SlideShare a Scribd company logo
ASSEMBLY LINE
BALANCING
MODUL 7
What is Line Balancing ??
 Assigning each task to a work within an assembly
line in order to meet the required production rate
and to achieve a minimum amount of idle time.
 Line balancing is the procedure in which tasks
along the assembly line are assigned to work
station so each line has approximately same
amount of work.
Terms Defined
 Delay/idle time of a workstation: the difference
between the cycle time (CT) and the station time
(ST).
 Cycle time (CT): the time between the completion
of 2 successive assemblies, assumed constant
for all assemblies for a given conveyor speed.
Terms Defined (Cont.)
 Line efficiency (LE): the ratio of total station time to
the cycle time multiplied by the number of
workstations
 Balance Delay
 Balance Delay
 Work element: a part of the total work content in an
assembly process.
Terms Defined (Cont.)
 Smoothness index (SI): an index to indicate the
relative smoothness of a given assembly line
balance. A smoothness index of zero indicates a
perfect balance
 Workstation (WS): a location on the assembly line
where a work element or elements are performed
on the product.
Precedence Constraint
 Precedence Constraint is a restriction on the
order of execution of work elements.
 There are two conditions taht usually appear in
assembling process:
1. There is no dependency of the components in the
works
2. If a component has been selected to be
assembled, then the sequence begins to
assemble other components.
Precedence diagram
 Precedence diagram: a diagram that describes
the ordering in which work elements should be
performed. It shows that some jobs cannot be
performed unless their predecessors are
completed. The layout of workstations along the
assembly line depends on the precedence
diagram
 Presedence diagram symbols:
Symbol element
Relationship between symbols
Precedence Diagram
Zoning Constraint
 Allocation of work elements at the work station is
also limited by zoning constraints that
preclude or require grouping of certain elements
of the work on a particular station.
Line Balancing Methods
 Helgeson dan Birnie / Ranked Positional
Weight (RPW)
 Kilbridge and Wester Heuristic (Region
Approach)
 Largest Candidate Rule
Helgeson dan Birnie / Ranked
Positional Weight (RPW)
Step 1- Calculate the weight of the position of each
work elements.
Step 2- Sort the elements according to the weight of the
position of the largest to the smallest.
Step 3 -Calculate the cycle time.
 4. Place the working element with the greatest weight
on all the workstations do not violate precedence
relationships and time station does not exceed the
cycle time.
 5. Repeat step 4 until all the elements are placed.
 6. After forming a work station consisting of its
elements, then specify the value of efficient, balance
delay, and its smoothest index.
Kilbridge and Wester Heuristic
(Region Approach)
 Create precedence diagram of the problems faced.
Separate work elements in the diagram in columns
from right to left.
 2. Determine the cycle time (TC) of primes total time
working elements, and specify the number of work
stations.
 3. Place the work elements to work stations such that
the total time working element does not exceed the
cycle time. Remove elements of work that has been
placed on the list of work elements.
 4. When an element of work placement resulted in a
total time of work elements exceeds the cycle time
working elements are placed in the next work station.
 5. Repeat steps 3 and 4 until all work elements are
placed.
 6. Determine the value of efficient, balance delay, and
smoothness index
Largest Candidate Rule
 The basic principle is to combine the processes of
sorting operation on the basis of the largest
processing time to the smallest elements of the
operating time
 Steps:
1. Starting from the top, select the element to be
assigned to the first station, which meets the
requirements of precedence and does not cause the
total amount exceeds Tek on stretcher station Ts.
2. If there are no other elements that can be assigned
without exceeding Ts, then move on to the next
station.
3. Repeat steps 1 and 2 for the other stations until the
completion of all elements assigned.
4. Determine the value of efficient, balance delay, its
smoothness index.

More Related Content

What's hot

79971255 assembly-line-balancing
79971255 assembly-line-balancing79971255 assembly-line-balancing
79971255 assembly-line-balancing
Joseph Konnully
 
Final line balancing ppt 4
Final line balancing ppt 4Final line balancing ppt 4
Final line balancing ppt 4
navyamukhi1
 
Time study
Time studyTime study
Time study
Lav Gupta
 
Line balancing and its formulation
Line balancing and its formulationLine balancing and its formulation
Line balancing and its formulation
avijit biswas
 
Line balancing
Line balancingLine balancing
Cellular manufacturing
Cellular manufacturingCellular manufacturing
Cellular manufacturing
ananya0122
 
PREDETERMINED MOTION TIME SYSTEM (PMTS).pptx
PREDETERMINED MOTION TIME SYSTEM (PMTS).pptxPREDETERMINED MOTION TIME SYSTEM (PMTS).pptx
PREDETERMINED MOTION TIME SYSTEM (PMTS).pptx
LakshayKumar504432
 
UNIT 2 - WORK STUDY
UNIT 2 -  WORK STUDYUNIT 2 -  WORK STUDY
Assembly Line Balancing
Assembly Line BalancingAssembly Line Balancing
Assembly Line Balancing
Alan Wei Teck
 
Line balancing
Line balancingLine balancing
Line balancing
geetha_64
 
Performance rating
Performance ratingPerformance rating
Performance rating
Shivam Kumar
 
Industrial Engineering (Method Study and Work study)
Industrial Engineering (Method Study and Work study)Industrial Engineering (Method Study and Work study)
Industrial Engineering (Method Study and Work study)
Vishal Shinde
 
Ranked Positional Weight Method | Management
Ranked Positional Weight Method | ManagementRanked Positional Weight Method | Management
Ranked Positional Weight Method | Management
Transweb Global Inc
 
Lecture 2 process charts work study
Lecture 2 process charts work studyLecture 2 process charts work study
Lecture 2 process charts work study
rahulmeshram14
 
travel chart for plant layout
travel chart for plant layouttravel chart for plant layout
travel chart for plant layout
Yash Patel
 
Assembly systems & line balance
Assembly systems & line balanceAssembly systems & line balance
Assembly systems & line balanceSudhir Reddy
 
work measurement_operation management
work measurement_operation managementwork measurement_operation management
work measurement_operation management
Saravanan Murugan
 

What's hot (20)

79971255 assembly-line-balancing
79971255 assembly-line-balancing79971255 assembly-line-balancing
79971255 assembly-line-balancing
 
Final line balancing ppt 4
Final line balancing ppt 4Final line balancing ppt 4
Final line balancing ppt 4
 
Time study
Time studyTime study
Time study
 
TIME STUDY
TIME STUDYTIME STUDY
TIME STUDY
 
Line balancing and its formulation
Line balancing and its formulationLine balancing and its formulation
Line balancing and its formulation
 
Line balancing
Line balancingLine balancing
Line balancing
 
Cellular manufacturing
Cellular manufacturingCellular manufacturing
Cellular manufacturing
 
PREDETERMINED MOTION TIME SYSTEM (PMTS).pptx
PREDETERMINED MOTION TIME SYSTEM (PMTS).pptxPREDETERMINED MOTION TIME SYSTEM (PMTS).pptx
PREDETERMINED MOTION TIME SYSTEM (PMTS).pptx
 
UNIT 2 - WORK STUDY
UNIT 2 -  WORK STUDYUNIT 2 -  WORK STUDY
UNIT 2 - WORK STUDY
 
Assembly Line Balancing
Assembly Line BalancingAssembly Line Balancing
Assembly Line Balancing
 
Line balancing
Line balancingLine balancing
Line balancing
 
Performance rating
Performance ratingPerformance rating
Performance rating
 
Industrial Engineering (Method Study and Work study)
Industrial Engineering (Method Study and Work study)Industrial Engineering (Method Study and Work study)
Industrial Engineering (Method Study and Work study)
 
Ranked Positional Weight Method | Management
Ranked Positional Weight Method | ManagementRanked Positional Weight Method | Management
Ranked Positional Weight Method | Management
 
Lecture 2 process charts work study
Lecture 2 process charts work studyLecture 2 process charts work study
Lecture 2 process charts work study
 
Work sample
Work sampleWork sample
Work sample
 
Work study
Work studyWork study
Work study
 
travel chart for plant layout
travel chart for plant layouttravel chart for plant layout
travel chart for plant layout
 
Assembly systems & line balance
Assembly systems & line balanceAssembly systems & line balance
Assembly systems & line balance
 
work measurement_operation management
work measurement_operation managementwork measurement_operation management
work measurement_operation management
 

Viewers also liked

Operations Management : Line Balancing
Operations Management : Line BalancingOperations Management : Line Balancing
Operations Management : Line Balancing
Rohan Bharaj
 
Line balancing and heuristics
Line balancing and heuristicsLine balancing and heuristics
Line balancing and heuristics
Abrity Bhattacharya
 
The learning process
The learning processThe learning process
The learning process
Kerry Harrison
 
Production and Faults in Cutting, Sewing & Finishing in a Knit Garment Industry
Production and Faults in Cutting, Sewing & Finishing in a Knit Garment IndustryProduction and Faults in Cutting, Sewing & Finishing in a Knit Garment Industry
Production and Faults in Cutting, Sewing & Finishing in a Knit Garment IndustryMd.Abdullah Al Faruk
 
Spreading and cutting machines
Spreading and cutting machinesSpreading and cutting machines
Spreading and cutting machines
Kundan Ganvir
 
Study on Lean Manufacturing Process in Garments Production
Study on Lean Manufacturing Process in Garments ProductionStudy on Lean Manufacturing Process in Garments Production
Study on Lean Manufacturing Process in Garments Production
Momin Uddin
 
Assembly Line Balancing -Example
Assembly Line Balancing -ExampleAssembly Line Balancing -Example
Assembly Line Balancing -Example
Joseph Konnully
 
Garments production system
Garments production systemGarments production system
Garments production systemamnapervaiz14
 
Garment manufacturing process from fabric to poduct
Garment manufacturing process from fabric to poductGarment manufacturing process from fabric to poduct
Garment manufacturing process from fabric to poduct
Karthika M Dev
 
LEARNING CURVE
LEARNING CURVELEARNING CURVE
LEARNING CURVE
Ahmad Tariq Bhatti
 

Viewers also liked (18)

Operations Management : Line Balancing
Operations Management : Line BalancingOperations Management : Line Balancing
Operations Management : Line Balancing
 
Line balancing and heuristics
Line balancing and heuristicsLine balancing and heuristics
Line balancing and heuristics
 
Assembly Line Balancing
Assembly Line BalancingAssembly Line Balancing
Assembly Line Balancing
 
Line Balancing In Garments Industry
Line Balancing In Garments IndustryLine Balancing In Garments Industry
Line Balancing In Garments Industry
 
The learning process
The learning processThe learning process
The learning process
 
Cutting
CuttingCutting
Cutting
 
Cutting
CuttingCutting
Cutting
 
Production and Faults in Cutting, Sewing & Finishing in a Knit Garment Industry
Production and Faults in Cutting, Sewing & Finishing in a Knit Garment IndustryProduction and Faults in Cutting, Sewing & Finishing in a Knit Garment Industry
Production and Faults in Cutting, Sewing & Finishing in a Knit Garment Industry
 
Spreading and cutting machines
Spreading and cutting machinesSpreading and cutting machines
Spreading and cutting machines
 
Garment costing
Garment costingGarment costing
Garment costing
 
Study on Lean Manufacturing Process in Garments Production
Study on Lean Manufacturing Process in Garments ProductionStudy on Lean Manufacturing Process in Garments Production
Study on Lean Manufacturing Process in Garments Production
 
Assembly Line Balancing -Example
Assembly Line Balancing -ExampleAssembly Line Balancing -Example
Assembly Line Balancing -Example
 
Garments production system
Garments production systemGarments production system
Garments production system
 
WORK study& LINE BALANCING
WORK study& LINE BALANCING WORK study& LINE BALANCING
WORK study& LINE BALANCING
 
Garment manufacturing process from fabric to poduct
Garment manufacturing process from fabric to poductGarment manufacturing process from fabric to poduct
Garment manufacturing process from fabric to poduct
 
Learning curve
Learning curveLearning curve
Learning curve
 
LEARNING CURVE
LEARNING CURVELEARNING CURVE
LEARNING CURVE
 
Apparel manufacturing process
Apparel manufacturing processApparel manufacturing process
Apparel manufacturing process
 

Similar to assembly line balancing

assemblysystemslinebalance-130718104948-phpapp02.pdf
assemblysystemslinebalance-130718104948-phpapp02.pdfassemblysystemslinebalance-130718104948-phpapp02.pdf
assemblysystemslinebalance-130718104948-phpapp02.pdf
AshokPhotography
 
Industrial engineeering pli
Industrial engineeering   pliIndustrial engineeering   pli
Industrial engineeering pli
Dhyey Shukla
 
final Line balancing slide12.ppt
final Line balancing slide12.pptfinal Line balancing slide12.ppt
final Line balancing slide12.ppt
xicohos114
 
Work Process Analysis of 4-170 Pizoelectric accelerometer at CECVP Project W...
Work Process Analysis of  4-170 Pizoelectric accelerometer at CECVP Project W...Work Process Analysis of  4-170 Pizoelectric accelerometer at CECVP Project W...
Work Process Analysis of 4-170 Pizoelectric accelerometer at CECVP Project W...Joseph Uken
 
Chapter 6-Scheduling in Industrial of Engineering
Chapter 6-Scheduling in Industrial of EngineeringChapter 6-Scheduling in Industrial of Engineering
Chapter 6-Scheduling in Industrial of Engineering
FaizAzmy2
 
IRJET- Integration of Job Release Policies and Job Scheduling Policies in...
IRJET-  	  Integration of Job Release Policies and Job Scheduling Policies in...IRJET-  	  Integration of Job Release Policies and Job Scheduling Policies in...
IRJET- Integration of Job Release Policies and Job Scheduling Policies in...
IRJET Journal
 
Manual Assembly Lines
Manual Assembly LinesManual Assembly Lines
Manual Assembly Lines
VADLAJAGADEESHWARAAC
 
Operations scheduling
Operations schedulingOperations scheduling
Operations scheduling
RajThakuri
 
Layout planning
Layout planningLayout planning
Layout planning8979473684
 
Chapter 2 line_balancing no pics
Chapter 2 line_balancing no picsChapter 2 line_balancing no pics
Chapter 2 line_balancing no picsNirav Jadav
 
Compensator Design for Speed Control of DC Motor by Root Locus Approach using...
Compensator Design for Speed Control of DC Motor by Root Locus Approach using...Compensator Design for Speed Control of DC Motor by Root Locus Approach using...
Compensator Design for Speed Control of DC Motor by Root Locus Approach using...
IRJET Journal
 
Balancing the line by using heuristic method based on cpm in salbp –a case study
Balancing the line by using heuristic method based on cpm in salbp –a case studyBalancing the line by using heuristic method based on cpm in salbp –a case study
Balancing the line by using heuristic method based on cpm in salbp –a case study
eSAT Journals
 
Clock driven scheduling
Clock driven schedulingClock driven scheduling
Clock driven scheduling
Kamal Acharya
 
unit-4-4Operations Planning and Control-Scheduling.ppt
unit-4-4Operations Planning and Control-Scheduling.pptunit-4-4Operations Planning and Control-Scheduling.ppt
unit-4-4Operations Planning and Control-Scheduling.ppt
almazwmbashira
 
Spry Scheduling and Haulage model - Tutorial
Spry Scheduling and Haulage model - TutorialSpry Scheduling and Haulage model - Tutorial
Spry Scheduling and Haulage model - Tutorial
VR M
 
Benchmark methods to analyze embedded processors and systems
Benchmark methods to analyze embedded processors and systemsBenchmark methods to analyze embedded processors and systems
Benchmark methods to analyze embedded processors and systems
XMOS
 
79971255-assembly-line-balancing-130223195412-phpapp02.pdf
79971255-assembly-line-balancing-130223195412-phpapp02.pdf79971255-assembly-line-balancing-130223195412-phpapp02.pdf
79971255-assembly-line-balancing-130223195412-phpapp02.pdf
Robin8015873726
 
Production & Operation Management Chapter33[1]
Production & Operation Management Chapter33[1]Production & Operation Management Chapter33[1]
Production & Operation Management Chapter33[1]
Hariharan Ponnusamy
 
ROBOT CYCLE TIME ANALYSIS
ROBOT CYCLE TIME ANALYSISROBOT CYCLE TIME ANALYSIS
ROBOT CYCLE TIME ANALYSIS
nirmal304
 
Case Study for Plant Layout :: A modern analysis
Case Study for Plant Layout :: A modern analysisCase Study for Plant Layout :: A modern analysis
Case Study for Plant Layout :: A modern analysis
Sarang Bhutada
 

Similar to assembly line balancing (20)

assemblysystemslinebalance-130718104948-phpapp02.pdf
assemblysystemslinebalance-130718104948-phpapp02.pdfassemblysystemslinebalance-130718104948-phpapp02.pdf
assemblysystemslinebalance-130718104948-phpapp02.pdf
 
Industrial engineeering pli
Industrial engineeering   pliIndustrial engineeering   pli
Industrial engineeering pli
 
final Line balancing slide12.ppt
final Line balancing slide12.pptfinal Line balancing slide12.ppt
final Line balancing slide12.ppt
 
Work Process Analysis of 4-170 Pizoelectric accelerometer at CECVP Project W...
Work Process Analysis of  4-170 Pizoelectric accelerometer at CECVP Project W...Work Process Analysis of  4-170 Pizoelectric accelerometer at CECVP Project W...
Work Process Analysis of 4-170 Pizoelectric accelerometer at CECVP Project W...
 
Chapter 6-Scheduling in Industrial of Engineering
Chapter 6-Scheduling in Industrial of EngineeringChapter 6-Scheduling in Industrial of Engineering
Chapter 6-Scheduling in Industrial of Engineering
 
IRJET- Integration of Job Release Policies and Job Scheduling Policies in...
IRJET-  	  Integration of Job Release Policies and Job Scheduling Policies in...IRJET-  	  Integration of Job Release Policies and Job Scheduling Policies in...
IRJET- Integration of Job Release Policies and Job Scheduling Policies in...
 
Manual Assembly Lines
Manual Assembly LinesManual Assembly Lines
Manual Assembly Lines
 
Operations scheduling
Operations schedulingOperations scheduling
Operations scheduling
 
Layout planning
Layout planningLayout planning
Layout planning
 
Chapter 2 line_balancing no pics
Chapter 2 line_balancing no picsChapter 2 line_balancing no pics
Chapter 2 line_balancing no pics
 
Compensator Design for Speed Control of DC Motor by Root Locus Approach using...
Compensator Design for Speed Control of DC Motor by Root Locus Approach using...Compensator Design for Speed Control of DC Motor by Root Locus Approach using...
Compensator Design for Speed Control of DC Motor by Root Locus Approach using...
 
Balancing the line by using heuristic method based on cpm in salbp –a case study
Balancing the line by using heuristic method based on cpm in salbp –a case studyBalancing the line by using heuristic method based on cpm in salbp –a case study
Balancing the line by using heuristic method based on cpm in salbp –a case study
 
Clock driven scheduling
Clock driven schedulingClock driven scheduling
Clock driven scheduling
 
unit-4-4Operations Planning and Control-Scheduling.ppt
unit-4-4Operations Planning and Control-Scheduling.pptunit-4-4Operations Planning and Control-Scheduling.ppt
unit-4-4Operations Planning and Control-Scheduling.ppt
 
Spry Scheduling and Haulage model - Tutorial
Spry Scheduling and Haulage model - TutorialSpry Scheduling and Haulage model - Tutorial
Spry Scheduling and Haulage model - Tutorial
 
Benchmark methods to analyze embedded processors and systems
Benchmark methods to analyze embedded processors and systemsBenchmark methods to analyze embedded processors and systems
Benchmark methods to analyze embedded processors and systems
 
79971255-assembly-line-balancing-130223195412-phpapp02.pdf
79971255-assembly-line-balancing-130223195412-phpapp02.pdf79971255-assembly-line-balancing-130223195412-phpapp02.pdf
79971255-assembly-line-balancing-130223195412-phpapp02.pdf
 
Production & Operation Management Chapter33[1]
Production & Operation Management Chapter33[1]Production & Operation Management Chapter33[1]
Production & Operation Management Chapter33[1]
 
ROBOT CYCLE TIME ANALYSIS
ROBOT CYCLE TIME ANALYSISROBOT CYCLE TIME ANALYSIS
ROBOT CYCLE TIME ANALYSIS
 
Case Study for Plant Layout :: A modern analysis
Case Study for Plant Layout :: A modern analysisCase Study for Plant Layout :: A modern analysis
Case Study for Plant Layout :: A modern analysis
 

Recently uploaded

Designing Great Products: The Power of Design and Leadership by Chief Designe...
Designing Great Products: The Power of Design and Leadership by Chief Designe...Designing Great Products: The Power of Design and Leadership by Chief Designe...
Designing Great Products: The Power of Design and Leadership by Chief Designe...
Product School
 
Connector Corner: Automate dynamic content and events by pushing a button
Connector Corner: Automate dynamic content and events by pushing a buttonConnector Corner: Automate dynamic content and events by pushing a button
Connector Corner: Automate dynamic content and events by pushing a button
DianaGray10
 
Transcript: Selling digital books in 2024: Insights from industry leaders - T...
Transcript: Selling digital books in 2024: Insights from industry leaders - T...Transcript: Selling digital books in 2024: Insights from industry leaders - T...
Transcript: Selling digital books in 2024: Insights from industry leaders - T...
BookNet Canada
 
UiPath Test Automation using UiPath Test Suite series, part 3
UiPath Test Automation using UiPath Test Suite series, part 3UiPath Test Automation using UiPath Test Suite series, part 3
UiPath Test Automation using UiPath Test Suite series, part 3
DianaGray10
 
JMeter webinar - integration with InfluxDB and Grafana
JMeter webinar - integration with InfluxDB and GrafanaJMeter webinar - integration with InfluxDB and Grafana
JMeter webinar - integration with InfluxDB and Grafana
RTTS
 
From Daily Decisions to Bottom Line: Connecting Product Work to Revenue by VP...
From Daily Decisions to Bottom Line: Connecting Product Work to Revenue by VP...From Daily Decisions to Bottom Line: Connecting Product Work to Revenue by VP...
From Daily Decisions to Bottom Line: Connecting Product Work to Revenue by VP...
Product School
 
The Art of the Pitch: WordPress Relationships and Sales
The Art of the Pitch: WordPress Relationships and SalesThe Art of the Pitch: WordPress Relationships and Sales
The Art of the Pitch: WordPress Relationships and Sales
Laura Byrne
 
LF Energy Webinar: Electrical Grid Modelling and Simulation Through PowSyBl -...
LF Energy Webinar: Electrical Grid Modelling and Simulation Through PowSyBl -...LF Energy Webinar: Electrical Grid Modelling and Simulation Through PowSyBl -...
LF Energy Webinar: Electrical Grid Modelling and Simulation Through PowSyBl -...
DanBrown980551
 
GraphRAG is All You need? LLM & Knowledge Graph
GraphRAG is All You need? LLM & Knowledge GraphGraphRAG is All You need? LLM & Knowledge Graph
GraphRAG is All You need? LLM & Knowledge Graph
Guy Korland
 
Leading Change strategies and insights for effective change management pdf 1.pdf
Leading Change strategies and insights for effective change management pdf 1.pdfLeading Change strategies and insights for effective change management pdf 1.pdf
Leading Change strategies and insights for effective change management pdf 1.pdf
OnBoard
 
GDG Cloud Southlake #33: Boule & Rebala: Effective AppSec in SDLC using Deplo...
GDG Cloud Southlake #33: Boule & Rebala: Effective AppSec in SDLC using Deplo...GDG Cloud Southlake #33: Boule & Rebala: Effective AppSec in SDLC using Deplo...
GDG Cloud Southlake #33: Boule & Rebala: Effective AppSec in SDLC using Deplo...
James Anderson
 
Software Delivery At the Speed of AI: Inflectra Invests In AI-Powered Quality
Software Delivery At the Speed of AI: Inflectra Invests In AI-Powered QualitySoftware Delivery At the Speed of AI: Inflectra Invests In AI-Powered Quality
Software Delivery At the Speed of AI: Inflectra Invests In AI-Powered Quality
Inflectra
 
PHP Frameworks: I want to break free (IPC Berlin 2024)
PHP Frameworks: I want to break free (IPC Berlin 2024)PHP Frameworks: I want to break free (IPC Berlin 2024)
PHP Frameworks: I want to break free (IPC Berlin 2024)
Ralf Eggert
 
Key Trends Shaping the Future of Infrastructure.pdf
Key Trends Shaping the Future of Infrastructure.pdfKey Trends Shaping the Future of Infrastructure.pdf
Key Trends Shaping the Future of Infrastructure.pdf
Cheryl Hung
 
FIDO Alliance Osaka Seminar: FIDO Security Aspects.pdf
FIDO Alliance Osaka Seminar: FIDO Security Aspects.pdfFIDO Alliance Osaka Seminar: FIDO Security Aspects.pdf
FIDO Alliance Osaka Seminar: FIDO Security Aspects.pdf
FIDO Alliance
 
IOS-PENTESTING-BEGINNERS-PRACTICAL-GUIDE-.pptx
IOS-PENTESTING-BEGINNERS-PRACTICAL-GUIDE-.pptxIOS-PENTESTING-BEGINNERS-PRACTICAL-GUIDE-.pptx
IOS-PENTESTING-BEGINNERS-PRACTICAL-GUIDE-.pptx
Abida Shariff
 
FIDO Alliance Osaka Seminar: Overview.pdf
FIDO Alliance Osaka Seminar: Overview.pdfFIDO Alliance Osaka Seminar: Overview.pdf
FIDO Alliance Osaka Seminar: Overview.pdf
FIDO Alliance
 
How world-class product teams are winning in the AI era by CEO and Founder, P...
How world-class product teams are winning in the AI era by CEO and Founder, P...How world-class product teams are winning in the AI era by CEO and Founder, P...
How world-class product teams are winning in the AI era by CEO and Founder, P...
Product School
 
State of ICS and IoT Cyber Threat Landscape Report 2024 preview
State of ICS and IoT Cyber Threat Landscape Report 2024 previewState of ICS and IoT Cyber Threat Landscape Report 2024 preview
State of ICS and IoT Cyber Threat Landscape Report 2024 preview
Prayukth K V
 
DevOps and Testing slides at DASA Connect
DevOps and Testing slides at DASA ConnectDevOps and Testing slides at DASA Connect
DevOps and Testing slides at DASA Connect
Kari Kakkonen
 

Recently uploaded (20)

Designing Great Products: The Power of Design and Leadership by Chief Designe...
Designing Great Products: The Power of Design and Leadership by Chief Designe...Designing Great Products: The Power of Design and Leadership by Chief Designe...
Designing Great Products: The Power of Design and Leadership by Chief Designe...
 
Connector Corner: Automate dynamic content and events by pushing a button
Connector Corner: Automate dynamic content and events by pushing a buttonConnector Corner: Automate dynamic content and events by pushing a button
Connector Corner: Automate dynamic content and events by pushing a button
 
Transcript: Selling digital books in 2024: Insights from industry leaders - T...
Transcript: Selling digital books in 2024: Insights from industry leaders - T...Transcript: Selling digital books in 2024: Insights from industry leaders - T...
Transcript: Selling digital books in 2024: Insights from industry leaders - T...
 
UiPath Test Automation using UiPath Test Suite series, part 3
UiPath Test Automation using UiPath Test Suite series, part 3UiPath Test Automation using UiPath Test Suite series, part 3
UiPath Test Automation using UiPath Test Suite series, part 3
 
JMeter webinar - integration with InfluxDB and Grafana
JMeter webinar - integration with InfluxDB and GrafanaJMeter webinar - integration with InfluxDB and Grafana
JMeter webinar - integration with InfluxDB and Grafana
 
From Daily Decisions to Bottom Line: Connecting Product Work to Revenue by VP...
From Daily Decisions to Bottom Line: Connecting Product Work to Revenue by VP...From Daily Decisions to Bottom Line: Connecting Product Work to Revenue by VP...
From Daily Decisions to Bottom Line: Connecting Product Work to Revenue by VP...
 
The Art of the Pitch: WordPress Relationships and Sales
The Art of the Pitch: WordPress Relationships and SalesThe Art of the Pitch: WordPress Relationships and Sales
The Art of the Pitch: WordPress Relationships and Sales
 
LF Energy Webinar: Electrical Grid Modelling and Simulation Through PowSyBl -...
LF Energy Webinar: Electrical Grid Modelling and Simulation Through PowSyBl -...LF Energy Webinar: Electrical Grid Modelling and Simulation Through PowSyBl -...
LF Energy Webinar: Electrical Grid Modelling and Simulation Through PowSyBl -...
 
GraphRAG is All You need? LLM & Knowledge Graph
GraphRAG is All You need? LLM & Knowledge GraphGraphRAG is All You need? LLM & Knowledge Graph
GraphRAG is All You need? LLM & Knowledge Graph
 
Leading Change strategies and insights for effective change management pdf 1.pdf
Leading Change strategies and insights for effective change management pdf 1.pdfLeading Change strategies and insights for effective change management pdf 1.pdf
Leading Change strategies and insights for effective change management pdf 1.pdf
 
GDG Cloud Southlake #33: Boule & Rebala: Effective AppSec in SDLC using Deplo...
GDG Cloud Southlake #33: Boule & Rebala: Effective AppSec in SDLC using Deplo...GDG Cloud Southlake #33: Boule & Rebala: Effective AppSec in SDLC using Deplo...
GDG Cloud Southlake #33: Boule & Rebala: Effective AppSec in SDLC using Deplo...
 
Software Delivery At the Speed of AI: Inflectra Invests In AI-Powered Quality
Software Delivery At the Speed of AI: Inflectra Invests In AI-Powered QualitySoftware Delivery At the Speed of AI: Inflectra Invests In AI-Powered Quality
Software Delivery At the Speed of AI: Inflectra Invests In AI-Powered Quality
 
PHP Frameworks: I want to break free (IPC Berlin 2024)
PHP Frameworks: I want to break free (IPC Berlin 2024)PHP Frameworks: I want to break free (IPC Berlin 2024)
PHP Frameworks: I want to break free (IPC Berlin 2024)
 
Key Trends Shaping the Future of Infrastructure.pdf
Key Trends Shaping the Future of Infrastructure.pdfKey Trends Shaping the Future of Infrastructure.pdf
Key Trends Shaping the Future of Infrastructure.pdf
 
FIDO Alliance Osaka Seminar: FIDO Security Aspects.pdf
FIDO Alliance Osaka Seminar: FIDO Security Aspects.pdfFIDO Alliance Osaka Seminar: FIDO Security Aspects.pdf
FIDO Alliance Osaka Seminar: FIDO Security Aspects.pdf
 
IOS-PENTESTING-BEGINNERS-PRACTICAL-GUIDE-.pptx
IOS-PENTESTING-BEGINNERS-PRACTICAL-GUIDE-.pptxIOS-PENTESTING-BEGINNERS-PRACTICAL-GUIDE-.pptx
IOS-PENTESTING-BEGINNERS-PRACTICAL-GUIDE-.pptx
 
FIDO Alliance Osaka Seminar: Overview.pdf
FIDO Alliance Osaka Seminar: Overview.pdfFIDO Alliance Osaka Seminar: Overview.pdf
FIDO Alliance Osaka Seminar: Overview.pdf
 
How world-class product teams are winning in the AI era by CEO and Founder, P...
How world-class product teams are winning in the AI era by CEO and Founder, P...How world-class product teams are winning in the AI era by CEO and Founder, P...
How world-class product teams are winning in the AI era by CEO and Founder, P...
 
State of ICS and IoT Cyber Threat Landscape Report 2024 preview
State of ICS and IoT Cyber Threat Landscape Report 2024 previewState of ICS and IoT Cyber Threat Landscape Report 2024 preview
State of ICS and IoT Cyber Threat Landscape Report 2024 preview
 
DevOps and Testing slides at DASA Connect
DevOps and Testing slides at DASA ConnectDevOps and Testing slides at DASA Connect
DevOps and Testing slides at DASA Connect
 

assembly line balancing

  • 2. What is Line Balancing ??  Assigning each task to a work within an assembly line in order to meet the required production rate and to achieve a minimum amount of idle time.  Line balancing is the procedure in which tasks along the assembly line are assigned to work station so each line has approximately same amount of work.
  • 3. Terms Defined  Delay/idle time of a workstation: the difference between the cycle time (CT) and the station time (ST).  Cycle time (CT): the time between the completion of 2 successive assemblies, assumed constant for all assemblies for a given conveyor speed.
  • 4. Terms Defined (Cont.)  Line efficiency (LE): the ratio of total station time to the cycle time multiplied by the number of workstations  Balance Delay  Balance Delay  Work element: a part of the total work content in an assembly process.
  • 5. Terms Defined (Cont.)  Smoothness index (SI): an index to indicate the relative smoothness of a given assembly line balance. A smoothness index of zero indicates a perfect balance  Workstation (WS): a location on the assembly line where a work element or elements are performed on the product.
  • 6. Precedence Constraint  Precedence Constraint is a restriction on the order of execution of work elements.  There are two conditions taht usually appear in assembling process: 1. There is no dependency of the components in the works 2. If a component has been selected to be assembled, then the sequence begins to assemble other components.
  • 7. Precedence diagram  Precedence diagram: a diagram that describes the ordering in which work elements should be performed. It shows that some jobs cannot be performed unless their predecessors are completed. The layout of workstations along the assembly line depends on the precedence diagram  Presedence diagram symbols: Symbol element Relationship between symbols
  • 9. Zoning Constraint  Allocation of work elements at the work station is also limited by zoning constraints that preclude or require grouping of certain elements of the work on a particular station.
  • 10. Line Balancing Methods  Helgeson dan Birnie / Ranked Positional Weight (RPW)  Kilbridge and Wester Heuristic (Region Approach)  Largest Candidate Rule
  • 11. Helgeson dan Birnie / Ranked Positional Weight (RPW) Step 1- Calculate the weight of the position of each work elements. Step 2- Sort the elements according to the weight of the position of the largest to the smallest. Step 3 -Calculate the cycle time.  4. Place the working element with the greatest weight on all the workstations do not violate precedence relationships and time station does not exceed the cycle time.  5. Repeat step 4 until all the elements are placed.  6. After forming a work station consisting of its elements, then specify the value of efficient, balance delay, and its smoothest index.
  • 12. Kilbridge and Wester Heuristic (Region Approach)  Create precedence diagram of the problems faced. Separate work elements in the diagram in columns from right to left.  2. Determine the cycle time (TC) of primes total time working elements, and specify the number of work stations.  3. Place the work elements to work stations such that the total time working element does not exceed the cycle time. Remove elements of work that has been placed on the list of work elements.  4. When an element of work placement resulted in a total time of work elements exceeds the cycle time working elements are placed in the next work station.  5. Repeat steps 3 and 4 until all work elements are placed.  6. Determine the value of efficient, balance delay, and smoothness index
  • 13. Largest Candidate Rule  The basic principle is to combine the processes of sorting operation on the basis of the largest processing time to the smallest elements of the operating time  Steps: 1. Starting from the top, select the element to be assigned to the first station, which meets the requirements of precedence and does not cause the total amount exceeds Tek on stretcher station Ts. 2. If there are no other elements that can be assigned without exceeding Ts, then move on to the next station. 3. Repeat steps 1 and 2 for the other stations until the completion of all elements assigned. 4. Determine the value of efficient, balance delay, its smoothness index.