Ms. Harsha Talodhikar Int. Journal of Engineering Research and Applications www.ijera.com
ISSN : 2248-9622, Vol. 5, Issue 3, ( Part -1) March 2015, pp.09-12
www.ijera.com 9 | P a g e
Implementation of Line of Balance Method for Scheduling High-
rise Building
Ms. Harsha Talodhikar*, Prof. Mrs. Smita V. Pataskar**
*(Department of Civil Engineering, Savitribai Phule Pune University, Pune, Maharashtra, India.)
** *(Department of Civil Engineering, Savitribai Phule Pune University, Pune, Maharashtra, India.)
ABSTRACT
In linear construction projects like high rise buildings, roadways, pipelines where activities are repeated after a
specific interval, it is very much important for project manager to monitor the project at each stage. Line of
Balance method is therefore useful for the project like high rise building to monitor the progress of the work.
This method is useful for calculating the total duration of the project, crew synchronization and also shows the
process, status, timing and phasing of the project activities. The overall objective of this study is to identify the
total duration required by the project for its completion and its comparison with the actual plan by using Line of
Balance method, to crash some of the activities and find out the total duration of crashed activities and to
calculate labours required for the crashed activities by drawing the graph of Histogram.Keywords- crashing,
crew synchronization, buffer, Histogram, Rate of Production
I. INTRODUCTION
A. BACKGROUND
The Line of Balance Scheduling Technique was
originated by the Goodyear Company in the early
1940’s and was developed by the U. S. Navy in the
early 1950’s for the programming and control of both
repetitive and non-repetitive projects. The
construction of projects of repetitive units can be
considered as the continuous manufacturing of many
units requiring a certain period of time for each unit
to be completed. It can be used in projects involving
activities of repetitive nature such as housing
projects, high rise buildings, long bridges, highway
construction, and pipelines (Lumsden, 1968). The
LOB was first applied to industrial manufacturing
and production control, where the objective was to
evaluate a production line flow rate of finished
products. The line of balance method is based on
underlying assumption that the rate of production for
an activity is uniform. The basic concepts of LOB
have been applied in the construction industry as a
planning and scheduling method in Finland in the
1980s (Harris and McCaffer, 1989).
The LOB chart provides an overview of the
project’s overall status by quantitatively representing
the cumulative completion of activities at a given
point of time. It graphically reveals any imbalance
that suggests a deviation in the progress of activities
which enables the management to focus on assessing
the deviation quantitatively (Khisty 1970).
B. AIMS AND OBJECTIVES OF STUDY
The main purpose of applying Line of Balance
method to high rise building is to:
 Draw the graph of repetitive activities, as
applying LOB facilitates the continuous
monitoring of the project, at each stage.
 Calculate rate of production of work.
 Compare the cost of actual and delay project.
 Draw the graph of activities after crashing, and
to know the rate of flow of the activities.
 Evaluate size of crew required for the crashed
activities.
C. LIMITATIONS
The study is limited to the following respects
 Inability to generate a clear critical path of the
project schedule, relative to the one provided by
CPM schedules.
 In CPM scheduling the user could divide project
by location and other systems like trades, in
LOB only location.
 Productivity rates in LOB schedule do not
include the effect of crews “learning curve, or if
the individuals working in the crews changed”.
II. LITERATURE REVIEW
i. PRACTICAL LIMITATIONS OF LINE OF
BALANCE IN SCHEDULING REPETITIVE
CONSTRUCTION UNITS
In this paper the author has explained, about
practical limitations, and constraints while using Line
of Balance method and also have studied different
factors to be considered while drawing as well as
using LOB.
Logical sequence: Scheduling construction
projects with repeating activities are performed based
on a combination of network technology and the
basic concept of LOB. The precedence relationships
RESEARCH ARTICLE OPEN ACCESS
Ms. Harsha Talodhikar Int. Journal of Engineering Research and Applications www.ijera.com
ISSN : 2248-9622, Vol. 5, Issue 3, ( Part -1) March 2015, pp.09-12
www.ijera.com 10 | P a g e
define the logical sequence between successive
construction activities. All types of logical
precedence relationships between succeeding
activities (start-to-start; start-to-finish; finish-to-finish
and finish-to-start) can be represented in the unit
network.
Crew work continuity: The application of such
work continuity during scheduling of repetitive
construction leads to the following managerial
function: (i) maximize the benefits from the learning
curve effect for each crew. These results have
considerable savings in time and cost. (ii) Minimize
the idle waiting intervals of equipment and labour.
(iii) Minimize extra effort associated with work
interruptions such as- setup time, temporary storage
of tools and materials.(iv) Minimise the off-on
movement of crews on a project once work has
begun.
Number of employed crews: The crew
availability constraint depends on the available
number of crews that can be assigned to activity in all
repetitive units of the construction project. Making
the schedule resource oriented, maximum efficiency
can be adopted.
Work crew size: A crew of optimum size is
defined as a combination of trade workers, materials,
and equipment that usually guarantees maximum
productivity in an activity. This crew is expected to
carry out the related activity in the most cost efficient
way.
Project resources: The distribution of resources
during the project process is one of particular
importance for construction managers. Not only do
managers have to make sure that the resources they
allocate to the activities do not exceed availabilities.
They would also want to see as smooth a distribution
as possible to avoid the disruption of hiring and firing
crews during the project progress.
Workflow direction: Upward direction: Most
work is scheduled in upward direction to follow the
construction of skeleton.
Downward direction: Some other construction
activities, how-ever, are scheduled in a downward
direction for reasons (i.e., safety or to prevent
damage of the installed work). The final finishing of
external cladding, clearing, and cleaning could be the
typical examples of such activities.
Author concluded that several issues associated
with LOB application have been identifies in this
research. The research determines the practical
limitations of LOB in scheduling repetitive
construction units.
ii. LOB AND CPM INTEGRATED METHOD
FOR SCHEDULING REPETITIVE PROJECTS
It is said that repetitive projects require schedules
that ensure the uninterrupted usage of resources from
a unit to similar units in a repetitive activity while
maintaining logical dependency constraintsand the
critical path method(CPM) is the most widely used
and accepted planning and scheduling method for
non-repetitive projects, but does not suit the planning
and scheduling method for repetitive projects. On the
other hand, Line of Balance(LOB) has been used in
scheduling repetitive activities, which is a resource
driven technique.
Author made few attempts to combine the
benefits of CPM and LOB technique in planning and
scheduling of repetitive projects. He developed an
integrated CPM and LOB model to schedule
repetitive projects in an easy non-graphical manner,
considering both resource continuity constraints and
logic dependencies. The activities which overlaps of
a single typical unit are used to model duration and
logical relationships of repetitive activities.
He proposed a model which consists of four
steps:
(i) LOB calculations: The objective of LOB
formulation is to achieve a resource- balanced
schedule by determining the number of crews to
be employed in each repetitive activity. This is
conducted such that the units are delivered with a
rate that meets a pre-specified project deadline
and crew’s work continuity is maintained.
(ii) Calculating activity duration: Overlapping
activities are generalized to represent repetitive
activities. For this, the duration is assumed
constant in all units of a repetitive activity.
(iii) Specifying logical relationships using
Overlapping activities: The logical dependency
relationship among different activities can be
specified according to the selected rate of
progress of each activity. It significantly
maintains the work continuity.
(iv) Time scheduling: After LOB calculations and the
relationship type among the consecutive
activities specified with their associated lags,
time analysis similar to that of CPM can be
performed.
The Author further concluded that scheduling of
repetitive projects represents a challenge for
construction planners and managers. Classical CPM
analysis does not suit characteristics of repetitive
projects, whereas LOB lacks the analytical qualities
of CPM scheduling.
iii. SCHEDULING PROJECT WITH
REPETITIVE ACTIVITIES
Authors have explained the repetitive scheduling
method(RSM), which recognizes the technical
constraints of CPM and they also includes an
additional resource continuity constraints to ensure
continuous resource usage. They also said that
construction contractors are often faced with projects
containing multiple units wherein activities repeat
from unit to unit. Therefore these projects require
Ms. Harsha Talodhikar Int. Journal of Engineering Research and Applications www.ijera.com
ISSN : 2248-9622, Vol. 5, Issue 3, ( Part -1) March 2015, pp.09-12
www.ijera.com 11 | P a g e
schedules that ensure the uninterrupted usage of
resources from an activity in one unit to a similar
activity in the next unit.
RSM method can be applied to both horizontal
and vertical projects containing either discrete or
continuous activities. An RSM schedule can be
presented graphically as an X-Y plot of a series of
production lines, all of which represent a repetitive
activity.
They have also explained about the controlling
sequence of activities as a new concept for the
determination of the project duration which is
introduced by RSM. This sequence includes activities
between control points on successive unit production
lines and extends from project start to project finish.
Lastly they concluded that the use of typical
CPM scheduling techniques cannot ensure this
continuity in resource utilization because only
technical precedence and resource availability
constraints are shown in CPM networks. The RSM
finds the additional resource continuity constraint
that cannot be shown in a network, and thus provides
for continuous resource usage.
III. METHODOLOGY
It is difficult for the project manager to find
which activity is going on particular floor when it
comes to the construction projectthat is broken down
into a large number of activities. Applicationof Line
of Balance scheduling technique can be done to the
project consisting of repetitive activities as it
facilitates the continuous monitoring of the project, at
each milestone.
The main objective of this study is to draw line
of balance graph for repetitive activities and compare
the actual and delay work at each stage of work and
crash the activities which are critical and to draw the
inferences.
 Data Collection: For drawing Line of Balance
graph, repetitive activities and their duration
should be known.
 Bar chart: The bar chart is pictorial
representation in two dimensions of the project.
The project is broken down into a number of
independent manageable jobs or units known as
activities for which suitable work duration is decided
on the basis of available resources.
 Drawing Line of Balance diagram: In LOB,
the time is plotted on X axis and the units or
stages on Y axis. The production rate of an
activity is the slope of the production line and is
expressed in terms of units per time. The line of
Balance technique assumes that the rate of
production for an activity is uniform. In other
words the rate of production is linear. The Line
of Balance technique uses man-hour estimate
and optimum crew size.
The two oblique and parallel lines used in line of
balance technique denote the start and finish times of
each activity in all the units from first to last.
 Plotting Histogram: A histogram is a bar graph
of raw data that creates a picture of the data
distribution. In my case Histogram will show
what is the maximum and minimum number of
labours required for a given period. Also, it will
be drawn for the crashed activities to find out
number of labours required.
 Calculation of Cost of the Project: Crashing of
activities will be done by reducing the duration
of the activities and increasing the resources,
therefore, it will effect on the total cost of the
project. Hence calculation of the cost of the
project will be done after crashing of activities.
 Inferences: From the Line of Balance graph of
the actual activities and the crashed activities,
inferences will be drawn whether this method is
suitable for crashed activities or not and the crew
size will be calculated from Histogram.
IV. FINDINGS FOR THE STUDY
For applying line of balance method to schedule
high-rise building, the activities like brickwork,
internal plaster, plumbing work, electrification work,
tiling, door and window frames, painting etc. which
are repeated from one floor to another and their
durations are collected.
The activities are then arranged in successive
manner and the graph of Line of Balance is drawn by
giving buffers at the top or bottom of the activity in
order to get the total duration of the project and to get
crew work continuity and rate of production is
calculated.
From graph it has seen that the duration of the
project is more. In order to reduce the duration of the
project, some activities which are critical and are
taking longer duration have to crash.
The critical activity has crashed by reducing the
duration and Line of Balance graph is drawn and
from graph it has been seen that the total duration of
the activity is reduced.
For getting the maximum and minimum number
of labours required, a graph is plotted for the
requirement of resources against the period of
requirement which is known as Resource Usage
Profile or in general language of statistics a
Histogram.
The Histogram is drawn for the actual work to
know the maximum and minimum number of labours
required for the project for the given period.
Ms. Harsha Talodhikar Int. Journal of Engineering Research and Applications www.ijera.com
ISSN : 2248-9622, Vol. 5, Issue 3, ( Part -1) March 2015, pp.09-12
www.ijera.com 12 | P a g e
Another graph of Histogram is drawn for the crashed
work to evaluate the number of labours required for
the crashed activity which is known as
Representation of Resources.
From the second graph of Histogram, Rate of
Production for the crashed activity is calculated by
using formula;
R=
𝐶
𝐷
Where,
R= Rate of Production
C= No. of crews/day
D= Duration(days)
Therefore, Rate of Production for the crashed activity
has been increased.
V. CONCLUSION
In high rise buildings, same activities are
repeated on each floor. In order to trace which
activity is going on particular floor, Line of Balance
method can be used. It is a graphical representation
of repetitive activities where project manager can
compare the planned and actual rate of production
and if the project is lagging behind the planned
schedule, the project manager can take suitable
action.
LOB and CPM method can be integrate for
scheduling repetitive activities, since to crash the
activity, critical activity should be known therefore
CPM can be used in Line of Balance method.
Since the activities are crashed to reduce the
duration of the project, but the cost of the project will
increase since the resources have to increase for the
project to be completed in stipulated time. Therefore
total cost of the project will increase by some
amount.
The study is limited to the projects where
activities are repeated in linear way or non-linear
way.
REFERENCES
Journal Papers:
[1] Sherif Mohamed Hafez,(2004), “ Practical
limitations of line of balance in scheduling
repetitive construction units”, The
Alexandria Engineering Journal, Vol. 43,
No. 5,pp (653-661).
[2] Mohammad A. Ammar, “LOB and CPM
Integrated Method for Scheduling Repetitive
Projects”, Journal of Construction
Engineering and Management, vol. 139,
No.1, January 1, 2013.
[3] David Arditi, M.ASCE1
;Onur B. Tokdemir2
; and Kangsuk Suh3
, “Challenges in Line-
of-Balance Scheduling”, Journal of
Construction Engineering and Management,
vol. 128, No.6, December 1, 2002.
[4] Robert B. Harris1
, Fellow, ASCE, and
Photios G. Ioannou2
, Member, ASCE,
“Scheduling Project with Repetitive
Activities”, Journal of Construction
Engineering and Management, vol. 124,
No.4, July/August, 1998.
[5] BY I-Tung Yang and Photios G. Ioannou,
(2002), “Resource-Driven Scheduling For
Repetitive Projects: A Pull- System
Approach” thesis work, pp (1-14) Science
Direct.
[6] Gregory A. Duffy, Garold D. Oberlender;
and David HyungSeokJeong, “ Linear
Scheduling Model with Varying Production
Rates”, (2011), “Journal of Construction
Engineering and Management” , The
Journal of Construction and Management,
Vol.I, pp (254-266).
[7] Magdalena Rogalska, Zdzislaw
Hejducki,(2007), “ Time Buffers in
Construction Process Scheduling”, The
Journal of Civil Engineering and
Management, Vol XIII, No 2, pp(143-148).
[8] Recardo Mendes Jr. and Luis Fernando M.
Heineck, (98),“Preplanning Method for
Multi-Story Building Construction Using
Line of Balance”, Proceedings IGLC 98.
Books:
[1] K.K. Chitkara, Construction Project
Management, pp (205-210).
[2] K. Nagarajan, Project Management, pp(89-
92).

More Related Content

What's hot

The Automation of Critical Path Method using Machine Learning: A Conceptual S...
The Automation of Critical Path Method using Machine Learning: A Conceptual S...The Automation of Critical Path Method using Machine Learning: A Conceptual S...
The Automation of Critical Path Method using Machine Learning: A Conceptual S...Dr. Amarjeet Singh
 
Economics of project evaluation cpm module2
Economics of project evaluation cpm module2Economics of project evaluation cpm module2
Economics of project evaluation cpm module2ahsanrabbani
 
Network analysis cpm module3
Network analysis cpm module3Network analysis cpm module3
Network analysis cpm module3ahsanrabbani
 
Difference between PERT and CPM
Difference between PERT and CPMDifference between PERT and CPM
Difference between PERT and CPMMunaf Dayee
 
Project management chapter 5
Project management chapter 5Project management chapter 5
Project management chapter 5VancityInstitute
 
Modeling Delay Percentage of Construction Projects in Egypt Using Statistical...
Modeling Delay Percentage of Construction Projects in Egypt Using Statistical...Modeling Delay Percentage of Construction Projects in Egypt Using Statistical...
Modeling Delay Percentage of Construction Projects in Egypt Using Statistical...IOSR Journals
 
A Multi-Objective Fuzzy Linear Programming Model for Cash Flow Management
A Multi-Objective Fuzzy Linear Programming Model for Cash Flow ManagementA Multi-Objective Fuzzy Linear Programming Model for Cash Flow Management
A Multi-Objective Fuzzy Linear Programming Model for Cash Flow ManagementIJERA Editor
 
A Study on Project Planning Using the Deterministic and Probabilistic Models ...
A Study on Project Planning Using the Deterministic and Probabilistic Models ...A Study on Project Planning Using the Deterministic and Probabilistic Models ...
A Study on Project Planning Using the Deterministic and Probabilistic Models ...IJERA Editor
 
Programme evaluation and review technique &Gantt Chart
Programme evaluation and review technique &Gantt ChartProgramme evaluation and review technique &Gantt Chart
Programme evaluation and review technique &Gantt ChartMathew Varghese V
 
“Application of the Program Evaluation Review and Technique
“Application of the Program Evaluation Review and Technique“Application of the Program Evaluation Review and Technique
“Application of the Program Evaluation Review and TechniquePantho Sarker
 
2 a review of different approaches to the facility layout problems
2   a review of different approaches to the facility layout problems2   a review of different approaches to the facility layout problems
2 a review of different approaches to the facility layout problemsQuốc Lê
 
Time-cost-risk optimization in construction work by using ant colony algorithm
Time-cost-risk optimization in construction work by using ant colony algorithmTime-cost-risk optimization in construction work by using ant colony algorithm
Time-cost-risk optimization in construction work by using ant colony algorithmVISHNU VIJAYAN
 
Program evaluation and review technique
Program evaluation and review techniqueProgram evaluation and review technique
Program evaluation and review techniqueGautam Chopra
 
4 b. Project management - network analysis
4 b. Project management - network analysis4 b. Project management - network analysis
4 b. Project management - network analysisDr.R. SELVAM
 
Operation research-Network analysis (Critical Path Method)
Operation research-Network analysis (Critical Path Method)Operation research-Network analysis (Critical Path Method)
Operation research-Network analysis (Critical Path Method)Kamel Attar
 

What's hot (20)

The Automation of Critical Path Method using Machine Learning: A Conceptual S...
The Automation of Critical Path Method using Machine Learning: A Conceptual S...The Automation of Critical Path Method using Machine Learning: A Conceptual S...
The Automation of Critical Path Method using Machine Learning: A Conceptual S...
 
cpmpertmy (1)
cpmpertmy (1)cpmpertmy (1)
cpmpertmy (1)
 
PROJECT MANAGEMENT - CPM & PERT
PROJECT MANAGEMENT - CPM & PERTPROJECT MANAGEMENT - CPM & PERT
PROJECT MANAGEMENT - CPM & PERT
 
Economics of project evaluation cpm module2
Economics of project evaluation cpm module2Economics of project evaluation cpm module2
Economics of project evaluation cpm module2
 
Network analysis cpm module3
Network analysis cpm module3Network analysis cpm module3
Network analysis cpm module3
 
Difference between PERT and CPM
Difference between PERT and CPMDifference between PERT and CPM
Difference between PERT and CPM
 
Project management chapter 5
Project management chapter 5Project management chapter 5
Project management chapter 5
 
Modeling Delay Percentage of Construction Projects in Egypt Using Statistical...
Modeling Delay Percentage of Construction Projects in Egypt Using Statistical...Modeling Delay Percentage of Construction Projects in Egypt Using Statistical...
Modeling Delay Percentage of Construction Projects in Egypt Using Statistical...
 
A Multi-Objective Fuzzy Linear Programming Model for Cash Flow Management
A Multi-Objective Fuzzy Linear Programming Model for Cash Flow ManagementA Multi-Objective Fuzzy Linear Programming Model for Cash Flow Management
A Multi-Objective Fuzzy Linear Programming Model for Cash Flow Management
 
A Study on Project Planning Using the Deterministic and Probabilistic Models ...
A Study on Project Planning Using the Deterministic and Probabilistic Models ...A Study on Project Planning Using the Deterministic and Probabilistic Models ...
A Study on Project Planning Using the Deterministic and Probabilistic Models ...
 
Programme evaluation and review technique &Gantt Chart
Programme evaluation and review technique &Gantt ChartProgramme evaluation and review technique &Gantt Chart
Programme evaluation and review technique &Gantt Chart
 
P E R T
P E R TP E R T
P E R T
 
“Application of the Program Evaluation Review and Technique
“Application of the Program Evaluation Review and Technique“Application of the Program Evaluation Review and Technique
“Application of the Program Evaluation Review and Technique
 
2 a review of different approaches to the facility layout problems
2   a review of different approaches to the facility layout problems2   a review of different approaches to the facility layout problems
2 a review of different approaches to the facility layout problems
 
Cpm and pert
Cpm and pertCpm and pert
Cpm and pert
 
Time-cost-risk optimization in construction work by using ant colony algorithm
Time-cost-risk optimization in construction work by using ant colony algorithmTime-cost-risk optimization in construction work by using ant colony algorithm
Time-cost-risk optimization in construction work by using ant colony algorithm
 
Program evaluation and review technique
Program evaluation and review techniqueProgram evaluation and review technique
Program evaluation and review technique
 
Cpmpert
CpmpertCpmpert
Cpmpert
 
4 b. Project management - network analysis
4 b. Project management - network analysis4 b. Project management - network analysis
4 b. Project management - network analysis
 
Operation research-Network analysis (Critical Path Method)
Operation research-Network analysis (Critical Path Method)Operation research-Network analysis (Critical Path Method)
Operation research-Network analysis (Critical Path Method)
 

Viewers also liked

Discretizing of linear systems with time-delay Using method of Euler’s and Tu...
Discretizing of linear systems with time-delay Using method of Euler’s and Tu...Discretizing of linear systems with time-delay Using method of Euler’s and Tu...
Discretizing of linear systems with time-delay Using method of Euler’s and Tu...IJERA Editor
 
Synchronizing Parallel Tasks Using STM
Synchronizing Parallel Tasks Using STMSynchronizing Parallel Tasks Using STM
Synchronizing Parallel Tasks Using STMIJERA Editor
 
Smith & Waller_Bring the Family ISBT 2012
Smith & Waller_Bring the Family ISBT 2012Smith & Waller_Bring the Family ISBT 2012
Smith & Waller_Bring the Family ISBT 2012GEOFF SMITH
 
The Inception and Evolution of EIA and Environmental Clearance Process – Layi...
The Inception and Evolution of EIA and Environmental Clearance Process – Layi...The Inception and Evolution of EIA and Environmental Clearance Process – Layi...
The Inception and Evolution of EIA and Environmental Clearance Process – Layi...IJERA Editor
 
A Review and study of the design technique of Microstrip Patch Antenna Techno...
A Review and study of the design technique of Microstrip Patch Antenna Techno...A Review and study of the design technique of Microstrip Patch Antenna Techno...
A Review and study of the design technique of Microstrip Patch Antenna Techno...IJERA Editor
 
Large Eddy Simulation of Turbulence Modeling for wind Flow past Wall Mounted ...
Large Eddy Simulation of Turbulence Modeling for wind Flow past Wall Mounted ...Large Eddy Simulation of Turbulence Modeling for wind Flow past Wall Mounted ...
Large Eddy Simulation of Turbulence Modeling for wind Flow past Wall Mounted ...IJERA Editor
 
Alyante Enterprise C.A.T.A. Informatica
Alyante Enterprise C.A.T.A. InformaticaAlyante Enterprise C.A.T.A. Informatica
Alyante Enterprise C.A.T.A. InformaticaC.A.T.A. INFORMATICA
 
A Brief Study of Video Encryption Algorithms
A Brief Study of Video Encryption AlgorithmsA Brief Study of Video Encryption Algorithms
A Brief Study of Video Encryption AlgorithmsIJERA Editor
 
Analysing The Composite Structure Of Riverted ,Hybrid And Bonded Joints
Analysing The Composite Structure Of Riverted ,Hybrid And Bonded JointsAnalysing The Composite Structure Of Riverted ,Hybrid And Bonded Joints
Analysing The Composite Structure Of Riverted ,Hybrid And Bonded JointsIJERA Editor
 
InternalAuditorTraining(QMS)_Jaya
InternalAuditorTraining(QMS)_JayaInternalAuditorTraining(QMS)_Jaya
InternalAuditorTraining(QMS)_JayaJaya Halder
 

Viewers also liked (14)

svejse_arbejdsbord
svejse_arbejdsbordsvejse_arbejdsbord
svejse_arbejdsbord
 
Discretizing of linear systems with time-delay Using method of Euler’s and Tu...
Discretizing of linear systems with time-delay Using method of Euler’s and Tu...Discretizing of linear systems with time-delay Using method of Euler’s and Tu...
Discretizing of linear systems with time-delay Using method of Euler’s and Tu...
 
Synchronizing Parallel Tasks Using STM
Synchronizing Parallel Tasks Using STMSynchronizing Parallel Tasks Using STM
Synchronizing Parallel Tasks Using STM
 
My Detail
My DetailMy Detail
My Detail
 
Smith & Waller_Bring the Family ISBT 2012
Smith & Waller_Bring the Family ISBT 2012Smith & Waller_Bring the Family ISBT 2012
Smith & Waller_Bring the Family ISBT 2012
 
The Inception and Evolution of EIA and Environmental Clearance Process – Layi...
The Inception and Evolution of EIA and Environmental Clearance Process – Layi...The Inception and Evolution of EIA and Environmental Clearance Process – Layi...
The Inception and Evolution of EIA and Environmental Clearance Process – Layi...
 
A Review and study of the design technique of Microstrip Patch Antenna Techno...
A Review and study of the design technique of Microstrip Patch Antenna Techno...A Review and study of the design technique of Microstrip Patch Antenna Techno...
A Review and study of the design technique of Microstrip Patch Antenna Techno...
 
Large Eddy Simulation of Turbulence Modeling for wind Flow past Wall Mounted ...
Large Eddy Simulation of Turbulence Modeling for wind Flow past Wall Mounted ...Large Eddy Simulation of Turbulence Modeling for wind Flow past Wall Mounted ...
Large Eddy Simulation of Turbulence Modeling for wind Flow past Wall Mounted ...
 
Alyante Enterprise C.A.T.A. Informatica
Alyante Enterprise C.A.T.A. InformaticaAlyante Enterprise C.A.T.A. Informatica
Alyante Enterprise C.A.T.A. Informatica
 
ante-projeto PU
ante-projeto PUante-projeto PU
ante-projeto PU
 
A Brief Study of Video Encryption Algorithms
A Brief Study of Video Encryption AlgorithmsA Brief Study of Video Encryption Algorithms
A Brief Study of Video Encryption Algorithms
 
Analysing The Composite Structure Of Riverted ,Hybrid And Bonded Joints
Analysing The Composite Structure Of Riverted ,Hybrid And Bonded JointsAnalysing The Composite Structure Of Riverted ,Hybrid And Bonded Joints
Analysing The Composite Structure Of Riverted ,Hybrid And Bonded Joints
 
Classic Rock
Classic Rock Classic Rock
Classic Rock
 
InternalAuditorTraining(QMS)_Jaya
InternalAuditorTraining(QMS)_JayaInternalAuditorTraining(QMS)_Jaya
InternalAuditorTraining(QMS)_Jaya
 

Similar to Line of Balance Method for Scheduling High-Rise Buildings

Line of Balance
Line of BalanceLine of Balance
Line of BalanceIJMER
 
A Case Study On Applying Lean Construction To Concrete
A Case Study On Applying Lean Construction To ConcreteA Case Study On Applying Lean Construction To Concrete
A Case Study On Applying Lean Construction To ConcreteDawn Cook
 
J.S. Daniel paper of fast tracking design in megaproject construction
J.S. Daniel paper of fast tracking design in megaproject constructionJ.S. Daniel paper of fast tracking design in megaproject construction
J.S. Daniel paper of fast tracking design in megaproject constructionJ.S. Daniel
 
EJMCM_Volume 7_Issue 4_Pages 310-318.pdf
EJMCM_Volume 7_Issue 4_Pages 310-318.pdfEJMCM_Volume 7_Issue 4_Pages 310-318.pdf
EJMCM_Volume 7_Issue 4_Pages 310-318.pdfkripeshdubey1
 
Literature Review in Project Scheduling Techniques
Literature Review in Project Scheduling TechniquesLiterature Review in Project Scheduling Techniques
Literature Review in Project Scheduling TechniquesObi-Ugbo Alex
 
I0313048051
I0313048051I0313048051
I0313048051theijes
 
Construction Project Managment Techniques
Construction Project Managment TechniquesConstruction Project Managment Techniques
Construction Project Managment Techniquesguestc8140fe
 
Resource scheduling in Construction Projects Using MSP
Resource scheduling in Construction Projects Using MSPResource scheduling in Construction Projects Using MSP
Resource scheduling in Construction Projects Using MSPSagar Kaptan
 
Complex Project Crashing Algorithm
Complex Project Crashing AlgorithmComplex Project Crashing Algorithm
Complex Project Crashing AlgorithmIOSR Journals
 
IRJET- Application of Time Divisions Scheduling Techniques for Duration and Q...
IRJET- Application of Time Divisions Scheduling Techniques for Duration and Q...IRJET- Application of Time Divisions Scheduling Techniques for Duration and Q...
IRJET- Application of Time Divisions Scheduling Techniques for Duration and Q...IRJET Journal
 
An Integrated BIM System To Track The Time And Cost Of Construction Projects ...
An Integrated BIM System To Track The Time And Cost Of Construction Projects ...An Integrated BIM System To Track The Time And Cost Of Construction Projects ...
An Integrated BIM System To Track The Time And Cost Of Construction Projects ...Nat Rice
 
Planning And Scheduling Construction For Decades
Planning And Scheduling Construction For DecadesPlanning And Scheduling Construction For Decades
Planning And Scheduling Construction For DecadesBeth Hall
 
OR PERT CPM AND JOB SCHEDULING
OR PERT CPM AND JOB SCHEDULINGOR PERT CPM AND JOB SCHEDULING
OR PERT CPM AND JOB SCHEDULINGJignesh Kariya
 
Scheduling coordination and control of projects
Scheduling coordination and control of projects Scheduling coordination and control of projects
Scheduling coordination and control of projects Somashekar S.M
 
Construction project management
Construction project managementConstruction project management
Construction project managementsaif hasan
 
STUDY AND IMPLEMENTATION OF LAST PLANNER SYSTEM (LPS) IN CONSTRUCTION PROJECTS
STUDY AND IMPLEMENTATION OF LAST PLANNER SYSTEM (LPS) IN CONSTRUCTION PROJECTSSTUDY AND IMPLEMENTATION OF LAST PLANNER SYSTEM (LPS) IN CONSTRUCTION PROJECTS
STUDY AND IMPLEMENTATION OF LAST PLANNER SYSTEM (LPS) IN CONSTRUCTION PROJECTSIRJET Journal
 
Senstivity Analysis of Project Scheduling using Fuzzy Set Theory
Senstivity Analysis of Project Scheduling using Fuzzy Set TheorySenstivity Analysis of Project Scheduling using Fuzzy Set Theory
Senstivity Analysis of Project Scheduling using Fuzzy Set TheoryIRJET Journal
 

Similar to Line of Balance Method for Scheduling High-Rise Buildings (20)

Line of Balance
Line of BalanceLine of Balance
Line of Balance
 
A Case Study On Applying Lean Construction To Concrete
A Case Study On Applying Lean Construction To ConcreteA Case Study On Applying Lean Construction To Concrete
A Case Study On Applying Lean Construction To Concrete
 
J.S. Daniel paper of fast tracking design in megaproject construction
J.S. Daniel paper of fast tracking design in megaproject constructionJ.S. Daniel paper of fast tracking design in megaproject construction
J.S. Daniel paper of fast tracking design in megaproject construction
 
EJMCM_Volume 7_Issue 4_Pages 310-318.pdf
EJMCM_Volume 7_Issue 4_Pages 310-318.pdfEJMCM_Volume 7_Issue 4_Pages 310-318.pdf
EJMCM_Volume 7_Issue 4_Pages 310-318.pdf
 
Literature Review in Project Scheduling Techniques
Literature Review in Project Scheduling TechniquesLiterature Review in Project Scheduling Techniques
Literature Review in Project Scheduling Techniques
 
20320140505001
2032014050500120320140505001
20320140505001
 
I0313048051
I0313048051I0313048051
I0313048051
 
Construction Project Managment Techniques
Construction Project Managment TechniquesConstruction Project Managment Techniques
Construction Project Managment Techniques
 
Resource scheduling in Construction Projects Using MSP
Resource scheduling in Construction Projects Using MSPResource scheduling in Construction Projects Using MSP
Resource scheduling in Construction Projects Using MSP
 
Complex Project Crashing Algorithm
Complex Project Crashing AlgorithmComplex Project Crashing Algorithm
Complex Project Crashing Algorithm
 
IRJET- Application of Time Divisions Scheduling Techniques for Duration and Q...
IRJET- Application of Time Divisions Scheduling Techniques for Duration and Q...IRJET- Application of Time Divisions Scheduling Techniques for Duration and Q...
IRJET- Application of Time Divisions Scheduling Techniques for Duration and Q...
 
An Integrated BIM System To Track The Time And Cost Of Construction Projects ...
An Integrated BIM System To Track The Time And Cost Of Construction Projects ...An Integrated BIM System To Track The Time And Cost Of Construction Projects ...
An Integrated BIM System To Track The Time And Cost Of Construction Projects ...
 
Planning And Scheduling Construction For Decades
Planning And Scheduling Construction For DecadesPlanning And Scheduling Construction For Decades
Planning And Scheduling Construction For Decades
 
OR PERT CPM AND JOB SCHEDULING
OR PERT CPM AND JOB SCHEDULINGOR PERT CPM AND JOB SCHEDULING
OR PERT CPM AND JOB SCHEDULING
 
Scheduling coordination and control of projects
Scheduling coordination and control of projects Scheduling coordination and control of projects
Scheduling coordination and control of projects
 
H1303055462
H1303055462H1303055462
H1303055462
 
Construction project management
Construction project managementConstruction project management
Construction project management
 
asdfds
asdfdsasdfds
asdfds
 
STUDY AND IMPLEMENTATION OF LAST PLANNER SYSTEM (LPS) IN CONSTRUCTION PROJECTS
STUDY AND IMPLEMENTATION OF LAST PLANNER SYSTEM (LPS) IN CONSTRUCTION PROJECTSSTUDY AND IMPLEMENTATION OF LAST PLANNER SYSTEM (LPS) IN CONSTRUCTION PROJECTS
STUDY AND IMPLEMENTATION OF LAST PLANNER SYSTEM (LPS) IN CONSTRUCTION PROJECTS
 
Senstivity Analysis of Project Scheduling using Fuzzy Set Theory
Senstivity Analysis of Project Scheduling using Fuzzy Set TheorySenstivity Analysis of Project Scheduling using Fuzzy Set Theory
Senstivity Analysis of Project Scheduling using Fuzzy Set Theory
 

Recently uploaded

UNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular ConduitsUNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular Conduitsrknatarajan
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performancesivaprakash250
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxpranjaldaimarysona
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...Call Girls in Nagpur High Profile
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxupamatechverse
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)Suman Mia
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSISrknatarajan
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxupamatechverse
 
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).pptssuser5c9d4b1
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college projectTonystark477637
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSSIVASHANKAR N
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 

Recently uploaded (20)

UNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular ConduitsUNIT-II FMM-Flow Through Circular Conduits
UNIT-II FMM-Flow Through Circular Conduits
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performance
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptx
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINEDJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptx
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSIS
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptx
 
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college project
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
 

Line of Balance Method for Scheduling High-Rise Buildings

  • 1. Ms. Harsha Talodhikar Int. Journal of Engineering Research and Applications www.ijera.com ISSN : 2248-9622, Vol. 5, Issue 3, ( Part -1) March 2015, pp.09-12 www.ijera.com 9 | P a g e Implementation of Line of Balance Method for Scheduling High- rise Building Ms. Harsha Talodhikar*, Prof. Mrs. Smita V. Pataskar** *(Department of Civil Engineering, Savitribai Phule Pune University, Pune, Maharashtra, India.) ** *(Department of Civil Engineering, Savitribai Phule Pune University, Pune, Maharashtra, India.) ABSTRACT In linear construction projects like high rise buildings, roadways, pipelines where activities are repeated after a specific interval, it is very much important for project manager to monitor the project at each stage. Line of Balance method is therefore useful for the project like high rise building to monitor the progress of the work. This method is useful for calculating the total duration of the project, crew synchronization and also shows the process, status, timing and phasing of the project activities. The overall objective of this study is to identify the total duration required by the project for its completion and its comparison with the actual plan by using Line of Balance method, to crash some of the activities and find out the total duration of crashed activities and to calculate labours required for the crashed activities by drawing the graph of Histogram.Keywords- crashing, crew synchronization, buffer, Histogram, Rate of Production I. INTRODUCTION A. BACKGROUND The Line of Balance Scheduling Technique was originated by the Goodyear Company in the early 1940’s and was developed by the U. S. Navy in the early 1950’s for the programming and control of both repetitive and non-repetitive projects. The construction of projects of repetitive units can be considered as the continuous manufacturing of many units requiring a certain period of time for each unit to be completed. It can be used in projects involving activities of repetitive nature such as housing projects, high rise buildings, long bridges, highway construction, and pipelines (Lumsden, 1968). The LOB was first applied to industrial manufacturing and production control, where the objective was to evaluate a production line flow rate of finished products. The line of balance method is based on underlying assumption that the rate of production for an activity is uniform. The basic concepts of LOB have been applied in the construction industry as a planning and scheduling method in Finland in the 1980s (Harris and McCaffer, 1989). The LOB chart provides an overview of the project’s overall status by quantitatively representing the cumulative completion of activities at a given point of time. It graphically reveals any imbalance that suggests a deviation in the progress of activities which enables the management to focus on assessing the deviation quantitatively (Khisty 1970). B. AIMS AND OBJECTIVES OF STUDY The main purpose of applying Line of Balance method to high rise building is to:  Draw the graph of repetitive activities, as applying LOB facilitates the continuous monitoring of the project, at each stage.  Calculate rate of production of work.  Compare the cost of actual and delay project.  Draw the graph of activities after crashing, and to know the rate of flow of the activities.  Evaluate size of crew required for the crashed activities. C. LIMITATIONS The study is limited to the following respects  Inability to generate a clear critical path of the project schedule, relative to the one provided by CPM schedules.  In CPM scheduling the user could divide project by location and other systems like trades, in LOB only location.  Productivity rates in LOB schedule do not include the effect of crews “learning curve, or if the individuals working in the crews changed”. II. LITERATURE REVIEW i. PRACTICAL LIMITATIONS OF LINE OF BALANCE IN SCHEDULING REPETITIVE CONSTRUCTION UNITS In this paper the author has explained, about practical limitations, and constraints while using Line of Balance method and also have studied different factors to be considered while drawing as well as using LOB. Logical sequence: Scheduling construction projects with repeating activities are performed based on a combination of network technology and the basic concept of LOB. The precedence relationships RESEARCH ARTICLE OPEN ACCESS
  • 2. Ms. Harsha Talodhikar Int. Journal of Engineering Research and Applications www.ijera.com ISSN : 2248-9622, Vol. 5, Issue 3, ( Part -1) March 2015, pp.09-12 www.ijera.com 10 | P a g e define the logical sequence between successive construction activities. All types of logical precedence relationships between succeeding activities (start-to-start; start-to-finish; finish-to-finish and finish-to-start) can be represented in the unit network. Crew work continuity: The application of such work continuity during scheduling of repetitive construction leads to the following managerial function: (i) maximize the benefits from the learning curve effect for each crew. These results have considerable savings in time and cost. (ii) Minimize the idle waiting intervals of equipment and labour. (iii) Minimize extra effort associated with work interruptions such as- setup time, temporary storage of tools and materials.(iv) Minimise the off-on movement of crews on a project once work has begun. Number of employed crews: The crew availability constraint depends on the available number of crews that can be assigned to activity in all repetitive units of the construction project. Making the schedule resource oriented, maximum efficiency can be adopted. Work crew size: A crew of optimum size is defined as a combination of trade workers, materials, and equipment that usually guarantees maximum productivity in an activity. This crew is expected to carry out the related activity in the most cost efficient way. Project resources: The distribution of resources during the project process is one of particular importance for construction managers. Not only do managers have to make sure that the resources they allocate to the activities do not exceed availabilities. They would also want to see as smooth a distribution as possible to avoid the disruption of hiring and firing crews during the project progress. Workflow direction: Upward direction: Most work is scheduled in upward direction to follow the construction of skeleton. Downward direction: Some other construction activities, how-ever, are scheduled in a downward direction for reasons (i.e., safety or to prevent damage of the installed work). The final finishing of external cladding, clearing, and cleaning could be the typical examples of such activities. Author concluded that several issues associated with LOB application have been identifies in this research. The research determines the practical limitations of LOB in scheduling repetitive construction units. ii. LOB AND CPM INTEGRATED METHOD FOR SCHEDULING REPETITIVE PROJECTS It is said that repetitive projects require schedules that ensure the uninterrupted usage of resources from a unit to similar units in a repetitive activity while maintaining logical dependency constraintsand the critical path method(CPM) is the most widely used and accepted planning and scheduling method for non-repetitive projects, but does not suit the planning and scheduling method for repetitive projects. On the other hand, Line of Balance(LOB) has been used in scheduling repetitive activities, which is a resource driven technique. Author made few attempts to combine the benefits of CPM and LOB technique in planning and scheduling of repetitive projects. He developed an integrated CPM and LOB model to schedule repetitive projects in an easy non-graphical manner, considering both resource continuity constraints and logic dependencies. The activities which overlaps of a single typical unit are used to model duration and logical relationships of repetitive activities. He proposed a model which consists of four steps: (i) LOB calculations: The objective of LOB formulation is to achieve a resource- balanced schedule by determining the number of crews to be employed in each repetitive activity. This is conducted such that the units are delivered with a rate that meets a pre-specified project deadline and crew’s work continuity is maintained. (ii) Calculating activity duration: Overlapping activities are generalized to represent repetitive activities. For this, the duration is assumed constant in all units of a repetitive activity. (iii) Specifying logical relationships using Overlapping activities: The logical dependency relationship among different activities can be specified according to the selected rate of progress of each activity. It significantly maintains the work continuity. (iv) Time scheduling: After LOB calculations and the relationship type among the consecutive activities specified with their associated lags, time analysis similar to that of CPM can be performed. The Author further concluded that scheduling of repetitive projects represents a challenge for construction planners and managers. Classical CPM analysis does not suit characteristics of repetitive projects, whereas LOB lacks the analytical qualities of CPM scheduling. iii. SCHEDULING PROJECT WITH REPETITIVE ACTIVITIES Authors have explained the repetitive scheduling method(RSM), which recognizes the technical constraints of CPM and they also includes an additional resource continuity constraints to ensure continuous resource usage. They also said that construction contractors are often faced with projects containing multiple units wherein activities repeat from unit to unit. Therefore these projects require
  • 3. Ms. Harsha Talodhikar Int. Journal of Engineering Research and Applications www.ijera.com ISSN : 2248-9622, Vol. 5, Issue 3, ( Part -1) March 2015, pp.09-12 www.ijera.com 11 | P a g e schedules that ensure the uninterrupted usage of resources from an activity in one unit to a similar activity in the next unit. RSM method can be applied to both horizontal and vertical projects containing either discrete or continuous activities. An RSM schedule can be presented graphically as an X-Y plot of a series of production lines, all of which represent a repetitive activity. They have also explained about the controlling sequence of activities as a new concept for the determination of the project duration which is introduced by RSM. This sequence includes activities between control points on successive unit production lines and extends from project start to project finish. Lastly they concluded that the use of typical CPM scheduling techniques cannot ensure this continuity in resource utilization because only technical precedence and resource availability constraints are shown in CPM networks. The RSM finds the additional resource continuity constraint that cannot be shown in a network, and thus provides for continuous resource usage. III. METHODOLOGY It is difficult for the project manager to find which activity is going on particular floor when it comes to the construction projectthat is broken down into a large number of activities. Applicationof Line of Balance scheduling technique can be done to the project consisting of repetitive activities as it facilitates the continuous monitoring of the project, at each milestone. The main objective of this study is to draw line of balance graph for repetitive activities and compare the actual and delay work at each stage of work and crash the activities which are critical and to draw the inferences.  Data Collection: For drawing Line of Balance graph, repetitive activities and their duration should be known.  Bar chart: The bar chart is pictorial representation in two dimensions of the project. The project is broken down into a number of independent manageable jobs or units known as activities for which suitable work duration is decided on the basis of available resources.  Drawing Line of Balance diagram: In LOB, the time is plotted on X axis and the units or stages on Y axis. The production rate of an activity is the slope of the production line and is expressed in terms of units per time. The line of Balance technique assumes that the rate of production for an activity is uniform. In other words the rate of production is linear. The Line of Balance technique uses man-hour estimate and optimum crew size. The two oblique and parallel lines used in line of balance technique denote the start and finish times of each activity in all the units from first to last.  Plotting Histogram: A histogram is a bar graph of raw data that creates a picture of the data distribution. In my case Histogram will show what is the maximum and minimum number of labours required for a given period. Also, it will be drawn for the crashed activities to find out number of labours required.  Calculation of Cost of the Project: Crashing of activities will be done by reducing the duration of the activities and increasing the resources, therefore, it will effect on the total cost of the project. Hence calculation of the cost of the project will be done after crashing of activities.  Inferences: From the Line of Balance graph of the actual activities and the crashed activities, inferences will be drawn whether this method is suitable for crashed activities or not and the crew size will be calculated from Histogram. IV. FINDINGS FOR THE STUDY For applying line of balance method to schedule high-rise building, the activities like brickwork, internal plaster, plumbing work, electrification work, tiling, door and window frames, painting etc. which are repeated from one floor to another and their durations are collected. The activities are then arranged in successive manner and the graph of Line of Balance is drawn by giving buffers at the top or bottom of the activity in order to get the total duration of the project and to get crew work continuity and rate of production is calculated. From graph it has seen that the duration of the project is more. In order to reduce the duration of the project, some activities which are critical and are taking longer duration have to crash. The critical activity has crashed by reducing the duration and Line of Balance graph is drawn and from graph it has been seen that the total duration of the activity is reduced. For getting the maximum and minimum number of labours required, a graph is plotted for the requirement of resources against the period of requirement which is known as Resource Usage Profile or in general language of statistics a Histogram. The Histogram is drawn for the actual work to know the maximum and minimum number of labours required for the project for the given period.
  • 4. Ms. Harsha Talodhikar Int. Journal of Engineering Research and Applications www.ijera.com ISSN : 2248-9622, Vol. 5, Issue 3, ( Part -1) March 2015, pp.09-12 www.ijera.com 12 | P a g e Another graph of Histogram is drawn for the crashed work to evaluate the number of labours required for the crashed activity which is known as Representation of Resources. From the second graph of Histogram, Rate of Production for the crashed activity is calculated by using formula; R= 𝐶 𝐷 Where, R= Rate of Production C= No. of crews/day D= Duration(days) Therefore, Rate of Production for the crashed activity has been increased. V. CONCLUSION In high rise buildings, same activities are repeated on each floor. In order to trace which activity is going on particular floor, Line of Balance method can be used. It is a graphical representation of repetitive activities where project manager can compare the planned and actual rate of production and if the project is lagging behind the planned schedule, the project manager can take suitable action. LOB and CPM method can be integrate for scheduling repetitive activities, since to crash the activity, critical activity should be known therefore CPM can be used in Line of Balance method. Since the activities are crashed to reduce the duration of the project, but the cost of the project will increase since the resources have to increase for the project to be completed in stipulated time. Therefore total cost of the project will increase by some amount. The study is limited to the projects where activities are repeated in linear way or non-linear way. REFERENCES Journal Papers: [1] Sherif Mohamed Hafez,(2004), “ Practical limitations of line of balance in scheduling repetitive construction units”, The Alexandria Engineering Journal, Vol. 43, No. 5,pp (653-661). [2] Mohammad A. Ammar, “LOB and CPM Integrated Method for Scheduling Repetitive Projects”, Journal of Construction Engineering and Management, vol. 139, No.1, January 1, 2013. [3] David Arditi, M.ASCE1 ;Onur B. Tokdemir2 ; and Kangsuk Suh3 , “Challenges in Line- of-Balance Scheduling”, Journal of Construction Engineering and Management, vol. 128, No.6, December 1, 2002. [4] Robert B. Harris1 , Fellow, ASCE, and Photios G. Ioannou2 , Member, ASCE, “Scheduling Project with Repetitive Activities”, Journal of Construction Engineering and Management, vol. 124, No.4, July/August, 1998. [5] BY I-Tung Yang and Photios G. Ioannou, (2002), “Resource-Driven Scheduling For Repetitive Projects: A Pull- System Approach” thesis work, pp (1-14) Science Direct. [6] Gregory A. Duffy, Garold D. Oberlender; and David HyungSeokJeong, “ Linear Scheduling Model with Varying Production Rates”, (2011), “Journal of Construction Engineering and Management” , The Journal of Construction and Management, Vol.I, pp (254-266). [7] Magdalena Rogalska, Zdzislaw Hejducki,(2007), “ Time Buffers in Construction Process Scheduling”, The Journal of Civil Engineering and Management, Vol XIII, No 2, pp(143-148). [8] Recardo Mendes Jr. and Luis Fernando M. Heineck, (98),“Preplanning Method for Multi-Story Building Construction Using Line of Balance”, Proceedings IGLC 98. Books: [1] K.K. Chitkara, Construction Project Management, pp (205-210). [2] K. Nagarajan, Project Management, pp(89- 92).