Critical Review on Causes and Effects of Variation Order on
Construction Project
Anatol Berhanu Gobana1, Abhishek Singh Thakur 2
1PG Student, Dept. of Civil Engineering, Parul University, Gujarat, India
2Assistant professor, Dept. of Civil Engineering, Parul University, Gujarat, India
---------------------------------------------------------------------***---------------------------------------------------------------------
Abstract -The greatest inevitable situation in construction
projects is variation. This variation orders are available in all
kind of construction projects and acting a significant part in
defining the ultimate budget and duration of the projects.
Variation Order is a common occurrence in construction
projects. It includes a modification of the prior scope of tasks
as in the contract. Change order of scope of work is caused
from various issues. The origins of variation orders are
characterized under employer related, consultant related,
building executor related and other related causes. The down
side of this variation order was it brought cost and schedule
overrun and causes disagreement and claims among the
contract parties. Thus, this paper is an effort to define
variation order, causes and effect of variation order, waste
related with change orders and differentliteraturereviewsare
discussed.
Key Words: variation order, causes, effects, construction
projects.
1. INTRODUCTION
The charge of a construction project is one of the greatest
important factors in the construction manufacturing.
Because of different reasons, the budget of a project can
suggestively differ from the first valued price. Their sources
might be alterations in scope of task, specifications, or any
other agreement form. In the construction business,
variation orders are made after changes occur. Itcoversaset
of orders which permitsalterations or alterationstobedone
to an earlier consent in case of capacity or nature of work to
be carried out. When a variation order is created, it brings
several undesirable effects to both the employer and the
construction executors. For completionoflargeconstruction
projects we have to complete small construction tasks in
regular manner. For that lot of exertions are taken. The
variation orders are unlucky causes to interrupt the
movement of construction procedure instantaneously stay
the construction project. They involved alteration, extra
work, deleting, and exchanging in terms of quality, quantity
and duration of work. When extra work, subtraction, or any
other revision had done project goalmouths and scope of
project are considered to be variation, whether they
accelerate or deduct the project budget or schedule.Changes
in construction projects means to an modification to design,
construction tasks, project sequencers or project
characteristics produced by adjustments of previous
situations, assumptions, or requirements. Variation orders
have effect on complete project routine because changesare
able to bring considerable alteration to the agreement
period, total direct and indirect cost, or both. [10]
The tackling of these variations needs sufficientskill;inwhat
manner we manage that change without affecting our final
achievement. Monitoring change order is the greatest
importance to the achievement of construction project.
These variations sometimes occur after the grant of the
preliminary agreement or after work might have started at
the construction sites. The key reasons of variation orders
are characterized beneath employer related, consultant
related and contractor related and other related sources of
change orders. When the number of change order on a
project rises, in the similar way the likelihood of
misinterpretation between the agreement teams. Such a
misinterpretation may happen due to one of the parties has
no talent of the variation order procedure itself, the budget
included in executing changes, or the postponements,
disagreements, and interruption of the construction
sequence and calendar which can unfavourably impact
project management. [4]
1.1 Variation order in construction project
A construction contract is a business agreement that is
subject to variability. Contractual articles relating to
variations allow contractual teams involved in the tender to
easily motivate change orders within the influence of the
scope of the works without altering the original contract.
Change orders involve extra work, subtraction, alterations
and replacements in terms of quality, quantity and duration
of works. Without contractual Clauses, the contractors who
were licensed on building should have to decide to upright
the building as per the design and represented in the
agreement forms. Any insignificant alteration that the
employer needs to prepare far along mean that the contract
must be removed and a fresh added was drawn up. [5]
Variation order is the eccentricity practiced in some scheme
from base agreement or task scope equally agreed at
contracting duration. It is written contract among the
construction partiesthat symbolize extra work,omission, or
reconsideration to the agreement documents, identifies the
alteration in price and time and describes the nature of the
task involved.Change ordersincreases for altered sourcesof
whichcertain reasons are predictable and the leftonearenot
predicted. [11]
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 04 Issue: 12 | Dec-2017 www.irjet.net p-ISSN: 2395-0072
© 2017, IRJET | Impact Factor value: 6.171 | ISO 9001:2008 Certified Journal | Page 1603
1.2 Causes of variation orders.
Many papers had identified that different originof variation
orders in construction project. The enormity of the many
origins of change order were listed before this time by
different researchers revealsthat changeshasbecomeoneof
the construction project factors that weakens construction
projects and it focuses many stakeholders.Thisvariationhas
been characterized into consultantrelated,employerrelated,
building executor related and other related change order
and the other variation is listed asforce majeure.Theorigins
of project change in project may originate from either
external or internal pressures that are being applied to the
project. External causes may be due to of technological
changes, changes in the customer expectations and tastes,
alterations in competitor’s activities, modifications in
government and policies, adjustments in the economy and
finally demographic amendments in the society. Internal
causes may emanate as of changes in management policy,
changes in organizational objectives andchangesinthelong-
term survival strategy of the organizations involved. [1]
The foremost origin of change orders on construction
projects are inadequate working drawing, design
inconsistencies, disagreement between contract sum, the
alteration of plans by employers, impairment in rapid
decision making procedure, insufficient project aim and
objectives, and replacement of materials or procedures,
location of site, lack of expert manpower, building executor
anticipation on profit and contractor’s financial difficulties.
As a results of literature reviews, origins of change orders
were listed out such as: Alteration of schedule, differencesin
scope, employers financial difficulties, Weakness to quick
decision-making process, stubborn nature of the employer,
Change in specifications by the employers, Alteration in
design by the consultant, disagreement among contract
documents, Design complexity,Insufficientworkingdrawing,
Alteration in specification by the consultant, Unobtainability
of equipment, lack of well-trained manpower, Contractor’s
monetary problems and Poor workmanship. [1, 3]
Below figure reveals that origin of change order in many
construction projects using a survey study analysis focused
on the amount of incidences and percentage. [9]
Fig 1. Causes of variation order, Adopted from [9]
1.3 Effects of Variation Orders
Variation orders exert various effects on the projects.
Numerousresearchershave emphasized theeffectofchange
order. Impact is the pressure of hollow of one thing on
another. In construction, extra work or omission of scope of
activitiesof the project can bring effect on the portionsofthe
project directly or indirectly. Therefore, itisalwaysaspecific
issue as the contractor feels that the disadvantage due to
change order is the burden of the designers and owners.
Conversely, employers characteristically claim that the
slowdown of outcome is because of poor monitoring due to
building executors. However, not every variation order will
impact the consequence of the project. Changes in any
prearranged activity will bring a disorder and needs the
rearrangement or rechecking of the existing plan under the
recent developments. It was found that variation orders
issued during many stages of constructionprojectsadversely
exaggerated equally budget and calendar of projects. [10]
1.4 Waste associated with variation orders
The origin of variation orders can be strong-minded by
referring to both the reasons for their incidence and
following effects. Variation orders cab be classified as,
beneficial and detrimental change orders. A beneficial
change order is one delivered to increase the quality
standard, decrease price, calendar, or grade of effort in a
project. A beneficial variation order abolishes needless
prices from a project; and hence, it improves the employer
welfarescontrary to the reserve inputbyabolishingneedless
prices. While most construction industry stakeholders are
debatably interested in the lessening of overall production
prices, they are not always mindful of theextentofnon-value
providing extra tasks on construction projects. Accordingly,
there is a lack of knowledge about valueless costs related
with change orders. The realistic quantification ofsuch costs
is sticky because of shortage of suitable techniques for their
measurement. In common practice, non-value-addingprices
ascending from change ordersthat are typically transported
to be miscalculated. For instance, one may capable to
compute the pricesof terminated works, but valuelessprice
arising from non-productive period; redesign and
expenditures are not credited to such an action. Very often
these prices are unwittingly relocated beneaththeversionof
contingencies. [10]
2. LITERATURE REVIEWS
OjoAyodeji, Sunday (2010), published a paper on impact of
variation orders on public construction projects. The
investigation proves that insufficient workings drawing
details, design inconsistencies, and disagreement between
contract parties are the most predominant sources of
changesdue to consultants, alteration of plansbyemployers,
impairment in quick decision making process, and
insufficient project objectives contributed mostly to
variations by the employers. Contractors’ predominant
reasons for variations are opposing site situations, lack of
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 04 Issue: 12 | Dec-2017 www.irjet.net p-ISSN: 2395-0072
© 2017, IRJET | Impact Factor value: 6.171 | ISO 9001:2008 Certified Journal | Page 1604
skilled manpower, and contractor’s desired cost-
effectiveness. There is a connection among the assessments
by the respondent concerning the consultant related
variations and the projects fingered by the consultants. The
investigation has shown that effect of variation has superior
important effect on the projects held by the consultantsthan
the in-house project staff regardless of the kind and scope of
the projects. It is expected that these will support the
administration to recheck the conditions at which the
consultant and the in-house staff operate to better
understand the usefulness of the consultantandthein-house
construction professional staff.
R.U.Halwatura and N.P.N.P.Ranasinghe, (2013), have
published a paper on causes of change order in road
construction Projects. The study concluded that the
consultants do not take about satisfactory investigations at
the initial investigation and design phase. Therefore,several
site conditions rise in the construction stage. Additionally,
employers do not have talented professional stafftoprepare
inquiries and estimates, which are prepared by consultants
and are not precise in most situations. Therefore, several
needless variations happen during the construction phase.
Apart from this most of the time the foremost reasons were,
the fault of the client is not pointed out and not documented.
According to the survey results, a political force during
construction phase is listed out as a leading factor.
A.A. Oladapo,(2007), has studied a paper on assessment of
the cost and time impact of variation orderson construction
projects. The study has discovered that alterations in
specifications and scope, initiated mostly by project owners
and their consultants, are the maximum predominant
sources of variation. This results mainly from changes in
owners’ income/financial ability, changes in owners’
interests/requirements, design errors and insufficient time
for preparation of agreement forms. The study concludes
that variation had a significant impact on project budgetand
schedule invades and that project size and type did not
significantly affect the project prices and calendar. The
expectation of this study was that to enable project clients,
consultants, contractors and other stakeholders to realize
and appreciate the real effect of variation on project routine.
Amiruddin, Ismail, Towhid and Pourrostam, (2012),
published paper on factors causing variation orders and
their effects in roadway construction projects. This study
which was held on an estate in the southern part of Iran has
been capable to separate origins and impacts of variation
orders in construction projects. It was observed that
alteration of plans or scope by employer, errors and
omissions in design and clients’ financialdifficultieswerethe
serious factors that cause the existence variation orders in
roadway construction projects. In addition, the
consequences prove that schedule and budget overrunsand
disagreement had great important effectsonprojectroutine.
It is to the advantage of this study that its applications are
very relevant not only in Iran’s roadwayconstructionsystem
but also in other developing countries construction
industries.
Alia Alaryan, Emadelbeltagi, Ashraf Elshahat and Mahmoud
Dawood,(2014), published a paper on change orders on
construction Projects. The investigation found that the most
five common causes of change orders can be listed out as:
alteration of plans by client, alteration of project scope by
client, difficulties on site, errors and omission in design,
insufficient design and inadequate working drawing details.
The most five common effects of change orderareincreasing
the project’s budget, accelerate the duration of individual
events, postponing in completionschedule,additionalmoney
for contractor, and delaying in payment. Finally, themostsix
common control actions are: inspecting and reviewing the
contract documents, reviewing design before change
approval, the change order must be negotiated by educated
persons, the scope of change orders must be precisely done,
careful checking in writing must be handed, and the
respectable utensils to control the incidence of change
including the areas of concern in monthly reports and
meetings.
Ijaola, I.A and Iyagba R.O, (2012), published paper on
comparative study of causes of change orders in
construction project. This study investigated the causes,
effect, advantage and solutions of variation order in Nigeria
and compare it with that of Oman. It was concluded that the
major causesof change ordersin NigeriaandOmanarethose
related to employers and the major reason is that owner
request for additional works. The impact of these changes
has leads to claims and disputes, time overrun and cost
inflation in both Nigeria and Oman. The study also identified
the contractor asthe most helping partiesof change orderin
Nigeria as most respondents believed that the building
executor uses suitable areas in general conditions and asks
extra payment to be paid for them. The contractor was also
ranked as most beneficiary of variation order in Oman.
Noraziah Mohammad, Adi Irfan Che Ani , Riza Atiq O.K.
Rakmat (2017), published paper on causes and effects of
variation orders in the construction of terrace housing
Projects. The 18 causes of changes that are identified
through a literature review were used as a guide or
foundation in collecting information to know the sources of
changes in working in strip Selangor, found that only 10
causes of employment changes are related to changes in
work for the terrace houses in the district of Selangor. From
the consequences of case studies there are five main causes
that led to the introduction of changes in the housing
projects in the state. The causes are as follows:
 Changes in the scope of the work by the client.
 Exchange of construction materials by the client.
 Specification changes by the client.
 Changes in building design by the consultant.
 Differences between the contract forms and
drawings.
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 04 Issue: 12 | Dec-2017 www.irjet.net p-ISSN: 2395-0072
© 2017, IRJET | Impact Factor value: 6.171 | ISO 9001:2008 Certified Journal | Page 1605
Among the main effects were identified and investigated in
joining with variation order are as follows:
 Increase project time
 The increase in the project cost.
 delay logistics
 The impact on the quality of the project
 Destruction and reconstruction
M.Gokulkarthi, K.S. Gowrishankar (2015), publishedapaper
on a study on impacts of change order in construction
projects. Based on the field survey conducted and the
consequences were achieved, the following as can be
determined and outlined:
 Changing the plans by the owners is the main
source of change orders. This is because shortageof
participation in the design growth and incapability
to imagine it while not appreciating the undesirable
impact on it.
 Because of new materialsare becoming availablein
the market or change in mind, substituting
materials and/or proceduresis thesecondsourceof
change orders.
 Consultants are the second major contributor to
changes by generating conflictingdesigndocuments
or through alteration in design afterwards.
 Rise in project price and duration are the main two
effects being noted for change orders.
 Clarity of scope of change orders ranked the first
among controls adopted.
Onkar U. Jadhav , Prof. Abhijit N. Bhirud (2015), published
paper on an analysis of causes and effects of change orders
on construction Projects. As per survey carried out get
different kinds of answers and responses from the
construction place .The root sources of variation order in
construction projects in is client alterations, extra activities
and adjustment to prior work. Another key reason is lack of
building executor participation in design phase. It may
indicate absence of thoughtful design at the period of actual
construction. The other causes are unrealistic design
periods, the absence of information between contractorand
the consultants.
The effects are the most important change orders increases
the cost of the projects. Probably increase the period of
individual activates that effect on completion timetable of
the projects. Paying extra money for the contractor is the
mostly effects caused on different construction sites.
Ruben Ndihokubwayo, Theo Haupt (2009), published paper
on Variation orders on constructionprojects:valueaddingor
waste? Study found that consultants accepted time frames
proposed by clients instead of proposing realistic
timeframes to accomplish the design. As a result they
embarked on tendering whether the design was completed
or not because they knew other required changes would be
permissible under the conditions of contract. It was
therefore determined that the employerwasthefurthermost
leading source agent of variation orders. Most variation
ordersadded value to the project. However, waste wasstilla
consequence of them. It was investigated that changeorders
were not persuasively estimated resulting in increased
construction budget. Time and cost escalation and disputes
had foremost effects on project routine. There were no
standard methodsfor recording and administeringvariation
orders. While respondentssuggestedthatchangeordermust
be reduced, they acknowledged that clients had the right to
initiate changes provided they were contractually
permissible and were preparedtoremuneratetheassociated
costs.
Aftab Hameed Memon, Ismail AbdulRahman and Mohamad
Faris AbulHasan (2014), published a paper on Significant
Causes and Effects of Variation Orders in Construction
Projects. The investigation was attempting to list out the
foremost sources and impacts of changes in construction
projects. Average index analysisof the collected information
through survey shows that:
 In Malaysian construction projects, variations are
often experienced in JKR projects.
 Five most important causes are absence of
apparatus, poor workmanship, design difficulty,
alteration of schedule and impairment to quick
decision making procedure.
 Logistic delays, postponement in conclusion and
increase project budget are important impact of
variations confronted in construction projects.
3. CONCLUSION
Based on various literature reviews the causes and effect of
variation orders were categorized under employer related,
consultant related, contractors related and other related
grounded on type of the task. The employer related causes
were change of plans, alteration of project scope, extra tasks
and adjustment to previous work and financial difficulties,
The consultant related causes were; insufficient workings
drawing details, design inconsistencies, and disagreement
among contract documents are the most predominant
origins of variations, Contractors’ prevalent reasons for
variations were differing site conditions, lack of trained
manpower, and contractor’sdesiredprofitability.Theimpact
of change order within construction project wereresultedin
claims and disputes, time overrun and cost overrun, delay
logistics, impact on the quality of the project, anddemolition
and rebuilding. Yet, no unique method is available for
minimizing variation orderseffectively.However,theireffect
can be minimized with an appropriate study about the
causes. The consultants’ and the contractors’ response
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 04 Issue: 12 | Dec-2017 www.irjet.net p-ISSN: 2395-0072
© 2017, IRJET | Impact Factor value: 6.171 | ISO 9001:2008 Certified Journal | Page 1606
argued on the strategy that states adequate planning in
advance is required by all involved parties before works
start on site to minimize variation orders. This was because
a well-planned project can eliminate change that will
increase because of shortage of prior project development.
REFERENCES
[1] OjoAyodeji, Sunday, published a paper on Impact of
Variation Orders on Public Construction Projects,
Ministry of National Development,IndependenceHouse,
Victoria, Volume 1, Issue September, PP 101-110, 2010.
[2] R.U. Halwatura and N.P.N.P. Ranasinghe Hindawi,
Causes of Variation Orders in Road Construction
Projects, Publishing Corporation ISRN Construction
Engineering 2013, in Sri Lanka, Volume 13, PP1-7,2013
[3] A.A. Oladapo, Durban, Assessment of the cost and time
impact of variation orders on construction projects
,Journal of Engineering, Design and Technology, South
Africa, Volume 5, Issue 1, PP 35-48, 2007
[4] Amiruddin Ismail, Towhid Pourrostam, Amir
Soleymanzadeh and Majid Ghouyounchizad, Factors
Causing Variation Orders and their Effects in Roadway
Construction Projects, Research Journal of Applied
Sciences, Engineering and Technology, Shoushtar, Iran,
Volume 4, Issue 23, PP 4669-4972, 2012.
[5] Alia Alaryan, Emadelbeltagi Ashraf Elshahat and
Mahmoud Dawood Alia Alaryan et, Causes and Effectsof
Change Orders on Construction Projects, Int. Journal of
Engineering Research and Applications, Volume4,Issue
2, PP 2248-962201, 2014.
[6] Ijaola, I.A and Iyagba R.OA, Comparative StudyofCauses
of Change Orders in Public Construction Project in
Nigeria and Oman, Journal of Emerging Trends in
Economics and ManagementSciences(JETEMS),Volume
3, Issue 5,PP 495-501, 2012.
[7] Noraziah Mohammad, Adi Irfan Che Ani , Riza Atiq O.K.
Rakmat, Causes and Effects of Variation Orders in the
Constructionof Terrace Housing Projects, International
Journal of Supply Chain Management, Volume6,Issue,1,
PP 226-223, 2017
[8] M.Gokulkarthi, K.S.Gowrishankar, A ComparativeStudy
of Causes of Change Orders in Public Construction
Project ,Journal of Emerging Trends in Economics and
Management Sciences, Volume 3, Issue 1, PP 65-72,
2015.
[9] Onkar U. Jadhav , Prof. Abhijit N. Bhirud, An Analysis Of
Causes and Effects Of Change Orders On Construction,
International Journal of Engineering Research and
General Science,Volume 4, Issue 2, PP 2248-962201,
2015.
[10] Ruben Ndihokubwayo and Theo Haupt,Variation
Orders On Construction Projects: Value Adding Or
Waste?, International Journal of Construction Project
Management, Volume 1, PP 1-17, 2009
[11] Aftab Hameed Memon, Ismail Abdul Rahman and
Mohamad Faris Abul Hasan, Published paper on
Significant Causes and Effects of Variation Orders in
Construction Projects, Research Journal of Applied
Sciences, Engineering and Technology, Volume 7, Issue
21, PP 4494-4502, 2014.

More Related Content

What's hot

IRJET- Schedule Delay Analysis in Construction Management using Primavera P6
IRJET- Schedule Delay Analysis in Construction Management using Primavera P6IRJET- Schedule Delay Analysis in Construction Management using Primavera P6
IRJET- Schedule Delay Analysis in Construction Management using Primavera P6IRJET Journal
 
A Review of Cost overruns in Construction Project Management
A Review of Cost overruns in Construction Project ManagementA Review of Cost overruns in Construction Project Management
A Review of Cost overruns in Construction Project Managementijsrd.com
 
project on construction of house report.
project on construction of house report.project on construction of house report.
project on construction of house report.Hagi Sahib
 
Construction Compliance Consultants
Construction Compliance ConsultantsConstruction Compliance Consultants
Construction Compliance Consultantsbfitzsimons1974
 
Construction project management
Construction project managementConstruction project management
Construction project managementsaif hasan
 
Effect of construction delays on project time overrun
Effect of construction delays on project time overrunEffect of construction delays on project time overrun
Effect of construction delays on project time overruneSAT Publishing House
 
Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...
Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...
Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...iosrjce
 
Cost Overrun Causes Related to the Design Phase in the Egyptian Construction ...
Cost Overrun Causes Related to the Design Phase in the Egyptian Construction ...Cost Overrun Causes Related to the Design Phase in the Egyptian Construction ...
Cost Overrun Causes Related to the Design Phase in the Egyptian Construction ...World-Academic Journal
 
Basement remodel rev eh
Basement remodel rev ehBasement remodel rev eh
Basement remodel rev ehesands2437
 
5 Popular Types of Construction Contracts
5 Popular Types of Construction Contracts5 Popular Types of Construction Contracts
5 Popular Types of Construction ContractsSHAZEBALIKHAN1
 
Project Engineer 3
Project Engineer 3Project Engineer 3
Project Engineer 3Sunil Mall
 
Project change management plan template
Project change management plan templateProject change management plan template
Project change management plan templateVivek Srivastava
 
My 5 Learnings of Waterfall Project Management
My 5 Learnings of Waterfall Project ManagementMy 5 Learnings of Waterfall Project Management
My 5 Learnings of Waterfall Project ManagementSHAZEBALIKHAN1
 
Reasons for the Delay and Cost Overrun in Residential Projects - 2017
Reasons for the Delay and Cost Overrun in Residential Projects - 2017Reasons for the Delay and Cost Overrun in Residential Projects - 2017
Reasons for the Delay and Cost Overrun in Residential Projects - 2017Sankalp Swarnkar
 
How Does MS Project Works 6- Task Controlling Factors
How Does MS Project Works 6- Task Controlling FactorsHow Does MS Project Works 6- Task Controlling Factors
How Does MS Project Works 6- Task Controlling FactorsSHAZEBALIKHAN1
 
“Investigation of Time-Cost Effectiveness on Construction Projects”
“Investigation of Time-Cost Effectiveness on Construction Projects”“Investigation of Time-Cost Effectiveness on Construction Projects”
“Investigation of Time-Cost Effectiveness on Construction Projects”IOSR Journals
 
Project Management Control
Project Management ControlProject Management Control
Project Management ControlVinay Mangrulkar
 
Resume - Khalid Hussain Project
Resume - Khalid Hussain ProjectResume - Khalid Hussain Project
Resume - Khalid Hussain ProjectKhalid Hussain
 
Construction Project Management Class Project Presentation
Construction Project Management Class Project PresentationConstruction Project Management Class Project Presentation
Construction Project Management Class Project PresentationWayne Holley
 

What's hot (20)

IRJET- Schedule Delay Analysis in Construction Management using Primavera P6
IRJET- Schedule Delay Analysis in Construction Management using Primavera P6IRJET- Schedule Delay Analysis in Construction Management using Primavera P6
IRJET- Schedule Delay Analysis in Construction Management using Primavera P6
 
A Review of Cost overruns in Construction Project Management
A Review of Cost overruns in Construction Project ManagementA Review of Cost overruns in Construction Project Management
A Review of Cost overruns in Construction Project Management
 
project on construction of house report.
project on construction of house report.project on construction of house report.
project on construction of house report.
 
Claims
ClaimsClaims
Claims
 
Construction Compliance Consultants
Construction Compliance ConsultantsConstruction Compliance Consultants
Construction Compliance Consultants
 
Construction project management
Construction project managementConstruction project management
Construction project management
 
Effect of construction delays on project time overrun
Effect of construction delays on project time overrunEffect of construction delays on project time overrun
Effect of construction delays on project time overrun
 
Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...
Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...
Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...
 
Cost Overrun Causes Related to the Design Phase in the Egyptian Construction ...
Cost Overrun Causes Related to the Design Phase in the Egyptian Construction ...Cost Overrun Causes Related to the Design Phase in the Egyptian Construction ...
Cost Overrun Causes Related to the Design Phase in the Egyptian Construction ...
 
Basement remodel rev eh
Basement remodel rev ehBasement remodel rev eh
Basement remodel rev eh
 
5 Popular Types of Construction Contracts
5 Popular Types of Construction Contracts5 Popular Types of Construction Contracts
5 Popular Types of Construction Contracts
 
Project Engineer 3
Project Engineer 3Project Engineer 3
Project Engineer 3
 
Project change management plan template
Project change management plan templateProject change management plan template
Project change management plan template
 
My 5 Learnings of Waterfall Project Management
My 5 Learnings of Waterfall Project ManagementMy 5 Learnings of Waterfall Project Management
My 5 Learnings of Waterfall Project Management
 
Reasons for the Delay and Cost Overrun in Residential Projects - 2017
Reasons for the Delay and Cost Overrun in Residential Projects - 2017Reasons for the Delay and Cost Overrun in Residential Projects - 2017
Reasons for the Delay and Cost Overrun in Residential Projects - 2017
 
How Does MS Project Works 6- Task Controlling Factors
How Does MS Project Works 6- Task Controlling FactorsHow Does MS Project Works 6- Task Controlling Factors
How Does MS Project Works 6- Task Controlling Factors
 
“Investigation of Time-Cost Effectiveness on Construction Projects”
“Investigation of Time-Cost Effectiveness on Construction Projects”“Investigation of Time-Cost Effectiveness on Construction Projects”
“Investigation of Time-Cost Effectiveness on Construction Projects”
 
Project Management Control
Project Management ControlProject Management Control
Project Management Control
 
Resume - Khalid Hussain Project
Resume - Khalid Hussain ProjectResume - Khalid Hussain Project
Resume - Khalid Hussain Project
 
Construction Project Management Class Project Presentation
Construction Project Management Class Project PresentationConstruction Project Management Class Project Presentation
Construction Project Management Class Project Presentation
 

Similar to Critical Review on Causes and Effects of Variation Orders in Construction Projects

A Study for the Causes of Variation Orders in Different Sectors of Constructi...
A Study for the Causes of Variation Orders in Different Sectors of Constructi...A Study for the Causes of Variation Orders in Different Sectors of Constructi...
A Study for the Causes of Variation Orders in Different Sectors of Constructi...Sarah Adams
 
028 fast-tracking projects & cost overrun
028 fast-tracking projects & cost overrun028 fast-tracking projects & cost overrun
028 fast-tracking projects & cost overrunDr Fereidoun Dejahang
 
Project change request template v2.0
Project change request template v2.0Project change request template v2.0
Project change request template v2.0Aditya Pandey
 
A study on the analysis and evaluation of delays in private construction Proj...
A study on the analysis and evaluation of delays in private construction Proj...A study on the analysis and evaluation of delays in private construction Proj...
A study on the analysis and evaluation of delays in private construction Proj...IRJET Journal
 
HOW TO MINIMIZE DELAYS IN CONSTRUCTION OF COMMERCIAL PROJECT
HOW TO MINIMIZE DELAYS IN CONSTRUCTION OF COMMERCIAL PROJECTHOW TO MINIMIZE DELAYS IN CONSTRUCTION OF COMMERCIAL PROJECT
HOW TO MINIMIZE DELAYS IN CONSTRUCTION OF COMMERCIAL PROJECTIRJET Journal
 
Changes in construction projects
Changes in construction projectsChanges in construction projects
Changes in construction projectsMohamed Abdalla
 
1616-5398-2-PB.pdf
1616-5398-2-PB.pdf1616-5398-2-PB.pdf
1616-5398-2-PB.pdfEyobMiteku
 
Study on the analysis and evaluation of delays in public sector construction ...
Study on the analysis and evaluation of delays in public sector construction ...Study on the analysis and evaluation of delays in public sector construction ...
Study on the analysis and evaluation of delays in public sector construction ...IRJET Journal
 
Planning & Scheduling of Commercial Building using Microsoft Project & Applic...
Planning & Scheduling of Commercial Building using Microsoft Project & Applic...Planning & Scheduling of Commercial Building using Microsoft Project & Applic...
Planning & Scheduling of Commercial Building using Microsoft Project & Applic...IRJET Journal
 
Change management
Change managementChange management
Change managementmehak1990
 
014 changes-cost overrun measurement
014 changes-cost overrun measurement014 changes-cost overrun measurement
014 changes-cost overrun measurementDrFereydounDejahang
 
014 changes-cost overrun measurement
014 changes-cost overrun measurement014 changes-cost overrun measurement
014 changes-cost overrun measurementDr Fereidoun Dejahang
 
014 changes-cost overrun measurement
014 changes-cost overrun measurement014 changes-cost overrun measurement
014 changes-cost overrun measurementdrdej19
 
014 changes-cost overrun measurement
014 changes-cost overrun measurement014 changes-cost overrun measurement
014 changes-cost overrun measurementDrFereydounDejahang
 
014 changes-cost overrun measurement
014 changes-cost overrun measurement014 changes-cost overrun measurement
014 changes-cost overrun measurementDr Fereidoun Dejahang
 
014 changes-cost overrun measurement
014 changes-cost overrun measurement014 changes-cost overrun measurement
014 changes-cost overrun measurementDr Fereidoun Dejahang
 
IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...
IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...
IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...IRJET Journal
 

Similar to Critical Review on Causes and Effects of Variation Orders in Construction Projects (20)

A Study for the Causes of Variation Orders in Different Sectors of Constructi...
A Study for the Causes of Variation Orders in Different Sectors of Constructi...A Study for the Causes of Variation Orders in Different Sectors of Constructi...
A Study for the Causes of Variation Orders in Different Sectors of Constructi...
 
TOPIC7.pdf
TOPIC7.pdfTOPIC7.pdf
TOPIC7.pdf
 
028 fast-tracking projects & cost overrun
028 fast-tracking projects & cost overrun028 fast-tracking projects & cost overrun
028 fast-tracking projects & cost overrun
 
Project change request template v2.0
Project change request template v2.0Project change request template v2.0
Project change request template v2.0
 
A study on the analysis and evaluation of delays in private construction Proj...
A study on the analysis and evaluation of delays in private construction Proj...A study on the analysis and evaluation of delays in private construction Proj...
A study on the analysis and evaluation of delays in private construction Proj...
 
HOW TO MINIMIZE DELAYS IN CONSTRUCTION OF COMMERCIAL PROJECT
HOW TO MINIMIZE DELAYS IN CONSTRUCTION OF COMMERCIAL PROJECTHOW TO MINIMIZE DELAYS IN CONSTRUCTION OF COMMERCIAL PROJECT
HOW TO MINIMIZE DELAYS IN CONSTRUCTION OF COMMERCIAL PROJECT
 
Changes in construction
Changes in constructionChanges in construction
Changes in construction
 
Changes in construction projects
Changes in construction projectsChanges in construction projects
Changes in construction projects
 
1616-5398-2-PB.pdf
1616-5398-2-PB.pdf1616-5398-2-PB.pdf
1616-5398-2-PB.pdf
 
Unit 1
Unit 1Unit 1
Unit 1
 
Study on the analysis and evaluation of delays in public sector construction ...
Study on the analysis and evaluation of delays in public sector construction ...Study on the analysis and evaluation of delays in public sector construction ...
Study on the analysis and evaluation of delays in public sector construction ...
 
Planning & Scheduling of Commercial Building using Microsoft Project & Applic...
Planning & Scheduling of Commercial Building using Microsoft Project & Applic...Planning & Scheduling of Commercial Building using Microsoft Project & Applic...
Planning & Scheduling of Commercial Building using Microsoft Project & Applic...
 
Change management
Change managementChange management
Change management
 
014 changes-cost overrun measurement
014 changes-cost overrun measurement014 changes-cost overrun measurement
014 changes-cost overrun measurement
 
014 changes-cost overrun measurement
014 changes-cost overrun measurement014 changes-cost overrun measurement
014 changes-cost overrun measurement
 
014 changes-cost overrun measurement
014 changes-cost overrun measurement014 changes-cost overrun measurement
014 changes-cost overrun measurement
 
014 changes-cost overrun measurement
014 changes-cost overrun measurement014 changes-cost overrun measurement
014 changes-cost overrun measurement
 
014 changes-cost overrun measurement
014 changes-cost overrun measurement014 changes-cost overrun measurement
014 changes-cost overrun measurement
 
014 changes-cost overrun measurement
014 changes-cost overrun measurement014 changes-cost overrun measurement
014 changes-cost overrun measurement
 
IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...
IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...
IRJET- Factors Influencing Time and Cost Overruns in Indian Construction Proj...
 

More from IRJET Journal

TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...IRJET Journal
 
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURESTUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTUREIRJET Journal
 
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...IRJET Journal
 
Effect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsEffect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsIRJET Journal
 
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...IRJET Journal
 
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...IRJET Journal
 
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...IRJET Journal
 
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...IRJET Journal
 
A REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASA REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASIRJET Journal
 
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...IRJET Journal
 
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProP.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProIRJET Journal
 
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...IRJET Journal
 
Survey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemSurvey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemIRJET Journal
 
Review on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesReview on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesIRJET Journal
 
React based fullstack edtech web application
React based fullstack edtech web applicationReact based fullstack edtech web application
React based fullstack edtech web applicationIRJET Journal
 
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...IRJET Journal
 
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.IRJET Journal
 
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...IRJET Journal
 
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignMultistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignIRJET Journal
 
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...IRJET Journal
 

More from IRJET Journal (20)

TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
 
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURESTUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
 
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
 
Effect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsEffect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil Characteristics
 
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
 
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
 
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
 
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
 
A REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASA REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADAS
 
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
 
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProP.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
 
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
 
Survey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemSurvey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare System
 
Review on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesReview on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridges
 
React based fullstack edtech web application
React based fullstack edtech web applicationReact based fullstack edtech web application
React based fullstack edtech web application
 
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
 
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
 
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
 
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignMultistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
 
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
 

Recently uploaded

Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxDeepakSakkari2
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024Mark Billinghurst
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learningmisbanausheenparvam
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfAsst.prof M.Gokilavani
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx959SahilShah
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxPoojaBan
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoão Esperancinha
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girlsssuser7cb4ff
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfAsst.prof M.Gokilavani
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile servicerehmti665
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxbritheesh05
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 

Recently uploaded (20)

Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptx
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learning
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptx
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girls
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptx
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 

Critical Review on Causes and Effects of Variation Orders in Construction Projects

  • 1. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 04 Issue: 12 | Dec-2017 www.irjet.net p-ISSN: 2395-0072 © 2017, IRJET | Impact Factor value: 6.171 | ISO 9001:2008 Certified Journal | Page 1602 Critical Review on Causes and Effects of Variation Order on Construction Project Anatol Berhanu Gobana1, Abhishek Singh Thakur 2 1PG Student, Dept. of Civil Engineering, Parul University, Gujarat, India 2Assistant professor, Dept. of Civil Engineering, Parul University, Gujarat, India ---------------------------------------------------------------------***--------------------------------------------------------------------- Abstract -The greatest inevitable situation in construction projects is variation. This variation orders are available in all kind of construction projects and acting a significant part in defining the ultimate budget and duration of the projects. Variation Order is a common occurrence in construction projects. It includes a modification of the prior scope of tasks as in the contract. Change order of scope of work is caused from various issues. The origins of variation orders are characterized under employer related, consultant related, building executor related and other related causes. The down side of this variation order was it brought cost and schedule overrun and causes disagreement and claims among the contract parties. Thus, this paper is an effort to define variation order, causes and effect of variation order, waste related with change orders and differentliteraturereviewsare discussed. Key Words: variation order, causes, effects, construction projects. 1. INTRODUCTION The charge of a construction project is one of the greatest important factors in the construction manufacturing. Because of different reasons, the budget of a project can suggestively differ from the first valued price. Their sources might be alterations in scope of task, specifications, or any other agreement form. In the construction business, variation orders are made after changes occur. Itcoversaset of orders which permitsalterations or alterationstobedone to an earlier consent in case of capacity or nature of work to be carried out. When a variation order is created, it brings several undesirable effects to both the employer and the construction executors. For completionoflargeconstruction projects we have to complete small construction tasks in regular manner. For that lot of exertions are taken. The variation orders are unlucky causes to interrupt the movement of construction procedure instantaneously stay the construction project. They involved alteration, extra work, deleting, and exchanging in terms of quality, quantity and duration of work. When extra work, subtraction, or any other revision had done project goalmouths and scope of project are considered to be variation, whether they accelerate or deduct the project budget or schedule.Changes in construction projects means to an modification to design, construction tasks, project sequencers or project characteristics produced by adjustments of previous situations, assumptions, or requirements. Variation orders have effect on complete project routine because changesare able to bring considerable alteration to the agreement period, total direct and indirect cost, or both. [10] The tackling of these variations needs sufficientskill;inwhat manner we manage that change without affecting our final achievement. Monitoring change order is the greatest importance to the achievement of construction project. These variations sometimes occur after the grant of the preliminary agreement or after work might have started at the construction sites. The key reasons of variation orders are characterized beneath employer related, consultant related and contractor related and other related sources of change orders. When the number of change order on a project rises, in the similar way the likelihood of misinterpretation between the agreement teams. Such a misinterpretation may happen due to one of the parties has no talent of the variation order procedure itself, the budget included in executing changes, or the postponements, disagreements, and interruption of the construction sequence and calendar which can unfavourably impact project management. [4] 1.1 Variation order in construction project A construction contract is a business agreement that is subject to variability. Contractual articles relating to variations allow contractual teams involved in the tender to easily motivate change orders within the influence of the scope of the works without altering the original contract. Change orders involve extra work, subtraction, alterations and replacements in terms of quality, quantity and duration of works. Without contractual Clauses, the contractors who were licensed on building should have to decide to upright the building as per the design and represented in the agreement forms. Any insignificant alteration that the employer needs to prepare far along mean that the contract must be removed and a fresh added was drawn up. [5] Variation order is the eccentricity practiced in some scheme from base agreement or task scope equally agreed at contracting duration. It is written contract among the construction partiesthat symbolize extra work,omission, or reconsideration to the agreement documents, identifies the alteration in price and time and describes the nature of the task involved.Change ordersincreases for altered sourcesof whichcertain reasons are predictable and the leftonearenot predicted. [11]
  • 2. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 04 Issue: 12 | Dec-2017 www.irjet.net p-ISSN: 2395-0072 © 2017, IRJET | Impact Factor value: 6.171 | ISO 9001:2008 Certified Journal | Page 1603 1.2 Causes of variation orders. Many papers had identified that different originof variation orders in construction project. The enormity of the many origins of change order were listed before this time by different researchers revealsthat changeshasbecomeoneof the construction project factors that weakens construction projects and it focuses many stakeholders.Thisvariationhas been characterized into consultantrelated,employerrelated, building executor related and other related change order and the other variation is listed asforce majeure.Theorigins of project change in project may originate from either external or internal pressures that are being applied to the project. External causes may be due to of technological changes, changes in the customer expectations and tastes, alterations in competitor’s activities, modifications in government and policies, adjustments in the economy and finally demographic amendments in the society. Internal causes may emanate as of changes in management policy, changes in organizational objectives andchangesinthelong- term survival strategy of the organizations involved. [1] The foremost origin of change orders on construction projects are inadequate working drawing, design inconsistencies, disagreement between contract sum, the alteration of plans by employers, impairment in rapid decision making procedure, insufficient project aim and objectives, and replacement of materials or procedures, location of site, lack of expert manpower, building executor anticipation on profit and contractor’s financial difficulties. As a results of literature reviews, origins of change orders were listed out such as: Alteration of schedule, differencesin scope, employers financial difficulties, Weakness to quick decision-making process, stubborn nature of the employer, Change in specifications by the employers, Alteration in design by the consultant, disagreement among contract documents, Design complexity,Insufficientworkingdrawing, Alteration in specification by the consultant, Unobtainability of equipment, lack of well-trained manpower, Contractor’s monetary problems and Poor workmanship. [1, 3] Below figure reveals that origin of change order in many construction projects using a survey study analysis focused on the amount of incidences and percentage. [9] Fig 1. Causes of variation order, Adopted from [9] 1.3 Effects of Variation Orders Variation orders exert various effects on the projects. Numerousresearchershave emphasized theeffectofchange order. Impact is the pressure of hollow of one thing on another. In construction, extra work or omission of scope of activitiesof the project can bring effect on the portionsofthe project directly or indirectly. Therefore, itisalwaysaspecific issue as the contractor feels that the disadvantage due to change order is the burden of the designers and owners. Conversely, employers characteristically claim that the slowdown of outcome is because of poor monitoring due to building executors. However, not every variation order will impact the consequence of the project. Changes in any prearranged activity will bring a disorder and needs the rearrangement or rechecking of the existing plan under the recent developments. It was found that variation orders issued during many stages of constructionprojectsadversely exaggerated equally budget and calendar of projects. [10] 1.4 Waste associated with variation orders The origin of variation orders can be strong-minded by referring to both the reasons for their incidence and following effects. Variation orders cab be classified as, beneficial and detrimental change orders. A beneficial change order is one delivered to increase the quality standard, decrease price, calendar, or grade of effort in a project. A beneficial variation order abolishes needless prices from a project; and hence, it improves the employer welfarescontrary to the reserve inputbyabolishingneedless prices. While most construction industry stakeholders are debatably interested in the lessening of overall production prices, they are not always mindful of theextentofnon-value providing extra tasks on construction projects. Accordingly, there is a lack of knowledge about valueless costs related with change orders. The realistic quantification ofsuch costs is sticky because of shortage of suitable techniques for their measurement. In common practice, non-value-addingprices ascending from change ordersthat are typically transported to be miscalculated. For instance, one may capable to compute the pricesof terminated works, but valuelessprice arising from non-productive period; redesign and expenditures are not credited to such an action. Very often these prices are unwittingly relocated beneaththeversionof contingencies. [10] 2. LITERATURE REVIEWS OjoAyodeji, Sunday (2010), published a paper on impact of variation orders on public construction projects. The investigation proves that insufficient workings drawing details, design inconsistencies, and disagreement between contract parties are the most predominant sources of changesdue to consultants, alteration of plansbyemployers, impairment in quick decision making process, and insufficient project objectives contributed mostly to variations by the employers. Contractors’ predominant reasons for variations are opposing site situations, lack of
  • 3. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 04 Issue: 12 | Dec-2017 www.irjet.net p-ISSN: 2395-0072 © 2017, IRJET | Impact Factor value: 6.171 | ISO 9001:2008 Certified Journal | Page 1604 skilled manpower, and contractor’s desired cost- effectiveness. There is a connection among the assessments by the respondent concerning the consultant related variations and the projects fingered by the consultants. The investigation has shown that effect of variation has superior important effect on the projects held by the consultantsthan the in-house project staff regardless of the kind and scope of the projects. It is expected that these will support the administration to recheck the conditions at which the consultant and the in-house staff operate to better understand the usefulness of the consultantandthein-house construction professional staff. R.U.Halwatura and N.P.N.P.Ranasinghe, (2013), have published a paper on causes of change order in road construction Projects. The study concluded that the consultants do not take about satisfactory investigations at the initial investigation and design phase. Therefore,several site conditions rise in the construction stage. Additionally, employers do not have talented professional stafftoprepare inquiries and estimates, which are prepared by consultants and are not precise in most situations. Therefore, several needless variations happen during the construction phase. Apart from this most of the time the foremost reasons were, the fault of the client is not pointed out and not documented. According to the survey results, a political force during construction phase is listed out as a leading factor. A.A. Oladapo,(2007), has studied a paper on assessment of the cost and time impact of variation orderson construction projects. The study has discovered that alterations in specifications and scope, initiated mostly by project owners and their consultants, are the maximum predominant sources of variation. This results mainly from changes in owners’ income/financial ability, changes in owners’ interests/requirements, design errors and insufficient time for preparation of agreement forms. The study concludes that variation had a significant impact on project budgetand schedule invades and that project size and type did not significantly affect the project prices and calendar. The expectation of this study was that to enable project clients, consultants, contractors and other stakeholders to realize and appreciate the real effect of variation on project routine. Amiruddin, Ismail, Towhid and Pourrostam, (2012), published paper on factors causing variation orders and their effects in roadway construction projects. This study which was held on an estate in the southern part of Iran has been capable to separate origins and impacts of variation orders in construction projects. It was observed that alteration of plans or scope by employer, errors and omissions in design and clients’ financialdifficultieswerethe serious factors that cause the existence variation orders in roadway construction projects. In addition, the consequences prove that schedule and budget overrunsand disagreement had great important effectsonprojectroutine. It is to the advantage of this study that its applications are very relevant not only in Iran’s roadwayconstructionsystem but also in other developing countries construction industries. Alia Alaryan, Emadelbeltagi, Ashraf Elshahat and Mahmoud Dawood,(2014), published a paper on change orders on construction Projects. The investigation found that the most five common causes of change orders can be listed out as: alteration of plans by client, alteration of project scope by client, difficulties on site, errors and omission in design, insufficient design and inadequate working drawing details. The most five common effects of change orderareincreasing the project’s budget, accelerate the duration of individual events, postponing in completionschedule,additionalmoney for contractor, and delaying in payment. Finally, themostsix common control actions are: inspecting and reviewing the contract documents, reviewing design before change approval, the change order must be negotiated by educated persons, the scope of change orders must be precisely done, careful checking in writing must be handed, and the respectable utensils to control the incidence of change including the areas of concern in monthly reports and meetings. Ijaola, I.A and Iyagba R.O, (2012), published paper on comparative study of causes of change orders in construction project. This study investigated the causes, effect, advantage and solutions of variation order in Nigeria and compare it with that of Oman. It was concluded that the major causesof change ordersin NigeriaandOmanarethose related to employers and the major reason is that owner request for additional works. The impact of these changes has leads to claims and disputes, time overrun and cost inflation in both Nigeria and Oman. The study also identified the contractor asthe most helping partiesof change orderin Nigeria as most respondents believed that the building executor uses suitable areas in general conditions and asks extra payment to be paid for them. The contractor was also ranked as most beneficiary of variation order in Oman. Noraziah Mohammad, Adi Irfan Che Ani , Riza Atiq O.K. Rakmat (2017), published paper on causes and effects of variation orders in the construction of terrace housing Projects. The 18 causes of changes that are identified through a literature review were used as a guide or foundation in collecting information to know the sources of changes in working in strip Selangor, found that only 10 causes of employment changes are related to changes in work for the terrace houses in the district of Selangor. From the consequences of case studies there are five main causes that led to the introduction of changes in the housing projects in the state. The causes are as follows:  Changes in the scope of the work by the client.  Exchange of construction materials by the client.  Specification changes by the client.  Changes in building design by the consultant.  Differences between the contract forms and drawings.
  • 4. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 04 Issue: 12 | Dec-2017 www.irjet.net p-ISSN: 2395-0072 © 2017, IRJET | Impact Factor value: 6.171 | ISO 9001:2008 Certified Journal | Page 1605 Among the main effects were identified and investigated in joining with variation order are as follows:  Increase project time  The increase in the project cost.  delay logistics  The impact on the quality of the project  Destruction and reconstruction M.Gokulkarthi, K.S. Gowrishankar (2015), publishedapaper on a study on impacts of change order in construction projects. Based on the field survey conducted and the consequences were achieved, the following as can be determined and outlined:  Changing the plans by the owners is the main source of change orders. This is because shortageof participation in the design growth and incapability to imagine it while not appreciating the undesirable impact on it.  Because of new materialsare becoming availablein the market or change in mind, substituting materials and/or proceduresis thesecondsourceof change orders.  Consultants are the second major contributor to changes by generating conflictingdesigndocuments or through alteration in design afterwards.  Rise in project price and duration are the main two effects being noted for change orders.  Clarity of scope of change orders ranked the first among controls adopted. Onkar U. Jadhav , Prof. Abhijit N. Bhirud (2015), published paper on an analysis of causes and effects of change orders on construction Projects. As per survey carried out get different kinds of answers and responses from the construction place .The root sources of variation order in construction projects in is client alterations, extra activities and adjustment to prior work. Another key reason is lack of building executor participation in design phase. It may indicate absence of thoughtful design at the period of actual construction. The other causes are unrealistic design periods, the absence of information between contractorand the consultants. The effects are the most important change orders increases the cost of the projects. Probably increase the period of individual activates that effect on completion timetable of the projects. Paying extra money for the contractor is the mostly effects caused on different construction sites. Ruben Ndihokubwayo, Theo Haupt (2009), published paper on Variation orders on constructionprojects:valueaddingor waste? Study found that consultants accepted time frames proposed by clients instead of proposing realistic timeframes to accomplish the design. As a result they embarked on tendering whether the design was completed or not because they knew other required changes would be permissible under the conditions of contract. It was therefore determined that the employerwasthefurthermost leading source agent of variation orders. Most variation ordersadded value to the project. However, waste wasstilla consequence of them. It was investigated that changeorders were not persuasively estimated resulting in increased construction budget. Time and cost escalation and disputes had foremost effects on project routine. There were no standard methodsfor recording and administeringvariation orders. While respondentssuggestedthatchangeordermust be reduced, they acknowledged that clients had the right to initiate changes provided they were contractually permissible and were preparedtoremuneratetheassociated costs. Aftab Hameed Memon, Ismail AbdulRahman and Mohamad Faris AbulHasan (2014), published a paper on Significant Causes and Effects of Variation Orders in Construction Projects. The investigation was attempting to list out the foremost sources and impacts of changes in construction projects. Average index analysisof the collected information through survey shows that:  In Malaysian construction projects, variations are often experienced in JKR projects.  Five most important causes are absence of apparatus, poor workmanship, design difficulty, alteration of schedule and impairment to quick decision making procedure.  Logistic delays, postponement in conclusion and increase project budget are important impact of variations confronted in construction projects. 3. CONCLUSION Based on various literature reviews the causes and effect of variation orders were categorized under employer related, consultant related, contractors related and other related grounded on type of the task. The employer related causes were change of plans, alteration of project scope, extra tasks and adjustment to previous work and financial difficulties, The consultant related causes were; insufficient workings drawing details, design inconsistencies, and disagreement among contract documents are the most predominant origins of variations, Contractors’ prevalent reasons for variations were differing site conditions, lack of trained manpower, and contractor’sdesiredprofitability.Theimpact of change order within construction project wereresultedin claims and disputes, time overrun and cost overrun, delay logistics, impact on the quality of the project, anddemolition and rebuilding. Yet, no unique method is available for minimizing variation orderseffectively.However,theireffect can be minimized with an appropriate study about the causes. The consultants’ and the contractors’ response
  • 5. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 04 Issue: 12 | Dec-2017 www.irjet.net p-ISSN: 2395-0072 © 2017, IRJET | Impact Factor value: 6.171 | ISO 9001:2008 Certified Journal | Page 1606 argued on the strategy that states adequate planning in advance is required by all involved parties before works start on site to minimize variation orders. This was because a well-planned project can eliminate change that will increase because of shortage of prior project development. REFERENCES [1] OjoAyodeji, Sunday, published a paper on Impact of Variation Orders on Public Construction Projects, Ministry of National Development,IndependenceHouse, Victoria, Volume 1, Issue September, PP 101-110, 2010. [2] R.U. Halwatura and N.P.N.P. Ranasinghe Hindawi, Causes of Variation Orders in Road Construction Projects, Publishing Corporation ISRN Construction Engineering 2013, in Sri Lanka, Volume 13, PP1-7,2013 [3] A.A. Oladapo, Durban, Assessment of the cost and time impact of variation orders on construction projects ,Journal of Engineering, Design and Technology, South Africa, Volume 5, Issue 1, PP 35-48, 2007 [4] Amiruddin Ismail, Towhid Pourrostam, Amir Soleymanzadeh and Majid Ghouyounchizad, Factors Causing Variation Orders and their Effects in Roadway Construction Projects, Research Journal of Applied Sciences, Engineering and Technology, Shoushtar, Iran, Volume 4, Issue 23, PP 4669-4972, 2012. [5] Alia Alaryan, Emadelbeltagi Ashraf Elshahat and Mahmoud Dawood Alia Alaryan et, Causes and Effectsof Change Orders on Construction Projects, Int. Journal of Engineering Research and Applications, Volume4,Issue 2, PP 2248-962201, 2014. [6] Ijaola, I.A and Iyagba R.OA, Comparative StudyofCauses of Change Orders in Public Construction Project in Nigeria and Oman, Journal of Emerging Trends in Economics and ManagementSciences(JETEMS),Volume 3, Issue 5,PP 495-501, 2012. [7] Noraziah Mohammad, Adi Irfan Che Ani , Riza Atiq O.K. Rakmat, Causes and Effects of Variation Orders in the Constructionof Terrace Housing Projects, International Journal of Supply Chain Management, Volume6,Issue,1, PP 226-223, 2017 [8] M.Gokulkarthi, K.S.Gowrishankar, A ComparativeStudy of Causes of Change Orders in Public Construction Project ,Journal of Emerging Trends in Economics and Management Sciences, Volume 3, Issue 1, PP 65-72, 2015. [9] Onkar U. Jadhav , Prof. Abhijit N. Bhirud, An Analysis Of Causes and Effects Of Change Orders On Construction, International Journal of Engineering Research and General Science,Volume 4, Issue 2, PP 2248-962201, 2015. [10] Ruben Ndihokubwayo and Theo Haupt,Variation Orders On Construction Projects: Value Adding Or Waste?, International Journal of Construction Project Management, Volume 1, PP 1-17, 2009 [11] Aftab Hameed Memon, Ismail Abdul Rahman and Mohamad Faris Abul Hasan, Published paper on Significant Causes and Effects of Variation Orders in Construction Projects, Research Journal of Applied Sciences, Engineering and Technology, Volume 7, Issue 21, PP 4494-4502, 2014.