SlideShare a Scribd company logo
1 of 21
Download to read offline
PROPOSAL ON THE BEST PROCUREMENT
METHOD, TENDERING METHOD and CONTRACT
ARRANGEMENT
[ QSB 60604 PROFESSIONAL PRACTICE 1 ]
Group Members:
KO BOU SIM (0325271)
KONG YE XIANG (0323886)
LAU MAO HUA (0320249)
LEE KAILYN (0320273)
LEE SHZE HWA (0320053)
Introduction
★ Development of a RM600 Million Hotel and Shopping Complex in the center of the
Golden Triangle, Kuala Lumpur
★ Meet client’s satisfaction
★ Fit client’s requirement
★ Ensure project’s successfulness
Proposed Procurement Method :
Management
Contracting
Procurement
Method
Management Contracting Procurement Method
★ Both design and construction process proceed in parallel.
★ Shorten the overall construction time.
★ Involvement of Management Contactor (MC) in the early design stage.
★ Responsibility of MC :
- Manage all the works package contractors.
- Coordinate all the construction activities.
- Act as advisor to improve the constructability of the design.
Management Contracting Procurement Method
Recommendation of Procurement Method
Time saving
★ The design and construction process overlapped.
★ Plan the work in sequence to allow the commencement of construction work while the building
still designing.
Flexibility in design
★ Can be effective to the uncertainty of project requirement.
★ Able to cope with any variation of the design.
Recommendation of Procurement Method
Better cost management
★ MC required to submit a contract cost plan based on contract prime cost of work packages at the
beginning stage.
★ Enable MC to monitor and control the cost against the actual prime cost .
Competitive price
★ Competition between the package subcontractor arise.
★ Able to obtain a cheaper price from several work package contractors.
Disadvantages of Management Contracting Method
★ Greater variation.
★ Uncertainty of final cost until the last work package has been signed.
★ Require an experienced and capable MC to manage all the work package
constructors.
Proposed Tendering Process :
Two-Stage
Selective
Tendering
★ Initial stage : pre-qualification
★ Second stage : negotiation between employer and contractor
★ Reasonably transparent.
★ Able to get rid of non-performing contractors.
Recommendation : Two-stage Selection tender
Advantages
★ Contractor’s knowledge of their previous experience on the similar scheme is available at the
early stage.
★ Relationship between contractor and their chosen team is more likely to have a better
understanding of the requirement through shared knowledge and good communication.
★ Eliminate the risks during implementation of the project.
★ Better monitoring and programming on costing process and pre construction design
development.
★ Lead to the introduce of value engineering in the project and also provide a better
understanding of financial commitment.
★ Cost certainty is improved and the risk to the employer is reduced.
Advantages
★ Contractor is able to suggest on practical issues and buildability issues at an earlier stage.
★ To identify and resolve any hurdles may occur during construction.
★ Enables client to have a clearer mind on the sustainability issues and environmental
restriction.
Advantages
Contract Arrangement :
Type of Contract
TYPE OF CONTRACT - COST PLUS FIXED FEE
★ Fixed service fee is derived from Contract Cost plan (estimated prime cost for various
subcontractor ) .
★ Works is awarded to work packages contractor on lump sum basis.
★ Estimated prime cost used to monitor against actual prime cost upon award.
★ Total Contract Sum= Prime cost of work packages + Fixed services fee for MC.
TYPE OF CONTRACT - COST PLUS FIXED FEE
BENEFIT FOR CLIENT
★ Service fee is fixed and it does not fluctuate with the actual cost.
★ Motivate to carry out work in faster way which shorten the completion time.
BENEFIT FOR CONTRACTOR
★ Conduct the work in diligent manner.
Contract Arrangement :
Form of Contract
FORM OF CONTRACT - PAM 2006 (WITHOUT QUANTITIES)
★ Amended provision to suits project setting-MC procurement.
Table above shows the organization chart of Management Contracting procurement method.
FORM OF CONTRACT - PAM 2006 (WITHOUT QUANTITIES)
★ Pre-tender stage: MC + Consultant team - Buildability and Feasibility of design.
★ Post-tender stage: Consultant team’s obligation transfer to MC - issuance of certificate
★ Example: Interim claim, Valuation of Variations.
THANK YOU

More Related Content

What's hot

PP1 presentation slide.
PP1 presentation slide.PP1 presentation slide.
PP1 presentation slide.lucaschinsheng
 
A Report on Procurement Strategies - PP1
A Report on Procurement Strategies - PP1 A Report on Procurement Strategies - PP1
A Report on Procurement Strategies - PP1 Pang Khai Shuen
 
Professional practice-1-presentation
Professional practice-1-presentationProfessional practice-1-presentation
Professional practice-1-presentationTimun Loh
 
Considerations in Procurement Strategy - 2014 Olswang Construction Law Confer...
Considerations in Procurement Strategy - 2014 Olswang Construction Law Confer...Considerations in Procurement Strategy - 2014 Olswang Construction Law Confer...
Considerations in Procurement Strategy - 2014 Olswang Construction Law Confer...Francis Ho
 
Persons involved in tenders and contract
Persons involved in tenders and contractPersons involved in tenders and contract
Persons involved in tenders and contractshiva prakash
 
Using Two-Stage Tendering Effectively
Using Two-Stage Tendering EffectivelyUsing Two-Stage Tendering Effectively
Using Two-Stage Tendering EffectivelyFrancis Ho
 
Estimating and Tendering methods for Construction Work
Estimating and Tendering methods for Construction WorkEstimating and Tendering methods for Construction Work
Estimating and Tendering methods for Construction WorkDaniel Ross
 
Professional Practice 1 Tutorial 3
Professional Practice 1 Tutorial 3Professional Practice 1 Tutorial 3
Professional Practice 1 Tutorial 3ashleyyeap
 
Assignment - Management Contracting
Assignment - Management ContractingAssignment - Management Contracting
Assignment - Management ContractingKai Yun Pang
 
Tendering in Construction
Tendering in ConstructionTendering in Construction
Tendering in Constructionshillier38
 
Single stage design and build method & construction project management
Single stage design and build method & construction project managementSingle stage design and build method & construction project management
Single stage design and build method & construction project managementJohn Constance
 
Professional Practice 1
Professional Practice 1Professional Practice 1
Professional Practice 1Lee Pei Gie
 
Construction industry and estimating
Construction industry and estimatingConstruction industry and estimating
Construction industry and estimatingalanchong88
 
Assignment - Report
Assignment - ReportAssignment - Report
Assignment - ReportKai Yun Pang
 
Measure And Pay Contract
Measure And Pay Contract Measure And Pay Contract
Measure And Pay Contract Venuri Lakshani
 

What's hot (19)

PP1 presentation slide.
PP1 presentation slide.PP1 presentation slide.
PP1 presentation slide.
 
A Report on Procurement Strategies - PP1
A Report on Procurement Strategies - PP1 A Report on Procurement Strategies - PP1
A Report on Procurement Strategies - PP1
 
Professional practice-1-presentation
Professional practice-1-presentationProfessional practice-1-presentation
Professional practice-1-presentation
 
Considerations in Procurement Strategy - 2014 Olswang Construction Law Confer...
Considerations in Procurement Strategy - 2014 Olswang Construction Law Confer...Considerations in Procurement Strategy - 2014 Olswang Construction Law Confer...
Considerations in Procurement Strategy - 2014 Olswang Construction Law Confer...
 
Pp1 group assignment
Pp1 group assignmentPp1 group assignment
Pp1 group assignment
 
Persons involved in tenders and contract
Persons involved in tenders and contractPersons involved in tenders and contract
Persons involved in tenders and contract
 
Using Two-Stage Tendering Effectively
Using Two-Stage Tendering EffectivelyUsing Two-Stage Tendering Effectively
Using Two-Stage Tendering Effectively
 
Estimating and Tendering methods for Construction Work
Estimating and Tendering methods for Construction WorkEstimating and Tendering methods for Construction Work
Estimating and Tendering methods for Construction Work
 
Pp1 seminar
Pp1 seminarPp1 seminar
Pp1 seminar
 
Professional Practice 1 Tutorial 3
Professional Practice 1 Tutorial 3Professional Practice 1 Tutorial 3
Professional Practice 1 Tutorial 3
 
Assignment - Management Contracting
Assignment - Management ContractingAssignment - Management Contracting
Assignment - Management Contracting
 
Tendering in Construction
Tendering in ConstructionTendering in Construction
Tendering in Construction
 
Procurement Methods
Procurement MethodsProcurement Methods
Procurement Methods
 
Single stage design and build method & construction project management
Single stage design and build method & construction project managementSingle stage design and build method & construction project management
Single stage design and build method & construction project management
 
Professional Practice 1
Professional Practice 1Professional Practice 1
Professional Practice 1
 
Changes in construction
Changes in constructionChanges in construction
Changes in construction
 
Construction industry and estimating
Construction industry and estimatingConstruction industry and estimating
Construction industry and estimating
 
Assignment - Report
Assignment - ReportAssignment - Report
Assignment - Report
 
Measure And Pay Contract
Measure And Pay Contract Measure And Pay Contract
Measure And Pay Contract
 

Similar to PP1 presentation

Professional practice 1 report
Professional practice 1 reportProfessional practice 1 report
Professional practice 1 reportNgo Jia Haur
 
Lecture 4 - selection of contract forms
Lecture 4 - selection of contract formsLecture 4 - selection of contract forms
Lecture 4 - selection of contract formskohwenqi
 
Contract Management - Contracts Types and Payment Structure
Contract Management - Contracts Types and Payment StructureContract Management - Contracts Types and Payment Structure
Contract Management - Contracts Types and Payment StructureHASMANIRA
 
Professional practice 1 (1)
Professional practice 1 (1)Professional practice 1 (1)
Professional practice 1 (1)tfkc1212
 
Professional practice 1
Professional practice 1Professional practice 1
Professional practice 1tfkc1212
 
Professional Practice 1
Professional Practice 1Professional Practice 1
Professional Practice 1Lin Hui
 
Professional Practice I Assignment Slides
Professional Practice I Assignment SlidesProfessional Practice I Assignment Slides
Professional Practice I Assignment Slidesashleyyeap
 
Pp1 assignment
Pp1 assignmentPp1 assignment
Pp1 assignmentLwj Welson
 
Pp1 assignment
Pp1 assignmentPp1 assignment
Pp1 assignmentLwj Welson
 
Professional Practice
Professional PracticeProfessional Practice
Professional Practiceseenyeeyong
 
Professional Practice I Assignment
Professional Practice I AssignmentProfessional Practice I Assignment
Professional Practice I Assignmentashleyyeap
 
Procurement Strategies: A Seminar
Procurement Strategies: A SeminarProcurement Strategies: A Seminar
Procurement Strategies: A SeminarPang Khai Shuen
 
PP1 - Presentation Slides
PP1 - Presentation Slides PP1 - Presentation Slides
PP1 - Presentation Slides Pang Khai Shuen
 
4. offer tendering - site
4. offer   tendering - site4. offer   tendering - site
4. offer tendering - siteAbdulaziz Kaya
 
Professional practice 1 (QS)
Professional practice 1 (QS)Professional practice 1 (QS)
Professional practice 1 (QS)Hasif Alias
 
Professional Practice 1 Proposal Report
Professional Practice 1 Proposal ReportProfessional Practice 1 Proposal Report
Professional Practice 1 Proposal ReportArissa Loh
 

Similar to PP1 presentation (20)

Professional practice 1 report
Professional practice 1 reportProfessional practice 1 report
Professional practice 1 report
 
Lecture 4 - selection of contract forms
Lecture 4 - selection of contract formsLecture 4 - selection of contract forms
Lecture 4 - selection of contract forms
 
TOPIC2.pdf
TOPIC2.pdfTOPIC2.pdf
TOPIC2.pdf
 
Contract Management - Contracts Types and Payment Structure
Contract Management - Contracts Types and Payment StructureContract Management - Contracts Types and Payment Structure
Contract Management - Contracts Types and Payment Structure
 
Professional practice 1 (1)
Professional practice 1 (1)Professional practice 1 (1)
Professional practice 1 (1)
 
Professional practice 1
Professional practice 1Professional practice 1
Professional practice 1
 
Professional Practice 1
Professional Practice 1Professional Practice 1
Professional Practice 1
 
Professional Practice I Assignment Slides
Professional Practice I Assignment SlidesProfessional Practice I Assignment Slides
Professional Practice I Assignment Slides
 
TOPIC1.pdf
TOPIC1.pdfTOPIC1.pdf
TOPIC1.pdf
 
Pp1 assignment
Pp1 assignmentPp1 assignment
Pp1 assignment
 
Pp1 assignment
Pp1 assignmentPp1 assignment
Pp1 assignment
 
Professional Practice
Professional PracticeProfessional Practice
Professional Practice
 
Professional Practice I Assignment
Professional Practice I AssignmentProfessional Practice I Assignment
Professional Practice I Assignment
 
Procurement Strategies: A Seminar
Procurement Strategies: A SeminarProcurement Strategies: A Seminar
Procurement Strategies: A Seminar
 
PP1 - Presentation Slides
PP1 - Presentation Slides PP1 - Presentation Slides
PP1 - Presentation Slides
 
4. offer tendering - site
4. offer   tendering - site4. offer   tendering - site
4. offer tendering - site
 
Professional practice 1 (QS)
Professional practice 1 (QS)Professional practice 1 (QS)
Professional practice 1 (QS)
 
Professional Practice 1 Proposal Report
Professional Practice 1 Proposal ReportProfessional Practice 1 Proposal Report
Professional Practice 1 Proposal Report
 
Time cost trade off with primavera (real case)
Time cost trade off with primavera (real case)Time cost trade off with primavera (real case)
Time cost trade off with primavera (real case)
 
TURNKEY PROJECT.pptx
TURNKEY PROJECT.pptxTURNKEY PROJECT.pptx
TURNKEY PROJECT.pptx
 

More from Shze Hwa Lee

Professional practice 2
Professional practice 2Professional practice 2
Professional practice 2Shze Hwa Lee
 
Be presentation slides
Be presentation slidesBe presentation slides
Be presentation slidesShze Hwa Lee
 
Be Report Finalize
Be Report FinalizeBe Report Finalize
Be Report FinalizeShze Hwa Lee
 
Fm report template
Fm report templateFm report template
Fm report templateShze Hwa Lee
 
Finased csi report
Finased csi reportFinased csi report
Finased csi reportShze Hwa Lee
 
Software Presentation Slides
Software Presentation SlidesSoftware Presentation Slides
Software Presentation SlidesShze Hwa Lee
 
Software Application Report
Software Application ReportSoftware Application Report
Software Application ReportShze Hwa Lee
 
Estimating presentation
Estimating presentationEstimating presentation
Estimating presentationShze Hwa Lee
 
Seminar 1 Questions
Seminar 1 QuestionsSeminar 1 Questions
Seminar 1 QuestionsShze Hwa Lee
 
Estimating presentation (question 1)
Estimating presentation (question 1)Estimating presentation (question 1)
Estimating presentation (question 1)Shze Hwa Lee
 
PP1 report group 7 (finalized)
PP1 report group 7 (finalized)PP1 report group 7 (finalized)
PP1 report group 7 (finalized)Shze Hwa Lee
 
Measurement 4 presentation
Measurement 4 presentation Measurement 4 presentation
Measurement 4 presentation Shze Hwa Lee
 
Bs 2 group assignment
Bs 2 group assignmentBs 2 group assignment
Bs 2 group assignmentShze Hwa Lee
 
People dynamic (assingment 1)
People dynamic (assingment 1) People dynamic (assingment 1)
People dynamic (assingment 1) Shze Hwa Lee
 
Safety and Health individual assignment
Safety and Health individual assignment Safety and Health individual assignment
Safety and Health individual assignment Shze Hwa Lee
 

More from Shze Hwa Lee (20)

Professional practice 2
Professional practice 2Professional practice 2
Professional practice 2
 
Pp2 p5
Pp2   p5Pp2   p5
Pp2 p5
 
Cp 24062018 2241
Cp 24062018 2241Cp 24062018 2241
Cp 24062018 2241
 
Be finalise a3
Be finalise a3Be finalise a3
Be finalise a3
 
Be presentation slides
Be presentation slidesBe presentation slides
Be presentation slides
 
Be Report Finalize
Be Report FinalizeBe Report Finalize
Be Report Finalize
 
Fm report template
Fm report templateFm report template
Fm report template
 
Csi presentation
Csi   presentationCsi   presentation
Csi presentation
 
Finased csi report
Finased csi reportFinased csi report
Finased csi report
 
Software Presentation Slides
Software Presentation SlidesSoftware Presentation Slides
Software Presentation Slides
 
Software Application Report
Software Application ReportSoftware Application Report
Software Application Report
 
Estimating presentation
Estimating presentationEstimating presentation
Estimating presentation
 
Seminar 1 Questions
Seminar 1 QuestionsSeminar 1 Questions
Seminar 1 Questions
 
Estimating presentation (question 1)
Estimating presentation (question 1)Estimating presentation (question 1)
Estimating presentation (question 1)
 
PP1 report group 7 (finalized)
PP1 report group 7 (finalized)PP1 report group 7 (finalized)
PP1 report group 7 (finalized)
 
Measurement 4 presentation
Measurement 4 presentation Measurement 4 presentation
Measurement 4 presentation
 
ECA presentation
ECA presentationECA presentation
ECA presentation
 
Bs 2 group assignment
Bs 2 group assignmentBs 2 group assignment
Bs 2 group assignment
 
People dynamic (assingment 1)
People dynamic (assingment 1) People dynamic (assingment 1)
People dynamic (assingment 1)
 
Safety and Health individual assignment
Safety and Health individual assignment Safety and Health individual assignment
Safety and Health individual assignment
 

Recently uploaded

Alper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentAlper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentInMediaRes1
 
_Math 4-Q4 Week 5.pptx Steps in Collecting Data
_Math 4-Q4 Week 5.pptx Steps in Collecting Data_Math 4-Q4 Week 5.pptx Steps in Collecting Data
_Math 4-Q4 Week 5.pptx Steps in Collecting DataJhengPantaleon
 
Hybridoma Technology ( Production , Purification , and Application )
Hybridoma Technology  ( Production , Purification , and Application  ) Hybridoma Technology  ( Production , Purification , and Application  )
Hybridoma Technology ( Production , Purification , and Application ) Sakshi Ghasle
 
Introduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher EducationIntroduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher Educationpboyjonauth
 
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTiammrhaywood
 
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17Celine George
 
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxSOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxiammrhaywood
 
Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)eniolaolutunde
 
Sanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfSanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfsanyamsingh5019
 
Class 11 Legal Studies Ch-1 Concept of State .pdf
Class 11 Legal Studies Ch-1 Concept of State .pdfClass 11 Legal Studies Ch-1 Concept of State .pdf
Class 11 Legal Studies Ch-1 Concept of State .pdfakmcokerachita
 
Science 7 - LAND and SEA BREEZE and its Characteristics
Science 7 - LAND and SEA BREEZE and its CharacteristicsScience 7 - LAND and SEA BREEZE and its Characteristics
Science 7 - LAND and SEA BREEZE and its CharacteristicsKarinaGenton
 
URLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website AppURLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website AppCeline George
 
mini mental status format.docx
mini    mental       status     format.docxmini    mental       status     format.docx
mini mental status format.docxPoojaSen20
 
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️9953056974 Low Rate Call Girls In Saket, Delhi NCR
 
Paris 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityParis 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityGeoBlogs
 
Introduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxIntroduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxpboyjonauth
 
How to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxHow to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxmanuelaromero2013
 

Recently uploaded (20)

Alper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentAlper Gobel In Media Res Media Component
Alper Gobel In Media Res Media Component
 
Staff of Color (SOC) Retention Efforts DDSD
Staff of Color (SOC) Retention Efforts DDSDStaff of Color (SOC) Retention Efforts DDSD
Staff of Color (SOC) Retention Efforts DDSD
 
_Math 4-Q4 Week 5.pptx Steps in Collecting Data
_Math 4-Q4 Week 5.pptx Steps in Collecting Data_Math 4-Q4 Week 5.pptx Steps in Collecting Data
_Math 4-Q4 Week 5.pptx Steps in Collecting Data
 
Hybridoma Technology ( Production , Purification , and Application )
Hybridoma Technology  ( Production , Purification , and Application  ) Hybridoma Technology  ( Production , Purification , and Application  )
Hybridoma Technology ( Production , Purification , and Application )
 
Introduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher EducationIntroduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher Education
 
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
 
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
 
Código Creativo y Arte de Software | Unidad 1
Código Creativo y Arte de Software | Unidad 1Código Creativo y Arte de Software | Unidad 1
Código Creativo y Arte de Software | Unidad 1
 
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxSOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
 
Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)
 
Sanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfSanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdf
 
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
 
Class 11 Legal Studies Ch-1 Concept of State .pdf
Class 11 Legal Studies Ch-1 Concept of State .pdfClass 11 Legal Studies Ch-1 Concept of State .pdf
Class 11 Legal Studies Ch-1 Concept of State .pdf
 
Science 7 - LAND and SEA BREEZE and its Characteristics
Science 7 - LAND and SEA BREEZE and its CharacteristicsScience 7 - LAND and SEA BREEZE and its Characteristics
Science 7 - LAND and SEA BREEZE and its Characteristics
 
URLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website AppURLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website App
 
mini mental status format.docx
mini    mental       status     format.docxmini    mental       status     format.docx
mini mental status format.docx
 
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
call girls in Kamla Market (DELHI) 🔝 >༒9953330565🔝 genuine Escort Service 🔝✔️✔️
 
Paris 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityParis 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activity
 
Introduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxIntroduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptx
 
How to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxHow to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptx
 

PP1 presentation

  • 1. PROPOSAL ON THE BEST PROCUREMENT METHOD, TENDERING METHOD and CONTRACT ARRANGEMENT [ QSB 60604 PROFESSIONAL PRACTICE 1 ]
  • 2. Group Members: KO BOU SIM (0325271) KONG YE XIANG (0323886) LAU MAO HUA (0320249) LEE KAILYN (0320273) LEE SHZE HWA (0320053)
  • 3. Introduction ★ Development of a RM600 Million Hotel and Shopping Complex in the center of the Golden Triangle, Kuala Lumpur ★ Meet client’s satisfaction ★ Fit client’s requirement ★ Ensure project’s successfulness
  • 4. Proposed Procurement Method : Management Contracting Procurement Method
  • 5. Management Contracting Procurement Method ★ Both design and construction process proceed in parallel. ★ Shorten the overall construction time. ★ Involvement of Management Contactor (MC) in the early design stage. ★ Responsibility of MC : - Manage all the works package contractors. - Coordinate all the construction activities. - Act as advisor to improve the constructability of the design.
  • 7. Recommendation of Procurement Method Time saving ★ The design and construction process overlapped. ★ Plan the work in sequence to allow the commencement of construction work while the building still designing. Flexibility in design ★ Can be effective to the uncertainty of project requirement. ★ Able to cope with any variation of the design.
  • 8. Recommendation of Procurement Method Better cost management ★ MC required to submit a contract cost plan based on contract prime cost of work packages at the beginning stage. ★ Enable MC to monitor and control the cost against the actual prime cost . Competitive price ★ Competition between the package subcontractor arise. ★ Able to obtain a cheaper price from several work package contractors.
  • 9. Disadvantages of Management Contracting Method ★ Greater variation. ★ Uncertainty of final cost until the last work package has been signed. ★ Require an experienced and capable MC to manage all the work package constructors.
  • 10. Proposed Tendering Process : Two-Stage Selective Tendering
  • 11. ★ Initial stage : pre-qualification ★ Second stage : negotiation between employer and contractor ★ Reasonably transparent. ★ Able to get rid of non-performing contractors. Recommendation : Two-stage Selection tender
  • 12. Advantages ★ Contractor’s knowledge of their previous experience on the similar scheme is available at the early stage. ★ Relationship between contractor and their chosen team is more likely to have a better understanding of the requirement through shared knowledge and good communication. ★ Eliminate the risks during implementation of the project.
  • 13. ★ Better monitoring and programming on costing process and pre construction design development. ★ Lead to the introduce of value engineering in the project and also provide a better understanding of financial commitment. ★ Cost certainty is improved and the risk to the employer is reduced. Advantages
  • 14. ★ Contractor is able to suggest on practical issues and buildability issues at an earlier stage. ★ To identify and resolve any hurdles may occur during construction. ★ Enables client to have a clearer mind on the sustainability issues and environmental restriction. Advantages
  • 16. TYPE OF CONTRACT - COST PLUS FIXED FEE ★ Fixed service fee is derived from Contract Cost plan (estimated prime cost for various subcontractor ) . ★ Works is awarded to work packages contractor on lump sum basis. ★ Estimated prime cost used to monitor against actual prime cost upon award. ★ Total Contract Sum= Prime cost of work packages + Fixed services fee for MC.
  • 17. TYPE OF CONTRACT - COST PLUS FIXED FEE BENEFIT FOR CLIENT ★ Service fee is fixed and it does not fluctuate with the actual cost. ★ Motivate to carry out work in faster way which shorten the completion time. BENEFIT FOR CONTRACTOR ★ Conduct the work in diligent manner.
  • 19. FORM OF CONTRACT - PAM 2006 (WITHOUT QUANTITIES) ★ Amended provision to suits project setting-MC procurement. Table above shows the organization chart of Management Contracting procurement method.
  • 20. FORM OF CONTRACT - PAM 2006 (WITHOUT QUANTITIES) ★ Pre-tender stage: MC + Consultant team - Buildability and Feasibility of design. ★ Post-tender stage: Consultant team’s obligation transfer to MC - issuance of certificate ★ Example: Interim claim, Valuation of Variations.