DAMAC Heights Project 
Prepared by: Sameh Ibrahim Reviewed by: Fuad Hasan
DAMAC Heights Project 
DAMAC Heights Tower Location
Project Description 
Project Statistics
DAMAC Heights Project 
Site Plan
Project Description 
DAMAC Heights Tower located at plot No.A3A,392-569 at Dubai Marina and 
comprises of the following criteria; 
Dates/Cost Projection 
Date of Forecast Completion: 14-May-16 
Project Value: 508,301,847 AED 
Area/Height Calculations 
Tower Built Up Area: 141,542 m2 
Tower Height: 335 m 
Floor Distribution 
Non-Branded Flats: Level 6 to 42 
Branded Flats (FENDI): Level 43 to 84 
Parking Slots /Rooms Count 
Total Flats: 637 
1 Bedroom: 282 
2 Bedroom: 258 
3 Bedroom: 86 
4 Bedroom: 9 
5 Bedroom: 2 
Parking Slots: 649 
Retail: 1 
DAMAC Heights Project 
Floors Count 
Basement Floors: 5 
Podium Floors: 5 
Typical Floors: 79 
Mechanical Floors: 3 
Top Roof: 1
DAMAC Heights Project 
Life Style 
Podium 5 is called Life Style and includes 
the following service areas: 
1- Swimming Pool 
2- Bar Area 
3- Residential Lounge 
4- Kids Room 
5- Cinema 
6- Male Gym 
7- Female Gym 
8- Men SPA 
9- Woman SPA 
10- Reception 
11- Gymnasium Room 
Fendi Entrance 
At Ground floor, there is special Entrance 
Lobby and Lift Lobby for Branded Flats 
(FENDI)
Client 
Damac Gulf Properties 
Supervision 
Consultant 
AECOM Middle East 
Master Developer 
Emaar Properties 
Main Contractor 
Arabtec Construction 
L.L.C 
MEP 
REMCO CO. L.L.C 
Elevators 
Toshiba Middle East 
External Facade 
ALICO CO. Ltd. 
DAMAC Heights Project 
Project Stakeholders 
Client- Consultants 
Designer 
Ramboll Middle East 
Main Contractor 
Key Sub-Contractors 
BMU 
DANWAY L.L.C 
Fit Out for Non 
Branded Flats 
JC Maclean
Main Packages-Delivery 
Structural & Finishes Package 
 Firm: Arabtec Construction L.L.C 
 Contract Value: 244,747,597 AED 
External Façade Package 
 Firm: ALICO CO. Ltd 
 Contract Value: 62,967,933 AED 
QATAR 
ACCOUNT 
MANAGEMENT 
PROGRAM 
Electromechanical Package 
 Firm: REMCO CO. L.L.C 
 Contract Value: 82,000,000 AED 
Fit Out Package 
(non branded flats) 
 Firm: JC Maclean 
 Contract Value: 14,747,525 AED 
DAMAC Heights Project
Main Packages-Delivery 
Elevators Package 
 Firm: Toshiba Middle East 
 Contract Value: 11,332,200 AED 
QATAR 
ACCOUNT 
MANAGEMENT 
PROGRAM 
Fit Out Package 
(Life Style / Main entrance) 
 Firm: To be nominated 
 Contract Value: N/A 
BMU Package 
 Firm: DANWAY L.L.C 
 Contract Value: 1,300,000 AED 
Fit Out Package 
(branded flats) 
 Firm: To be nominated 
 Contract Value: N/A 
DAMAC Heights Project
DAMAC Heights Project 
QATAR 
ACCOUNT 
MANAGEMENT 
PROGRAM 
AECOM Delivery Team 
Project Control Architectural Structural MEP (Mechanical) MEP (Electrical) HSE 
Planning Manager 
Sameh Ibrahim 
Sr. Architect 
Ramon Olavydez  
Inspector 
Sanat Rane  
Sr. Struct. Engineer 
Reuben Samaniego 
Sr. Struct. Engineer 
Ali Mahmoud 
Mech. Manager 
Ahmed Raouf  
Sr. Mech. Engineer 
Aiman Al-Nakawa 
Elect. Manager 
Kousay Al Kureishi 
Sr. Elec. Engineer 
Mateen Khawajah 
Document Control 
Abdul Latheef  
Project Secretary 
Abdulla Muhyiden 
Project Director 
Fuad Hasan  
Sr. Resident Engineer 
Radhi Mohamed  
HSE Officer 
Mohammad Faisi  
Inspector 
Roberto Magtira  
Inspector 
Percival Vicente 
Inspector 
Shibu Mathew  
Admin 
Inspector 
Frederick Abellar  
Fit out Inspector 
TBA
DAMAC Heights Project 
Project Headlines 
Damac Heights Tower 
Construction Week Online 
Dubai, United Arab Emirates 
An Interview was run by 
Construction Week Online 
Magazine with DAMAC Senior 
Project Manager, Samer H. 
Skaik
Key Design Features 
Fendi Apartments
DAMAC Heights Project 
Typical Floor Layout
Fendi Casa Apartments Bed Room
Fendi Casa Apartments Living Room
Fendi Casa Apartments Master Bathroom
Fendi Casa Apartments Powder Room
Fendi Casa Apartments Walk-IN Closet
Key Design Features 
Life Style @ Podium 5
DAMAC Heights Project 
Life Style Layout @ Podium 5
DAMAC Heights Project 
Life Style ID @ Podium 5
Life Style Kids Play Area
Life Style Cinema
Life Style Bar Lounge
Life Style Gym Room
Life Style Ladies Jacuzzi
Life Style Ladies Make-Up
Life Style Lounge Area
Life Style Male Jacuzzi
Life Style Reception
Key Design Features 
Non Branded Entrance @ Ground Floor
DAMAC Heights Project 
Non Branded Entrance Layout @ Ground Floor
Non Branded Entrance Entrance Lobby
Non Branded Entrance Lift Lobby
Key Design Features 
Fendi Casa Entrance @ Ground Floor
DAMAC Heights Project 
Fendi Entrance Layout @ Ground Floor
Fendi Entrance Entrance Lobby
Fendi Entrance Reception Area
Current Progress 
Site Works
DAMAC Heights Project 
Project Schedule 
Statistics – May 2014 
Area Performance Indicators Measure This Month Last Month 
Time 
SPI EV / PV 0.91 
SV EV - PV (AED m) -17.7 
Float (MS01) 
Days Float 
Remaining 
-79 
12.5 11.4 
0.91 
-79 
Planned % 
-6 
Actual % 
Structure Delay 
Schedule Performance 
Index 
Project Potential Delay
DAMAC Heights Project 
Negative Floats Contour 
Risk Rating
Structure - Slab at Level 20 
Structural Progress 
Concrete Pouring 
Levels 
6th 
7th 
8th 
9th 
10th 
11th 
12th 
13th 
14th 
15th 
16th 
17th 
18th 
19th 
20th 
21st 
22nd 
23rd 
Core Walls Slabs Columns Stairs 
100% 100% 100% 100% 
100% 100% 100% 100% 
100% 100% 100% 100% 
100% 100% 100% 0% 
100% 100% 100% 0% 
100% 100% 100% 0% 
100% 100% 100% 0% 
100% 100% 100% 0% 
100% 100% 100% 0% 
100% 100% 100% 0% 
100% 100% 100% 0% 
100% 100% 100% 0% 
100% 100% 100% 0% 
100% 100% 100% 0% 
100% 100% 50% 0% 
100% 0% 0% 0% 
100% 0% 0% 0% 
40% 0% 0% 0% 
38.89% 
0.62% 
4.21% 
37.98% 
0.17% 
0.2 % 
%Pld %Act
MEP – H/L Installations at Level 6 
High Level Installation 
Levels 
6th 
7th 
8th 
9th 
10th 
11th 
12th 
13th 
14th 
15th 
16th 
HAVC Fire Fighting Plumbing Electrical 
92% 95% 93% 79% 
90% 86% 88% 56% 
86% 86% 88% 56% 
59% 86% 78% 44% 
54% 86% 56% 44% 
54% 76% 54% 35% 
10% 38% 0% 35% 
0% 48% 0% 35% 
0% 0% 0% 35% 
0% 0% 0% 35% 
0% 0% 0% 35% 
38.89% 
0.62% 
4.21% 
37.98% 
0.17% 
0.2 % 
%Pld %Act 
MEP Progress
Architectural – Block Works at 
Level 6 
Architectural Progress 
Block Works 
Levels 
6th 
7th 
8th 
9th 
10th 
11th 
12th 
13th 
14th 
15th 
16th 
Block Works 
95% 
95% 
95% 
85% 
40% 
0% 
15% 
0% 
0% 
0% 
0% 
38.89% 
0.17% 
0.62% 
4.21% 
37.98% 
0.2 % 
%Pld %Act
Enabling Work– Pressure 
Grouting in Zone B 
Enabling Work 
Progress 
Zone B Construction 
Section 
B-B 
Due to the flood event that occurred in 2012 that caused 
major flooding to the site. Pressure Grouting was 
introduced as a method of reducing water infiltration. 
The pressure grouting is still ongoing and is scheduled to 
be completed by the 3rd week of June-14. 
After completing the pressure grouting, the excavation 
shall commence in Zone B and the remaining 11 stories of 
that zone will take approx. 10 months. 
The above event is the subject of an EOT claim and is 
being negotiated between DAMAC and ATC. 
Zone B 
95% Pressure Grouting % 
Progress
Current Progress 
Quality Assurance and Control
DAMAC Heights Project 
Quality Assurance and Control 
74% 26% 
NCR Closed % NCR Opened % 
68 50 
18 
Total NCR Raised 
Total NCR Closed 
Total NCR Opened 
Statistics – May 2014 
Area Performance Indicators Measure This Month Last Month 
Quality NCR Close Out Issued/Closed 68/50 59/41
DAMAC Heights Project 
Quality Assurance and Control 
NCRs Root Cause 
Key Quality Improvement Measures 
Quality Improvement Measures 
• CurreŶtly ATC keeps suďŵittiŶg the ĐoŶĐrete test results iŶ tiŵely ŵaŶŶer as was 
instructed by AECOM. 
• AECOM iŶstruĐted ATC to suďŵit the struĐtural ĐlearaŶĐe ďefore the ĐoŵŵeŶĐeŵeŶt of 
MEP work. 
• AECOM is going to hold Quality Technical Meetings on weekly basis to monitor the 
quality.
Current Progress 
Health and Safety
DAMAC Heights Project 
Health and Safety 
1201 8 
Work Force Average Improvement Notices 
3 4 
64 
issued 
Near Misses First Aid Cases 
Tool Box Talks 
Statistics – May 2014 
Area Performance Indicators Measure This Month Last Month 
Health and 
Safety 
Near Misses 
No. of Near 
Misses 
3 0
Project Risks 
Top 5 Risks
DAMAC Heights Project 
Top 5 Risks 
Risk ID Risk Event Cause Rating Risk Response 
Risk 
Owner 
RS_01 Flooding in Zone B 
Existing ground cavities 
that allows for the flow 
of water through it. 
Pressure Grouting has commenced 
and is scheduled to be completed in 
June 14. 
DAMAC/ 
AECOM 
RS_02 
Delays in possessing 
DEWA approval for LV 
shop drawings and 
delays in procuring LV 
Panels and Bus Bars. 
Late of issuing MEP IFC 
drawings. 
DAMAC has to finalize the ID design 
for FENDI Apartments and then 
RME has to issue the final MEP IFC 
drawings to ATC. 
DAMAC/R 
ME 
RS_03 
Delays in pouring the 
slab of level 30 
8 days estimated cycle 
will not be achieved as 
the slab will need for 2 
weeks at least. 
AECOM highlighted this issue to 
ATC in the weekly progress 
meeting. ATC 
RS_04 
Delays In MEP high level 
installations 
Delays in giving access 
from ATC to REMCO and 
then delays from REMCO 
in doing the installations 
due to the shortage of 
manpower. 
ATC has to give full access to 
REMCO on time. REMCO has to 
increase the allocated manpower in 
order to work concurrently in 5 
levels. 
ATC/ 
REMCO 
RS_05 
Delays in nomination of 
the PS items 
DAMAC's tenders 
floating/awarding 
process delayed. 
DAMAC has to expedite the PS 
items' procuring process in order to 
avoid delaying the site works. DAMAC 
5 
4 
3 
2 
1 
0 
Critical 
Severe 
Manageable 
Negligible 
Risk Rating
• Historical pre-existing issues. 
• Continuous design changes. 
• Soil improvement in Zone B. 
“ Working with a 
Commercial 
Developer 
demands a 
Bespoke 
Approach ” 
Project Challenges 
• Employer procurement system. 
• Management and coordination of 
client processes.. 
• Lack of detailed scheduling 
specification within the contract.
DAMAC Heights Project

More Related Content

What's hot

training report
training reporttraining report
training reportLilonheart
 
Building Information Modelling (BIM) in India
Building Information Modelling (BIM) in IndiaBuilding Information Modelling (BIM) in India
Building Information Modelling (BIM) in IndiaBe2camp Admin
 
Rate analysis in civil engineering
Rate analysis in civil engineeringRate analysis in civil engineering
Rate analysis in civil engineeringKailash Chander
 
Financial management of construction contracts
Financial management of construction contractsFinancial management of construction contracts
Financial management of construction contractsidnobleg77
 
Role of Project Management Consultancy in Construction Project
Role of Project Management Consultancy in Construction ProjectRole of Project Management Consultancy in Construction Project
Role of Project Management Consultancy in Construction ProjectIOSR Journals
 
Infrastructure project ring road, Ahmadabad
Infrastructure project ring road, Ahmadabad Infrastructure project ring road, Ahmadabad
Infrastructure project ring road, Ahmadabad Ar Vandana Talikoti
 
Construction Monthly Progress Report - June 2011
Construction Monthly Progress Report - June 2011Construction Monthly Progress Report - June 2011
Construction Monthly Progress Report - June 2011Jamal Nelson, CCM
 
Wbs & Bar chart for Civil engg
Wbs & Bar chart for Civil engg Wbs & Bar chart for Civil engg
Wbs & Bar chart for Civil engg Meet Shah
 
Managing Cash Flows On Construction Projects
Managing Cash Flows On Construction ProjectsManaging Cash Flows On Construction Projects
Managing Cash Flows On Construction ProjectsAGC of California
 
Stages In Construction
Stages In ConstructionStages In Construction
Stages In ConstructionAB MAKASANA
 
Project management report of stadium
Project management report of stadiumProject management report of stadium
Project management report of stadiumSLIIT, Sri Lanka
 

What's hot (20)

training report
training reporttraining report
training report
 
PEB Steel Company profile
PEB Steel Company profilePEB Steel Company profile
PEB Steel Company profile
 
RIBA plan of work
RIBA plan of workRIBA plan of work
RIBA plan of work
 
Building Information Modeling (BIM)
Building Information Modeling (BIM)Building Information Modeling (BIM)
Building Information Modeling (BIM)
 
Building Information Modelling (BIM) in India
Building Information Modelling (BIM) in IndiaBuilding Information Modelling (BIM) in India
Building Information Modelling (BIM) in India
 
Rate analysis in civil engineering
Rate analysis in civil engineeringRate analysis in civil engineering
Rate analysis in civil engineering
 
Financial management of construction contracts
Financial management of construction contractsFinancial management of construction contracts
Financial management of construction contracts
 
Role of Project Management Consultancy in Construction Project
Role of Project Management Consultancy in Construction ProjectRole of Project Management Consultancy in Construction Project
Role of Project Management Consultancy in Construction Project
 
Analysis of rates
Analysis of ratesAnalysis of rates
Analysis of rates
 
Valuation
ValuationValuation
Valuation
 
Valuation
ValuationValuation
Valuation
 
Infrastructure project ring road, Ahmadabad
Infrastructure project ring road, Ahmadabad Infrastructure project ring road, Ahmadabad
Infrastructure project ring road, Ahmadabad
 
Construction Monthly Progress Report - June 2011
Construction Monthly Progress Report - June 2011Construction Monthly Progress Report - June 2011
Construction Monthly Progress Report - June 2011
 
Wbs & Bar chart for Civil engg
Wbs & Bar chart for Civil engg Wbs & Bar chart for Civil engg
Wbs & Bar chart for Civil engg
 
Airport Construction
Airport ConstructionAirport Construction
Airport Construction
 
Managing Cash Flows On Construction Projects
Managing Cash Flows On Construction ProjectsManaging Cash Flows On Construction Projects
Managing Cash Flows On Construction Projects
 
What is completion certificate and how to obtain it
What is completion certificate and how to obtain itWhat is completion certificate and how to obtain it
What is completion certificate and how to obtain it
 
Stages In Construction
Stages In ConstructionStages In Construction
Stages In Construction
 
Project management report of stadium
Project management report of stadiumProject management report of stadium
Project management report of stadium
 
Development Plan- Planning interventions by (VNIT) Visvesvaraya National Inst...
Development Plan- Planning interventions by (VNIT) Visvesvaraya National Inst...Development Plan- Planning interventions by (VNIT) Visvesvaraya National Inst...
Development Plan- Planning interventions by (VNIT) Visvesvaraya National Inst...
 

Similar to DAMAC Heights Project

Similar to DAMAC Heights Project (20)

Oberoi Hotel
Oberoi HotelOberoi Hotel
Oberoi Hotel
 
Amjad survey inspector
Amjad survey inspectorAmjad survey inspector
Amjad survey inspector
 
SABER CV
SABER CVSABER CV
SABER CV
 
Ahmed cv 2014-1
Ahmed cv  2014-1Ahmed cv  2014-1
Ahmed cv 2014-1
 
Ahmed cv 2014
Ahmed cv  2014Ahmed cv  2014
Ahmed cv 2014
 
LEAD MECHANICAL CONSTRUCTION ENGINEER 1
LEAD MECHANICAL CONSTRUCTION ENGINEER 1LEAD MECHANICAL CONSTRUCTION ENGINEER 1
LEAD MECHANICAL CONSTRUCTION ENGINEER 1
 
Shakir CV
Shakir CV Shakir CV
Shakir CV
 
Sandeep kumar pandey updated 2019
Sandeep kumar pandey updated 2019Sandeep kumar pandey updated 2019
Sandeep kumar pandey updated 2019
 
Cv mechanical supervisor
Cv mechanical supervisorCv mechanical supervisor
Cv mechanical supervisor
 
r_1
r_1r_1
r_1
 
Topside
TopsideTopside
Topside
 
Anas Khalifa's CV_JAN.-2017
Anas Khalifa's CV_JAN.-2017Anas Khalifa's CV_JAN.-2017
Anas Khalifa's CV_JAN.-2017
 
Anas Khalifa's CV_JAN.-2017
Anas Khalifa's CV_JAN.-2017Anas Khalifa's CV_JAN.-2017
Anas Khalifa's CV_JAN.-2017
 
Mine Haul Road Upgrade Project OZ Minerals Prominent Hill South Australia
Mine Haul Road Upgrade Project OZ Minerals Prominent Hill South AustraliaMine Haul Road Upgrade Project OZ Minerals Prominent Hill South Australia
Mine Haul Road Upgrade Project OZ Minerals Prominent Hill South Australia
 
FPSO & FLNG Asia 2016 - Final
FPSO & FLNG Asia 2016 - FinalFPSO & FLNG Asia 2016 - Final
FPSO & FLNG Asia 2016 - Final
 
Antara Dashboard-002.pptx
Antara Dashboard-002.pptxAntara Dashboard-002.pptx
Antara Dashboard-002.pptx
 
Abraham Sanni CV
Abraham Sanni CVAbraham Sanni CV
Abraham Sanni CV
 
Construction Oil and Gas Forum Jan 2015 Abu Dhabi Brochure
Construction Oil and Gas Forum Jan 2015 Abu Dhabi BrochureConstruction Oil and Gas Forum Jan 2015 Abu Dhabi Brochure
Construction Oil and Gas Forum Jan 2015 Abu Dhabi Brochure
 
Curriculum Vitae of R M Rico
Curriculum Vitae of R M RicoCurriculum Vitae of R M Rico
Curriculum Vitae of R M Rico
 
Oct. -2015-CV
Oct. -2015-CVOct. -2015-CV
Oct. -2015-CV
 

More from Sam Kendall, MSc, BSc Civil Eng., PMP®, MIEAust

More from Sam Kendall, MSc, BSc Civil Eng., PMP®, MIEAust (20)

Kandil Mohammed Ibrahim_Sameh_Dissertation
Kandil Mohammed Ibrahim_Sameh_DissertationKandil Mohammed Ibrahim_Sameh_Dissertation
Kandil Mohammed Ibrahim_Sameh_Dissertation
 
Summary Progress Of Facade Works
Summary Progress Of Facade WorksSummary Progress Of Facade Works
Summary Progress Of Facade Works
 
Summary Progress Of Concrete Works
Summary Progress Of Concrete WorksSummary Progress Of Concrete Works
Summary Progress Of Concrete Works
 
Progress Of Ceiling Per Floors
Progress Of Ceiling Per FloorsProgress Of Ceiling Per Floors
Progress Of Ceiling Per Floors
 
N1
N1N1
N1
 
Progress Of Slab
Progress Of SlabProgress Of Slab
Progress Of Slab
 
Overall Progress S-Curve For Ceiling
Overall Progress S-Curve For CeilingOverall Progress S-Curve For Ceiling
Overall Progress S-Curve For Ceiling
 
Overall Progress S-Curve For Facades
Overall Progress S-Curve For FacadesOverall Progress S-Curve For Facades
Overall Progress S-Curve For Facades
 
Overall Progress S-Curve For Elevators
Overall Progress S-Curve For ElevatorsOverall Progress S-Curve For Elevators
Overall Progress S-Curve For Elevators
 
Overall Progres S-Curve For Concrete Works
Overall Progres S-Curve For Concrete WorksOverall Progres S-Curve For Concrete Works
Overall Progres S-Curve For Concrete Works
 
Window Analysis @ 30-June-2012
Window Analysis @ 30-June-2012Window Analysis @ 30-June-2012
Window Analysis @ 30-June-2012
 
01. P269 - Project Implementation Programme - Rev 00
01. P269 - Project Implementation Programme -  Rev 0001. P269 - Project Implementation Programme -  Rev 00
01. P269 - Project Implementation Programme - Rev 00
 
13. Overall S-Curve
13. Overall S-Curve13. Overall S-Curve
13. Overall S-Curve
 
10. Overall Implementation Programme
10. Overall Implementation Programme10. Overall Implementation Programme
10. Overall Implementation Programme
 
Building-Structure Planning Model
Building-Structure Planning ModelBuilding-Structure Planning Model
Building-Structure Planning Model
 
AWI20202 commercial
AWI20202 commercialAWI20202 commercial
AWI20202 commercial
 
Rihan Height Project Execution Plan-Rev00
Rihan Height Project Execution Plan-Rev00Rihan Height Project Execution Plan-Rev00
Rihan Height Project Execution Plan-Rev00
 
Monthly Progress Report No.13 - September 2011
Monthly Progress Report No.13 - September 2011Monthly Progress Report No.13 - September 2011
Monthly Progress Report No.13 - September 2011
 
Final Submission EOT 1
Final Submission EOT 1Final Submission EOT 1
Final Submission EOT 1
 
Cash Flow Portfolio
Cash Flow PortfolioCash Flow Portfolio
Cash Flow Portfolio
 

DAMAC Heights Project

  • 1. DAMAC Heights Project Prepared by: Sameh Ibrahim Reviewed by: Fuad Hasan
  • 2. DAMAC Heights Project DAMAC Heights Tower Location
  • 5. Project Description DAMAC Heights Tower located at plot No.A3A,392-569 at Dubai Marina and comprises of the following criteria; Dates/Cost Projection Date of Forecast Completion: 14-May-16 Project Value: 508,301,847 AED Area/Height Calculations Tower Built Up Area: 141,542 m2 Tower Height: 335 m Floor Distribution Non-Branded Flats: Level 6 to 42 Branded Flats (FENDI): Level 43 to 84 Parking Slots /Rooms Count Total Flats: 637 1 Bedroom: 282 2 Bedroom: 258 3 Bedroom: 86 4 Bedroom: 9 5 Bedroom: 2 Parking Slots: 649 Retail: 1 DAMAC Heights Project Floors Count Basement Floors: 5 Podium Floors: 5 Typical Floors: 79 Mechanical Floors: 3 Top Roof: 1
  • 6. DAMAC Heights Project Life Style Podium 5 is called Life Style and includes the following service areas: 1- Swimming Pool 2- Bar Area 3- Residential Lounge 4- Kids Room 5- Cinema 6- Male Gym 7- Female Gym 8- Men SPA 9- Woman SPA 10- Reception 11- Gymnasium Room Fendi Entrance At Ground floor, there is special Entrance Lobby and Lift Lobby for Branded Flats (FENDI)
  • 7. Client Damac Gulf Properties Supervision Consultant AECOM Middle East Master Developer Emaar Properties Main Contractor Arabtec Construction L.L.C MEP REMCO CO. L.L.C Elevators Toshiba Middle East External Facade ALICO CO. Ltd. DAMAC Heights Project Project Stakeholders Client- Consultants Designer Ramboll Middle East Main Contractor Key Sub-Contractors BMU DANWAY L.L.C Fit Out for Non Branded Flats JC Maclean
  • 8. Main Packages-Delivery Structural & Finishes Package  Firm: Arabtec Construction L.L.C  Contract Value: 244,747,597 AED External Façade Package  Firm: ALICO CO. Ltd  Contract Value: 62,967,933 AED QATAR ACCOUNT MANAGEMENT PROGRAM Electromechanical Package  Firm: REMCO CO. L.L.C  Contract Value: 82,000,000 AED Fit Out Package (non branded flats)  Firm: JC Maclean  Contract Value: 14,747,525 AED DAMAC Heights Project
  • 9. Main Packages-Delivery Elevators Package  Firm: Toshiba Middle East  Contract Value: 11,332,200 AED QATAR ACCOUNT MANAGEMENT PROGRAM Fit Out Package (Life Style / Main entrance)  Firm: To be nominated  Contract Value: N/A BMU Package  Firm: DANWAY L.L.C  Contract Value: 1,300,000 AED Fit Out Package (branded flats)  Firm: To be nominated  Contract Value: N/A DAMAC Heights Project
  • 10. DAMAC Heights Project QATAR ACCOUNT MANAGEMENT PROGRAM AECOM Delivery Team Project Control Architectural Structural MEP (Mechanical) MEP (Electrical) HSE Planning Manager Sameh Ibrahim Sr. Architect Ramon Olavydez  Inspector Sanat Rane  Sr. Struct. Engineer Reuben Samaniego Sr. Struct. Engineer Ali Mahmoud Mech. Manager Ahmed Raouf  Sr. Mech. Engineer Aiman Al-Nakawa Elect. Manager Kousay Al Kureishi Sr. Elec. Engineer Mateen Khawajah Document Control Abdul Latheef  Project Secretary Abdulla Muhyiden Project Director Fuad Hasan  Sr. Resident Engineer Radhi Mohamed  HSE Officer Mohammad Faisi  Inspector Roberto Magtira  Inspector Percival Vicente Inspector Shibu Mathew  Admin Inspector Frederick Abellar  Fit out Inspector TBA
  • 11. DAMAC Heights Project Project Headlines Damac Heights Tower Construction Week Online Dubai, United Arab Emirates An Interview was run by Construction Week Online Magazine with DAMAC Senior Project Manager, Samer H. Skaik
  • 12. Key Design Features Fendi Apartments
  • 13. DAMAC Heights Project Typical Floor Layout
  • 15. Fendi Casa Apartments Living Room
  • 16. Fendi Casa Apartments Master Bathroom
  • 17. Fendi Casa Apartments Powder Room
  • 18. Fendi Casa Apartments Walk-IN Closet
  • 19. Key Design Features Life Style @ Podium 5
  • 20. DAMAC Heights Project Life Style Layout @ Podium 5
  • 21. DAMAC Heights Project Life Style ID @ Podium 5
  • 22. Life Style Kids Play Area
  • 24. Life Style Bar Lounge
  • 26. Life Style Ladies Jacuzzi
  • 27. Life Style Ladies Make-Up
  • 29. Life Style Male Jacuzzi
  • 31. Key Design Features Non Branded Entrance @ Ground Floor
  • 32. DAMAC Heights Project Non Branded Entrance Layout @ Ground Floor
  • 33. Non Branded Entrance Entrance Lobby
  • 34. Non Branded Entrance Lift Lobby
  • 35. Key Design Features Fendi Casa Entrance @ Ground Floor
  • 36. DAMAC Heights Project Fendi Entrance Layout @ Ground Floor
  • 40. DAMAC Heights Project Project Schedule Statistics – May 2014 Area Performance Indicators Measure This Month Last Month Time SPI EV / PV 0.91 SV EV - PV (AED m) -17.7 Float (MS01) Days Float Remaining -79 12.5 11.4 0.91 -79 Planned % -6 Actual % Structure Delay Schedule Performance Index Project Potential Delay
  • 41. DAMAC Heights Project Negative Floats Contour Risk Rating
  • 42. Structure - Slab at Level 20 Structural Progress Concrete Pouring Levels 6th 7th 8th 9th 10th 11th 12th 13th 14th 15th 16th 17th 18th 19th 20th 21st 22nd 23rd Core Walls Slabs Columns Stairs 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 0% 100% 100% 100% 0% 100% 100% 100% 0% 100% 100% 100% 0% 100% 100% 100% 0% 100% 100% 100% 0% 100% 100% 100% 0% 100% 100% 100% 0% 100% 100% 100% 0% 100% 100% 100% 0% 100% 100% 100% 0% 100% 100% 50% 0% 100% 0% 0% 0% 100% 0% 0% 0% 40% 0% 0% 0% 38.89% 0.62% 4.21% 37.98% 0.17% 0.2 % %Pld %Act
  • 43. MEP – H/L Installations at Level 6 High Level Installation Levels 6th 7th 8th 9th 10th 11th 12th 13th 14th 15th 16th HAVC Fire Fighting Plumbing Electrical 92% 95% 93% 79% 90% 86% 88% 56% 86% 86% 88% 56% 59% 86% 78% 44% 54% 86% 56% 44% 54% 76% 54% 35% 10% 38% 0% 35% 0% 48% 0% 35% 0% 0% 0% 35% 0% 0% 0% 35% 0% 0% 0% 35% 38.89% 0.62% 4.21% 37.98% 0.17% 0.2 % %Pld %Act MEP Progress
  • 44. Architectural – Block Works at Level 6 Architectural Progress Block Works Levels 6th 7th 8th 9th 10th 11th 12th 13th 14th 15th 16th Block Works 95% 95% 95% 85% 40% 0% 15% 0% 0% 0% 0% 38.89% 0.17% 0.62% 4.21% 37.98% 0.2 % %Pld %Act
  • 45. Enabling Work– Pressure Grouting in Zone B Enabling Work Progress Zone B Construction Section B-B Due to the flood event that occurred in 2012 that caused major flooding to the site. Pressure Grouting was introduced as a method of reducing water infiltration. The pressure grouting is still ongoing and is scheduled to be completed by the 3rd week of June-14. After completing the pressure grouting, the excavation shall commence in Zone B and the remaining 11 stories of that zone will take approx. 10 months. The above event is the subject of an EOT claim and is being negotiated between DAMAC and ATC. Zone B 95% Pressure Grouting % Progress
  • 46. Current Progress Quality Assurance and Control
  • 47. DAMAC Heights Project Quality Assurance and Control 74% 26% NCR Closed % NCR Opened % 68 50 18 Total NCR Raised Total NCR Closed Total NCR Opened Statistics – May 2014 Area Performance Indicators Measure This Month Last Month Quality NCR Close Out Issued/Closed 68/50 59/41
  • 48. DAMAC Heights Project Quality Assurance and Control NCRs Root Cause Key Quality Improvement Measures Quality Improvement Measures • CurreŶtly ATC keeps suďŵittiŶg the ĐoŶĐrete test results iŶ tiŵely ŵaŶŶer as was instructed by AECOM. • AECOM iŶstruĐted ATC to suďŵit the struĐtural ĐlearaŶĐe ďefore the ĐoŵŵeŶĐeŵeŶt of MEP work. • AECOM is going to hold Quality Technical Meetings on weekly basis to monitor the quality.
  • 50. DAMAC Heights Project Health and Safety 1201 8 Work Force Average Improvement Notices 3 4 64 issued Near Misses First Aid Cases Tool Box Talks Statistics – May 2014 Area Performance Indicators Measure This Month Last Month Health and Safety Near Misses No. of Near Misses 3 0
  • 51. Project Risks Top 5 Risks
  • 52. DAMAC Heights Project Top 5 Risks Risk ID Risk Event Cause Rating Risk Response Risk Owner RS_01 Flooding in Zone B Existing ground cavities that allows for the flow of water through it. Pressure Grouting has commenced and is scheduled to be completed in June 14. DAMAC/ AECOM RS_02 Delays in possessing DEWA approval for LV shop drawings and delays in procuring LV Panels and Bus Bars. Late of issuing MEP IFC drawings. DAMAC has to finalize the ID design for FENDI Apartments and then RME has to issue the final MEP IFC drawings to ATC. DAMAC/R ME RS_03 Delays in pouring the slab of level 30 8 days estimated cycle will not be achieved as the slab will need for 2 weeks at least. AECOM highlighted this issue to ATC in the weekly progress meeting. ATC RS_04 Delays In MEP high level installations Delays in giving access from ATC to REMCO and then delays from REMCO in doing the installations due to the shortage of manpower. ATC has to give full access to REMCO on time. REMCO has to increase the allocated manpower in order to work concurrently in 5 levels. ATC/ REMCO RS_05 Delays in nomination of the PS items DAMAC's tenders floating/awarding process delayed. DAMAC has to expedite the PS items' procuring process in order to avoid delaying the site works. DAMAC 5 4 3 2 1 0 Critical Severe Manageable Negligible Risk Rating
  • 53. • Historical pre-existing issues. • Continuous design changes. • Soil improvement in Zone B. “ Working with a Commercial Developer demands a Bespoke Approach ” Project Challenges • Employer procurement system. • Management and coordination of client processes.. • Lack of detailed scheduling specification within the contract.