The document discusses Program Evaluation and Review Technique (PERT) for a project with 8 activities. It shows the optimistic, most likely, and pessimistic times for each activity. It then calculates the expected time for each activity using PERT formulas. A network diagram is drawn showing the dependencies between activities. The critical path through the network is identified as activities 1-2-4-6-7-8, with an earliest completion time of 32.67 weeks.