SlideShare a Scribd company logo
1 of 35
• Building program definition
• Economic feasibility assessment,
• Site assessment and selection
• Governmental constraints assessment
• Sustainability rating
• Design team selection
The American Institute of Architects (AIA)
Document B141, Standard Form of
Agreement Between Owner and Architect,
defines the building program as “the
owner’s objectives, schedule, constraints
and criteria including space requirements
and relationships, special equipment,
flexibility, expandability, systems, and
site requirements.”
Selecting the general contractor is a crucial part of a
project. A number of selection methods exist. The
method used in selecting the general contractor, its
timing, and the contractor’s obligations under the
contract distinguishes one project delivery method from
the other.
Some of the most commonly used delivery methods are:
• Design-bid-build method
• Design-negotiate-build method
• Construction manager as agent method
• Construction manager at risk method
• Design-build method
• Integrated project delivery method
Following are three commonly used versions of
the DBB method of delivery:
• DBB method—competitive sealed bidding (open
bidding)
• DBB method—competitive sealed proposal
• DBB method— invitational bidding (closed
bidding)
In preparing the contract documents, the design team’s
challenge is to efficiently produce the graphics and text
that effectively communicate the design intent to the
construction professionals and the related product
suppliers and manufacturers so that they can do
the following:
• Propose accurate and competitive bids
• Prepare detailed and descriptive submittals for
approval
• Construct the building with a minimum number of
questions, revisions, and changes
The construction drawings and the specifications
should provide a fairly detailed delineation of the
building. However, they do not describe it to the
extent that fabricators can produce building
components directly from them. Therefore, the
fabricators generate their own drawings, referred
to as shop drawings, to provide the higher level of
detail necessary to fabricate and assemble the
components.
In addition to shop drawings, full-size mock-up
samples of one or more critical elements of the
building may be required in some projects. This is
done to establish the quality of materials and
workmanship by which the completed work will
be judged. For example, it is not unusual for the
architect to ask for a mock-up of a typical area of
the curtain wall of a high-rise building before the
fabrication of the actual curtain wall is
undertaken. Mock-up samples go through the
same approval process as the shop drawings.
In addition to shop drawings and any mock-up
samples, some other submittals required from
the contractor for the architect’s review are:
• Product material samples
• Product data
• Certifications
• Calculations
• The architect determines the what and where.
• The contractor determines the how (means and
methods) and when (sequence) of construction.
• Substantial completion inspection
• Final completion inspection
There is hardly a construction project that does not
require changes after construction has begun. The
contract between the owner and the contractor
recognizes this fact and includes provisions for the
owner’s right to order a change and the contractor’s
obligation to accept the change order in return for
an equitable price adjustment. Here again, the
architect performs a quasi-judicial role to arrive at a
suitable agreement and price between the owner
and the contractor
1. cmpm
1. cmpm
1. cmpm

More Related Content

What's hot

Presentation civil engineering (fm)
Presentation  civil engineering (fm)Presentation  civil engineering (fm)
Presentation civil engineering (fm)Sarah Esa
 
TOGAF Classroom Series - M13 adm phases (g - h)
TOGAF Classroom Series - M13 adm phases (g - h)TOGAF Classroom Series - M13 adm phases (g - h)
TOGAF Classroom Series - M13 adm phases (g - h)Cuneyt Kaya
 
Organizational Skills And Technical Competences as LEAD PIPING ENGINEER (...
Organizational  Skills  And  Technical  Competences as LEAD PIPING ENGINEER (...Organizational  Skills  And  Technical  Competences as LEAD PIPING ENGINEER (...
Organizational Skills And Technical Competences as LEAD PIPING ENGINEER (...Corneliu Liviu Costea
 
TOGAD Classroom Series - M5 adm-iteration-landscape
TOGAD Classroom Series - M5 adm-iteration-landscapeTOGAD Classroom Series - M5 adm-iteration-landscape
TOGAD Classroom Series - M5 adm-iteration-landscapeCuneyt Kaya
 
Organizational Skills And Technical Competences as LEAD PIPING MATERIAL ENG.
Organizational  Skills  And  Technical  Competences as LEAD PIPING MATERIAL ENG.Organizational  Skills  And  Technical  Competences as LEAD PIPING MATERIAL ENG.
Organizational Skills And Technical Competences as LEAD PIPING MATERIAL ENG.Corneliu Liviu Costea
 
TOGF Classroom Series - M12 migration-planning-techniques
TOGF Classroom Series - M12 migration-planning-techniquesTOGF Classroom Series - M12 migration-planning-techniques
TOGF Classroom Series - M12 migration-planning-techniquesCuneyt Kaya
 
Aec bim presentation
Aec bim presentationAec bim presentation
Aec bim presentationAnkur Sardana
 

What's hot (7)

Presentation civil engineering (fm)
Presentation  civil engineering (fm)Presentation  civil engineering (fm)
Presentation civil engineering (fm)
 
TOGAF Classroom Series - M13 adm phases (g - h)
TOGAF Classroom Series - M13 adm phases (g - h)TOGAF Classroom Series - M13 adm phases (g - h)
TOGAF Classroom Series - M13 adm phases (g - h)
 
Organizational Skills And Technical Competences as LEAD PIPING ENGINEER (...
Organizational  Skills  And  Technical  Competences as LEAD PIPING ENGINEER (...Organizational  Skills  And  Technical  Competences as LEAD PIPING ENGINEER (...
Organizational Skills And Technical Competences as LEAD PIPING ENGINEER (...
 
TOGAD Classroom Series - M5 adm-iteration-landscape
TOGAD Classroom Series - M5 adm-iteration-landscapeTOGAD Classroom Series - M5 adm-iteration-landscape
TOGAD Classroom Series - M5 adm-iteration-landscape
 
Organizational Skills And Technical Competences as LEAD PIPING MATERIAL ENG.
Organizational  Skills  And  Technical  Competences as LEAD PIPING MATERIAL ENG.Organizational  Skills  And  Technical  Competences as LEAD PIPING MATERIAL ENG.
Organizational Skills And Technical Competences as LEAD PIPING MATERIAL ENG.
 
TOGF Classroom Series - M12 migration-planning-techniques
TOGF Classroom Series - M12 migration-planning-techniquesTOGF Classroom Series - M12 migration-planning-techniques
TOGF Classroom Series - M12 migration-planning-techniques
 
Aec bim presentation
Aec bim presentationAec bim presentation
Aec bim presentation
 

Similar to 1. cmpm

Guc arct 702 legislations lecture 4 - project delivery process and business...
Guc arct 702 legislations   lecture 4 - project delivery process and business...Guc arct 702 legislations   lecture 4 - project delivery process and business...
Guc arct 702 legislations lecture 4 - project delivery process and business...Galala University
 
Project Phase, Project Teams & Construction Phase.pdf
Project Phase, Project Teams & Construction Phase.pdfProject Phase, Project Teams & Construction Phase.pdf
Project Phase, Project Teams & Construction Phase.pdfMOHDFIRRDHAUSBINMOHD
 
Construction Stages and Construction Teams
Construction Stages and Construction TeamsConstruction Stages and Construction Teams
Construction Stages and Construction TeamsMOHDFIRRDHAUSBINMOHD
 
working drawing basic
working drawing basic working drawing basic
working drawing basic download26
 
Construction contracts docuements_08092008
Construction contracts docuements_08092008Construction contracts docuements_08092008
Construction contracts docuements_08092008AYM1979
 
Legal issues associated with project management and consulting
Legal issues associated with project management and consultingLegal issues associated with project management and consulting
Legal issues associated with project management and consultingThis account is closed
 
Professional practice-1-presentation
Professional practice-1-presentationProfessional practice-1-presentation
Professional practice-1-presentationTimun Loh
 
CSCM Chapter 1 construction supply chain management
CSCM Chapter 1 construction supply chain managementCSCM Chapter 1 construction supply chain management
CSCM Chapter 1 construction supply chain managementEst
 
Shop Drawings, Construction Drawings and As-Built Drawings - What’s the diffe...
Shop Drawings, Construction Drawings and As-Built Drawings - What’s the diffe...Shop Drawings, Construction Drawings and As-Built Drawings - What’s the diffe...
Shop Drawings, Construction Drawings and As-Built Drawings - What’s the diffe...Hitech CADD Services
 
Project 1 - Architect
Project 1 - Architect Project 1 - Architect
Project 1 - Architect leejanett3
 
building economics.PPT LAESE, BUDGET MANAGEMENT
building economics.PPT LAESE, BUDGET MANAGEMENTbuilding economics.PPT LAESE, BUDGET MANAGEMENT
building economics.PPT LAESE, BUDGET MANAGEMENTRiyaVerma238431
 
Cjmconstructionconsultingpresentation 13086519950433-phpapp02-110621053129-ph...
Cjmconstructionconsultingpresentation 13086519950433-phpapp02-110621053129-ph...Cjmconstructionconsultingpresentation 13086519950433-phpapp02-110621053129-ph...
Cjmconstructionconsultingpresentation 13086519950433-phpapp02-110621053129-ph...Neha V
 
qsqs-141129025329-conversion-gate01.pdf
qsqs-141129025329-conversion-gate01.pdfqsqs-141129025329-conversion-gate01.pdf
qsqs-141129025329-conversion-gate01.pdfrivenhau
 

Similar to 1. cmpm (20)

Guc arct 702 legislations lecture 4 - project delivery process and business...
Guc arct 702 legislations   lecture 4 - project delivery process and business...Guc arct 702 legislations   lecture 4 - project delivery process and business...
Guc arct 702 legislations lecture 4 - project delivery process and business...
 
Project Phase, Project Teams & Construction Phase.pdf
Project Phase, Project Teams & Construction Phase.pdfProject Phase, Project Teams & Construction Phase.pdf
Project Phase, Project Teams & Construction Phase.pdf
 
Lecture 1.pptx
Lecture 1.pptxLecture 1.pptx
Lecture 1.pptx
 
Construction Stages and Construction Teams
Construction Stages and Construction TeamsConstruction Stages and Construction Teams
Construction Stages and Construction Teams
 
working drawing basic
working drawing basic working drawing basic
working drawing basic
 
Construction contracts docuements_08092008
Construction contracts docuements_08092008Construction contracts docuements_08092008
Construction contracts docuements_08092008
 
Shop Drawing Services | Silicon Consultant LLC.pptx
Shop Drawing Services | Silicon Consultant LLC.pptxShop Drawing Services | Silicon Consultant LLC.pptx
Shop Drawing Services | Silicon Consultant LLC.pptx
 
Preparation of boq
Preparation of boqPreparation of boq
Preparation of boq
 
Legal issues associated with project management and consulting
Legal issues associated with project management and consultingLegal issues associated with project management and consulting
Legal issues associated with project management and consulting
 
Professional practice-1-presentation
Professional practice-1-presentationProfessional practice-1-presentation
Professional practice-1-presentation
 
CSCM Chapter 1 construction supply chain management
CSCM Chapter 1 construction supply chain managementCSCM Chapter 1 construction supply chain management
CSCM Chapter 1 construction supply chain management
 
Ddg architecture
Ddg architectureDdg architecture
Ddg architecture
 
CONS6817_S03'16
CONS6817_S03'16CONS6817_S03'16
CONS6817_S03'16
 
Shop Drawings, Construction Drawings and As-Built Drawings - What’s the diffe...
Shop Drawings, Construction Drawings and As-Built Drawings - What’s the diffe...Shop Drawings, Construction Drawings and As-Built Drawings - What’s the diffe...
Shop Drawings, Construction Drawings and As-Built Drawings - What’s the diffe...
 
Project 1 - Architect
Project 1 - Architect Project 1 - Architect
Project 1 - Architect
 
building economics.PPT LAESE, BUDGET MANAGEMENT
building economics.PPT LAESE, BUDGET MANAGEMENTbuilding economics.PPT LAESE, BUDGET MANAGEMENT
building economics.PPT LAESE, BUDGET MANAGEMENT
 
Cjmconstructionconsultingpresentation 13086519950433-phpapp02-110621053129-ph...
Cjmconstructionconsultingpresentation 13086519950433-phpapp02-110621053129-ph...Cjmconstructionconsultingpresentation 13086519950433-phpapp02-110621053129-ph...
Cjmconstructionconsultingpresentation 13086519950433-phpapp02-110621053129-ph...
 
qsqs-141129025329-conversion-gate01.pdf
qsqs-141129025329-conversion-gate01.pdfqsqs-141129025329-conversion-gate01.pdf
qsqs-141129025329-conversion-gate01.pdf
 
QS.pdf
QS.pdfQS.pdf
QS.pdf
 
Bid & spec 101
Bid & spec 101Bid & spec 101
Bid & spec 101
 

More from CyrianAsidoy

11. safety control
11. safety control11. safety control
11. safety controlCyrianAsidoy
 
10. quality control
10. quality control10. quality control
10. quality controlCyrianAsidoy
 
9. quality and productivity
9. quality and productivity9. quality and productivity
9. quality and productivityCyrianAsidoy
 
8. monitoring & control
8. monitoring & control8. monitoring & control
8. monitoring & controlCyrianAsidoy
 
7.resource allocation
7.resource allocation7.resource allocation
7.resource allocationCyrianAsidoy
 
6. project control (1)
6. project control (1)6. project control (1)
6. project control (1)CyrianAsidoy
 
5 a. personal protective equipment
5 a. personal protective equipment5 a. personal protective equipment
5 a. personal protective equipmentCyrianAsidoy
 
5. scaffolds ppt construction
5. scaffolds ppt construction5. scaffolds ppt construction
5. scaffolds ppt constructionCyrianAsidoy
 
2. construction disputes
2.  construction disputes2.  construction disputes
2. construction disputesCyrianAsidoy
 

More from CyrianAsidoy (10)

11. safety control
11. safety control11. safety control
11. safety control
 
10. quality control
10. quality control10. quality control
10. quality control
 
9. quality and productivity
9. quality and productivity9. quality and productivity
9. quality and productivity
 
8. monitoring & control
8. monitoring & control8. monitoring & control
8. monitoring & control
 
7.resource allocation
7.resource allocation7.resource allocation
7.resource allocation
 
6. project control (1)
6. project control (1)6. project control (1)
6. project control (1)
 
5 a. personal protective equipment
5 a. personal protective equipment5 a. personal protective equipment
5 a. personal protective equipment
 
5. scaffolds ppt construction
5. scaffolds ppt construction5. scaffolds ppt construction
5. scaffolds ppt construction
 
3. excavations2
3. excavations23. excavations2
3. excavations2
 
2. construction disputes
2.  construction disputes2.  construction disputes
2. construction disputes
 

Recently uploaded

Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...RajaP95
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Call Girls in Nagpur High Profile
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlysanyuktamishra911
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxpranjaldaimarysona
 
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).pptssuser5c9d4b1
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Christo Ananth
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)Suman Mia
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...ranjana rawat
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Christo Ananth
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSSIVASHANKAR N
 

Recently uploaded (20)

Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
 
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
IMPLICATIONS OF THE ABOVE HOLISTIC UNDERSTANDING OF HARMONY ON PROFESSIONAL E...
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghly
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptx
 
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
 

1. cmpm

  • 1.
  • 2.
  • 3. • Building program definition • Economic feasibility assessment, • Site assessment and selection • Governmental constraints assessment • Sustainability rating • Design team selection
  • 4. The American Institute of Architects (AIA) Document B141, Standard Form of Agreement Between Owner and Architect, defines the building program as “the owner’s objectives, schedule, constraints and criteria including space requirements and relationships, special equipment, flexibility, expandability, systems, and site requirements.”
  • 5.
  • 6.
  • 7.
  • 8.
  • 9.
  • 10.
  • 11.
  • 12.
  • 13.
  • 14.
  • 15.
  • 16.
  • 17.
  • 18. Selecting the general contractor is a crucial part of a project. A number of selection methods exist. The method used in selecting the general contractor, its timing, and the contractor’s obligations under the contract distinguishes one project delivery method from the other. Some of the most commonly used delivery methods are: • Design-bid-build method • Design-negotiate-build method • Construction manager as agent method • Construction manager at risk method • Design-build method • Integrated project delivery method
  • 19. Following are three commonly used versions of the DBB method of delivery: • DBB method—competitive sealed bidding (open bidding) • DBB method—competitive sealed proposal • DBB method— invitational bidding (closed bidding)
  • 20.
  • 21.
  • 22.
  • 23.
  • 24.
  • 25.
  • 26.
  • 27. In preparing the contract documents, the design team’s challenge is to efficiently produce the graphics and text that effectively communicate the design intent to the construction professionals and the related product suppliers and manufacturers so that they can do the following: • Propose accurate and competitive bids • Prepare detailed and descriptive submittals for approval • Construct the building with a minimum number of questions, revisions, and changes
  • 28. The construction drawings and the specifications should provide a fairly detailed delineation of the building. However, they do not describe it to the extent that fabricators can produce building components directly from them. Therefore, the fabricators generate their own drawings, referred to as shop drawings, to provide the higher level of detail necessary to fabricate and assemble the components.
  • 29. In addition to shop drawings, full-size mock-up samples of one or more critical elements of the building may be required in some projects. This is done to establish the quality of materials and workmanship by which the completed work will be judged. For example, it is not unusual for the architect to ask for a mock-up of a typical area of the curtain wall of a high-rise building before the fabrication of the actual curtain wall is undertaken. Mock-up samples go through the same approval process as the shop drawings.
  • 30. In addition to shop drawings and any mock-up samples, some other submittals required from the contractor for the architect’s review are: • Product material samples • Product data • Certifications • Calculations
  • 31. • The architect determines the what and where. • The contractor determines the how (means and methods) and when (sequence) of construction. • Substantial completion inspection • Final completion inspection
  • 32. There is hardly a construction project that does not require changes after construction has begun. The contract between the owner and the contractor recognizes this fact and includes provisions for the owner’s right to order a change and the contractor’s obligation to accept the change order in return for an equitable price adjustment. Here again, the architect performs a quasi-judicial role to arrive at a suitable agreement and price between the owner and the contractor

Editor's Notes

  1. Building construction is a complex, significant, and rewarding process. It begins with an idea and culminates in a structure that may serve its occupants for several decades, even centuries. Like the manufacturing of products, building construction requires an ordered and planned assembly of materials. It is, however, far more complicated than product manufacturing. Buildings are assembled outdoors by a large number of diverse constructors and artisans on all types of sites and are subject to all kinds of weather. Because of a building’s uniqueness, we invoke first principles in each building project. Although it may seem that we are “reinventing the wheel,” we are in fact refining and improving the building delivery process. In so doing, we bring to the task the collective wisdom of the architects, engineers, and contractors who have done so before us.
  2. The process by which a building project is delivered to its owner may be divided into the following five phases, referred to as the project delivery phases. Although there is usually some overlap between adjacent phases, they generally follow this order:
  3. During the predesign phase (also called the planning phase), the project is defined in terms of its function, purpose, scope, size, and economics. This is the most crucial of the five phases, and is almost always managed by the owner and the owner’s team. The success or failure of the project may depend on how well this phase is defined, detailed, and managed. Obviously, the clearer the project’s definition, the easier it is to proceed to the subsequent phases. Some of the important predesign tasks are: • Building program definition • Economic feasibility assessment, including the project’s overall budget and financing • Site assessment and selection, including verifying the site’s appropriateness and determining its designated land use (Chapter 2 ) • Governmental constraints assessment, for example, building code and zoning constraints ( Chapter 2 ) and other legal aspects of the project • Sustainability rating—whether the owner would like the project to achieve the U.S. Green Building Council’s (USGBC’s) Leadership in Energy and Environmental Design (LEED) certification at some level (see Chapter 10 ) • Design team selection
  4. This includes defining the activities, functions, and spaces required in the building, along with their approximate sizes and their relationships with each other. For a house or another small project, the program is usually simple and can be developed by the owner without external assistance. For a large project, however, where the owner may be an institution (such as a corporation, school board, hospital, religious organization, or governmental entity), developing the program may be a complex exercise. This may be due to the size and complexity of the project or the need to involve several individuals—a corporation’s board of directors, for example—in decision making. These constituencies may have different views of the project, making it difficult to create a consensus.
  5. The design phase begins after the selection of the architect. Because the architect (usually a firm) may have limited capabilities for handling the broad range of building-design activities, several different, more specialized consultants are usually required, depending on the size and scope of the project. In most projects, the design team consists of the architect, civil and structural consultants, and mechanical, electrical, plumbing, and fire-protection (MEPF) consultants. In complex projects, the design team may also include an acoustical consultant, roofing and waterproofing consultant, cost consultant, building code consultant, signage consultant, interior designer, landscape architect, and so on. Some design firms have an entire design team (architects and specialized consultants) on staff, in which case the owner will contract with a single firm. Generally, however, the design team comprises several different design firms. In such cases, the owner typically contracts the architect, who in turn contracts the remaining design team members, Figure 1.1 . Thus, the architect functions as the prime design professional and, to a limited degree, as the owner’s representative. The architect is liable to the owner for his or her own work and that of the consultants. For that reason, most architects ensure that their consultants carry adequate liability insurance. In some projects, the owner may contract some consultants directly, particularly a civil consultant (for a survey of the site, site grading, slope stabilization, and site drainage), a geotechnical consultant (for investigation of the soil properties), and a landscape architect (for landscape and site design), Figure 1.2 . These consultants may be engaged before or at the same time as the architect. Even when a consultant is contracted directly by the owner, the architect retains some liability for the consultant’s work. This liability occurs because the architect, being the prime design professional, coordinates the entire design effort, and the consultants’ work is influenced a great deal by the architectural decisions. Therefore, the working relationship between the architect and an owner-contracted consultant remains essentially the same as if the consultant were chosen by the architect.
  6. In some cases, an engineer or another professional may coordinate the design process. This generally occurs when a building is a minor component of a large-scale project. For example, in a highly technical project such as a power plant, an electrical engineer may be the prime design professional. In most building projects, the design phase consists of three stages: • Schematic design stage • Design development stage • Construction documents stage
  7. The schematic design gives graphic shape to the project program. It is an overall design concept that illustrates the key ideas of the design solution. The major player in this stage is the architect, who develops the design scheme (or several design options) with only limited help from the consultants. Because most projects have strict budgetary limitations, a rough estimate of the project’s probable cost is generally produced at this stage. The schematic design usually goes through several revisions, because the first design scheme prepared by the architect will rarely be approved by the owner. The architect communicates the design proposal(s) to the owner through various types of drawings—plans, elevations, sections, freehand sketches, and three-dimensional graphics (isometrics, axonometrics, and perspectives). For some projects, a three-dimensional scale model of the entire building or the complex of buildings, showing the context (neighboring buildings) within which the project is sited, may be needed. Once the schematic design is approved by the owner, the process of designing the building in greater detail begins. During this stage, the schematic design is developed further— hence the term design development (DD) stage. While the emphasis in the SD stage is on the creative, conceptual, and innovative aspects of design, the DD stage focuses on developing practical and pragmatic solutions for the exterior envelope, structure, fenestration, interior systems, MEPF systems, and so forth. This development involves strategic consultations with all members of the design team. Therefore, the most critical feature of the DD stage is decision making, which may range from broad design aspects to details. At this stage, the vast majority of decisions about products, materials, and equipment are made. Efficient execution of the construction documents depends directly on how well the DD is managed. A more detailed version of the specifications and probable cost of the project is also prepared at this stage. The purpose of the construction documents (CD) stage is to prepare all documents required by the contractor to construct the building. During this stage, the consultants and architect collaborate intensively to work out the “nuts and bolts” of the building and develop the required documentation, referred to as construction documents. All of the consultants advise the architect, but they also collaborate with each other (generally through the architect) so that the work of one consultant agrees with that of the others.
  8. CONSTRUCTION DRAWINGS During the CD stage, the architect and consultants prepare their own sets of drawings, referred to as construction drawings. Thus, a project has architectural construction drawings, civil and structural construction drawings, MEPF construction drawings, landscape construction drawings, and so on. Construction drawings are dimensioned drawings (usually computer generated) that fully delineate the building. They consist of floor plans, elevations, sections, schedules, and various large-scale details. The details depict a small portion of the building that cannot be adequately described on smaller-scale plans, elevations, or sections. Construction drawings are the drawings that the construction team uses to build the building. Therefore, they must indicate the geometry, layout, dimensions, types of materials, details of assembling the components, colors and textures, and so on. Construction drawings are generally two-dimensional drawings, but three-dimensional isometrics are sometimes used for complex details. Construction drawings are also used by the contractor to prepare a detailed cost estimate of the project at the time of bidding. Construction drawings are not a sequence of assembly instructions, such as for a bicycle. Instead, they indicate what every component is and where it will be located when the building is completed. In other words, the design team decides the “what” and “where” of the building. The “how” and “when” of the building are entirely in the contractor’s domain. SPECIFICATIONS Buildings cannot be constructed from drawings alone, because there is a great deal of information that cannot be included in the drawings. For instance, the drawings will give the locations of columns, their dimensions, and the material used (such as reinforced concrete), but the quality of materials, their properties (the strength of concrete, for example), and the test methods required to confirm compliance cannot be furnished on the drawings. This information is included in the document called specifications. Specifications are written technical descriptions of the design intent, whereas the drawings provide the graphic description. The two components of the construction documents—the specifications and the construction drawings—complement each other and generally deal with different aspects of the project. Because they are complementary, they are supposed to be used in conjunction with each other. There is no order of precedence between the construction drawings and the specifications. Thus, if an item is described in only one place—either the specification or the drawings—it is part of the project, as if described in the other. For instance, if the construction drawings do not show the door hardware (hinges, locks, handles, and other components) but the hardware is described in the specifications, the owner will get the doors with the stated hardware. If the drawings had precedence over the specifications, the owner would receive doors without hinges and handles.
  9. Just as the construction drawings are prepared separately by the architect and each consultant for their respective portions of the work, so are the specifications. The specifications from various design team members are assembled by the architect in a single document called the project manual. Because the specifications consist of printed (typed) pages (not graphic images), a project manual is a bound document—like a book.
  10. The preconstruction phase generally begins after the construction drawings and specifications have been completed and culminates in the selection of the construction team. The construction of even a small building involves so many specialized skills and trades that the work cannot normally be undertaken by a single construction firm. Instead, the work is generally done by a team consisting of the general contractor and a number of specialty subcontractors Thus, a project may have roofing; window and curtain wall; plumbing; and heating, ventilation, and air-conditioning (HVAC) subcontractors, among others, in addition to the general contractor. The general contractor’s own work may be limited to certain components of the building (such as the structural components—load-bearing walls, reinforced concrete beams and columns, roof and floor slabs, etc.), with all the remaining work subcontracted.
  11. The design-bid-build method is the oldest and most familiar method of project delivery. This method is covered first. Because the essential features of construction and postconstruction phases are almost identical in all delivery methods, a discussion of what is included in these two phases is presented next. Subsequently, other methods are discussed in terms of how they differ from the design-bid-build method.
  12. In the design-bid-build method, the general contractor is selected through competition. The owner obtains multiple bids for the project from which the general contractor, who provides the “best value for money,” is selected. Within this overall approach, several versions are available to suit the requirements of the project and the particular needs of the owner. Collectively, these delivery versions are referred to as the design-bid-build (DBB) method because in this version, the design, bid, and construction phases of a project are sequential, and one phase does not begin until the previous phase has been completed, Figure 1.7 . Following are three commonly used versions of the DBB method of delivery: • DBB method—competitive sealed bidding (open bidding) • DBB method—competitive sealed proposal • DBB method— invitational bidding (closed bidding)
  13. On several publicly funded projects, the award of a construction contract to the general contractor is based on competitive sealed bidding, also called open bidding. This refers to the process by which qualified contractors are invited to bid on the project. The invitation is generally issued through advertisements in newspapers, trade publications, and other public media. The advertisement for bids includes a description of the project, its location, where to obtain the bidding documents, the price of the bidding documents, the bid opening date and location, and other important information. The purpose of the advertisement is to notify and thereby attract a sufficient number of contractors to compete for the construction contract.
  14. DBB METHOD—COMPETITIVE SEALED PROPOSAL This method is very similar to competitive sealed bidding and is commonly used for publicly funded projects. The difference between competitive sealed bidding and competitive sealed proposal methods is that the owner’s selection of the general contractor is not based on price alone but also on such other criteria as the contractor’s past experience, safety record, proposed personnel, project schedule, and so on. To ensure fairness, the advertisement and bidding documents must provide the details of the selection criteria, with relative weightings assigned to each criterion. DBB METHOD—INVITATIONAL BIDDING Invitational bidding, also called closed bidding, is another variation of the DBB method that is generally used for quasi-public and some private projects. In this method, the owner preselects general contractors who have demonstrated, based on their experience, resources, and financial standing, their qualifications to perform the work. The selected contractors are then invited to bid for the project, and the contractor with the lowest bid is then awarded the contract. The architect (as the owner’s representative) may be involved in the prescreening process.
  15. Once the general contractor has been selected and the contract awarded, the construction work begins, as described in the contract documents. The contract documents are virtually the same as the bidding documents, except that the contract documents are part of a signed legal contract between the owner and the contractor. They generally do not contain Division 00 of the MasterFormat. In preparing the contract documents, the design team’s challenge is to efficiently produce the graphics and text that effectively communicate the design intent to the construction professionals and the related product suppliers and manufacturers so that they can do the following: • Propose accurate and competitive bids • Prepare detailed and descriptive submittals for approval • Construct the building with a minimum number of questions, revisions, and changes
  16. The construction drawings and the specifications should provide a fairly detailed delineation of the building. However, they do not describe it to the extent that fabricators can produce building components directly from them. Therefore, the fabricators generate their own drawings, referred to as shop drawings, to provide the higher level of detail necessary to fabricate and assemble the components. Shop drawings are not generic, consisting of manufacturers’ or suppliers’ catalogs, but are specially prepared for the project by the manufacturer, fabricator, erector, or subcontractors. For example, an aluminum window manufacturer must produce shop drawings to show that the required windows conform with the construction drawings and the specifications. Similarly, precast concrete panels, stone cladding, structural steel frame, marble or granite flooring, air-conditioning ducts, and other components require shop drawings before they are fabricated and installed. Before commencing fabrication, the fabricator submits the shop drawings to the general contractor. The general contractor reviews them, marks them “approved,” if appropriate and then submits them to the architect for review and approval. Subcontractors or manufacturers cannot submit shop drawings directly to the architect.
  17. There are only two times during the construction of a project that the architect makes an exception to being an observer of construction. At these times, the architect inspects the work. These inspections are meant to verify the general contractor’s claim that the work is (a) substantially complete and (b) has been completed and hence is ready for final payment. These inspections, explained in Section 1.10, are referred to as: • Substantial completion inspection • Final completion inspection
  18. In addition to construction observation and inspection, there are several other duties the architect must discharge in administering the contract between the owner and the contractor. These are outlined in the box “Summary of Architect’s Functions as Construction Contract Administrator.” Certifying (validating) the contractor’s periodic requests for payment against the work done and the materials stored at the construction site is perhaps the most critical of these functions. An application for payment (typically made once a month unless stated differently in the contract) is followed by the architect’s evaluation of the work and necessary documentation to verify the contractor’s claim. Because the architect is not involved in day-to-day supervision, the issuance of the certificate of payment by the architect does not imply acceptance of the quality or quantity of the contractor’s work. However, the architect has to be judicious and impartial to both the owner and the contractor and perform within the bounds of the contract.