SlideShare a Scribd company logo
1 of 52
Construction Disputes
Dr. Khaled Hesham Hyari
Department of Civil Engineering
The Hashemite University
2
-
5
1. Introduction
2. Construction Site Disputes
3. Sources of Construction Site Disputes
4. Planning for Problems
5. The Role of Relationships
6. What to do if a problem arises?
7. Avoiding Construction Disputes
8. Job Site Dispute Resolution
9. Resolving Construction Disputes
Content
3
-
5
• The construction industry is not as famous for
its construction quality as it is for its
confrontation, claims, and litigation
• The attributes of honor, integrity, and pride in
workmanship have been replaced with
conflict, claims, delayed projects and cost
overruns
1. Introduction
4
-
5
• Talk with anyone in the construction industry
and ask them is there a project you have
completed without any conflict? The answer in
100% of the time will be no
• The construction project does not exist that
hasn't seen some kind of misunderstanding,
disagreement, problem, unforeseen event,
design error or construction defect
• You cannot avoid conflict
2. Construction Site Disputes I
5
-
5
• Not all of these situations evolve into disputes,
however, and not all disputes become claims or
lawsuits.
• Don’t get confused with indecision,
disagreement, stress or other common
experiences that may cause, or be caused by
conflict.
– By definition, conflict only occurs between
parties who need each other and who cannot
simply leave the relationship with no negative
consequences.
2. Construction Site Dispute II
6
-
5
• Quality of work (Defective work)
• Responsibility for delays
• Differing Site Conditions
• Incomplete Scope Definition
• Poor communications
• Suspension of Work
• Disruption
• Variation Orders
• Variations in Estimated Quantities
• Inappropriate contract type
• Defective Specifications and Drawings
• Acceleration of the Work
• Force Majeure
3. Sources of Construction Site Disputes
7
-
5
• Many disputes are cumulative.
– Unresolved small problems create antagonisms
between the parties and make it more difficult to
resolve new conflicts as they arise.
– It is not uncommon for parties to wait until the end
of the project to address all of the unresolved
disputes that have arisen.
– While they are waiting, their unstated expectations
continue to go unmet, and the level of antagonism
rises.
– In a nasty circle, as relationships deteriorate, the
cooperation so vital to the success of a project also
erodes.
– Mistrust may begin to cause delays and disruptions,
which in turn cause added costs that then breed
more problems.
4. Planning for Problems I
8
-
5
• Against this volatile background, the stage is
set for a serious dispute. When the final
straw, perhaps an error occurs, serious but
otherwise forgivable, it may be too late for
negotiations.
• The longer the resolution of a problem is put
off, the more expensive it is to correct.
4. Planning for Problems II
9
-
5
• As time goes by, what might have required
only a quick and relatively inexpensive
solution becomes a difficult and costly defect
to remedy.
• The best and least expensive way is to have a
project-wide commitment that at the first
indication of a problem, participants will work
together to resolve it and not allow it to
escalate into a dispute where third-party
resolution is required.
4. Planning for Problems III
10
-
5
• Establishing trust among parties:
–Requires at least one person willing to risk
something.
–Trust also demands open and unbiased
communication. One way to do this is to try
to put yourself in the other parties' places
5. The Role of Relationships I
11
-
5
• Parties who are aware that their relationship
will be of brief duration are more likely to
resist agreement.
• On the other hand, if all parties to the conflict
have had or anticipate a long-term
relationship, cooperation is more likely
5. The Role of Relationships II
12
-
5
• Remain calm
• Report the incident immediately
• Keep seeking alternatives and solutions
• Do not automatically assume you are responsible,
no matter what the facts first seem to indicate
• Communicate
• Document and photograph
• Try to resolve the conflict with the others involved. If
direct negotiation fails, seek mediation by a third
party
6. What to do if a problem arises? I
13
-
5
• Remain calm
– Examine any accusation calmly and objectively
– Authorities on dispute handling recommend that
you assume a neutral attitude, and seek to
understand the other party's position
– This is much more productive than a quick and
heated denial
6. What to do if a problem arises? II
14
-
5
• Report the incident immediately.
–Do not wait until someone has made a
formal claim against you.
–Be sure that your staff understands that
reporting such a situation is positive
behavior to be rewarded, not punished
–The longer a problem is ignored, the more
expensive and difficult its resolution is
–If your sixth sense is telling you something
is wrong, report it.
6. What to do if a problem arises? III
15
-
5
• Keep seeking alternatives and solutions.
– Remain flexible and continue to seek solutions to
a conflict before it escalates into a major lawsuit
– Allow yourself and your associates the freedom
to keep generating ideas for solving the problem
– Together, you may be able to come up with a
creative solution that will work for everyone
6. What to do if a problem arises? IV
16
-
5
• Do not automatically assume you are
responsible, no matter what the facts first
seem to indicate.
– Any loss situation involves many factors; do not
try to rush to a verdict before all the facts have
been evaluated.
– It is almost impossible to undo the damage done
when you mistakenly assume responsibility and
communicate it to the other parties connected
with the loss
6. What to do if a problem arises? V
17
-
5
• Communicate.
– Although you should not automatically assume
responsibility, do not cease communicating with
others
– Keep talking and listening
– Certainly, continued communication will help
preserve your relationships with the other party
and may motivate everyone to resolve the
dispute quickly
6. What to do if a problem arises? VI
18
-
5
• Document and photograph.
– All data and correspondence relating to the
dispute should be documented. Keep detailed
notes on all communications.
– Notes and records not only help clarify the issue
but will also be needed by any lawyer who may
come to your rescue in the event of a suit.
– "A picture is worth a thousand words" still holds
true in potential claims situations. Photographing
or videotaping the disputed subject matter is an
excellent way of preserving the record for the
future.
6. What to do if a problem arises? VII
19
-
5
• Try to resolve the conflict with the others
involved. If direct negotiation fails, seek
mediation by a third party
– Sit down and talk to the other parties ASAP, try to
find a solution you can all live with
– If informal negotiations fail, invite a neutral,
experienced mediator to help you reach a
settlement
– If these processes fail, or are not attempted, the
dispute could escalate into binding arbitration or
litigation
6. What to do if a problem arises? VIII
20
-
5
Prevention
7. Avoiding Construction Disputes I
• “For every $1 you spend on disputes
management during the front-end of the
project, you will save at least $20 to $25 on
claims during construction”
21
-
5
• Recommendations for Conflict Prevention
(Avoidance):
– Partnering & Team Building
– Incentives for Cooperation
– Realistic Risk Allocation
– Constructability Analysis
– Dispute Resolution Clauses
– Competent Engineering & Documentation
– Training and Development
– Honesty in Contracting
– Continuity of Personnel
7. Avoiding Construction Disputes II
22
-
5
• Recommendations for Conflict Prevention
(Avoidance):
– Being ready for unforeseen or changed conditions
– Balancing interests of team members with regard
to schedule, payments, decision making, and
performance.
– Performing contract obligations on time
7. Avoiding Construction Disputes III
23
-
5
Project Partnering & Team Building I
• The goal is to create a shared vision of the project
• The concept behind today's partnering is to dispel
the adversarial "us-versus-them" approach often
found on today's construction projects and to
promote "let's-all-pull together" attitudes.
• Typically, partnering involves a series of workshops
with representatives from all parties to the project
• A facilitator conducts team-building activities aimed
at achieving mutually agreed-upon goals
24
-
5
• The benefits of partnering can be significant
– The quality of the project is typically improved
– The workplace tends to be safer
– Partnered projects tend to be brought in on time
or even ahead of schedule and the process
typically helps reduce cost overruns
– The designers' roles in the problem-solving
process may be enhanced and their participation
in construction phase services is more likely
– Best of all, there is a reduced exposure to
litigation for all parties to the project
Project Partnering & Team Building II
25
-
5
• For partnering to work, it must be owner-
driven and have the full backing of the top
management of all participating team
members
• Partnering does not guarantee that disputes
will not arise
–It is a way to manage and resolve the
disputes that do come up
Project Partnering & Team Building III
26
-
5
• Partnering has had great success and holds
even greater promise for the future.
• It is a straightforward and proven mechanism
to handle construction disputes as they were
once handled
Project Partnering & Team Building IV
27
-
5
• Cost/Schedule Incentive Matrix
– A matrix that defines incentives to contractors for
certain reductions in time and cost of the project
• Subjective determination of fee
– In cost + fee projects a portion of the fee is
awarded based on owner’s evaluation of
performance
Incentives for Cooperation
28
-
5
• Structuring contracts to allocate risks clearly and
fairly.
• A study by Shen (1997) surveyed 85 contractors in
Hong Kong and identified the following sources of
risk:
– Insufficient or incorrect design information
– Variations in ground and weather conditions
– Subcontractors’ manpower shortage
– Shortage of materials/plant resources
– Poor coordination with subcontractors
– Poor accuracy of project plan
– Shortage of skills/techniques
– failed works due to poor workmanship
Realistic Risk Allocation
29
-
5
Equitable Risk Sharing
• A study by Vega (1997) on risk sharing in
large infrastructure projects, it was
concluded that
– “The general guiding principle of risk
allocation should be that the different parties
involved should seek a multi-beneficial
distribution risk. A dominant party that off-
loads all project risks onto others is unlikely to
enhance the chances for a successful
outcome.”
Realistic Risk Allocation II
30
-
5
• Reduces disagreements because it eliminates
errors, omissions, and impractical details
• The contractor assigns engineers to work with
the design team in order to improve
construction details
• Performed during the planning, design, and
procurement phases
Constructability Analysis
31
-
5
• A well-drafted contract provides procedures for
conflict resolution without involving courts. (i.e.
ADR).
• Examples include:
– Relying on designer to resolve conflicts between
the owner and contractor;
– Using third-party mediator to help participants
structure negotiations, provide neutral evaluation
and encourage fair settlement;
– The use of dispute review board judges, or
standing neutrals to resolve disputes and
– Binding arbitration.
Dispute Resolution Clauses
32
-
5
• Step Negotiations: A commitment to solve a
problem ASAP at the lowest possible level of
management
– If parties directly involved cannot resolve a
problem at the job site, their supervisors then
meet to work out a solution
– If they, in turn, cannot agree, then the problem will
be passed on to higher management in both
organizations, and so on
8. Job Site Dispute Resolution I
33
-
5
• Step Negotiations
– Often each of these parties is identified at the
beginning of the project and there may be a
predetermined time limit for resolving an issue at
a given level
8. Job Site Dispute Resolution II
34
-
5
• An important task for construction project
managers. The mechanism for dispute
resolution can be specified in the original
contract or, less desireably, decided when a
dispute arises.
9. Resolving Construction Disputes I
35
-
5
Escalating
Hostility
and Cost
Mediation
Prevention
Negotiation
Standing Neutral
Arbitration
Litigation
9. Resolving Construction Disputes II
36
-
5
Prevention
Negotiation
9. Resolving Construction Disputes III
• Step 2: Negotiation:
– Typically does not involve third parties such as
judges
– The negotiation process is usually informal,
unstructured and relatively inexpensive.
37
-
5
Prevention
Negotiation
Standing Neutral
• Step 3: Standing Neutral
– The concept of a standing neutral involves an
independent person, or persons, who is/are totally
neutral to the problem
9. Resolving Construction Disputes IV
38
-
5
• Standing Neutral:
– At the beginning of the construction phase of the
project, the parties select one or more independent
construction industry experts to be available as a
standing neutral throughout the project
– The neutral acts immediately to resolve any dispute
which the parties can not resolve themselves.
– Terms such as dispute review board, standing
mediator, and standing arbitrator are also used.
9. Resolving Construction Disputes V
39
-
5
• Dispute Review Board
– Commonly consists of three members: a representative
from the owner, one from the contractor and a third,
selected by these two representatives. The third member
chairs the board
– The members usually have experience in the kind of
construction work being undertaken and are also familiar
and experienced in dispute resolution
– It is important that all the board members are independent
of any of the contracting parties, although they are paid by
them
9. Resolving Construction Disputes VI
40
-
5
• Essential elements of a successful DRB:
– All members are neutral and subject to the
approval of both parties
– All members sign a three party agreement
obligating them to serve both parties equally and
fairly
– All fees and expenses of the DRP are shared
equally by the parties
– The DRP is organized when work begins, before
there are any disputes
– The DRP keeps an eye on job developments by
means of relevant documentation and regular site
visits
9. Resolving Construction Disputes VII
41
-
5
• Essential elements of a successful DRB:
– An informal but comprehensive hearing is
arranged promptly
– The written recommendations of the DRP are not
binding on either party but are permissible as
evidence, to the extent permitted by law, in case
of later arbitration or litigation
– The members are released from any personal or
professional liability arising from their DRP
activities
9. Resolving Construction Disputes VIII
42
-
5
Mediation
Prevention
Negotiation
Standing Neutral
• Step 4 Mediation: A process in which the parties to a
dispute, with the assistance of a neutral third party
(the mediator), identifies the disputed issues, develop
options, consider alternatives and endeavor to reach
an agreement
9. Resolving Construction Disputes IX
43
-
5
• Mediation
– It is a non-binding resolution
– In mediation, the third party serves only as a
facilitator to help the participants reach a mutually
acceptable resolution.
– The mediator has no advisory or determinative
role in regard to the content of the dispute or the
outcome of its resolution
9. Resolving Construction Disputes X
44
-
5
Mediation
Prevention
Negotiation
Standing Neutral
Arbitration
•Step 5: Arbitration
9. Resolving Construction Disputes XI
• Binding arbitration:
Referral of a dispute to
one or more impartial
persons for final and
binding determination.,
• Designed for quick,
practical, and
economical settlements.
45
-
5
• Arbitration
– In this procedures, a third party serves a central
role in the resolution.
– These outside parties are usually chosen by
mutually agreement of the parties involved and will
have specialized knowledge of the dispute subject.
– The third party may make a decision which is
binding on the participants
– It is a binding resolution mechanism.
• Arbitration has evolved to a form very similar to
litigation, which defies its purpose
9. Resolving Construction Disputes XII
46
-
5
Non-Binding Resolution
Prevention
Negotiation
Standing Neutral
Binding Resolution
Litigation
• Step 6: Litigation
– Litigation of
construction
disputes is usually
complex,
expensive, and
time consuming.
9. Resolving Construction Disputes XIII
47
-
5
• In most cases, litigation is the last resort and least
preferable way to resolve a dispute.
• In such instances, the parties are wise to conduct a
thorough and objective review of the costs and
benefits of litigation throughout the conflict.
• If litigation remains an option, each participant
carefully evaluates not only the merits of his or her
case, but also the likelihood of how well the facts
can be presented in a formal judicial proceeding.
9. Resolving Construction Disputes XIV
48
-
5
• Main problems with litigation
– Too expensive
– Time consuming since it involves legal
representation and waiting in queues of cases
for available court times Too slow
– Lack of equality between powerful and under
resourced litigants
– Difficult to forecast cost and length of litigation
– Incomprehensible by many litigants
– Too adversarial
9. Resolving Construction Disputes XV
49
-
5
• Litigation Costs: In pursuit of legal remedies
(litigation or arbitration), substantial direct and
indirect costs are involved included, but not limited
to:
– Direct external costs, e.g. attorneys’ fees, court
costs, deposition costs, expert fees, investigation
costs (soil, hydrology, testing).
– Direct internal costs, e.g. costs of key personnel
working with attorneys and experts, attending
forum proceedings, and other incidental costs.
9. Resolving Construction Disputes XVI
50
-
5
• Litigation Costs
– Indirect costs, e.g. the interruption of management
and key personnel duties, impacts on reputation,
reduction in bonding capacity, interruption of cash
flow, etc.
– Loss of client relationship (temporarily or
permanent).
9. Resolving Construction Disputes XVII
51
-
5
Escalating
Hostility
and Cost
Mediation
Prevention
Negotiation
Standing Neutral
Arbitration
Litigation
Construction Dispute Resolution Steps
52
-
5
• List 5 possible issues that might lead to a
conflict in a construction project. Be specific
and illustrate the reason for disagreement
between the conflicting parties
• One page
• Due one week from now
Homework

More Related Content

What's hot

Construction Documents
Construction DocumentsConstruction Documents
Construction Documents
Allan Berry
 
Estimation (power point)
Estimation (power point)Estimation (power point)
Estimation (power point)
Waqas Aslam
 

What's hot (20)

BIDDING-TENDER-CONTRACT
BIDDING-TENDER-CONTRACTBIDDING-TENDER-CONTRACT
BIDDING-TENDER-CONTRACT
 
Construction Documents
Construction DocumentsConstruction Documents
Construction Documents
 
Introduction to construction management
Introduction to construction managementIntroduction to construction management
Introduction to construction management
 
Fidic conditions of contract presentation
Fidic conditions of contract presentationFidic conditions of contract presentation
Fidic conditions of contract presentation
 
TENDER DOCUMENT
TENDER DOCUMENTTENDER DOCUMENT
TENDER DOCUMENT
 
Fidic Form of Contract.
Fidic Form of Contract.Fidic Form of Contract.
Fidic Form of Contract.
 
Estimation (power point)
Estimation (power point)Estimation (power point)
Estimation (power point)
 
Duties and job roles of QS.pptx
Duties and job roles of QS.pptxDuties and job roles of QS.pptx
Duties and job roles of QS.pptx
 
time cost trade off
 time cost trade off time cost trade off
time cost trade off
 
Introduction to construction project management
Introduction to construction project managementIntroduction to construction project management
Introduction to construction project management
 
Construction contracts
Construction contractsConstruction contracts
Construction contracts
 
Construction Cost Control
Construction Cost ControlConstruction Cost Control
Construction Cost Control
 
Preparation of boq
Preparation of boqPreparation of boq
Preparation of boq
 
contract administration PPT
 contract administration PPT contract administration PPT
contract administration PPT
 
Construction Planning
Construction PlanningConstruction Planning
Construction Planning
 
Contract & Tender Management
Contract & Tender ManagementContract & Tender Management
Contract & Tender Management
 
Arbitration Of Construction Disputes
Arbitration Of Construction DisputesArbitration Of Construction Disputes
Arbitration Of Construction Disputes
 
Tenders for construction
Tenders for constructionTenders for construction
Tenders for construction
 
Types of contracts
Types of contractsTypes of contracts
Types of contracts
 
Project Controls Expo 18th Nov 2014 - "PACING DELAY The Practical Effect on C...
Project Controls Expo 18th Nov 2014 - "PACING DELAY The Practical Effect on C...Project Controls Expo 18th Nov 2014 - "PACING DELAY The Practical Effect on C...
Project Controls Expo 18th Nov 2014 - "PACING DELAY The Practical Effect on C...
 

Similar to 2. construction disputes

Stay_out_of_Litigation[1]-practical tips
Stay_out_of_Litigation[1]-practical tipsStay_out_of_Litigation[1]-practical tips
Stay_out_of_Litigation[1]-practical tips
Subramaniam Ramaswamy
 
Negotiation in Employee Relations
Negotiation in Employee Relations Negotiation in Employee Relations
Negotiation in Employee Relations
parags06
 
Negotiation skills
Negotiation skillsNegotiation skills
Negotiation skills
fluffy_fury
 
Decision Making & Negotiating
Decision Making & NegotiatingDecision Making & Negotiating
Decision Making & Negotiating
Rajiv Bajaj
 

Similar to 2. construction disputes (20)

Early Dispute Resolution in the Construction Industry
Early Dispute Resolution in the Construction IndustryEarly Dispute Resolution in the Construction Industry
Early Dispute Resolution in the Construction Industry
 
Being the Best We Can be Through Working Together
Being the Best We Can be Through Working TogetherBeing the Best We Can be Through Working Together
Being the Best We Can be Through Working Together
 
Conflict resolution techniques for the pmp certification exam
Conflict resolution techniques for the pmp certification examConflict resolution techniques for the pmp certification exam
Conflict resolution techniques for the pmp certification exam
 
Stay_out_of_Litigation[1]-practical tips
Stay_out_of_Litigation[1]-practical tipsStay_out_of_Litigation[1]-practical tips
Stay_out_of_Litigation[1]-practical tips
 
Negotiation skills
Negotiation skillsNegotiation skills
Negotiation skills
 
Flawless consulting 08292013
Flawless consulting 08292013Flawless consulting 08292013
Flawless consulting 08292013
 
CONFLICT AND NEGOTATIONS
CONFLICT AND NEGOTATIONSCONFLICT AND NEGOTATIONS
CONFLICT AND NEGOTATIONS
 
Breakthrough Negotiation Skills
Breakthrough Negotiation SkillsBreakthrough Negotiation Skills
Breakthrough Negotiation Skills
 
Negotiation skills
Negotiation skillsNegotiation skills
Negotiation skills
 
TOPIC8.pdf
TOPIC8.pdfTOPIC8.pdf
TOPIC8.pdf
 
Conducting the Mediation
Conducting the MediationConducting the Mediation
Conducting the Mediation
 
20 11-13 ncm best practice imaw 2020
20 11-13 ncm best practice imaw 202020 11-13 ncm best practice imaw 2020
20 11-13 ncm best practice imaw 2020
 
How To Create Win-Win Strategic Partnerships
How To Create Win-Win Strategic PartnershipsHow To Create Win-Win Strategic Partnerships
How To Create Win-Win Strategic Partnerships
 
Negotiation in Employee Relations
Negotiation in Employee Relations Negotiation in Employee Relations
Negotiation in Employee Relations
 
Making the Deal.pptx
Making the Deal.pptxMaking the Deal.pptx
Making the Deal.pptx
 
Negotiation skills
Negotiation skillsNegotiation skills
Negotiation skills
 
A Successful Negotiation
A Successful NegotiationA Successful Negotiation
A Successful Negotiation
 
HOW NEGOTIATION FLAMES ASSIST RESOLVING DISPUTES AT THE WORKPLACE
HOW NEGOTIATION FLAMES ASSIST RESOLVING DISPUTES AT THE WORKPLACEHOW NEGOTIATION FLAMES ASSIST RESOLVING DISPUTES AT THE WORKPLACE
HOW NEGOTIATION FLAMES ASSIST RESOLVING DISPUTES AT THE WORKPLACE
 
Decision Making & Negotiating
Decision Making & NegotiatingDecision Making & Negotiating
Decision Making & Negotiating
 
Dispute resolution in construction
Dispute resolution in construction Dispute resolution in construction
Dispute resolution in construction
 

More from CyrianAsidoy (10)

11. safety control
11. safety control11. safety control
11. safety control
 
10. quality control
10. quality control10. quality control
10. quality control
 
9. quality and productivity
9. quality and productivity9. quality and productivity
9. quality and productivity
 
8. monitoring & control
8. monitoring & control8. monitoring & control
8. monitoring & control
 
7.resource allocation
7.resource allocation7.resource allocation
7.resource allocation
 
6. project control (1)
6. project control (1)6. project control (1)
6. project control (1)
 
5 a. personal protective equipment
5 a. personal protective equipment5 a. personal protective equipment
5 a. personal protective equipment
 
5. scaffolds ppt construction
5. scaffolds ppt construction5. scaffolds ppt construction
5. scaffolds ppt construction
 
3. excavations2
3. excavations23. excavations2
3. excavations2
 
1. cmpm
1. cmpm1. cmpm
1. cmpm
 

Recently uploaded

electrical installation and maintenance.
electrical installation and maintenance.electrical installation and maintenance.
electrical installation and maintenance.
benjamincojr
 
ALCOHOL PRODUCTION- Beer Brewing Process.pdf
ALCOHOL PRODUCTION- Beer Brewing Process.pdfALCOHOL PRODUCTION- Beer Brewing Process.pdf
ALCOHOL PRODUCTION- Beer Brewing Process.pdf
Madan Karki
 
Tembisa Central Terminating Pills +27838792658 PHOMOLONG Top Abortion Pills F...
Tembisa Central Terminating Pills +27838792658 PHOMOLONG Top Abortion Pills F...Tembisa Central Terminating Pills +27838792658 PHOMOLONG Top Abortion Pills F...
Tembisa Central Terminating Pills +27838792658 PHOMOLONG Top Abortion Pills F...
drjose256
 
21P35A0312 Internship eccccccReport.docx
21P35A0312 Internship eccccccReport.docx21P35A0312 Internship eccccccReport.docx
21P35A0312 Internship eccccccReport.docx
rahulmanepalli02
 

Recently uploaded (20)

electrical installation and maintenance.
electrical installation and maintenance.electrical installation and maintenance.
electrical installation and maintenance.
 
Software Engineering Practical File Front Pages.pdf
Software Engineering Practical File Front Pages.pdfSoftware Engineering Practical File Front Pages.pdf
Software Engineering Practical File Front Pages.pdf
 
Diploma Engineering Drawing Qp-2024 Ece .pdf
Diploma Engineering Drawing Qp-2024 Ece .pdfDiploma Engineering Drawing Qp-2024 Ece .pdf
Diploma Engineering Drawing Qp-2024 Ece .pdf
 
Low Altitude Air Defense (LAAD) Gunner’s Handbook
Low Altitude Air Defense (LAAD) Gunner’s HandbookLow Altitude Air Defense (LAAD) Gunner’s Handbook
Low Altitude Air Defense (LAAD) Gunner’s Handbook
 
ALCOHOL PRODUCTION- Beer Brewing Process.pdf
ALCOHOL PRODUCTION- Beer Brewing Process.pdfALCOHOL PRODUCTION- Beer Brewing Process.pdf
ALCOHOL PRODUCTION- Beer Brewing Process.pdf
 
Raashid final report on Embedded Systems
Raashid final report on Embedded SystemsRaashid final report on Embedded Systems
Raashid final report on Embedded Systems
 
Tembisa Central Terminating Pills +27838792658 PHOMOLONG Top Abortion Pills F...
Tembisa Central Terminating Pills +27838792658 PHOMOLONG Top Abortion Pills F...Tembisa Central Terminating Pills +27838792658 PHOMOLONG Top Abortion Pills F...
Tembisa Central Terminating Pills +27838792658 PHOMOLONG Top Abortion Pills F...
 
5G and 6G refer to generations of mobile network technology, each representin...
5G and 6G refer to generations of mobile network technology, each representin...5G and 6G refer to generations of mobile network technology, each representin...
5G and 6G refer to generations of mobile network technology, each representin...
 
SLIDESHARE PPT-DECISION MAKING METHODS.pptx
SLIDESHARE PPT-DECISION MAKING METHODS.pptxSLIDESHARE PPT-DECISION MAKING METHODS.pptx
SLIDESHARE PPT-DECISION MAKING METHODS.pptx
 
Operating System chapter 9 (Virtual Memory)
Operating System chapter 9 (Virtual Memory)Operating System chapter 9 (Virtual Memory)
Operating System chapter 9 (Virtual Memory)
 
Lab Manual Arduino UNO Microcontrollar.docx
Lab Manual Arduino UNO Microcontrollar.docxLab Manual Arduino UNO Microcontrollar.docx
Lab Manual Arduino UNO Microcontrollar.docx
 
NO1 Best Powerful Vashikaran Specialist Baba Vashikaran Specialist For Love V...
NO1 Best Powerful Vashikaran Specialist Baba Vashikaran Specialist For Love V...NO1 Best Powerful Vashikaran Specialist Baba Vashikaran Specialist For Love V...
NO1 Best Powerful Vashikaran Specialist Baba Vashikaran Specialist For Love V...
 
handbook on reinforce concrete and detailing
handbook on reinforce concrete and detailinghandbook on reinforce concrete and detailing
handbook on reinforce concrete and detailing
 
Artificial Intelligence in due diligence
Artificial Intelligence in due diligenceArtificial Intelligence in due diligence
Artificial Intelligence in due diligence
 
litvinenko_Henry_Intrusion_Hong-Kong_2024.pdf
litvinenko_Henry_Intrusion_Hong-Kong_2024.pdflitvinenko_Henry_Intrusion_Hong-Kong_2024.pdf
litvinenko_Henry_Intrusion_Hong-Kong_2024.pdf
 
Dynamo Scripts for Task IDs and Space Naming.pptx
Dynamo Scripts for Task IDs and Space Naming.pptxDynamo Scripts for Task IDs and Space Naming.pptx
Dynamo Scripts for Task IDs and Space Naming.pptx
 
21P35A0312 Internship eccccccReport.docx
21P35A0312 Internship eccccccReport.docx21P35A0312 Internship eccccccReport.docx
21P35A0312 Internship eccccccReport.docx
 
AI in Healthcare Innovative use cases and applications.pdf
AI in Healthcare Innovative use cases and applications.pdfAI in Healthcare Innovative use cases and applications.pdf
AI in Healthcare Innovative use cases and applications.pdf
 
Passive Air Cooling System and Solar Water Heater.ppt
Passive Air Cooling System and Solar Water Heater.pptPassive Air Cooling System and Solar Water Heater.ppt
Passive Air Cooling System and Solar Water Heater.ppt
 
Seismic Hazard Assessment Software in Python by Prof. Dr. Costas Sachpazis
Seismic Hazard Assessment Software in Python by Prof. Dr. Costas SachpazisSeismic Hazard Assessment Software in Python by Prof. Dr. Costas Sachpazis
Seismic Hazard Assessment Software in Python by Prof. Dr. Costas Sachpazis
 

2. construction disputes

  • 1. Construction Disputes Dr. Khaled Hesham Hyari Department of Civil Engineering The Hashemite University
  • 2. 2 - 5 1. Introduction 2. Construction Site Disputes 3. Sources of Construction Site Disputes 4. Planning for Problems 5. The Role of Relationships 6. What to do if a problem arises? 7. Avoiding Construction Disputes 8. Job Site Dispute Resolution 9. Resolving Construction Disputes Content
  • 3. 3 - 5 • The construction industry is not as famous for its construction quality as it is for its confrontation, claims, and litigation • The attributes of honor, integrity, and pride in workmanship have been replaced with conflict, claims, delayed projects and cost overruns 1. Introduction
  • 4. 4 - 5 • Talk with anyone in the construction industry and ask them is there a project you have completed without any conflict? The answer in 100% of the time will be no • The construction project does not exist that hasn't seen some kind of misunderstanding, disagreement, problem, unforeseen event, design error or construction defect • You cannot avoid conflict 2. Construction Site Disputes I
  • 5. 5 - 5 • Not all of these situations evolve into disputes, however, and not all disputes become claims or lawsuits. • Don’t get confused with indecision, disagreement, stress or other common experiences that may cause, or be caused by conflict. – By definition, conflict only occurs between parties who need each other and who cannot simply leave the relationship with no negative consequences. 2. Construction Site Dispute II
  • 6. 6 - 5 • Quality of work (Defective work) • Responsibility for delays • Differing Site Conditions • Incomplete Scope Definition • Poor communications • Suspension of Work • Disruption • Variation Orders • Variations in Estimated Quantities • Inappropriate contract type • Defective Specifications and Drawings • Acceleration of the Work • Force Majeure 3. Sources of Construction Site Disputes
  • 7. 7 - 5 • Many disputes are cumulative. – Unresolved small problems create antagonisms between the parties and make it more difficult to resolve new conflicts as they arise. – It is not uncommon for parties to wait until the end of the project to address all of the unresolved disputes that have arisen. – While they are waiting, their unstated expectations continue to go unmet, and the level of antagonism rises. – In a nasty circle, as relationships deteriorate, the cooperation so vital to the success of a project also erodes. – Mistrust may begin to cause delays and disruptions, which in turn cause added costs that then breed more problems. 4. Planning for Problems I
  • 8. 8 - 5 • Against this volatile background, the stage is set for a serious dispute. When the final straw, perhaps an error occurs, serious but otherwise forgivable, it may be too late for negotiations. • The longer the resolution of a problem is put off, the more expensive it is to correct. 4. Planning for Problems II
  • 9. 9 - 5 • As time goes by, what might have required only a quick and relatively inexpensive solution becomes a difficult and costly defect to remedy. • The best and least expensive way is to have a project-wide commitment that at the first indication of a problem, participants will work together to resolve it and not allow it to escalate into a dispute where third-party resolution is required. 4. Planning for Problems III
  • 10. 10 - 5 • Establishing trust among parties: –Requires at least one person willing to risk something. –Trust also demands open and unbiased communication. One way to do this is to try to put yourself in the other parties' places 5. The Role of Relationships I
  • 11. 11 - 5 • Parties who are aware that their relationship will be of brief duration are more likely to resist agreement. • On the other hand, if all parties to the conflict have had or anticipate a long-term relationship, cooperation is more likely 5. The Role of Relationships II
  • 12. 12 - 5 • Remain calm • Report the incident immediately • Keep seeking alternatives and solutions • Do not automatically assume you are responsible, no matter what the facts first seem to indicate • Communicate • Document and photograph • Try to resolve the conflict with the others involved. If direct negotiation fails, seek mediation by a third party 6. What to do if a problem arises? I
  • 13. 13 - 5 • Remain calm – Examine any accusation calmly and objectively – Authorities on dispute handling recommend that you assume a neutral attitude, and seek to understand the other party's position – This is much more productive than a quick and heated denial 6. What to do if a problem arises? II
  • 14. 14 - 5 • Report the incident immediately. –Do not wait until someone has made a formal claim against you. –Be sure that your staff understands that reporting such a situation is positive behavior to be rewarded, not punished –The longer a problem is ignored, the more expensive and difficult its resolution is –If your sixth sense is telling you something is wrong, report it. 6. What to do if a problem arises? III
  • 15. 15 - 5 • Keep seeking alternatives and solutions. – Remain flexible and continue to seek solutions to a conflict before it escalates into a major lawsuit – Allow yourself and your associates the freedom to keep generating ideas for solving the problem – Together, you may be able to come up with a creative solution that will work for everyone 6. What to do if a problem arises? IV
  • 16. 16 - 5 • Do not automatically assume you are responsible, no matter what the facts first seem to indicate. – Any loss situation involves many factors; do not try to rush to a verdict before all the facts have been evaluated. – It is almost impossible to undo the damage done when you mistakenly assume responsibility and communicate it to the other parties connected with the loss 6. What to do if a problem arises? V
  • 17. 17 - 5 • Communicate. – Although you should not automatically assume responsibility, do not cease communicating with others – Keep talking and listening – Certainly, continued communication will help preserve your relationships with the other party and may motivate everyone to resolve the dispute quickly 6. What to do if a problem arises? VI
  • 18. 18 - 5 • Document and photograph. – All data and correspondence relating to the dispute should be documented. Keep detailed notes on all communications. – Notes and records not only help clarify the issue but will also be needed by any lawyer who may come to your rescue in the event of a suit. – "A picture is worth a thousand words" still holds true in potential claims situations. Photographing or videotaping the disputed subject matter is an excellent way of preserving the record for the future. 6. What to do if a problem arises? VII
  • 19. 19 - 5 • Try to resolve the conflict with the others involved. If direct negotiation fails, seek mediation by a third party – Sit down and talk to the other parties ASAP, try to find a solution you can all live with – If informal negotiations fail, invite a neutral, experienced mediator to help you reach a settlement – If these processes fail, or are not attempted, the dispute could escalate into binding arbitration or litigation 6. What to do if a problem arises? VIII
  • 20. 20 - 5 Prevention 7. Avoiding Construction Disputes I • “For every $1 you spend on disputes management during the front-end of the project, you will save at least $20 to $25 on claims during construction”
  • 21. 21 - 5 • Recommendations for Conflict Prevention (Avoidance): – Partnering & Team Building – Incentives for Cooperation – Realistic Risk Allocation – Constructability Analysis – Dispute Resolution Clauses – Competent Engineering & Documentation – Training and Development – Honesty in Contracting – Continuity of Personnel 7. Avoiding Construction Disputes II
  • 22. 22 - 5 • Recommendations for Conflict Prevention (Avoidance): – Being ready for unforeseen or changed conditions – Balancing interests of team members with regard to schedule, payments, decision making, and performance. – Performing contract obligations on time 7. Avoiding Construction Disputes III
  • 23. 23 - 5 Project Partnering & Team Building I • The goal is to create a shared vision of the project • The concept behind today's partnering is to dispel the adversarial "us-versus-them" approach often found on today's construction projects and to promote "let's-all-pull together" attitudes. • Typically, partnering involves a series of workshops with representatives from all parties to the project • A facilitator conducts team-building activities aimed at achieving mutually agreed-upon goals
  • 24. 24 - 5 • The benefits of partnering can be significant – The quality of the project is typically improved – The workplace tends to be safer – Partnered projects tend to be brought in on time or even ahead of schedule and the process typically helps reduce cost overruns – The designers' roles in the problem-solving process may be enhanced and their participation in construction phase services is more likely – Best of all, there is a reduced exposure to litigation for all parties to the project Project Partnering & Team Building II
  • 25. 25 - 5 • For partnering to work, it must be owner- driven and have the full backing of the top management of all participating team members • Partnering does not guarantee that disputes will not arise –It is a way to manage and resolve the disputes that do come up Project Partnering & Team Building III
  • 26. 26 - 5 • Partnering has had great success and holds even greater promise for the future. • It is a straightforward and proven mechanism to handle construction disputes as they were once handled Project Partnering & Team Building IV
  • 27. 27 - 5 • Cost/Schedule Incentive Matrix – A matrix that defines incentives to contractors for certain reductions in time and cost of the project • Subjective determination of fee – In cost + fee projects a portion of the fee is awarded based on owner’s evaluation of performance Incentives for Cooperation
  • 28. 28 - 5 • Structuring contracts to allocate risks clearly and fairly. • A study by Shen (1997) surveyed 85 contractors in Hong Kong and identified the following sources of risk: – Insufficient or incorrect design information – Variations in ground and weather conditions – Subcontractors’ manpower shortage – Shortage of materials/plant resources – Poor coordination with subcontractors – Poor accuracy of project plan – Shortage of skills/techniques – failed works due to poor workmanship Realistic Risk Allocation
  • 29. 29 - 5 Equitable Risk Sharing • A study by Vega (1997) on risk sharing in large infrastructure projects, it was concluded that – “The general guiding principle of risk allocation should be that the different parties involved should seek a multi-beneficial distribution risk. A dominant party that off- loads all project risks onto others is unlikely to enhance the chances for a successful outcome.” Realistic Risk Allocation II
  • 30. 30 - 5 • Reduces disagreements because it eliminates errors, omissions, and impractical details • The contractor assigns engineers to work with the design team in order to improve construction details • Performed during the planning, design, and procurement phases Constructability Analysis
  • 31. 31 - 5 • A well-drafted contract provides procedures for conflict resolution without involving courts. (i.e. ADR). • Examples include: – Relying on designer to resolve conflicts between the owner and contractor; – Using third-party mediator to help participants structure negotiations, provide neutral evaluation and encourage fair settlement; – The use of dispute review board judges, or standing neutrals to resolve disputes and – Binding arbitration. Dispute Resolution Clauses
  • 32. 32 - 5 • Step Negotiations: A commitment to solve a problem ASAP at the lowest possible level of management – If parties directly involved cannot resolve a problem at the job site, their supervisors then meet to work out a solution – If they, in turn, cannot agree, then the problem will be passed on to higher management in both organizations, and so on 8. Job Site Dispute Resolution I
  • 33. 33 - 5 • Step Negotiations – Often each of these parties is identified at the beginning of the project and there may be a predetermined time limit for resolving an issue at a given level 8. Job Site Dispute Resolution II
  • 34. 34 - 5 • An important task for construction project managers. The mechanism for dispute resolution can be specified in the original contract or, less desireably, decided when a dispute arises. 9. Resolving Construction Disputes I
  • 36. 36 - 5 Prevention Negotiation 9. Resolving Construction Disputes III • Step 2: Negotiation: – Typically does not involve third parties such as judges – The negotiation process is usually informal, unstructured and relatively inexpensive.
  • 37. 37 - 5 Prevention Negotiation Standing Neutral • Step 3: Standing Neutral – The concept of a standing neutral involves an independent person, or persons, who is/are totally neutral to the problem 9. Resolving Construction Disputes IV
  • 38. 38 - 5 • Standing Neutral: – At the beginning of the construction phase of the project, the parties select one or more independent construction industry experts to be available as a standing neutral throughout the project – The neutral acts immediately to resolve any dispute which the parties can not resolve themselves. – Terms such as dispute review board, standing mediator, and standing arbitrator are also used. 9. Resolving Construction Disputes V
  • 39. 39 - 5 • Dispute Review Board – Commonly consists of three members: a representative from the owner, one from the contractor and a third, selected by these two representatives. The third member chairs the board – The members usually have experience in the kind of construction work being undertaken and are also familiar and experienced in dispute resolution – It is important that all the board members are independent of any of the contracting parties, although they are paid by them 9. Resolving Construction Disputes VI
  • 40. 40 - 5 • Essential elements of a successful DRB: – All members are neutral and subject to the approval of both parties – All members sign a three party agreement obligating them to serve both parties equally and fairly – All fees and expenses of the DRP are shared equally by the parties – The DRP is organized when work begins, before there are any disputes – The DRP keeps an eye on job developments by means of relevant documentation and regular site visits 9. Resolving Construction Disputes VII
  • 41. 41 - 5 • Essential elements of a successful DRB: – An informal but comprehensive hearing is arranged promptly – The written recommendations of the DRP are not binding on either party but are permissible as evidence, to the extent permitted by law, in case of later arbitration or litigation – The members are released from any personal or professional liability arising from their DRP activities 9. Resolving Construction Disputes VIII
  • 42. 42 - 5 Mediation Prevention Negotiation Standing Neutral • Step 4 Mediation: A process in which the parties to a dispute, with the assistance of a neutral third party (the mediator), identifies the disputed issues, develop options, consider alternatives and endeavor to reach an agreement 9. Resolving Construction Disputes IX
  • 43. 43 - 5 • Mediation – It is a non-binding resolution – In mediation, the third party serves only as a facilitator to help the participants reach a mutually acceptable resolution. – The mediator has no advisory or determinative role in regard to the content of the dispute or the outcome of its resolution 9. Resolving Construction Disputes X
  • 44. 44 - 5 Mediation Prevention Negotiation Standing Neutral Arbitration •Step 5: Arbitration 9. Resolving Construction Disputes XI • Binding arbitration: Referral of a dispute to one or more impartial persons for final and binding determination., • Designed for quick, practical, and economical settlements.
  • 45. 45 - 5 • Arbitration – In this procedures, a third party serves a central role in the resolution. – These outside parties are usually chosen by mutually agreement of the parties involved and will have specialized knowledge of the dispute subject. – The third party may make a decision which is binding on the participants – It is a binding resolution mechanism. • Arbitration has evolved to a form very similar to litigation, which defies its purpose 9. Resolving Construction Disputes XII
  • 46. 46 - 5 Non-Binding Resolution Prevention Negotiation Standing Neutral Binding Resolution Litigation • Step 6: Litigation – Litigation of construction disputes is usually complex, expensive, and time consuming. 9. Resolving Construction Disputes XIII
  • 47. 47 - 5 • In most cases, litigation is the last resort and least preferable way to resolve a dispute. • In such instances, the parties are wise to conduct a thorough and objective review of the costs and benefits of litigation throughout the conflict. • If litigation remains an option, each participant carefully evaluates not only the merits of his or her case, but also the likelihood of how well the facts can be presented in a formal judicial proceeding. 9. Resolving Construction Disputes XIV
  • 48. 48 - 5 • Main problems with litigation – Too expensive – Time consuming since it involves legal representation and waiting in queues of cases for available court times Too slow – Lack of equality between powerful and under resourced litigants – Difficult to forecast cost and length of litigation – Incomprehensible by many litigants – Too adversarial 9. Resolving Construction Disputes XV
  • 49. 49 - 5 • Litigation Costs: In pursuit of legal remedies (litigation or arbitration), substantial direct and indirect costs are involved included, but not limited to: – Direct external costs, e.g. attorneys’ fees, court costs, deposition costs, expert fees, investigation costs (soil, hydrology, testing). – Direct internal costs, e.g. costs of key personnel working with attorneys and experts, attending forum proceedings, and other incidental costs. 9. Resolving Construction Disputes XVI
  • 50. 50 - 5 • Litigation Costs – Indirect costs, e.g. the interruption of management and key personnel duties, impacts on reputation, reduction in bonding capacity, interruption of cash flow, etc. – Loss of client relationship (temporarily or permanent). 9. Resolving Construction Disputes XVII
  • 52. 52 - 5 • List 5 possible issues that might lead to a conflict in a construction project. Be specific and illustrate the reason for disagreement between the conflicting parties • One page • Due one week from now Homework