SlideShare a Scribd company logo
1 of 49
SAFEASSIGNCHECKTEST - CSU SAFEASSIGN
PLAGIARISM CHECK TOOL
SafeAssign Originality Report Generator I
Odell Kruah
on Fri, Nov 30 2018, 4:44 PM
100% highest match
Submission ID: d0da8619-c56f-4e34-9af1-6edd71018503
Attachments (1)
PROJECT VI.docx
1 ODELL KRUAH PROJECT MANAGEMENT UNIT VI
NOVEMBER 30,
2018
Part 1
1 DEVELOP AN IN-DEPTH SCHEDULE FOR THE PROJECT
YOU
SELECTED AND USED TO DEVELOP THE STATEMENT OF
WORK AND
WORK BREAKDOWN STRUCTURE IN UNIT III. PLEASE
REFER TO
THE INTEGRATED PROJECT IN CHAPTER 10 ON PAGE 363
(PROJECT
SCHEDULING) OF THE TEXTBOOK FOR MORE
INFORMATION. BE
SURE TO INCLUDE THE FOLLOWING COMPONENTS:
· AN ACTIVITY PRECEDENCE DIAGRAM, · AN ACTIVITY
DURATION
TABLE, AND · A NETWORK DIAGRAM AND GANTT
CHARTS.
· AN ACTIVITY PRECEDENCE DIAGRAM:
(http://safeassign.blackboard.com/)
PROJECT VI.docx
Word Count: 862 Attachment ID: 244309330
100%
ACTIVITY DURATION TABLE:
ACTIVITY EXPECTED DURATION PREDECESSOR
A 5 DAYS ----
B 10 DAYS A
C 8 DAYS A
D 1 DAY A
E 5 DAYS B, C
F 10 DAYS D, E
G 14 DAYS F
H 3 DAYS G
I 12 DAYS F
J 6 DAYS H, I
A NETWORK DIAGRAM AND GANTT CHARTS:
A
B
C
D
E
F
G
H
I
J
Part 2
1 PLEASE COMPLETE CASE STUDY 10.1: PROJECT
SCHEDULING AT
BLANQUE CHECK CONSTRUCTION ON PAGE 360 OF THE
TEXTBOOK,
AND ANSWER THE THREE QUESTIONS AT THE END.
Q1(ANS)
PRECEDENCE DIAGRAM:
1 C=DIFFERENT CONSRUCTION TYPES OF SCHEDULING
METHODS
TYPE FROM 1 TO 9 P= DIFFERENT CONSRUCTION
PROJECTS WHICH
SHOW THE TYPES OF SCHEDULING METHODS TYPE
FROM 1 TO 9
O1=ORGANIZATION ONE O2= ORGANIZATION 2
S E C4 C5 O1 P9 P8 O2 P7 P6 P5 P4 P3 P2 C9 C8 C7 C6 C1 C2
C3 P1
Q2(ANS) ACCORDING TO MY RESEARCH LEVEL AND
LITERATURE
REVIEW THE EXPERT OPINION AND PAST HISTORY
BOTH ARE THE
BEST TO SOLVE PROBLEM FOR CALCULATING THE
CRITICAL
PATH ,WHICH MAY ALSO TELL US THE DURATION OR
PROJECT
DELAY TO HANDLE OR RUN OUR CONSTRUCTION
COMPANY.
Q3(ANS) THESE BOTH HAVE SOME STRENGTHENS AND
WEAKNESSES AND BOTH GIVE THE RESULTS PROBABLY
SAME , BUT
ACCORDING TO LITERATURE AOA IS THE BENEFICIAL
FOR
MODELING IT WILL BE HELPFUL AND IN THE BUSINESS
FIELD IT
WILL BE IMPORTANT AON WILL BE LESS WIDELY USED
, IN CASE OF
LARGE AND COMPLEX PROJECTS IT IS EASIER TO
EMPLOY THE
PATH PROCESS USED IN THE AOA. ACCORDING TO AOA
WE
ACHIEVE THE EVERY MILESTONE AND PARTICULARLY
USED THE
DUMMY PROJECTS OR ACTIVITIES THE CONCEPT OF
DUMMY
PROJECT IS NOT SIMPLE AND EASY IT REQUIRE MORE
TRAINING
AND PRACTICE. AON CONVENTION ,AOA NETWORK
USED BOTH
NODES AND ARROW TO LABEL THE PROJECT.
Part 3
1 DEVELOP A NETWORK ACTIVITY CHART, AND
IDENTIFY THE
CRITICAL PATH FOR A PROJECT BASED ON THE
INFORMATION
PROVIDED IN THE GANTT CHART BELOW. DRAW THE
ACTIVITY
NETWORK AS A GANTT CHART. WHAT IS THE EXPECTED
DURATION
OF THE PROJECT?
ACTIVITY EXPECTED DURATION PREDECESSOR
A 5 DAYS ----
B 10 DAYS A
C 8 DAYS A
D 1 DAY A
E 5 DAYS B, C
F 10 DAYS D, E
G 14 DAYS F
H 3 DAYS G
I 12 DAYS F
J 6 DAYS H, I
AN ACTIVITY PRECEDENCE DIAGRAM:
THE TOTAL PATHS CAN BE CALCULATED THERE THE
FIRST
DIAGRAM CAN BE DEFINED THE OVERALL PATHS
WHICH ARE
GIVEN BELOW
ABEFIJ=5+10+5+10+12+6=48
ABEFGHJ=5+10+5+10+14+3+6=53
ACEFIJ=5+8+5+10+12+6=46
ACEFGHJ=5+10+5+10+14+3+6=51
ADFIJ=5+1+10+12+6=34 ADFGHJ=5+1+10+14+3+6=39
Critical path:
1 THE 2ND PATH CAN BE CONSTRUCTED FOR THE
CRITICAL PATH
WHICH HAVE THE LONGEST PATH DURATION
ABEFGHJ=5+10+5+10+14+3+6=53 ITS KNOWN AS A
CRITICAL PATH
FOR THE GIVEN ACTIVITY.
PRECEDENCE DIAGRAM AND CRITICAL PATH
END H J G F E B A A J H G E F I START D C B J END
START END END
Part 4
1 USING THE INFORMATION PROVIDED IN THE GANTT
CHART
BELOW, CONSTRUCT THE PROJECT ACTIVITY NETWORK
USING THE
ACTIVITY-ON-NODE (AON) METHODOLOGY, AND LABEL
EACH
NODE. IDENTIFY THE CRITICAL PATH AND OTHER
PATHS
THROUGH THE NETWORK.
Activity
Duration
Predecessors
A
3
--
B
5
A
C
7
A
D
3
B, C
E
5
B
F
4
D
G
2
C
H
5
1 E, F, G
ACTIVITY DURATION ES EF LS
LF Slack
1 A 3 0 3 0
0 --
1 B 5 3 8 8
13 5
1 C 7 3 10 3
10 --
1 D 3 10 13 13
13 --
1 E 5 8 13 13
17 5
1 F 4 13 17 13
17
1 G 2 10 12 15
17 5
1 H 5 17 22 17
22 --
SOLUTION:
1 1 PART 1:
6
0
3
3
8
8
13
0 A
5 B
10
13
5 E
3 D
1 0 3 0
8 5 13
3 5 17
17
22
1 13 3 13
0 H
END
13
17
3
10
0 F
1 17 5 22
0 C
1 13 4 17
3 7 10
10
12
5 G
LEGEND
1 15 2 17
ES ID EF
SL DISCRIPTION
1 LS DURATION LF
THE CRITICAL PATH CAN BE CHOOSE WHICH HAVE THE
MINIMUM
SLACK AND THEN FIND THE DURATION OR DELAY OF
CRITICAL
PATH FIRST OF ALL WE FIND THE CRITICAL PATH OF
GIVEN
ACTIVITY THE CRITICAL PATH HAVE MINIMUM SLACK
BUT DELAY
SHOULD BE MAXIMUM ,WHICH ARE GIVEN BELOW
ACDFH=3+7+3+4+5=22DAYS/MIN WITH THE CRITICAL
POINT OF
SLACK THE FLEXIBILITY OF THE PROJECT IS LIMITED
G
Citations (1/1)
Matched Text
1 Another student's paper
Suspected Entry: 62% match
Uploaded - PROJECT VI.docx
ODELL KRUAH PROJECT MANAGEMENT
UNIT VI NOVEMBER 30, 2018
Source - Another student's paper
Unit VI Project Odell Kruah Columbia Southern
University 11/18/2018
Suspected Entry: 100% match
Uploaded - PROJECT VI.docx
DEVELOP AN IN-DEPTH SCHEDULE FOR
THE PROJECT YOU SELECTED AND USED
TO DEVELOP THE STATEMENT OF WORK
AND WORK BREAKDOWN STRUCTURE IN
UNIT III
Source - Another student's paper
Develop an in-depth schedule for the project
you selected and used to develop the statement
of work and work breakdown structure in Unit III
Suspected Entry: 100% match
Uploaded - PROJECT VI.docx
PLEASE REFER TO THE INTEGRATED
PROJECT IN CHAPTER 10 ON PAGE 363
(PROJECT SCHEDULING) OF THE
TEXTBOOK FOR MORE INFORMATION
Source - Another student's paper
Please refer to the Integrated Project in Chapter
10 on page 363 (Project Scheduling) of the
textbook for more information
Suspected Entry: 100% match
Uploaded - PROJECT VI.docx
BE SURE TO INCLUDE THE FOLLOWING
COMPONENTS
Source - Another student's paper
Be sure to include the following components
Suspected Entry: 100% match
Uploaded - PROJECT VI.docx
· AN ACTIVITY PRECEDENCE DIAGRAM, ·
AN ACTIVITY DURATION TABLE, AND · A
NETWORK DIAGRAM AND GANTT CHARTS
Source - Another student's paper
· an activity precedence diagram, · an activity
duration table, and · a network diagram and
Gantt charts
Suspected Entry: 100% match
Uploaded - PROJECT VI.docx
· AN ACTIVITY PRECEDENCE DIAGRAM
Source - Another student's paper
· An activity precedence diagram
Suspected Entry: 100% match
Uploaded - PROJECT VI.docx
ACTIVITY DURATION TABLE
Source - Another student's paper
Activity duration table
Suspected Entry: 100% match
Uploaded - PROJECT VI.docx
ACTIVITY EXPECTED DURATION
PREDECESSOR
Source - Another student's paper
Activity Expected Duration Predecessor
Suspected Entry: 100% match
Uploaded - PROJECT VI.docx
A 5 DAYS ----
Source - Another student's paper
A 5 days ----
Suspected Entry: 99% match
Uploaded - PROJECT VI.docx
B 10 DAYS A
Source - Another student's paper
B 10 days A
Suspected Entry: 99% match
Uploaded - PROJECT VI.docx
C 8 DAYS A
Source - Another student's paper
C 8 days A
Suspected Entry: 100% match
Uploaded - PROJECT VI.docx
D 1 DAY A
Source - Another student's paper
D 1 day A
Suspected Entry: 100% match
Uploaded - PROJECT VI.docx
E 5 DAYS B, C
Source - Another student's paper
E 5 days B, C
Suspected Entry: 99% match
Uploaded - PROJECT VI.docx
F 10 DAYS D, E
Source - Another student's paper
F 10 days D, E
Suspected Entry: 99% match
Uploaded - PROJECT VI.docx
G 14 DAYS F
Source - Another student's paper
G 14 days F
Suspected Entry: 99% match
Uploaded - PROJECT VI.docx
H 3 DAYS G
Source - Another student's paper
H 3 days G
Suspected Entry: 100% match
Uploaded - PROJECT VI.docx
I 12 DAYS F
Source - Another student's paper
I 12 days F
Suspected Entry: 100% match
Uploaded - PROJECT VI.docx
J 6 DAYS H, I
Source - Another student's paper
j 6 days H, I
Suspected Entry: 100% match
Uploaded - PROJECT VI.docx
A NETWORK DIAGRAM AND GANTT
CHARTS
Source - Another student's paper
A network diagram and Gantt charts
Suspected Entry: 100% match
Uploaded - PROJECT VI.docx
PLEASE COMPLETE CASE STUDY 10.1
Source - Another student's paper
Please complete Case Study 10.1
Suspected Entry: 99% match
Uploaded - PROJECT VI.docx
PROJECT SCHEDULING AT BLANQUE
CHECK CONSTRUCTION ON PAGE 360 OF
THE TEXTBOOK, AND ANSWER THE THREE
QUESTIONS AT THE END
Source - Another student's paper
Project Scheduling at Blanque Check
Construction on page 360 of the textbook and
answer the three questions at the end
Suspected Entry: 100% match
Uploaded - PROJECT VI.docx
C=DIFFERENT CONSRUCTION TYPES OF
SCHEDULING METHODS TYPE FROM 1 TO 9
P= DIFFERENT CONSRUCTION PROJECTS
WHICH SHOW THE TYPES OF SCHEDULING
METHODS TYPE FROM 1 TO 9
O1=ORGANIZATION ONE O2=
ORGANIZATION 2
Source - Another student's paper
C=DIFFERENT CONSRUCTION TYPES OF
SCHEDULING METHODS TYPE FROM 1 TO 9
P= DIFFERENT CONSRUCTION PROJECTS
WHICH SHOW THE TYPES OF SCHEDULING
METHODS TYPE FROM 1 TO 9
O1=ORGANIZATION ONE O2=
ORGANIZATION 2
Suspected Entry: 100% match
Uploaded - PROJECT VI.docx
S E C4 C5 O1 P9 P8 O2 P7 P6 P5 P4 P3 P2
C9 C8 C7 C6 C1 C2 C3 P1
Source - Another student's paper
S E C4 C5 O1 P9 P8 O2 P7 P6 P5 P4 P3 P2
C9 C8 C7 C6 C1 C2 C3 P1
Suspected Entry: 100% match
Uploaded - PROJECT VI.docx
Q2(ANS) ACCORDING TO MY RESEARCH
LEVEL AND LITERATURE REVIEW THE
EXPERT OPINION AND PAST HISTORY
BOTH ARE THE BEST TO SOLVE PROBLEM
FOR CALCULATING THE CRITICAL
PATH ,WHICH MAY ALSO TELL US THE
DURATION OR PROJECT DELAY TO
HANDLE OR RUN OUR CONSTRUCTION
COMPANY
Source - Another student's paper
Q2(ANS) According to my research level and
literature review the expert opinion and past
history both are the best to solve problem for
calculating the critical path ,which may also tell
us the duration or project delay to handle or run
our construction company
Suspected Entry: 100% match
Uploaded - PROJECT VI.docx
Q3(ANS) THESE BOTH HAVE SOME
STRENGTHENS AND WEAKNESSES AND
BOTH GIVE THE RESULTS PROBABLY
SAME , BUT ACCORDING TO LITERATURE
AOA IS THE BENEFICIAL FOR MODELING IT
WILL BE HELPFUL AND IN THE BUSINESS
FIELD IT WILL BE IMPORTANT AON WILL
BE LESS WIDELY USED , IN CASE OF
LARGE AND COMPLEX PROJECTS IT IS
EASIER TO EMPLOY THE PATH PROCESS
USED IN THE AOA
Source - Another student's paper
Q3(ANS) These both have some strengthens
and weaknesses and both give the results
probably same , but according to literature AOA
is the beneficial for modeling it will be helpful
and in the business field it will be important
AON will be less widely used , in case of large
and complex projects it is easier to employ the
path process used in the AOA
Suspected Entry: 100% match
Uploaded - PROJECT VI.docx
ACCORDING TO AOA WE ACHIEVE THE
EVERY MILESTONE AND PARTICULARLY
USED THE DUMMY PROJECTS OR
ACTIVITIES THE CONCEPT OF DUMMY
PROJECT IS NOT SIMPLE AND EASY IT
REQUIRE MORE TRAINING AND PRACTICE
Source - Another student's paper
according to AOA we achieve the every
milestone and particularly used the dummy
projects or activities the concept of dummy
project is not simple and easy it require more
training and practice
Suspected Entry: 100% match
Uploaded - PROJECT VI.docx
AON CONVENTION ,AOA NETWORK USED
BOTH NODES AND ARROW TO LABEL THE
PROJECT
Source - Another student's paper
AON Convention ,AOA network used both
nodes and arrow to label the project
Suspected Entry: 100% match
Uploaded - PROJECT VI.docx
DEVELOP A NETWORK ACTIVITY CHART,
AND IDENTIFY THE CRITICAL PATH FOR A
PROJECT BASED ON THE INFORMATION
PROVIDED IN THE GANTT CHART BELOW
Source - Another student's paper
Develop a network activity chart and identify the
critical path for a project based on the
information provided in the Gantt chart below
Suspected Entry: 100% match
Uploaded - PROJECT VI.docx
DRAW THE ACTIVITY NETWORK AS A
GANTT CHART
Source - Another student's paper
Draw the activity network as a Gantt chart
Suspected Entry: 100% match
Uploaded - PROJECT VI.docx
WHAT IS THE EXPECTED DURATION OF
THE PROJECT
Source - Another student's paper
What is the expected duration of the project
Suspected Entry: 100% match
Uploaded - PROJECT VI.docx
ACTIVITY EXPECTED DURATION
PREDECESSOR
Source - Another student's paper
Activity Expected Duration Predecessor
Suspected Entry: 100% match
Uploaded - PROJECT VI.docx Source - Another student's paper
A 5 DAYS ---- A 5 days ----
Suspected Entry: 99% match
Uploaded - PROJECT VI.docx
B 10 DAYS A
Source - Another student's paper
B 10 days A
Suspected Entry: 99% match
Uploaded - PROJECT VI.docx
C 8 DAYS A
Source - Another student's paper
C 8 days A
Suspected Entry: 100% match
Uploaded - PROJECT VI.docx
D 1 DAY A
Source - Another student's paper
D 1 day A
Suspected Entry: 100% match
Uploaded - PROJECT VI.docx
E 5 DAYS B, C
Source - Another student's paper
E 5 days B, C
Suspected Entry: 99% match
Uploaded - PROJECT VI.docx
F 10 DAYS D, E
Source - Another student's paper
F 10 days D, E
Suspected Entry: 99% match
Uploaded - PROJECT VI.docx
G 14 DAYS F
Source - Another student's paper
G 14 days F
Suspected Entry: 99% match
Uploaded - PROJECT VI.docx
H 3 DAYS G
Source - Another student's paper
H 3 days G
Suspected Entry: 100% match
Uploaded - PROJECT VI.docx
I 12 DAYS F
Source - Another student's paper
I 12 days F
Suspected Entry: 100% match
Uploaded - PROJECT VI.docx
J 6 DAYS H, I
Source - Another student's paper
j 6 days H, I
Suspected Entry: 100% match
Uploaded - PROJECT VI.docx
AN ACTIVITY PRECEDENCE DIAGRAM
Source - Another student's paper
· An activity precedence diagram
Suspected Entry: 99% match
Uploaded - PROJECT VI.docx
THE TOTAL PATHS CAN BE CALCULATED
THERE THE FIRST DIAGRAM CAN BE
DEFINED THE OVERALL PATHS WHICH
ARE GIVEN BELOW
Source - Another student's paper
The total paths can be calculated there the first
diagram can be defined the overall paths which
are given below
Suspected Entry: 100% match
Uploaded - PROJECT VI.docx
ABEFIJ=5+10+5+10+12+6=48
ABEFGHJ=5+10+5+10+14+3+6=53
Source - Another student's paper
ABEFIJ=5+10+5+10+12+6=48
ABEFGHJ=5+10+5+10+14+3+6=53
ACEFIJ=5+8+5+10+12+6=46
ACEFGHJ=5+10+5+10+14+3+6=51
ADFIJ=5+1+10+12+6=34
ADFGHJ=5+1+10+14+3+6=39
ACEFIJ=5+8+5+10+12+6=46
ACEFGHJ=5+10+5+10+14+3+6=51
ADFIJ=5+1+10+12+6=34
ADFGHJ=5+1+10+14+3+6=39
Suspected Entry: 99% match
Uploaded - PROJECT VI.docx
THE 2ND PATH CAN BE CONSTRUCTED
FOR THE CRITICAL PATH WHICH HAVE THE
LONGEST PATH DURATION
Source - Another student's paper
The 2nd path can be constructed for the critical
path which have the longest path duration
Suspected Entry: 99% match
Uploaded - PROJECT VI.docx
ABEFGHJ=5+10+5+10+14+3+6=53 ITS
KNOWN AS A CRITICAL PATH FOR THE
GIVEN ACTIVITY
Source - Another student's paper
ABEFGHJ=5+10+5+10+14+3+6=53 Its known
as a critical path for the given activity
Suspected Entry: 99% match
Uploaded - PROJECT VI.docx
PRECEDENCE DIAGRAM AND CRITICAL
PATH
Source - Another student's paper
Precedence diagram and critical path
Suspected Entry: 100% match
Uploaded - PROJECT VI.docx
END H J G F E B A A J H G E F I START D C
B J END START END END
Source - Another student's paper
end H j G F E B A A J H G E F I START D C B
J END START end END
Suspected Entry: 100% match
Uploaded - PROJECT VI.docx Source - Another student's paper
USING THE INFORMATION PROVIDED IN
THE GANTT CHART BELOW, CONSTRUCT
THE PROJECT ACTIVITY NETWORK USING
THE ACTIVITY-ON-NODE (AON)
METHODOLOGY, AND LABEL EACH NODE
Using the information provided in the Gantt
chart below, construct the project activity
network using the activity-on-node (AON)
methodology, and label each node
Suspected Entry: 100% match
Uploaded - PROJECT VI.docx
IDENTIFY THE CRITICAL PATH AND OTHER
PATHS THROUGH THE NETWORK
Source - Another student's paper
Identify the critical path and other paths through
the network
Suspected Entry: 100% match
Uploaded - PROJECT VI.docx
E, F, G
Source - Another student's paper
E, F, G
Suspected Entry: 100% match
Uploaded - PROJECT VI.docx
ACTIVITY DURATION ES EF LS
Source - Another student's paper
Activity Duration ES EF LS
Suspected Entry: 100% match
Uploaded - PROJECT VI.docx
A 3 0 3 0
Source - Another student's paper
A 3 0 3 0
Suspected Entry: 100% match
Uploaded - PROJECT VI.docx
B 5 3 8 8
Source - Another student's paper
B 5 3 8 8
Suspected Entry: 100% match
Uploaded - PROJECT VI.docx
C 7 3 10 3
Source - Another student's paper
C 7 3 10 3
Suspected Entry: 100% match
Uploaded - PROJECT VI.docx
D 3 10 13 13
Source - Another student's paper
D 3 10 13 13
Suspected Entry: 100% match
Uploaded - PROJECT VI.docx
E 5 8 13 13
Source - Another student's paper
E 5 8 13 13
Suspected Entry: 100% match
Uploaded - PROJECT VI.docx
F 4 13 17 13
Source - Another student's paper
F 4 13 17 13
Suspected Entry: 100% match
Uploaded - PROJECT VI.docx
G 2 10 12 15
Source - Another student's paper
G 2 10 12 15
Suspected Entry: 99% match
Uploaded - PROJECT VI.docx
H 5 17 22 17
Source - Another student's paper
H 5 17 22 17
Suspected Entry: 100% match
Uploaded - PROJECT VI.docx
1 PART 1
Source - Another student's paper
1 Part 1
Suspected Entry: 100% match
Uploaded - PROJECT VI.docx
0 3 0
Source - Another student's paper
0 3 0
Suspected Entry: 100% match
Uploaded - PROJECT VI.docx
8 5 13
Source - Another student's paper
8 5 13
Suspected Entry: 100% match
Uploaded - PROJECT VI.docx
3 5 17
Source - Another student's paper
3 5 17
Suspected Entry: 100% match
Uploaded - PROJECT VI.docx
13 3 13
Source - Another student's paper
13 3 13
Suspected Entry: 100% match
Uploaded - PROJECT VI.docx
17 5 22
Source - Another student's paper
17 5 22
Suspected Entry: 100% match
Uploaded - PROJECT VI.docx
13 4 17
Source - Another student's paper
13 4 17
Suspected Entry: 100% match
Uploaded - PROJECT VI.docx
3 7 10
Source - Another student's paper
3 7 10
Suspected Entry: 100% match
Uploaded - PROJECT VI.docx
15 2 17
Source - Another student's paper
15 2 17
Suspected Entry: 100% match
Uploaded - PROJECT VI.docx
ES ID EF
Source - Another student's paper
ES ID EF
Suspected Entry: 100% match
Uploaded - PROJECT VI.docx
LS DURATION LF
Source - Another student's paper
LS DURATION LF
Suspected Entry: 99% match
Uploaded - PROJECT VI.docx
THE CRITICAL PATH CAN BE CHOOSE
WHICH HAVE THE MINIMUM SLACK AND
THEN FIND THE DURATION OR DELAY OF
CRITICAL PATH FIRST OF ALL WE FIND
THE CRITICAL PATH OF GIVEN ACTIVITY
THE CRITICAL PATH HAVE MINIMUM
SLACK BUT DELAY SHOULD BE
MAXIMUM ,WHICH ARE GIVEN BELOW
Source - Another student's paper
The critical path can be choose which have the
minimum slack and then find the duration or
delay of critical path first of all we find the critical
path of given activity the critical path have
minimum slack but delay should be maximum,
which are given below
Suspected Entry: 100% match
Uploaded - PROJECT VI.docx
ACDFH=3+7+3+4+5=22DAYS/MIN WITH THE
CRITICAL POINT OF SLACK THE
FLEXIBILITY OF THE PROJECT IS LIMITED
Source - Another student's paper
ACDFH=3+7+3+4+5=22days/min With the
critical point of slack, the flexibility of the project
is limited
Running head: UNIT VI PROJECT
1
Part 1:
UNIT VI PROJECT 6
Unit VI Project
Your Name
Columbia Southern University
Part 1
Develop an in-depth schedule for the project you selected and
used to develop the statement of work and work breakdown
structure in Unit III. Please refer to the Integrated Project in
Chapter 10 on page 363 (Project Scheduling) of the textbook for
more information. Be sure to include the following components:
· an activity precedence diagram,
· an activity duration table, and
· a network diagram and Gantt charts.
Part 2
Please complete Case Study 10.1: Project Scheduling at Blanque
Check Construction on page 360 of the textbook, and answer the
three questions at the end.
Part 3
Develop a network activity chart, and identify the critical path
for a project based on the information provided in the Gantt
chart below. Draw the activity network as a Gantt chart. What is
the expected duration of the project?
Activity
Expected Duration
Predecessor
A
5 days
----
B
10 days
A
C
8 days
A
D
1 day
A
E
5 days
B, C
F
10 days
D, E
G
14 days
F
H
3 days
G
I
12 days
F
j
6 days
H, I
Part 4
Using the information provided in the Gantt chart below,
construct the project activity network using the activity-on-node
(AON) methodology, and label each node. Identify the critical
path and other paths through the network.
Activity
Duration
Predecessors
A
3
--
B
5
A
C
7
A
D
3
B, C
E
5
B
F
4
D
G
2
C
H
5
E, F, G
Activity
Duration
ES
EF
LS
LF
Slack
A
3
0
3
0
0
--
B
5
3
8
8
13
5
C
7
3
10
3
10
--
D
3
10
13
13
13
--
E
5
8
12
13
17
5
F
4
13
17
13
17
G
2
10
12
15
17
5
H
5
17
22
17
22
--
References

More Related Content

Similar to SAFEASSIGNCHECKTEST - CSU SAFEASSIGN PLAGIARISM CHECK TOOL.docx

Initial Project Meeting Agenda PowerPoint Presentation Slides
Initial Project Meeting Agenda PowerPoint Presentation Slides Initial Project Meeting Agenda PowerPoint Presentation Slides
Initial Project Meeting Agenda PowerPoint Presentation Slides SlideTeam
 
Student Research Award
Student Research AwardStudent Research Award
Student Research AwardJonathan Lepp
 
best note.pptx
best note.pptxbest note.pptx
best note.pptxDejeneDay
 
Project management@ ppt doms
Project management@ ppt doms Project management@ ppt doms
Project management@ ppt doms Babasab Patil
 
1. SHORT PAPERWAN Technologies Paper Research Point-to-Point .docx
1. SHORT PAPERWAN Technologies Paper Research Point-to-Point .docx1. SHORT PAPERWAN Technologies Paper Research Point-to-Point .docx
1. SHORT PAPERWAN Technologies Paper Research Point-to-Point .docxMargaritoWhitt221
 
ntcir14centre-overview
ntcir14centre-overviewntcir14centre-overview
ntcir14centre-overviewTetsuya Sakai
 
EO notes Lecture 27 Project Management 2.ppt
EO notes Lecture 27 Project Management 2.pptEO notes Lecture 27 Project Management 2.ppt
EO notes Lecture 27 Project Management 2.pptyashchotaliyael21
 
Bus 517 final exam – strayer new
Bus 517 final exam – strayer newBus 517 final exam – strayer new
Bus 517 final exam – strayer newKatherineJack1
 
Bus 517 final exam – strayer new
Bus 517 final exam – strayer newBus 517 final exam – strayer new
Bus 517 final exam – strayer newSarajacobe
 
Bus 517 final exam – strayer new
Bus 517 final exam – strayer newBus 517 final exam – strayer new
Bus 517 final exam – strayer newEmmaJack2018
 
Bus 517 final exam – strayer new
Bus 517 final exam – strayer newBus 517 final exam – strayer new
Bus 517 final exam – strayer newlizabonilla
 
Bus 517 final exam – strayer new
Bus 517 final exam – strayer newBus 517 final exam – strayer new
Bus 517 final exam – strayer newemmywatson2017
 
Bus 517 final exam – strayer new
Bus 517 final exam – strayer newBus 517 final exam – strayer new
Bus 517 final exam – strayer newLillieDickey
 
Bus 517 final exam – strayer new
Bus 517 final exam – strayer newBus 517 final exam – strayer new
Bus 517 final exam – strayer newsarahlazeto
 
Bus 517 final exam – strayer new
Bus 517 final exam – strayer newBus 517 final exam – strayer new
Bus 517 final exam – strayer newsweetsour2017
 

Similar to SAFEASSIGNCHECKTEST - CSU SAFEASSIGN PLAGIARISM CHECK TOOL.docx (20)

Initial Project Meeting Agenda PowerPoint Presentation Slides
Initial Project Meeting Agenda PowerPoint Presentation Slides Initial Project Meeting Agenda PowerPoint Presentation Slides
Initial Project Meeting Agenda PowerPoint Presentation Slides
 
Bballard2000 dissertation
Bballard2000 dissertationBballard2000 dissertation
Bballard2000 dissertation
 
Lecture 2 PERT-CPM.pdf
Lecture 2 PERT-CPM.pdfLecture 2 PERT-CPM.pdf
Lecture 2 PERT-CPM.pdf
 
Student Research Award
Student Research AwardStudent Research Award
Student Research Award
 
best note.pptx
best note.pptxbest note.pptx
best note.pptx
 
Uav Dissertation
Uav DissertationUav Dissertation
Uav Dissertation
 
Project management@ ppt doms
Project management@ ppt doms Project management@ ppt doms
Project management@ ppt doms
 
1. SHORT PAPERWAN Technologies Paper Research Point-to-Point .docx
1. SHORT PAPERWAN Technologies Paper Research Point-to-Point .docx1. SHORT PAPERWAN Technologies Paper Research Point-to-Point .docx
1. SHORT PAPERWAN Technologies Paper Research Point-to-Point .docx
 
ntcir14centre-overview
ntcir14centre-overviewntcir14centre-overview
ntcir14centre-overview
 
IT6511 Networks Laboratory
IT6511 Networks LaboratoryIT6511 Networks Laboratory
IT6511 Networks Laboratory
 
Pmp6
Pmp6Pmp6
Pmp6
 
EO notes Lecture 27 Project Management 2.ppt
EO notes Lecture 27 Project Management 2.pptEO notes Lecture 27 Project Management 2.ppt
EO notes Lecture 27 Project Management 2.ppt
 
Bus 517 final exam – strayer new
Bus 517 final exam – strayer newBus 517 final exam – strayer new
Bus 517 final exam – strayer new
 
Bus 517 final exam – strayer new
Bus 517 final exam – strayer newBus 517 final exam – strayer new
Bus 517 final exam – strayer new
 
Bus 517 final exam – strayer new
Bus 517 final exam – strayer newBus 517 final exam – strayer new
Bus 517 final exam – strayer new
 
Bus 517 final exam – strayer new
Bus 517 final exam – strayer newBus 517 final exam – strayer new
Bus 517 final exam – strayer new
 
Bus 517 final exam – strayer new
Bus 517 final exam – strayer newBus 517 final exam – strayer new
Bus 517 final exam – strayer new
 
Bus 517 final exam – strayer new
Bus 517 final exam – strayer newBus 517 final exam – strayer new
Bus 517 final exam – strayer new
 
Bus 517 final exam – strayer new
Bus 517 final exam – strayer newBus 517 final exam – strayer new
Bus 517 final exam – strayer new
 
Bus 517 final exam – strayer new
Bus 517 final exam – strayer newBus 517 final exam – strayer new
Bus 517 final exam – strayer new
 

More from rtodd599

SAGE was founded in 1965 by Sa.docx
SAGE was founded in 1965 by Sa.docxSAGE was founded in 1965 by Sa.docx
SAGE was founded in 1965 by Sa.docxrtodd599
 
SafeAssignCheckTest - CSU SafeAssign Plagiarism Check ToolSafeAs.docx
SafeAssignCheckTest - CSU SafeAssign Plagiarism Check ToolSafeAs.docxSafeAssignCheckTest - CSU SafeAssign Plagiarism Check ToolSafeAs.docx
SafeAssignCheckTest - CSU SafeAssign Plagiarism Check ToolSafeAs.docxrtodd599
 
Safety Management System1SMS-1Jeffrey D Carpenter, CSP.docx
Safety Management System1SMS-1Jeffrey D Carpenter, CSP.docxSafety Management System1SMS-1Jeffrey D Carpenter, CSP.docx
Safety Management System1SMS-1Jeffrey D Carpenter, CSP.docxrtodd599
 
Sajan Thapa1) Allegory suggests that enlightenment or educatio.docx
Sajan Thapa1) Allegory suggests that enlightenment or educatio.docxSajan Thapa1) Allegory suggests that enlightenment or educatio.docx
Sajan Thapa1) Allegory suggests that enlightenment or educatio.docxrtodd599
 
Safety and Health Providing a safe and secure environment for emplo.docx
Safety and Health Providing a safe and secure environment for emplo.docxSafety and Health Providing a safe and secure environment for emplo.docx
Safety and Health Providing a safe and secure environment for emplo.docxrtodd599
 
SAGE OpenJuly-September 2013 1 –10© The Author(s) 2013D.docx
SAGE OpenJuly-September 2013 1 –10© The Author(s) 2013D.docxSAGE OpenJuly-September 2013 1 –10© The Author(s) 2013D.docx
SAGE OpenJuly-September 2013 1 –10© The Author(s) 2013D.docxrtodd599
 
Safeby Rachael FabelurinSubmission dat e 07 - Jan- 201.docx
Safeby Rachael FabelurinSubmission dat e  07 - Jan- 201.docxSafeby Rachael FabelurinSubmission dat e  07 - Jan- 201.docx
Safeby Rachael FabelurinSubmission dat e 07 - Jan- 201.docxrtodd599
 
Safe Work Environment  Please respond to the followingRecommen.docx
Safe Work Environment  Please respond to the followingRecommen.docxSafe Work Environment  Please respond to the followingRecommen.docx
Safe Work Environment  Please respond to the followingRecommen.docxrtodd599
 
Sadder and Less Accurate False Memory for NegativeMaterial .docx
Sadder and Less Accurate False Memory for NegativeMaterial .docxSadder and Less Accurate False Memory for NegativeMaterial .docx
Sadder and Less Accurate False Memory for NegativeMaterial .docxrtodd599
 
Safe Work Environment  Please respond to the followingRecomme.docx
Safe Work Environment  Please respond to the followingRecomme.docxSafe Work Environment  Please respond to the followingRecomme.docx
Safe Work Environment  Please respond to the followingRecomme.docxrtodd599
 
Safe Work Environment  Please respond to the followingRecomme.docx
Safe Work Environment  Please respond to the followingRecomme.docxSafe Work Environment  Please respond to the followingRecomme.docx
Safe Work Environment  Please respond to the followingRecomme.docxrtodd599
 
S216 MAN506 ORGANISATIONAL BEHAVIOUR httpsonline.cdu.edu..docx
S216 MAN506 ORGANISATIONAL BEHAVIOUR httpsonline.cdu.edu..docxS216 MAN506 ORGANISATIONAL BEHAVIOUR httpsonline.cdu.edu..docx
S216 MAN506 ORGANISATIONAL BEHAVIOUR httpsonline.cdu.edu..docxrtodd599
 
SAAD COLLEGE OF NURSING AND ALLIED HEALTH SCIENCESUNIVERSI.docx
SAAD COLLEGE OF NURSING AND ALLIED HEALTH SCIENCESUNIVERSI.docxSAAD COLLEGE OF NURSING AND ALLIED HEALTH SCIENCESUNIVERSI.docx
SAAD COLLEGE OF NURSING AND ALLIED HEALTH SCIENCESUNIVERSI.docxrtodd599
 
S18SOCI111SocialNetworksHomework4DUE66198.docx
S18SOCI111SocialNetworksHomework4DUE66198.docxS18SOCI111SocialNetworksHomework4DUE66198.docx
S18SOCI111SocialNetworksHomework4DUE66198.docxrtodd599
 
SAAD COLLEGE OF NURSING AND ALLIED HEALTH SC.docx
SAAD COLLEGE OF NURSING AND ALLIED HEALTH SC.docxSAAD COLLEGE OF NURSING AND ALLIED HEALTH SC.docx
SAAD COLLEGE OF NURSING AND ALLIED HEALTH SC.docxrtodd599
 
Sadly today police are not often viewed in the best light. Not a.docx
Sadly today police are not often viewed in the best light. Not a.docxSadly today police are not often viewed in the best light. Not a.docx
Sadly today police are not often viewed in the best light. Not a.docxrtodd599
 
S w 909E24 ENGRO CHEMICALS PAKISTAN LIMITED — .docx
S w  909E24    ENGRO CHEMICALS PAKISTAN LIMITED — .docxS w  909E24    ENGRO CHEMICALS PAKISTAN LIMITED — .docx
S w 909E24 ENGRO CHEMICALS PAKISTAN LIMITED — .docxrtodd599
 
SA #1 What is Ekman Divergence Wherewhat are three location.docx
SA #1 What is Ekman Divergence Wherewhat are three location.docxSA #1 What is Ekman Divergence Wherewhat are three location.docx
SA #1 What is Ekman Divergence Wherewhat are three location.docxrtodd599
 
S&J Plumbing, Inc.s 2010 income statement shows a net profit before.docx
S&J Plumbing, Inc.s 2010 income statement shows a net profit before.docxS&J Plumbing, Inc.s 2010 income statement shows a net profit before.docx
S&J Plumbing, Inc.s 2010 income statement shows a net profit before.docxrtodd599
 
S2021Instructions In describing your pro and con arguments, be sure.docx
S2021Instructions In describing your pro and con arguments, be sure.docxS2021Instructions In describing your pro and con arguments, be sure.docx
S2021Instructions In describing your pro and con arguments, be sure.docxrtodd599
 

More from rtodd599 (20)

SAGE was founded in 1965 by Sa.docx
SAGE was founded in 1965 by Sa.docxSAGE was founded in 1965 by Sa.docx
SAGE was founded in 1965 by Sa.docx
 
SafeAssignCheckTest - CSU SafeAssign Plagiarism Check ToolSafeAs.docx
SafeAssignCheckTest - CSU SafeAssign Plagiarism Check ToolSafeAs.docxSafeAssignCheckTest - CSU SafeAssign Plagiarism Check ToolSafeAs.docx
SafeAssignCheckTest - CSU SafeAssign Plagiarism Check ToolSafeAs.docx
 
Safety Management System1SMS-1Jeffrey D Carpenter, CSP.docx
Safety Management System1SMS-1Jeffrey D Carpenter, CSP.docxSafety Management System1SMS-1Jeffrey D Carpenter, CSP.docx
Safety Management System1SMS-1Jeffrey D Carpenter, CSP.docx
 
Sajan Thapa1) Allegory suggests that enlightenment or educatio.docx
Sajan Thapa1) Allegory suggests that enlightenment or educatio.docxSajan Thapa1) Allegory suggests that enlightenment or educatio.docx
Sajan Thapa1) Allegory suggests that enlightenment or educatio.docx
 
Safety and Health Providing a safe and secure environment for emplo.docx
Safety and Health Providing a safe and secure environment for emplo.docxSafety and Health Providing a safe and secure environment for emplo.docx
Safety and Health Providing a safe and secure environment for emplo.docx
 
SAGE OpenJuly-September 2013 1 –10© The Author(s) 2013D.docx
SAGE OpenJuly-September 2013 1 –10© The Author(s) 2013D.docxSAGE OpenJuly-September 2013 1 –10© The Author(s) 2013D.docx
SAGE OpenJuly-September 2013 1 –10© The Author(s) 2013D.docx
 
Safeby Rachael FabelurinSubmission dat e 07 - Jan- 201.docx
Safeby Rachael FabelurinSubmission dat e  07 - Jan- 201.docxSafeby Rachael FabelurinSubmission dat e  07 - Jan- 201.docx
Safeby Rachael FabelurinSubmission dat e 07 - Jan- 201.docx
 
Safe Work Environment  Please respond to the followingRecommen.docx
Safe Work Environment  Please respond to the followingRecommen.docxSafe Work Environment  Please respond to the followingRecommen.docx
Safe Work Environment  Please respond to the followingRecommen.docx
 
Sadder and Less Accurate False Memory for NegativeMaterial .docx
Sadder and Less Accurate False Memory for NegativeMaterial .docxSadder and Less Accurate False Memory for NegativeMaterial .docx
Sadder and Less Accurate False Memory for NegativeMaterial .docx
 
Safe Work Environment  Please respond to the followingRecomme.docx
Safe Work Environment  Please respond to the followingRecomme.docxSafe Work Environment  Please respond to the followingRecomme.docx
Safe Work Environment  Please respond to the followingRecomme.docx
 
Safe Work Environment  Please respond to the followingRecomme.docx
Safe Work Environment  Please respond to the followingRecomme.docxSafe Work Environment  Please respond to the followingRecomme.docx
Safe Work Environment  Please respond to the followingRecomme.docx
 
S216 MAN506 ORGANISATIONAL BEHAVIOUR httpsonline.cdu.edu..docx
S216 MAN506 ORGANISATIONAL BEHAVIOUR httpsonline.cdu.edu..docxS216 MAN506 ORGANISATIONAL BEHAVIOUR httpsonline.cdu.edu..docx
S216 MAN506 ORGANISATIONAL BEHAVIOUR httpsonline.cdu.edu..docx
 
SAAD COLLEGE OF NURSING AND ALLIED HEALTH SCIENCESUNIVERSI.docx
SAAD COLLEGE OF NURSING AND ALLIED HEALTH SCIENCESUNIVERSI.docxSAAD COLLEGE OF NURSING AND ALLIED HEALTH SCIENCESUNIVERSI.docx
SAAD COLLEGE OF NURSING AND ALLIED HEALTH SCIENCESUNIVERSI.docx
 
S18SOCI111SocialNetworksHomework4DUE66198.docx
S18SOCI111SocialNetworksHomework4DUE66198.docxS18SOCI111SocialNetworksHomework4DUE66198.docx
S18SOCI111SocialNetworksHomework4DUE66198.docx
 
SAAD COLLEGE OF NURSING AND ALLIED HEALTH SC.docx
SAAD COLLEGE OF NURSING AND ALLIED HEALTH SC.docxSAAD COLLEGE OF NURSING AND ALLIED HEALTH SC.docx
SAAD COLLEGE OF NURSING AND ALLIED HEALTH SC.docx
 
Sadly today police are not often viewed in the best light. Not a.docx
Sadly today police are not often viewed in the best light. Not a.docxSadly today police are not often viewed in the best light. Not a.docx
Sadly today police are not often viewed in the best light. Not a.docx
 
S w 909E24 ENGRO CHEMICALS PAKISTAN LIMITED — .docx
S w  909E24    ENGRO CHEMICALS PAKISTAN LIMITED — .docxS w  909E24    ENGRO CHEMICALS PAKISTAN LIMITED — .docx
S w 909E24 ENGRO CHEMICALS PAKISTAN LIMITED — .docx
 
SA #1 What is Ekman Divergence Wherewhat are three location.docx
SA #1 What is Ekman Divergence Wherewhat are three location.docxSA #1 What is Ekman Divergence Wherewhat are three location.docx
SA #1 What is Ekman Divergence Wherewhat are three location.docx
 
S&J Plumbing, Inc.s 2010 income statement shows a net profit before.docx
S&J Plumbing, Inc.s 2010 income statement shows a net profit before.docxS&J Plumbing, Inc.s 2010 income statement shows a net profit before.docx
S&J Plumbing, Inc.s 2010 income statement shows a net profit before.docx
 
S2021Instructions In describing your pro and con arguments, be sure.docx
S2021Instructions In describing your pro and con arguments, be sure.docxS2021Instructions In describing your pro and con arguments, be sure.docx
S2021Instructions In describing your pro and con arguments, be sure.docx
 

Recently uploaded

Painted Grey Ware.pptx, PGW Culture of India
Painted Grey Ware.pptx, PGW Culture of IndiaPainted Grey Ware.pptx, PGW Culture of India
Painted Grey Ware.pptx, PGW Culture of IndiaVirag Sontakke
 
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxPOINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxSayali Powar
 
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17Celine George
 
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions  for the students and aspirants of Chemistry12th.pptxOrganic Name Reactions  for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions for the students and aspirants of Chemistry12th.pptxVS Mahajan Coaching Centre
 
MARGINALIZATION (Different learners in Marginalized Group
MARGINALIZATION (Different learners in Marginalized GroupMARGINALIZATION (Different learners in Marginalized Group
MARGINALIZATION (Different learners in Marginalized GroupJonathanParaisoCruz
 
Earth Day Presentation wow hello nice great
Earth Day Presentation wow hello nice greatEarth Day Presentation wow hello nice great
Earth Day Presentation wow hello nice greatYousafMalik24
 
Roles & Responsibilities in Pharmacovigilance
Roles & Responsibilities in PharmacovigilanceRoles & Responsibilities in Pharmacovigilance
Roles & Responsibilities in PharmacovigilanceSamikshaHamane
 
Pharmacognosy Flower 3. Compositae 2023.pdf
Pharmacognosy Flower 3. Compositae 2023.pdfPharmacognosy Flower 3. Compositae 2023.pdf
Pharmacognosy Flower 3. Compositae 2023.pdfMahmoud M. Sallam
 
Solving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxSolving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxOH TEIK BIN
 
Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)eniolaolutunde
 
EPANDING THE CONTENT OF AN OUTLINE using notes.pptx
EPANDING THE CONTENT OF AN OUTLINE using notes.pptxEPANDING THE CONTENT OF AN OUTLINE using notes.pptx
EPANDING THE CONTENT OF AN OUTLINE using notes.pptxRaymartEstabillo3
 
Introduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxIntroduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxpboyjonauth
 
CARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxCARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxGaneshChakor2
 
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️9953056974 Low Rate Call Girls In Saket, Delhi NCR
 
Introduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher EducationIntroduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher Educationpboyjonauth
 
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...Marc Dusseiller Dusjagr
 
Employee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxEmployee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxNirmalaLoungPoorunde1
 
Hierarchy of management that covers different levels of management
Hierarchy of management that covers different levels of managementHierarchy of management that covers different levels of management
Hierarchy of management that covers different levels of managementmkooblal
 
How to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxHow to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxmanuelaromero2013
 

Recently uploaded (20)

Painted Grey Ware.pptx, PGW Culture of India
Painted Grey Ware.pptx, PGW Culture of IndiaPainted Grey Ware.pptx, PGW Culture of India
Painted Grey Ware.pptx, PGW Culture of India
 
Model Call Girl in Bikash Puri Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Bikash Puri  Delhi reach out to us at 🔝9953056974🔝Model Call Girl in Bikash Puri  Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Bikash Puri Delhi reach out to us at 🔝9953056974🔝
 
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxPOINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
 
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
 
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions  for the students and aspirants of Chemistry12th.pptxOrganic Name Reactions  for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
 
MARGINALIZATION (Different learners in Marginalized Group
MARGINALIZATION (Different learners in Marginalized GroupMARGINALIZATION (Different learners in Marginalized Group
MARGINALIZATION (Different learners in Marginalized Group
 
Earth Day Presentation wow hello nice great
Earth Day Presentation wow hello nice greatEarth Day Presentation wow hello nice great
Earth Day Presentation wow hello nice great
 
Roles & Responsibilities in Pharmacovigilance
Roles & Responsibilities in PharmacovigilanceRoles & Responsibilities in Pharmacovigilance
Roles & Responsibilities in Pharmacovigilance
 
Pharmacognosy Flower 3. Compositae 2023.pdf
Pharmacognosy Flower 3. Compositae 2023.pdfPharmacognosy Flower 3. Compositae 2023.pdf
Pharmacognosy Flower 3. Compositae 2023.pdf
 
Solving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxSolving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptx
 
Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)
 
EPANDING THE CONTENT OF AN OUTLINE using notes.pptx
EPANDING THE CONTENT OF AN OUTLINE using notes.pptxEPANDING THE CONTENT OF AN OUTLINE using notes.pptx
EPANDING THE CONTENT OF AN OUTLINE using notes.pptx
 
Introduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxIntroduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptx
 
CARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxCARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptx
 
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
 
Introduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher EducationIntroduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher Education
 
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
 
Employee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxEmployee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptx
 
Hierarchy of management that covers different levels of management
Hierarchy of management that covers different levels of managementHierarchy of management that covers different levels of management
Hierarchy of management that covers different levels of management
 
How to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxHow to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptx
 

SAFEASSIGNCHECKTEST - CSU SAFEASSIGN PLAGIARISM CHECK TOOL.docx

  • 1. SAFEASSIGNCHECKTEST - CSU SAFEASSIGN PLAGIARISM CHECK TOOL SafeAssign Originality Report Generator I Odell Kruah on Fri, Nov 30 2018, 4:44 PM 100% highest match Submission ID: d0da8619-c56f-4e34-9af1-6edd71018503 Attachments (1) PROJECT VI.docx 1 ODELL KRUAH PROJECT MANAGEMENT UNIT VI NOVEMBER 30, 2018 Part 1 1 DEVELOP AN IN-DEPTH SCHEDULE FOR THE PROJECT YOU SELECTED AND USED TO DEVELOP THE STATEMENT OF WORK AND WORK BREAKDOWN STRUCTURE IN UNIT III. PLEASE REFER TO THE INTEGRATED PROJECT IN CHAPTER 10 ON PAGE 363
  • 2. (PROJECT SCHEDULING) OF THE TEXTBOOK FOR MORE INFORMATION. BE SURE TO INCLUDE THE FOLLOWING COMPONENTS: · AN ACTIVITY PRECEDENCE DIAGRAM, · AN ACTIVITY DURATION TABLE, AND · A NETWORK DIAGRAM AND GANTT CHARTS. · AN ACTIVITY PRECEDENCE DIAGRAM: (http://safeassign.blackboard.com/) PROJECT VI.docx Word Count: 862 Attachment ID: 244309330 100% ACTIVITY DURATION TABLE: ACTIVITY EXPECTED DURATION PREDECESSOR A 5 DAYS ---- B 10 DAYS A C 8 DAYS A D 1 DAY A
  • 3. E 5 DAYS B, C F 10 DAYS D, E G 14 DAYS F H 3 DAYS G I 12 DAYS F J 6 DAYS H, I A NETWORK DIAGRAM AND GANTT CHARTS: A B C D E F G H I J
  • 4. Part 2 1 PLEASE COMPLETE CASE STUDY 10.1: PROJECT SCHEDULING AT BLANQUE CHECK CONSTRUCTION ON PAGE 360 OF THE TEXTBOOK, AND ANSWER THE THREE QUESTIONS AT THE END. Q1(ANS) PRECEDENCE DIAGRAM: 1 C=DIFFERENT CONSRUCTION TYPES OF SCHEDULING METHODS TYPE FROM 1 TO 9 P= DIFFERENT CONSRUCTION PROJECTS WHICH SHOW THE TYPES OF SCHEDULING METHODS TYPE FROM 1 TO 9 O1=ORGANIZATION ONE O2= ORGANIZATION 2 S E C4 C5 O1 P9 P8 O2 P7 P6 P5 P4 P3 P2 C9 C8 C7 C6 C1 C2 C3 P1 Q2(ANS) ACCORDING TO MY RESEARCH LEVEL AND LITERATURE REVIEW THE EXPERT OPINION AND PAST HISTORY BOTH ARE THE BEST TO SOLVE PROBLEM FOR CALCULATING THE
  • 5. CRITICAL PATH ,WHICH MAY ALSO TELL US THE DURATION OR PROJECT DELAY TO HANDLE OR RUN OUR CONSTRUCTION COMPANY. Q3(ANS) THESE BOTH HAVE SOME STRENGTHENS AND WEAKNESSES AND BOTH GIVE THE RESULTS PROBABLY SAME , BUT ACCORDING TO LITERATURE AOA IS THE BENEFICIAL FOR MODELING IT WILL BE HELPFUL AND IN THE BUSINESS FIELD IT WILL BE IMPORTANT AON WILL BE LESS WIDELY USED , IN CASE OF LARGE AND COMPLEX PROJECTS IT IS EASIER TO EMPLOY THE PATH PROCESS USED IN THE AOA. ACCORDING TO AOA WE ACHIEVE THE EVERY MILESTONE AND PARTICULARLY USED THE DUMMY PROJECTS OR ACTIVITIES THE CONCEPT OF DUMMY
  • 6. PROJECT IS NOT SIMPLE AND EASY IT REQUIRE MORE TRAINING AND PRACTICE. AON CONVENTION ,AOA NETWORK USED BOTH NODES AND ARROW TO LABEL THE PROJECT. Part 3 1 DEVELOP A NETWORK ACTIVITY CHART, AND IDENTIFY THE CRITICAL PATH FOR A PROJECT BASED ON THE INFORMATION PROVIDED IN THE GANTT CHART BELOW. DRAW THE ACTIVITY NETWORK AS A GANTT CHART. WHAT IS THE EXPECTED DURATION OF THE PROJECT? ACTIVITY EXPECTED DURATION PREDECESSOR A 5 DAYS ---- B 10 DAYS A C 8 DAYS A D 1 DAY A E 5 DAYS B, C
  • 7. F 10 DAYS D, E G 14 DAYS F H 3 DAYS G I 12 DAYS F J 6 DAYS H, I AN ACTIVITY PRECEDENCE DIAGRAM: THE TOTAL PATHS CAN BE CALCULATED THERE THE FIRST DIAGRAM CAN BE DEFINED THE OVERALL PATHS WHICH ARE GIVEN BELOW ABEFIJ=5+10+5+10+12+6=48 ABEFGHJ=5+10+5+10+14+3+6=53 ACEFIJ=5+8+5+10+12+6=46 ACEFGHJ=5+10+5+10+14+3+6=51 ADFIJ=5+1+10+12+6=34 ADFGHJ=5+1+10+14+3+6=39 Critical path: 1 THE 2ND PATH CAN BE CONSTRUCTED FOR THE CRITICAL PATH WHICH HAVE THE LONGEST PATH DURATION
  • 8. ABEFGHJ=5+10+5+10+14+3+6=53 ITS KNOWN AS A CRITICAL PATH FOR THE GIVEN ACTIVITY. PRECEDENCE DIAGRAM AND CRITICAL PATH END H J G F E B A A J H G E F I START D C B J END START END END Part 4 1 USING THE INFORMATION PROVIDED IN THE GANTT CHART BELOW, CONSTRUCT THE PROJECT ACTIVITY NETWORK USING THE ACTIVITY-ON-NODE (AON) METHODOLOGY, AND LABEL EACH NODE. IDENTIFY THE CRITICAL PATH AND OTHER PATHS THROUGH THE NETWORK. Activity Duration Predecessors A
  • 10. G 2 C H 5 1 E, F, G ACTIVITY DURATION ES EF LS LF Slack 1 A 3 0 3 0 0 -- 1 B 5 3 8 8 13 5 1 C 7 3 10 3 10 -- 1 D 3 10 13 13 13 -- 1 E 5 8 13 13 17 5
  • 11. 1 F 4 13 17 13 17 1 G 2 10 12 15 17 5 1 H 5 17 22 17 22 -- SOLUTION: 1 1 PART 1: 6 0 3 3 8 8 13 0 A 5 B
  • 12. 10 13 5 E 3 D 1 0 3 0 8 5 13 3 5 17 17 22 1 13 3 13 0 H END 13 17 3 10 0 F
  • 13. 1 17 5 22 0 C 1 13 4 17 3 7 10 10 12 5 G LEGEND 1 15 2 17 ES ID EF SL DISCRIPTION 1 LS DURATION LF THE CRITICAL PATH CAN BE CHOOSE WHICH HAVE THE MINIMUM SLACK AND THEN FIND THE DURATION OR DELAY OF CRITICAL PATH FIRST OF ALL WE FIND THE CRITICAL PATH OF GIVEN
  • 14. ACTIVITY THE CRITICAL PATH HAVE MINIMUM SLACK BUT DELAY SHOULD BE MAXIMUM ,WHICH ARE GIVEN BELOW ACDFH=3+7+3+4+5=22DAYS/MIN WITH THE CRITICAL POINT OF SLACK THE FLEXIBILITY OF THE PROJECT IS LIMITED G Citations (1/1) Matched Text 1 Another student's paper Suspected Entry: 62% match Uploaded - PROJECT VI.docx ODELL KRUAH PROJECT MANAGEMENT UNIT VI NOVEMBER 30, 2018 Source - Another student's paper Unit VI Project Odell Kruah Columbia Southern University 11/18/2018 Suspected Entry: 100% match
  • 15. Uploaded - PROJECT VI.docx DEVELOP AN IN-DEPTH SCHEDULE FOR THE PROJECT YOU SELECTED AND USED TO DEVELOP THE STATEMENT OF WORK AND WORK BREAKDOWN STRUCTURE IN UNIT III Source - Another student's paper Develop an in-depth schedule for the project you selected and used to develop the statement of work and work breakdown structure in Unit III Suspected Entry: 100% match Uploaded - PROJECT VI.docx PLEASE REFER TO THE INTEGRATED PROJECT IN CHAPTER 10 ON PAGE 363 (PROJECT SCHEDULING) OF THE TEXTBOOK FOR MORE INFORMATION Source - Another student's paper Please refer to the Integrated Project in Chapter
  • 16. 10 on page 363 (Project Scheduling) of the textbook for more information Suspected Entry: 100% match Uploaded - PROJECT VI.docx BE SURE TO INCLUDE THE FOLLOWING COMPONENTS Source - Another student's paper Be sure to include the following components Suspected Entry: 100% match Uploaded - PROJECT VI.docx · AN ACTIVITY PRECEDENCE DIAGRAM, · AN ACTIVITY DURATION TABLE, AND · A NETWORK DIAGRAM AND GANTT CHARTS Source - Another student's paper · an activity precedence diagram, · an activity duration table, and · a network diagram and Gantt charts Suspected Entry: 100% match
  • 17. Uploaded - PROJECT VI.docx · AN ACTIVITY PRECEDENCE DIAGRAM Source - Another student's paper · An activity precedence diagram Suspected Entry: 100% match Uploaded - PROJECT VI.docx ACTIVITY DURATION TABLE Source - Another student's paper Activity duration table Suspected Entry: 100% match Uploaded - PROJECT VI.docx ACTIVITY EXPECTED DURATION PREDECESSOR Source - Another student's paper Activity Expected Duration Predecessor Suspected Entry: 100% match Uploaded - PROJECT VI.docx
  • 18. A 5 DAYS ---- Source - Another student's paper A 5 days ---- Suspected Entry: 99% match Uploaded - PROJECT VI.docx B 10 DAYS A Source - Another student's paper B 10 days A Suspected Entry: 99% match Uploaded - PROJECT VI.docx C 8 DAYS A Source - Another student's paper C 8 days A Suspected Entry: 100% match Uploaded - PROJECT VI.docx D 1 DAY A Source - Another student's paper D 1 day A
  • 19. Suspected Entry: 100% match Uploaded - PROJECT VI.docx E 5 DAYS B, C Source - Another student's paper E 5 days B, C Suspected Entry: 99% match Uploaded - PROJECT VI.docx F 10 DAYS D, E Source - Another student's paper F 10 days D, E Suspected Entry: 99% match Uploaded - PROJECT VI.docx G 14 DAYS F Source - Another student's paper G 14 days F Suspected Entry: 99% match Uploaded - PROJECT VI.docx
  • 20. H 3 DAYS G Source - Another student's paper H 3 days G Suspected Entry: 100% match Uploaded - PROJECT VI.docx I 12 DAYS F Source - Another student's paper I 12 days F Suspected Entry: 100% match Uploaded - PROJECT VI.docx J 6 DAYS H, I Source - Another student's paper j 6 days H, I Suspected Entry: 100% match Uploaded - PROJECT VI.docx A NETWORK DIAGRAM AND GANTT CHARTS
  • 21. Source - Another student's paper A network diagram and Gantt charts Suspected Entry: 100% match Uploaded - PROJECT VI.docx PLEASE COMPLETE CASE STUDY 10.1 Source - Another student's paper Please complete Case Study 10.1 Suspected Entry: 99% match Uploaded - PROJECT VI.docx PROJECT SCHEDULING AT BLANQUE CHECK CONSTRUCTION ON PAGE 360 OF THE TEXTBOOK, AND ANSWER THE THREE QUESTIONS AT THE END Source - Another student's paper Project Scheduling at Blanque Check Construction on page 360 of the textbook and answer the three questions at the end Suspected Entry: 100% match
  • 22. Uploaded - PROJECT VI.docx C=DIFFERENT CONSRUCTION TYPES OF SCHEDULING METHODS TYPE FROM 1 TO 9 P= DIFFERENT CONSRUCTION PROJECTS WHICH SHOW THE TYPES OF SCHEDULING METHODS TYPE FROM 1 TO 9 O1=ORGANIZATION ONE O2= ORGANIZATION 2 Source - Another student's paper C=DIFFERENT CONSRUCTION TYPES OF SCHEDULING METHODS TYPE FROM 1 TO 9 P= DIFFERENT CONSRUCTION PROJECTS WHICH SHOW THE TYPES OF SCHEDULING METHODS TYPE FROM 1 TO 9 O1=ORGANIZATION ONE O2= ORGANIZATION 2 Suspected Entry: 100% match Uploaded - PROJECT VI.docx
  • 23. S E C4 C5 O1 P9 P8 O2 P7 P6 P5 P4 P3 P2 C9 C8 C7 C6 C1 C2 C3 P1 Source - Another student's paper S E C4 C5 O1 P9 P8 O2 P7 P6 P5 P4 P3 P2 C9 C8 C7 C6 C1 C2 C3 P1 Suspected Entry: 100% match Uploaded - PROJECT VI.docx Q2(ANS) ACCORDING TO MY RESEARCH LEVEL AND LITERATURE REVIEW THE EXPERT OPINION AND PAST HISTORY BOTH ARE THE BEST TO SOLVE PROBLEM FOR CALCULATING THE CRITICAL PATH ,WHICH MAY ALSO TELL US THE DURATION OR PROJECT DELAY TO HANDLE OR RUN OUR CONSTRUCTION COMPANY Source - Another student's paper
  • 24. Q2(ANS) According to my research level and literature review the expert opinion and past history both are the best to solve problem for calculating the critical path ,which may also tell us the duration or project delay to handle or run our construction company Suspected Entry: 100% match Uploaded - PROJECT VI.docx Q3(ANS) THESE BOTH HAVE SOME STRENGTHENS AND WEAKNESSES AND BOTH GIVE THE RESULTS PROBABLY SAME , BUT ACCORDING TO LITERATURE AOA IS THE BENEFICIAL FOR MODELING IT WILL BE HELPFUL AND IN THE BUSINESS FIELD IT WILL BE IMPORTANT AON WILL BE LESS WIDELY USED , IN CASE OF LARGE AND COMPLEX PROJECTS IT IS EASIER TO EMPLOY THE PATH PROCESS
  • 25. USED IN THE AOA Source - Another student's paper Q3(ANS) These both have some strengthens and weaknesses and both give the results probably same , but according to literature AOA is the beneficial for modeling it will be helpful and in the business field it will be important AON will be less widely used , in case of large and complex projects it is easier to employ the path process used in the AOA Suspected Entry: 100% match Uploaded - PROJECT VI.docx ACCORDING TO AOA WE ACHIEVE THE EVERY MILESTONE AND PARTICULARLY USED THE DUMMY PROJECTS OR ACTIVITIES THE CONCEPT OF DUMMY PROJECT IS NOT SIMPLE AND EASY IT REQUIRE MORE TRAINING AND PRACTICE
  • 26. Source - Another student's paper according to AOA we achieve the every milestone and particularly used the dummy projects or activities the concept of dummy project is not simple and easy it require more training and practice Suspected Entry: 100% match Uploaded - PROJECT VI.docx AON CONVENTION ,AOA NETWORK USED BOTH NODES AND ARROW TO LABEL THE PROJECT Source - Another student's paper AON Convention ,AOA network used both nodes and arrow to label the project Suspected Entry: 100% match Uploaded - PROJECT VI.docx DEVELOP A NETWORK ACTIVITY CHART,
  • 27. AND IDENTIFY THE CRITICAL PATH FOR A PROJECT BASED ON THE INFORMATION PROVIDED IN THE GANTT CHART BELOW Source - Another student's paper Develop a network activity chart and identify the critical path for a project based on the information provided in the Gantt chart below Suspected Entry: 100% match Uploaded - PROJECT VI.docx DRAW THE ACTIVITY NETWORK AS A GANTT CHART Source - Another student's paper Draw the activity network as a Gantt chart Suspected Entry: 100% match Uploaded - PROJECT VI.docx WHAT IS THE EXPECTED DURATION OF THE PROJECT Source - Another student's paper
  • 28. What is the expected duration of the project Suspected Entry: 100% match Uploaded - PROJECT VI.docx ACTIVITY EXPECTED DURATION PREDECESSOR Source - Another student's paper Activity Expected Duration Predecessor Suspected Entry: 100% match Uploaded - PROJECT VI.docx Source - Another student's paper A 5 DAYS ---- A 5 days ---- Suspected Entry: 99% match Uploaded - PROJECT VI.docx B 10 DAYS A Source - Another student's paper B 10 days A Suspected Entry: 99% match Uploaded - PROJECT VI.docx
  • 29. C 8 DAYS A Source - Another student's paper C 8 days A Suspected Entry: 100% match Uploaded - PROJECT VI.docx D 1 DAY A Source - Another student's paper D 1 day A Suspected Entry: 100% match Uploaded - PROJECT VI.docx E 5 DAYS B, C Source - Another student's paper E 5 days B, C Suspected Entry: 99% match Uploaded - PROJECT VI.docx F 10 DAYS D, E Source - Another student's paper F 10 days D, E
  • 30. Suspected Entry: 99% match Uploaded - PROJECT VI.docx G 14 DAYS F Source - Another student's paper G 14 days F Suspected Entry: 99% match Uploaded - PROJECT VI.docx H 3 DAYS G Source - Another student's paper H 3 days G Suspected Entry: 100% match Uploaded - PROJECT VI.docx I 12 DAYS F Source - Another student's paper I 12 days F Suspected Entry: 100% match Uploaded - PROJECT VI.docx
  • 31. J 6 DAYS H, I Source - Another student's paper j 6 days H, I Suspected Entry: 100% match Uploaded - PROJECT VI.docx AN ACTIVITY PRECEDENCE DIAGRAM Source - Another student's paper · An activity precedence diagram Suspected Entry: 99% match Uploaded - PROJECT VI.docx THE TOTAL PATHS CAN BE CALCULATED THERE THE FIRST DIAGRAM CAN BE DEFINED THE OVERALL PATHS WHICH ARE GIVEN BELOW Source - Another student's paper The total paths can be calculated there the first diagram can be defined the overall paths which are given below
  • 32. Suspected Entry: 100% match Uploaded - PROJECT VI.docx ABEFIJ=5+10+5+10+12+6=48 ABEFGHJ=5+10+5+10+14+3+6=53 Source - Another student's paper ABEFIJ=5+10+5+10+12+6=48 ABEFGHJ=5+10+5+10+14+3+6=53 ACEFIJ=5+8+5+10+12+6=46 ACEFGHJ=5+10+5+10+14+3+6=51 ADFIJ=5+1+10+12+6=34 ADFGHJ=5+1+10+14+3+6=39 ACEFIJ=5+8+5+10+12+6=46 ACEFGHJ=5+10+5+10+14+3+6=51 ADFIJ=5+1+10+12+6=34 ADFGHJ=5+1+10+14+3+6=39 Suspected Entry: 99% match Uploaded - PROJECT VI.docx
  • 33. THE 2ND PATH CAN BE CONSTRUCTED FOR THE CRITICAL PATH WHICH HAVE THE LONGEST PATH DURATION Source - Another student's paper The 2nd path can be constructed for the critical path which have the longest path duration Suspected Entry: 99% match Uploaded - PROJECT VI.docx ABEFGHJ=5+10+5+10+14+3+6=53 ITS KNOWN AS A CRITICAL PATH FOR THE GIVEN ACTIVITY Source - Another student's paper ABEFGHJ=5+10+5+10+14+3+6=53 Its known as a critical path for the given activity Suspected Entry: 99% match Uploaded - PROJECT VI.docx PRECEDENCE DIAGRAM AND CRITICAL PATH
  • 34. Source - Another student's paper Precedence diagram and critical path Suspected Entry: 100% match Uploaded - PROJECT VI.docx END H J G F E B A A J H G E F I START D C B J END START END END Source - Another student's paper end H j G F E B A A J H G E F I START D C B J END START end END Suspected Entry: 100% match Uploaded - PROJECT VI.docx Source - Another student's paper USING THE INFORMATION PROVIDED IN THE GANTT CHART BELOW, CONSTRUCT THE PROJECT ACTIVITY NETWORK USING THE ACTIVITY-ON-NODE (AON) METHODOLOGY, AND LABEL EACH NODE Using the information provided in the Gantt
  • 35. chart below, construct the project activity network using the activity-on-node (AON) methodology, and label each node Suspected Entry: 100% match Uploaded - PROJECT VI.docx IDENTIFY THE CRITICAL PATH AND OTHER PATHS THROUGH THE NETWORK Source - Another student's paper Identify the critical path and other paths through the network Suspected Entry: 100% match Uploaded - PROJECT VI.docx E, F, G Source - Another student's paper E, F, G Suspected Entry: 100% match Uploaded - PROJECT VI.docx ACTIVITY DURATION ES EF LS
  • 36. Source - Another student's paper Activity Duration ES EF LS Suspected Entry: 100% match Uploaded - PROJECT VI.docx A 3 0 3 0 Source - Another student's paper A 3 0 3 0 Suspected Entry: 100% match Uploaded - PROJECT VI.docx B 5 3 8 8 Source - Another student's paper B 5 3 8 8 Suspected Entry: 100% match Uploaded - PROJECT VI.docx C 7 3 10 3 Source - Another student's paper C 7 3 10 3
  • 37. Suspected Entry: 100% match Uploaded - PROJECT VI.docx D 3 10 13 13 Source - Another student's paper D 3 10 13 13 Suspected Entry: 100% match Uploaded - PROJECT VI.docx E 5 8 13 13 Source - Another student's paper E 5 8 13 13 Suspected Entry: 100% match Uploaded - PROJECT VI.docx F 4 13 17 13 Source - Another student's paper F 4 13 17 13 Suspected Entry: 100% match Uploaded - PROJECT VI.docx G 2 10 12 15
  • 38. Source - Another student's paper G 2 10 12 15 Suspected Entry: 99% match Uploaded - PROJECT VI.docx H 5 17 22 17 Source - Another student's paper H 5 17 22 17 Suspected Entry: 100% match Uploaded - PROJECT VI.docx 1 PART 1 Source - Another student's paper 1 Part 1 Suspected Entry: 100% match Uploaded - PROJECT VI.docx 0 3 0 Source - Another student's paper 0 3 0
  • 39. Suspected Entry: 100% match Uploaded - PROJECT VI.docx 8 5 13 Source - Another student's paper 8 5 13 Suspected Entry: 100% match Uploaded - PROJECT VI.docx 3 5 17 Source - Another student's paper 3 5 17 Suspected Entry: 100% match Uploaded - PROJECT VI.docx 13 3 13 Source - Another student's paper 13 3 13 Suspected Entry: 100% match Uploaded - PROJECT VI.docx 17 5 22
  • 40. Source - Another student's paper 17 5 22 Suspected Entry: 100% match Uploaded - PROJECT VI.docx 13 4 17 Source - Another student's paper 13 4 17 Suspected Entry: 100% match Uploaded - PROJECT VI.docx 3 7 10 Source - Another student's paper 3 7 10 Suspected Entry: 100% match Uploaded - PROJECT VI.docx 15 2 17 Source - Another student's paper 15 2 17
  • 41. Suspected Entry: 100% match Uploaded - PROJECT VI.docx ES ID EF Source - Another student's paper ES ID EF Suspected Entry: 100% match Uploaded - PROJECT VI.docx LS DURATION LF Source - Another student's paper LS DURATION LF Suspected Entry: 99% match Uploaded - PROJECT VI.docx THE CRITICAL PATH CAN BE CHOOSE WHICH HAVE THE MINIMUM SLACK AND THEN FIND THE DURATION OR DELAY OF CRITICAL PATH FIRST OF ALL WE FIND THE CRITICAL PATH OF GIVEN ACTIVITY THE CRITICAL PATH HAVE MINIMUM
  • 42. SLACK BUT DELAY SHOULD BE MAXIMUM ,WHICH ARE GIVEN BELOW Source - Another student's paper The critical path can be choose which have the minimum slack and then find the duration or delay of critical path first of all we find the critical path of given activity the critical path have minimum slack but delay should be maximum, which are given below Suspected Entry: 100% match Uploaded - PROJECT VI.docx ACDFH=3+7+3+4+5=22DAYS/MIN WITH THE CRITICAL POINT OF SLACK THE FLEXIBILITY OF THE PROJECT IS LIMITED Source - Another student's paper ACDFH=3+7+3+4+5=22days/min With the critical point of slack, the flexibility of the project
  • 43. is limited Running head: UNIT VI PROJECT 1 Part 1: UNIT VI PROJECT 6 Unit VI Project Your Name Columbia Southern University Part 1 Develop an in-depth schedule for the project you selected and used to develop the statement of work and work breakdown structure in Unit III. Please refer to the Integrated Project in Chapter 10 on page 363 (Project Scheduling) of the textbook for more information. Be sure to include the following components: · an activity precedence diagram, · an activity duration table, and · a network diagram and Gantt charts. Part 2 Please complete Case Study 10.1: Project Scheduling at Blanque
  • 44. Check Construction on page 360 of the textbook, and answer the three questions at the end. Part 3 Develop a network activity chart, and identify the critical path for a project based on the information provided in the Gantt chart below. Draw the activity network as a Gantt chart. What is the expected duration of the project? Activity Expected Duration Predecessor A 5 days ---- B 10 days A C 8 days A D 1 day A E 5 days B, C F 10 days D, E G 14 days F H
  • 45. 3 days G I 12 days F j 6 days H, I Part 4 Using the information provided in the Gantt chart below, construct the project activity network using the activity-on-node (AON) methodology, and label each node. Identify the critical path and other paths through the network. Activity Duration Predecessors A 3 -- B 5 A C