4.11 Case 1: Determination of
Float/Slack in CPM Network
CalculationsPresented By:
Dr. V. M. Tidake
Ph. D (Financial Management), MBA(FM), MBA(HRM) BE(Chem)
Dean EDP & Associate Professor MBA
2
Sanjivani College of Engineering, Kopargaon
Department of MBA
www.sanjivanimba.org.in
4. www.sanjivanimba.org.in
NETWORK CALCULATIONS
The following table gives the activities in a construction project and
other relevant information-
1. Draw the Network for the project
2. Find the Critical Path
3. Determine the expected project completion time
4. Prepare an activity schedule showing ES, EF, LS, LF and float.
Activity Duration (Days)
1-2 20
1-3 25
2-3 10
2-4 12
3-4 6
4-5 10