SlideShare a Scribd company logo
1 of 30
Download to read offline
EXTENSION OF
KUALA LUMPUR
TWIN TOWER
PROCUREMENT
PROCUREMENT METHOD
Client’s requirements:
● Have full control of the design and able to introduce
changes from beginning till the completion
● Not interested in the daily dealing with too many
parties except the few key members of the project
● Complete project on time
● Minimum variation to the contract price during the
construction
RECOMMENDATION:
TRADITIONAL
PROCUREMENT
METHOD
TRADITIONAL PROCUREMENT METHOD
How does it work?
● Design phase to Construction phase
● Consultant teams are appointed at the
early stage to carry out the design process.
● Work will then tender out to the suitable
contractor only after design process is
completed.
● Client can involved in the design stage to
ensure it is within their requirements.
TRADITIONAL PROCUREMENT METHOD
TRADITIONAL PROCUREMENT METHOD
● TIME
1. Priority of this project fall into
quality and cost due to time is not
constraints.
2. Provides medium time risk to the
client because it requires longer
time frame for the Pre and Post
Tender Stage.
Duration of the project is 5
years
WHY THIS METHOD?
Time given is sufficient for
this Kuala Lumpur Twin
Tower Mega project
TRADITIONAL PROCUREMENT METHOD
1. Client can be involved in the design
process with the consultant team to
ensure that it is within the their
requirement.
2. Client able to make decision,
changes and provide instruction
during the designing stage with the
consultant team
Have full control of the design and able
to introduce changes from beginning till
the completion
WHY THIS METHOD?
Kuala Lumpur Twin Tower is a tourist area and
the landmark of Malaysia, quality of the work
must be taken into consideration.
● QUALITY
TRADITIONAL PROCUREMENT METHOD
Construction cost given is RM 1.2 billion.
1. This method is the most suitable as it provide lower cost risk to the
client due to the use of lump sum contract.
2. Any overcharging fees will be bear by contractor.
3. The amount is agreed between the parties in the contract before the
construction start.
4. Having a completed design of the project before tendering process
can provide the client certainty of the construction cost and the
design quality.
● COST
Minimum variation to the contract price during the construction
TRADITIONAL PROCUREMENT METHOD
1. The client only have to communicate with the consultant team
and only have contractual relationship with the main contractor
and consultants.
2. This form of procurement is also suitable for both experience
and inexperienced client because client can get advice from the
consultant team regarding to the project.
3. Subcontractors are dealt directly by the main contractor.
The client is not interest to deal with too many parties except the
few key members of the project.
CONCLUSION
TRADITIONAL METHOD
- Longer time frame but ensures better quality and cost delivered
- Does not need to deal with multiple parties but only key players
- Price certainty of construction cost unlike other methods
- For experience and inexperience clients unlike other methods
TENDER METHOD
TENDER METHOD
Client’s requirements:
● Reasonably transparent
selection process
● Eliminate potentially
non-performing contractor
RECOMMENDATION:
TWO STAGE
SELECTIVE TENDERING
SELECTIVE TENDERING
Tender Procedure
Pre-qualification Stage
1. Advertisement in newspaper
to invite interested tenderers
to submit their company
profiles for evaluation in the
Pre-qualification Form
2. A list of pre-qualified
contractors will then be
included in the final tender list
and invited to collect the
tender documents.
SELECTIVE TENDERING
Tender Procedure
Pre-qualification Stage
1. Advertisement in newspaper
to invite interested tenderers
to submit their company
profiles for evaluation in the
Pre-qualification Form
2. A list of pre-qualified
contractors will then be
included in the final tender list
and invited to collect the
tender documents.
Eliminate potentially
non-performing
contractors.
Reasonably transparent
selection process
SELECTIVE TENDERING
Tender Procedure
3. The list of pre-qualified contractors will
proceed on to the tendering process.
4. Evaluation process of tender
submissions from the list of pre-qualified
contractors takes place.
5. The most competent and suitable
contractor will be selected.
Quality
Assured
SELECTIVE TENDERING
Tender Procedure
6. The selected contractor will proceed on to the
negotiation process.
7. The price negotiation would take place until an
agreement is reached and both parties are satisfied,
leading them to enter into contract for construction
works to commence.
SELECTIVE TENDERING
(TWO STAGE)
Reasonably transparent selection process
Eliminate potentially non-performing contractor
Quality Assurance
CONTRACTUAL
ARRANGEMENT
CONTRACTUAL ARRANGEMENT
WHAT IS LUMP SUM CONTRACT ?
“Lump sum” price for all the work agreed before the work begin whereby
contractor is required to submit a total and global price.
Contractor is responsible for executing the complete contract work for a stated
total sum of money.
TYPE OF CONTRACT
LUMP SUM CONTRACT
CONTRACTUAL ARRANGEMENT
WHY LUMP SUM CONTRACT ?
Based on client’s condition and consideration :
1) Unfamiliar with construction industry
2) Not interested on dealing with too many parties
3) Minimum variation
TYPE OF CONTRACT
LUMP SUM CONTRACT
CONTRACTUAL ARRANGEMENT
PAM CONTRACT 2006 (WITH QUANTITIES)
WHY PAM CONTRACT 2006 ?
- private sector project
- traditional procurement method
FORM OF CONTRACT
CONTRACTUAL ARRANGEMENT
● TIME
● QUALITY
● HEALTH AND SAFETY
EMPLOYER’S CONSIDERATION AND REQUIREMENT
CONTRACTUAL ARRANGEMENT
● TIME
1. Clause 21.1
Possession of the site for execution of the works on the Date of Commencement
2. Article 7
Completion Date
3. Clause 22.1
Certificate of Non-Completion
4. Clause 22.2
Pay for the agreed Liquidated Damages (RM 250,000.00 a day)
5. Clause 15.2
Written notice for practically completed.
EMPLOYER’S CONSIDERATION AND REQUIREMENT
CONTRACTUAL ARRANGEMENT
● QUALITY
Clauses 6.0
Material, Goods and Workmanship To Conform to Description, Testing And
Inspection supports the requirement of good workmanship
Clauses 6.3
Inspection and testing
Clauses 6.5
Work not in accordance with the contract
Clauses 6.8
Warranties in respect of materials and goods
EMPLOYER’S CONSIDERATION AND REQUIREMENT
CONTRACTUAL ARRANGEMENT
● HEALTH AND SAFETY
A) GENERAL ITEMS IN PRELIMINARIES
B) EMPLOYEE’S SOCIAL SECURITY ACT 1969
C) WORKMEN’S COMPENSATION ACT 1952
D) PAM CONTRACT 2006 (WITH QUANTITIES)
E) OCCUPATIONAL SAFETY AND HEALTH 1994 ( OSHA 1994)
EMPLOYER’S CONSIDERATION AND REQUIREMENT
CONCLUSION
THANK YOU!
KENNETH TAN SIN KWANG 0322482
CHAN YI FUNG 0323057
LEE FONG YEN 0321976
LEE LIN HUI 0322797
LEONG LI JING 0323628
LEONG MIN HUI 0327596
ADELE LU KHAI SYN 0323151
LEW QUO MING 0322884
WONG JIA JING 0327221
YEAP PHAY SHIAN 0322243
YEE JYH LIN 0322408
THANK YOU!
KENNETH TAN SIN KWANG 0322482
CHAN YI FUNG 0323057
LEE FONG YEN 0321976
LEE LIN HUI 0322797
LEONG LI JING 0323628
LEONG MIN HUI 0327596
ADELE LU KHAI SYN 0323151
LEW QUO MING 0322884
WONG JIA JING 0327221
YEAP PHAY SHIAN 0322243
YEE JYH LIN 0322408

More Related Content

What's hot

Tender & Tender Notice
Tender & Tender NoticeTender & Tender Notice
Tender & Tender NoticeSakshi Kirar
 
Measurement 4:presentation slides
Measurement 4:presentation slidesMeasurement 4:presentation slides
Measurement 4:presentation slides마 이환
 
gas pipe line project report.
gas pipe line project report.gas pipe line project report.
gas pipe line project report.Hagi Sahib
 
Tender and tender document
Tender and tender documentTender and tender document
Tender and tender documentAkshataFarakate
 
QUANTITY SURVEYING
QUANTITY SURVEYINGQUANTITY SURVEYING
QUANTITY SURVEYINGlizwi nyandu
 
Professional practice 1
Professional practice 1Professional practice 1
Professional practice 1tfkc1212
 
Tendering Document for the Procurement of Works
Tendering Document for the Procurement of WorksTendering Document for the Procurement of Works
Tendering Document for the Procurement of WorksMohammad Alimuzzaman Bappy
 
Project Management Report
Project Management ReportProject Management Report
Project Management ReportSANKET SENAPATI
 
Basement remodel rev eh
Basement remodel rev ehBasement remodel rev eh
Basement remodel rev ehesands2437
 
Project management final report
Project management final reportProject management final report
Project management final reportSANKET SENAPATI
 
Estimating tender presentation
Estimating tender presentation Estimating tender presentation
Estimating tender presentation seenyeeyong
 
Eco friendly electricity generating tiles project
Eco friendly electricity generating tiles projectEco friendly electricity generating tiles project
Eco friendly electricity generating tiles projectHagi Sahib
 
Tenders contract -arti
Tenders contract -artiTenders contract -arti
Tenders contract -artijagadish108
 
Civil tenders and contracts spce
Civil tenders and contracts spceCivil tenders and contracts spce
Civil tenders and contracts spceirkportal
 
Beach house construction desktop 02 29
Beach house construction desktop 02 29Beach house construction desktop 02 29
Beach house construction desktop 02 29sheylaobm
 

What's hot (20)

Contract
Contract Contract
Contract
 
Tender & Tender Notice
Tender & Tender NoticeTender & Tender Notice
Tender & Tender Notice
 
Measurement 4:presentation slides
Measurement 4:presentation slidesMeasurement 4:presentation slides
Measurement 4:presentation slides
 
gas pipe line project report.
gas pipe line project report.gas pipe line project report.
gas pipe line project report.
 
Tender and tender document
Tender and tender documentTender and tender document
Tender and tender document
 
QUANTITY SURVEYING
QUANTITY SURVEYINGQUANTITY SURVEYING
QUANTITY SURVEYING
 
Tendering-professional practices-jamia millia islamia
Tendering-professional practices-jamia millia islamiaTendering-professional practices-jamia millia islamia
Tendering-professional practices-jamia millia islamia
 
Professional practice 1
Professional practice 1Professional practice 1
Professional practice 1
 
Tendering Document for the Procurement of Works
Tendering Document for the Procurement of WorksTendering Document for the Procurement of Works
Tendering Document for the Procurement of Works
 
Project Management Report
Project Management ReportProject Management Report
Project Management Report
 
Basement remodel rev eh
Basement remodel rev ehBasement remodel rev eh
Basement remodel rev eh
 
Project management final report
Project management final reportProject management final report
Project management final report
 
Estimating tender presentation
Estimating tender presentation Estimating tender presentation
Estimating tender presentation
 
Eco friendly electricity generating tiles project
Eco friendly electricity generating tiles projectEco friendly electricity generating tiles project
Eco friendly electricity generating tiles project
 
Tenders contract -arti
Tenders contract -artiTenders contract -arti
Tenders contract -arti
 
Civil tenders and contracts spce
Civil tenders and contracts spceCivil tenders and contracts spce
Civil tenders and contracts spce
 
Michelle Simpson Assignment #2
Michelle Simpson Assignment #2Michelle Simpson Assignment #2
Michelle Simpson Assignment #2
 
CV- AMAL
CV- AMALCV- AMAL
CV- AMAL
 
Professional practce
Professional practceProfessional practce
Professional practce
 
Beach house construction desktop 02 29
Beach house construction desktop 02 29Beach house construction desktop 02 29
Beach house construction desktop 02 29
 

Similar to Professional Practice I Assignment Slides

Professional practice 1 report
Professional practice 1 reportProfessional practice 1 report
Professional practice 1 reportNgo Jia Haur
 
Assignment - Management Contracting
Assignment - Management ContractingAssignment - Management Contracting
Assignment - Management ContractingKai Yun Pang
 
Professional Practice 1 Proposal Report
Professional Practice 1 Proposal ReportProfessional Practice 1 Proposal Report
Professional Practice 1 Proposal ReportArissa Loh
 
Pp1 assignment group 8
Pp1 assignment group 8Pp1 assignment group 8
Pp1 assignment group 8lohwenjun
 
Pp1 report
Pp1 reportPp1 report
Pp1 reportahmong4
 
Professional practice 1 (1)
Professional practice 1 (1)Professional practice 1 (1)
Professional practice 1 (1)tfkc1212
 
PP1 presentation
PP1 presentationPP1 presentation
PP1 presentationKailyn Lee
 
Professional practice 1 (QS)
Professional practice 1 (QS)Professional practice 1 (QS)
Professional practice 1 (QS)Hasif Alias
 
Pp1 assignment
Pp1 assignmentPp1 assignment
Pp1 assignmentLwj Welson
 
Pp1 assignment
Pp1 assignmentPp1 assignment
Pp1 assignmentLwj Welson
 
Contract Management - Contracts Types and Payment Structure
Contract Management - Contracts Types and Payment StructureContract Management - Contracts Types and Payment Structure
Contract Management - Contracts Types and Payment StructureHASMANIRA
 
Professional practice-1-presentation
Professional practice-1-presentationProfessional practice-1-presentation
Professional practice-1-presentationTimun Loh
 
PP1 assignment
PP1 assignment PP1 assignment
PP1 assignment Enoch Wong
 
Professional Practice 1
Professional Practice 1Professional Practice 1
Professional Practice 1Lee Pei Gie
 
Using Two-Stage Tendering Effectively
Using Two-Stage Tendering EffectivelyUsing Two-Stage Tendering Effectively
Using Two-Stage Tendering EffectivelyFrancis Ho
 
Pp1 group assignment presentation slides
Pp1 group assignment presentation slidesPp1 group assignment presentation slides
Pp1 group assignment presentation slidesPui Chun Shian
 

Similar to Professional Practice I Assignment Slides (20)

Professional practice 1 report
Professional practice 1 reportProfessional practice 1 report
Professional practice 1 report
 
Assignment - Management Contracting
Assignment - Management ContractingAssignment - Management Contracting
Assignment - Management Contracting
 
Professional Practice 1 Proposal Report
Professional Practice 1 Proposal ReportProfessional Practice 1 Proposal Report
Professional Practice 1 Proposal Report
 
Pp1 assignment group 8
Pp1 assignment group 8Pp1 assignment group 8
Pp1 assignment group 8
 
Pp1 group assignment
Pp1 group assignmentPp1 group assignment
Pp1 group assignment
 
Pp1 report
Pp1 reportPp1 report
Pp1 report
 
Professional practice 1 (1)
Professional practice 1 (1)Professional practice 1 (1)
Professional practice 1 (1)
 
PP1 presentation
PP1 presentationPP1 presentation
PP1 presentation
 
PP1 presentation
PP1 presentationPP1 presentation
PP1 presentation
 
Professional practice 1 (QS)
Professional practice 1 (QS)Professional practice 1 (QS)
Professional practice 1 (QS)
 
Pp1 assignment
Pp1 assignmentPp1 assignment
Pp1 assignment
 
Pp1 assignment
Pp1 assignmentPp1 assignment
Pp1 assignment
 
TOPIC2.pdf
TOPIC2.pdfTOPIC2.pdf
TOPIC2.pdf
 
Contract Management - Contracts Types and Payment Structure
Contract Management - Contracts Types and Payment StructureContract Management - Contracts Types and Payment Structure
Contract Management - Contracts Types and Payment Structure
 
Unit 5 Tendering
Unit 5 Tendering Unit 5 Tendering
Unit 5 Tendering
 
Professional practice-1-presentation
Professional practice-1-presentationProfessional practice-1-presentation
Professional practice-1-presentation
 
PP1 assignment
PP1 assignment PP1 assignment
PP1 assignment
 
Professional Practice 1
Professional Practice 1Professional Practice 1
Professional Practice 1
 
Using Two-Stage Tendering Effectively
Using Two-Stage Tendering EffectivelyUsing Two-Stage Tendering Effectively
Using Two-Stage Tendering Effectively
 
Pp1 group assignment presentation slides
Pp1 group assignment presentation slidesPp1 group assignment presentation slides
Pp1 group assignment presentation slides
 

More from ashleyyeap

CSI JOURNAL cover page
CSI JOURNAL cover pageCSI JOURNAL cover page
CSI JOURNAL cover pageashleyyeap
 
Fm group assignment
Fm group assignment Fm group assignment
Fm group assignment ashleyyeap
 
Pp2 assignment-final
Pp2 assignment-finalPp2 assignment-final
Pp2 assignment-finalashleyyeap
 
PP2 final account assignment calculations
PP2 final account assignment calculationsPP2 final account assignment calculations
PP2 final account assignment calculationsashleyyeap
 
Fm august 2018 group assignment brief
Fm august 2018 group assignment briefFm august 2018 group assignment brief
Fm august 2018 group assignment briefashleyyeap
 
Building Economics Assignment Report
Building Economics Assignment ReportBuilding Economics Assignment Report
Building Economics Assignment Reportashleyyeap
 
Building Economics Preliminary Cost Appraisal
Building Economics Preliminary Cost Appraisal Building Economics Preliminary Cost Appraisal
Building Economics Preliminary Cost Appraisal ashleyyeap
 
PP2 Seminar Presentation
PP2 Seminar PresentationPP2 Seminar Presentation
PP2 Seminar Presentationashleyyeap
 
Pp2 final account assignment excel
Pp2 final account assignment excelPp2 final account assignment excel
Pp2 final account assignment excelashleyyeap
 
Pp2 assignment-final
Pp2 assignment-finalPp2 assignment-final
Pp2 assignment-finalashleyyeap
 
Pp2 coursework 2 201808
Pp2 coursework 2   201808Pp2 coursework 2   201808
Pp2 coursework 2 201808ashleyyeap
 
Measurement Assignment
Measurement AssignmentMeasurement Assignment
Measurement Assignmentashleyyeap
 
Professional Practice 1 Tutorial 3
Professional Practice 1 Tutorial 3Professional Practice 1 Tutorial 3
Professional Practice 1 Tutorial 3ashleyyeap
 
Professional Practice 1 Tutorial 7
Professional Practice 1 Tutorial 7Professional Practice 1 Tutorial 7
Professional Practice 1 Tutorial 7ashleyyeap
 
Estimating Assignment
Estimating Assignment Estimating Assignment
Estimating Assignment ashleyyeap
 
Software Assignment
Software AssignmentSoftware Assignment
Software Assignmentashleyyeap
 
Management Science Assignment
Management Science Assignment Management Science Assignment
Management Science Assignment ashleyyeap
 
People Dynamics Individual Assignment - Case Study
People Dynamics Individual Assignment - Case StudyPeople Dynamics Individual Assignment - Case Study
People Dynamics Individual Assignment - Case Studyashleyyeap
 
Building Services II Presentation Slides
Building Services II Presentation SlidesBuilding Services II Presentation Slides
Building Services II Presentation Slidesashleyyeap
 

More from ashleyyeap (20)

CSI JOURNAL cover page
CSI JOURNAL cover pageCSI JOURNAL cover page
CSI JOURNAL cover page
 
CSI JOURNAL
CSI JOURNALCSI JOURNAL
CSI JOURNAL
 
Fm group assignment
Fm group assignment Fm group assignment
Fm group assignment
 
Pp2 assignment-final
Pp2 assignment-finalPp2 assignment-final
Pp2 assignment-final
 
PP2 final account assignment calculations
PP2 final account assignment calculationsPP2 final account assignment calculations
PP2 final account assignment calculations
 
Fm august 2018 group assignment brief
Fm august 2018 group assignment briefFm august 2018 group assignment brief
Fm august 2018 group assignment brief
 
Building Economics Assignment Report
Building Economics Assignment ReportBuilding Economics Assignment Report
Building Economics Assignment Report
 
Building Economics Preliminary Cost Appraisal
Building Economics Preliminary Cost Appraisal Building Economics Preliminary Cost Appraisal
Building Economics Preliminary Cost Appraisal
 
PP2 Seminar Presentation
PP2 Seminar PresentationPP2 Seminar Presentation
PP2 Seminar Presentation
 
Pp2 final account assignment excel
Pp2 final account assignment excelPp2 final account assignment excel
Pp2 final account assignment excel
 
Pp2 assignment-final
Pp2 assignment-finalPp2 assignment-final
Pp2 assignment-final
 
Pp2 coursework 2 201808
Pp2 coursework 2   201808Pp2 coursework 2   201808
Pp2 coursework 2 201808
 
Measurement Assignment
Measurement AssignmentMeasurement Assignment
Measurement Assignment
 
Professional Practice 1 Tutorial 3
Professional Practice 1 Tutorial 3Professional Practice 1 Tutorial 3
Professional Practice 1 Tutorial 3
 
Professional Practice 1 Tutorial 7
Professional Practice 1 Tutorial 7Professional Practice 1 Tutorial 7
Professional Practice 1 Tutorial 7
 
Estimating Assignment
Estimating Assignment Estimating Assignment
Estimating Assignment
 
Software Assignment
Software AssignmentSoftware Assignment
Software Assignment
 
Management Science Assignment
Management Science Assignment Management Science Assignment
Management Science Assignment
 
People Dynamics Individual Assignment - Case Study
People Dynamics Individual Assignment - Case StudyPeople Dynamics Individual Assignment - Case Study
People Dynamics Individual Assignment - Case Study
 
Building Services II Presentation Slides
Building Services II Presentation SlidesBuilding Services II Presentation Slides
Building Services II Presentation Slides
 

Recently uploaded

“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...Marc Dusseiller Dusjagr
 
How to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxHow to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxmanuelaromero2013
 
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions  for the students and aspirants of Chemistry12th.pptxOrganic Name Reactions  for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions for the students and aspirants of Chemistry12th.pptxVS Mahajan Coaching Centre
 
Blooming Together_ Growing a Community Garden Worksheet.docx
Blooming Together_ Growing a Community Garden Worksheet.docxBlooming Together_ Growing a Community Garden Worksheet.docx
Blooming Together_ Growing a Community Garden Worksheet.docxUnboundStockton
 
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Sapana Sha
 
Biting mechanism of poisonous snakes.pdf
Biting mechanism of poisonous snakes.pdfBiting mechanism of poisonous snakes.pdf
Biting mechanism of poisonous snakes.pdfadityarao40181
 
Science 7 - LAND and SEA BREEZE and its Characteristics
Science 7 - LAND and SEA BREEZE and its CharacteristicsScience 7 - LAND and SEA BREEZE and its Characteristics
Science 7 - LAND and SEA BREEZE and its CharacteristicsKarinaGenton
 
The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13Steve Thomason
 
Introduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxIntroduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxpboyjonauth
 
Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17Celine George
 
भारत-रोम व्यापार.pptx, Indo-Roman Trade,
भारत-रोम व्यापार.pptx, Indo-Roman Trade,भारत-रोम व्यापार.pptx, Indo-Roman Trade,
भारत-रोम व्यापार.pptx, Indo-Roman Trade,Virag Sontakke
 
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Krashi Coaching
 
ENGLISH5 QUARTER4 MODULE1 WEEK1-3 How Visual and Multimedia Elements.pptx
ENGLISH5 QUARTER4 MODULE1 WEEK1-3 How Visual and Multimedia Elements.pptxENGLISH5 QUARTER4 MODULE1 WEEK1-3 How Visual and Multimedia Elements.pptx
ENGLISH5 QUARTER4 MODULE1 WEEK1-3 How Visual and Multimedia Elements.pptxAnaBeatriceAblay2
 
EPANDING THE CONTENT OF AN OUTLINE using notes.pptx
EPANDING THE CONTENT OF AN OUTLINE using notes.pptxEPANDING THE CONTENT OF AN OUTLINE using notes.pptx
EPANDING THE CONTENT OF AN OUTLINE using notes.pptxRaymartEstabillo3
 
Proudly South Africa powerpoint Thorisha.pptx
Proudly South Africa powerpoint Thorisha.pptxProudly South Africa powerpoint Thorisha.pptx
Proudly South Africa powerpoint Thorisha.pptxthorishapillay1
 
How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17Celine George
 
Pharmacognosy Flower 3. Compositae 2023.pdf
Pharmacognosy Flower 3. Compositae 2023.pdfPharmacognosy Flower 3. Compositae 2023.pdf
Pharmacognosy Flower 3. Compositae 2023.pdfMahmoud M. Sallam
 
Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)eniolaolutunde
 
Class 11 Legal Studies Ch-1 Concept of State .pdf
Class 11 Legal Studies Ch-1 Concept of State .pdfClass 11 Legal Studies Ch-1 Concept of State .pdf
Class 11 Legal Studies Ch-1 Concept of State .pdfakmcokerachita
 

Recently uploaded (20)

“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
 
How to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxHow to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptx
 
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions  for the students and aspirants of Chemistry12th.pptxOrganic Name Reactions  for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
 
Blooming Together_ Growing a Community Garden Worksheet.docx
Blooming Together_ Growing a Community Garden Worksheet.docxBlooming Together_ Growing a Community Garden Worksheet.docx
Blooming Together_ Growing a Community Garden Worksheet.docx
 
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
 
Biting mechanism of poisonous snakes.pdf
Biting mechanism of poisonous snakes.pdfBiting mechanism of poisonous snakes.pdf
Biting mechanism of poisonous snakes.pdf
 
Science 7 - LAND and SEA BREEZE and its Characteristics
Science 7 - LAND and SEA BREEZE and its CharacteristicsScience 7 - LAND and SEA BREEZE and its Characteristics
Science 7 - LAND and SEA BREEZE and its Characteristics
 
The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13The Most Excellent Way | 1 Corinthians 13
The Most Excellent Way | 1 Corinthians 13
 
Introduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxIntroduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptx
 
Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17
 
भारत-रोम व्यापार.pptx, Indo-Roman Trade,
भारत-रोम व्यापार.pptx, Indo-Roman Trade,भारत-रोम व्यापार.pptx, Indo-Roman Trade,
भारत-रोम व्यापार.pptx, Indo-Roman Trade,
 
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
 
ENGLISH5 QUARTER4 MODULE1 WEEK1-3 How Visual and Multimedia Elements.pptx
ENGLISH5 QUARTER4 MODULE1 WEEK1-3 How Visual and Multimedia Elements.pptxENGLISH5 QUARTER4 MODULE1 WEEK1-3 How Visual and Multimedia Elements.pptx
ENGLISH5 QUARTER4 MODULE1 WEEK1-3 How Visual and Multimedia Elements.pptx
 
EPANDING THE CONTENT OF AN OUTLINE using notes.pptx
EPANDING THE CONTENT OF AN OUTLINE using notes.pptxEPANDING THE CONTENT OF AN OUTLINE using notes.pptx
EPANDING THE CONTENT OF AN OUTLINE using notes.pptx
 
Proudly South Africa powerpoint Thorisha.pptx
Proudly South Africa powerpoint Thorisha.pptxProudly South Africa powerpoint Thorisha.pptx
Proudly South Africa powerpoint Thorisha.pptx
 
How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17
 
Pharmacognosy Flower 3. Compositae 2023.pdf
Pharmacognosy Flower 3. Compositae 2023.pdfPharmacognosy Flower 3. Compositae 2023.pdf
Pharmacognosy Flower 3. Compositae 2023.pdf
 
Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)
 
9953330565 Low Rate Call Girls In Rohini Delhi NCR
9953330565 Low Rate Call Girls In Rohini  Delhi NCR9953330565 Low Rate Call Girls In Rohini  Delhi NCR
9953330565 Low Rate Call Girls In Rohini Delhi NCR
 
Class 11 Legal Studies Ch-1 Concept of State .pdf
Class 11 Legal Studies Ch-1 Concept of State .pdfClass 11 Legal Studies Ch-1 Concept of State .pdf
Class 11 Legal Studies Ch-1 Concept of State .pdf
 

Professional Practice I Assignment Slides

  • 3. PROCUREMENT METHOD Client’s requirements: ● Have full control of the design and able to introduce changes from beginning till the completion ● Not interested in the daily dealing with too many parties except the few key members of the project ● Complete project on time ● Minimum variation to the contract price during the construction
  • 5. TRADITIONAL PROCUREMENT METHOD How does it work? ● Design phase to Construction phase ● Consultant teams are appointed at the early stage to carry out the design process. ● Work will then tender out to the suitable contractor only after design process is completed. ● Client can involved in the design stage to ensure it is within their requirements.
  • 7. TRADITIONAL PROCUREMENT METHOD ● TIME 1. Priority of this project fall into quality and cost due to time is not constraints. 2. Provides medium time risk to the client because it requires longer time frame for the Pre and Post Tender Stage. Duration of the project is 5 years WHY THIS METHOD? Time given is sufficient for this Kuala Lumpur Twin Tower Mega project
  • 8. TRADITIONAL PROCUREMENT METHOD 1. Client can be involved in the design process with the consultant team to ensure that it is within the their requirement. 2. Client able to make decision, changes and provide instruction during the designing stage with the consultant team Have full control of the design and able to introduce changes from beginning till the completion WHY THIS METHOD? Kuala Lumpur Twin Tower is a tourist area and the landmark of Malaysia, quality of the work must be taken into consideration. ● QUALITY
  • 9. TRADITIONAL PROCUREMENT METHOD Construction cost given is RM 1.2 billion. 1. This method is the most suitable as it provide lower cost risk to the client due to the use of lump sum contract. 2. Any overcharging fees will be bear by contractor. 3. The amount is agreed between the parties in the contract before the construction start. 4. Having a completed design of the project before tendering process can provide the client certainty of the construction cost and the design quality. ● COST Minimum variation to the contract price during the construction
  • 10. TRADITIONAL PROCUREMENT METHOD 1. The client only have to communicate with the consultant team and only have contractual relationship with the main contractor and consultants. 2. This form of procurement is also suitable for both experience and inexperienced client because client can get advice from the consultant team regarding to the project. 3. Subcontractors are dealt directly by the main contractor. The client is not interest to deal with too many parties except the few key members of the project.
  • 11. CONCLUSION TRADITIONAL METHOD - Longer time frame but ensures better quality and cost delivered - Does not need to deal with multiple parties but only key players - Price certainty of construction cost unlike other methods - For experience and inexperience clients unlike other methods
  • 13. TENDER METHOD Client’s requirements: ● Reasonably transparent selection process ● Eliminate potentially non-performing contractor
  • 15. SELECTIVE TENDERING Tender Procedure Pre-qualification Stage 1. Advertisement in newspaper to invite interested tenderers to submit their company profiles for evaluation in the Pre-qualification Form 2. A list of pre-qualified contractors will then be included in the final tender list and invited to collect the tender documents.
  • 16. SELECTIVE TENDERING Tender Procedure Pre-qualification Stage 1. Advertisement in newspaper to invite interested tenderers to submit their company profiles for evaluation in the Pre-qualification Form 2. A list of pre-qualified contractors will then be included in the final tender list and invited to collect the tender documents. Eliminate potentially non-performing contractors. Reasonably transparent selection process
  • 17. SELECTIVE TENDERING Tender Procedure 3. The list of pre-qualified contractors will proceed on to the tendering process. 4. Evaluation process of tender submissions from the list of pre-qualified contractors takes place. 5. The most competent and suitable contractor will be selected. Quality Assured
  • 18. SELECTIVE TENDERING Tender Procedure 6. The selected contractor will proceed on to the negotiation process. 7. The price negotiation would take place until an agreement is reached and both parties are satisfied, leading them to enter into contract for construction works to commence.
  • 19. SELECTIVE TENDERING (TWO STAGE) Reasonably transparent selection process Eliminate potentially non-performing contractor Quality Assurance
  • 21. CONTRACTUAL ARRANGEMENT WHAT IS LUMP SUM CONTRACT ? “Lump sum” price for all the work agreed before the work begin whereby contractor is required to submit a total and global price. Contractor is responsible for executing the complete contract work for a stated total sum of money. TYPE OF CONTRACT LUMP SUM CONTRACT
  • 22. CONTRACTUAL ARRANGEMENT WHY LUMP SUM CONTRACT ? Based on client’s condition and consideration : 1) Unfamiliar with construction industry 2) Not interested on dealing with too many parties 3) Minimum variation TYPE OF CONTRACT LUMP SUM CONTRACT
  • 23. CONTRACTUAL ARRANGEMENT PAM CONTRACT 2006 (WITH QUANTITIES) WHY PAM CONTRACT 2006 ? - private sector project - traditional procurement method FORM OF CONTRACT
  • 24. CONTRACTUAL ARRANGEMENT ● TIME ● QUALITY ● HEALTH AND SAFETY EMPLOYER’S CONSIDERATION AND REQUIREMENT
  • 25. CONTRACTUAL ARRANGEMENT ● TIME 1. Clause 21.1 Possession of the site for execution of the works on the Date of Commencement 2. Article 7 Completion Date 3. Clause 22.1 Certificate of Non-Completion 4. Clause 22.2 Pay for the agreed Liquidated Damages (RM 250,000.00 a day) 5. Clause 15.2 Written notice for practically completed. EMPLOYER’S CONSIDERATION AND REQUIREMENT
  • 26. CONTRACTUAL ARRANGEMENT ● QUALITY Clauses 6.0 Material, Goods and Workmanship To Conform to Description, Testing And Inspection supports the requirement of good workmanship Clauses 6.3 Inspection and testing Clauses 6.5 Work not in accordance with the contract Clauses 6.8 Warranties in respect of materials and goods EMPLOYER’S CONSIDERATION AND REQUIREMENT
  • 27. CONTRACTUAL ARRANGEMENT ● HEALTH AND SAFETY A) GENERAL ITEMS IN PRELIMINARIES B) EMPLOYEE’S SOCIAL SECURITY ACT 1969 C) WORKMEN’S COMPENSATION ACT 1952 D) PAM CONTRACT 2006 (WITH QUANTITIES) E) OCCUPATIONAL SAFETY AND HEALTH 1994 ( OSHA 1994) EMPLOYER’S CONSIDERATION AND REQUIREMENT
  • 29. THANK YOU! KENNETH TAN SIN KWANG 0322482 CHAN YI FUNG 0323057 LEE FONG YEN 0321976 LEE LIN HUI 0322797 LEONG LI JING 0323628 LEONG MIN HUI 0327596 ADELE LU KHAI SYN 0323151 LEW QUO MING 0322884 WONG JIA JING 0327221 YEAP PHAY SHIAN 0322243 YEE JYH LIN 0322408
  • 30. THANK YOU! KENNETH TAN SIN KWANG 0322482 CHAN YI FUNG 0323057 LEE FONG YEN 0321976 LEE LIN HUI 0322797 LEONG LI JING 0323628 LEONG MIN HUI 0327596 ADELE LU KHAI SYN 0323151 LEW QUO MING 0322884 WONG JIA JING 0327221 YEAP PHAY SHIAN 0322243 YEE JYH LIN 0322408