Project Execution Plan 2045 
Rev.0 
KHARAFI NATIONAL - UAE 
District Cooling for Rihan Heights 
Date: 30 Oct 2010 
AWI 202 Att. 2 Rev. 1 12 Sep. 2006 
PROJECT NO. (2045) 
PROJECT EXECUTION PLAN 
PART B: COMMERCIAL SECTION
Project Execution Plan 2045 
Rev.0 
1. TABLE OF CONTENTS 
Part B: Commercial 
1. Financial & Contractual.................................................................2 
2. Bonds & Insurance.........................................................................3 
3. Notifications – Time Requirements...............................................4 
4. Key Concerns.................................................................................5 
5. Subcontracts (Financial)................................................................6 
Appendices 
1. Overall Cost Summary Report 
2. Schedule of Price 
3. Cash Flow Chart 
a.Cash In Data 
b.Cash Out Data 
c.Cash Flow 
4. Signatures of Senior Project Staff 
5. Record Log for Claim Incidents 
AWI 202 Att. 2 Rev. 1 12 Sep. 2006 Page 1 of 6
Project Execution Plan 2045 
Rev.0 
. 
1. Financial & Contractual 
1.1 General 
This project is a District Cooling Plant for Rihan Heights; it is a fast track 
project to be Completed within 10 Months. 
· Type of Contract Lump Sum Fixed Price 
· Total Lump Sum Value AED 53,166,016.00 
· Provisional Sum ( Temporary 
Generator) AED 2,504,439.00 
· Profit & Risk AED 2,658,300 
· Contingency AED 469,798 
· Advance Payment 10% of Accepted Contract Value 
· Amount of performance Security 10% of Accepted Contract Value 
· Delay Damages for the Works 100,000.00 AED per calendar day of 
delay 
· Maximum amount of delay damages Ten (10) % of the final Contract 
Value 
· Start repayment of advance payment 2nd Interim Payment Certificate 
· Repayment amortization of advance 
payment 
10.50% deductions from each 
Payment Certificate 
· Percentage of retention Ten (10) % of each monthly interim 
payment 
· Limit of Retention Money Five (5)% of Contract Value 
1.2 Contract Price and payment 
· Plant and Material are entitled to an 
interim payment at cost for: Chiller 
Module, Cooling Tower, Electrical 
Modules and Heat exchanger 
20% upon Placement of Order 
40% When be ready for Shipment 
40% When be brought to site 
· Plant and Material are entitled to an 
interim payment at cost for: Pre 
insulated 
Pipes,Valves,Transformers, UPS, 
Fire 
Protection,Control&Automation 
System 
100% when be brought to site 
AWI 202 Att. 2 Rev. 1 12 Sep. 2006 Page 2 of6
Project Execution Plan 2045 
Rev.0 
. 
2.0 Bonds & 
Insurance 
By Client 
· Construction All Risk Insurance & Third Party Liabilities. 
By Kharafi National 
· Workmen’s Compensation Insurance, Third Party Liability, Employer’s Liability Insurance 
USD 5 million, Motor Vehicles Insurance, Contractor’s Plant & Equipment Insurance. 
· Marine Cargo Insurance. 
· Professional Indemnity in an amount of AED 10 million from the commencement date until 
the date which is twelve (12) years after the date of Taking Over Certificate. 
· The Performance Security shall be for an amount equivalent to ten (10) percent. 
AWI 202 Att. 2 Rev. 1 12 Sep. 2006 Page 3 of6
Project Execution Plan 2045 
Rev.0 
. 
3.0 Notifications -Time Requirements 
Time for Notice to commence Within 28 days of the date of letter of 
Acceptance (the commencement date 
is 18- July-2010 
Time for submission of time 
program 
Within 28 days of the 
Commencement Date 
Periods of submission of insurance 
(evidence of insurance). 
Within 28 days of the 
Commencement Date 
Relevant policies Within 28 days of the 
Commencement Date 
3.1 
3.1 Claims (additional payment and time) 
As per Sub-Clause 8.4 (c) of Contract Agreement 
The Contractor shall be entitled subject to Sub-Clause 20.1 [Contractor’s 
Claims] to an extension of the Time for Completion if and to the extent that 
completion for the purposes of Sub-Clause 10.1 [Taking Over of the Works 
and Sections] is or will be delayed by any of the following causes: 
(a) a Variation (unless an adjustment to the Time for Completion 
has been agreed under Sub-Clause 13.3 [Variation Procedure]), 
(b) a cause of delay giving an entitlement to extension of time under 
a Sub-Clause of these Conditions, or 
(c) Any delay, impediment or prevention caused by or attributable to 
the Employer, the Employer’s Personnel, or the Employer’s 
other contractors on the Site. 
If the Contractor considers himself to be entitled to an extension of the Time 
for Completion, the Contractor shall give notice to the Employer in 
accordance with Sub-Clause 20.1 [Contractor’s Claims]. When determining 
each extension of time under Sub-Clause 20.1, the Employer shall review 
previous determinations and may increase, but shall not decrease, the total 
extension of time. 
AWI 202 Att. 2 Rev. 1 12 Sep. 2006 Page 4 of6
Project Execution Plan 2045 
Rev.0 
. 
4.0 Key 
4.1 Material and Equipment Delivery 
· Material approvals and early procurement is critical to avoid further material 
delays whereas such delays will clear the way to have a risk of liquidated 
damages. 
· Material Submittal & Procurement log to be monitored closely. 
4.2 Work progress and control 
· Closely monitoring the progress in order to meet the Contract Completion Date. 
· Project Controls Procedure will be implemented. 
· Strategy for controlling manual manpower productivity to avoid the overrunning 
of man-hour budget. 
· Data base for recording productivity will be implemented. 
4.3 Overruns 
· Overrun is expected in the subcontracts for Hydrostatic test- Flushing and 
Chemical Cleaning as the estimated budget was found to be low. 
AWI 202 Att. 2 Rev. 1 12 Sep. 2006 Page 5 of6
Project Execution Plan 2045 
Rev.0 
. 
5.0 Subcontracts 
The following Item will be assigned to subcontractors 
Task No. Expenditure Type SUBCONTRACT Potential 
Subcontractors Value (AED) 
Mechanical 
4.15.07 Subcontracts Testing HVAC Initial Start-up Under process 115,017 
4.15.07 Subcontracts Testing HVAC Testing, Balancing Under process 80,018 
4.15.10 Subcontracts Special Systems Fire Fighting System Under process 122,425 
4.15.11 Subcontracts Special Systems Fire Fighting System Under process 826,767 
4.15.12 Subcontracts Construction Electric Chain Hoist Under process 40,843 
4.15.07 Subcontracts Construction Flushing /Chemical Flushing Under process 35,000 
4.15.07 Subcontracts Construction Testing & Commissioning Under process 25,000 
4.15.13 Subcontracts Construction Modular District Cooling Plant 
(Stellar) Stellar 21,253,000 
Electrical 
4.15.08 Subcontracts Construction HV Cable Laying & Termination NCI 45,500 
4.15.09 Subcontracts Special Systems Fire Alarm System Under process 19,941 
4.15.09 Subcontracts Special Systems Telecommunication System Under process 2,000 
4.15.08 Subcontracts Construction Cabling Under process 76,500 
4.15.14 Subcontracts Special Systems Special System - SCADA Control & 
Automation (Stellar) Stellar 1,026,596 
Civil Works 
4.15.02 Subcontracts Construction Waterproofing Beam Engineering 132,831 
4.15.04 Subcontracts Construction Steel Doors Under process 89,676 
4.15.04 Subcontracts Construction Wooden Doors Under process 12,805 
4.15.04 Subcontracts Construction Aluminum Windows, louver windows Under process 40,200 
4.15.05 Subcontracts Construction Metal Works Under process 5,250 
4.15.05 Subcontracts Construction Suspended Ceiling Under process 11,197 
4.15.02 Subcontracts Construction Epoxy Floor Coating Under process 15,235 
4.15.04 Subcontracts Construction Steel Gates Under process 38,750 
4.15.02 Subcontracts Construction GRP Lining Under process 182,280 
4.15.06 Subcontracts Construction Geotechnical Report Matrix Laboratory 13,529 
4.15.07 Subcontracts Construction Material Testing Under process 31,000 
4.15.05 Subcontracts Construction GRP Ladder Under process 10,712 
4.15.05 Subcontracts Construction Kitchen Equipments Under process 15,804 
Misc. 
4.15.06 Subcontracts Engineering Environment Assessment Study Under process 30,000 
4.15.15 Subcontracts Services Services during Defect Liability 
Period Under process 210,675 
4.15.06 Subcontracts Engineering Design (Stamping Purpose Only) DC PRO 125,000 
4.15.15 Subcontracts Services Operation & Maintenance for 12 
Months Under process 1,396,524 
AWI 202 Att. 2 Rev. 1 12 Sep. 2006 Page 6 of6

More Related Content

What's hot

61T01411 Monthly Report for Month of Nov 2014 for Valeo FS Project - 20141129
61T01411 Monthly Report for Month of Nov 2014 for Valeo FS Project - 2014112961T01411 Monthly Report for Month of Nov 2014 for Valeo FS Project - 20141129
61T01411 Monthly Report for Month of Nov 2014 for Valeo FS Project - 20141129James Zhang (Chi, Zhang)
 
Advanced training for construction management: CONTRACTS MANAGEMENT part 2 (...
Advanced training for  construction management: CONTRACTS MANAGEMENT part 2 (...Advanced training for  construction management: CONTRACTS MANAGEMENT part 2 (...
Advanced training for construction management: CONTRACTS MANAGEMENT part 2 (...Antonio Coladarce
 
Case study 1 effective and efficient communication
Case study 1 effective and efficient communicationCase study 1 effective and efficient communication
Case study 1 effective and efficient communicationMustafa Ozgoren
 
ICI FINAL REPORT PDF
ICI FINAL REPORT PDFICI FINAL REPORT PDF
ICI FINAL REPORT PDFClement Seong
 
CE1 - Final Reviewed - 10 Feb 2016
CE1 - Final Reviewed - 10 Feb 2016CE1 - Final Reviewed - 10 Feb 2016
CE1 - Final Reviewed - 10 Feb 2016Ali Issa
 
Sample wind apartment ins val rep
Sample wind apartment ins val repSample wind apartment ins val rep
Sample wind apartment ins val repIndependentgroup
 
Presentation 7-pp-final
Presentation 7-pp-finalPresentation 7-pp-final
Presentation 7-pp-finalWan Nee
 
1 regatta quay rehab boq 20120420 blank
1 regatta quay rehab boq 20120420 blank 1 regatta quay rehab boq 20120420 blank
1 regatta quay rehab boq 20120420 blank Thomas Magatu
 
Curriculum Vitae end to start 19-7-2016
Curriculum Vitae end to start 19-7-2016Curriculum Vitae end to start 19-7-2016
Curriculum Vitae end to start 19-7-2016Ayman Issa
 
Construction plan
Construction planConstruction plan
Construction planMianusama14
 
Partial possession-by-employer-29052017-finalized (1)
Partial possession-by-employer-29052017-finalized (1)Partial possession-by-employer-29052017-finalized (1)
Partial possession-by-employer-29052017-finalized (1)Tee Joanne
 

What's hot (20)

Monthly Progress Report No.13 - September 2011
Monthly Progress Report No.13 - September 2011Monthly Progress Report No.13 - September 2011
Monthly Progress Report No.13 - September 2011
 
Rihan Height Project Execution Plan-Rev00
Rihan Height Project Execution Plan-Rev00Rihan Height Project Execution Plan-Rev00
Rihan Height Project Execution Plan-Rev00
 
Kandil_Sameh_AR50360
Kandil_Sameh_AR50360Kandil_Sameh_AR50360
Kandil_Sameh_AR50360
 
Contract 2 - Project Progress Status. Oct-13
Contract 2 - Project Progress Status. Oct-13Contract 2 - Project Progress Status. Oct-13
Contract 2 - Project Progress Status. Oct-13
 
Cost Forecast Report
Cost Forecast ReportCost Forecast Report
Cost Forecast Report
 
01. P269 - Project Implementation Programme - Rev 00
01. P269 - Project Implementation Programme -  Rev 0001. P269 - Project Implementation Programme -  Rev 00
01. P269 - Project Implementation Programme - Rev 00
 
Cash Flow Portfolio
Cash Flow PortfolioCash Flow Portfolio
Cash Flow Portfolio
 
61T01411 Monthly Report for Month of Nov 2014 for Valeo FS Project - 20141129
61T01411 Monthly Report for Month of Nov 2014 for Valeo FS Project - 2014112961T01411 Monthly Report for Month of Nov 2014 for Valeo FS Project - 20141129
61T01411 Monthly Report for Month of Nov 2014 for Valeo FS Project - 20141129
 
Kandil Mohammed Ibrahim_Sameh_Dissertation
Kandil Mohammed Ibrahim_Sameh_DissertationKandil Mohammed Ibrahim_Sameh_Dissertation
Kandil Mohammed Ibrahim_Sameh_Dissertation
 
Advanced training for construction management: CONTRACTS MANAGEMENT part 2 (...
Advanced training for  construction management: CONTRACTS MANAGEMENT part 2 (...Advanced training for  construction management: CONTRACTS MANAGEMENT part 2 (...
Advanced training for construction management: CONTRACTS MANAGEMENT part 2 (...
 
Case study 1 effective and efficient communication
Case study 1 effective and efficient communicationCase study 1 effective and efficient communication
Case study 1 effective and efficient communication
 
ICI FINAL REPORT PDF
ICI FINAL REPORT PDFICI FINAL REPORT PDF
ICI FINAL REPORT PDF
 
CV - HV-1
CV - HV-1CV - HV-1
CV - HV-1
 
CE1 - Final Reviewed - 10 Feb 2016
CE1 - Final Reviewed - 10 Feb 2016CE1 - Final Reviewed - 10 Feb 2016
CE1 - Final Reviewed - 10 Feb 2016
 
Sample wind apartment ins val rep
Sample wind apartment ins val repSample wind apartment ins val rep
Sample wind apartment ins val rep
 
Presentation 7-pp-final
Presentation 7-pp-finalPresentation 7-pp-final
Presentation 7-pp-final
 
1 regatta quay rehab boq 20120420 blank
1 regatta quay rehab boq 20120420 blank 1 regatta quay rehab boq 20120420 blank
1 regatta quay rehab boq 20120420 blank
 
Curriculum Vitae end to start 19-7-2016
Curriculum Vitae end to start 19-7-2016Curriculum Vitae end to start 19-7-2016
Curriculum Vitae end to start 19-7-2016
 
Construction plan
Construction planConstruction plan
Construction plan
 
Partial possession-by-employer-29052017-finalized (1)
Partial possession-by-employer-29052017-finalized (1)Partial possession-by-employer-29052017-finalized (1)
Partial possession-by-employer-29052017-finalized (1)
 

Similar to District Cooling Plan Execution

Psscoc 2008 db contract
Psscoc 2008 db contractPsscoc 2008 db contract
Psscoc 2008 db contractVance Ang
 
Extension of Time (EoT) in Construction Project presentation
Extension of Time (EoT) in Construction Project presentationExtension of Time (EoT) in Construction Project presentation
Extension of Time (EoT) in Construction Project presentationAyush Joshi
 
FIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdf
FIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdfFIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdf
FIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdfBayuDarma4
 
CONDITIONS OF CONTRACT FOR WORKS OF CIVIL ENGINEERING CONSTRUCTION
CONDITIONS OF CONTRACT  FOR WORKS OF CIVIL  ENGINEERING CONSTRUCTIONCONDITIONS OF CONTRACT  FOR WORKS OF CIVIL  ENGINEERING CONSTRUCTION
CONDITIONS OF CONTRACT FOR WORKS OF CIVIL ENGINEERING CONSTRUCTIONBahzad5
 
Professional Practice II (Group Assignment)
Professional Practice II (Group Assignment)Professional Practice II (Group Assignment)
Professional Practice II (Group Assignment)Yee Len Wan
 
EOT Related Cost Compensation Determination
EOT Related Cost Compensation DeterminationEOT Related Cost Compensation Determination
EOT Related Cost Compensation DeterminationVimal Daluwatta
 
PP2 - Group Assignment
PP2 - Group AssignmentPP2 - Group Assignment
PP2 - Group AssignmentLin Hui
 
HM hub and NPD second masterclass seminar 6.11.15.PPT
HM hub and NPD second masterclass seminar 6.11.15.PPTHM hub and NPD second masterclass seminar 6.11.15.PPT
HM hub and NPD second masterclass seminar 6.11.15.PPTEuan Pirie
 
PP Seminar Tutorial 7
PP Seminar Tutorial 7PP Seminar Tutorial 7
PP Seminar Tutorial 7Farah Sham
 
Guidelines for Modified Scheme for setting up of Compound Semiconductors and ...
Guidelines for Modified Scheme for setting up of Compound Semiconductors and ...Guidelines for Modified Scheme for setting up of Compound Semiconductors and ...
Guidelines for Modified Scheme for setting up of Compound Semiconductors and ...ssuser668a58
 
Project Controls Expo, 18th Nov 2014 - "NEC3 Contracts – Managing Risk and Ch...
Project Controls Expo, 18th Nov 2014 - "NEC3 Contracts – Managing Risk and Ch...Project Controls Expo, 18th Nov 2014 - "NEC3 Contracts – Managing Risk and Ch...
Project Controls Expo, 18th Nov 2014 - "NEC3 Contracts – Managing Risk and Ch...Project Controls Expo
 
time bar clauses
time bar clausestime bar clauses
time bar clausesAMILA GAYAN
 
Ss 07 training fidic moustafa ismail 2018__ lec 7B
Ss 07 training fidic moustafa ismail  2018__ lec 7BSs 07 training fidic moustafa ismail  2018__ lec 7B
Ss 07 training fidic moustafa ismail 2018__ lec 7BMoustafa Ismail Abu Dief
 

Similar to District Cooling Plan Execution (20)

Claims and insolvencies (1)
Claims and insolvencies (1)Claims and insolvencies (1)
Claims and insolvencies (1)
 
Psscoc 2008 db contract
Psscoc 2008 db contractPsscoc 2008 db contract
Psscoc 2008 db contract
 
Cl report final
Cl report finalCl report final
Cl report final
 
Extension of Time (EoT) in Construction Project presentation
Extension of Time (EoT) in Construction Project presentationExtension of Time (EoT) in Construction Project presentation
Extension of Time (EoT) in Construction Project presentation
 
FIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdf
FIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdfFIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdf
FIDIC delay damages –v- Liquidated damages ( PDFDrive ).pdf
 
CONDITIONS OF CONTRACT FOR WORKS OF CIVIL ENGINEERING CONSTRUCTION
CONDITIONS OF CONTRACT  FOR WORKS OF CIVIL  ENGINEERING CONSTRUCTIONCONDITIONS OF CONTRACT  FOR WORKS OF CIVIL  ENGINEERING CONSTRUCTION
CONDITIONS OF CONTRACT FOR WORKS OF CIVIL ENGINEERING CONSTRUCTION
 
Professional Practice II (Group Assignment)
Professional Practice II (Group Assignment)Professional Practice II (Group Assignment)
Professional Practice II (Group Assignment)
 
EOT Related Cost Compensation Determination
EOT Related Cost Compensation DeterminationEOT Related Cost Compensation Determination
EOT Related Cost Compensation Determination
 
PP2 - Group Assignment
PP2 - Group AssignmentPP2 - Group Assignment
PP2 - Group Assignment
 
HM hub and NPD second masterclass seminar 6.11.15.PPT
HM hub and NPD second masterclass seminar 6.11.15.PPTHM hub and NPD second masterclass seminar 6.11.15.PPT
HM hub and NPD second masterclass seminar 6.11.15.PPT
 
PP Seminar Tutorial 7
PP Seminar Tutorial 7PP Seminar Tutorial 7
PP Seminar Tutorial 7
 
Guidelines for Modified Scheme for setting up of Compound Semiconductors and ...
Guidelines for Modified Scheme for setting up of Compound Semiconductors and ...Guidelines for Modified Scheme for setting up of Compound Semiconductors and ...
Guidelines for Modified Scheme for setting up of Compound Semiconductors and ...
 
Project Controls Expo, 18th Nov 2014 - "NEC3 Contracts – Managing Risk and Ch...
Project Controls Expo, 18th Nov 2014 - "NEC3 Contracts – Managing Risk and Ch...Project Controls Expo, 18th Nov 2014 - "NEC3 Contracts – Managing Risk and Ch...
Project Controls Expo, 18th Nov 2014 - "NEC3 Contracts – Managing Risk and Ch...
 
Cl presentation
Cl presentationCl presentation
Cl presentation
 
time bar clauses
time bar clausestime bar clauses
time bar clauses
 
Nes 362
Nes 362Nes 362
Nes 362
 
Cl compilation
Cl compilationCl compilation
Cl compilation
 
Ss 07 training fidic moustafa ismail 2018__ lec 7B
Ss 07 training fidic moustafa ismail  2018__ lec 7BSs 07 training fidic moustafa ismail  2018__ lec 7B
Ss 07 training fidic moustafa ismail 2018__ lec 7B
 
Essentials of EOT Claims
Essentials of EOT ClaimsEssentials of EOT Claims
Essentials of EOT Claims
 
MSP
MSPMSP
MSP
 

More from Sam Kendall, MSc, BSc Civil Eng., PMP®, MIEAust

More from Sam Kendall, MSc, BSc Civil Eng., PMP®, MIEAust (18)

Summary Progress Of Facade Works
Summary Progress Of Facade WorksSummary Progress Of Facade Works
Summary Progress Of Facade Works
 
Summary Progress Of Concrete Works
Summary Progress Of Concrete WorksSummary Progress Of Concrete Works
Summary Progress Of Concrete Works
 
Progress Of Ceiling Per Floors
Progress Of Ceiling Per FloorsProgress Of Ceiling Per Floors
Progress Of Ceiling Per Floors
 
N1
N1N1
N1
 
Progress Of Slab
Progress Of SlabProgress Of Slab
Progress Of Slab
 
Overall Progress S-Curve For Ceiling
Overall Progress S-Curve For CeilingOverall Progress S-Curve For Ceiling
Overall Progress S-Curve For Ceiling
 
Overall Progress S-Curve For Facades
Overall Progress S-Curve For FacadesOverall Progress S-Curve For Facades
Overall Progress S-Curve For Facades
 
Overall Progress S-Curve For Elevators
Overall Progress S-Curve For ElevatorsOverall Progress S-Curve For Elevators
Overall Progress S-Curve For Elevators
 
Overall Progres S-Curve For Concrete Works
Overall Progres S-Curve For Concrete WorksOverall Progres S-Curve For Concrete Works
Overall Progres S-Curve For Concrete Works
 
13. Overall S-Curve
13. Overall S-Curve13. Overall S-Curve
13. Overall S-Curve
 
Building-Structure Planning Model
Building-Structure Planning ModelBuilding-Structure Planning Model
Building-Structure Planning Model
 
Final Submission EOT 1
Final Submission EOT 1Final Submission EOT 1
Final Submission EOT 1
 
Resources Histograms
Resources HistogramsResources Histograms
Resources Histograms
 
Resources Calculations for Bldg. A
Resources Calculations for Bldg. AResources Calculations for Bldg. A
Resources Calculations for Bldg. A
 
Kandil_Sameh_AR50123
Kandil_Sameh_AR50123Kandil_Sameh_AR50123
Kandil_Sameh_AR50123
 
Kandil_Sameh_CPMPart 3 _b
Kandil_Sameh_CPMPart 3 _bKandil_Sameh_CPMPart 3 _b
Kandil_Sameh_CPMPart 3 _b
 
Kandil_Sameh_CPMPart 5 _b
Kandil_Sameh_CPMPart 5 _bKandil_Sameh_CPMPart 5 _b
Kandil_Sameh_CPMPart 5 _b
 
Kandil_Sameh_AR50411_Part 1 to 5
Kandil_Sameh_AR50411_Part 1 to 5Kandil_Sameh_AR50411_Part 1 to 5
Kandil_Sameh_AR50411_Part 1 to 5
 

District Cooling Plan Execution

  • 1. Project Execution Plan 2045 Rev.0 KHARAFI NATIONAL - UAE District Cooling for Rihan Heights Date: 30 Oct 2010 AWI 202 Att. 2 Rev. 1 12 Sep. 2006 PROJECT NO. (2045) PROJECT EXECUTION PLAN PART B: COMMERCIAL SECTION
  • 2. Project Execution Plan 2045 Rev.0 1. TABLE OF CONTENTS Part B: Commercial 1. Financial & Contractual.................................................................2 2. Bonds & Insurance.........................................................................3 3. Notifications – Time Requirements...............................................4 4. Key Concerns.................................................................................5 5. Subcontracts (Financial)................................................................6 Appendices 1. Overall Cost Summary Report 2. Schedule of Price 3. Cash Flow Chart a.Cash In Data b.Cash Out Data c.Cash Flow 4. Signatures of Senior Project Staff 5. Record Log for Claim Incidents AWI 202 Att. 2 Rev. 1 12 Sep. 2006 Page 1 of 6
  • 3. Project Execution Plan 2045 Rev.0 . 1. Financial & Contractual 1.1 General This project is a District Cooling Plant for Rihan Heights; it is a fast track project to be Completed within 10 Months. · Type of Contract Lump Sum Fixed Price · Total Lump Sum Value AED 53,166,016.00 · Provisional Sum ( Temporary Generator) AED 2,504,439.00 · Profit & Risk AED 2,658,300 · Contingency AED 469,798 · Advance Payment 10% of Accepted Contract Value · Amount of performance Security 10% of Accepted Contract Value · Delay Damages for the Works 100,000.00 AED per calendar day of delay · Maximum amount of delay damages Ten (10) % of the final Contract Value · Start repayment of advance payment 2nd Interim Payment Certificate · Repayment amortization of advance payment 10.50% deductions from each Payment Certificate · Percentage of retention Ten (10) % of each monthly interim payment · Limit of Retention Money Five (5)% of Contract Value 1.2 Contract Price and payment · Plant and Material are entitled to an interim payment at cost for: Chiller Module, Cooling Tower, Electrical Modules and Heat exchanger 20% upon Placement of Order 40% When be ready for Shipment 40% When be brought to site · Plant and Material are entitled to an interim payment at cost for: Pre insulated Pipes,Valves,Transformers, UPS, Fire Protection,Control&Automation System 100% when be brought to site AWI 202 Att. 2 Rev. 1 12 Sep. 2006 Page 2 of6
  • 4. Project Execution Plan 2045 Rev.0 . 2.0 Bonds & Insurance By Client · Construction All Risk Insurance & Third Party Liabilities. By Kharafi National · Workmen’s Compensation Insurance, Third Party Liability, Employer’s Liability Insurance USD 5 million, Motor Vehicles Insurance, Contractor’s Plant & Equipment Insurance. · Marine Cargo Insurance. · Professional Indemnity in an amount of AED 10 million from the commencement date until the date which is twelve (12) years after the date of Taking Over Certificate. · The Performance Security shall be for an amount equivalent to ten (10) percent. AWI 202 Att. 2 Rev. 1 12 Sep. 2006 Page 3 of6
  • 5. Project Execution Plan 2045 Rev.0 . 3.0 Notifications -Time Requirements Time for Notice to commence Within 28 days of the date of letter of Acceptance (the commencement date is 18- July-2010 Time for submission of time program Within 28 days of the Commencement Date Periods of submission of insurance (evidence of insurance). Within 28 days of the Commencement Date Relevant policies Within 28 days of the Commencement Date 3.1 3.1 Claims (additional payment and time) As per Sub-Clause 8.4 (c) of Contract Agreement The Contractor shall be entitled subject to Sub-Clause 20.1 [Contractor’s Claims] to an extension of the Time for Completion if and to the extent that completion for the purposes of Sub-Clause 10.1 [Taking Over of the Works and Sections] is or will be delayed by any of the following causes: (a) a Variation (unless an adjustment to the Time for Completion has been agreed under Sub-Clause 13.3 [Variation Procedure]), (b) a cause of delay giving an entitlement to extension of time under a Sub-Clause of these Conditions, or (c) Any delay, impediment or prevention caused by or attributable to the Employer, the Employer’s Personnel, or the Employer’s other contractors on the Site. If the Contractor considers himself to be entitled to an extension of the Time for Completion, the Contractor shall give notice to the Employer in accordance with Sub-Clause 20.1 [Contractor’s Claims]. When determining each extension of time under Sub-Clause 20.1, the Employer shall review previous determinations and may increase, but shall not decrease, the total extension of time. AWI 202 Att. 2 Rev. 1 12 Sep. 2006 Page 4 of6
  • 6. Project Execution Plan 2045 Rev.0 . 4.0 Key 4.1 Material and Equipment Delivery · Material approvals and early procurement is critical to avoid further material delays whereas such delays will clear the way to have a risk of liquidated damages. · Material Submittal & Procurement log to be monitored closely. 4.2 Work progress and control · Closely monitoring the progress in order to meet the Contract Completion Date. · Project Controls Procedure will be implemented. · Strategy for controlling manual manpower productivity to avoid the overrunning of man-hour budget. · Data base for recording productivity will be implemented. 4.3 Overruns · Overrun is expected in the subcontracts for Hydrostatic test- Flushing and Chemical Cleaning as the estimated budget was found to be low. AWI 202 Att. 2 Rev. 1 12 Sep. 2006 Page 5 of6
  • 7. Project Execution Plan 2045 Rev.0 . 5.0 Subcontracts The following Item will be assigned to subcontractors Task No. Expenditure Type SUBCONTRACT Potential Subcontractors Value (AED) Mechanical 4.15.07 Subcontracts Testing HVAC Initial Start-up Under process 115,017 4.15.07 Subcontracts Testing HVAC Testing, Balancing Under process 80,018 4.15.10 Subcontracts Special Systems Fire Fighting System Under process 122,425 4.15.11 Subcontracts Special Systems Fire Fighting System Under process 826,767 4.15.12 Subcontracts Construction Electric Chain Hoist Under process 40,843 4.15.07 Subcontracts Construction Flushing /Chemical Flushing Under process 35,000 4.15.07 Subcontracts Construction Testing & Commissioning Under process 25,000 4.15.13 Subcontracts Construction Modular District Cooling Plant (Stellar) Stellar 21,253,000 Electrical 4.15.08 Subcontracts Construction HV Cable Laying & Termination NCI 45,500 4.15.09 Subcontracts Special Systems Fire Alarm System Under process 19,941 4.15.09 Subcontracts Special Systems Telecommunication System Under process 2,000 4.15.08 Subcontracts Construction Cabling Under process 76,500 4.15.14 Subcontracts Special Systems Special System - SCADA Control & Automation (Stellar) Stellar 1,026,596 Civil Works 4.15.02 Subcontracts Construction Waterproofing Beam Engineering 132,831 4.15.04 Subcontracts Construction Steel Doors Under process 89,676 4.15.04 Subcontracts Construction Wooden Doors Under process 12,805 4.15.04 Subcontracts Construction Aluminum Windows, louver windows Under process 40,200 4.15.05 Subcontracts Construction Metal Works Under process 5,250 4.15.05 Subcontracts Construction Suspended Ceiling Under process 11,197 4.15.02 Subcontracts Construction Epoxy Floor Coating Under process 15,235 4.15.04 Subcontracts Construction Steel Gates Under process 38,750 4.15.02 Subcontracts Construction GRP Lining Under process 182,280 4.15.06 Subcontracts Construction Geotechnical Report Matrix Laboratory 13,529 4.15.07 Subcontracts Construction Material Testing Under process 31,000 4.15.05 Subcontracts Construction GRP Ladder Under process 10,712 4.15.05 Subcontracts Construction Kitchen Equipments Under process 15,804 Misc. 4.15.06 Subcontracts Engineering Environment Assessment Study Under process 30,000 4.15.15 Subcontracts Services Services during Defect Liability Period Under process 210,675 4.15.06 Subcontracts Engineering Design (Stamping Purpose Only) DC PRO 125,000 4.15.15 Subcontracts Services Operation & Maintenance for 12 Months Under process 1,396,524 AWI 202 Att. 2 Rev. 1 12 Sep. 2006 Page 6 of6