SlideShare a Scribd company logo
1 of 23
Professional
Practice 1
Group Members:
Nicole Thain Huey Wei
Phon Kit Poi
Pui Chun Shian
Ranee Leow Kai Yen
Satesh Raj A/L P. Devaraj
Sew Yue Ling
Soo Ping Zheng
Soo Yon Li
Tam Zhao Wei
Tan Jia San
Farah Aida
TRADITIONAL
PROCUREMENT
WHY TRADITIONAL PROCUREMENT ?
Completion on time (5 years)
Variation in design
Minimum variation in Contract Sum
Deal with minimum parties
Full control of design
1. Brief
Stage
2. Design
Stage
3. Tendering
(Competition) Stage
4. Construction
Stage
Completion on time (5 years)✔
Variation in design
Minimum variation in Contract Sum
✔
✔
↓ Cost Risk
↓ Design Risk
Deal with minimum parties
Full control of design
✔
✔
CONCLUSION
- ↑ Time frame
- Construction cost certainty
- ↓ Price variation
- Partial / Full control of
design
- ↓ Design Variation
- ↓ Parties to deal with
TWO STAGE SELECTIVE
TENDERING
WHY TWO STAGE SELECTIVE
TENDERING ?
Reasonably transparent
Eliminate non-performing contractors
TWO STAGE SELECTIVE TENDERING
Open to only
selected numbers
of “Pre-qualified”
contractors
Reduce tender
cost, saves time &
resources
Low risk but high
reward
Lower risk of
buildability issue
Reasonably transparent
✔
STAGE 1
❏ An advertisement will be placed
on major newspaper/social
platform
❏ Interested tenderers will submit
their companies particulars in a
“Pre-qualification Form”
Eliminate non-performing contractors
✔
STAGE 2
❏ A “Pre-qualification” form will be
attached with the advertisement
❏ Evaluation Stage : based on the
“Pre-qualification Form”
TWO-STAGE SELECTIVE TENDERING
TIMELINE
Invitation To Tender
● Advertisement
● Pre-Qualification
Form
Pre-Qualification Stage
● Based on experience,
financial capabilities
and competencies.
Collection of Tender
● Charged with
documentation fees
Tender Closing
● Submit into a “tender
box”
● QS submit Pre-Tender
Estimate
Tender Opening
● Tender figures are
recorded and jointly
verified
Tender Evaluation
● Check for major
arithmetical errors
● Prepare tender report
● Call lowest 3 tenderers for
tender interview
Tender Interview
● Queried on any issues
● May be requested to
submit a revised
tender
Tender Award
● Prepare and issue
Letter of Award
● Return within 14
days
CONTRACT
ARRANGEMENT
LUMP SUM CONTRACT
WHY LUMP SUM CONTRACT?
● Construction designs are completed > Requested work is well-defined
● Minimize variations during construction > minimize variation to price
as well
● Reduce owner risks
● Contractor has greater control over profit expectations
LIQUIDATED ASCERTAINED DAMAGES (LAD)
● Client’s Requirement : Imposed Liquidated Damages of RM
250,000.00 a day.
Ensure project to complete on time
✔
Include early completion
compensation for the
contractor
Early completion might
produce higher savings
for the project owner
LUMP SUM CONTRACT
PAM CONTRACT 2006 (WITH QUANTITIES)
● Home base form : Risks are known to be local industry
● Intended to be used as a building contractor and not as civil
engineering contract
● It is estimated that 90% of the building contracts in the private sector are
based on the PAM Contract 2006
Functions of PAM Contract 2006 (With Quantities)
● Evidences legal relationship between parties in the contract
● Provides the administrative procedure
● Incorporate all special requirements and circumstances of a project
● Expresses the obligation of the parties
● Set out reasonable clarity of the project
PAM CONTRACT 2006 (WITH QUANTITIES)
Clause 6.1 - Standards of works, materials, goods and workmanship
● Materials, goods and workmanship shall be according to the standards
described in the contract documents
● If there is any discrepancy, the contractor can instruct sub-contractors to
demolish and rectify the defect works
Clause 15.4 - Schedule of defects
● Sub-contractor must provide defect liability period after completion of works
and correct the defects within 28 Days from receipt of schedule of defects
from contractor.
QUALITY
HEALTH & SAFETY
OSHA (Occupational Safety & Health Administration)
- The Occupational Safety & Health Act 1970
- To keep their work environment safe
- < 10 workers X file injury / illness report
- Compulsory training to the workers as a guarantee to
the employer
1. Appoint a Safety
Advisor
HOW TO ENHANCE HEALTH & SAFETY ?
Essential to give professional
advices.
OSHA Clause 8.1
- Training & Competency
2. Proposed Site
Management Plan
(SMP)
Compliance to Occupational Safety
and Health in Construction Industry
(Management)
- Ensure a safer working
environment
3. Allow Separate
Specification for
Health & Safety
The Health & Safety
Specification may include any
details regarding health and
safety matters
THANK YOU
THANK YOU

More Related Content

What's hot

Types of Contract in Construction Management
Types of Contract in Construction ManagementTypes of Contract in Construction Management
Types of Contract in Construction ManagementShahin MB
 
PP1 assignment presentation slides
PP1 assignment presentation slidesPP1 assignment presentation slides
PP1 assignment presentation slidesDoreen Yeo
 
Measurement 4 presentation
Measurement 4 presentation Measurement 4 presentation
Measurement 4 presentation Shze Hwa Lee
 
A Report on Procurement Strategies - PP1
A Report on Procurement Strategies - PP1 A Report on Procurement Strategies - PP1
A Report on Procurement Strategies - PP1 Pang Khai Shuen
 
Construction contracts docuements_08092008
Construction contracts docuements_08092008Construction contracts docuements_08092008
Construction contracts docuements_08092008AYM1979
 
Estimating and Tendering methods for Construction Work
Estimating and Tendering methods for Construction WorkEstimating and Tendering methods for Construction Work
Estimating and Tendering methods for Construction WorkDaniel Ross
 
Using Two-Stage Tendering Effectively
Using Two-Stage Tendering EffectivelyUsing Two-Stage Tendering Effectively
Using Two-Stage Tendering EffectivelyFrancis Ho
 
Persons involved in tenders and contract
Persons involved in tenders and contractPersons involved in tenders and contract
Persons involved in tenders and contractshiva prakash
 
Construction Documents
Construction DocumentsConstruction Documents
Construction DocumentsAllan Berry
 
Single stage design and build method & construction project management
Single stage design and build method & construction project managementSingle stage design and build method & construction project management
Single stage design and build method & construction project managementJohn Constance
 
Pp1 presentation 2
Pp1 presentation 2Pp1 presentation 2
Pp1 presentation 2shensin1015
 
Traditional procurement method
Traditional procurement methodTraditional procurement method
Traditional procurement methodhiewliming
 
Contract Specifications, Bidding and Contractor Selection for Capital Replace...
Contract Specifications, Bidding and Contractor Selection for Capital Replace...Contract Specifications, Bidding and Contractor Selection for Capital Replace...
Contract Specifications, Bidding and Contractor Selection for Capital Replace...Kipcon Inc.
 

What's hot (18)

Tender
TenderTender
Tender
 
Pp1 group assignment
Pp1 group assignmentPp1 group assignment
Pp1 group assignment
 
Types of Contract in Construction Management
Types of Contract in Construction ManagementTypes of Contract in Construction Management
Types of Contract in Construction Management
 
PP1 assignment presentation slides
PP1 assignment presentation slidesPP1 assignment presentation slides
PP1 assignment presentation slides
 
Measurement 4 presentation
Measurement 4 presentation Measurement 4 presentation
Measurement 4 presentation
 
A Report on Procurement Strategies - PP1
A Report on Procurement Strategies - PP1 A Report on Procurement Strategies - PP1
A Report on Procurement Strategies - PP1
 
Construction contracts docuements_08092008
Construction contracts docuements_08092008Construction contracts docuements_08092008
Construction contracts docuements_08092008
 
Estimating and Tendering methods for Construction Work
Estimating and Tendering methods for Construction WorkEstimating and Tendering methods for Construction Work
Estimating and Tendering methods for Construction Work
 
Using Two-Stage Tendering Effectively
Using Two-Stage Tendering EffectivelyUsing Two-Stage Tendering Effectively
Using Two-Stage Tendering Effectively
 
Persons involved in tenders and contract
Persons involved in tenders and contractPersons involved in tenders and contract
Persons involved in tenders and contract
 
Chapter 2- Contract Management
Chapter 2- Contract ManagementChapter 2- Contract Management
Chapter 2- Contract Management
 
Construction Documents
Construction DocumentsConstruction Documents
Construction Documents
 
Pp1 final
Pp1 finalPp1 final
Pp1 final
 
Single stage design and build method & construction project management
Single stage design and build method & construction project managementSingle stage design and build method & construction project management
Single stage design and build method & construction project management
 
PP1 presentation
PP1 presentationPP1 presentation
PP1 presentation
 
Pp1 presentation 2
Pp1 presentation 2Pp1 presentation 2
Pp1 presentation 2
 
Traditional procurement method
Traditional procurement methodTraditional procurement method
Traditional procurement method
 
Contract Specifications, Bidding and Contractor Selection for Capital Replace...
Contract Specifications, Bidding and Contractor Selection for Capital Replace...Contract Specifications, Bidding and Contractor Selection for Capital Replace...
Contract Specifications, Bidding and Contractor Selection for Capital Replace...
 

Similar to Mega project

4. offer tendering - site
4. offer   tendering - site4. offer   tendering - site
4. offer tendering - siteAbdulaziz Kaya
 
Professional practice 1 report
Professional practice 1 reportProfessional practice 1 report
Professional practice 1 reportNgo Jia Haur
 
Assignment - Management Contracting
Assignment - Management ContractingAssignment - Management Contracting
Assignment - Management ContractingKai Yun Pang
 
Building Construction 4. offer tendering - site
Building Construction 4. offer   tendering - siteBuilding Construction 4. offer   tendering - site
Building Construction 4. offer tendering - siteHamdija Velagic
 
Professional Practice 1
Professional Practice 1Professional Practice 1
Professional Practice 1Lin Hui
 
Professional Practice I Assignment Slides
Professional Practice I Assignment SlidesProfessional Practice I Assignment Slides
Professional Practice I Assignment Slidesashleyyeap
 
PP1 presentation
PP1 presentationPP1 presentation
PP1 presentationKailyn Lee
 
Procurement Strategies: A Seminar
Procurement Strategies: A SeminarProcurement Strategies: A Seminar
Procurement Strategies: A SeminarPang Khai Shuen
 
A.Sanchez_Part2_Planning and Scheduling Construction Projects_The Schedule As...
A.Sanchez_Part2_Planning and Scheduling Construction Projects_The Schedule As...A.Sanchez_Part2_Planning and Scheduling Construction Projects_The Schedule As...
A.Sanchez_Part2_Planning and Scheduling Construction Projects_The Schedule As...Alberto Sanchez
 
Assignment - Management Contracting (Presentation Slide)
Assignment - Management Contracting (Presentation Slide)Assignment - Management Contracting (Presentation Slide)
Assignment - Management Contracting (Presentation Slide)Kai Yun Pang
 
Project managment (pm) solved assignments summer 2015
Project managment  (pm) solved assignments summer 2015Project managment  (pm) solved assignments summer 2015
Project managment (pm) solved assignments summer 2015smumbahelp
 
Change management and dispute resolution
Change management and dispute resolutionChange management and dispute resolution
Change management and dispute resolutionAlex Iskandar
 
Professional Practice 1 Tutorial 3
Professional Practice 1 Tutorial 3Professional Practice 1 Tutorial 3
Professional Practice 1 Tutorial 3ashleyyeap
 
Pp1 assignment
Pp1 assignmentPp1 assignment
Pp1 assignmentLwj Welson
 
Pp1 assignment
Pp1 assignmentPp1 assignment
Pp1 assignmentLwj Welson
 

Similar to Mega project (20)

4. offer tendering - site
4. offer   tendering - site4. offer   tendering - site
4. offer tendering - site
 
Professional practice 1 report
Professional practice 1 reportProfessional practice 1 report
Professional practice 1 report
 
Assignment - Management Contracting
Assignment - Management ContractingAssignment - Management Contracting
Assignment - Management Contracting
 
Building Construction 4. offer tendering - site
Building Construction 4. offer   tendering - siteBuilding Construction 4. offer   tendering - site
Building Construction 4. offer tendering - site
 
Professional Practice 1
Professional Practice 1Professional Practice 1
Professional Practice 1
 
Professional Practice I Assignment Slides
Professional Practice I Assignment SlidesProfessional Practice I Assignment Slides
Professional Practice I Assignment Slides
 
PP1 presentation
PP1 presentationPP1 presentation
PP1 presentation
 
Procurement Strategies: A Seminar
Procurement Strategies: A SeminarProcurement Strategies: A Seminar
Procurement Strategies: A Seminar
 
A.Sanchez_Part2_Planning and Scheduling Construction Projects_The Schedule As...
A.Sanchez_Part2_Planning and Scheduling Construction Projects_The Schedule As...A.Sanchez_Part2_Planning and Scheduling Construction Projects_The Schedule As...
A.Sanchez_Part2_Planning and Scheduling Construction Projects_The Schedule As...
 
Assignment - Management Contracting (Presentation Slide)
Assignment - Management Contracting (Presentation Slide)Assignment - Management Contracting (Presentation Slide)
Assignment - Management Contracting (Presentation Slide)
 
Project managment (pm) solved assignments summer 2015
Project managment  (pm) solved assignments summer 2015Project managment  (pm) solved assignments summer 2015
Project managment (pm) solved assignments summer 2015
 
Questions in notes
Questions in notesQuestions in notes
Questions in notes
 
Questions in notes
Questions in notesQuestions in notes
Questions in notes
 
Questions in notes
Questions in notesQuestions in notes
Questions in notes
 
Time cost trade off with primavera (real case)
Time cost trade off with primavera (real case)Time cost trade off with primavera (real case)
Time cost trade off with primavera (real case)
 
Pre Bid Risk Assessment
Pre Bid Risk AssessmentPre Bid Risk Assessment
Pre Bid Risk Assessment
 
Change management and dispute resolution
Change management and dispute resolutionChange management and dispute resolution
Change management and dispute resolution
 
Professional Practice 1 Tutorial 3
Professional Practice 1 Tutorial 3Professional Practice 1 Tutorial 3
Professional Practice 1 Tutorial 3
 
Pp1 assignment
Pp1 assignmentPp1 assignment
Pp1 assignment
 
Pp1 assignment
Pp1 assignmentPp1 assignment
Pp1 assignment
 

More from Farah Sham

Conference Paper
Conference PaperConference Paper
Conference PaperFarah Sham
 
My Community Service Journal
My Community Service JournalMy Community Service Journal
My Community Service JournalFarah Sham
 
Orphanage Community Service Initiative
Orphanage Community Service InitiativeOrphanage Community Service Initiative
Orphanage Community Service InitiativeFarah Sham
 
Infographic Poster Report
Infographic Poster ReportInfographic Poster Report
Infographic Poster ReportFarah Sham
 
Hubungan Etnik Magazine Masyarakat India di Brickfiields
Hubungan Etnik Magazine Masyarakat India di BrickfiieldsHubungan Etnik Magazine Masyarakat India di Brickfiields
Hubungan Etnik Magazine Masyarakat India di BrickfiieldsFarah Sham
 
Strategic Management: Individual Assignment
Strategic Management: Individual AssignmentStrategic Management: Individual Assignment
Strategic Management: Individual AssignmentFarah Sham
 
Strategic Management Presentation
Strategic Management Presentation Strategic Management Presentation
Strategic Management Presentation Farah Sham
 
Strategic Management Group Report
Strategic Management Group ReportStrategic Management Group Report
Strategic Management Group ReportFarah Sham
 
Pp2 coursework 1 p10
Pp2 coursework 1 p10 Pp2 coursework 1 p10
Pp2 coursework 1 p10 Farah Sham
 
PP2 Assignment: Group
PP2 Assignment: GroupPP2 Assignment: Group
PP2 Assignment: GroupFarah Sham
 
Building Economics Tutorial
Building Economics TutorialBuilding Economics Tutorial
Building Economics TutorialFarah Sham
 
Building Economics Presentation
Building Economics PresentationBuilding Economics Presentation
Building Economics PresentationFarah Sham
 
A3 CONSTRUCTION METHODOLOGY
A3 CONSTRUCTION METHODOLOGYA3 CONSTRUCTION METHODOLOGY
A3 CONSTRUCTION METHODOLOGYFarah Sham
 
Building Economics Cost Data
Building Economics Cost Data Building Economics Cost Data
Building Economics Cost Data Farah Sham
 
Building Economics Cost Plan Report
Building Economics Cost Plan ReportBuilding Economics Cost Plan Report
Building Economics Cost Plan ReportFarah Sham
 
MEASUREMENT TENDER DOCUMENTATION
MEASUREMENT TENDER DOCUMENTATIONMEASUREMENT TENDER DOCUMENTATION
MEASUREMENT TENDER DOCUMENTATIONFarah Sham
 
Software application
Software application Software application
Software application Farah Sham
 
Project tender
Project tender Project tender
Project tender Farah Sham
 
Project tender
Project tenderProject tender
Project tenderFarah Sham
 
Software application for qs material standard rate
Software application for qs   material  standard rateSoftware application for qs   material  standard rate
Software application for qs material standard rateFarah Sham
 

More from Farah Sham (20)

Conference Paper
Conference PaperConference Paper
Conference Paper
 
My Community Service Journal
My Community Service JournalMy Community Service Journal
My Community Service Journal
 
Orphanage Community Service Initiative
Orphanage Community Service InitiativeOrphanage Community Service Initiative
Orphanage Community Service Initiative
 
Infographic Poster Report
Infographic Poster ReportInfographic Poster Report
Infographic Poster Report
 
Hubungan Etnik Magazine Masyarakat India di Brickfiields
Hubungan Etnik Magazine Masyarakat India di BrickfiieldsHubungan Etnik Magazine Masyarakat India di Brickfiields
Hubungan Etnik Magazine Masyarakat India di Brickfiields
 
Strategic Management: Individual Assignment
Strategic Management: Individual AssignmentStrategic Management: Individual Assignment
Strategic Management: Individual Assignment
 
Strategic Management Presentation
Strategic Management Presentation Strategic Management Presentation
Strategic Management Presentation
 
Strategic Management Group Report
Strategic Management Group ReportStrategic Management Group Report
Strategic Management Group Report
 
Pp2 coursework 1 p10
Pp2 coursework 1 p10 Pp2 coursework 1 p10
Pp2 coursework 1 p10
 
PP2 Assignment: Group
PP2 Assignment: GroupPP2 Assignment: Group
PP2 Assignment: Group
 
Building Economics Tutorial
Building Economics TutorialBuilding Economics Tutorial
Building Economics Tutorial
 
Building Economics Presentation
Building Economics PresentationBuilding Economics Presentation
Building Economics Presentation
 
A3 CONSTRUCTION METHODOLOGY
A3 CONSTRUCTION METHODOLOGYA3 CONSTRUCTION METHODOLOGY
A3 CONSTRUCTION METHODOLOGY
 
Building Economics Cost Data
Building Economics Cost Data Building Economics Cost Data
Building Economics Cost Data
 
Building Economics Cost Plan Report
Building Economics Cost Plan ReportBuilding Economics Cost Plan Report
Building Economics Cost Plan Report
 
MEASUREMENT TENDER DOCUMENTATION
MEASUREMENT TENDER DOCUMENTATIONMEASUREMENT TENDER DOCUMENTATION
MEASUREMENT TENDER DOCUMENTATION
 
Software application
Software application Software application
Software application
 
Project tender
Project tender Project tender
Project tender
 
Project tender
Project tenderProject tender
Project tender
 
Software application for qs material standard rate
Software application for qs   material  standard rateSoftware application for qs   material  standard rate
Software application for qs material standard rate
 

Recently uploaded

Introduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher EducationIntroduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher Educationpboyjonauth
 
Grant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy ConsultingGrant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy ConsultingTechSoup
 
Interactive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communicationInteractive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communicationnomboosow
 
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...Marc Dusseiller Dusjagr
 
microwave assisted reaction. General introduction
microwave assisted reaction. General introductionmicrowave assisted reaction. General introduction
microwave assisted reaction. General introductionMaksud Ahmed
 
How to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxHow to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxmanuelaromero2013
 
The basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxThe basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxheathfieldcps1
 
URLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website AppURLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website AppCeline George
 
Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)eniolaolutunde
 
Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17Celine George
 
Accessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactAccessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactdawncurless
 
Web & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfWeb & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfJayanti Pande
 
Activity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfActivity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfciinovamais
 
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Krashi Coaching
 
CARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxCARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxGaneshChakor2
 
Student login on Anyboli platform.helpin
Student login on Anyboli platform.helpinStudent login on Anyboli platform.helpin
Student login on Anyboli platform.helpinRaunakKeshri1
 
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Sapana Sha
 

Recently uploaded (20)

Introduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher EducationIntroduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher Education
 
Grant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy ConsultingGrant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy Consulting
 
Interactive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communicationInteractive Powerpoint_How to Master effective communication
Interactive Powerpoint_How to Master effective communication
 
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
“Oh GOSH! Reflecting on Hackteria's Collaborative Practices in a Global Do-It...
 
microwave assisted reaction. General introduction
microwave assisted reaction. General introductionmicrowave assisted reaction. General introduction
microwave assisted reaction. General introduction
 
How to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptxHow to Make a Pirate ship Primary Education.pptx
How to Make a Pirate ship Primary Education.pptx
 
The basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxThe basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptx
 
URLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website AppURLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website App
 
Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)Software Engineering Methodologies (overview)
Software Engineering Methodologies (overview)
 
Mattingly "AI & Prompt Design: The Basics of Prompt Design"
Mattingly "AI & Prompt Design: The Basics of Prompt Design"Mattingly "AI & Prompt Design: The Basics of Prompt Design"
Mattingly "AI & Prompt Design: The Basics of Prompt Design"
 
Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17
 
Accessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactAccessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impact
 
Staff of Color (SOC) Retention Efforts DDSD
Staff of Color (SOC) Retention Efforts DDSDStaff of Color (SOC) Retention Efforts DDSD
Staff of Color (SOC) Retention Efforts DDSD
 
Web & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdfWeb & Social Media Analytics Previous Year Question Paper.pdf
Web & Social Media Analytics Previous Year Question Paper.pdf
 
Activity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdfActivity 01 - Artificial Culture (1).pdf
Activity 01 - Artificial Culture (1).pdf
 
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
 
CARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxCARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptx
 
Student login on Anyboli platform.helpin
Student login on Anyboli platform.helpinStudent login on Anyboli platform.helpin
Student login on Anyboli platform.helpin
 
Código Creativo y Arte de Software | Unidad 1
Código Creativo y Arte de Software | Unidad 1Código Creativo y Arte de Software | Unidad 1
Código Creativo y Arte de Software | Unidad 1
 
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
 

Mega project

  • 1. Professional Practice 1 Group Members: Nicole Thain Huey Wei Phon Kit Poi Pui Chun Shian Ranee Leow Kai Yen Satesh Raj A/L P. Devaraj Sew Yue Ling Soo Ping Zheng Soo Yon Li Tam Zhao Wei Tan Jia San Farah Aida
  • 3. WHY TRADITIONAL PROCUREMENT ? Completion on time (5 years) Variation in design Minimum variation in Contract Sum Deal with minimum parties Full control of design
  • 4. 1. Brief Stage 2. Design Stage 3. Tendering (Competition) Stage 4. Construction Stage Completion on time (5 years)✔
  • 5. Variation in design Minimum variation in Contract Sum ✔ ✔ ↓ Cost Risk ↓ Design Risk
  • 6. Deal with minimum parties Full control of design ✔ ✔
  • 7. CONCLUSION - ↑ Time frame - Construction cost certainty - ↓ Price variation - Partial / Full control of design - ↓ Design Variation - ↓ Parties to deal with
  • 9. WHY TWO STAGE SELECTIVE TENDERING ? Reasonably transparent Eliminate non-performing contractors
  • 10. TWO STAGE SELECTIVE TENDERING Open to only selected numbers of “Pre-qualified” contractors Reduce tender cost, saves time & resources Low risk but high reward Lower risk of buildability issue
  • 11. Reasonably transparent ✔ STAGE 1 ❏ An advertisement will be placed on major newspaper/social platform ❏ Interested tenderers will submit their companies particulars in a “Pre-qualification Form”
  • 12. Eliminate non-performing contractors ✔ STAGE 2 ❏ A “Pre-qualification” form will be attached with the advertisement ❏ Evaluation Stage : based on the “Pre-qualification Form”
  • 13. TWO-STAGE SELECTIVE TENDERING TIMELINE Invitation To Tender ● Advertisement ● Pre-Qualification Form Pre-Qualification Stage ● Based on experience, financial capabilities and competencies. Collection of Tender ● Charged with documentation fees Tender Closing ● Submit into a “tender box” ● QS submit Pre-Tender Estimate Tender Opening ● Tender figures are recorded and jointly verified Tender Evaluation ● Check for major arithmetical errors ● Prepare tender report ● Call lowest 3 tenderers for tender interview Tender Interview ● Queried on any issues ● May be requested to submit a revised tender Tender Award ● Prepare and issue Letter of Award ● Return within 14 days
  • 15. LUMP SUM CONTRACT WHY LUMP SUM CONTRACT? ● Construction designs are completed > Requested work is well-defined ● Minimize variations during construction > minimize variation to price as well ● Reduce owner risks ● Contractor has greater control over profit expectations
  • 16. LIQUIDATED ASCERTAINED DAMAGES (LAD) ● Client’s Requirement : Imposed Liquidated Damages of RM 250,000.00 a day. Ensure project to complete on time ✔ Include early completion compensation for the contractor Early completion might produce higher savings for the project owner LUMP SUM CONTRACT
  • 17. PAM CONTRACT 2006 (WITH QUANTITIES) ● Home base form : Risks are known to be local industry ● Intended to be used as a building contractor and not as civil engineering contract ● It is estimated that 90% of the building contracts in the private sector are based on the PAM Contract 2006
  • 18. Functions of PAM Contract 2006 (With Quantities) ● Evidences legal relationship between parties in the contract ● Provides the administrative procedure ● Incorporate all special requirements and circumstances of a project ● Expresses the obligation of the parties ● Set out reasonable clarity of the project PAM CONTRACT 2006 (WITH QUANTITIES)
  • 19. Clause 6.1 - Standards of works, materials, goods and workmanship ● Materials, goods and workmanship shall be according to the standards described in the contract documents ● If there is any discrepancy, the contractor can instruct sub-contractors to demolish and rectify the defect works Clause 15.4 - Schedule of defects ● Sub-contractor must provide defect liability period after completion of works and correct the defects within 28 Days from receipt of schedule of defects from contractor. QUALITY
  • 20. HEALTH & SAFETY OSHA (Occupational Safety & Health Administration) - The Occupational Safety & Health Act 1970 - To keep their work environment safe - < 10 workers X file injury / illness report - Compulsory training to the workers as a guarantee to the employer
  • 21. 1. Appoint a Safety Advisor HOW TO ENHANCE HEALTH & SAFETY ? Essential to give professional advices. OSHA Clause 8.1 - Training & Competency 2. Proposed Site Management Plan (SMP) Compliance to Occupational Safety and Health in Construction Industry (Management) - Ensure a safer working environment 3. Allow Separate Specification for Health & Safety The Health & Safety Specification may include any details regarding health and safety matters

Editor's Notes

  1. Based on BQ and drawings( contractor qs has to estimate) The type of contract that we have chosen is the lump sum contract. Why lump sum contract? The reason being is because lump sum contract is based on completed construction design. This allow a well defined work scope to be delivered to the contractor. Hence, the variation during the construction can be minimize and eventually the variation of price will be minimized too. By using lump sum contract, the risk of the owner will be transferred to the contractor. And the contractor will have greater control over profit expectations.
  2. Based on BQ and drawings( contractor qs has to estimate) So for the Clients requirement for LAD, the client would like to impose RM250,000 a day which is a big amount. By using the lump sum contract, one of the its characteristics is that it includes early completion compensation for the contractor by this means the project owner can have higher savings.
  3. For form of contract, we chose the PAM Contract 2006 (With Quantities). This is because it is a home base form where the risks are known to local industry. Besides that, it is intended to be used as a building contractor and not as civil engineering contract unlike FIDIC which can only be used for civil engineering projects such as oil rigs etc. And by using the PAM Contract, its obviously gives flexibility to the employer and the contractor It is estimated that 90% of the building contracts in the private sector are based on PAM Contract 2006, because it includes relevant clauses to assure the rights for the involved parties. This is the reason why PWD Contract is not our choice for this project.
  4. As for the functions of PAM Contract, it gives and evidences legal relationship between parties in the contract so that if either side of the party breach the contract, legal actions can be made. With this, it reminds the parties to follow the contract whenever the project is ongoing. It also provide administrative procedure so qthat any professions that would look at the PAM contract would not get lost or would know what to do if let’s say there’s a claim for extension of time. And the PAM contract has also written clearly all the special requirements and what are the circumstances of a project. What to do if something happens and so on. Sometimes, parties do not know what actually is their obligations towards the job but by referring to PAM contract, the obligations of the parties will be stated clearly in the Contract. As mentioned that most of the times claims happen due to different type of reasons like extension of time, late site possessions and so on. To look for what should be done or what are the clarifications, contractors can refer back to the PAM contract and the clarifications are definitely reasonable.
  5. The employer has also mentioned about the quality of the works carried out. And we can guarantee the standard of works, materials, goods and workmanship under clause 6.1 of the PAM Contract. It also says that if there is any difference in the works, the contractors or the subcons are liable to change the demolish the works and changed it into the original plan. Basically the employers do not need to worry about it because under clause 15.4 of the PAM Contract, it has stated that the contractor must issue the DLP after the completion of works and the contractors need to amend the defects within 28 days from the receipt of schedule of defects from contractor.
  6. A single construction has lots of management that need to be handled appropriately, one of the most concern factor while the construction is going on is the safety of everyone near to the site, mainly the workers on site. So the one that we will introduce to the employer is the Occupational Safety & Health Administration which is also known as OSHA. Well, to know more about them, they actually practice the Occupational Safety & Health Act which is published in 1970. The main reason they have established the act is to keep the workers’ and the working environment safe. By that, they could save more lives by reducing the accidents that will happen. They have also mentioned that if the company has less than 10 workers, there’s no need for filing an injury or illness report to them. And the employer can communicate plans made orally to the workers. But, the plan must be written if there are over 10 employees. The written plan should be kept in the workplace, and must be always available for employee review. The main purpose of OSHA is they provide compulsory trainings to the worker as a guarantee to the employer. In such way, the workers would work professionally and diligently in the construction site.
  7. So there are ways to enhance healthy & safety. But first, the Employer should appoint a safety advisor. A safety advisor is extremely essential for the construction works to give professional advices on the precautions and safety measures and by that, there will be a huge improvement in the Site’s health and safety standard. OSHA has mentioned clearly about the safe environment in a working place. Under clause 8.1 of OSHA, Training and Competency has been one of the most highlighted part for them as they only prefer workers who have learnt about the safety precautions and make sure workers will apply them on site. Sometimes, workers are not aware of the safety signs but the safety signs are one of the ways to help workers to know what is going on on the particular work site. So the second step is to Propose a Site Management Plan. As you have already appoint a safety advisor, he/she will help you in doing the management plan. But make sure it is compliance to OSHA in construction industry and it is to ensure a safer working environment for all involved individuals such as employees, contractors, visitors and the community. It is a documented safety plans for a specific construction workplace that should include the following matters: (i) General principles of prevention (ii) Minimum welfare facilities required for construction sites (iii) Work involving particular risks Last step is to Allow Specification for Health & Safety. Besides specifications for building designs, a separate specifications for health and safety can be developed to enhance the Health & Safety requirement of the project. The Health & Safety Specification may include any details regarding health and safety matters that needs extra attention from all relevant parties.