SlideShare a Scribd company logo
Study on the Construction Process of
Superstructure of a Seven Storied Residential
Building
Presented By-
Md. Mahfuzur Rahman Jony Md. Khokan Mia
Id# 14106020 Id# 14106028
Program: BSCE Program: BSCE
IUBAT – International University of Business Agriculture and Technology
1
4/1/2018
CONTENTS
 Introduction
 Objectives
 Company overview
 Company organogram and our project details
 Design specification
 Construction materials & equipment's
 Construction process of beam, slab, stair & column
 Problems & solution
 Recommendation
 Conclusion
2
4/1/2018
INTRODUCTION
 In this presentation we will try to present our 4 month’s practicum
experience of the construction work of a seven storied residential building.
 We observed the construction process of super structural parts of a
reinforced concrete building.
 Here we have focused on mainly column, stair, beam and slab construction
process.
3
4/1/2018
OBJECTIVES
 To get knowledge about the structural drawing & design specification.
 To implement the structural drawing into construction site.
 To understand the construction and supervision work of column, stair,
beam and slab.
 To learn about the estimating details of Super Structural work.
 To acquire knowledge about the steps involving construction process.
 To learn how to solve the rising problems and unexpected events.
4
4/1/2018
Company Overview
Company Name: Tokyo Development Engineer’s Ltd.
Office Address: House- 26, Road- 09, Sector-13,
Uttara, Dhaka- 1230
Phone: 02-550 89047, 550 88865
E-mail: tokyobd@yahoo.com
Web: www.tokyobd.com
5
4/1/2018
Company Organogram6
4/1/2018
About Our Project
Our project name: Tokyo Karim’s Garden
Address: House #742, Road #23,Block-F,
Bashundhara Residential Area.
Property Details: Unit Size: 1650 sft.
(Bedroom-3, Formal living, Family living,
Dining, Bathroom-3)
Building Facing: North facing
Building Storied: (GF+6) = 7 (Seven)
Storied Residential Building.
Structural Designer:
Kawser Talukder
B.Sc. Engg. (BUET)
FIEB,RAJUK ENLISTED
Fig: 3D View of Tokyo Karim’s Garden
7
4/1/2018
Typical Floor Plan8
4/1/2018
9
Design Specification
4/1/2018
General:
 Design method followed is USD according to BNBC, 2006 and ACI Code 2008.
Concrete:
 f’c = 3500 psi for columns, Cap
 f’c (specific strength) = Minimum 20 Mpa (3000 psi) for all other members.
 Minimum cement concrete ratio 1:1.5:3 for column and cap.
 Minimum cement concrete ratio 1:2:4 for other members.
Concrete Aggregate:
 Fine aggregate: Local Sand of FM 1.2 & Sylhet Sand of FM 2.0 (minimum)
 Coarse Aggregate: 20 mm down well graded stone chips shall be used as coarse aggregate in column,
Shear Wall and Cap and Brick Chips in other members.
Steel Reinforcement:
 Reinforcement are 72 grade deformed bar having minimum fy = 500 Mpa (72,000 psi)
Water:
 Portable water to be used in concrete mix
Design Specification10
4/1/2018
Design Specification (Continued)
Lap Length:
Bar
type
Bar
Positi
on
Bar Size
10 12 16 20 25
Tensio
n
Top
450 600 750 900 1625
Botto
m 400 475 650 800 1250
Compression
300 350 475 600 750
11
Clear Cover:
Member Location of
Condition
Clear
Cover
Column Above ground
Level
1.5”
(40
mm)
Beam Top Side &
Bottom
1.5”
(40
mm)
Slab &
Stair
Top and
Bottom
1” (25
mm)
4/1/2018
Construction Materials
Materials:
Cement
Fine Aggregate
Fig: Seven Rings Special Cement
Fig: Local Sand Fig: Sylhet Sand
FM Practical Design
Specification
Sylhet 3.0 2.0
12
4/1/2018
Construction Materials (Cont.)
Fig: Brick Chips Fig: Stone Chips
Fig: Reinforcement bar
Materials:
 BSI Rod (72 Grade)
 20 mm down graded Stone-Column
 20 mm down brick Chips- slab,
stair
13
4/1/2018
Main Equipment's
Fig: Mixer Machine
Fig: Bar CutterFig: Vibrator
Fig: Crane
14
4/1/2018
Field Test of Cement
Fig: Checking Hard Lumps Fig: Checking Temperature Fig: Checking Manufacturing Date
Name of the Test Practical Standard
Adulteration Test No hard Lumps No hard Lumps
Temperature Test Cool Cool
Manufacturing Date It should used within 90 days It was used within 90 days
15
Table: comparison between practical and standard
4/1/2018
Field Test of Aggregate
Fig: Colour Check Fig: Earthy Substance Check
Fig: Salt Test
Name of Test practical Standard
Salt Test No salty Taste No salty Taste
Silt Test No Earthy
Sub.
No Earthy
Sub.
Color check Golden
Yellow
Golden
Yellow
16
4/1/2018
Angular size Test:
Field Test of Aggregate(continued)
Large size ¾
inch
60%,
Medium size
½ inches
30%
Small size ¼
inch
10%
Fig: Checking Angular Size
17
4/1/2018
Field Test of Bricks
Fig: Tee Test
Fig: Hardness Test
Fig: Soundness Test
Name of Test Practical Standard
Hardness Test No Mark on Surface No Mark on Surface
Soundness Test Metallic Sound Metallic Sound
Tee Test Broken Remain Unbroken
18
4/1/2018
Field Test of Bricks (continued)
Fig: Checking Brick Size
Practical Standard
9.5”x4.5”x2.75” 9.5”x4.5”x2.75”
19
4/1/2018
SL Sieve Size
(mm)
Retain(gm)
Retained
Weight
Percentage
Cumulative
(%)
1 4.75 7 0.70 0.70
2 2.36 17 1.71 2.41
3 1.18 89 8.93 11.34
4 0.600 750 75.23 86.57
5 0.300 130 13.03 99.60
6 0.150 4 0.40 100
7 pan 0 0.00 100
Lab Test
Practical FM Design Specification FM
3.00 2.0
Fineness Modulus (FM) = Summation of cumulative (%)  100
= (0.70 + 2.41 + 11.34 + 86.57 + 99.60 + 100)  100
=3.006 = 3.00
20
Lab Test of Fine Aggregate:
Fig: Sieve Analysis of Fine Aggregate
4/1/2018
Lab Test (continued)
SL Sieve Size
(mm)
Retain(gm) Retained
Weight
Percentage
Cumulative
(%)
1 25 720 36.04 36.04
2 19 813 40.69 76.73
3 12.5 450 22.52 99.25
4 10 7 0.35 99.60
5 4.75 0.00 0.00 99.60
6 pan 8 0.40 100
Practical FM Design Specification FM
5.00 6.0-6.9
Fineness Modulus (FM) = Summation of cumulative (%)  100
= (36.04 + 76.73 + 99.25 + 99.60 + 99.60 + 100)  100
= 5.12 = 5.00
21
Lab Test of Coarse Aggregate:
Fig: Sieve Analysis of Coarse
Aggregate
4/1/2018
 Concrete Mixing Ratio is 1:1.5:3
 Load = 171.44 KN
Cylinder Test
Name of Test Practical Design
Specification
Concrete
compressive
strength
3165 psi for 21
days
3150 psi for 21
days
22
4/1/2018
Formwork Materials
Fig: Plain sheets
Fig: Wooden frame
Fig: Steel Shutter
Fig: Bamboo Props
23
4/1/2018
We have observed the following construction process:
 Construction of column.
 Construction of stair.
 Construction of beam.
 Construction of slab.
Construction Process24
4/1/2018
25
Construction of Column
4/1/2018
 Total 14 Columns
 Five Types of
Column(C-1 to C-5)
& We observed C-2
Type
Construction of Column26
Column Layout plan:
4/1/2018
 We observed the entire columns but as we are going to explained C-2
type column. The column size is 12”X18”. 6-20mm & 4-16mm bar are
used is this column in 3th Floor.
Construction of Column27
Column Schedule:
4/1/2018
The following works are followed at the time of column construction:
 Kicker making.
 Reinforcement bar placing.
 Shuttering.
 Casting.
 Curing.
Construction of Column28
4/1/2018
Construction of Column29
Fig: Kicker Making and Checking
Kicker Making:
4/1/2018
Construction of Column
Fig: Column Ties Fig: Placing tie on Column Fig: Tie Binding
30
Reinforcement Bar Placing:
4/1/2018
 10mm@ 4”c/c spacing is at the
end section for tie binding.
 10mm@ 8”c/c spacing at the mid
section for tie binding.
 25” Provide as lapping length for
16 mm bar
Construction of Column
Fig: 4” c/c Spacing
Fig: 8” c/c SpacingFig: Checking Lapping Length
31
Checking Bar Arrangement:
4/1/2018
 Main Bar: 6-20Ø & 4-16Ø
bar Used.
 Tie Bar: 19-10Ø bar Used
Construction of Column
Fig: Column Main Bar & Tie Spacing
Fig: Cross Section(C-2)
32
Details of Column (C-2):
4/1/2018
Construction of Column
Fig: Cleaning Shutter Fig: Fixing Shutter Fig: Completed Shuttering
Fig: Checking Vertical Alignment at bottom, mid and top section
33
Column Shuttering & Checking:
4/1/2018
 Mixing by Mixer Machine
 Mixing Ratio- 1: 1.5 : 3
 Using Vibrator
 Cement Grout Spread
 cement, Sylhet Sand &
Stone
 Water-Cement Ratio: 0.40
 4′-4″ column casted
Construction of Column
Fig: Column Casting Fig: Using Vibrator
34
Column Casting:
4/1/2018
 Remove the nuts by the screw
 Then De-Shutter the Column
 Curing by Hose Pipe
Fig: Column De-Shuttering Fig: Column Curing
35
4/1/2018
Construction of Column
Curing of Column
 Number of Column: 1 NO
 Height of the column: 8.25 ft.
 Column Dimension: 1.0×1.5 ft. Or (12”X18”)
 Total Volume: (1×1.5×8.25) = 12.40 cu. ft.
 Dry Volume: 12.40 ×1.5 =18.56 cu. ft.
 Mixing Ratio = 1:1.5:3
 Water/Cement ratio = 0.4
Concrete Calculation:
 Cement= (Dry Volume x Cement
ratio)/Summations of ratio
 Sand = (Dry Volume x Sand
ratio)/Summations of ratio
 Stone = (Dry Volume x Stone
ratio)/Summations of ratio
 So, Cement = 3.0 bags
 Sand = 5.0 cu. ft.
 Stone = 11 cu. ft.
Reinforcement Calculation:
 20mm & 16mm bar = 1× ((6×10×.75) +
(4×10×.48)) = 64.2 kg.
 10mm bar = 1×19×7×.19 = 25.27 kg.
36 Sample Estimation for C-2
Cement Sand Stone
3.0 bags 5.0 cu. ft. 11 cu. ft.
Main Bar Tie Bar
64.2 kg 25.27 kg 4/1/2018
37 Concrete Details of All Column
Column Name No. of
Column
Size of Column Cement Sand Stone
C-1 2
12”X15”
3.0 bags 5.0 cu. ft 11 cu. ft.
C-2 1
12”X18”
13 bags 23 cu. ft 46 cu. ft.
C-3 6
12”X20”
18 bags 34.0 cu. ft. 68 cu. ft.
C-4 4
12”X20”
3.0 bags 5.0 cu. ft 11 cu. ft.
C-5 1
12”X18”
5.0 bags 9.0 cu. ft. 17 cu. ft.
4/1/2018
38
0
20
40
60
80
100
120
140
160
180
Cement (kg) Sand (cu. ft.) Stone (cu. ft.)
Estimated
Actual
Materials Estimated Actual
Cement 42 bags 41 bags
Sand 76 cu. ft. 78 cu. ft
Stone 153 cu. ft. 154 cu. ft.
Concrete Details of All Column
Comparison between Estimated vs Actual Materials:
39 Reinforcement Details of All Column
Column
Name
No. of
Column
Tie Bar Size of
Column
Reinforcemen
t of Column
Main bar
Weight
Tie bar
Weight
C-1 2 19-10 Ø
12”X15”
4-20mm+
4-16mm
99 kg 38 kg
C-2 1 19-10 Ø
12”X18”
6-20mm+
4-16mm
64 kg 26 kg
C-3 6 19-10 Ø
12”X20”
6-25mm+
6-20mm
443 kg 159 kg
C-4 4 19-10 Ø
12”X20”
6-25mm+
6-20mm
461 kg 159 kg
C-5 1 19-10 Ø
12”X18” 10-20mm
90 kg 26 kg
40
0
50
100
150
200
250
300
350
400
450
500
C-1 C-2 C-3 C-4 C-5
Estimated
Main bar (kg)
Used Main Bar
(kg)
Reinforcement Details of All Column
Column
Name
Estimated
Main bar
(kg)
Used Main
Bar
C-1 99
101
C-2 64
65
C-3 443
450
C-4 461
467
C-5 90
92
Comparison between Estimated vs Actual Reinforcements:
Working Schedule of Column
22-Sep 27-Sep 2-Oct 7-Oct 12-Oct 17-Oct
Reinforcement Placement of Column
Tie Binding
Column Shuttering
Column Casting
Column Curing
Duration
41
4/1/2018
42
Construction of Stair
4/1/2018
The following works are followed at the time of stair construction:
 Shuttering of stair.
 Reinforcement bar placing.
 Shuttering of treads and risers.
 Casting of stair.
 Curing of stair.
Construction of Stair43
4/1/2018
 Stair total length 14.5′ & width 8′
 Stair has Two Flight
 Each Flight has 8 Steps
 Each step height 6″ & wide 10″
44
4/1/2018
Construction of Stair
Stair Plan:
 First timber
planks fixed.
 Runner
attached with
timber
planks.
 Bamboo
props
Support the
Runner.
Fig: Stair Shuttering and using Jute Fabric
4/1/2018
45 Construction of Stair
Shuttering of Stair:
 Main Bar: 12mm@ 6”
c/c
 Binder Bar: 10mm@ 6”
c/c
 Extra Top bar length L/4
 12mm@ 6” c/c in
Landing & 2-16mm bar
in Landing
46
4/1/2018
Construction of Stair
Reinforcement Details:
47 Construction of Stair
Fig: Reinforcement bar placing
Reinforcement Bar placing & Checking:
Fig: Checking
Fig: Making Riser & Tread Fig: Checking Tread Fig: Checking Riser
48
4/1/2018
Construction of Stair
Making & Checking Riser &Tread:
Fig: Pouring water Fig: Casting of Stair
Fig: Using VibratorFig: Complete Casted Stair Fig: using Trowel
49
4/1/2018
Construction of Stair
Casting of Stair:
Fig: Curing of Stair
 Curing Start at Next day
 Spreading Water by hose pipe
 2-3 times on a day
50
4/1/2018
Construction of Stair
Curing of Stair:
4/1/2018
51 Estimation of Stair
Landing = (8’×4’+8’×3.5’) ×6”
= 30 cft
Waist slab = (9’×3’7”×6”×2)
=32.2 cft
Step = (1/2×10”×6”×3’7”×17)
=12.7 cft
Total volume = (30+32.3+12.7) =75 cft
Dry volume = 75×1.5 =112.5 cft
Mixing ratio = 1:2:4
Summation of ratio =1+2+4 =7
Cement = (112.5X1)/7 = 16.1 X 0.8 = 13 bags
Sand = (112.5X2)/7 = 32.14 cft
Brick chips = (112.5X4)/7 = 64.3 cft
Concrete calculation:
Cement Sand Brick chips
13 bags 33 cft 65 cft
0
10
20
30
40
50
60
70
80
Cement Sand Brick chips
Estimaed
Actual
4/1/2018
52 Estimation of Stair
Reinforcement calculation:
Cement Sand Brick chips
13 bags 33 cft 65 cft
0
10
20
30
40
50
60
70
80
Cement Sand Brick chips
Estimaed
Actual
Main bar length = 4+3.5+9 = 16.5 ft.
Number of bar = 8 and 12mm@6”.
So, weight of main bar = 0.27×8×16.5 = 35.64 kg×2 = 71.28 kg
Binder bar length = 3.83 ft.
Number of binder = 33 and 10mm@6”.
So, weight of binder bar = 0.19×18×3.83 = 13.10 kg×2 = 26.2 kg
Extra top length = 7 ft.
Number of bar = 8 and 12mm@6”.
So, weight of top bar = 0.27×7×8 = 15.12 kg×2 = 30.24 kg
Extra top length = 6.5 ft.
Number of bar = 8 and 12mm@6”.
So, weight of top bar length = 0.27×6.5×8 = 14.04 kg×2 = 28.08 kg
Binder bar length = 3.83 ft.
Number of binder = 6 and 10mm@6”
So, weight of binder bar = 0.19×3.83×6 = 4.37 kg×4 = 17.48 kg
Working Schedule of Stair
5-Oct 10-Oct 15-Oct 20-Oct 25-Oct 30-Oct 4-Nov
Shuttering of Stair
Reinforcement Placement on Stiar
Tread and Riser Making
Casting of Stair
Curing of Stair
Duration
53
4/1/2018
4/1/2018
54
Construction of Beam & Slab
Construction of Beam & Slab
The following works are followed at the time of beam & slab construction:
 Shuttering
 Reinforcement bar placing
 Casting
 Curing
55
4/1/2018
Fig: Bottom shutter of Beam Fig: All side shutter of Beam
4/1/2018
56
 First timber
planks fixed.
 Runner
attached with
timber
planks.
 Bamboo
props
Support the
Runner.
Shuttering of Beam:
Construction of Beam & Slab
Fig: Runner placing on Slab
Fig: Wooden plank placing on Slab
Fig: Runner supported by bamboo Props
Fig: Steel Sheet Placing on Slab 4/1/2018
57 Construction of Beam & Slab
Shuttering of Slab:
4/1/2018
58
Compariso
n
Required Used
Bamboo
Props
241 233
Wooden
Runner
51 50
Steel Sheet 54 57
0
50
100
150
200
250
300
Bamboo Props Wooden Runner Steel Sheet
Required
Used
Construction of Beam & Slab
Calculation Shuttering Materials of Beam & Slab:
Construction of Beam & Slab
4/1/2018
59
Beam Layout Plan:
 Total 14 Beams.
 Classify (FB-1
to FB-14)
 Here I am
going to explain
FB-1
Fig: Reinforcement details of beam (FB- 1) 4/1/2018
60 Construction of Beam & Slab
Reinforcement Details of Beam:
 Top Bar: 2-20 mm
 Ext Top Bar: 1- 20mm
 Bottom Bar: 2-16mm
 Ext Bottom Bar:1-16mm
 Stirrup: 63-10 mm
Fig: Keep the Stirrup on Marked Place
Fig: Placement of Stirrup
Fig: Fixing Bottom & Top bar
Fig: Stirrup Binding
4/1/2018
61 Construction of Beam & Slab
Reinforcement Bar Placing:
Fig: Extra top & bottom bar placement 4/1/2018
62 Construction of Beam & Slab
Reinforcement Bar Placing:
Fig: Checking stirrup spacing at end
section
Fig: Checking stirrup spacing at mid
section
Fig: Checking clear cover of beam
4/1/2018
63
Checking Reinforcement Bar Arrangement:
Construction of Beam & Slab
4/1/2018
64
Concrete Calculation:
Beam size = 10″ x 21″
L= 38.42 ft
Volume = .83 x 1.75 × 38.42 =
55.81 cft
Dry volume = 1.5 × 55.81 = 83.72
cft
Ratio = 1:2:4
Cement = (83.72 × 1) / 7 = 11.96 x
.8= 14.96 bags
Sand = (83.72 × 2)/ 7 = 23.92 cft
Brick chips = (83.72 ×4) /7 = 47.48 cft
Reinforcement Calculation:
Total length for straight bar = L + 2×hook+
lapping = 38.42+2× (6/12) = 39.42 ft
Main Bar: 2-20mm& 2-16mm =2×.75
×39.42+2×.48×39.42 = 96.97 kg.
Extra Top bar length: 33.08 ft.
Extra Bottom length: 8.00 ft.
Extra Bar: 1-20mm & 1-16mm = 1×33.08×.75
+ 1×8.00×.48 = 28.65 kg.
Tie bar Length: 5.17 ft.
Total Number of Tie: 63 NOS
Tie bar: 10mm = 63×5.17×.19
= 61.88 kg.
4/1/2018
65
Name of Beam Main Bar Weight Extra Bar Weight Tie Bar Weight
FB-1 (12”x20”) 96.97 kg. 28.65 kg. 61.88 kg.
FB-2(10”X20”) 35.7 kg 00 kg 16.15 kg
FB-3(10”X21”) 94.91 kg 19.29 kg 32.42 kg
FB-4(10”X10”) 27 kg 6 kg 10.6 kg
FB-5(10”X10”) 31.26 kg 16.11 kg 17.76 kg
FB-6(10”X10”) 19.5 kg 00 kg 10.75 kg
FB-7(10”X21”) 49.29 kg 16.53 kg 41.26 kg
FB-8(10”X15”) 48.24 kg 11.38 kg 30.11 kg
FB-9(7”X15”) 46.5 kg 00 kg 21.62 kg
FB-10(10”X20”)(7”X20”) 96.75 kg 36.64 kg 51.87 kg
FB-11(10”X12”) 35.49 kg 16.25 kg 15.33 kg
FB-12(10”X20”) 96.75 kg 29.25 kg 79.8 kg
FB-13(10”X20”) 62.01 kg 14.75 kg 30.4 kg
FB-14(10”X15”) 40.26 kg 9.32 kg 20.58 kg
4/1/2018
66
Name Cement Sand Bricks Chips
FB-2(10”X20”) 2.60 bags 6.50 cft 12.98 cft.
FB-3(10”X21”) 3.44 bags 8.61 cft 17.23 cft
FB-4(10”X10”) 0.95 bags 2.36 cft 4.73 cft
FB-5(10”X10”) 1.34 bags 3.35 cft 6.70 cft
FB-6(10”X10”) .65 bags 1.62 cft 3.25 cft
FB-7(10”X21”) 6.14 bags 15.36 cft 30.71 cft
FB-8(10”X15”) 2.68 bags 6.71 cft 13.41 cft
FB-9(7”X15”) 1.80 bags 4.51 cft 9.01 cft
FB-10(10”X20”)(7”X20”) 6.39 bags 15.97 cft 31.94 cft
FB-11(10”X12”) 1.54 bags 3.85 cft 7.714 cft
FB-12(10”X20”) 7.41 bags 18.53 cft 37.05 cft
FB-13(10”X20”) 4.67 bags 11.68 cft 23.37 cft
FB-14(10”X15”) 2.21 bags 5.52 cft 11.05 cft
4/1/2018
67
Beam Used Stirrups Required Stirrups
FB-1 56 53
FB-2 17 16
FB-3 33 33
BF-4 22 22
FB-5 35 38
FB-6 20 22
FB-7 42 38
Fb-8 38 40
Fb-9 31 33
Fb-10 67 64
Fb-11 22 23
Fb-12 84 80
Fb-13 32 32
Fb-14 26 26
0
10
20
30
40
50
60
70
80
90
Used Stirrups
Required Stirrups
Fig: Bottom slab reinforcement
4/1/2018
68 Construction of Beam & Slab
Reinforcement Details of Bottom Slab:
 Main Bar: 10 mm
 Binder: 10 mm
Fig: Checking cc distance
reinforcement of slab
Fig: Checking lapping length of
bottom slab reinforcement
Fig: Checking 1ʺclear cover on
bottom slab reinforcement
Fig: Bottom slab reinforcement placement Fig: After placing bottom slab reinforcement
4/1/2018
69 Construction of Beam & Slab
Reinforcement placing on Bottom Slab & Checking:
Fig: Top slab reinforcement
4/1/2018
70 Construction of Beam & Slab
Reinforcement Details of Top Slab :
 Main Bar:
10mm & 12 mm
 Binder: 10 mm
Fig: Concrete block for maintain clear coverFig: Top slab reinforcement placement 4/1/2018
71 Construction of Beam & Slab
Reinforcement Bar Placing on Top Slab :
Fig: Checking 3ʺclear cover on top
slab reinforcement
Fig: Checking extra top bar length Fig: Checking top bar spacing4/1/2018
72 Construction of Beam & Slab
Checking Top Slab Reinforcement Bar Placement:
Fig: Concrete mixing in mixer machine Fig: Using crane for pulling up the concrete
Fig: Concrete place on Slab
Fig: Casting the beam
4/1/2018
73 Construction of Beam & Slab
Casting of Beam & Slab:
Fig: Using vibrator for compaction Fig: Using steel runner for leveling
Fig: Placement of U-bar Fig: checking depth of slab
4/1/2018
74 Construction of Beam & Slab
Casting of Beam & Slab:
4/1/2018
75 Construction of Beam & Slab
Casting of Beam & Slab:
Fig: Making Pond for Curing Fig: Curing the Slab
4/1/2018
76 Construction of Beam & Slab
Curing of Beam & Slab:
4/1/2018
77
pan Cement Sand Bricks
Span-1 4.06 bags 10.16 cft 20.32 cft
Span-2 9.66 bags 24.15 cft 48.30 cft
Span-3 4.85 bags 12.12 cft 24.24 cft
Span-4 3.93 bags 9.83 cft 19.67 cft
Span-5 13 bags 33 cft. 67 cft.
Span-6 15.50 bags 38.72 cft 77.45 cft
Span-7 6.64 bags 16.61 cft 33.22 cft
4/1/2018
78 Span Bottom bar Weight Top bar Weight
Span-1 42 kg 40 kg
Span-2 87 kg 84 kg
Span-3 83 kg 53 kg
Span-4 64 kg 48 kg
Span-5 219 kg 104 kg
Span-6 175 kg 101 kg
Span-7 80 kg 55 kg
Working Schedule of Beam & Slab
8-Oct 18-Oct 28-Oct 7-Nov 17-Nov 27-Nov 7-Dec
Shuttering of Beam
Shuttering of Slab
Thin Sheet Placement & Leveling
Reinforcement Placement on Beam
Reinforcement Placement on Slab
Shuttering of Stair
Casting of Beam,Stair & Slab
Curing of Slab
Duration
4/1/2018
79
 Total length for straight bar = L +
2×hook+ lapping = 38.42+2× (6/12) =
39.42 ft
 Main Bar: 2-20mm& 2-16mm = 2×.75
×39.42+2×.48×39.42 = 96.97 kg.
 Extra Top bar length: 33.08 ft.
 Extra Bottom length: 8.00 ft.
 Extra Bar: 1-20mm & 1-16mm =
1×33.08×.75 + 1×8.00×.48 = 28.65 kg.
 Tie bar Length: 5.17 ft.
 Total Number of Tie: 63 NOS
 Tie bar: 10mm = 63×5.17×.19 = 61.88
kg.
 Beam size = 10″ x 21″ , L= 38.42 ft
Volume = .83 x 1.75 × 38.42 = 55.81 cft
 Dry volume = 1.5 × 55.81 = 83.72 cft
 Ratio = 1:2:4
 Cement = (83.72 × 1) / 7 = 11.96 x .8 = 14.96
bags
 Sand = (83.72 × 2)/ 7 = 23.92 cft
 Brick chips = (83.72 ×4) /7 = 47.48 cft
80 Sample Estimation of FB-1
4/1/2018
 Problem-1: During the column casting, liquid of concrete mix came out
from the form of column due to leakage in formwork or improper
shuttering of column.
 Solution: We alert the labor about the leakage on the column Shutter and
said to used jute tap properly which can protect the leakage on shutter.
Problem and Solution
Fig: Leakage of formwork
4/1/2018
81
 Problem-2: Column C-3, after
removing the shuttering there are
honeycomb on the column which can
occur due to improper vibration.
Problem and Solution (Continued)
Fig: Honeycomb in column
4/1/2018
82
Solution: We suggest the labor to fill the
honeycomb by cement paste. Then they
filled the place by cement paste and
make plain by rubbing the jute tap.
Fig: Using cement paste in honeycomb
 Problem-3: In beam FB-2, Stirrup spacing is changed and being some
transverse during the placement of beam.
Problem and Solution (Continued)
Fig: Changed spacing in stirrup
Solution: We inform the labor about it and then they rebind the ties
maintaining the correct spacing.
4/1/2018
83
 Problem-4: Safety should be the first condition in construction work. Wearing
helmet and pant is safer than lungi and free head.
Problem and Solution (Continued)
Solution: We talk with them and make aware about the safety but they don‘t take
any measure. Most of the time, they work unsafely. When we said about the
safety, they replied that they would be habituated in this condition.
Fig: Working without safety
4/1/2018
84
During our practicum period we are face some problems and our
recommendation are:
 There are no working schedule in the construction site. Company should
have work schedule for every project . Maintain work schedule properly
can save cost.
 The management should aware of the safety. A little training and care can
prevent accidents in the project.
 Company should need to do some test like slump test, cylinder test etc.
Some test like this can ensure the strength able construction.
Recommendation
4/1/2018
85
We have supervised beam, slab, stair & column construction work. After
supervising our construction site, We have learned about beam, slab, stair &
column construction and achieved practical experience. We have also learned
construction management. It was an awesome experience dealing with
different types of people at construction site. It seems to me that the practical
knowledge is the most essential to be an efficient engineer. I tried to give my
full afford as trainee engineers. Overall the internship program laid sound
foundation for us to start our career.
Conclusions
4/1/2018
86
Thanks To All
4/1/2018
87

More Related Content

What's hot

Project Report on Concrete Mix Design of Grade M35
Project Report on Concrete Mix Design of Grade M35Project Report on Concrete Mix Design of Grade M35
Project Report on Concrete Mix Design of Grade M35Gyan Prakash
 
Industrial Training report Civil Engineering.
Industrial Training report Civil Engineering.Industrial Training report Civil Engineering.
Industrial Training report Civil Engineering.JAPJEETSINGH13
 
Construction of residential building
Construction of residential buildingConstruction of residential building
Construction of residential buildingSumit Singh
 
PWD CC ROAD CONSTRUCTION WORK TRAINING REPORT
PWD CC ROAD CONSTRUCTION WORK TRAINING REPORTPWD CC ROAD CONSTRUCTION WORK TRAINING REPORT
PWD CC ROAD CONSTRUCTION WORK TRAINING REPORTSatyam Anand
 
SUMMER TRAINING REPORT ON BUILDING CONSTRUCTION
SUMMER TRAINING REPORT ON BUILDING CONSTRUCTIONSUMMER TRAINING REPORT ON BUILDING CONSTRUCTION
SUMMER TRAINING REPORT ON BUILDING CONSTRUCTIONVed Jangid
 
INDUSTRIAL TRAINING PRESENTATION FOR CIVIL ENGINEERING
INDUSTRIAL TRAINING PRESENTATION FOR CIVIL ENGINEERING INDUSTRIAL TRAINING PRESENTATION FOR CIVIL ENGINEERING
INDUSTRIAL TRAINING PRESENTATION FOR CIVIL ENGINEERING Ram1239
 
Industrial training report of construction of the residential building
Industrial training report of construction of the residential buildingIndustrial training report of construction of the residential building
Industrial training report of construction of the residential buildingsuraj jha
 
ROAD CONSTRUCTION(BITUMEN) SUMMER TRAINING REPORT
ROAD CONSTRUCTION(BITUMEN) SUMMER TRAINING REPORTROAD CONSTRUCTION(BITUMEN) SUMMER TRAINING REPORT
ROAD CONSTRUCTION(BITUMEN) SUMMER TRAINING REPORTssuser5fea8f
 
REPORTS ON BUILDING CONSTRUCTION
REPORTS ON BUILDING CONSTRUCTIONREPORTS ON BUILDING CONSTRUCTION
REPORTS ON BUILDING CONSTRUCTIONRising Sher
 
final year Project (civil)
final year Project (civil)final year Project (civil)
final year Project (civil)Alankar jaiswal
 
project final year civil
project final year civilproject final year civil
project final year civilAlankar jaiswal
 
Civil engineering internship report
Civil engineering internship reportCivil engineering internship report
Civil engineering internship reportMd Mohsin Mohsin
 
PRESENTATION ON ROAD CONSTRUCTION INTERNSHIP NH34 BY IMRUL QUESH
PRESENTATION ON ROAD CONSTRUCTION  INTERNSHIP NH34 BY IMRUL QUESHPRESENTATION ON ROAD CONSTRUCTION  INTERNSHIP NH34 BY IMRUL QUESH
PRESENTATION ON ROAD CONSTRUCTION INTERNSHIP NH34 BY IMRUL QUESHImrul Quesh
 
ppt on pwd cement concrete road pavement
ppt on pwd cement concrete road pavementppt on pwd cement concrete road pavement
ppt on pwd cement concrete road pavementNIWASHISH VISWAS
 
Recycle material used in road construction
Recycle material used in road constructionRecycle material used in road construction
Recycle material used in road constructionpavan bathani
 

What's hot (20)

Project Report on Concrete Mix Design of Grade M35
Project Report on Concrete Mix Design of Grade M35Project Report on Concrete Mix Design of Grade M35
Project Report on Concrete Mix Design of Grade M35
 
Industrial Training report Civil Engineering.
Industrial Training report Civil Engineering.Industrial Training report Civil Engineering.
Industrial Training report Civil Engineering.
 
Construction of residential building
Construction of residential buildingConstruction of residential building
Construction of residential building
 
PWD CC ROAD CONSTRUCTION WORK TRAINING REPORT
PWD CC ROAD CONSTRUCTION WORK TRAINING REPORTPWD CC ROAD CONSTRUCTION WORK TRAINING REPORT
PWD CC ROAD CONSTRUCTION WORK TRAINING REPORT
 
Repair and Rehabilitation
Repair and RehabilitationRepair and Rehabilitation
Repair and Rehabilitation
 
SUMMER TRAINING REPORT ON BUILDING CONSTRUCTION
SUMMER TRAINING REPORT ON BUILDING CONSTRUCTIONSUMMER TRAINING REPORT ON BUILDING CONSTRUCTION
SUMMER TRAINING REPORT ON BUILDING CONSTRUCTION
 
INDUSTRIAL TRAINING PRESENTATION FOR CIVIL ENGINEERING
INDUSTRIAL TRAINING PRESENTATION FOR CIVIL ENGINEERING INDUSTRIAL TRAINING PRESENTATION FOR CIVIL ENGINEERING
INDUSTRIAL TRAINING PRESENTATION FOR CIVIL ENGINEERING
 
Industrial training report of construction of the residential building
Industrial training report of construction of the residential buildingIndustrial training report of construction of the residential building
Industrial training report of construction of the residential building
 
ROAD CONSTRUCTION(BITUMEN) SUMMER TRAINING REPORT
ROAD CONSTRUCTION(BITUMEN) SUMMER TRAINING REPORTROAD CONSTRUCTION(BITUMEN) SUMMER TRAINING REPORT
ROAD CONSTRUCTION(BITUMEN) SUMMER TRAINING REPORT
 
REPORTS ON BUILDING CONSTRUCTION
REPORTS ON BUILDING CONSTRUCTIONREPORTS ON BUILDING CONSTRUCTION
REPORTS ON BUILDING CONSTRUCTION
 
Internship review (Civil Engineering)
Internship review (Civil Engineering)Internship review (Civil Engineering)
Internship review (Civil Engineering)
 
final year Project (civil)
final year Project (civil)final year Project (civil)
final year Project (civil)
 
project final year civil
project final year civilproject final year civil
project final year civil
 
Civil engineering internship report
Civil engineering internship reportCivil engineering internship report
Civil engineering internship report
 
PRESENTATION ON ROAD CONSTRUCTION INTERNSHIP NH34 BY IMRUL QUESH
PRESENTATION ON ROAD CONSTRUCTION  INTERNSHIP NH34 BY IMRUL QUESHPRESENTATION ON ROAD CONSTRUCTION  INTERNSHIP NH34 BY IMRUL QUESH
PRESENTATION ON ROAD CONSTRUCTION INTERNSHIP NH34 BY IMRUL QUESH
 
Road construction report
Road construction reportRoad construction report
Road construction report
 
ppt on pwd cement concrete road pavement
ppt on pwd cement concrete road pavementppt on pwd cement concrete road pavement
ppt on pwd cement concrete road pavement
 
Bituminous Road
 Bituminous Road Bituminous Road
Bituminous Road
 
Recycle material used in road construction
Recycle material used in road constructionRecycle material used in road construction
Recycle material used in road construction
 
Pile foundations
Pile foundationsPile foundations
Pile foundations
 

Similar to Civil Engineering Internship Presentation-Anis Rahman Khokan

CEMENT CONCRETE MIX DESIGN.ppt
CEMENT CONCRETE  MIX DESIGN.pptCEMENT CONCRETE  MIX DESIGN.ppt
CEMENT CONCRETE MIX DESIGN.pptKuberBhusal1
 
partial replacement of fine aggregate by glass powder in concrete
partial replacement of fine aggregate by glass powder in concretepartial replacement of fine aggregate by glass powder in concrete
partial replacement of fine aggregate by glass powder in concreteParthi Ban
 
Casting unit 1 notes
Casting unit 1 notesCasting unit 1 notes
Casting unit 1 notesrmkcet
 
IRJET- Analytical Study of Solid Slab with Different Types of Cavity
IRJET- Analytical Study of Solid Slab with Different Types of CavityIRJET- Analytical Study of Solid Slab with Different Types of Cavity
IRJET- Analytical Study of Solid Slab with Different Types of CavityIRJET Journal
 
IRJET- Construction of Hollow Reinforced Concrete Block
IRJET- Construction of Hollow Reinforced Concrete BlockIRJET- Construction of Hollow Reinforced Concrete Block
IRJET- Construction of Hollow Reinforced Concrete BlockIRJET Journal
 
IRJET- Analysis of Properties of Mix Design Concrete using Steel Scrap
IRJET- Analysis of Properties of Mix Design Concrete using Steel ScrapIRJET- Analysis of Properties of Mix Design Concrete using Steel Scrap
IRJET- Analysis of Properties of Mix Design Concrete using Steel ScrapIRJET Journal
 
parthaproppt-copy-150405131505-conversion-gate01.pptx
parthaproppt-copy-150405131505-conversion-gate01.pptxparthaproppt-copy-150405131505-conversion-gate01.pptx
parthaproppt-copy-150405131505-conversion-gate01.pptxpakkurathikailashpav
 
Industrial training report
Industrial training reportIndustrial training report
Industrial training reportkiransuresh7
 
Industrial training report
Industrial training reportIndustrial training report
Industrial training reportkiransuresh7
 
IRJET- An Experimental Study on Mechanical Properties of Concrete by Partial ...
IRJET- An Experimental Study on Mechanical Properties of Concrete by Partial ...IRJET- An Experimental Study on Mechanical Properties of Concrete by Partial ...
IRJET- An Experimental Study on Mechanical Properties of Concrete by Partial ...IRJET Journal
 
Experimental study on partial repalcement of fine aggregate with construction...
Experimental study on partial repalcement of fine aggregate with construction...Experimental study on partial repalcement of fine aggregate with construction...
Experimental study on partial repalcement of fine aggregate with construction...eSAT Journals
 
IRJET- Study on Behaviour of Concrete Beams Containing Granite Powder
IRJET- Study on Behaviour of Concrete Beams Containing Granite PowderIRJET- Study on Behaviour of Concrete Beams Containing Granite Powder
IRJET- Study on Behaviour of Concrete Beams Containing Granite PowderIRJET Journal
 
IRJET- Experimental Investigation on Partial Replacement of M-Sand by Steel Slag
IRJET- Experimental Investigation on Partial Replacement of M-Sand by Steel SlagIRJET- Experimental Investigation on Partial Replacement of M-Sand by Steel Slag
IRJET- Experimental Investigation on Partial Replacement of M-Sand by Steel SlagIRJET Journal
 
IRJET- Study on Characteristics of Pervious Concrete and its Colourful Applic...
IRJET- Study on Characteristics of Pervious Concrete and its Colourful Applic...IRJET- Study on Characteristics of Pervious Concrete and its Colourful Applic...
IRJET- Study on Characteristics of Pervious Concrete and its Colourful Applic...IRJET Journal
 
IRJET - Fly Ash Interlocking Brick by using Geopolymer Concrete
IRJET - Fly Ash Interlocking Brick by using Geopolymer ConcreteIRJET - Fly Ash Interlocking Brick by using Geopolymer Concrete
IRJET - Fly Ash Interlocking Brick by using Geopolymer ConcreteIRJET Journal
 
IRJET- An Experimental Investigation of steel Concrete Composite Deck Slab
IRJET- An Experimental Investigation of steel Concrete Composite Deck SlabIRJET- An Experimental Investigation of steel Concrete Composite Deck Slab
IRJET- An Experimental Investigation of steel Concrete Composite Deck SlabIRJET Journal
 
IRJET- Experimental Study on Partial Replacement of Coarse Aggregate by C...
IRJET-  	  Experimental Study on Partial Replacement of Coarse Aggregate by C...IRJET-  	  Experimental Study on Partial Replacement of Coarse Aggregate by C...
IRJET- Experimental Study on Partial Replacement of Coarse Aggregate by C...IRJET Journal
 
IRJET - Experimental Investigation on Plasticizing Agent in Concrete
IRJET - Experimental Investigation on Plasticizing Agent in ConcreteIRJET - Experimental Investigation on Plasticizing Agent in Concrete
IRJET - Experimental Investigation on Plasticizing Agent in ConcreteIRJET Journal
 

Similar to Civil Engineering Internship Presentation-Anis Rahman Khokan (20)

CEMENT CONCRETE MIX DESIGN.ppt
CEMENT CONCRETE  MIX DESIGN.pptCEMENT CONCRETE  MIX DESIGN.ppt
CEMENT CONCRETE MIX DESIGN.ppt
 
partial replacement of fine aggregate by glass powder in concrete
partial replacement of fine aggregate by glass powder in concretepartial replacement of fine aggregate by glass powder in concrete
partial replacement of fine aggregate by glass powder in concrete
 
Casting unit 1 notes
Casting unit 1 notesCasting unit 1 notes
Casting unit 1 notes
 
IRJET- Analytical Study of Solid Slab with Different Types of Cavity
IRJET- Analytical Study of Solid Slab with Different Types of CavityIRJET- Analytical Study of Solid Slab with Different Types of Cavity
IRJET- Analytical Study of Solid Slab with Different Types of Cavity
 
IRJET- Construction of Hollow Reinforced Concrete Block
IRJET- Construction of Hollow Reinforced Concrete BlockIRJET- Construction of Hollow Reinforced Concrete Block
IRJET- Construction of Hollow Reinforced Concrete Block
 
IRJET- Analysis of Properties of Mix Design Concrete using Steel Scrap
IRJET- Analysis of Properties of Mix Design Concrete using Steel ScrapIRJET- Analysis of Properties of Mix Design Concrete using Steel Scrap
IRJET- Analysis of Properties of Mix Design Concrete using Steel Scrap
 
parthaproppt-copy-150405131505-conversion-gate01.pptx
parthaproppt-copy-150405131505-conversion-gate01.pptxparthaproppt-copy-150405131505-conversion-gate01.pptx
parthaproppt-copy-150405131505-conversion-gate01.pptx
 
Industrial training report
Industrial training reportIndustrial training report
Industrial training report
 
Industrial training report
Industrial training reportIndustrial training report
Industrial training report
 
Concrete Mix Design.pdf
Concrete Mix Design.pdfConcrete Mix Design.pdf
Concrete Mix Design.pdf
 
IRJET- An Experimental Study on Mechanical Properties of Concrete by Partial ...
IRJET- An Experimental Study on Mechanical Properties of Concrete by Partial ...IRJET- An Experimental Study on Mechanical Properties of Concrete by Partial ...
IRJET- An Experimental Study on Mechanical Properties of Concrete by Partial ...
 
Experimental study on partial repalcement of fine aggregate with construction...
Experimental study on partial repalcement of fine aggregate with construction...Experimental study on partial repalcement of fine aggregate with construction...
Experimental study on partial repalcement of fine aggregate with construction...
 
IRJET- Study on Behaviour of Concrete Beams Containing Granite Powder
IRJET- Study on Behaviour of Concrete Beams Containing Granite PowderIRJET- Study on Behaviour of Concrete Beams Containing Granite Powder
IRJET- Study on Behaviour of Concrete Beams Containing Granite Powder
 
IRJET- Experimental Investigation on Partial Replacement of M-Sand by Steel Slag
IRJET- Experimental Investigation on Partial Replacement of M-Sand by Steel SlagIRJET- Experimental Investigation on Partial Replacement of M-Sand by Steel Slag
IRJET- Experimental Investigation on Partial Replacement of M-Sand by Steel Slag
 
IRJET- Study on Characteristics of Pervious Concrete and its Colourful Applic...
IRJET- Study on Characteristics of Pervious Concrete and its Colourful Applic...IRJET- Study on Characteristics of Pervious Concrete and its Colourful Applic...
IRJET- Study on Characteristics of Pervious Concrete and its Colourful Applic...
 
Trial mixing concrete .pdf
Trial mixing concrete .pdfTrial mixing concrete .pdf
Trial mixing concrete .pdf
 
IRJET - Fly Ash Interlocking Brick by using Geopolymer Concrete
IRJET - Fly Ash Interlocking Brick by using Geopolymer ConcreteIRJET - Fly Ash Interlocking Brick by using Geopolymer Concrete
IRJET - Fly Ash Interlocking Brick by using Geopolymer Concrete
 
IRJET- An Experimental Investigation of steel Concrete Composite Deck Slab
IRJET- An Experimental Investigation of steel Concrete Composite Deck SlabIRJET- An Experimental Investigation of steel Concrete Composite Deck Slab
IRJET- An Experimental Investigation of steel Concrete Composite Deck Slab
 
IRJET- Experimental Study on Partial Replacement of Coarse Aggregate by C...
IRJET-  	  Experimental Study on Partial Replacement of Coarse Aggregate by C...IRJET-  	  Experimental Study on Partial Replacement of Coarse Aggregate by C...
IRJET- Experimental Study on Partial Replacement of Coarse Aggregate by C...
 
IRJET - Experimental Investigation on Plasticizing Agent in Concrete
IRJET - Experimental Investigation on Plasticizing Agent in ConcreteIRJET - Experimental Investigation on Plasticizing Agent in Concrete
IRJET - Experimental Investigation on Plasticizing Agent in Concrete
 

Recently uploaded

Basic Civil Engineering Notes of Chapter-6, Topic- Ecosystem, Biodiversity G...
Basic Civil Engineering Notes of Chapter-6,  Topic- Ecosystem, Biodiversity G...Basic Civil Engineering Notes of Chapter-6,  Topic- Ecosystem, Biodiversity G...
Basic Civil Engineering Notes of Chapter-6, Topic- Ecosystem, Biodiversity G...Denish Jangid
 
Embracing GenAI - A Strategic Imperative
Embracing GenAI - A Strategic ImperativeEmbracing GenAI - A Strategic Imperative
Embracing GenAI - A Strategic ImperativePeter Windle
 
Sectors of the Indian Economy - Class 10 Study Notes pdf
Sectors of the Indian Economy - Class 10 Study Notes pdfSectors of the Indian Economy - Class 10 Study Notes pdf
Sectors of the Indian Economy - Class 10 Study Notes pdfVivekanand Anglo Vedic Academy
 
Palestine last event orientationfvgnh .pptx
Palestine last event orientationfvgnh .pptxPalestine last event orientationfvgnh .pptx
Palestine last event orientationfvgnh .pptxRaedMohamed3
 
Basic phrases for greeting and assisting costumers
Basic phrases for greeting and assisting costumersBasic phrases for greeting and assisting costumers
Basic phrases for greeting and assisting costumersPedroFerreira53928
 
Jose-Rizal-and-Philippine-Nationalism-National-Symbol-2.pptx
Jose-Rizal-and-Philippine-Nationalism-National-Symbol-2.pptxJose-Rizal-and-Philippine-Nationalism-National-Symbol-2.pptx
Jose-Rizal-and-Philippine-Nationalism-National-Symbol-2.pptxricssacare
 
Home assignment II on Spectroscopy 2024 Answers.pdf
Home assignment II on Spectroscopy 2024 Answers.pdfHome assignment II on Spectroscopy 2024 Answers.pdf
Home assignment II on Spectroscopy 2024 Answers.pdfTamralipta Mahavidyalaya
 
Danh sách HSG Bộ môn cấp trường - Cấp THPT.pdf
Danh sách HSG Bộ môn cấp trường - Cấp THPT.pdfDanh sách HSG Bộ môn cấp trường - Cấp THPT.pdf
Danh sách HSG Bộ môn cấp trường - Cấp THPT.pdfQucHHunhnh
 
The geography of Taylor Swift - some ideas
The geography of Taylor Swift - some ideasThe geography of Taylor Swift - some ideas
The geography of Taylor Swift - some ideasGeoBlogs
 
NLC-2024-Orientation-for-RO-SDO (1).pptx
NLC-2024-Orientation-for-RO-SDO (1).pptxNLC-2024-Orientation-for-RO-SDO (1).pptx
NLC-2024-Orientation-for-RO-SDO (1).pptxssuserbdd3e8
 
Students, digital devices and success - Andreas Schleicher - 27 May 2024..pptx
Students, digital devices and success - Andreas Schleicher - 27 May 2024..pptxStudents, digital devices and success - Andreas Schleicher - 27 May 2024..pptx
Students, digital devices and success - Andreas Schleicher - 27 May 2024..pptxEduSkills OECD
 
Phrasal Verbs.XXXXXXXXXXXXXXXXXXXXXXXXXX
Phrasal Verbs.XXXXXXXXXXXXXXXXXXXXXXXXXXPhrasal Verbs.XXXXXXXXXXXXXXXXXXXXXXXXXX
Phrasal Verbs.XXXXXXXXXXXXXXXXXXXXXXXXXXMIRIAMSALINAS13
 
Overview on Edible Vaccine: Pros & Cons with Mechanism
Overview on Edible Vaccine: Pros & Cons with MechanismOverview on Edible Vaccine: Pros & Cons with Mechanism
Overview on Edible Vaccine: Pros & Cons with MechanismDeeptiGupta154
 
1.4 modern child centered education - mahatma gandhi-2.pptx
1.4 modern child centered education - mahatma gandhi-2.pptx1.4 modern child centered education - mahatma gandhi-2.pptx
1.4 modern child centered education - mahatma gandhi-2.pptxJosvitaDsouza2
 
MARUTI SUZUKI- A Successful Joint Venture in India.pptx
MARUTI SUZUKI- A Successful Joint Venture in India.pptxMARUTI SUZUKI- A Successful Joint Venture in India.pptx
MARUTI SUZUKI- A Successful Joint Venture in India.pptxbennyroshan06
 
The Roman Empire A Historical Colossus.pdf
The Roman Empire A Historical Colossus.pdfThe Roman Empire A Historical Colossus.pdf
The Roman Empire A Historical Colossus.pdfkaushalkr1407
 
678020731-Sumas-y-Restas-Para-Colorear.pdf
678020731-Sumas-y-Restas-Para-Colorear.pdf678020731-Sumas-y-Restas-Para-Colorear.pdf
678020731-Sumas-y-Restas-Para-Colorear.pdfCarlosHernanMontoyab2
 

Recently uploaded (20)

Chapter 3 - Islamic Banking Products and Services.pptx
Chapter 3 - Islamic Banking Products and Services.pptxChapter 3 - Islamic Banking Products and Services.pptx
Chapter 3 - Islamic Banking Products and Services.pptx
 
Basic Civil Engineering Notes of Chapter-6, Topic- Ecosystem, Biodiversity G...
Basic Civil Engineering Notes of Chapter-6,  Topic- Ecosystem, Biodiversity G...Basic Civil Engineering Notes of Chapter-6,  Topic- Ecosystem, Biodiversity G...
Basic Civil Engineering Notes of Chapter-6, Topic- Ecosystem, Biodiversity G...
 
Embracing GenAI - A Strategic Imperative
Embracing GenAI - A Strategic ImperativeEmbracing GenAI - A Strategic Imperative
Embracing GenAI - A Strategic Imperative
 
Sectors of the Indian Economy - Class 10 Study Notes pdf
Sectors of the Indian Economy - Class 10 Study Notes pdfSectors of the Indian Economy - Class 10 Study Notes pdf
Sectors of the Indian Economy - Class 10 Study Notes pdf
 
Palestine last event orientationfvgnh .pptx
Palestine last event orientationfvgnh .pptxPalestine last event orientationfvgnh .pptx
Palestine last event orientationfvgnh .pptx
 
Basic phrases for greeting and assisting costumers
Basic phrases for greeting and assisting costumersBasic phrases for greeting and assisting costumers
Basic phrases for greeting and assisting costumers
 
Jose-Rizal-and-Philippine-Nationalism-National-Symbol-2.pptx
Jose-Rizal-and-Philippine-Nationalism-National-Symbol-2.pptxJose-Rizal-and-Philippine-Nationalism-National-Symbol-2.pptx
Jose-Rizal-and-Philippine-Nationalism-National-Symbol-2.pptx
 
NCERT Solutions Power Sharing Class 10 Notes pdf
NCERT Solutions Power Sharing Class 10 Notes pdfNCERT Solutions Power Sharing Class 10 Notes pdf
NCERT Solutions Power Sharing Class 10 Notes pdf
 
Home assignment II on Spectroscopy 2024 Answers.pdf
Home assignment II on Spectroscopy 2024 Answers.pdfHome assignment II on Spectroscopy 2024 Answers.pdf
Home assignment II on Spectroscopy 2024 Answers.pdf
 
Danh sách HSG Bộ môn cấp trường - Cấp THPT.pdf
Danh sách HSG Bộ môn cấp trường - Cấp THPT.pdfDanh sách HSG Bộ môn cấp trường - Cấp THPT.pdf
Danh sách HSG Bộ môn cấp trường - Cấp THPT.pdf
 
The geography of Taylor Swift - some ideas
The geography of Taylor Swift - some ideasThe geography of Taylor Swift - some ideas
The geography of Taylor Swift - some ideas
 
NLC-2024-Orientation-for-RO-SDO (1).pptx
NLC-2024-Orientation-for-RO-SDO (1).pptxNLC-2024-Orientation-for-RO-SDO (1).pptx
NLC-2024-Orientation-for-RO-SDO (1).pptx
 
Students, digital devices and success - Andreas Schleicher - 27 May 2024..pptx
Students, digital devices and success - Andreas Schleicher - 27 May 2024..pptxStudents, digital devices and success - Andreas Schleicher - 27 May 2024..pptx
Students, digital devices and success - Andreas Schleicher - 27 May 2024..pptx
 
Introduction to Quality Improvement Essentials
Introduction to Quality Improvement EssentialsIntroduction to Quality Improvement Essentials
Introduction to Quality Improvement Essentials
 
Phrasal Verbs.XXXXXXXXXXXXXXXXXXXXXXXXXX
Phrasal Verbs.XXXXXXXXXXXXXXXXXXXXXXXXXXPhrasal Verbs.XXXXXXXXXXXXXXXXXXXXXXXXXX
Phrasal Verbs.XXXXXXXXXXXXXXXXXXXXXXXXXX
 
Overview on Edible Vaccine: Pros & Cons with Mechanism
Overview on Edible Vaccine: Pros & Cons with MechanismOverview on Edible Vaccine: Pros & Cons with Mechanism
Overview on Edible Vaccine: Pros & Cons with Mechanism
 
1.4 modern child centered education - mahatma gandhi-2.pptx
1.4 modern child centered education - mahatma gandhi-2.pptx1.4 modern child centered education - mahatma gandhi-2.pptx
1.4 modern child centered education - mahatma gandhi-2.pptx
 
MARUTI SUZUKI- A Successful Joint Venture in India.pptx
MARUTI SUZUKI- A Successful Joint Venture in India.pptxMARUTI SUZUKI- A Successful Joint Venture in India.pptx
MARUTI SUZUKI- A Successful Joint Venture in India.pptx
 
The Roman Empire A Historical Colossus.pdf
The Roman Empire A Historical Colossus.pdfThe Roman Empire A Historical Colossus.pdf
The Roman Empire A Historical Colossus.pdf
 
678020731-Sumas-y-Restas-Para-Colorear.pdf
678020731-Sumas-y-Restas-Para-Colorear.pdf678020731-Sumas-y-Restas-Para-Colorear.pdf
678020731-Sumas-y-Restas-Para-Colorear.pdf
 

Civil Engineering Internship Presentation-Anis Rahman Khokan

  • 1. Study on the Construction Process of Superstructure of a Seven Storied Residential Building Presented By- Md. Mahfuzur Rahman Jony Md. Khokan Mia Id# 14106020 Id# 14106028 Program: BSCE Program: BSCE IUBAT – International University of Business Agriculture and Technology 1 4/1/2018
  • 2. CONTENTS  Introduction  Objectives  Company overview  Company organogram and our project details  Design specification  Construction materials & equipment's  Construction process of beam, slab, stair & column  Problems & solution  Recommendation  Conclusion 2 4/1/2018
  • 3. INTRODUCTION  In this presentation we will try to present our 4 month’s practicum experience of the construction work of a seven storied residential building.  We observed the construction process of super structural parts of a reinforced concrete building.  Here we have focused on mainly column, stair, beam and slab construction process. 3 4/1/2018
  • 4. OBJECTIVES  To get knowledge about the structural drawing & design specification.  To implement the structural drawing into construction site.  To understand the construction and supervision work of column, stair, beam and slab.  To learn about the estimating details of Super Structural work.  To acquire knowledge about the steps involving construction process.  To learn how to solve the rising problems and unexpected events. 4 4/1/2018
  • 5. Company Overview Company Name: Tokyo Development Engineer’s Ltd. Office Address: House- 26, Road- 09, Sector-13, Uttara, Dhaka- 1230 Phone: 02-550 89047, 550 88865 E-mail: tokyobd@yahoo.com Web: www.tokyobd.com 5 4/1/2018
  • 7. About Our Project Our project name: Tokyo Karim’s Garden Address: House #742, Road #23,Block-F, Bashundhara Residential Area. Property Details: Unit Size: 1650 sft. (Bedroom-3, Formal living, Family living, Dining, Bathroom-3) Building Facing: North facing Building Storied: (GF+6) = 7 (Seven) Storied Residential Building. Structural Designer: Kawser Talukder B.Sc. Engg. (BUET) FIEB,RAJUK ENLISTED Fig: 3D View of Tokyo Karim’s Garden 7 4/1/2018
  • 10. General:  Design method followed is USD according to BNBC, 2006 and ACI Code 2008. Concrete:  f’c = 3500 psi for columns, Cap  f’c (specific strength) = Minimum 20 Mpa (3000 psi) for all other members.  Minimum cement concrete ratio 1:1.5:3 for column and cap.  Minimum cement concrete ratio 1:2:4 for other members. Concrete Aggregate:  Fine aggregate: Local Sand of FM 1.2 & Sylhet Sand of FM 2.0 (minimum)  Coarse Aggregate: 20 mm down well graded stone chips shall be used as coarse aggregate in column, Shear Wall and Cap and Brick Chips in other members. Steel Reinforcement:  Reinforcement are 72 grade deformed bar having minimum fy = 500 Mpa (72,000 psi) Water:  Portable water to be used in concrete mix Design Specification10 4/1/2018
  • 11. Design Specification (Continued) Lap Length: Bar type Bar Positi on Bar Size 10 12 16 20 25 Tensio n Top 450 600 750 900 1625 Botto m 400 475 650 800 1250 Compression 300 350 475 600 750 11 Clear Cover: Member Location of Condition Clear Cover Column Above ground Level 1.5” (40 mm) Beam Top Side & Bottom 1.5” (40 mm) Slab & Stair Top and Bottom 1” (25 mm) 4/1/2018
  • 12. Construction Materials Materials: Cement Fine Aggregate Fig: Seven Rings Special Cement Fig: Local Sand Fig: Sylhet Sand FM Practical Design Specification Sylhet 3.0 2.0 12 4/1/2018
  • 13. Construction Materials (Cont.) Fig: Brick Chips Fig: Stone Chips Fig: Reinforcement bar Materials:  BSI Rod (72 Grade)  20 mm down graded Stone-Column  20 mm down brick Chips- slab, stair 13 4/1/2018
  • 14. Main Equipment's Fig: Mixer Machine Fig: Bar CutterFig: Vibrator Fig: Crane 14 4/1/2018
  • 15. Field Test of Cement Fig: Checking Hard Lumps Fig: Checking Temperature Fig: Checking Manufacturing Date Name of the Test Practical Standard Adulteration Test No hard Lumps No hard Lumps Temperature Test Cool Cool Manufacturing Date It should used within 90 days It was used within 90 days 15 Table: comparison between practical and standard 4/1/2018
  • 16. Field Test of Aggregate Fig: Colour Check Fig: Earthy Substance Check Fig: Salt Test Name of Test practical Standard Salt Test No salty Taste No salty Taste Silt Test No Earthy Sub. No Earthy Sub. Color check Golden Yellow Golden Yellow 16 4/1/2018
  • 17. Angular size Test: Field Test of Aggregate(continued) Large size ¾ inch 60%, Medium size ½ inches 30% Small size ¼ inch 10% Fig: Checking Angular Size 17 4/1/2018
  • 18. Field Test of Bricks Fig: Tee Test Fig: Hardness Test Fig: Soundness Test Name of Test Practical Standard Hardness Test No Mark on Surface No Mark on Surface Soundness Test Metallic Sound Metallic Sound Tee Test Broken Remain Unbroken 18 4/1/2018
  • 19. Field Test of Bricks (continued) Fig: Checking Brick Size Practical Standard 9.5”x4.5”x2.75” 9.5”x4.5”x2.75” 19 4/1/2018
  • 20. SL Sieve Size (mm) Retain(gm) Retained Weight Percentage Cumulative (%) 1 4.75 7 0.70 0.70 2 2.36 17 1.71 2.41 3 1.18 89 8.93 11.34 4 0.600 750 75.23 86.57 5 0.300 130 13.03 99.60 6 0.150 4 0.40 100 7 pan 0 0.00 100 Lab Test Practical FM Design Specification FM 3.00 2.0 Fineness Modulus (FM) = Summation of cumulative (%) 100 = (0.70 + 2.41 + 11.34 + 86.57 + 99.60 + 100) 100 =3.006 = 3.00 20 Lab Test of Fine Aggregate: Fig: Sieve Analysis of Fine Aggregate 4/1/2018
  • 21. Lab Test (continued) SL Sieve Size (mm) Retain(gm) Retained Weight Percentage Cumulative (%) 1 25 720 36.04 36.04 2 19 813 40.69 76.73 3 12.5 450 22.52 99.25 4 10 7 0.35 99.60 5 4.75 0.00 0.00 99.60 6 pan 8 0.40 100 Practical FM Design Specification FM 5.00 6.0-6.9 Fineness Modulus (FM) = Summation of cumulative (%) 100 = (36.04 + 76.73 + 99.25 + 99.60 + 99.60 + 100) 100 = 5.12 = 5.00 21 Lab Test of Coarse Aggregate: Fig: Sieve Analysis of Coarse Aggregate 4/1/2018
  • 22.  Concrete Mixing Ratio is 1:1.5:3  Load = 171.44 KN Cylinder Test Name of Test Practical Design Specification Concrete compressive strength 3165 psi for 21 days 3150 psi for 21 days 22 4/1/2018
  • 23. Formwork Materials Fig: Plain sheets Fig: Wooden frame Fig: Steel Shutter Fig: Bamboo Props 23 4/1/2018
  • 24. We have observed the following construction process:  Construction of column.  Construction of stair.  Construction of beam.  Construction of slab. Construction Process24 4/1/2018
  • 26.  Total 14 Columns  Five Types of Column(C-1 to C-5) & We observed C-2 Type Construction of Column26 Column Layout plan: 4/1/2018
  • 27.  We observed the entire columns but as we are going to explained C-2 type column. The column size is 12”X18”. 6-20mm & 4-16mm bar are used is this column in 3th Floor. Construction of Column27 Column Schedule: 4/1/2018
  • 28. The following works are followed at the time of column construction:  Kicker making.  Reinforcement bar placing.  Shuttering.  Casting.  Curing. Construction of Column28 4/1/2018
  • 29. Construction of Column29 Fig: Kicker Making and Checking Kicker Making: 4/1/2018
  • 30. Construction of Column Fig: Column Ties Fig: Placing tie on Column Fig: Tie Binding 30 Reinforcement Bar Placing: 4/1/2018
  • 31.  10mm@ 4”c/c spacing is at the end section for tie binding.  10mm@ 8”c/c spacing at the mid section for tie binding.  25” Provide as lapping length for 16 mm bar Construction of Column Fig: 4” c/c Spacing Fig: 8” c/c SpacingFig: Checking Lapping Length 31 Checking Bar Arrangement: 4/1/2018
  • 32.  Main Bar: 6-20Ø & 4-16Ø bar Used.  Tie Bar: 19-10Ø bar Used Construction of Column Fig: Column Main Bar & Tie Spacing Fig: Cross Section(C-2) 32 Details of Column (C-2): 4/1/2018
  • 33. Construction of Column Fig: Cleaning Shutter Fig: Fixing Shutter Fig: Completed Shuttering Fig: Checking Vertical Alignment at bottom, mid and top section 33 Column Shuttering & Checking: 4/1/2018
  • 34.  Mixing by Mixer Machine  Mixing Ratio- 1: 1.5 : 3  Using Vibrator  Cement Grout Spread  cement, Sylhet Sand & Stone  Water-Cement Ratio: 0.40  4′-4″ column casted Construction of Column Fig: Column Casting Fig: Using Vibrator 34 Column Casting: 4/1/2018
  • 35.  Remove the nuts by the screw  Then De-Shutter the Column  Curing by Hose Pipe Fig: Column De-Shuttering Fig: Column Curing 35 4/1/2018 Construction of Column Curing of Column
  • 36.  Number of Column: 1 NO  Height of the column: 8.25 ft.  Column Dimension: 1.0×1.5 ft. Or (12”X18”)  Total Volume: (1×1.5×8.25) = 12.40 cu. ft.  Dry Volume: 12.40 ×1.5 =18.56 cu. ft.  Mixing Ratio = 1:1.5:3  Water/Cement ratio = 0.4 Concrete Calculation:  Cement= (Dry Volume x Cement ratio)/Summations of ratio  Sand = (Dry Volume x Sand ratio)/Summations of ratio  Stone = (Dry Volume x Stone ratio)/Summations of ratio  So, Cement = 3.0 bags  Sand = 5.0 cu. ft.  Stone = 11 cu. ft. Reinforcement Calculation:  20mm & 16mm bar = 1× ((6×10×.75) + (4×10×.48)) = 64.2 kg.  10mm bar = 1×19×7×.19 = 25.27 kg. 36 Sample Estimation for C-2 Cement Sand Stone 3.0 bags 5.0 cu. ft. 11 cu. ft. Main Bar Tie Bar 64.2 kg 25.27 kg 4/1/2018
  • 37. 37 Concrete Details of All Column Column Name No. of Column Size of Column Cement Sand Stone C-1 2 12”X15” 3.0 bags 5.0 cu. ft 11 cu. ft. C-2 1 12”X18” 13 bags 23 cu. ft 46 cu. ft. C-3 6 12”X20” 18 bags 34.0 cu. ft. 68 cu. ft. C-4 4 12”X20” 3.0 bags 5.0 cu. ft 11 cu. ft. C-5 1 12”X18” 5.0 bags 9.0 cu. ft. 17 cu. ft.
  • 38. 4/1/2018 38 0 20 40 60 80 100 120 140 160 180 Cement (kg) Sand (cu. ft.) Stone (cu. ft.) Estimated Actual Materials Estimated Actual Cement 42 bags 41 bags Sand 76 cu. ft. 78 cu. ft Stone 153 cu. ft. 154 cu. ft. Concrete Details of All Column Comparison between Estimated vs Actual Materials:
  • 39. 39 Reinforcement Details of All Column Column Name No. of Column Tie Bar Size of Column Reinforcemen t of Column Main bar Weight Tie bar Weight C-1 2 19-10 Ø 12”X15” 4-20mm+ 4-16mm 99 kg 38 kg C-2 1 19-10 Ø 12”X18” 6-20mm+ 4-16mm 64 kg 26 kg C-3 6 19-10 Ø 12”X20” 6-25mm+ 6-20mm 443 kg 159 kg C-4 4 19-10 Ø 12”X20” 6-25mm+ 6-20mm 461 kg 159 kg C-5 1 19-10 Ø 12”X18” 10-20mm 90 kg 26 kg
  • 40. 40 0 50 100 150 200 250 300 350 400 450 500 C-1 C-2 C-3 C-4 C-5 Estimated Main bar (kg) Used Main Bar (kg) Reinforcement Details of All Column Column Name Estimated Main bar (kg) Used Main Bar C-1 99 101 C-2 64 65 C-3 443 450 C-4 461 467 C-5 90 92 Comparison between Estimated vs Actual Reinforcements:
  • 41. Working Schedule of Column 22-Sep 27-Sep 2-Oct 7-Oct 12-Oct 17-Oct Reinforcement Placement of Column Tie Binding Column Shuttering Column Casting Column Curing Duration 41 4/1/2018
  • 43. The following works are followed at the time of stair construction:  Shuttering of stair.  Reinforcement bar placing.  Shuttering of treads and risers.  Casting of stair.  Curing of stair. Construction of Stair43 4/1/2018
  • 44.  Stair total length 14.5′ & width 8′  Stair has Two Flight  Each Flight has 8 Steps  Each step height 6″ & wide 10″ 44 4/1/2018 Construction of Stair Stair Plan:
  • 45.  First timber planks fixed.  Runner attached with timber planks.  Bamboo props Support the Runner. Fig: Stair Shuttering and using Jute Fabric 4/1/2018 45 Construction of Stair Shuttering of Stair:
  • 46.  Main Bar: 12mm@ 6” c/c  Binder Bar: 10mm@ 6” c/c  Extra Top bar length L/4  12mm@ 6” c/c in Landing & 2-16mm bar in Landing 46 4/1/2018 Construction of Stair Reinforcement Details:
  • 47. 47 Construction of Stair Fig: Reinforcement bar placing Reinforcement Bar placing & Checking: Fig: Checking
  • 48. Fig: Making Riser & Tread Fig: Checking Tread Fig: Checking Riser 48 4/1/2018 Construction of Stair Making & Checking Riser &Tread:
  • 49. Fig: Pouring water Fig: Casting of Stair Fig: Using VibratorFig: Complete Casted Stair Fig: using Trowel 49 4/1/2018 Construction of Stair Casting of Stair:
  • 50. Fig: Curing of Stair  Curing Start at Next day  Spreading Water by hose pipe  2-3 times on a day 50 4/1/2018 Construction of Stair Curing of Stair:
  • 51. 4/1/2018 51 Estimation of Stair Landing = (8’×4’+8’×3.5’) ×6” = 30 cft Waist slab = (9’×3’7”×6”×2) =32.2 cft Step = (1/2×10”×6”×3’7”×17) =12.7 cft Total volume = (30+32.3+12.7) =75 cft Dry volume = 75×1.5 =112.5 cft Mixing ratio = 1:2:4 Summation of ratio =1+2+4 =7 Cement = (112.5X1)/7 = 16.1 X 0.8 = 13 bags Sand = (112.5X2)/7 = 32.14 cft Brick chips = (112.5X4)/7 = 64.3 cft Concrete calculation: Cement Sand Brick chips 13 bags 33 cft 65 cft 0 10 20 30 40 50 60 70 80 Cement Sand Brick chips Estimaed Actual
  • 52. 4/1/2018 52 Estimation of Stair Reinforcement calculation: Cement Sand Brick chips 13 bags 33 cft 65 cft 0 10 20 30 40 50 60 70 80 Cement Sand Brick chips Estimaed Actual Main bar length = 4+3.5+9 = 16.5 ft. Number of bar = 8 and 12mm@6”. So, weight of main bar = 0.27×8×16.5 = 35.64 kg×2 = 71.28 kg Binder bar length = 3.83 ft. Number of binder = 33 and 10mm@6”. So, weight of binder bar = 0.19×18×3.83 = 13.10 kg×2 = 26.2 kg Extra top length = 7 ft. Number of bar = 8 and 12mm@6”. So, weight of top bar = 0.27×7×8 = 15.12 kg×2 = 30.24 kg Extra top length = 6.5 ft. Number of bar = 8 and 12mm@6”. So, weight of top bar length = 0.27×6.5×8 = 14.04 kg×2 = 28.08 kg Binder bar length = 3.83 ft. Number of binder = 6 and 10mm@6” So, weight of binder bar = 0.19×3.83×6 = 4.37 kg×4 = 17.48 kg
  • 53. Working Schedule of Stair 5-Oct 10-Oct 15-Oct 20-Oct 25-Oct 30-Oct 4-Nov Shuttering of Stair Reinforcement Placement on Stiar Tread and Riser Making Casting of Stair Curing of Stair Duration 53 4/1/2018
  • 55. Construction of Beam & Slab The following works are followed at the time of beam & slab construction:  Shuttering  Reinforcement bar placing  Casting  Curing 55 4/1/2018
  • 56. Fig: Bottom shutter of Beam Fig: All side shutter of Beam 4/1/2018 56  First timber planks fixed.  Runner attached with timber planks.  Bamboo props Support the Runner. Shuttering of Beam: Construction of Beam & Slab
  • 57. Fig: Runner placing on Slab Fig: Wooden plank placing on Slab Fig: Runner supported by bamboo Props Fig: Steel Sheet Placing on Slab 4/1/2018 57 Construction of Beam & Slab Shuttering of Slab:
  • 58. 4/1/2018 58 Compariso n Required Used Bamboo Props 241 233 Wooden Runner 51 50 Steel Sheet 54 57 0 50 100 150 200 250 300 Bamboo Props Wooden Runner Steel Sheet Required Used Construction of Beam & Slab Calculation Shuttering Materials of Beam & Slab:
  • 59. Construction of Beam & Slab 4/1/2018 59 Beam Layout Plan:  Total 14 Beams.  Classify (FB-1 to FB-14)  Here I am going to explain FB-1
  • 60. Fig: Reinforcement details of beam (FB- 1) 4/1/2018 60 Construction of Beam & Slab Reinforcement Details of Beam:  Top Bar: 2-20 mm  Ext Top Bar: 1- 20mm  Bottom Bar: 2-16mm  Ext Bottom Bar:1-16mm  Stirrup: 63-10 mm
  • 61. Fig: Keep the Stirrup on Marked Place Fig: Placement of Stirrup Fig: Fixing Bottom & Top bar Fig: Stirrup Binding 4/1/2018 61 Construction of Beam & Slab Reinforcement Bar Placing:
  • 62. Fig: Extra top & bottom bar placement 4/1/2018 62 Construction of Beam & Slab Reinforcement Bar Placing:
  • 63. Fig: Checking stirrup spacing at end section Fig: Checking stirrup spacing at mid section Fig: Checking clear cover of beam 4/1/2018 63 Checking Reinforcement Bar Arrangement: Construction of Beam & Slab
  • 64. 4/1/2018 64 Concrete Calculation: Beam size = 10″ x 21″ L= 38.42 ft Volume = .83 x 1.75 × 38.42 = 55.81 cft Dry volume = 1.5 × 55.81 = 83.72 cft Ratio = 1:2:4 Cement = (83.72 × 1) / 7 = 11.96 x .8= 14.96 bags Sand = (83.72 × 2)/ 7 = 23.92 cft Brick chips = (83.72 ×4) /7 = 47.48 cft Reinforcement Calculation: Total length for straight bar = L + 2×hook+ lapping = 38.42+2× (6/12) = 39.42 ft Main Bar: 2-20mm& 2-16mm =2×.75 ×39.42+2×.48×39.42 = 96.97 kg. Extra Top bar length: 33.08 ft. Extra Bottom length: 8.00 ft. Extra Bar: 1-20mm & 1-16mm = 1×33.08×.75 + 1×8.00×.48 = 28.65 kg. Tie bar Length: 5.17 ft. Total Number of Tie: 63 NOS Tie bar: 10mm = 63×5.17×.19 = 61.88 kg.
  • 65. 4/1/2018 65 Name of Beam Main Bar Weight Extra Bar Weight Tie Bar Weight FB-1 (12”x20”) 96.97 kg. 28.65 kg. 61.88 kg. FB-2(10”X20”) 35.7 kg 00 kg 16.15 kg FB-3(10”X21”) 94.91 kg 19.29 kg 32.42 kg FB-4(10”X10”) 27 kg 6 kg 10.6 kg FB-5(10”X10”) 31.26 kg 16.11 kg 17.76 kg FB-6(10”X10”) 19.5 kg 00 kg 10.75 kg FB-7(10”X21”) 49.29 kg 16.53 kg 41.26 kg FB-8(10”X15”) 48.24 kg 11.38 kg 30.11 kg FB-9(7”X15”) 46.5 kg 00 kg 21.62 kg FB-10(10”X20”)(7”X20”) 96.75 kg 36.64 kg 51.87 kg FB-11(10”X12”) 35.49 kg 16.25 kg 15.33 kg FB-12(10”X20”) 96.75 kg 29.25 kg 79.8 kg FB-13(10”X20”) 62.01 kg 14.75 kg 30.4 kg FB-14(10”X15”) 40.26 kg 9.32 kg 20.58 kg
  • 66. 4/1/2018 66 Name Cement Sand Bricks Chips FB-2(10”X20”) 2.60 bags 6.50 cft 12.98 cft. FB-3(10”X21”) 3.44 bags 8.61 cft 17.23 cft FB-4(10”X10”) 0.95 bags 2.36 cft 4.73 cft FB-5(10”X10”) 1.34 bags 3.35 cft 6.70 cft FB-6(10”X10”) .65 bags 1.62 cft 3.25 cft FB-7(10”X21”) 6.14 bags 15.36 cft 30.71 cft FB-8(10”X15”) 2.68 bags 6.71 cft 13.41 cft FB-9(7”X15”) 1.80 bags 4.51 cft 9.01 cft FB-10(10”X20”)(7”X20”) 6.39 bags 15.97 cft 31.94 cft FB-11(10”X12”) 1.54 bags 3.85 cft 7.714 cft FB-12(10”X20”) 7.41 bags 18.53 cft 37.05 cft FB-13(10”X20”) 4.67 bags 11.68 cft 23.37 cft FB-14(10”X15”) 2.21 bags 5.52 cft 11.05 cft
  • 67. 4/1/2018 67 Beam Used Stirrups Required Stirrups FB-1 56 53 FB-2 17 16 FB-3 33 33 BF-4 22 22 FB-5 35 38 FB-6 20 22 FB-7 42 38 Fb-8 38 40 Fb-9 31 33 Fb-10 67 64 Fb-11 22 23 Fb-12 84 80 Fb-13 32 32 Fb-14 26 26 0 10 20 30 40 50 60 70 80 90 Used Stirrups Required Stirrups
  • 68. Fig: Bottom slab reinforcement 4/1/2018 68 Construction of Beam & Slab Reinforcement Details of Bottom Slab:  Main Bar: 10 mm  Binder: 10 mm
  • 69. Fig: Checking cc distance reinforcement of slab Fig: Checking lapping length of bottom slab reinforcement Fig: Checking 1ʺclear cover on bottom slab reinforcement Fig: Bottom slab reinforcement placement Fig: After placing bottom slab reinforcement 4/1/2018 69 Construction of Beam & Slab Reinforcement placing on Bottom Slab & Checking:
  • 70. Fig: Top slab reinforcement 4/1/2018 70 Construction of Beam & Slab Reinforcement Details of Top Slab :  Main Bar: 10mm & 12 mm  Binder: 10 mm
  • 71. Fig: Concrete block for maintain clear coverFig: Top slab reinforcement placement 4/1/2018 71 Construction of Beam & Slab Reinforcement Bar Placing on Top Slab :
  • 72. Fig: Checking 3ʺclear cover on top slab reinforcement Fig: Checking extra top bar length Fig: Checking top bar spacing4/1/2018 72 Construction of Beam & Slab Checking Top Slab Reinforcement Bar Placement:
  • 73. Fig: Concrete mixing in mixer machine Fig: Using crane for pulling up the concrete Fig: Concrete place on Slab Fig: Casting the beam 4/1/2018 73 Construction of Beam & Slab Casting of Beam & Slab:
  • 74. Fig: Using vibrator for compaction Fig: Using steel runner for leveling Fig: Placement of U-bar Fig: checking depth of slab 4/1/2018 74 Construction of Beam & Slab Casting of Beam & Slab:
  • 75. 4/1/2018 75 Construction of Beam & Slab Casting of Beam & Slab:
  • 76. Fig: Making Pond for Curing Fig: Curing the Slab 4/1/2018 76 Construction of Beam & Slab Curing of Beam & Slab:
  • 77. 4/1/2018 77 pan Cement Sand Bricks Span-1 4.06 bags 10.16 cft 20.32 cft Span-2 9.66 bags 24.15 cft 48.30 cft Span-3 4.85 bags 12.12 cft 24.24 cft Span-4 3.93 bags 9.83 cft 19.67 cft Span-5 13 bags 33 cft. 67 cft. Span-6 15.50 bags 38.72 cft 77.45 cft Span-7 6.64 bags 16.61 cft 33.22 cft
  • 78. 4/1/2018 78 Span Bottom bar Weight Top bar Weight Span-1 42 kg 40 kg Span-2 87 kg 84 kg Span-3 83 kg 53 kg Span-4 64 kg 48 kg Span-5 219 kg 104 kg Span-6 175 kg 101 kg Span-7 80 kg 55 kg
  • 79. Working Schedule of Beam & Slab 8-Oct 18-Oct 28-Oct 7-Nov 17-Nov 27-Nov 7-Dec Shuttering of Beam Shuttering of Slab Thin Sheet Placement & Leveling Reinforcement Placement on Beam Reinforcement Placement on Slab Shuttering of Stair Casting of Beam,Stair & Slab Curing of Slab Duration 4/1/2018 79
  • 80.  Total length for straight bar = L + 2×hook+ lapping = 38.42+2× (6/12) = 39.42 ft  Main Bar: 2-20mm& 2-16mm = 2×.75 ×39.42+2×.48×39.42 = 96.97 kg.  Extra Top bar length: 33.08 ft.  Extra Bottom length: 8.00 ft.  Extra Bar: 1-20mm & 1-16mm = 1×33.08×.75 + 1×8.00×.48 = 28.65 kg.  Tie bar Length: 5.17 ft.  Total Number of Tie: 63 NOS  Tie bar: 10mm = 63×5.17×.19 = 61.88 kg.  Beam size = 10″ x 21″ , L= 38.42 ft Volume = .83 x 1.75 × 38.42 = 55.81 cft  Dry volume = 1.5 × 55.81 = 83.72 cft  Ratio = 1:2:4  Cement = (83.72 × 1) / 7 = 11.96 x .8 = 14.96 bags  Sand = (83.72 × 2)/ 7 = 23.92 cft  Brick chips = (83.72 ×4) /7 = 47.48 cft 80 Sample Estimation of FB-1 4/1/2018
  • 81.  Problem-1: During the column casting, liquid of concrete mix came out from the form of column due to leakage in formwork or improper shuttering of column.  Solution: We alert the labor about the leakage on the column Shutter and said to used jute tap properly which can protect the leakage on shutter. Problem and Solution Fig: Leakage of formwork 4/1/2018 81
  • 82.  Problem-2: Column C-3, after removing the shuttering there are honeycomb on the column which can occur due to improper vibration. Problem and Solution (Continued) Fig: Honeycomb in column 4/1/2018 82 Solution: We suggest the labor to fill the honeycomb by cement paste. Then they filled the place by cement paste and make plain by rubbing the jute tap. Fig: Using cement paste in honeycomb
  • 83.  Problem-3: In beam FB-2, Stirrup spacing is changed and being some transverse during the placement of beam. Problem and Solution (Continued) Fig: Changed spacing in stirrup Solution: We inform the labor about it and then they rebind the ties maintaining the correct spacing. 4/1/2018 83
  • 84.  Problem-4: Safety should be the first condition in construction work. Wearing helmet and pant is safer than lungi and free head. Problem and Solution (Continued) Solution: We talk with them and make aware about the safety but they don‘t take any measure. Most of the time, they work unsafely. When we said about the safety, they replied that they would be habituated in this condition. Fig: Working without safety 4/1/2018 84
  • 85. During our practicum period we are face some problems and our recommendation are:  There are no working schedule in the construction site. Company should have work schedule for every project . Maintain work schedule properly can save cost.  The management should aware of the safety. A little training and care can prevent accidents in the project.  Company should need to do some test like slump test, cylinder test etc. Some test like this can ensure the strength able construction. Recommendation 4/1/2018 85
  • 86. We have supervised beam, slab, stair & column construction work. After supervising our construction site, We have learned about beam, slab, stair & column construction and achieved practical experience. We have also learned construction management. It was an awesome experience dealing with different types of people at construction site. It seems to me that the practical knowledge is the most essential to be an efficient engineer. I tried to give my full afford as trainee engineers. Overall the internship program laid sound foundation for us to start our career. Conclusions 4/1/2018 86