PROJECT ON TIME STUDY TO INCREASE THE OVERALL PRODUCTIVITY
Nikhil Chatap1, Kamalesh Chavan2, Neha Barhate3, Pooja Hirudkar4, Nilesh Chavan5,
Prof. V.P.Kulkarni6
(1,2,3,4,5)Students of School of Mechanical and Civil Engineering, MIT Academy of Engineering, Alandi (D).
SPPU University
(6) Assistant Professor of School of Mechanical and Civil Engineering, MIT Academy of Engineering, Alandi (D).
SPPU University
-----------------------------------------------------------------------***--------------------------------------------------------------------
Abstract:- This report outlines the results of our observation in small scale industry. It is a small scale industry and machining
of forged and casting components is carried out there. We went through various departments, technical and non-technical,
and have collected detailed information on their respective functions and their impact on the outcomes of the company. We
have made an attempt to describe some of the things we came across during the course of time. As it is a small scale industry
so we saw a shortage of labours as well improper working conditions due to which their productivity rate was abating. There
were a lot of factors responsible for that which our team comes to know after a detail study of all the processes and time
restricted to complete those processes.
Keywords- Time study, Daily check sheet, OEE (Over Equipment Efficiency), Overall productivity
1. Introduction:
1.1 About Organization:
Organization was established in 2002, i.e. 16 years ago. It is located in Mahalunge MIDC area. It is a small scale
industry and machining of a forged and casting components is carried out there. The organization involves 30 members
including 2 supervisors, 2 quality person and a plant head. As it is small scale industry it serves many big industries by
providing finished parts. The company works in two different shift i.e. Day shift and Night Shift. The industry has 5 CNC
machines and 3 VMC machines for machining of a components. There are total 21 types of a parts are machined currently
in industry.
Some machined components are shown below
Before Machining After machining
Before Machining After machining
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 06 Issue: 04 | Apr 2019 www.irjet.net p-ISSN: 2395-0072
© 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 1619
1.2 About Project:
In Time study, our main purpose was to reduce the cycle time and hence increase the productivity. So, initially we
have noted down all the minor and major activities of the worker and the time taken by him to complete that work. For
this we have prepared a sheet as well. We have match the standard cycle time with the current cycle time. We find a time
gap and we work on improvements to improve it.
1.3 Project Details
Project title: Time study.
Project Outline:
 Analysis of the work into small, easily measurable components or elements.
 Measurement of those components
 Synthesis from measured component to arrive at the time for the complete job.
 To reduce the time, cycle to increase the productivity.
 To reduces the breakdowns, minor stoppages due to lack of basic conditions.
Project Definitions:
In order to increase the overall productivity, the losses need to minimize. Detailed study of the process by using the time
study measurement helps to analyse and identify the different types of losses. The major losses can be easily find out by
using this method, and improvements in such major losses leads to better and continuous working condition which will
help to enhance the overall productivity.
During this time study we have divided the main task into different subtasks and noted down the time required to
perform each task currently. We recorded the data for 2 weeks continuously from which we identified the major losses
and provided the improvements as mentioned below. This improvement resulted into decrease of time cycle.
1.4 Purpose:
To decrease the cycle time of the machining of the product and which will result into the overall increase the
productivity.
1.5 Significance of study:
Machining is completely machine orientated task. Equipment or any product are designed to be reliable but they face
the breakdowns due to lack of basic conditions which will decrease the overall productivity. To restore the basic condition
operator has to do daily cleaning, inspection, lubrication and refastening of the machining.
In order to reduce the time required to restore basic condition need to be minimized to increase the overall efficiency of
the equipment.
2. Implementation Details:
We have done a time study on a CNC operator who has an experienced of 10 years of working on CNC. The main
activities of the worker is to cleaning the interior, loading the job, machining a job, unloading the job and checking the final
dimensions of the job.
We initially visited the industry, and observed a loss over there. According to that, we have prepared a losses sheet and
an activity sheet. In which we have noted down the time required to complete the machining of the job and the losses. The
format of the sheet is as shown below.
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 06 Issue: 04 | Apr 2019 www.irjet.net p-ISSN: 2395-0072
© 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 1620
Chart No. 1 Daily loss report sheet
Chart No. 2 Daily Activity Report
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 06 Issue: 04 | Apr 2019 www.irjet.net p-ISSN: 2395-0072
© 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 1621
2.1 Daily Activity chart before :
Chart No. 3 Daily Activity Chart Before
2.2 Daily Activity chart after:
Chart No. 4 Daily Activity Chart After
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 06 Issue: 04 | Apr 2019 www.irjet.net p-ISSN: 2395-0072
© 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 1622
2.3 Improvements Details:
Initially the cycle time was 3.5 min as mentioned in the above chart. In order to reduce the cycle time, we have
done some improvements as mentioned below:
1) Initially the job was used to be lie on the floor for which operator has to bend down to pick up the job for which he used
to take 5 secs to do this. Now, we have arranged a table on the side from where he used to take job now within 3 sec. Here
we have save a time of 2 sec.
2) He used to take the air pipe two times for cleaning of the set up first and then for the cleaning up of job. Now, we have
change the sequence of action by which the operator has to take the air pipe once firstly he used to have a cleaning of the
job and of the set up. Initially he used to take 12 secs to do so and now it comes to the 10 sec only.
3) Initially the operator used to take 9 secs for loading of job as the job were used randomly oriented and now it took only
7 sec as to do so.
4) Initially the operator used to check all the parameters daily as mentioned above, which used to take around 13.5 min
daily, for that we have neglected some parameters to check daily as they are not necessary to check on daily basis but can
be checked on weekly basis and we reduce it to the 7.5 min. In that we also reduced the set up arrangement time as well.
Sr.No Activity Before Time After Time Time saving
1 Daily parameters checking time 13.5 min 7.5 min 6 min
2 Job Picking time 5 sec 3 sec 2 sec
3 Cleaning of job and set up 12 sec 10 sec 2 sec
4 Loading time for job 9 sec 7 sec 2 sec
Table No. 1 Cycle time improved chart
3. Result and Calculations:
Sr. No Activity Before After
1 Operator duty hours 12 12
2 Daily Target 200 jobs 200 jobs
3 Daily rework time 16 min 16 min
4 Daily Inspection time 13.5 min 7.5 min
5 Weekly Inspection Time 0 7.5 min
6 Non- productive time 65 min 65 min
7 Cycle time for 1 job 210 sec 204 sec
8 Total productive time 625.5 min 631.5 min
9 No. of jobs completed daily 178 jobs 192 jobs
10 Efficiency of operator 89 % 96%
Table No. 2 Result Table
3.1 Calculation:
Increase in job machined per shift = 185-178 = 7
Increase in productivity percentage for one shift for one CNC m/c = (185-178)/178 = 3.9 %
International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056
Volume: 06 Issue: 04 | Apr 2019 www.irjet.net p-ISSN: 2395-0072
© 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 1623
Labour cost = 51.28 Rs / Hr
Total cost saving for 1 shift = [7/ (3.4*60)] * 51.28 = Rs. 20.34
Total saving per day for 1 m/c = 2*20.34 = Rs. 40.682
Total saving in plant for 1 day = 5 * 40.682 = Rs. 203.4
Total saving per month in plant = 26 * 192.3 = Rs. 5288.667
Total saving per year in plant = 12 * 5288.667 = Rs. 63464.128
Conclusion:
It is found that time study is very effective in repetitive job analysis. A small improvement in the cycle processing can
save a small time for one small process, as it is a repetitive process the overall impact of the small time improvement is
very high and it increases the overall productivity up to large extent. Time study has its several advantages regarding the
development of the culture of an organisation. The culture of the continuous improvement gets developed in the
organization. Selection of the proper method of doing time study is very important and one should give a complete thought
process before doing the time study. The operator selected for the time study should have experienced of doing the same
job and should be cooperative towards the time study person.
The time study gives the information about the time loss during various operation and the particular area which plays
major roles in the losses can be targeted for the improvement. Thus this is how the total productivity of the organization
can be improved by conducting the time study at various stages.
References:
1. Barnes, R. (1980). Motion and Time Study Design and Measurement of Work (7th ed.). United States: John Wiley & Sons.
Inc.
2. Finkler, Steven A., A Comparison of work-sampling and time-and-motion techniques for studies in health services
research, Health Service Research, Chicago. Dec 1993. Vol. 28, Issue 5.
3. Marvin E. Mundel and David L. Danner (1994). Motion and Time Study – Improving Productivity, Seventh Edition.
4.http://eprints.utem.edu.my/11217/1/Productivity_Improvement_Through_Motion_And_Time_Study.pdf
5. Niebel, B. W. (1988), Motion and Time Study, Richard D. Irwin, Inc., Homewood, III.
6.http://www.arpnjournals.org/jeas/research_papers/rp_2016/jeas_0116_3387.pdf
7.http://ijaresm.net/Pepar/VOLUME_1/ISSUE_3/7.pdf
8.https://www.ims-productivity.com/page.cfm/content/Time-Study/

More Related Content

What's hot

IRJET - Productivity Improvement by Time Study and Motion Study
IRJET - Productivity Improvement by Time Study and Motion StudyIRJET - Productivity Improvement by Time Study and Motion Study
IRJET - Productivity Improvement by Time Study and Motion StudyIRJET Journal
 
PRODUCTIVITY IMPROVEMENT THROUGH LEAN TOOLS ON ENGINE COOLING ASSEMBLY
PRODUCTIVITY IMPROVEMENT THROUGH LEAN TOOLS ON  ENGINE COOLING ASSEMBLYPRODUCTIVITY IMPROVEMENT THROUGH LEAN TOOLS ON  ENGINE COOLING ASSEMBLY
PRODUCTIVITY IMPROVEMENT THROUGH LEAN TOOLS ON ENGINE COOLING ASSEMBLYDIPRANJAN GUPTA
 
IRJET- A Case Study Approach of Quality Tools in Manufacturing Industry
IRJET- A Case Study Approach of Quality Tools in Manufacturing IndustryIRJET- A Case Study Approach of Quality Tools in Manufacturing Industry
IRJET- A Case Study Approach of Quality Tools in Manufacturing IndustryIRJET Journal
 
Designing Facility Layout and Effective Material Handling for a Ceramic Insul...
Designing Facility Layout and Effective Material Handling for a Ceramic Insul...Designing Facility Layout and Effective Material Handling for a Ceramic Insul...
Designing Facility Layout and Effective Material Handling for a Ceramic Insul...IRJET Journal
 
IRJET - Invistigation and Implement of Six Sigma and Reduce Labour Cost a...
IRJET -  	  Invistigation and Implement of Six Sigma and Reduce Labour Cost a...IRJET -  	  Invistigation and Implement of Six Sigma and Reduce Labour Cost a...
IRJET - Invistigation and Implement of Six Sigma and Reduce Labour Cost a...IRJET Journal
 
INDUSTRIAL ENGINEERING DESIGN PROJECT
INDUSTRIAL ENGINEERING DESIGN PROJECTINDUSTRIAL ENGINEERING DESIGN PROJECT
INDUSTRIAL ENGINEERING DESIGN PROJECTAmir Mohammad Redzuan
 
1.1 Work study and method study -Industrial Engineering Basics
1.1 Work study and method study -Industrial Engineering Basics1.1 Work study and method study -Industrial Engineering Basics
1.1 Work study and method study -Industrial Engineering BasicsDr. Surya Prakash
 
Design of facilty Layout of a LED bulb Production sysem
Design of facilty Layout of a LED bulb Production sysemDesign of facilty Layout of a LED bulb Production sysem
Design of facilty Layout of a LED bulb Production sysemMaheer Sohbat
 
Production & materials management
Production & materials managementProduction & materials management
Production & materials managementVaibhav Shah
 
Implementation of Single Minute Exchange of Die in Motor Manufacturing Unit
Implementation of Single Minute Exchange of Die in Motor Manufacturing UnitImplementation of Single Minute Exchange of Die in Motor Manufacturing Unit
Implementation of Single Minute Exchange of Die in Motor Manufacturing UnitIRJET Journal
 
IRJET- Efficiency Enhancement by Reducing Production and Machining Time
IRJET-  	  Efficiency Enhancement by Reducing Production and Machining TimeIRJET-  	  Efficiency Enhancement by Reducing Production and Machining Time
IRJET- Efficiency Enhancement by Reducing Production and Machining TimeIRJET Journal
 
Production and material management
Production and material managementProduction and material management
Production and material managementsksbatish
 
Method Study
Method StudyMethod Study
Method Studyajithsrc
 
IRJET- Maintenance Management of Construction Equipment on Construction P...
IRJET-  	  Maintenance Management of Construction Equipment on Construction P...IRJET-  	  Maintenance Management of Construction Equipment on Construction P...
IRJET- Maintenance Management of Construction Equipment on Construction P...IRJET Journal
 
Modul 1 process planning and standard time calculation
Modul 1 process planning and standard time calculationModul 1 process planning and standard time calculation
Modul 1 process planning and standard time calculationAmalia Syafitri
 
k10798 aaftab alam opc me 6th sem
k10798 aaftab alam opc me 6th semk10798 aaftab alam opc me 6th sem
k10798 aaftab alam opc me 6th semGuddu Ali
 

What's hot (20)

IRJET - Productivity Improvement by Time Study and Motion Study
IRJET - Productivity Improvement by Time Study and Motion StudyIRJET - Productivity Improvement by Time Study and Motion Study
IRJET - Productivity Improvement by Time Study and Motion Study
 
PRODUCTIVITY IMPROVEMENT THROUGH LEAN TOOLS ON ENGINE COOLING ASSEMBLY
PRODUCTIVITY IMPROVEMENT THROUGH LEAN TOOLS ON  ENGINE COOLING ASSEMBLYPRODUCTIVITY IMPROVEMENT THROUGH LEAN TOOLS ON  ENGINE COOLING ASSEMBLY
PRODUCTIVITY IMPROVEMENT THROUGH LEAN TOOLS ON ENGINE COOLING ASSEMBLY
 
IRJET- A Case Study Approach of Quality Tools in Manufacturing Industry
IRJET- A Case Study Approach of Quality Tools in Manufacturing IndustryIRJET- A Case Study Approach of Quality Tools in Manufacturing Industry
IRJET- A Case Study Approach of Quality Tools in Manufacturing Industry
 
Designing Facility Layout and Effective Material Handling for a Ceramic Insul...
Designing Facility Layout and Effective Material Handling for a Ceramic Insul...Designing Facility Layout and Effective Material Handling for a Ceramic Insul...
Designing Facility Layout and Effective Material Handling for a Ceramic Insul...
 
Assistant Manager - Mechanical
Assistant Manager - MechanicalAssistant Manager - Mechanical
Assistant Manager - Mechanical
 
Koti (assistant manager mech)
Koti (assistant manager mech)Koti (assistant manager mech)
Koti (assistant manager mech)
 
IRJET - Invistigation and Implement of Six Sigma and Reduce Labour Cost a...
IRJET -  	  Invistigation and Implement of Six Sigma and Reduce Labour Cost a...IRJET -  	  Invistigation and Implement of Six Sigma and Reduce Labour Cost a...
IRJET - Invistigation and Implement of Six Sigma and Reduce Labour Cost a...
 
INDUSTRIAL ENGINEERING DESIGN PROJECT
INDUSTRIAL ENGINEERING DESIGN PROJECTINDUSTRIAL ENGINEERING DESIGN PROJECT
INDUSTRIAL ENGINEERING DESIGN PROJECT
 
1.1 Work study and method study -Industrial Engineering Basics
1.1 Work study and method study -Industrial Engineering Basics1.1 Work study and method study -Industrial Engineering Basics
1.1 Work study and method study -Industrial Engineering Basics
 
Design of facilty Layout of a LED bulb Production sysem
Design of facilty Layout of a LED bulb Production sysemDesign of facilty Layout of a LED bulb Production sysem
Design of facilty Layout of a LED bulb Production sysem
 
Production & materials management
Production & materials managementProduction & materials management
Production & materials management
 
Implementation of Single Minute Exchange of Die in Motor Manufacturing Unit
Implementation of Single Minute Exchange of Die in Motor Manufacturing UnitImplementation of Single Minute Exchange of Die in Motor Manufacturing Unit
Implementation of Single Minute Exchange of Die in Motor Manufacturing Unit
 
Work measurement
Work measurementWork measurement
Work measurement
 
IRJET- Efficiency Enhancement by Reducing Production and Machining Time
IRJET-  	  Efficiency Enhancement by Reducing Production and Machining TimeIRJET-  	  Efficiency Enhancement by Reducing Production and Machining Time
IRJET- Efficiency Enhancement by Reducing Production and Machining Time
 
Production and material management
Production and material managementProduction and material management
Production and material management
 
Method Study
Method StudyMethod Study
Method Study
 
IRJET- Maintenance Management of Construction Equipment on Construction P...
IRJET-  	  Maintenance Management of Construction Equipment on Construction P...IRJET-  	  Maintenance Management of Construction Equipment on Construction P...
IRJET- Maintenance Management of Construction Equipment on Construction P...
 
Modul 1 process planning and standard time calculation
Modul 1 process planning and standard time calculationModul 1 process planning and standard time calculation
Modul 1 process planning and standard time calculation
 
k10798 aaftab alam opc me 6th sem
k10798 aaftab alam opc me 6th semk10798 aaftab alam opc me 6th sem
k10798 aaftab alam opc me 6th sem
 
Resume
ResumeResume
Resume
 

Similar to IRJET- Project on Time Study to Increase the Overall Productivity

IRJET- Project on Time Study to Increase the Overall Productivity
IRJET- Project on Time Study to Increase the Overall ProductivityIRJET- Project on Time Study to Increase the Overall Productivity
IRJET- Project on Time Study to Increase the Overall ProductivityIRJET Journal
 
IRJET- Productivity Improvement in Manufacturing Industry using Lean Tools
IRJET- Productivity Improvement in Manufacturing Industry using Lean ToolsIRJET- Productivity Improvement in Manufacturing Industry using Lean Tools
IRJET- Productivity Improvement in Manufacturing Industry using Lean ToolsIRJET Journal
 
Sheet Metal Assembly Process Optimization Using Lean Manufacturing Tool
Sheet Metal Assembly Process Optimization Using Lean Manufacturing ToolSheet Metal Assembly Process Optimization Using Lean Manufacturing Tool
Sheet Metal Assembly Process Optimization Using Lean Manufacturing ToolIRJET Journal
 
‘5S’ Implementation in a Fasteners Manufacturing Company
‘5S’ Implementation in a Fasteners Manufacturing Company‘5S’ Implementation in a Fasteners Manufacturing Company
‘5S’ Implementation in a Fasteners Manufacturing CompanyIRJET Journal
 
Success story of Carrier Engineers, an SME Cluster Member of CII
Success story of Carrier Engineers, an SME Cluster Member of CIISuccess story of Carrier Engineers, an SME Cluster Member of CII
Success story of Carrier Engineers, an SME Cluster Member of CIIConfederation of Indian Industry
 
Project Report on Textile Industrial Engineering
Project Report on Textile Industrial EngineeringProject Report on Textile Industrial Engineering
Project Report on Textile Industrial EngineeringAmanuzzaman Aman
 
A case study on productivity improvement of wearing insert and cutting ring
A case study on productivity improvement of wearing insert and cutting ringA case study on productivity improvement of wearing insert and cutting ring
A case study on productivity improvement of wearing insert and cutting ringIJECSJournal
 
IRJET- A Case Study for Overall Equipment Effectiveness Improved in Manufactu...
IRJET- A Case Study for Overall Equipment Effectiveness Improved in Manufactu...IRJET- A Case Study for Overall Equipment Effectiveness Improved in Manufactu...
IRJET- A Case Study for Overall Equipment Effectiveness Improved in Manufactu...IRJET Journal
 
Productivity Enhancement Using Method Study
Productivity Enhancement Using Method StudyProductivity Enhancement Using Method Study
Productivity Enhancement Using Method StudyIRJET Journal
 
IRJET- Productivity Improvement by Time Study Analysis Moderate Scale Ind...
IRJET-  	  Productivity Improvement by Time Study Analysis Moderate Scale Ind...IRJET-  	  Productivity Improvement by Time Study Analysis Moderate Scale Ind...
IRJET- Productivity Improvement by Time Study Analysis Moderate Scale Ind...IRJET Journal
 
IRJET- Value Stream Mapping (VSM) – A Case Study in Manufacturing Facility
IRJET- Value Stream Mapping (VSM) – A Case Study in Manufacturing FacilityIRJET- Value Stream Mapping (VSM) – A Case Study in Manufacturing Facility
IRJET- Value Stream Mapping (VSM) – A Case Study in Manufacturing FacilityIRJET Journal
 
IRJET- Last Planner System
IRJET- Last Planner SystemIRJET- Last Planner System
IRJET- Last Planner SystemIRJET Journal
 
IRJET- Production Line Optimization using Lean Tools: A Case Study of Automot...
IRJET- Production Line Optimization using Lean Tools: A Case Study of Automot...IRJET- Production Line Optimization using Lean Tools: A Case Study of Automot...
IRJET- Production Line Optimization using Lean Tools: A Case Study of Automot...IRJET Journal
 
Development of fixture_to_reduce_the_cycle_time_of_c_8_griding_machine
Development of fixture_to_reduce_the_cycle_time_of_c_8_griding_machineDevelopment of fixture_to_reduce_the_cycle_time_of_c_8_griding_machine
Development of fixture_to_reduce_the_cycle_time_of_c_8_griding_machineLaukik Raut
 
International Journal of Engineering Research and Development
International Journal of Engineering Research and DevelopmentInternational Journal of Engineering Research and Development
International Journal of Engineering Research and DevelopmentIJERD Editor
 
IMPLEMENTATION OF LEAN TECHNIQUES IN INDIAN SCEANIRO AND TESTING ITS FITNESS
IMPLEMENTATION OF LEAN TECHNIQUES IN INDIAN SCEANIRO AND TESTING ITS FITNESSIMPLEMENTATION OF LEAN TECHNIQUES IN INDIAN SCEANIRO AND TESTING ITS FITNESS
IMPLEMENTATION OF LEAN TECHNIQUES IN INDIAN SCEANIRO AND TESTING ITS FITNESSIRJET Journal
 
IRJET- Productivity Improvement Kaizen of XC-60 Housing
IRJET- Productivity Improvement Kaizen of XC-60 HousingIRJET- Productivity Improvement Kaizen of XC-60 Housing
IRJET- Productivity Improvement Kaizen of XC-60 HousingIRJET Journal
 
The Impact of Lean Production on the Cycle Time: A Case Study of a Welding As...
The Impact of Lean Production on the Cycle Time: A Case Study of a Welding As...The Impact of Lean Production on the Cycle Time: A Case Study of a Welding As...
The Impact of Lean Production on the Cycle Time: A Case Study of a Welding As...ijsrd.com
 
Application of Industrial Engineering to increase the productivity of an E-Ri...
Application of Industrial Engineering to increase the productivity of an E-Ri...Application of Industrial Engineering to increase the productivity of an E-Ri...
Application of Industrial Engineering to increase the productivity of an E-Ri...ijtsrd
 

Similar to IRJET- Project on Time Study to Increase the Overall Productivity (20)

IRJET- Project on Time Study to Increase the Overall Productivity
IRJET- Project on Time Study to Increase the Overall ProductivityIRJET- Project on Time Study to Increase the Overall Productivity
IRJET- Project on Time Study to Increase the Overall Productivity
 
IRJET- Productivity Improvement in Manufacturing Industry using Lean Tools
IRJET- Productivity Improvement in Manufacturing Industry using Lean ToolsIRJET- Productivity Improvement in Manufacturing Industry using Lean Tools
IRJET- Productivity Improvement in Manufacturing Industry using Lean Tools
 
Sheet Metal Assembly Process Optimization Using Lean Manufacturing Tool
Sheet Metal Assembly Process Optimization Using Lean Manufacturing ToolSheet Metal Assembly Process Optimization Using Lean Manufacturing Tool
Sheet Metal Assembly Process Optimization Using Lean Manufacturing Tool
 
‘5S’ Implementation in a Fasteners Manufacturing Company
‘5S’ Implementation in a Fasteners Manufacturing Company‘5S’ Implementation in a Fasteners Manufacturing Company
‘5S’ Implementation in a Fasteners Manufacturing Company
 
Success story of Carrier Engineers, an SME Cluster Member of CII
Success story of Carrier Engineers, an SME Cluster Member of CIISuccess story of Carrier Engineers, an SME Cluster Member of CII
Success story of Carrier Engineers, an SME Cluster Member of CII
 
Project Report on Textile Industrial Engineering
Project Report on Textile Industrial EngineeringProject Report on Textile Industrial Engineering
Project Report on Textile Industrial Engineering
 
A case study on productivity improvement of wearing insert and cutting ring
A case study on productivity improvement of wearing insert and cutting ringA case study on productivity improvement of wearing insert and cutting ring
A case study on productivity improvement of wearing insert and cutting ring
 
IRJET- A Case Study for Overall Equipment Effectiveness Improved in Manufactu...
IRJET- A Case Study for Overall Equipment Effectiveness Improved in Manufactu...IRJET- A Case Study for Overall Equipment Effectiveness Improved in Manufactu...
IRJET- A Case Study for Overall Equipment Effectiveness Improved in Manufactu...
 
Productivity Enhancement Using Method Study
Productivity Enhancement Using Method StudyProductivity Enhancement Using Method Study
Productivity Enhancement Using Method Study
 
IRJET- Productivity Improvement by Time Study Analysis Moderate Scale Ind...
IRJET-  	  Productivity Improvement by Time Study Analysis Moderate Scale Ind...IRJET-  	  Productivity Improvement by Time Study Analysis Moderate Scale Ind...
IRJET- Productivity Improvement by Time Study Analysis Moderate Scale Ind...
 
LEAN STANDARDIZED WORK TOOL
LEAN STANDARDIZED WORK TOOLLEAN STANDARDIZED WORK TOOL
LEAN STANDARDIZED WORK TOOL
 
IRJET- Value Stream Mapping (VSM) – A Case Study in Manufacturing Facility
IRJET- Value Stream Mapping (VSM) – A Case Study in Manufacturing FacilityIRJET- Value Stream Mapping (VSM) – A Case Study in Manufacturing Facility
IRJET- Value Stream Mapping (VSM) – A Case Study in Manufacturing Facility
 
IRJET- Last Planner System
IRJET- Last Planner SystemIRJET- Last Planner System
IRJET- Last Planner System
 
IRJET- Production Line Optimization using Lean Tools: A Case Study of Automot...
IRJET- Production Line Optimization using Lean Tools: A Case Study of Automot...IRJET- Production Line Optimization using Lean Tools: A Case Study of Automot...
IRJET- Production Line Optimization using Lean Tools: A Case Study of Automot...
 
Development of fixture_to_reduce_the_cycle_time_of_c_8_griding_machine
Development of fixture_to_reduce_the_cycle_time_of_c_8_griding_machineDevelopment of fixture_to_reduce_the_cycle_time_of_c_8_griding_machine
Development of fixture_to_reduce_the_cycle_time_of_c_8_griding_machine
 
International Journal of Engineering Research and Development
International Journal of Engineering Research and DevelopmentInternational Journal of Engineering Research and Development
International Journal of Engineering Research and Development
 
IMPLEMENTATION OF LEAN TECHNIQUES IN INDIAN SCEANIRO AND TESTING ITS FITNESS
IMPLEMENTATION OF LEAN TECHNIQUES IN INDIAN SCEANIRO AND TESTING ITS FITNESSIMPLEMENTATION OF LEAN TECHNIQUES IN INDIAN SCEANIRO AND TESTING ITS FITNESS
IMPLEMENTATION OF LEAN TECHNIQUES IN INDIAN SCEANIRO AND TESTING ITS FITNESS
 
IRJET- Productivity Improvement Kaizen of XC-60 Housing
IRJET- Productivity Improvement Kaizen of XC-60 HousingIRJET- Productivity Improvement Kaizen of XC-60 Housing
IRJET- Productivity Improvement Kaizen of XC-60 Housing
 
The Impact of Lean Production on the Cycle Time: A Case Study of a Welding As...
The Impact of Lean Production on the Cycle Time: A Case Study of a Welding As...The Impact of Lean Production on the Cycle Time: A Case Study of a Welding As...
The Impact of Lean Production on the Cycle Time: A Case Study of a Welding As...
 
Application of Industrial Engineering to increase the productivity of an E-Ri...
Application of Industrial Engineering to increase the productivity of an E-Ri...Application of Industrial Engineering to increase the productivity of an E-Ri...
Application of Industrial Engineering to increase the productivity of an E-Ri...
 

More from IRJET Journal

TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...IRJET Journal
 
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURESTUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTUREIRJET Journal
 
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...IRJET Journal
 
Effect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsEffect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsIRJET Journal
 
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...IRJET Journal
 
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...IRJET Journal
 
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...IRJET Journal
 
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...IRJET Journal
 
A REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASA REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASIRJET Journal
 
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...IRJET Journal
 
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProP.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProIRJET Journal
 
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...IRJET Journal
 
Survey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemSurvey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemIRJET Journal
 
Review on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesReview on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesIRJET Journal
 
React based fullstack edtech web application
React based fullstack edtech web applicationReact based fullstack edtech web application
React based fullstack edtech web applicationIRJET Journal
 
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...IRJET Journal
 
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.IRJET Journal
 
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...IRJET Journal
 
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignMultistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignIRJET Journal
 
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...IRJET Journal
 

More from IRJET Journal (20)

TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
TUNNELING IN HIMALAYAS WITH NATM METHOD: A SPECIAL REFERENCES TO SUNGAL TUNNE...
 
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURESTUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
STUDY THE EFFECT OF RESPONSE REDUCTION FACTOR ON RC FRAMED STRUCTURE
 
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
A COMPARATIVE ANALYSIS OF RCC ELEMENT OF SLAB WITH STARK STEEL (HYSD STEEL) A...
 
Effect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil CharacteristicsEffect of Camber and Angles of Attack on Airfoil Characteristics
Effect of Camber and Angles of Attack on Airfoil Characteristics
 
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
A Review on the Progress and Challenges of Aluminum-Based Metal Matrix Compos...
 
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
Dynamic Urban Transit Optimization: A Graph Neural Network Approach for Real-...
 
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
Structural Analysis and Design of Multi-Storey Symmetric and Asymmetric Shape...
 
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
A Review of “Seismic Response of RC Structures Having Plan and Vertical Irreg...
 
A REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADASA REVIEW ON MACHINE LEARNING IN ADAS
A REVIEW ON MACHINE LEARNING IN ADAS
 
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
Long Term Trend Analysis of Precipitation and Temperature for Asosa district,...
 
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD ProP.E.B. Framed Structure Design and Analysis Using STAAD Pro
P.E.B. Framed Structure Design and Analysis Using STAAD Pro
 
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
A Review on Innovative Fiber Integration for Enhanced Reinforcement of Concre...
 
Survey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare SystemSurvey Paper on Cloud-Based Secured Healthcare System
Survey Paper on Cloud-Based Secured Healthcare System
 
Review on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridgesReview on studies and research on widening of existing concrete bridges
Review on studies and research on widening of existing concrete bridges
 
React based fullstack edtech web application
React based fullstack edtech web applicationReact based fullstack edtech web application
React based fullstack edtech web application
 
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
A Comprehensive Review of Integrating IoT and Blockchain Technologies in the ...
 
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
A REVIEW ON THE PERFORMANCE OF COCONUT FIBRE REINFORCED CONCRETE.
 
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
Optimizing Business Management Process Workflows: The Dynamic Influence of Mi...
 
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic DesignMultistoried and Multi Bay Steel Building Frame by using Seismic Design
Multistoried and Multi Bay Steel Building Frame by using Seismic Design
 
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
Cost Optimization of Construction Using Plastic Waste as a Sustainable Constr...
 

Recently uploaded

HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSRajkumarAkumalla
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSISrknatarajan
 
High Profile Call Girls Dahisar Arpita 9907093804 Independent Escort Service ...
High Profile Call Girls Dahisar Arpita 9907093804 Independent Escort Service ...High Profile Call Girls Dahisar Arpita 9907093804 Independent Escort Service ...
High Profile Call Girls Dahisar Arpita 9907093804 Independent Escort Service ...Call girls in Ahmedabad High profile
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).pptssuser5c9d4b1
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSSIVASHANKAR N
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...Call Girls in Nagpur High Profile
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...ranjana rawat
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingrknatarajan
 
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...ranjana rawat
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...ranjana rawat
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Christo Ananth
 

Recently uploaded (20)

HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICSHARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
HARDNESS, FRACTURE TOUGHNESS AND STRENGTH OF CERAMICS
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSIS
 
High Profile Call Girls Dahisar Arpita 9907093804 Independent Escort Service ...
High Profile Call Girls Dahisar Arpita 9907093804 Independent Escort Service ...High Profile Call Girls Dahisar Arpita 9907093804 Independent Escort Service ...
High Profile Call Girls Dahisar Arpita 9907093804 Independent Escort Service ...
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
247267395-1-Symmetric-and-distributed-shared-memory-architectures-ppt (1).ppt
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
 
Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and RoutesRoadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service NashikCall Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
Call Girls Service Nashik Vaishnavi 7001305949 Independent Escort Service Nashik
 
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and workingUNIT-V FMM.HYDRAULIC TURBINE - Construction and working
UNIT-V FMM.HYDRAULIC TURBINE - Construction and working
 
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...
(TARA) Talegaon Dabhade Call Girls Just Call 7001035870 [ Cash on Delivery ] ...
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
 

IRJET- Project on Time Study to Increase the Overall Productivity

  • 1. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 06 Issue: 04 | Apr 2019 www.irjet.net p-ISSN: 2395-0072 © 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 1618 PROJECT ON TIME STUDY TO INCREASE THE OVERALL PRODUCTIVITY Nikhil Chatap1, Kamalesh Chavan2, Neha Barhate3, Pooja Hirudkar4, Nilesh Chavan5, Prof. V.P.Kulkarni6 (1,2,3,4,5)Students of School of Mechanical and Civil Engineering, MIT Academy of Engineering, Alandi (D). SPPU University (6) Assistant Professor of School of Mechanical and Civil Engineering, MIT Academy of Engineering, Alandi (D). SPPU University -----------------------------------------------------------------------***-------------------------------------------------------------------- Abstract:- This report outlines the results of our observation in small scale industry. It is a small scale industry and machining of forged and casting components is carried out there. We went through various departments, technical and non-technical, and have collected detailed information on their respective functions and their impact on the outcomes of the company. We have made an attempt to describe some of the things we came across during the course of time. As it is a small scale industry so we saw a shortage of labours as well improper working conditions due to which their productivity rate was abating. There were a lot of factors responsible for that which our team comes to know after a detail study of all the processes and time restricted to complete those processes. Keywords- Time study, Daily check sheet, OEE (Over Equipment Efficiency), Overall productivity 1. Introduction: 1.1 About Organization: Organization was established in 2002, i.e. 16 years ago. It is located in Mahalunge MIDC area. It is a small scale industry and machining of a forged and casting components is carried out there. The organization involves 30 members including 2 supervisors, 2 quality person and a plant head. As it is small scale industry it serves many big industries by providing finished parts. The company works in two different shift i.e. Day shift and Night Shift. The industry has 5 CNC machines and 3 VMC machines for machining of a components. There are total 21 types of a parts are machined currently in industry. Some machined components are shown below Before Machining After machining Before Machining After machining
  • 2. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 06 Issue: 04 | Apr 2019 www.irjet.net p-ISSN: 2395-0072 © 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 1619 1.2 About Project: In Time study, our main purpose was to reduce the cycle time and hence increase the productivity. So, initially we have noted down all the minor and major activities of the worker and the time taken by him to complete that work. For this we have prepared a sheet as well. We have match the standard cycle time with the current cycle time. We find a time gap and we work on improvements to improve it. 1.3 Project Details Project title: Time study. Project Outline:  Analysis of the work into small, easily measurable components or elements.  Measurement of those components  Synthesis from measured component to arrive at the time for the complete job.  To reduce the time, cycle to increase the productivity.  To reduces the breakdowns, minor stoppages due to lack of basic conditions. Project Definitions: In order to increase the overall productivity, the losses need to minimize. Detailed study of the process by using the time study measurement helps to analyse and identify the different types of losses. The major losses can be easily find out by using this method, and improvements in such major losses leads to better and continuous working condition which will help to enhance the overall productivity. During this time study we have divided the main task into different subtasks and noted down the time required to perform each task currently. We recorded the data for 2 weeks continuously from which we identified the major losses and provided the improvements as mentioned below. This improvement resulted into decrease of time cycle. 1.4 Purpose: To decrease the cycle time of the machining of the product and which will result into the overall increase the productivity. 1.5 Significance of study: Machining is completely machine orientated task. Equipment or any product are designed to be reliable but they face the breakdowns due to lack of basic conditions which will decrease the overall productivity. To restore the basic condition operator has to do daily cleaning, inspection, lubrication and refastening of the machining. In order to reduce the time required to restore basic condition need to be minimized to increase the overall efficiency of the equipment. 2. Implementation Details: We have done a time study on a CNC operator who has an experienced of 10 years of working on CNC. The main activities of the worker is to cleaning the interior, loading the job, machining a job, unloading the job and checking the final dimensions of the job. We initially visited the industry, and observed a loss over there. According to that, we have prepared a losses sheet and an activity sheet. In which we have noted down the time required to complete the machining of the job and the losses. The format of the sheet is as shown below.
  • 3. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 06 Issue: 04 | Apr 2019 www.irjet.net p-ISSN: 2395-0072 © 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 1620 Chart No. 1 Daily loss report sheet Chart No. 2 Daily Activity Report
  • 4. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 06 Issue: 04 | Apr 2019 www.irjet.net p-ISSN: 2395-0072 © 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 1621 2.1 Daily Activity chart before : Chart No. 3 Daily Activity Chart Before 2.2 Daily Activity chart after: Chart No. 4 Daily Activity Chart After
  • 5. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 06 Issue: 04 | Apr 2019 www.irjet.net p-ISSN: 2395-0072 © 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 1622 2.3 Improvements Details: Initially the cycle time was 3.5 min as mentioned in the above chart. In order to reduce the cycle time, we have done some improvements as mentioned below: 1) Initially the job was used to be lie on the floor for which operator has to bend down to pick up the job for which he used to take 5 secs to do this. Now, we have arranged a table on the side from where he used to take job now within 3 sec. Here we have save a time of 2 sec. 2) He used to take the air pipe two times for cleaning of the set up first and then for the cleaning up of job. Now, we have change the sequence of action by which the operator has to take the air pipe once firstly he used to have a cleaning of the job and of the set up. Initially he used to take 12 secs to do so and now it comes to the 10 sec only. 3) Initially the operator used to take 9 secs for loading of job as the job were used randomly oriented and now it took only 7 sec as to do so. 4) Initially the operator used to check all the parameters daily as mentioned above, which used to take around 13.5 min daily, for that we have neglected some parameters to check daily as they are not necessary to check on daily basis but can be checked on weekly basis and we reduce it to the 7.5 min. In that we also reduced the set up arrangement time as well. Sr.No Activity Before Time After Time Time saving 1 Daily parameters checking time 13.5 min 7.5 min 6 min 2 Job Picking time 5 sec 3 sec 2 sec 3 Cleaning of job and set up 12 sec 10 sec 2 sec 4 Loading time for job 9 sec 7 sec 2 sec Table No. 1 Cycle time improved chart 3. Result and Calculations: Sr. No Activity Before After 1 Operator duty hours 12 12 2 Daily Target 200 jobs 200 jobs 3 Daily rework time 16 min 16 min 4 Daily Inspection time 13.5 min 7.5 min 5 Weekly Inspection Time 0 7.5 min 6 Non- productive time 65 min 65 min 7 Cycle time for 1 job 210 sec 204 sec 8 Total productive time 625.5 min 631.5 min 9 No. of jobs completed daily 178 jobs 192 jobs 10 Efficiency of operator 89 % 96% Table No. 2 Result Table 3.1 Calculation: Increase in job machined per shift = 185-178 = 7 Increase in productivity percentage for one shift for one CNC m/c = (185-178)/178 = 3.9 %
  • 6. International Research Journal of Engineering and Technology (IRJET) e-ISSN: 2395-0056 Volume: 06 Issue: 04 | Apr 2019 www.irjet.net p-ISSN: 2395-0072 © 2019, IRJET | Impact Factor value: 7.211 | ISO 9001:2008 Certified Journal | Page 1623 Labour cost = 51.28 Rs / Hr Total cost saving for 1 shift = [7/ (3.4*60)] * 51.28 = Rs. 20.34 Total saving per day for 1 m/c = 2*20.34 = Rs. 40.682 Total saving in plant for 1 day = 5 * 40.682 = Rs. 203.4 Total saving per month in plant = 26 * 192.3 = Rs. 5288.667 Total saving per year in plant = 12 * 5288.667 = Rs. 63464.128 Conclusion: It is found that time study is very effective in repetitive job analysis. A small improvement in the cycle processing can save a small time for one small process, as it is a repetitive process the overall impact of the small time improvement is very high and it increases the overall productivity up to large extent. Time study has its several advantages regarding the development of the culture of an organisation. The culture of the continuous improvement gets developed in the organization. Selection of the proper method of doing time study is very important and one should give a complete thought process before doing the time study. The operator selected for the time study should have experienced of doing the same job and should be cooperative towards the time study person. The time study gives the information about the time loss during various operation and the particular area which plays major roles in the losses can be targeted for the improvement. Thus this is how the total productivity of the organization can be improved by conducting the time study at various stages. References: 1. Barnes, R. (1980). Motion and Time Study Design and Measurement of Work (7th ed.). United States: John Wiley & Sons. Inc. 2. Finkler, Steven A., A Comparison of work-sampling and time-and-motion techniques for studies in health services research, Health Service Research, Chicago. Dec 1993. Vol. 28, Issue 5. 3. Marvin E. Mundel and David L. Danner (1994). Motion and Time Study – Improving Productivity, Seventh Edition. 4.http://eprints.utem.edu.my/11217/1/Productivity_Improvement_Through_Motion_And_Time_Study.pdf 5. Niebel, B. W. (1988), Motion and Time Study, Richard D. Irwin, Inc., Homewood, III. 6.http://www.arpnjournals.org/jeas/research_papers/rp_2016/jeas_0116_3387.pdf 7.http://ijaresm.net/Pepar/VOLUME_1/ISSUE_3/7.pdf 8.https://www.ims-productivity.com/page.cfm/content/Time-Study/