302-DECISION SCIENCE
Unit No.4. Network Analysis
4.15 Case 1: Network Analysis
Presented By:
Dr. V. M. Tidake
Ph. D (Financial Management), MBA(FM), MBA(HRM) BE(Chem)
Dean EDP & Associate Professor MBA
2
Sanjivani College of Engineering, Kopargaon
Department of MBA
www.sanjivanimba.org.in
3. www.sanjivanimba.org.in
At the End of the Session Student will be able to
understand-
A. Case 1: Network Analysis.
Program Evaluation and Review Technique
4. www.sanjivanimba.org.in
The following information is gathered for a project-
1. Draw the Network Diagram,
2. Determine the Critical Path and Project Duration.
3. What is effect on project duration if-
a. D is changed to 6 weeks
b. F is changed to 8 weeks
Activity A B C D E F G H I J
Preceding Activity - A A A D B,C,E D D H F,G,I
Duration (Weeks) 1 3 4 3 2 4 9 5 2 2
Network Analysis
5. www.sanjivanimba.org.in
NETWORK ANALYSIS
a. Rewriting the Precedence Relationship as follows-
Predecessor
Activity
Activity Duration in
Weeks
- A 1
A B 3
A C 4
A D 3
D E 2
B, C, E F 4
D G 9
D H 5
H I 2
F, G, I J 2