This document discusses a case study on network analysis. It presents the activities involved in erecting a storage steel shed for an industrial unit, including erecting a site workshop, fencing the site, bending reinforcement, digging foundations, fabricating steel work, installing a concrete making plant, placing reinforcement, concreting the foundation, painting steel work, erecting the steel structure, and giving finishing touches. It rewrites the predecessor relationships between activities and draws the network diagram showing the sequence of the 11 activities and their dependencies.