rollers (Ref: Russel W. Lenz 2011)......................... 24 Table 4: Specification of Dumping Murrum for the Subbase....................................................... 44 Table 5: Specifications of stone base laying on site ..................................................................... 46 Table 6: The average results obtained CH 0+300 to CH 0+500................................................... 63
  • 9. viii ABBREVIATIONS DCP Dynamic Cone Penetrometer MoWT Ministry of Works and Transport GPS Global Positioning System RTK Real Time Kinematic BM Benchmark TBM Temporary Benchmark PBM Permanent Benchmark HOC Height of Collimation CH Chainage CL Center Line LHS Left Hand Side RHS Right Hand Side RL Reduced Level E Eastings N Northings Z Elevation/ Vertical height from datum BS Back Sight FS Fore Sight IS Intermediate Sight PPE Personal Protective Equipment CBR California Bearing Ratio CRR Crushed Run Rock HMA Hot Mix Asphalt MDD Maximum Dry Density OMC Optimum Moisture Content MC Medium Cutback
  • 10. ix ABSTRACT A successful industrial training is necessary for the award of a degree of a Bachelor of Science in Civil engineering. The main aim of the training program was to expose students to a more practical approach of theoretical concepts learnt at the university This report depicts the activities carried out during my eight weeks, during the internship period from 6th /June to 29th /August 2015 on the Seguku-Kasenge-Buddo (10 km) road redesign and build project under Wakiso District Local Government (client). The project was contracted by Abubaker Technical Services and General Supplies Limited and supervised by UB Consulting Engineers Limited. This report involves details of all the activities I was involved in during the internship period. These have been separated into various sections namely; Introduction, Literature review, and methodology. The introduction is made up of objectives of training, brief background on the contractor and consultant, a project setting layout, a summary of road design specifications as well as the scope of works Literature review was compiled on most of the aspects of the site works, from textbooks, internet and published articles to describe some literal concepts of the works done on site and the theory underlying most of the field practices carried out during the training. It is made up of pavement types and properties, materials, theory behind earthworks, pavement layer construction, asphalt concrete placement and compaction activities, drainage works and field surveying operations Methodology including Field survey operations, Earthworks, Pavement layer construction, asphalt works and drainage works Field surveys involve setting out of road centerline and cross section on formation level, road chaining, setting up pegs to assist in checking levels on constructed road and final validation works and checks on finished layers Earthworks are made up of the processes involved in preparing the subgrade (>95% CBR, 12m width) for the overlying pavement layers such as grubbing, cutting and filling, rock filling at the section in the swamp.
  • 11. x The process of pavement layer construction and asphalt concrete laying is then described as required following the design specifications from the subbase (11m width, 170mm depth), base (9.5m width, 150mm depth) to the wearing course (9m width, 30mm depth). A description of several field tests carried out such DCP to determine subgrade strength (CBR value) and bearing capacity, field density test by sand replacement method on compacted layers to determine level of compaction of base and subbase, and nuclear density gauge tests to determine level of compaction of asphalt concrete layer. Drainage works involve the drainage features on site, setting out process, excavation, levelling and finally stone pitching of the drain surfaces
  • 12. 1 CHAPTER ONE: INTRODUCTION This report includes a theoretical and technical account of the activities I participated in during my eight week long industrial training from 6th June to 29th July 2016. The information in this report is based on my personal observations, experience during participation in site activities, consultation and the theoretical background obtained from the lecture rooms. 1.1 Background Industrial training is an important part of training to students especially the engineering student since it prepares the student for real work in the field. This course introduces students to various technological skills in industries and provides on-the- job training and exposure. It’s through this kind of training that the student is exposed to the real application of the theoretical knowledge from the classroom to the field. 1.2 Objectives  Expose students to practical aspects of engineering and construction activities  Provide an opportunity to students to relate the knowledge obtained during lectures to actual field operations  Create an understanding of the roles played by different project personnel during project execution  Enable students learn how to work in a team (casual workers, technicians, engineers, etc).  Teach students different engineering ethics necessary for career building  Enhance problem solving capacity of the students using available appropriate technology and surrounding condition  Enable students to have a hands-on with tools and equipment not readily available in the University laboratories and are of great importance in the engineering field  Enable students appreciate various challenges faced in the field and critical areas necessitating further research studies.
  • 13. 2  Create a more imaginative understanding, to students, of concepts taught in lecture rooms, making the job of a lecturer much easier to carry out  Equip students with a feel of the work environment away from school, which may in turn assist them during later decision making concerning aspects of study, work, and life generally 1.3 Project Setting The ongoing project is the “DESIGN AND BUILD OF SEGUKU-KASENGE-BUDDO (10KM) AND LUBOWA (QUALITY SUPERMARKET) HILL VIEW ROAD (2.1KM) WAKISO DISTRICT LOCAL GOVERNMENT LOT 1”: CONTRACT NO. WAK1555/WRKS/2015-2016/00002 The contract agreement was made between the Wakiso District local government and Abubaker Technical Services and General Supplies Limited (Main contractor), to carry out the project of reconstruction /upgrading and periodic maintenance of Lubowa Quality Supermarket Hill view Road (2.1 km) and Seguku Busawula Kasenge Buddo Road (10.0 km) LOT 1; The project was contracted with an assigned duration of 18 months, with an expected starting date of 26TH/03/2016 and last till 25TH/09/2017. This project was overall estimated to cost Ushs. 15,188,224,517 ($4,467,125) fully funded by Government of the Republic of Uganda as a rehabilitation grant. The Figure 1 below depicts the structure of the stakeholders involved in the ongoing project, which was deployed as the project sign board:
  • 14. 3 Figure 1: Project stakeholder set-up 1.3.1 Consultant’s Background The consultants to the project are UB Consulting Engineers Ltd, established in Uganda in 2011 and is operated by indigenous Ugandans. UB Consulting Engineers Ltd. is a leading consultancy service provider to both private and public sectors in the fields of engineering, management, computing, architecture and surveying in East Africa, specializing in Materials and Geotechnical
  • 15. 4 Engineering, Structural & Bridge Engineering, Highways Engineering, Hydrology and Hydraulics, Sociology. Physical address: P. O. Box 22509, Kampala | Plot 3, Nasuuna lane, Masanafu, Lugala – Rubaga division Tel.: +256 200908255 or +256 414-581938 Email: ub@ubconsulting.co.ug | www.ubconsulting.co.ug 1.3.2 Contractor’s Background The main contractor to whom the project was awarded is Abubaker Technical Services and General Supplies Limited, commended for its highly qualified and experienced team able to implement complicated projects and meet the most challenging requirements. The contractor has also been involved in some of the following projects as part of the company’s experience:  Maintenance of Nakivubo channel section (From Jan 2008 to Dec 2009 worth Ushs.867M)  Periodic Maintenance of Nsambya and Hanlon Roads in Makindye Division (From Aug 2012 to Jan 2013 worth Ushs.3.7Bn)  Construction of Access Road to Petroleum Directorate Head Office Building in Entebbe (March 2016 worth Ushs.1.7Bn)  Construction of Selected Infrastructure sub-projects in Mbarara Municipality (From March 2016 worth Ushs.18Bn) And over 50 other projects have been contracted successfully by the indigenous company over the years since 2005. Physical address: P.O. Box 29087 Kampala, Uganda Telephone: +256-392-949990 Email: abutech2002@yahoo.com The site offices of the contractor were located at CH 2+300, offset 10m on the RHS.
  • 16. 5 Aims of the Project The major aim of this project is to upgrade the existing gravel road which was ravaged by poor drainage and has narrow sections to bituminous standards. This is owing to the considerable increase in the volume of traffic. This will be achieved by;  Increasing the width of the road.  Implementing the geometric design for the new road, providing extra widening in corners, super elevation and busy centers such as towns and trading centers.  Improving drainage especially in swampy areas through use of rock fill and providing drainage conduits for example culverts, stone pitched trenches. 1.4 Road design specifications The following design specifications shown in Table 1 below were adopted in the implementation of the road construction for the Seguku-Kasenge-Buddo road project PARAMETER REMARKS Chainage 0+000 - 10+000 Location Seguku-Kasenge-Buddo Lane Width 3.5 m Number of lanes 2 Shoulder Width 1.0 m Design Speed 50 km/hr Design Life 10 years Normal Camber (cross slope) 2.50% 1.5 Scope of works My training on the Seguku-Kasenge-Buddo road project lasted from 7th June 2016 to 29th July 2016. I carried out my training affiliated to the consultant of the project, UB consulting engineers Ltd. During the 8-week internship period, I was involved in four major activities, namely:  Surveying and road setting out
  • 17. 6  Pavement layer construction and asphalt works  Insitu pavement layer tests  Drainage works
  • 18. 7 CHAPTER TWO: LITERATURE REVIEW 2.1 Pavement A pavement is a structure made up of carefully selected and well-proportioned materials in different layers designed to transfer loads applied to the surface so that the underlying subgrade is not overstressed. The major aims of pavement design are:  Structure - Provide a structure that has adequate strength to distribute the wheel loads to the soil without undue deflection, compaction or consolidation.  Surface - Provide a surface that is adequately stable so as to not deform under traffic load, is weather resistant, has adequate skid resistance, is adequately smooth and is sufficiently wear resistant. The Figure 2 below shows some of the main features of pavement Figure 2: Main features of a pavement (Ref: http://visualdictionary.com/) Centerline: Axis along the middle of the road Lane: Strip of roadway intended to accommodate a single line of moving vehicles Shoulder: Part of the road outside the carriageway, but at substantially the same level, for accommodation of stopped vehicles for emergency use, and for lateral support of the carriageway. It is the unpaved width at edge of road section Side Drain: A longitudinal drain offset from, and parallel to, the carriageway Footway: Portion of a road reserved exclusively for pedestrians
  • 19. 8 Subgrade: Is the formation or foundation layer, the structure that must eventually support all loads that cone onto the pavement Subbase: Is made up of granular material or stabilized material and it may be used in areas where frost action is severe, where the subgrade soil is extremely weak, or where construction working table is needed Base: This is a layer or layers of very high stability and density. Its principal purpose is to distribute or spread the stresses created by wheel loads acting on the wearing surface so that the stresses transmitted to the subgrade will not result in excessive deformation foundation layer Road camber: The slope from a high point (typically at the center line of a road) across the lanes of a highway. It is also called cross fall/cross slope. Carriageway: Part of the roadway including the various traffic lanes and auxiliary lanes but excluding shoulders Roadway: Part of the road comprising the carriageway, shoulders and median 2.1.1 Flexible Pavement A flexible pavement structure is typically composed of several layers of material with better quality materials on top where the intensity of stress from traffic loads is high and lower quality materials at the bottom where the stress intensity is low. Flexible pavements can be analyzed as a multilayer system under loading. When hot mix asphalt (HMA) is used as the surface course, it is the stiffest and may contribute to the pavement strength. The underlying layers are less stiff but are still important to pavement strength as well as drainage and frost protection (Russel W. Lenz 2011). When a seal coat is used as the surface course, the base generally is the layer that contributes most to the structural stiffness. Figure 3 below shows a typical section for a flexible pavement.
  • 20. 9 Figure 3: Components of flexible pavement (Ref: E-info Wiki; Civil and Environmental Engineering portal) 2.1.2 Perpetual Pavement Perpetual pavement is a term used to describe a long-life structural design. It uses premium HMA mixtures, appropriate construction techniques and occasional maintenance to renew the surface. Close attention must be paid to proper construction techniques to avoid problems with permeability, trapping moisture, segregation with depth, and variability of density with depth. A perpetual pavement can last 30 years or more if properly maintained. Figure 4: Generalized perpetual pavement design (Ref: onlinemanuals.txdot.gov)
  • 21. 10 Structural deterioration typically occurs due to either classical bottom-up fatigue cracking, rutting of the HMA layers, or rutting of the subgrade. Perpetual pavement is designed to withstand almost infinite number of axle loads without structural deterioration by limiting the level of load-induced strain at the bottom of the HMA layers and top of the subgrade and using deformation resistant HMA mixtures (Russel W. Lenz 2011). 2.1.3 Rigid Pavement A rigid pavement structure is composed of a hydraulic cement concrete surface course and underlying base and subbase courses. The surface course (concrete slab) is the stiffest layer and provides the majority of strength. The base or subbase layers are orders of magnitude less stiff than the PCC surface but still make important contributions to pavement drainage and provide a working platform for construction equipment (Russel W. Lenz 2011). A typical structure of a rigid pavement is as shown in the Figure 5 below Rigid pavements are substantially stiffer than flexible pavements resulting in very low deflections under loading. Figure 5: Typical structure of rigid pavement (Ref: Highway Engineering class notes 2015) 2.1.3.1 Jointed Reinforced Concrete Pavement (JRCP) JRCP uses contraction joints and reinforcing steel to control cracking. Transverse joint spacing is longer than that for concrete pavement contraction design (CPCD). This rigid pavement
  • 22. 11 design option is no longer widely endorsed because of past difficulties in selecting effective rehabilitation strategies (Russel W. Lenz 2011). 2.1.3.2 Concrete Pavement Contraction Design (CPCD) Also known as the Joint Unreinforced Concrete Pavement (JUCP), CPCD uses contraction joints to control cracking and does not use any reinforcing steel. Transverse joint spacing is selected such that temperature and moisture stresses do not produce intermediate cracking between joints (Russel W. Lenz 2011). 2.1.3.3 Continuously Reinforced Concrete Pavement CRCP provides joint-free design. The formation of transverse cracks at relatively close intervals is a distinctive characteristic of CRCP. These cracks are held tightly by the reinforcement and should be of no concern as long as the cracks are uniformly spaced, do not spall excessively, and a uniform non-erosive base is provided (Russel W. Lenz 2011). 2.1.4 Composite Pavement A composite pavement is composed of both hot mix asphalt (HMA) and hydraulic cement concrete. Typically, composite pavements are asphalt overlays on top of concrete pavements. The HMA overlay may have been placed as the final stage of initial construction, or as part of a rehabilitation or safety treatment. Composite pavement behavior under traffic loading is essentially the same as rigid pavement (T.F. Fwa 2006) 2.1.5 Rigid and Flexible Pavement Characteristics The primary structural difference between a rigid and flexible pavement is the manner in which each type of pavement distributes traffic loads over the subgrade. A rigid pavement has a very high stiffness and distributes loads over a relatively wide area of subgrade – a major portion of the structural capacity is contributed by the slab itself as shown in Figure 6(b) below. The load carrying capacity of a true flexible pavement is derived from the load-distributing characteristics of a layered system (Yoder and Witczak, 1975) as shown in Figure 6(a) below.
  • 23. 12 Figure 6: Load transfer mechanism in flexible and rigid pavement (Ref: Handbook for highway engineering, T.F. Fwa) 2.2 Pavement Materials: 2.2.1 Soil Soil is any un-cemented or weakly cemented accumulation of mineral particles formed by the weathering of rocks, the void space between the particles containing water and/or air. (Craig, 2004). Soil is a most important part of the road structure. It is the soil that provides support to the road from below and therefore it should possess sufficient strength and stability under most adverse loading and climatic conditions. Soil used in embankments should be incompressible. This will prevent differential settlement in the sub-grade, to achieve this incompressibility the soil should be compacted and stabilized adequately. (Singh, 2004). Soil index properties Types of soils vary from place to place and area to area. The index properties of soil are as follows Grain size distribution is in coarse grained soils and is determined by sieve analysis. For the fine grained soils grain size distribution can be analyzed by sedimentation. Sieve analysis process is sieving a soil sample through the set of sieves kept one over the other, the largest sieve being at the top and the smallest at the bottom. The soil retained on each sieve is weighed and expressed as a percentage of the total weight of the sample. For consistency limits, atterberg’s tests are carried out to determine the consistency and plastic behavior of the fine soils.
  • 24. 13 Liquid limit: It is the minimum moisture content at which the soil will flow under its own weight when tapped 25 times in Casegrande apparatus device. This indicates the limit where soil changes from plastic to liquid state. At this limit of moisture, the effect of cohesion and internal friction becomes practically zero Plastic limit: this indicates the percentage of moisture at which the soil sample changes with decreasing wetness from a plastic to a semi-solid state. It is the maximum water content at which soils can be rolled into threads approximately 3mm diameter without breaking. Plastic index: the range of consistency within which soil exhibits plastic properties is called the plastic range and it is indicated by the plastic index. Plastic index is the numerical difference between liquid limit and plastic limit. Shrinkage limit: it is the moisture content expressed as a percentage at which volume change ceases. After obtaining the soil limits, the soil is classified using Unified Soil Classification System (USCS). 2.2.2 Aggregates: Stone aggregate is a principle material used in pavement construction. In bituminous pavements, aggregates constitute about 90% of the construction materials. This is the material primarily responsible for bearing stress occurring on the road and also to resist wear due to abrasive action of the traffic. The aggregates are obtained from natural rock. There are soft and hard aggregates. Hard aggregates are used to resist crushing effects and adverse weather conditions while soft aggregates are used in gravel roads. Aggregates are specified according to their grain size, shape, texture and gradation. Favorable properties of aggregates  Strength  Hardness  Toughness  Soundness  Shape of aggregate  Surface texture and angularity
  • 25. 14 2.3 Earthworks This refers to all soils material placed below the formation level including improved subgrade layers, fill and prepared roadbed. It involves site investigation, clearing and grubbing, excavation, and construction of the embankments, compaction and finishing operations. (MWHC, 2005). The different classifications of earthworks are described below: 2.3.1 Site Investigation A site investigation is required to determine the classification and the bearing strength of the subgrade. The susceptibility of the subgrade to frost heave and the position of the water table are also required. (Fwa, 2006). Methods of investigations  Boring and probing – Involves the determination of the nature of the ground in a geological structure and recovery of undisturbed samples for laboratory examination.  Geophysical techniques 2.3.2 Clearing and grubbing Clearing and grubbing involves the removal of trees, stumps, roots, debris from the area of excavation and embankment. Clearing refers the removal of material above the existing ground surface. Grubbing is the removal of objects to nominal depth below the surface. (MWHC, 2005) Figure 7: Land clearing and grubbing along the Lubowa Hill View road by 140H Motor grader
  • 26. 15 2.3.3 Excavation Excavation is the process of loosening and removing rock or earth from its original position and transporting it to a fill or waste deposit. Excavation involves; road and drainage excavation, excavation for structures and borrow excavation. (MWHC, 2005) 2.3.4 Cut and fill A cut is a section of the road where the formation level is below the original ground level requiring excavations before the construction of the pavement layers as shown in figure 9. A fill is a portion of a road prism consisting of approved material, which lies on the road bed and is bounded by embankment side slopes and on which the subgrade is placed as shown below. 2.3.5 Embankments Embankments are used in road construction when the vertical alignment of the road has to be raised above the level of the existing ground to satisfy the design standards, or prevent damage from surface or ground water. Many embankments are only 0.5-1.5m high, but heights of 5m may be used on major highways. Embankment and Pavement Structure The road embankment and pavement design for the Seguku-Kasenge-Buddo roadway is as given below: Table showing the road embankment and Pavement Structure for the project road carriage and shoulders. Surfacing 30mm single seal Base 150mm of Granular Base Course (CRS) compacted to 98% of BS-Heavy Sub-base 170mm gravel material (Natural Gravel Class G30) compacted to 95% of BS-Heavy Improved Subgrade 250mm improved sub-grade constructed with material of a minimum quality of G15 Class gravel compacted to 95% of BS-Heavy Fills Fills constructed with material of a minimum quality of G7 Class gravel compacted to 93% of BS-Heavy
  • 27. 16 Roadbed 150mm depth after clearing, grubbing and removal of topsoil and/or other unsuitable material compacted to 93% of BS-Heavy. 2.4 Asphalt Concrete Works Asphalt concrete mixes are made up of mixtures of aggregate and asphalt cement binder about 95% aggregate by weight, about 75% aggregate by volume ideally, 3-5% air voids HMA mix designs are carried out to develop an economical blend of aggregates and asphalt that meet design requirements using the Marshall or Hveem test Required properties:  Flexibility due to high binder content of low viscosity  Short-term loadings elastic properties of binder-aggregate matrix  Long-term durability  Sufficient workability: Ease in which material is handled and laid and compacted  Sufficient strength and stability under traffic loads  Sufficient air voids -Upper limit to prevent excessive environmental damage -Lower limit to allow room for initial densification due to traffic 2.4.1 Terms used Asphalt is the cementitious material being added as bituminous binder Asphalt concrete is the asphalt mix in place on the road including levelling and surface courses during and after spreading and compacting. Asphalt Mix is the mix after the asphalt mix aggregate and asphalt have been blended together. Asphalt Mix Design is the laboratory determination of the precise proportions of asphalt, reclaimed asphalt concrete, additives, and all virgin aggregates to be blended together to meet the specified properties for the asphalt mix. Job Mix Formula is the field determination of the precise proportions of asphalt, reclaimed asphalt concrete, additives, and all virgin aggregates to be blended together to meet the specified properties for the asphalt mix as produced at the plant (MoWT 2010)
  • 28. 17 2.4.2 Pavement Surface Preparation 2.4.2.1 Surface Condition The performance of a flexible pavement under traffic is directly related to the condition of the surface on which the pavement layers are placed. For a full-depth asphalt pavement, if the condition of the subgrade soil is poor, the ultimate durability of the roadway may be reduced. For hot mix asphalt (HMA) layers placed on top of a new, untreated granular base course, the base material should not be distorted by the trucks carrying the mix to the paver. For HMA placed as an overlay on top of an existing HMA layer, the surface should be free of major distresses, smooth and clean. 2.4.2.2 Prime Coat - Flexible Pavements For flexible pavements, the graded subgrade or the top granular base layer may be prepared with a prime coat. A prime coat is a sprayed application of a cutback (MC-30 or MC-70) or emulsion asphalt applied to the surface of untreated subgrade or base layers. The prime coat serves several purposes:  fills the surface voids and protect the base from weather  stabilizes the fines and preserve the base material  promotes bonding to the subsequent pavement layers. 2.4.2.3 Underseals Existing Surface Preparation for Overlays includes an under seal which is a sprayed application of asphalt binder (emulsion or hot applied asphalt binder) immediately covered by a layer of one-sized aggregate. The underseal provides several benefits, such as waterproofing the surface, sealing small cracks and protecting the underneath surface from solar radiations 2.4.2.4 Existing Surface Preparation for Overlays The degree of surface preparation for an overlay is dependent on the condition and type of the existing pavement. Generally, the existing pavement should be structurally sound, level, clean and capable of bonding to the overlay. To meet these prerequisites, the existing pavement is usually repaired, leveled, cleaned and then coated with a binding agent. This subsection covers:  repair  tack coats. A tack coat material is an emulsion layer applied between HMA pavement lifts to promote adequate bonding. If adjacent layers do not bond to one another they essentially behave as
  • 29. 18 multiple independent thin layers - none of which are designed to accommodate the anticipated traffic-imposed bending stresses. Inadequate bonding between layers can result in delamination (de-bonding) followed by longitudinal wheel path cracking, alligator cracking, potholes, and other distresses such as rutting that greatly reduce pavement life. Application Tack coats should be applied uniformly across the entire pavement surface and result in more than about 90% surface coverage. In order for this uniformity to be consistently achieved, all aspects of the application must be considered and carefully controlled. Specific aspects are:  the condition of the pavement surface receiving the tack coat  the application rate  type of tack coat according to specified standards Condition of the Pavement Surface Receiving the Tack Coat The pavement surface receiving the tack coat should be clean and dry to promote maximum bonding. Emulsified tack coat materials may be applied to cool and/or damp pavement Since existing and milled pavements can be quite dirty and dusty, their surfaces should be cleaned off by sweeping, washing or high pressure compressor blowing before any tack coat is placed, otherwise the tack coat material may bond to the dirt and dust rather than the adjacent pavement layers. This can result in excessive tracking of the tack coat material. Construction vehicles and equipment pick up the tack-dirt mixture on their tires and leave the existing roadway with little or no tack coat in the wheel paths Application Rate Tack coat application should result in a thin, uniform coating of tack coat material covering approximately 90% of the pavement surface (Flexible Pavements of Ohio, 2001). Too little tack coat can result in inadequate bonding between layers. Too much tack coat can create a lubricated slippage plane between layers, or can cause the tack coat material to be drawn into an overlay, negatively affecting mix properties and even creating a potential for bleeding in thin overlays Factors considered include:  Roughness of the pavement surface receiving the tack coat. Rough surfaces require more tack coat than smooth surfaces.
  • 30. 19  Distributor vehicle. Several vehicle-related adjustments and settings are critical to achieving uniform tack coat placement. Essentially the nozzle patterns, spray bar height and distribution pressure must work together to produce uniform tack coat application. Other Tack Coat Aspects considered include  Timing: Generally, a tack coat should be allowed enough time to break and set (emulsion) before applying the next layer of hot mix asphalt (HMA).  Tracking: Tracking is the pick-up of tack coat material by vehicle tires. Tracking deposits tack coat material on adjacent pavement surfaces. In extreme cases, tracking may deposit enough tack coat material to distort pavement surfaces or hinder a driver's ability to navigate (Flexible Pavements of Ohio, 2001).  Traffic on Tack Coats: Generally, traffic should not be allowed on tack coats. When a tacked road surface is exposed to traffic, the potential exists for reduced skid resistance, especially during wet weather (Flexible Pavements of Ohio, 2001). When tack coat surfaces must be opened to traffic, they should be covered with stone-dust/sand to provide friction and prevent pick-up 2.4.3 Mix Transport Mix transport can have a large impact on flexible pavement construction quality and efficiency. Mix characteristics such as laydown temperature, aggregate segregation and temperature (120- 150o C) differentials are largely determined by transport practices. Key considerations in mix transport are:  truck bed cleanliness and lubrication  proper mix loading techniques in order to prevent aggregate segregation  haul distance and mix temperature  timely mix unloading and unloading of the correct mix. If properly managed, mix transport can successfully move HMA from the production facility to the paving site with little or no change in mix characteristics 2.4.4 Mix placement Mix placement involves any equipment or procedures used to place the delivered HMA on the desired surface at the desired thickness. The basic concept of the asphalt paving involves:  HMA is loaded in the front,
  • 31. 20  carried to the rear by a set of flight feeders (conveyor belts),  spread out by a set of augers,  then leveled and compacted by a screed. This set of functions can be divided into two main systems; the tractor (or material feed system and the screed. Tractor (Material Feed System) The tractor contains the material feed system, which accepts the HMA at the front of the paver, moves it to the rear and spreads it out to the desired width in preparation for screed leveling and compaction. The basic tractor components are  Push Roller and Truck Hitch. The push roller is the portion of the paver that contacts the transport vehicle and the truck hitch holds the transport vehicle in contact with the paver as shown in Figure 8 below. They are located on the front of the hopper. Figure 8: Push roller and truck hitch  Hopper. The hopper is used as a temporary storage area for HMA delivered by the transport vehicle shown in Figure 9 below
  • 32. 21 Figure 9: Hopper on asphalt paving tractor  Conveyor. The conveyor mechanism carries the HMA from the hopper to the augers  Auger. The auger receives HMA from the conveyor and spreads it out evenly over the width to be paved as in Figure 10 below. There is one auger for each side of the paver and they can be operated independently Figure 10: Auger distributing HMA Screed The most critical feature of the paver is the self-leveling screed unit, which determines the profile of the HMA being placed (Roberts et al., 1996). The screed takes the head of HMA from the material delivery system, strikes it off at the correct thickness and provides initial mat compaction.
  • 33. 22 2.4.5 Compaction Compaction is the process by which the volume of air in an HMA mixture is reduced by using external forces to reorient the constituent aggregate particles into a more closely spaced arrangement. This reduction of air volume in a mixture produces a corresponding increase in HMA unit weight, or density (Roberts et al., 1996). Inadequate compaction results in a pavement with decreased stiffness, reduced fatigue life, accelerated aging/decreased durability, rutting, raveling, and moisture damage (Hughes, 1989) Table 1: Factors affecting compaction ENVIRONMENTAL FACTORS MIX PROPERTY FACTORS CONSTRUCTION FACTORS Temperature Aggregate Rollers  Ground temperature  Air temperature  Wind speed  Solar flux  Gradation  Size  Shape  Fractured faces  Volume  Type  Number  Speed and timing  Number of passes  Lift thickness Asphalt binder Other  Chemical properties  Physical properties  Amount  HMA production temperature  Haul distance  Haul distance  Foundation support 2.4.5.1 Compaction Equipment There are two basic pieces of equipment available for HMA compaction on the Seguku- Kasenge-Buddo road:  the steel wheeled roller  the pneumatic tire roller. Each piece of equipment compacts the HMA by two principal means:  By applying its weight to the HMA surface and compressing the material underneath the ground contact area. Since this compression will be greater for longer periods of contact, lower equipment speeds will produce more compression.
  • 34. 23  By creating a shear stress between the compressed material underneath the ground contact area and the adjacent uncompressed material. When combined with equipment speed, this produces a shear rate. Lowering equipment speed can decrease the shear rate, which increases the shearing stress. Higher shearing stresses are more capable of rearranging aggregate into denser configurations. Steel Wheel Rollers Steel wheel rollers are self-propelled compaction devices that use steel drums to compress the underlying HMA. They can have one, two or even three drums, although tandem (2 drum) rollers are most often used. The drums can be either static or vibratory Since asphalt cement binder sticks to steel wheels, most steel wheel rollers spray water on the drums to prevent HMA from sticking, and are equipped with a transverse bar on each drum to wipe off HMA. This water will however cool the HMA and can reduce the time available for compaction. A tandem wheel roller used in the compaction of the asphalt concrete layer as well as the base and subbase layers is shown in the Figure 11 below. Figure 11: 8tonne, 1500mm drum width Tandem steel wheel vibratory roller Some steel wheel rollers are equipped with vibratory drums. Drum vibration adds a dynamic load to the static roller weight to create a greater total compactive effort. Drum vibration also reduces friction and aggregate interlock during compaction, which allows aggregate particles to move into final positions that produce greater friction and interlock than could be achieved without vibration Pneumatic Tire Rollers The pneumatic tire roller is a self-propelled compaction device that uses pneumatic tires to compact the underlying HMA. Pneumatic tire rollers employ a set of smooth (no tread) tires
  • 35. 24 on each axle. Figure 12 below shows one of the pneumatic rollers used in the compaction of the wearing course Asphalt binder tends to stick to cold pneumatic tires but not too hot pneumatic tires. A release agent (like water) can be used to minimize this sticking Figure 12: 3 Front, 4 Rear wheel Dynapac Static Pneumatic tyred roller In addition to a static compressive force, pneumatic tire rollers also develop a kneading action between the tires that tends to realign aggregate within the HMA. This results in both advantages and disadvantages when compared to steel wheel rollers Table 2: Pros and Cons of pneumatic tyred rollers (Ref: Russel W. Lenz 2011) Advantages Disadvantages  They provide a more uniform degree of compaction than steel wheel rollers.  They provide a tighter, denser surface thus decreasing permeability of the layer.  They provide increased density that many times cannot be obtained with steel wheeled rollers.  They compact the mixture without causing checking (hairline surface cracks) and they help to remove any checking that is caused with steel wheeled rollers.  The individual tire arrangement may cause deformations in the mat that are difficult or impossible to remove with further rolling. Thus, they should not be used for finish rolling.  If the HMA binder contains a rubber modifier, HMA pickup (mix sticking to the tires) may be so severe as to warrant discontinuing use of the roller.
  • 36. 25 2.4.5.2 Compaction measurement Compaction reduces the volume of air in HMA. Therefore, the characteristic of concern is the volume of air within the compacted pavement. This volume is typically quantified as a percentage of air voids by volume and expressed as “percent air voids done on a core sample of the compacted asphalt pavement These procedures require a small pavement core, which is extracted from the compacted HMA. Since core extraction is time consuming and expensive, air voids are often measured indirectly using a portable density-measuring device such as a nuclear density gauge Figure 13: Humboldt HS-5001EZ Troxler Nuclear Density Gauge 2.4 Field Inspection Inspection refers to the act of taking keen observations at works in progress and those completed and making a proper judgment about your observations after which instructions you give instructions. It is done to ensure the works are of the expected quality through good workmanship. Look outs include;  Presence of deleterious materials  Suitability of the material being used  Checking compaction  Checking levels for the different pavement layers  Checking to find out if the right equipment is used for a particular type of work.
  • 37. 26 2.5 Drainage Structures Drainage is very important both in relation to road pavement construction and maintenance. This is the provision made for protecting the road from surface water or sub surface water. If water is allowed to enter the structure of the road, the pavement will be weakened and will be much susceptible to damage by traffic 2.5.1 Objective of Drainage The main objective of drainage is to protect the project road and the adjacent lands against potential damage from storm water and sub-surface water. A good drainage system, properly maintained, is vital to the successful operation of a road. It serves the following purpose;  To convey storm water from the surface of the carriageway to outfalls;  To control the level of the water table in the sub-grade beneath the carriageway;  To intercept ground and surface water flowing towards the road. 2.5.2 Hydraulic Structures Hydraulic structures in roads include; bridges, box and pipe culverts, side drains, and catch water drains. A culvert is a specific type of stream crossing, used generally to convey water flow through the road prism base. These usually consists of concrete, PVC or steel pipes, or a reinforced concrete box, placed under the road within an embankment to provide suitable means of conveying streams, or the contents of side drains under the road with no restrictions on traffic. The most common shape used is circular, rectangular or square. On this project, the bigger percentage of the culverts to be used was made of concrete diameter of 900 mm. 2.5.3 Terms used  Culvert entrance: The downstream end of a culvert through which water enter to pass upstream.  Culvert Exit: The upstream end of a culvert through which water exit to pass upstream  Culvert Inlet: The upstream end of a culvert through which stream flow enters.  Culvert Outlet: The downstream end of a culvert through which stream flow discharges.  Culvert End Structures
  • 38. 27 The Culvert End Structures includes; Head and Wing walls, Aprons, Catch basins and Drop Inlets. The details of these structures are given below; Headwall is a concrete, gabion, masonry, or timber wall built around the inlet or outlet of a drainage pipe or structure to increase inlet flow capacity, reduce risk of debris damage, retain the fill material and minimize scour around the structure. Wing wall is a masonry or concrete structures built onto the side of culvert inlet and outlet headwalls, designed to retain the roadway fill and direct water into and out of the drainage structure while protecting the road and fill from erosion. Apron is an extension of the head wall structure built at ground or stream level and designed to protect the stream bottom from high flow velocities and to safely move water away from the drainage structure. Catch Basin - The excavated or constructed basin at the inlet of a culvert cross-drain pipe, used to store water and direct it into the culvert pipe. Drop Inlet - Masonry or concrete basin, or a vertical riser on a metal culvert inlet, usually of the same diameter as the culvert, and often slotted, to allow water to flow into the culvert as water flow rises around the outside. Drop inlets are often used on ditch relief culverts where sediment or debris would plug the pipe. A drop inlet also helps control the elevation 2.5.4 Drainage of a Pavement This is the process of interception and removal of water from over, under and the vicinity of the pavement. Pavement performance and integrity often depends on the removal of water from above and below the pavement surface. The principle function of highway drainage is to remove surface water as rapidly and efficiently as possible from impermeable surfaces. (Fwa, 2006) Drainage of the pavement has two main components namely:  Surface drainage,  Sub-surface drainage. Surface water can enter the pavement construction through the porous surface, through cracks that develop as the pavement ages and at the end of the carriage way if it cannot find its way off the pavement. The following provisions ensure satisfactory surface drainage such that the service life of the road is not reduced by the damage that can be inflicted by poor drainage on the road;
  • 39. 28  Camber (Cross slope): This is a gradient in the cross section of the roadway surface that makes it possible for water to flow easily across the surface into the side drains or drop inlets.  Side slopes: These effects the movement of water from the vicinity of the road into the roadside ditches.  Side drains /Roadside ditches: The runoff is allowed to sheet flow across the roadway surface (affected by the camber) into the roadside ditches from where it can be conveyed through culverts to a natural stream.  Curbs, gutters and inlets: The roadside ditches may not always be possible or cost effective due to right of way restrictions, therefore curbs, gutters and drop inlets are used to intercept water from the pavement to drains below the surface.  Culverts and storm drains: These are open end conduits used to convey water from one side of the roadway through the embankment to the other side of the roadway. A network or system of conduits used to carry storm water intercepted by inlets is referred to as a storm drain system. 2.5.5 Culverts Culverts are closed conduits for passage of runoff from one open channel to another, made from several types of materials including concrete, plastic, aluminum, and corrugated steel. Culverts come in several commonly used shapes including circular, box, elliptical, pipe arch, and arch. Shape selection is based on construction costs, limitations on upstream water surface elevation, roadway embankment height, and hydraulic performance (FHWA 1985) Culverts are usually located in existing channel beds. This is generally the cheapest placement since it involves the least earthwork and re-routing of the water. 2.5.6 Culvert installation Culvert installation involves excavation, bedding placement, culvert placement, back filling and finishing. Finishing involves construction of outlet and inlet structures such as head wall, wing wall, and apron. These end structures are mostly made out of masonry Culvert cross-section Figure 2.20 below can show how to determine the design parameters of the cross-section of a culvert
  • 40. 29 Figure 14: Culvert cross-section Calculating design parameters 𝑉𝑜𝑙𝑢𝑚𝑒 𝑜𝑓 𝐸𝑥𝑐𝑎𝑣𝑎𝑡𝑖𝑜𝑛 = 𝐷𝑒𝑝𝑡ℎ 𝑜𝑓 𝑒𝑥𝑐𝑎𝑣𝑎𝑡𝑖𝑜𝑛 × 𝑊𝑖𝑑𝑡ℎ × 𝐿𝑒𝑛𝑔𝑡ℎ 𝑜𝑓 𝑐𝑢𝑙𝑣𝑒𝑟𝑡 𝑉𝑜𝑙𝑢𝑚𝑒 𝑜𝑓 𝐵𝑒𝑑𝑑𝑖𝑛𝑔 𝑚𝑎𝑡𝑒𝑟𝑖𝑎𝑙 = 𝐷𝑒𝑝𝑡ℎ 𝑜𝑓 𝑏𝑒𝑑𝑑𝑖𝑛𝑔 × 𝑊𝑖𝑑𝑡ℎ × 𝐿𝑒𝑛𝑔𝑡ℎ 𝑜𝑓 𝐶𝑢𝑙𝑣𝑒𝑟𝑡 𝑋𝑠𝑒𝑐𝑡𝑖𝑜𝑛𝑎𝑙 𝑎𝑟𝑒𝑎 𝑜𝑓 𝑏𝑎𝑐𝑘𝑓𝑖𝑙𝑙 = 𝑋𝑠𝑒𝑐𝑡𝑖𝑜𝑛𝑎𝑙 𝑎𝑟𝑒𝑎 𝑜𝑓 𝑒𝑥𝑐𝑎𝑣𝑎𝑡𝑖𝑜𝑛 − 𝐴𝑟𝑒𝑎 𝑜𝑓 𝑐𝑢𝑙𝑣𝑒𝑟𝑡 𝐴𝑟𝑒𝑎 𝑜𝑓 𝑐𝑢𝑙𝑣𝑒𝑟𝑡 = 𝜋𝐷2 4 𝑤ℎ𝑒𝑟𝑒 𝐷 − 𝐷𝑖𝑎𝑚𝑒𝑡𝑒𝑟 𝑜𝑓 𝑐𝑢𝑙𝑣𝑒𝑟𝑡 𝑉𝑜𝑙𝑢𝑚𝑒 𝑜𝑓 𝑏𝑎𝑐𝑘𝑓𝑖𝑙𝑙 = 𝑋𝑠𝑒𝑐𝑡𝑖𝑜𝑛𝑎𝑙 𝑎𝑟𝑒𝑎 𝑜𝑓 𝑏𝑎𝑐𝑘𝑓𝑖𝑙𝑙 × 𝐿𝑒𝑛𝑔𝑡ℎ 𝑜𝑓 𝐶𝑢𝑙𝑣𝑒𝑟𝑡 Culvert inlet/outlet Figure 2.21 below shows how to determine the design parameters of the culvert outlet
  • 41. 30 Figure 15: Culvert outlet/inlet Calculating design parameters 𝑉𝑜𝑙𝑢𝑚𝑒 𝑜𝑓 𝐻𝑒𝑎𝑑 𝑊𝑎𝑙𝑙 = ((𝐴 × 𝐵) − 𝐴𝑟𝑒𝑎 𝑜𝑓 𝐶𝑢𝑙𝑣𝑒𝑟𝑡) × 𝐻𝑒𝑎𝑑 𝑊𝑎𝑙𝑙 𝑇ℎ𝑖𝑐𝑘𝑛𝑒𝑠𝑠 𝑉𝑜𝑙𝑢𝑚𝑒 𝑜𝑓 𝑊𝑖𝑛𝑔 𝑊𝑎𝑙𝑙 = (( 𝐶 + 𝐷 2 ) × 𝐸) × 𝑊𝑖𝑛𝑔 𝑊𝑎𝑙𝑙 𝑇ℎ𝑖𝑐𝑘𝑛𝑒𝑠𝑠 𝑉𝑜𝑙𝑢𝑚𝑒 𝑜𝑓 𝐴𝑝𝑟𝑜𝑛 = (( 𝐹 + 𝐺 2 ) × 𝐻) × 𝐴𝑝𝑟𝑜𝑛 𝑇ℎ𝑖𝑐𝑘𝑛𝑒𝑠𝑠 2.5.7 Sub-surface drainage This involves the interception and removal of water from within the pavement.  Sources of sub-surface water include;  Shallow water table  Infiltration through surface cracks  Capillary rise  Seepage from the sides of the pavement  Evaporation and cooling Ground water will rise beneath any pavement through cuttings or where the water table is near the surface. Sidelong ground can lead to saturation from surface and sub-soil water flow, therefore under these circumstances sub- soil drainage should be provided.
  • 42. 31 Traffic loads can create serious problems in the road foundation if it becomes saturated, which include;  Reduction in strength of the subgrade, capping layer and unbound sub-base as pore water pressures are generated and particle interlock is lost.  Movement of fines within the capping layer and unbound sub-base leading to further loss of aggregate interlock, loss of strength and possible risk of frost damage.  Degradation of unbound aggregate generating even more fines.  Friction between the sub-base and structural layers is reduced, lowering the strength of the total construction.  The base of the asphalt layer may be subjected to scouring by water stripping the bitumen, creating voids and reducing strength. Water can also be forced into micro-cracks leading to rapid failure. If the water table is well below the formation level and both the capping layer material and sub-base have adequate permeability to carry away surface water, it is possible that sub-surface drainage is not necessary otherwise it should be provided for. The measures undertaken to provide for sub-surface drainage include;  Installation of drainage beds in the pavement. These are made of high permeability material such as sand. During water flows, the water may come with fine materials which gradually clog the sand layer, impairing its functionality. Therefore, filter layers such as geo- membranes are installed at the top and bottom of the drainage bed to prevent this.  Use of transverse perforated drains embedded within the drainage bed  Use of sand drains to lower the water table.  Longitudinal French drains. 2.6 Surveying Surveying may be defined as the art of making measurements of the relative positions of natural and manmade features on the earth’s surface and presentation of this information either graphically or numerically (Surveying II class notes 2014). To most engineers, Surveying is the process of measuring lengths; height differences and angles on site either for the preparation of large scale plans or in order that engineering works can be located in their correct positions on ground.
  • 43. 32 Land surveys can also be classified by purpose as follows: a) Topographic surveys: Used to establish the position and shape of natural and manmade features over a given area usually for purposes of producing a map of an area Such surveys are normally classified according to the scale of the final map. Typical scales are: 1:1000000, 1:50000, 1:10000, 1:1000, 1:500 etc. b) Cadastral surveys: Undertaken to produce plans of property boundaries for legal purposes. For instance, in many countries the registration of land ownership is based on cadastral surveys/plans c) Engineering surveys: Embrace all the survey work required before, during and after any engineering works. d) Hydrographic surveying: Carried out on water bodies like lakes, rivers and oceans. They involve measuring water depth and investigating the nature of the sea bed in order to produce navigational charts for mariners. Other uses of hydrographic surveys include: offshore oil exploration and production, design, construction and maintenance of harbors and inland water routes, scientific studies etc. 2.6.1 Major survey operations i) Setting out – This describes the process of establishing on paper designs on ground. Involves making an alignment for the proposed road using survey equipment. It comprises pegging out the route, and establishing the width and level of the road. Setting out involving horizontal control The process used in establishing horizontal control is one of working from the whole to the part. This involves starting with a small number of very accurately measured control points (primary control), which enclose the area in question and then using this to establish secondary control points from which the design is set out
  • 44. 33 Figure 16: Setting out involving horizontal control Once established and coordinated, control points can be used with a positioning technique to set out E, N coordinates of the design points of the proposed structure. They are generally used following the road centerline as the baseline. Setting out involving vertical control To provide a basis for vertical control, all levels on site will normally be reduced to a nearby Benchmark (BM). The actual BM used is normally agreed upon by the engineer and the contractor and is termed as the Master Benchmark (MBM). This is used for two main purposes;  To establish points of known reduced level near to and on the elements of the proposed scheme i.e. Temporary Bench marks (TBMs).  Used to check the reduced level of any nearby BMs and in case of any discrepancy, their amended values are used. When coordinated points are set out for horizontal control, the points are often leveled with reference to either the MBM or TBM to provide vertical control ii) Leveling – Involves determining the relative difference in elevation between two or more points by measuring from the ground level to the line of collimation. iii) Tape and offsetting – Often referred to as chain surveying deriving its name from the fact that the principal item of equipment traditionally was a measuring chain which has been replaced by an accurate steel band. (Bannister and Raymond 1998)
  • 45. 34 2.6.2 Surveying terms Offset: A distance measured perpendicular from the main line of measurement/ a side shoot measured from the centerline Benchmark: A height reference point or mark of known level Line of collimation: Optical axis of a telescope: also the line of sight through an instrument when set horizontal Datum: Horizontal, vertical or 3-dimensional coordinate reference definition Formation level: Excavation level (height) on which permanent works constructed Profile: A site marker delineating the shape/level etc of a construction element at that location Total station: A combined distance and angle (electronic) measuring survey instrument Dipping: This refers to the process of adding a specified magnitude to a given measurement, to provide room for setting out that measurement on ground or for inspection of setout measurements The dipping height for this project is 20cm (0.2m) and it is used to determine the up and down reduced levels which are then marked off on the two opposite offset pegs at every checkpoint. Figure 17: Illustration of dipping along road section Major Survey apparatus used include: Total station, GPS-RTK, Dumpy level, staff, tape measure, theodolite, travelers, wooden pegs, tripod stands, hammer and chisel
  • 46. 35 CHAPTER THREE: PRACTICAL WORKS 3.1 FIELD SURVEY OPERATIONS 3.1.1 Setting out Road centerline The road centerline points, horizontal position and vertical profile design specifications were provided by the consultant and would be the first feature of the pavement to be set out and act as a baseline/reference for other activities during the pavement construction Equipment  GPS-RTK machine  Tape measure  Nails  Hammer Procedure The base station receiver for the GPS machine was set up at known TBM by the chief surveyor, and switched on Figure 18: Using GPS to locate centerline of existing road Coordinates were initially installed in GPS memory as recorded from design documentations The rover rod, which was now positioned in a global coordinate framework was then carried off and used to establish known coordinates of the road centerline as read off from the geometric designs provided initially by the consultant.
  • 47. 36 Along the movement of the rover rod, a known point was traced on the ground, located with position by accurately horizontally adjusting the rover, until fairly accurate focus was achieved, with the aid of variable tones of the sounding alarm. At this centerline point, a nail was hammered into the ground to mark the location of the point Referring to the same BM location of the base station receiver, points along the entire road centerline were established at 20m intervals as provided in the geometric designs 3.1.2 Setting out subgrade transverse dimensions The subgrade cross section, was obtained by use of the marked out centerline and section details from the provided geometric designs. This was to help determine the cross dimensions to be cut and levelled for subgrade construction Equipment  Wooden pegs  Tape measure  Hammer  Chisel Procedure Using a tape measure, a distance of 6m was offset from the initially established centerline points, measured perpendicular to the longitudinal centerline outline, on both the LHS and RHS to obtain a 12m wide subgrade section At each of these offsets, a wooden peg was driven into the ground to demarcate the transverse dimensions of the road section. A chisel was used to create a hole in the ground in cases where the ground was too hard to be penetrated by wooden peg alone 3.1.3 Road chaining This involved writing out chainage numbers along road length as established in the initial surveying activities. This was done with the main aim of providing labels along the road length, which would in turn ease locating specified points along the road in the field, most especially during inspection and further surveys. Equipment  Weather resistant, visually clear paint (white)  Tape measure
  • 48. 37  Paint brush Procedure Along the road length, from the start, the road was labelled with respect to the chainage distances to the end point From the first nail, labelled CH0+000, the chainages were written on fairly permanent structures on the road side that were anticipated to last quite as long as the road design life, in order to provide them to be used at a later time in case of road maintenance works or repairs Chainages were written on walls of houses, trees, fences, etc, located outside the road reserve in the most practically visible places, for easy spotting appropriate depending on the location Figure 19: Labelling chainages along road 3.1.4 Setting out levels on offset pegs for construction of a road layer Equipment  Automatic level  Tripod stand  Staff  Tape measure  Marker  Change point
  • 49. 38 Procedure The automatic level was setup on the tripod stand at a convenient height, centered, leveled and focused. A BS reading was taken on a known nearby BM and the height of collimation (HOC) calculated. 𝐻𝑂𝐶 = 𝐵𝑆 + 𝑅𝐿 𝑜𝑓 𝐵𝑒𝑛𝑐ℎ𝑚𝑎𝑟𝑘 The required down and up staff readings (including 0.2m for dipping) were calculated from; 𝑅𝑒𝑞𝑢𝑖𝑟𝑒𝑑 𝑢𝑝 𝑜𝑟 𝑑𝑜𝑤𝑛 𝑠𝑡𝑎𝑓𝑓𝑟𝑒𝑎𝑑𝑖𝑛𝑔 = 𝐻𝑂𝐶 − 𝐷𝑒𝑠𝑖𝑔𝑛 𝑢𝑝 𝑜𝑟 𝑑𝑜𝑤𝑛 𝑅𝐿 (𝑖𝑛𝑐𝑙𝑢𝑑𝑖𝑛𝑔 20𝑐𝑚 𝑑𝑖𝑝𝑝𝑖𝑛𝑔) The staff was then held by the chainman on top of the peg, and then oriented vertically along the length of the peg until the required staff reading was observed through the automatic level The point at the bottom of the staff was then marked on the two pegs at each chainage using a marker. Change points were made after every appropriate distance, approximately 30m to ensure intervisibility between points of sight A foresight (FS) was then taken on a nearby benchmark as a check at the end of the survey, to check for the margin of error. 3.1.5 Checking levels on pegs Equipment  Automatic level,  Tripod  Calibrated staff Procedure The instrument (automatic level) was setup at a convenient height, centered, leveled and focused. A back sight (BS) reading was taken on a leveling staff held vertically at a benchmark (known reduced level) and the height of the height of collimation (H.O.C) calculated from, 𝐻𝑂𝐶 = 𝐵𝑆 + 𝑅𝐿 𝑜𝑓 𝐵𝑒𝑛𝑐ℎ𝑚𝑎𝑟𝑘 The required upper and down staff readings (including 0.2m for dipping) to be checked for were calculated from,
  • 50. 39 𝑅𝑒𝑞𝑢𝑖𝑟𝑒𝑑 𝑢𝑝 𝑜𝑟 𝑑𝑜𝑤𝑛 𝑠𝑡𝑎𝑓𝑓𝑟𝑒𝑎𝑑𝑖𝑛𝑔 = 𝐻𝑂𝐶 − 𝐷𝑒𝑠𝑖𝑔𝑛 𝑢𝑝 𝑜𝑟 𝑑𝑜𝑤𝑛 𝑅𝐿 (𝑖𝑛𝑐𝑙𝑢𝑑𝑖𝑛𝑔 20𝑐𝑚 𝑑𝑖𝑝𝑝𝑖𝑛𝑔) Intermediate sights (IS) were taken on the already marked up and down levels on the pegs on both the Left Hand Side (L.H.S) and Right Hand Side (R.H.S) of each marked peg checkpoint to check whether they corresponded with the calculated required up/down staff readings and the necessary corrections made using a marker. The leveling staff would be held in contact with face of the peg and the chainman would be directed by the surveyor to move the staff up and down until the calculated staff readings were in focus at the cross hairs. A foresight (FS) reading was taken on a nearby benchmark as a check that is, 𝑅𝑒𝑑𝑢𝑐𝑒𝑑 𝑙𝑒𝑣𝑒𝑙 𝑜𝑓 𝑏𝑒𝑛𝑐ℎ𝑚𝑎𝑟𝑘 = 𝐻𝑂𝐶 − 𝐹𝑆 3.1.6 Checking ground levels for finished road layers This was done to ensure that the levels achieved during construction of the road layer corresponded to those provided in the designs provided by the consultant. Equipment  Automatic level  Tripod  Leveling staff  Fiber tape measure,  Change point (CP)  Nails. Procedure The instrument was setup on a tripod stand at a convenient height, centered, leveled and focused. A back sight (BS) reading was taken to a leveling staff held vertically at a nearby benchmark and the height of collimation (H.O.C) calculated. 𝐻𝑂𝐶 = 𝐵𝑆 + 𝑅𝐿 𝑜𝑓 𝐵𝑒𝑛𝑐ℎ𝑚𝑎𝑟𝑘 Intermediate sights (IS) were taken along each chainage on the L.H.S and R.H.S at points defining the end of the carriageway and shoulder as well as the centerline. The reduced levels of these five points were calculated for every chainage from,
  • 51. 40 𝑅𝑒𝑑𝑢𝑐𝑒𝑑 𝑙𝑒𝑣𝑒𝑙 = 𝐻𝑂𝐶 − 𝐼𝑆 These measured reduced levels were compared with the design values for these five points along each chainage and the discrepancy/error between the corresponding readings calculated from, 𝐸𝑟𝑟𝑜𝑟 = 𝐷𝑒𝑠𝑖𝑔𝑛 𝑅𝐿 − 𝑀𝑒𝑎𝑠𝑢𝑟𝑒𝑑 𝑅𝐿 Therefore, a positive error indicates a fill (material should be brought and compacted in that section to make up for the difference) and a negative difference indicates a cut (material should be cut away from the section). Requirements The allowable difference was +/-20mm (0.02m) 3.1.7 Setting out the centerline on a finished road layer The purpose of setting out centers on a finished road layer is to enable the placement of offset pegs for construction of the next layer and they are also used in taking cross-sections/layouts along chainage. Equipment  Total station,  Rod with reflector prism,  Steel tape,  Tripod, nails,  Metallic hammer Procedure The total station was set up on the tripod stand at a convenient height, centered, leveled and focused. The instrument was traversed on the nearby benchmark as a check. For each chainage, the horizontal angle was set to 0°00’00’’ and the instrument fixed. The rod with reflector prism was then moved to and fro in the road way by a chainman directed by the surveyor looking through the telescope until the horizontal distance reading on the screen of the instrument was 0.00m. These points were marked on ground using nails and these were the points forming the centerline of the road way between chainages under investigation. The instrument was then traversed on a nearby benchmark (FS) as a check.
  • 52. 41 Note: The coordinates of all the benchmarks and center points were initially already stored in the total station. 3.2 Earthworks These involved all the work done right from bush clearing and grubbing to the finishing of the subgrade layer. It involved site investigation, excavation, compaction and finishing work as well as cuts and fills, road bed and removal to spoil of unsuitable or surplus material 3.2.1 Grubbing Grubbing was done to a depth of 150-200mm. the machines used included bull dozers, excavators, wheel loaders, dumper trucks and excavator hammers. It was carried out mainly  To prepare the surface for top soil stripping and excavation.  Create working space for the equipment  Remove harmful insects and animals to the workforce. 3.2.2 Cutting It is the process by which a raised section in the designed road width was reduced to attain the formation level for the pavement. Prior to cutting, levels were set by the surveyors on the pegs defining the slope on the design. Cutting began from the top slopping down using the bulldozer and finishes on the slope were done using the grader with its blade set to the required slopes. Figure 20: A cut section reduced to the designed road formation
  • 53. 42 Cut to Spoil: Any material with a CBR less than 7% was considered unsuitable for use in the construction processes so it was permanently removed and dumped away from the pavement width. Figure 21: Excavation and removal of unwanted material for dumping 3.2.3 Filling Filling is the process by which the road bed was raised in a low lying area to flash with the formation level or the existing road bed. It involved the use of natural gravel material of minimum California Bearing Ratio (CBR) of 7% (G7 materials) from the existing ground level or imported material being compacted to refusal density in layers of not greater 200mm.
  • 54. 43 Figure 22: Filling and compaction during road bed preparation. Fill /Bed road treatment Since Seguku-Kasenge-Buddo area are raised areas their water table are low and have less underground streams, the process of bed road treatments was needed in a few valleys order to make the water move easily horizontal below the yet to be laid pavement, this is done by establishing French drains and rock fills and the following was done;  Locate areas along the road that have underground springs and then dig up any loose soils to a depth of 4.5m manually using pick axe, spades, and hoes. The ditch is made in regular shape for example a cubical ditch  Boulders and rocks are placed in this ditch until it is almost full, it then blinded with small rocks and seal off with coarse sand on top. a steel drum roller is pass over the coarse sand layer to partially compact the rocks and consequently the coarse sand layer  A dump proof membrane (polythene paper) of gauge thickness 1000µm is placed on partially compacted layer, murram is poured over the DPC, spread, and water is sprinkled and mixed to attain optimal moisture content and finally compacted using a hand roller.
  • 55. 44 Figure 23: Rock filling at the swamp 3.2.4 Laying the subbase layer Gravel/murrum to be used was first tested in the laboratory for moisture content, MDD&OMC, through the proctor test, as well as sieve analysis and approved from a given borrow pit. Borrow pits with soil found to have the desired qualities were then excavated to obtain the gravel required in bulk quantities, and transported to the project site to be applied in the laying of the subbase. Murrum was heaped at specific distances apart depending on calibrated intervals from relation between the volume of the dumping trucks and layer thickness, for the subbase Table 3: Specification of Dumping Murrum for the Subbase Vol. of truck Thickness of layer Width of layer/lane Distance between 4m3 heaps 8m3 170mm 5.5m 4m The murrum was then spread along the road cross section using the blade of the grader
  • 56. 45 Levels are then taken using an automatic level and the pegs are put on either sides of the road bearing marks for the sub grade level, the camber level and deep. Then a process of dipping was carried out with the help of a string and a steel tape, this helps to establish road cross slope and also checks regions that need a cut or a fill Dipping height used was 200mm. If the string placed on either pegs and the string was above the 200mm height mark that region needed a fill, if the string is below the 200mm mark that region needed a cut Using the blade of the grader again a cut and a fill could be done until the required thickness and slope of the road camber could be achieved. Water was then sprinkled along the road using a water bowser at a specified rate, which depends on the discharge at the sprinkling bar and the speed of the water bowser which were 0.01m3 /s and 15km/h in order to achieve Optimal Moisture Content (OMC). Finally, the moist murram was heavily compacted using the tandem drum roller following monitored number of passes over layer to achieve Maximum Dry Density (MDD). Figure 24: Laying of subbase at CH 4+200 3.2.5 Preparing of stone base layer Gravel soils in the base layer were stabilized using crushed rock containing 40% CRR content and 60% gravel soil to form a highly rigid, strong and stable base layer.
  • 57. 46 The process of stabilization is always carried out to make the base coarse strong and durable by binding the crushed rock (CRR) and gravel particles together. The mixture is bound firmly forming a solid matrix when compacted well. Table 4: Specifications of stone base laying on site Vol of heaps Thickness of CRR Thickness of gravel Base thickness Width of base/lane Intervals between CRR Intervals between gravel 4m3 90mm 60mm 150mm 4.75m 5m 9m Heaps of components of the base layer were placed independently. Heaps of CRR were positioned to the finished subbase, spread out with the grader blade to provide a temporarily motorable surface for delivery trucks and then gravel was then delivered and heaps piled as shown in the table above The grader first spread the crushed rock to a depth of 90mm along the road, another layer of murram is spread at a depth of 60mm using a grader. The road was then scarified using the back forks of the grader to mix the placed crushed stone and murram. Water was the sprinkled along the road using a water bowser and the mixed thoroughly until the base is uniform. The dipping process was then carried out to find out regions that need a cut or fill, also road cambers are established at the same time using a grader to obtain a road thickness of 150mm.
  • 58. 47 Figure 25: Grading stone base and obtaining cross slopes More water was sprinkled using a water bowser until the stabilized base is has achieved optimal moisture content, and finally heavily compacted using a tandem steel drum roller to achieve MDD as determined in the laboratory. Figure 26: Laying of base layer (a) The grader plate spreading CRR (b) Blended layer of CRR and gravel (c) Spreading of gravel material (d) Water pump spraying water in blended mixture to be compacted
  • 59. 48 3.2.6 Checking depth of constructed pavement layers The depth of constructed pavement layers was checked manually along 100m intervals by a shallow excavation/ coring process where a section along the road length was cored using a pick axe, making an excavation of 𝐷𝑖𝑎𝑚𝑒𝑡𝑒𝑟 ≈ 50𝑚𝑚 The hole was dug to a 𝐷𝑒𝑝𝑡ℎ ≥ 350𝑚𝑚 and with the help of a steel tape, the depth of each layer was observed and noted, as a validation check to determine whether the depth of each layer conforms to the standards 3.3 Insitu Geotechnical tests 3.3.1 Dynamic Cone Penetrometer test (DCP) The DCP test was carried out on Insitu soils to establish the strength of the existing subgrade, and its ability to support traffic loads without risk of failing under bearing capacity or settlement Objective To determine the mechanical properties of existing pavement layers for use in structural pavement design and to provide a measure of a material’s insitu resistance to penetration. Principle The underlying principle of the DCP is that the rate of penetration of the cone, when driven by a standard force, is inversely proportional to the strength of the material for example in the CBR test. Where the pavement layers have different strengths, the boundaries between the layers can be identified and the thickness of the layers determined Reference BS 5930:1999 Equipment  DCP machine Bottom rod, top rod (hammer shaft), falling hammer (8kgs falling through 575mm), meter rule, 60° cone. Refer to figure 3.20 for DCP apparatus.  Road safety wear and equipment for traffic control
  • 60. 49 Figure 27: Casing for DCP test equipment The DCP machine was assembled appropriately with the cone firmly screwed to the bottom rod with a spanner, and clamp ring was fastened using alley keys, the meter rule placed in position and set up at the position where test was required The initial meter rule reading was recorded, the weight lifted till it touches the handle, and left to fall freely along the hammer shaft onto the coupling to make the first blow The depth achieved after a number of blows was read off the meter rule was recorded 10 or 5 blows were normally satisfactory for good quality strong layers 1 or 2 blows were appropriate on meeting fairly weaker subbase and subgrade layers Analysis of results DCP results were analysed using the UK DCP version 3.1 software. Raw data was entered into the program and analysis done; this program was chosen because it automatically generates the thickness of layers with uniform strength. A change in gradient indicates a point of change from one layer to another. The graphs were used to ascertain the depth of layers with uniform strengths by noting uniformity in gradient CBR values were evaluated using DCP results using the expression (Ref: http://civilblog.org) log10 𝐶𝐵𝑅 = 2.48 − 1.057 log10(𝐷𝐶𝑃 𝑣𝑎𝑙𝑢𝑒)
  • 61. 50 3.3.2 Field density test by sand replacement method Introduction The dry density of compacted soil or pavement material is a common measure of the amount of the compaction achieved. Knowing the field density and field moisture content, the dry density is calculated. It is one of the several methods to determine field density, as well as core cutter method, sand replacement, rubber balloon, heavy oil method, etc. The sand replacement procedure was carried out on at intervals along the road length, where the base layer had been finished. Objective To determine the field density of compacted base layer by sand replacement method References IS: 2720- PART-28 Principle The basic principle is to measure the insitu volume of a hole from which the material was excavated from the weight of sand with known density filling the hole. The insitu density of the material is given by the weight of the excavated material divided by the insitu volume Required equipment  Sand pouring cylinder Large capacity 16.5litres, 200mm diameter, 610mm length Medium: Capacity 150mm diameter, length 450mm  Leveling, excavating and scooping tools; Hand tools like scraper, hammer and chisel  Metal trays, some intact and with holes in middle 150mm diameter  Sand  Test sieves; 600mm and 300mm and 75µm aperture  Balance 30kgs, accuracy 1g  Air tight bags  Glass plate Test procedure Sand calibration
  • 62. 51 Sand to be used in the test is obtained from a borrow pit and washed on a 75µm sieve to eliminate silt sized particles, then spread out on a clean surface to sundry for 36 hours The sand is then sieved through a setup of 600mm and 300mm sieves, and material retained on the 300mm sieve was transferred to a metal pan and the rest discarded A mass of 16kgs of sand is poured into the sand pouring cylinder with a cone of known capacity placed on a glass plate, and the shutter opened The shutter is then opened, sand left to pour into the cone of known volume and the remaining sand in the cylinder is weighed 𝑀𝑎𝑠𝑠 𝑜𝑓 𝑠𝑎𝑛𝑑 𝑖𝑛 𝑐𝑜𝑛𝑒 = 𝑀𝑎𝑠𝑠 𝑝𝑜𝑢𝑟𝑒𝑑 − 𝑀𝑎𝑠𝑠 𝑙𝑒𝑓𝑡 𝑖𝑛 𝑡ℎ𝑒 𝑐𝑦𝑙𝑖𝑛𝑑𝑒𝑟 𝑎𝑓𝑡𝑒𝑟 𝑝𝑜𝑢𝑟𝑖𝑛𝑔 𝐷𝑒𝑛𝑠𝑖𝑡𝑦 𝑜𝑓 𝑠𝑎𝑛𝑑 = 𝑀𝑎𝑠𝑠 𝑜𝑓 𝑠𝑎𝑛𝑑 𝑖𝑛 𝑐𝑜𝑛𝑒 𝑉𝑜𝑙𝑢𝑚𝑒 𝑜𝑓 𝑡ℎ𝑒 𝑐𝑜𝑛𝑒 The procedure is repeated using different sized sand pouring cylinders, and the average density from the different tests is determined Measurement of field density An area was leveled and cleared in the open field and a tray was placed on the levelled surface Figure 28: Section of constructed base tested for density at CH 2+200 LHS
  • 63. 52 A circular hole of approximately 15cm diameter (size of the tray hole) was excavated 20cm deep (depth of calibrating container) and all the excavated soil was collected in an airtight bag. Figure 29: Excavating hole for testing The weight of the excavated soil was recorded The sand pouring cylinder was refilled, weighed, the tray removed and the sand pouring cylinder placed over the hole. The shutter was opened and the sand left to run out into the hole. The shutter of the cylinder was closed when no further movement was seen. The cylinder was removed and the mass of the sand pouring cylinder with the remaining sand was determined Figure 30: Sand replacement in excavated hole A representative sample of the excavated material was kept for moisture content determination Analysis of results The field density of the insitu pavement layer was determined from the expressions below
  • 64. 53 𝐷𝑒𝑛𝑠𝑖𝑡𝑦 𝑜𝑓 𝑠𝑎𝑛𝑑 = 𝑊𝑒𝑖𝑔ℎ𝑡 𝑜𝑓 𝑠𝑎𝑛𝑑 𝑖𝑛 𝑐𝑜𝑛𝑒 𝑉𝑜𝑙𝑢𝑚𝑒 𝑜𝑓 𝑐𝑜𝑛𝑒 (𝑔/𝑐𝑚3 ) 𝐹𝑖𝑒𝑙𝑑 𝑑𝑒𝑛𝑠𝑖𝑡𝑦 𝑜𝑓 𝑒𝑥𝑐𝑎𝑣𝑎𝑡𝑒𝑑 𝑠𝑜𝑖𝑙 = 𝑊𝑒𝑖𝑔ℎ𝑡 𝑜𝑓 𝑠𝑜𝑖𝑙 𝑒𝑥𝑐𝑎𝑣𝑎𝑡𝑒𝑑 𝑓𝑟𝑜𝑚 𝑠𝑜𝑖𝑙 𝑉𝑜𝑙𝑢𝑚𝑒 𝑜𝑓 𝑠𝑎𝑛𝑑 𝑓𝑖𝑙𝑙𝑖𝑛𝑔 𝑒𝑥𝑐𝑎𝑣𝑎𝑡𝑒𝑑 ℎ𝑜𝑙𝑒 (𝑔/𝑐𝑚3 ) Where 𝑉𝑜𝑙𝑢𝑚𝑒 𝑜𝑓 𝑠𝑎𝑛𝑑 𝑓𝑖𝑙𝑙𝑖𝑛𝑔 ℎ𝑜𝑙𝑒 = 𝑊𝑒𝑖𝑔ℎ𝑡 𝑜𝑓 𝑆𝑎𝑛𝑑 𝑖𝑛 ℎ𝑜𝑙𝑒 𝐷𝑒𝑛𝑠𝑖𝑡𝑦 𝑜𝑓 𝑠𝑎𝑛𝑑 (𝑐𝑚3 ) This density was then compared to the specifications for the compaction of that particular layer. The required compactions for each particular layer for the road project, for tests carried out at CH2+100 were as follows:  Road bed – 93%  Subgrade – 95%  Sub base – 95%  Base – 98% In case the field values did not meet the required values then the Ministry of Works and Transport reserved the right to instruct the contractor to repeat the compaction work. 3.4 Asphalt Concrete works The laying of the wearing course layer with premix was done following the following procedures:  Cleaning of the surface  Priming  Tack Coating  Paving of Bituminous mix/Spreading  Quality testing  Compacting 3.4.1 Cleaning Immediately before priming, loose stones were removed, dust and foreign material from the base surface. It was done using a mechanical broom and high-pressure air jet from compressor. It was done manually by workers using brooms in some instances where the sweeper truck was not reliable. Traffic was then kept off the cleaned surface.
  • 65. 54 Figure 31: Cleaning surface in preparation for asphalt paving 3.4.2 Priming process This is the process of spraying a mixture of bitumen and paraffin along the stabilized base in order seal off the base or protect the base from being affected by water. The primer used for the project was grade MC30 (minimum kinematic velocity 30poise at 140o F). The priming process involved calibration of the distributor, and spreading of the primer 3.4.2.1 Calibration of priming machine (Marine truck) Primer is applied onto finished base so as to seal the surface and prevent penetration of water to the road layers beneath. However, the spray rate needs to be within certain limits so as to avoid application of excess primer which would cause bleeding or too little primer that would leave some surface sections exposed. The specified range for this project was (0.8 - 0.9) kg/m2 Equipment  Metallic trays (30cm by 30cm)  Weighing scale  Calculator Procedure The weight of the empty trays was measured and recorded. The trays were placed along the finished base at different positions such that the primer could be collected from the spray bar of the distributor truck as it drove along. Each tray and its contents was weighed again and the masses recorded.