SlideShare a Scribd company logo
1 of 20
Tender 
Documentation 
Name: 
Yam Yih Hwan 
Wong Ha Shiong 
Low Rong Tzuoo 
Ng Jun Keat 
Harvey Yap Zhu Guang
Project Details 
 CADANGAN PEMAJUAN PERUMAHAN YANG 
MENGANDUNGI: 
• 21 UNIT RUMAH TERES 1½ TINGKAT (RT1) 
• 46 UNIT RUMAH TERES 1½ TINGKAT (RT) 
 DI ATAS LOT ASAL 3815, JALAN SEKOLAH, KG. BATU 10, 
KEBUN BAHRU, 42500 TELOK PANGLIMA GARANG, 
DAERAH KUALA LANGAT, SELANGOR DARUL EHSAN. 
 Private Sector Tendering 
 PAM 2006 Standard Form
Architect & Engineer 
1. Architect 
Details on 
(K.E.Guay Architect) 
2. Engineer 
(FLIP Consultancy)
Purpose of Tender Documents 
 Tender documents are prepared and sent out to 
potential tenderers to seek tenders. 
 To provide guidance on how the tender documents 
should be completed. 
 To set out the legal framework and the obligations 
between both parties.
Components in Tender 
Document 
1. Cover Letter 
2. Invitation to Tender 
3. Form of Tender 
4. Terms & Conditions 
5. General Summary 
6. Preliminaries 
7. Preambles 
8. Specifications 
9. Bill of Quantities
Declaration of non-collusion 
 To prevent corruption in the tender process:- 
 To proof that they have not colluded with any other party 
to fix or adjust the tender price during the preparation of 
tender.
Form of Tender 
 A form of tender covered the documents prepared by 
the Client and signed by the tenderer:- 
 to indicate that they understand the tender and accept 
the various terms and conditions of the contract, and 
other requirements of participating in the tender.
Conditions of Contract 
 Sets out the contractual terms that will be used:- 
 Information on your rights and obligations 
 Information on the Government's rights and obligations
Instructions to Tenderer 
 To explain some rules you need to follow while 
preparing the tender:- 
 Inform you how to submit your tender and alerts you to 
some things to be aware of. 
 If you do not follow the rules set out, there is a risk your 
tender will be rejected.
Conditions of Tendering 
 Tenders shall be submitted in writing on the forms 
provided. 
 The condition that need to be complied with by the 
tenderer in the submission of tender. 
 Any supplementary documents shall be signed and 
dated.
General Summary of Tender 
 Collection of all the proceed of bills of all sections of 
the projects:- 
 For tenderer to insert his sectional summary to arrive at a 
total amount which later becomes the Contract Sums.
Preliminaries 
 A description of the project that allows 
the contractor to assess costs in required by the method 
and circumstances of the works before the construction 
start. 
 General Summary 
 Form and Type of Contracts 
 Facilities to be provided by the contractor
Preamble 
 A preamble is an explanation of a document:- 
 A description of the parties to the contract. 
 A summary of the negotiations. 
 The objectives of the project.
Specification 
 Provides a comprehensive description of what is 
required, for example:- 
 Functional requirements 
 Technical requirements 
 Performance requirements 
 Quality of Materials 
 Workmanship 
 They do not include cost, quantity or drawn information
Bills of Quantities 
 As the basis of submitting the bid where all prices are 
entered for carrying out all works. 
 The bill of quantities assists tenderers in producing an 
estimate of:- 
 Construction costs for their tender, and, as it means all 
tenderers will be pricing the same quantities. 
 It also provides a fair and accurate system for 
tendering. 
 Each invited tenderer bids against the bill of quantities, 
stating their price for each work item.
List of P.C. and Provisional 
Sums 
 An allowance, for the supply of work or materials to be 
provided by a supplier:- 
 This allowance exclude any of the profit mark up 
or attendance. 
 Inserted into tender documents for a specific element of 
the works that is not yet defined in enough detail.
Drawings 
 List of drawings prepare by the Architect, Engineers and 
etc. 
 These are clear and concise detailed documents about 
the construction site, path construction and any related 
feature works. 
 Showing the allocation on each and every particular 
scope of works and its location.
Schedule of Work/Finishes 
 Schedules simply list the work required. 
 Any information about quality should be provided by 
reference to:- 
 Specifications 
 Information about location 
 Information about size 
 A detail finishes for the whole building.
Daywork rates 
 Contractor is paid for specifically instructed work on the 
basis of the cost of:- 
 Labour 
 Materials 
 Plant 
 Machineries 
 Along with a mark up for overheads and profit. 
 Generally used when work cannot be priced in the 
normal way.
Bank Guarantee Form 
 A guarantee from the bank ensuring that the liabilities 
of a debtor will be met. 
 In other words, if the debtor fails to settle a debt, the 
bank will cover it.

More Related Content

What's hot

Assignment - Tender Documentation (Presentation Slide)
Assignment - Tender Documentation (Presentation Slide)Assignment - Tender Documentation (Presentation Slide)
Assignment - Tender Documentation (Presentation Slide)Kai Yun Pang
 
QUANTITY SURVEYING
QUANTITY SURVEYINGQUANTITY SURVEYING
QUANTITY SURVEYINGlizwi nyandu
 
PP Seminar Tutorial 7
PP Seminar Tutorial 7PP Seminar Tutorial 7
PP Seminar Tutorial 7Farah Sham
 
Civil Quantity Survey and Estimation
Civil Quantity Survey and EstimationCivil Quantity Survey and Estimation
Civil Quantity Survey and EstimationGide India
 
Tendering process, Bid Evaluation & Award Process
Tendering process, Bid Evaluation & Award ProcessTendering process, Bid Evaluation & Award Process
Tendering process, Bid Evaluation & Award ProcessPrateek Kashyap
 
Contractor Selection - Special District Meeting
Contractor Selection - Special District MeetingContractor Selection - Special District Meeting
Contractor Selection - Special District MeetingWaseem Khan, PG
 
Types of Tender and their Process
Types of Tender and their ProcessTypes of Tender and their Process
Types of Tender and their Processarpantripathi2
 
Contract Specifications, Bidding and Contractor Selection for Capital Replace...
Contract Specifications, Bidding and Contractor Selection for Capital Replace...Contract Specifications, Bidding and Contractor Selection for Capital Replace...
Contract Specifications, Bidding and Contractor Selection for Capital Replace...Kipcon Inc.
 
Types of tender and their processing.
Types of tender and their processing.Types of tender and their processing.
Types of tender and their processing.Abhishek kumar maurya
 
Quantity-Surveyor (ICI+ITD)-pdf.pdf
Quantity-Surveyor (ICI+ITD)-pdf.pdfQuantity-Surveyor (ICI+ITD)-pdf.pdf
Quantity-Surveyor (ICI+ITD)-pdf.pdfChong Yi Hui
 
Tendering documentation
Tendering documentationTendering documentation
Tendering documentationnipuna_bopage
 
Construction contracts docuements_08092008
Construction contracts docuements_08092008Construction contracts docuements_08092008
Construction contracts docuements_08092008AYM1979
 

What's hot (20)

Assignment - Tender Documentation (Presentation Slide)
Assignment - Tender Documentation (Presentation Slide)Assignment - Tender Documentation (Presentation Slide)
Assignment - Tender Documentation (Presentation Slide)
 
QUANTITY SURVEYING
QUANTITY SURVEYINGQUANTITY SURVEYING
QUANTITY SURVEYING
 
M4ppt
M4pptM4ppt
M4ppt
 
PP Seminar
PP SeminarPP Seminar
PP Seminar
 
Module 4 lecture 1
Module  4 lecture 1Module  4 lecture 1
Module 4 lecture 1
 
Tender
TenderTender
Tender
 
PP Seminar Tutorial 7
PP Seminar Tutorial 7PP Seminar Tutorial 7
PP Seminar Tutorial 7
 
Mega project
Mega projectMega project
Mega project
 
Chapter 2- Contract Management
Chapter 2- Contract ManagementChapter 2- Contract Management
Chapter 2- Contract Management
 
Civil Quantity Survey and Estimation
Civil Quantity Survey and EstimationCivil Quantity Survey and Estimation
Civil Quantity Survey and Estimation
 
Tendering-professional practices-jamia millia islamia
Tendering-professional practices-jamia millia islamiaTendering-professional practices-jamia millia islamia
Tendering-professional practices-jamia millia islamia
 
Tendering process, Bid Evaluation & Award Process
Tendering process, Bid Evaluation & Award ProcessTendering process, Bid Evaluation & Award Process
Tendering process, Bid Evaluation & Award Process
 
Contractor Selection - Special District Meeting
Contractor Selection - Special District MeetingContractor Selection - Special District Meeting
Contractor Selection - Special District Meeting
 
Types of Tender and their Process
Types of Tender and their ProcessTypes of Tender and their Process
Types of Tender and their Process
 
Contract Specifications, Bidding and Contractor Selection for Capital Replace...
Contract Specifications, Bidding and Contractor Selection for Capital Replace...Contract Specifications, Bidding and Contractor Selection for Capital Replace...
Contract Specifications, Bidding and Contractor Selection for Capital Replace...
 
Pp1 seminar
Pp1 seminarPp1 seminar
Pp1 seminar
 
Types of tender and their processing.
Types of tender and their processing.Types of tender and their processing.
Types of tender and their processing.
 
Quantity-Surveyor (ICI+ITD)-pdf.pdf
Quantity-Surveyor (ICI+ITD)-pdf.pdfQuantity-Surveyor (ICI+ITD)-pdf.pdf
Quantity-Surveyor (ICI+ITD)-pdf.pdf
 
Tendering documentation
Tendering documentationTendering documentation
Tendering documentation
 
Construction contracts docuements_08092008
Construction contracts docuements_08092008Construction contracts docuements_08092008
Construction contracts docuements_08092008
 

Similar to Measurement 4:presentation slides

Tendering Bidding & Award of Contract Final Draft
Tendering Bidding & Award of Contract Final DraftTendering Bidding & Award of Contract Final Draft
Tendering Bidding & Award of Contract Final DraftMuneesh Methwani
 
Pp1 presentation 2
Pp1 presentation 2Pp1 presentation 2
Pp1 presentation 2shensin1015
 
Estimation and Costing - Contracts
Estimation and Costing - ContractsEstimation and Costing - Contracts
Estimation and Costing - Contractssrinivas2036
 
contract_management.ppt
contract_management.pptcontract_management.ppt
contract_management.pptssuser32da691
 
Architectural Professional Practice - Construction Documents
Architectural Professional Practice - Construction DocumentsArchitectural Professional Practice - Construction Documents
Architectural Professional Practice - Construction DocumentsGalala University
 
Preparation of bill sandeep
Preparation of bill sandeepPreparation of bill sandeep
Preparation of bill sandeepSandeep Yadav
 
Cost estimates & contract documents ce224 pdf
Cost estimates & contract documents   ce224 pdfCost estimates & contract documents   ce224 pdf
Cost estimates & contract documents ce224 pdfSaqib Imran
 
Tenders and procedure of tendering
Tenders and procedure of tenderingTenders and procedure of tendering
Tenders and procedure of tenderingvvsasane
 
General notes to building schedule of rates
General notes to building schedule of ratesGeneral notes to building schedule of rates
General notes to building schedule of ratesVj NiroSh
 
General notes to BSR BUILDING SCHEDULE OF RATES
General notes to BSR BUILDING SCHEDULE OF RATESGeneral notes to BSR BUILDING SCHEDULE OF RATES
General notes to BSR BUILDING SCHEDULE OF RATESR.R.G.S Bandara
 
4. offer tendering - site
4. offer   tendering - site4. offer   tendering - site
4. offer tendering - siteAbdulaziz Kaya
 
Topic 1 - Bidding Documents.pptx
Topic 1 - Bidding Documents.pptxTopic 1 - Bidding Documents.pptx
Topic 1 - Bidding Documents.pptxVanJasperCastillo
 

Similar to Measurement 4:presentation slides (20)

Tendering Bidding & Award of Contract Final Draft
Tendering Bidding & Award of Contract Final DraftTendering Bidding & Award of Contract Final Draft
Tendering Bidding & Award of Contract Final Draft
 
Tanmay presentation
Tanmay presentationTanmay presentation
Tanmay presentation
 
Pp1 presentation 2
Pp1 presentation 2Pp1 presentation 2
Pp1 presentation 2
 
Tendering
TenderingTendering
Tendering
 
Estimation and Costing - Contracts
Estimation and Costing - ContractsEstimation and Costing - Contracts
Estimation and Costing - Contracts
 
ACH 216 Lecture 04b (Bidding) Part 2
ACH 216 Lecture 04b (Bidding) Part 2ACH 216 Lecture 04b (Bidding) Part 2
ACH 216 Lecture 04b (Bidding) Part 2
 
contract_management.ppt
contract_management.pptcontract_management.ppt
contract_management.ppt
 
Working drawing and detailing
Working drawing and detailingWorking drawing and detailing
Working drawing and detailing
 
Contracts & tenders
Contracts & tendersContracts & tenders
Contracts & tenders
 
Chapter -Two (2).pdf
Chapter -Two (2).pdfChapter -Two (2).pdf
Chapter -Two (2).pdf
 
Architectural Professional Practice - Construction Documents
Architectural Professional Practice - Construction DocumentsArchitectural Professional Practice - Construction Documents
Architectural Professional Practice - Construction Documents
 
Preparation of bill sandeep
Preparation of bill sandeepPreparation of bill sandeep
Preparation of bill sandeep
 
Cost estimates & contract documents ce224 pdf
Cost estimates & contract documents   ce224 pdfCost estimates & contract documents   ce224 pdf
Cost estimates & contract documents ce224 pdf
 
Tenders and procedure of tendering
Tenders and procedure of tenderingTenders and procedure of tendering
Tenders and procedure of tendering
 
tendering
 tendering tendering
tendering
 
General notes to building schedule of rates
General notes to building schedule of ratesGeneral notes to building schedule of rates
General notes to building schedule of rates
 
General notes to BSR BUILDING SCHEDULE OF RATES
General notes to BSR BUILDING SCHEDULE OF RATESGeneral notes to BSR BUILDING SCHEDULE OF RATES
General notes to BSR BUILDING SCHEDULE OF RATES
 
4. offer tendering - site
4. offer   tendering - site4. offer   tendering - site
4. offer tendering - site
 
Tenders for construction
Tenders for constructionTenders for construction
Tenders for construction
 
Topic 1 - Bidding Documents.pptx
Topic 1 - Bidding Documents.pptxTopic 1 - Bidding Documents.pptx
Topic 1 - Bidding Documents.pptx
 

More from 마 이환

Research Methodology:Literature Review (Chapter 2)
Research Methodology:Literature Review (Chapter 2)Research Methodology:Literature Review (Chapter 2)
Research Methodology:Literature Review (Chapter 2)마 이환
 
Research Methodology:Introduction (Chapter 1)
Research Methodology:Introduction (Chapter 1)Research Methodology:Introduction (Chapter 1)
Research Methodology:Introduction (Chapter 1)마 이환
 
Sustainable Housing Development
Sustainable Housing DevelopmentSustainable Housing Development
Sustainable Housing Development마 이환
 
Assignment:Major Water Issue (revised)
Assignment:Major Water Issue (revised)Assignment:Major Water Issue (revised)
Assignment:Major Water Issue (revised)마 이환
 
Chapter 10a Insurance:Contractor's Indemnity to Employer
Chapter 10a   Insurance:Contractor's Indemnity to EmployerChapter 10a   Insurance:Contractor's Indemnity to Employer
Chapter 10a Insurance:Contractor's Indemnity to Employer마 이환
 
Professional Practice 2: Group Assignment
Professional Practice 2: Group AssignmentProfessional Practice 2: Group Assignment
Professional Practice 2: Group Assignment마 이환
 
Financial Management:Presentation Slides
Financial Management:Presentation SlidesFinancial Management:Presentation Slides
Financial Management:Presentation Slides마 이환
 
Financial Report:Comments & Evaluations
Financial Report:Comments & EvaluationsFinancial Report:Comments & Evaluations
Financial Report:Comments & Evaluations마 이환
 
Financial Report:Cash Budget, Income Statement & Balance Sheet
Financial Report:Cash Budget, Income Statement & Balance SheetFinancial Report:Cash Budget, Income Statement & Balance Sheet
Financial Report:Cash Budget, Income Statement & Balance Sheet마 이환
 
Building Economics:Tender Report
Building Economics:Tender ReportBuilding Economics:Tender Report
Building Economics:Tender Report마 이환
 
Building Economics:Individual Assessment
Building Economics:Individual AssessmentBuilding Economics:Individual Assessment
Building Economics:Individual Assessment마 이환
 
Schedule of agreed datelines
Schedule of agreed datelinesSchedule of agreed datelines
Schedule of agreed datelines마 이환
 
Reply for queries (architect)
Reply for queries (architect)Reply for queries (architect)
Reply for queries (architect)마 이환
 
Request for queries (architect)
Request for queries (architect)Request for queries (architect)
Request for queries (architect)마 이환
 
Lembayung impian sdn bhd
Lembayung impian sdn bhdLembayung impian sdn bhd
Lembayung impian sdn bhd마 이환
 
Software application:appendices
Software application:appendicesSoftware application:appendices
Software application:appendices마 이환
 
Software application:assignment
Software application:assignmentSoftware application:assignment
Software application:assignment마 이환
 
Yam yih hwan pp1 assignment aug 14
Yam yih hwan   pp1 assignment aug 14Yam yih hwan   pp1 assignment aug 14
Yam yih hwan pp1 assignment aug 14마 이환
 

More from 마 이환 (20)

Measurement V
Measurement VMeasurement V
Measurement V
 
Research Methodology:Literature Review (Chapter 2)
Research Methodology:Literature Review (Chapter 2)Research Methodology:Literature Review (Chapter 2)
Research Methodology:Literature Review (Chapter 2)
 
Research Methodology:Introduction (Chapter 1)
Research Methodology:Introduction (Chapter 1)Research Methodology:Introduction (Chapter 1)
Research Methodology:Introduction (Chapter 1)
 
Sustainable Housing Development
Sustainable Housing DevelopmentSustainable Housing Development
Sustainable Housing Development
 
Assignment:Major Water Issue (revised)
Assignment:Major Water Issue (revised)Assignment:Major Water Issue (revised)
Assignment:Major Water Issue (revised)
 
Chapter 10a Insurance:Contractor's Indemnity to Employer
Chapter 10a   Insurance:Contractor's Indemnity to EmployerChapter 10a   Insurance:Contractor's Indemnity to Employer
Chapter 10a Insurance:Contractor's Indemnity to Employer
 
Professional Practice 2: Group Assignment
Professional Practice 2: Group AssignmentProfessional Practice 2: Group Assignment
Professional Practice 2: Group Assignment
 
Financial Management:Presentation Slides
Financial Management:Presentation SlidesFinancial Management:Presentation Slides
Financial Management:Presentation Slides
 
Financial Report:Comments & Evaluations
Financial Report:Comments & EvaluationsFinancial Report:Comments & Evaluations
Financial Report:Comments & Evaluations
 
Financial Report:Cash Budget, Income Statement & Balance Sheet
Financial Report:Cash Budget, Income Statement & Balance SheetFinancial Report:Cash Budget, Income Statement & Balance Sheet
Financial Report:Cash Budget, Income Statement & Balance Sheet
 
Building Economics:Tender Report
Building Economics:Tender ReportBuilding Economics:Tender Report
Building Economics:Tender Report
 
Building Economics:Individual Assessment
Building Economics:Individual AssessmentBuilding Economics:Individual Assessment
Building Economics:Individual Assessment
 
Schedule of agreed datelines
Schedule of agreed datelinesSchedule of agreed datelines
Schedule of agreed datelines
 
Reply for queries (architect)
Reply for queries (architect)Reply for queries (architect)
Reply for queries (architect)
 
Request for queries (architect)
Request for queries (architect)Request for queries (architect)
Request for queries (architect)
 
Internal memo
Internal memoInternal memo
Internal memo
 
Lembayung impian sdn bhd
Lembayung impian sdn bhdLembayung impian sdn bhd
Lembayung impian sdn bhd
 
Software application:appendices
Software application:appendicesSoftware application:appendices
Software application:appendices
 
Software application:assignment
Software application:assignmentSoftware application:assignment
Software application:assignment
 
Yam yih hwan pp1 assignment aug 14
Yam yih hwan   pp1 assignment aug 14Yam yih hwan   pp1 assignment aug 14
Yam yih hwan pp1 assignment aug 14
 

Measurement 4:presentation slides

  • 1. Tender Documentation Name: Yam Yih Hwan Wong Ha Shiong Low Rong Tzuoo Ng Jun Keat Harvey Yap Zhu Guang
  • 2. Project Details  CADANGAN PEMAJUAN PERUMAHAN YANG MENGANDUNGI: • 21 UNIT RUMAH TERES 1½ TINGKAT (RT1) • 46 UNIT RUMAH TERES 1½ TINGKAT (RT)  DI ATAS LOT ASAL 3815, JALAN SEKOLAH, KG. BATU 10, KEBUN BAHRU, 42500 TELOK PANGLIMA GARANG, DAERAH KUALA LANGAT, SELANGOR DARUL EHSAN.  Private Sector Tendering  PAM 2006 Standard Form
  • 3. Architect & Engineer 1. Architect Details on (K.E.Guay Architect) 2. Engineer (FLIP Consultancy)
  • 4. Purpose of Tender Documents  Tender documents are prepared and sent out to potential tenderers to seek tenders.  To provide guidance on how the tender documents should be completed.  To set out the legal framework and the obligations between both parties.
  • 5. Components in Tender Document 1. Cover Letter 2. Invitation to Tender 3. Form of Tender 4. Terms & Conditions 5. General Summary 6. Preliminaries 7. Preambles 8. Specifications 9. Bill of Quantities
  • 6. Declaration of non-collusion  To prevent corruption in the tender process:-  To proof that they have not colluded with any other party to fix or adjust the tender price during the preparation of tender.
  • 7. Form of Tender  A form of tender covered the documents prepared by the Client and signed by the tenderer:-  to indicate that they understand the tender and accept the various terms and conditions of the contract, and other requirements of participating in the tender.
  • 8. Conditions of Contract  Sets out the contractual terms that will be used:-  Information on your rights and obligations  Information on the Government's rights and obligations
  • 9. Instructions to Tenderer  To explain some rules you need to follow while preparing the tender:-  Inform you how to submit your tender and alerts you to some things to be aware of.  If you do not follow the rules set out, there is a risk your tender will be rejected.
  • 10. Conditions of Tendering  Tenders shall be submitted in writing on the forms provided.  The condition that need to be complied with by the tenderer in the submission of tender.  Any supplementary documents shall be signed and dated.
  • 11. General Summary of Tender  Collection of all the proceed of bills of all sections of the projects:-  For tenderer to insert his sectional summary to arrive at a total amount which later becomes the Contract Sums.
  • 12. Preliminaries  A description of the project that allows the contractor to assess costs in required by the method and circumstances of the works before the construction start.  General Summary  Form and Type of Contracts  Facilities to be provided by the contractor
  • 13. Preamble  A preamble is an explanation of a document:-  A description of the parties to the contract.  A summary of the negotiations.  The objectives of the project.
  • 14. Specification  Provides a comprehensive description of what is required, for example:-  Functional requirements  Technical requirements  Performance requirements  Quality of Materials  Workmanship  They do not include cost, quantity or drawn information
  • 15. Bills of Quantities  As the basis of submitting the bid where all prices are entered for carrying out all works.  The bill of quantities assists tenderers in producing an estimate of:-  Construction costs for their tender, and, as it means all tenderers will be pricing the same quantities.  It also provides a fair and accurate system for tendering.  Each invited tenderer bids against the bill of quantities, stating their price for each work item.
  • 16. List of P.C. and Provisional Sums  An allowance, for the supply of work or materials to be provided by a supplier:-  This allowance exclude any of the profit mark up or attendance.  Inserted into tender documents for a specific element of the works that is not yet defined in enough detail.
  • 17. Drawings  List of drawings prepare by the Architect, Engineers and etc.  These are clear and concise detailed documents about the construction site, path construction and any related feature works.  Showing the allocation on each and every particular scope of works and its location.
  • 18. Schedule of Work/Finishes  Schedules simply list the work required.  Any information about quality should be provided by reference to:-  Specifications  Information about location  Information about size  A detail finishes for the whole building.
  • 19. Daywork rates  Contractor is paid for specifically instructed work on the basis of the cost of:-  Labour  Materials  Plant  Machineries  Along with a mark up for overheads and profit.  Generally used when work cannot be priced in the normal way.
  • 20. Bank Guarantee Form  A guarantee from the bank ensuring that the liabilities of a debtor will be met.  In other words, if the debtor fails to settle a debt, the bank will cover it.