SlideShare a Scribd company logo
Example of Assembly-Line Balancing

       Problem: An Assembly consists of the following elements as given in table below.


   Task          A         B     C     D        E   F         G         H   I       J         K       L

   Immediate Nil           A     B     B        B   B         C,D       G   E       I,F       H,J     K
   Predecessor
   Task Time   12          6     6     2        2   12        7         5   1       4         6       7




       The production rate required is one assembly every 15 minute. Determine the
       minimum no of workstations required so as to minimize the Balance- Delay. Find
       Balance Delay Station-wise.



STEP 1. List the sequential relationships among tasks and then draw a precedence diagram


                                                                            5 min
                                                        7min
                               6 min                                                                         7 min.
                                                                                H
                                                         G
                                                                                              6 min
                                                         s                                                      L
                                C
                                                         e
                                                         c.                               K
                                       2 min

    12 min.                                 D
               6 min                                              1 min
      A                B
                                           2 min                                                    4 min.
                                                                    I                     J

                                            E


                                           12 min


                                            F
STEP 2. . Calculate the required workstation cycle time

Cycle time is already glready given as so no need to calculate

CYCLE TIME = (PRODUCTION TIME PER DAY) /(OUTPUT PER DAY) = 15 minutes



STEP 3. Calculate the theoretical minimum number of workstations.

NUMBER OF WORK STATIONS = ( SUM OF TOTAL TASK TIMES) / (CYCLE TIME)

= 70 min’s / 15 min’s

                = 4.67 ≈5 (rounded)



                      Number of
     Task           Following Tasks
                                       STEP 4.Choose a primary rule that will determine how
      A                   11           tasks are to be assigned to workstations

      B                   10                For this example, our primary rule is to prioritize
                                       tasks based on the largest number of following tasks.
  C or D or E             4                 If there is a tie, our secondary rule is to prioritize
                                       tasks in the order of the longest task time.
   I,F or G               3                 In general, select rules that prioritize tasks
                                       according to the largest number of followers or based on
    H or J                2            length of time.
      K                   1

       L                  0




STEP 5. Beginning with the first workstation, assign each task, one at a time, until the sum of
the task times is equal to the workstation cycle time or until no other tasks can be assigned
due to sequence or time restrictions.
STEP 6. Repeat step 5 for the remaining workstations until all the tasks have been assigned to
     a workstation

     STEP 7.Evaluate the efficiency of the line balance.

     EFFICIENCY = (SUM OF ALL TASK TIMES))/(ACTUAL NO OF WORKSTATIONS)X(CYCLE TIME)

     = (70) / (6) X (15)

     = 0.778 OR 77. 78 %



     STEPS 5& 6. Balance made according to the Largest-Number-of-Following Tasks Rule.


Stations    Task    Task Time       Number of      Remaining     Feasible        Task with    Task with
                    (in minutes)    Following      Unassigned    Remaining       Most         Longest
                                    Tasks          Time          Tasks           Followers    Operating
                                                   (Balance-                                  Time
                                                   Delay)
Station 1     A            12            11           3 IDLE         None

Station 2     B            6             10              9           C,D,E         C,D,E          C
              C            6             4               3            D,E           D,E          D ,E
              D            2             4            1 IDLE         None


Station 3     E            2              4             13           F,I, G        F,I,G              F
              F            12             3              1              I
              I            1              3           0 IDLE         None

Station 4     G            7              3              8            H, J          H, J              H
              H            5              2           3 IDLE         None


Station 5     J            4              2             11            K
              K            6              1           5 IDLE         None



Station 6     L            7              0           8 IDLE         None

More Related Content

What's hot

8. chapter 7 work study (time and motion study)
8. chapter 7   work study (time and motion study)8. chapter 7   work study (time and motion study)
8. chapter 7 work study (time and motion study)
sundar sivam
 
Line balancing & EOQ
Line balancing & EOQLine balancing & EOQ
Assembly line balancing
Assembly line balancingAssembly line balancing
Assembly line balancing
shady anwer
 
Ranked Positional Weight Method | Management
Ranked Positional Weight Method | ManagementRanked Positional Weight Method | Management
Ranked Positional Weight Method | Management
Transweb Global Inc
 
cycle time, normal time and standard allowance
cycle time, normal time and standard allowancecycle time, normal time and standard allowance
cycle time, normal time and standard allowancePratibha Khemchandani
 
Performance rating
Performance ratingPerformance rating
Performance rating
Shivam Kumar
 
Cellular LayOut
Cellular LayOutCellular LayOut
Cellular LayOut
Fahad Ali
 
Centre of gravity method of location planning
Centre of gravity method of location planningCentre of gravity method of location planning
Centre of gravity method of location planningGaganjot Kaur
 
Man and machine chart
Man and machine chartMan and machine chart
Time And Motion Study
Time And  Motion  StudyTime And  Motion  Study
Time And Motion Study
ahmad bassiouny
 
PPT ON Just in time technique (JIT)
PPT ON Just in time technique (JIT)PPT ON Just in time technique (JIT)
Types of loading, production & operations management
Types of loading, production & operations managementTypes of loading, production & operations management
Types of loading, production & operations management
Mahima Mutnuru
 
Process layout
Process layoutProcess layout
Process layout
no
 
JIT
JITJIT
Production and Operation Management
Production and Operation ManagementProduction and Operation Management
Production and Operation Management
Jo Balucanag - Bitonio
 
Operation Process
Operation ProcessOperation Process
Operation Process
Dr. Prashant Kalaskar
 

What's hot (20)

8. chapter 7 work study (time and motion study)
8. chapter 7   work study (time and motion study)8. chapter 7   work study (time and motion study)
8. chapter 7 work study (time and motion study)
 
Line balancing & EOQ
Line balancing & EOQLine balancing & EOQ
Line balancing & EOQ
 
Assembly line balancing
Assembly line balancingAssembly line balancing
Assembly line balancing
 
Work sample
Work sampleWork sample
Work sample
 
Ranked Positional Weight Method | Management
Ranked Positional Weight Method | ManagementRanked Positional Weight Method | Management
Ranked Positional Weight Method | Management
 
cycle time, normal time and standard allowance
cycle time, normal time and standard allowancecycle time, normal time and standard allowance
cycle time, normal time and standard allowance
 
Operation management problems
Operation management problemsOperation management problems
Operation management problems
 
Performance rating
Performance ratingPerformance rating
Performance rating
 
assembly line balancing
assembly line balancingassembly line balancing
assembly line balancing
 
Toyota production system
Toyota production systemToyota production system
Toyota production system
 
Cellular LayOut
Cellular LayOutCellular LayOut
Cellular LayOut
 
Centre of gravity method of location planning
Centre of gravity method of location planningCentre of gravity method of location planning
Centre of gravity method of location planning
 
Man and machine chart
Man and machine chartMan and machine chart
Man and machine chart
 
Time And Motion Study
Time And  Motion  StudyTime And  Motion  Study
Time And Motion Study
 
PPT ON Just in time technique (JIT)
PPT ON Just in time technique (JIT)PPT ON Just in time technique (JIT)
PPT ON Just in time technique (JIT)
 
Types of loading, production & operations management
Types of loading, production & operations managementTypes of loading, production & operations management
Types of loading, production & operations management
 
Process layout
Process layoutProcess layout
Process layout
 
JIT
JITJIT
JIT
 
Production and Operation Management
Production and Operation ManagementProduction and Operation Management
Production and Operation Management
 
Operation Process
Operation ProcessOperation Process
Operation Process
 

Viewers also liked

An Introduction to Operations Management
An Introduction to Operations ManagementAn Introduction to Operations Management
An Introduction to Operations Management
Christian Reinboth
 
Sales & Operations Planning Process
Sales & Operations Planning ProcessSales & Operations Planning Process
Sales & Operations Planning Process
Harshal Badgujar
 
Measurement System Analysis
Measurement System AnalysisMeasurement System Analysis
Measurement System Analysis
Ronald Shewchuk
 
Reverse engineering
Reverse engineeringReverse engineering
Reverse engineering
Hicube Infosec
 
Reverse Engineering of Software Architecture
Reverse Engineering of Software ArchitectureReverse Engineering of Software Architecture
Reverse Engineering of Software ArchitectureDharmalingam Ganesan
 
Legacy Software Maintenance And Management
Legacy Software Maintenance And ManagementLegacy Software Maintenance And Management
Legacy Software Maintenance And Management
ValueCoders
 
Service Operation - Manajemen Layanan Teknologi Informasi
Service Operation - Manajemen Layanan Teknologi InformasiService Operation - Manajemen Layanan Teknologi Informasi
Service Operation - Manajemen Layanan Teknologi Informasi
Muhammad Idil Haq Amir
 
Unit 1 Service Operations Management
Unit 1 Service Operations ManagementUnit 1 Service Operations Management
Unit 1 Service Operations Management
Gopinath Guru
 
Measuring capacity lesson3
Measuring capacity lesson3Measuring capacity lesson3
Measuring capacity lesson3
Lidia Marie
 
Reverse engineering
Reverse engineeringReverse engineering
Reverse engineering
Daniel Stenberg
 
Software reverse engineering
Software reverse engineeringSoftware reverse engineering
Software reverse engineering
Parminder Singh
 
Reverse engineering
Reverse engineeringReverse engineering
Reverse engineeringSaswat Padhi
 
reverse engineering
reverse engineeringreverse engineering
reverse engineering
ayush_nitt
 
Reverse Engineering
Reverse EngineeringReverse Engineering
Reverse Engineeringsiddu019
 
intra and inter personal relations
intra and inter personal relationsintra and inter personal relations
intra and inter personal relations
Ganesh Sahu
 
Maintenance, Re-engineering &Reverse Engineering in Software Engineering
Maintenance,Re-engineering &Reverse Engineering in Software EngineeringMaintenance,Re-engineering &Reverse Engineering in Software Engineering
Maintenance, Re-engineering &Reverse Engineering in Software Engineering
Manish Kumar
 
Tools for capacity planning, measurement of capacity, capacity planning process
Tools for capacity planning, measurement of capacity, capacity planning processTools for capacity planning, measurement of capacity, capacity planning process
Tools for capacity planning, measurement of capacity, capacity planning process
Rohan Monis
 

Viewers also liked (20)

Line Balancing
Line BalancingLine Balancing
Line Balancing
 
An Introduction to Operations Management
An Introduction to Operations ManagementAn Introduction to Operations Management
An Introduction to Operations Management
 
Sales & Operations Planning Process
Sales & Operations Planning ProcessSales & Operations Planning Process
Sales & Operations Planning Process
 
Measurement System Analysis
Measurement System AnalysisMeasurement System Analysis
Measurement System Analysis
 
Reverse engineering
Reverse engineeringReverse engineering
Reverse engineering
 
Capacity 1
Capacity 1Capacity 1
Capacity 1
 
Line balancing
Line balancing Line balancing
Line balancing
 
Reverse Engineering of Software Architecture
Reverse Engineering of Software ArchitectureReverse Engineering of Software Architecture
Reverse Engineering of Software Architecture
 
Legacy Software Maintenance And Management
Legacy Software Maintenance And ManagementLegacy Software Maintenance And Management
Legacy Software Maintenance And Management
 
Service Operation - Manajemen Layanan Teknologi Informasi
Service Operation - Manajemen Layanan Teknologi InformasiService Operation - Manajemen Layanan Teknologi Informasi
Service Operation - Manajemen Layanan Teknologi Informasi
 
Unit 1 Service Operations Management
Unit 1 Service Operations ManagementUnit 1 Service Operations Management
Unit 1 Service Operations Management
 
Measuring capacity lesson3
Measuring capacity lesson3Measuring capacity lesson3
Measuring capacity lesson3
 
Reverse engineering
Reverse engineeringReverse engineering
Reverse engineering
 
Software reverse engineering
Software reverse engineeringSoftware reverse engineering
Software reverse engineering
 
Reverse engineering
Reverse engineeringReverse engineering
Reverse engineering
 
reverse engineering
reverse engineeringreverse engineering
reverse engineering
 
Reverse Engineering
Reverse EngineeringReverse Engineering
Reverse Engineering
 
intra and inter personal relations
intra and inter personal relationsintra and inter personal relations
intra and inter personal relations
 
Maintenance, Re-engineering &Reverse Engineering in Software Engineering
Maintenance,Re-engineering &Reverse Engineering in Software EngineeringMaintenance,Re-engineering &Reverse Engineering in Software Engineering
Maintenance, Re-engineering &Reverse Engineering in Software Engineering
 
Tools for capacity planning, measurement of capacity, capacity planning process
Tools for capacity planning, measurement of capacity, capacity planning processTools for capacity planning, measurement of capacity, capacity planning process
Tools for capacity planning, measurement of capacity, capacity planning process
 

More from Joseph Konnully

Workshop Practice manual 2016
 Workshop Practice manual 2016  Workshop Practice manual 2016
Workshop Practice manual 2016
Joseph Konnully
 
Worksampling
WorksamplingWorksampling
Worksampling
Joseph Konnully
 
Work study work measurement
Work study   work measurementWork study   work measurement
Work study work measurement
Joseph Konnully
 
Work Study- Methods Study
Work Study- Methods StudyWork Study- Methods Study
Work Study- Methods Study
Joseph Konnully
 
Plantlocationandlayoutplanning
PlantlocationandlayoutplanningPlantlocationandlayoutplanning
Plantlocationandlayoutplanning
Joseph Konnully
 
Plant location
Plant locationPlant location
Plant location
Joseph Konnully
 
Prniciples of Management
Prniciples   of  ManagementPrniciples   of  Management
Prniciples of Management
Joseph Konnully
 
Functionsofmanagement
FunctionsofmanagementFunctionsofmanagement
Functionsofmanagement
Joseph Konnully
 
Organisation - organisation structures
Organisation - organisation structuresOrganisation - organisation structures
Organisation - organisation structures
Joseph Konnully
 
Formsof businessorg
Formsof businessorgFormsof businessorg
Formsof businessorg
Joseph Konnully
 
Ddb29 ccceba547209ddab45a17330016
Ddb29 ccceba547209ddab45a17330016Ddb29 ccceba547209ddab45a17330016
Ddb29 ccceba547209ddab45a17330016Joseph Konnully
 
403 e86280b994e71948f9e0c1b385947
403 e86280b994e71948f9e0c1b385947403 e86280b994e71948f9e0c1b385947
403 e86280b994e71948f9e0c1b385947Joseph Konnully
 
Work Study Part- I
Work Study Part- IWork Study Part- I
Work Study Part- I
Joseph Konnully
 
Simplex method - Maximisation Case
Simplex method - Maximisation CaseSimplex method - Maximisation Case
Simplex method - Maximisation CaseJoseph Konnully
 
Linear programming - Model formulation, Graphical Method
Linear programming  - Model formulation, Graphical MethodLinear programming  - Model formulation, Graphical Method
Linear programming - Model formulation, Graphical MethodJoseph Konnully
 
Operations research - an overview
Operations research -  an overviewOperations research -  an overview
Operations research - an overview
Joseph Konnully
 
Aggregate Planning Problem
Aggregate Planning ProblemAggregate Planning Problem
Aggregate Planning ProblemJoseph Konnully
 
Principles of Motion Economy
Principles of Motion EconomyPrinciples of Motion Economy
Principles of Motion EconomyJoseph Konnully
 
79971255 assembly-line-balancing
79971255 assembly-line-balancing79971255 assembly-line-balancing
79971255 assembly-line-balancing
Joseph Konnully
 

More from Joseph Konnully (20)

Workshop Practice manual 2016
 Workshop Practice manual 2016  Workshop Practice manual 2016
Workshop Practice manual 2016
 
Worksampling
WorksamplingWorksampling
Worksampling
 
Work study work measurement
Work study   work measurementWork study   work measurement
Work study work measurement
 
Work Study- Methods Study
Work Study- Methods StudyWork Study- Methods Study
Work Study- Methods Study
 
Plantlocationandlayoutplanning
PlantlocationandlayoutplanningPlantlocationandlayoutplanning
Plantlocationandlayoutplanning
 
Plant location
Plant locationPlant location
Plant location
 
Prniciples of Management
Prniciples   of  ManagementPrniciples   of  Management
Prniciples of Management
 
Functionsofmanagement
FunctionsofmanagementFunctionsofmanagement
Functionsofmanagement
 
Organisation - organisation structures
Organisation - organisation structuresOrganisation - organisation structures
Organisation - organisation structures
 
Formsof businessorg
Formsof businessorgFormsof businessorg
Formsof businessorg
 
Ddb29 ccceba547209ddab45a17330016
Ddb29 ccceba547209ddab45a17330016Ddb29 ccceba547209ddab45a17330016
Ddb29 ccceba547209ddab45a17330016
 
403 e86280b994e71948f9e0c1b385947
403 e86280b994e71948f9e0c1b385947403 e86280b994e71948f9e0c1b385947
403 e86280b994e71948f9e0c1b385947
 
Work Study Part- I
Work Study Part- IWork Study Part- I
Work Study Part- I
 
Simplex method - Maximisation Case
Simplex method - Maximisation CaseSimplex method - Maximisation Case
Simplex method - Maximisation Case
 
Linear programming - Model formulation, Graphical Method
Linear programming  - Model formulation, Graphical MethodLinear programming  - Model formulation, Graphical Method
Linear programming - Model formulation, Graphical Method
 
Operations research - an overview
Operations research -  an overviewOperations research -  an overview
Operations research - an overview
 
Aggregate Planning Problem
Aggregate Planning ProblemAggregate Planning Problem
Aggregate Planning Problem
 
Mechanical Technology
Mechanical TechnologyMechanical Technology
Mechanical Technology
 
Principles of Motion Economy
Principles of Motion EconomyPrinciples of Motion Economy
Principles of Motion Economy
 
79971255 assembly-line-balancing
79971255 assembly-line-balancing79971255 assembly-line-balancing
79971255 assembly-line-balancing
 

Assembly Line Balancing -Example

  • 1. Example of Assembly-Line Balancing Problem: An Assembly consists of the following elements as given in table below. Task A B C D E F G H I J K L Immediate Nil A B B B B C,D G E I,F H,J K Predecessor Task Time 12 6 6 2 2 12 7 5 1 4 6 7 The production rate required is one assembly every 15 minute. Determine the minimum no of workstations required so as to minimize the Balance- Delay. Find Balance Delay Station-wise. STEP 1. List the sequential relationships among tasks and then draw a precedence diagram 5 min 7min 6 min 7 min. H G 6 min s L C e c. K 2 min 12 min. D 6 min 1 min A B 2 min 4 min. I J E 12 min F
  • 2. STEP 2. . Calculate the required workstation cycle time Cycle time is already glready given as so no need to calculate CYCLE TIME = (PRODUCTION TIME PER DAY) /(OUTPUT PER DAY) = 15 minutes STEP 3. Calculate the theoretical minimum number of workstations. NUMBER OF WORK STATIONS = ( SUM OF TOTAL TASK TIMES) / (CYCLE TIME) = 70 min’s / 15 min’s = 4.67 ≈5 (rounded) Number of Task Following Tasks STEP 4.Choose a primary rule that will determine how A 11 tasks are to be assigned to workstations B 10  For this example, our primary rule is to prioritize tasks based on the largest number of following tasks. C or D or E 4  If there is a tie, our secondary rule is to prioritize tasks in the order of the longest task time. I,F or G 3  In general, select rules that prioritize tasks according to the largest number of followers or based on H or J 2 length of time. K 1 L 0 STEP 5. Beginning with the first workstation, assign each task, one at a time, until the sum of the task times is equal to the workstation cycle time or until no other tasks can be assigned due to sequence or time restrictions.
  • 3. STEP 6. Repeat step 5 for the remaining workstations until all the tasks have been assigned to a workstation STEP 7.Evaluate the efficiency of the line balance. EFFICIENCY = (SUM OF ALL TASK TIMES))/(ACTUAL NO OF WORKSTATIONS)X(CYCLE TIME) = (70) / (6) X (15) = 0.778 OR 77. 78 % STEPS 5& 6. Balance made according to the Largest-Number-of-Following Tasks Rule. Stations Task Task Time Number of Remaining Feasible Task with Task with (in minutes) Following Unassigned Remaining Most Longest Tasks Time Tasks Followers Operating (Balance- Time Delay) Station 1 A 12 11 3 IDLE None Station 2 B 6 10 9 C,D,E C,D,E C C 6 4 3 D,E D,E D ,E D 2 4 1 IDLE None Station 3 E 2 4 13 F,I, G F,I,G F F 12 3 1 I I 1 3 0 IDLE None Station 4 G 7 3 8 H, J H, J H H 5 2 3 IDLE None Station 5 J 4 2 11 K K 6 1 5 IDLE None Station 6 L 7 0 8 IDLE None