SlideShare a Scribd company logo
1 of 35
Download to read offline
PREPARED
BY
SANJEEV
SINGH 12/15/2020SNJV432@GMAIL.COM 1
QUALITY CONTROL
• The designer(s), manufacture and
contractors must ensure that
minimum quality standards are met
and maintained.
• They must make sure that the
building will perform as required
and expected by its owners and
occupiers.
12/15/2020SNJV432@GMAIL.COM 2
QUALITY CONTROL
12/15/2020SNJV432@GMAIL.COM 3
QUALITY CONTROL
12/15/2020SNJV432@GMAIL.COM 4
QUALITY CONTROL
12/15/2020SNJV432@GMAIL.COM 5
ISO 9001 & QUALITY
ASSURANCE
1. process approach to system.
2. process measurement.
3. Process management.
4. customer satisfaction
monitoring.
5. continual improvement.
12/15/2020SNJV432@GMAIL.COM 6
ISO 9001 & QUALITY
ASSURANCE
ISO 9001: 2000 also puts a stronger
emphasis on the quality management
function of the organization as distinct
from:
1. quality assurance
2. quality control activities
3. five requirements.
12/15/2020SNJV432@GMAIL.COM 7
ISO 14000 & QUALITY ASSURANCE
❑ The ISO 14000 series consist of
five standards:
1.Environmental management systems
2.Environmental auditing
3.Environmental labelling
4.Environmental performance evaluation
5. Life cycle assessment
12/15/2020SNJV432@GMAIL.COM 8
QUALITY CONTROL
Construction Quality and Construction
Quality Control (QC)Inspectors
1. All construction processes,
procedures, and workmanship must
be inspected Quality Inspectors.
2. Inspection should include the
observations, measurements, and
documentation specified in
contractor’s Method Statement and
the Contract Documents. 12/15/2020SNJV432@GMAIL.COM 9
QUALITY CONTROL
Quality Control (QC) Testing Staff
Sampling and testing of field-tested Materials in
accordance with the contract documents.
Certified Testing Laboratory
Independent Referee Laboratory
Materials Quality Management
Contractor is responsible for providing Quality
Control (QC) sampling and testing, and carrying
out Quality Level Analysis during production to
submit when required by the client or client
representative.
12/15/2020SNJV432@GMAIL.COM 10
QUALITY CONTROL
Quality Assurance
Client’s QA Program defines the responsibilities
and roles of both contractor and it’s sub-
contractors.
The QA Program is contained in the contract
document.
The contractor is responsible for providing QC
sampling and testing of all the Materials
specified in the contract document. 12/15/2020SNJV432@GMAIL.COM 11
QUALITY CONTROL
In practice Building Control Officers (BCOs)and
inspectors are prepared to provide some advice
where they can and if they visit.
Large Private Developments –Sites where
main contractor is client
These sites are often those being developed by a
large private house builder.
The house builder/developer will often have a
project manager and site manager.
Larger sites-assistant site managers who have
responsibility for quality control. 12/15/2020SNJV432@GMAIL.COM 12
QUALITY CONTROL
•BCOs and inspectors from the Local
Authorities are prepared to provide some
advice where they can and if they visit.
• However, it is not their role.
• Often, the emphasis, on sites of this nature,
is on getting the work done as quickly as
possible to the minimum standard required
to satisfy the warranty provider and possibly
the BCO.
• This emphasis has developed as a result of
commercial pressures on time and finance
and the lack of skilled tradesmen. 12/15/2020SNJV432@GMAIL.COM 13
QUALITY CONTROL
Large Private Developments
(where main contractor is not
client)
1. The project manager/site manager for
the contractor have to satisfy the
client or their agents that the work
done meets the standard required.
2. The standard required will normally
have been agreed as part of the
original contract and the
specification.
12/15/2020SNJV432@GMAIL.COM 14
QUALITY CONTROL
It is the responsibility of the:
1. project manager
2. site manager/
3. assistant site managers
4. foremen to ensure that the
quality of work carried out
meets the requirement of the
specification. 12/15/2020SNJV432@GMAIL.COM 15
QUALITY CONTROL
Under Design & Build contracts:
• Most of the responsibility for quality
control of design, specification and
construction rests with the main
contractor.
• Under many forms of Design & Build
contract the client is able to check build
quality through the use of:
1. their own Clerk ofWorks
2. third-party inspection service providers.
12/15/2020SNJV432@GMAIL.COM 16
QUALITY CONTROL
Quality Assurance Schemes
The National Standards Authority of
Ireland (NSAI) is Ireland’s Standards
body.
They facilitate the development of
voluntary standard documents.
NSAI is a leading supplier of product and
system certification services, both
domestically and internationally.
The NSAI represent Irish interests in
European and international Standards
bodies.
12/15/2020SNJV432@GMAIL.COM 17
QUALITY CONTROL
The NSAI are responsible for the Timber
Frame Manufacturers’ Quality Approval
Scheme.
The scheme does not apply to timber
frame buildings, which are fabricated on
site (stick buildings).
It is based on the requirements of the
Irish Building Regulations, TGDs and
relevant Irish and British Standards.12/15/2020SNJV432@GMAIL.COM 18
QUALITY CONTROL
It considers:
Design
QA procedures related to design and
manufacture
Material specifications
Manufacturing process
Manufacturing information and
documentation
Production facilities 12/15/2020SNJV432@GMAIL.COM 19
QUALITY CONTROL
Site information and documentation
Quality records
Personnel
Training
12/15/2020SNJV432@GMAIL.COM 20
QUALITY CONTROL
HomeBond is a private company set up by the
Construction Industry Federation (CIF).
It operates independently of the CIF
HomeBond is a warrantor and inspects
constructions to determine:
‘good practice’ and/or HomeBond requirements
are being met.
HomeBond does not underwrite developments
but provides cover in the event that the
developments are not soundly constructed with
the appropriate materials. 12/15/2020SNJV432@GMAIL.COM 21
QUALITY CONTROL
HomeBond covers the dwelling against:
Major structural defects such as:
1. major defect in the foundations of a
dwelling
2. the load-bearing part of its floors
3. walls and roof or retaining walls
necessary for its support which affectsthe
structural stability of the dwelling’.
12/15/2020SNJV432@GMAIL.COM 22
QUALITY CONTROL
Major non-structural defects which
might lead to problems such as:
1.Smoke
2.Water penetration from an adjacent
building into the completed home.
12/15/2020SNJV432@GMAIL.COM 23
QUALITY CONTROL
A variety of sources of technical information
exists for those involved in the design,
manufacture and construction of timber frame
buildings in Ireland.
The principal sources of technical information for
each of the disciplines involved is set out below:
Architects
Guidance is given in the Technical Guidance
Documents on how to meet the requirements of
the National Building Regulations.
12/15/2020SNJV432@GMAIL.COM 24
QUALITY CONTROL
The requirements of HomeBond are
published in their House Building
Manual.
Appendix B of the House Building Manual
publication relates to timber frame
construction.
Additional guidance, relating specifically
to on-site practice is given in their Right
On Site leaflets.
12/15/2020SNJV432@GMAIL.COM 25
QUALITY CONTROL
The TRADA Technology publication (Timber
Frame Construction) provides a source of
standard details and advice on issues such as:
1. good practice guide
2 . a site supervisor checklist
3. guidance on appropriate material specifications.
In-company standard details or standard details
issued by the timber frame manufacturer.
WOODSPEC
TRADA/BRE Design Guide for Multi Storey
Timber Frame Buildings – Timber Stairs.12/15/2020SNJV432@GMAIL.COM 26
QUALITY CONTROL
Engineers
Guidance is given in the Technical Guidance
Documents on how to meet the
requirements of the National Building
Regulations.
BS 5268: Part 2: 1996: Structural use of
timber – Code of practice for permissible
stress design, materials and workmanship.
12/15/2020SNJV432@GMAIL.COM 27
QUALITY CONTROL
IS 193: 1996: Timber trussed rafters
for roofs.
IS 444: 1998: Use ofstructural
timber in buildings.
BS 5268: Part 4: 1978: Structural
use of timber – Fire resistance of
timber structures.
Section 4.1. Recommendations for
calculating the fire resistance of
timber members. 12/15/2020SNJV432@GMAIL.COM 28
QUALITY CONTROL
BS 5268: Part 4: 1978: Structural use of
timber – Fire resistance of timber
structures.
Section 4.2. Recommendations for
calculating the fire resistance of timber
stud walls and joisted floor constructions.
BS 5268: Part 6: 1996: Structural use of
timber – Code of practice for timber
framed walls.
Section 6.1. Dwellings not exceeding four
storeys.
12/15/2020SNJV432@GMAIL.COM 29
QUALITY CONTROL
Site Managers
In-company documentation.
The requirements of HomeBond are published in
their House Building Manual.
Appendix B of the House Building Manual
publication relates to timber frame construction.
Additional guidance, relating specifically to on-
site practice is given in their Right On Site
leaflets.
12/15/2020SNJV432@GMAIL.COM 30
QUALITY CONTROL
The TRADA Technology publication, Timber
Frame Construction, provides a source of
standard details and advice on good practice
including a site supervisors’ checklist and
guidance on appropriate material specifications.
Guidance is given in the Technical Guidance
Documents on how to meet the requirements of
the National Building Regulations.
TRADA/BRE Design Guide for Multi Storey
Timber Frame Buildings – Timber Stairs.
12/15/2020SNJV432@GMAIL.COM 31
QUALITY CONTROL
Clerk of Works
In-company documentation.
The requirements of HomeBond are published in
their House Building Manual.
Appendix B of the House Building Manual
publication relates to timber frame construction.
Additional guidance, relating specifically to on-
site practice is given in their Right On Site
leaflets.
12/15/2020SNJV432@GMAIL.COM 32
QUALITY CONTROL
The TRADA Technology publication,
Timber Frame Construction,
provides a source of standard details
and advice on good practice
including a site supervisors’
checklist and guidance on
appropriate material specifications.
12/15/2020SNJV432@GMAIL.COM 33
QUALITY CONTROL
Guidance is given in the Technical
Guidance Documents on how to meet
the requirements of the National
Building Regulations.
TRADA/BRE Design Guide for Multi
Storey Timber Frame Buildings –
Timber Stairs.
12/15/2020SNJV432@GMAIL.COM 34
12/15/2020SNJV432@GMAIL.COM 35

More Related Content

What's hot

Stages In Construction
Stages In ConstructionStages In Construction
Stages In ConstructionAB MAKASANA
 
Quality in Construction
Quality in ConstructionQuality in Construction
Quality in ConstructionDr K M SONI
 
estimation and quantity surveying
estimation and quantity surveyingestimation and quantity surveying
estimation and quantity surveyingsooricivil
 
1. STUDY ON QUALITY ASSURANCE AND QUALITY CONTROL MANAGEMENT SYSTEM IN 20 STO...
1.	STUDY ON QUALITY ASSURANCE AND QUALITY CONTROL MANAGEMENT SYSTEM IN 20 STO...1.	STUDY ON QUALITY ASSURANCE AND QUALITY CONTROL MANAGEMENT SYSTEM IN 20 STO...
1. STUDY ON QUALITY ASSURANCE AND QUALITY CONTROL MANAGEMENT SYSTEM IN 20 STO...AELC
 
Construction Management & Equipments
Construction Management & EquipmentsConstruction Management & Equipments
Construction Management & EquipmentsGAURAV. H .TANDON
 
Construction management
Construction managementConstruction management
Construction managementUsama Khalid
 
Quality control of concrete
Quality control of concreteQuality control of concrete
Quality control of concreteGaurang Kakadiya
 
Rate analysis in civil engineering
Rate analysis in civil engineeringRate analysis in civil engineering
Rate analysis in civil engineeringKailash Chander
 
Specifications, reports and tenders
Specifications, reports and tendersSpecifications, reports and tenders
Specifications, reports and tendersgayu pandian
 
02 Construction Projects
02 Construction Projects02 Construction Projects
02 Construction Projectsakashpadole
 
Construction phases
Construction phasesConstruction phases
Construction phasesMeesum Zaidi
 
Residential building construction ppt
Residential building construction pptResidential building construction ppt
Residential building construction pptBeing Deepak
 
Durability of concrete
Durability of concreteDurability of concrete
Durability of concreteRajesh Prasad
 
MEASUREMENT PDF
MEASUREMENT PDFMEASUREMENT PDF
MEASUREMENT PDFIDHAMUKI
 

What's hot (20)

Stages In Construction
Stages In ConstructionStages In Construction
Stages In Construction
 
Quality in Construction
Quality in ConstructionQuality in Construction
Quality in Construction
 
Formwork
FormworkFormwork
Formwork
 
Quality management
Quality managementQuality management
Quality management
 
estimation and quantity surveying
estimation and quantity surveyingestimation and quantity surveying
estimation and quantity surveying
 
Concrete technology
Concrete technologyConcrete technology
Concrete technology
 
1. STUDY ON QUALITY ASSURANCE AND QUALITY CONTROL MANAGEMENT SYSTEM IN 20 STO...
1.	STUDY ON QUALITY ASSURANCE AND QUALITY CONTROL MANAGEMENT SYSTEM IN 20 STO...1.	STUDY ON QUALITY ASSURANCE AND QUALITY CONTROL MANAGEMENT SYSTEM IN 20 STO...
1. STUDY ON QUALITY ASSURANCE AND QUALITY CONTROL MANAGEMENT SYSTEM IN 20 STO...
 
Construction Management & Equipments
Construction Management & EquipmentsConstruction Management & Equipments
Construction Management & Equipments
 
Construction management
Construction managementConstruction management
Construction management
 
Quality control of concrete
Quality control of concreteQuality control of concrete
Quality control of concrete
 
Rate analysis in civil engineering
Rate analysis in civil engineeringRate analysis in civil engineering
Rate analysis in civil engineering
 
Specifications, reports and tenders
Specifications, reports and tendersSpecifications, reports and tenders
Specifications, reports and tenders
 
02 Construction Projects
02 Construction Projects02 Construction Projects
02 Construction Projects
 
Construction phases
Construction phasesConstruction phases
Construction phases
 
Residential building construction ppt
Residential building construction pptResidential building construction ppt
Residential building construction ppt
 
Fresh and harden properties of concrete
Fresh and harden properties of concreteFresh and harden properties of concrete
Fresh and harden properties of concrete
 
Durability of concrete
Durability of concreteDurability of concrete
Durability of concrete
 
Formwork
FormworkFormwork
Formwork
 
MEASUREMENT PDF
MEASUREMENT PDFMEASUREMENT PDF
MEASUREMENT PDF
 
Conquas
ConquasConquas
Conquas
 

Similar to Quality control IN CONSTRUCTION

Certificado BBA - Aislamiento con productos Synthesia para suelos
Certificado BBA - Aislamiento con productos Synthesia para suelosCertificado BBA - Aislamiento con productos Synthesia para suelos
Certificado BBA - Aislamiento con productos Synthesia para suelosSynthesia Technology
 
Certificado BBA - Aislamiento con productos Synthesia para paredes
Certificado BBA - Aislamiento con productos Synthesia para paredesCertificado BBA - Aislamiento con productos Synthesia para paredes
Certificado BBA - Aislamiento con productos Synthesia para paredesSynthesia Technology
 
Mobile ManufactureFinal.docx
   Mobile ManufactureFinal.docx   Mobile ManufactureFinal.docx
Mobile ManufactureFinal.docxrobert345678
 
bsi BIM solutions | Ecobuild 2016
bsi BIM solutions | Ecobuild 2016bsi BIM solutions | Ecobuild 2016
bsi BIM solutions | Ecobuild 2016The NBS
 
5th Qatar BIM User Day, Understanding stakeholder roles in BIM
5th Qatar BIM User Day, Understanding stakeholder roles in BIM5th Qatar BIM User Day, Understanding stakeholder roles in BIM
5th Qatar BIM User Day, Understanding stakeholder roles in BIMBIM User Day
 
Certificado BBA - Aislamiento con productos Synthesia para rehabilitación de ...
Certificado BBA - Aislamiento con productos Synthesia para rehabilitación de ...Certificado BBA - Aislamiento con productos Synthesia para rehabilitación de ...
Certificado BBA - Aislamiento con productos Synthesia para rehabilitación de ...Synthesia Technology
 
Power Generation_Project Brief Instructions 2015
Power Generation_Project Brief Instructions 2015Power Generation_Project Brief Instructions 2015
Power Generation_Project Brief Instructions 2015Graeme Simmers
 
Peter Cox - Waterproofing Brickwork Certificate
Peter Cox - Waterproofing Brickwork CertificatePeter Cox - Waterproofing Brickwork Certificate
Peter Cox - Waterproofing Brickwork CertificatePeter_Cox
 
Best Practices for Improving the PCB Supply Chain: Part II
Best Practices for Improving the PCB Supply Chain: Part IIBest Practices for Improving the PCB Supply Chain: Part II
Best Practices for Improving the PCB Supply Chain: Part IICheryl Tulkoff
 
CIOB_Code_of_Quality_Management.pdf
CIOB_Code_of_Quality_Management.pdfCIOB_Code_of_Quality_Management.pdf
CIOB_Code_of_Quality_Management.pdfLuisMogrovejo3
 
CIOB_Code_of_Quality_Management.pdf
CIOB_Code_of_Quality_Management.pdfCIOB_Code_of_Quality_Management.pdf
CIOB_Code_of_Quality_Management.pdfLuisMogrovejo3
 
IRJET- Review on Study of Quality Practices in Construction
IRJET- Review on Study of Quality Practices in ConstructionIRJET- Review on Study of Quality Practices in Construction
IRJET- Review on Study of Quality Practices in ConstructionIRJET Journal
 
Improve the Productivity of Building Construction Project using Clash detecti...
Improve the Productivity of Building Construction Project using Clash detecti...Improve the Productivity of Building Construction Project using Clash detecti...
Improve the Productivity of Building Construction Project using Clash detecti...IRJET Journal
 
Certificado BBA - Aislamiento Synthesia para cubiertas
Certificado BBA - Aislamiento Synthesia para cubiertasCertificado BBA - Aislamiento Synthesia para cubiertas
Certificado BBA - Aislamiento Synthesia para cubiertasSynthesia Technology
 
National BIM Conference 2015 - JHunt
National BIM Conference 2015 - JHuntNational BIM Conference 2015 - JHunt
National BIM Conference 2015 - JHuntJohn Hunt
 
WPC Door Manufacturing Plant Project Report.pptx
WPC Door Manufacturing Plant Project Report.pptxWPC Door Manufacturing Plant Project Report.pptx
WPC Door Manufacturing Plant Project Report.pptxsurajimarc0777
 
Areca Nut Processing Plant Project Report.pptx
Areca Nut Processing Plant Project Report.pptxAreca Nut Processing Plant Project Report.pptx
Areca Nut Processing Plant Project Report.pptxsurajimarc0777
 

Similar to Quality control IN CONSTRUCTION (20)

Certificado BBA - Aislamiento con productos Synthesia para suelos
Certificado BBA - Aislamiento con productos Synthesia para suelosCertificado BBA - Aislamiento con productos Synthesia para suelos
Certificado BBA - Aislamiento con productos Synthesia para suelos
 
Certificado BBA - Aislamiento con productos Synthesia para paredes
Certificado BBA - Aislamiento con productos Synthesia para paredesCertificado BBA - Aislamiento con productos Synthesia para paredes
Certificado BBA - Aislamiento con productos Synthesia para paredes
 
Mobile ManufactureFinal.docx
   Mobile ManufactureFinal.docx   Mobile ManufactureFinal.docx
Mobile ManufactureFinal.docx
 
bsi BIM solutions | Ecobuild 2016
bsi BIM solutions | Ecobuild 2016bsi BIM solutions | Ecobuild 2016
bsi BIM solutions | Ecobuild 2016
 
5th Qatar BIM User Day, Understanding stakeholder roles in BIM
5th Qatar BIM User Day, Understanding stakeholder roles in BIM5th Qatar BIM User Day, Understanding stakeholder roles in BIM
5th Qatar BIM User Day, Understanding stakeholder roles in BIM
 
Certificado BBA - Aislamiento con productos Synthesia para rehabilitación de ...
Certificado BBA - Aislamiento con productos Synthesia para rehabilitación de ...Certificado BBA - Aislamiento con productos Synthesia para rehabilitación de ...
Certificado BBA - Aislamiento con productos Synthesia para rehabilitación de ...
 
Power Generation_Project Brief Instructions 2015
Power Generation_Project Brief Instructions 2015Power Generation_Project Brief Instructions 2015
Power Generation_Project Brief Instructions 2015
 
BBAapproval
BBAapprovalBBAapproval
BBAapproval
 
BBA approval
BBA approvalBBA approval
BBA approval
 
Peter Cox - Waterproofing Brickwork Certificate
Peter Cox - Waterproofing Brickwork CertificatePeter Cox - Waterproofing Brickwork Certificate
Peter Cox - Waterproofing Brickwork Certificate
 
Best Practices for Improving the PCB Supply Chain: Part II
Best Practices for Improving the PCB Supply Chain: Part IIBest Practices for Improving the PCB Supply Chain: Part II
Best Practices for Improving the PCB Supply Chain: Part II
 
CIOB_Code_of_Quality_Management.pdf
CIOB_Code_of_Quality_Management.pdfCIOB_Code_of_Quality_Management.pdf
CIOB_Code_of_Quality_Management.pdf
 
CIOB_Code_of_Quality_Management.pdf
CIOB_Code_of_Quality_Management.pdfCIOB_Code_of_Quality_Management.pdf
CIOB_Code_of_Quality_Management.pdf
 
IRJET- Review on Study of Quality Practices in Construction
IRJET- Review on Study of Quality Practices in ConstructionIRJET- Review on Study of Quality Practices in Construction
IRJET- Review on Study of Quality Practices in Construction
 
Bryan allcock trl9 ready
Bryan allcock   trl9 readyBryan allcock   trl9 ready
Bryan allcock trl9 ready
 
Improve the Productivity of Building Construction Project using Clash detecti...
Improve the Productivity of Building Construction Project using Clash detecti...Improve the Productivity of Building Construction Project using Clash detecti...
Improve the Productivity of Building Construction Project using Clash detecti...
 
Certificado BBA - Aislamiento Synthesia para cubiertas
Certificado BBA - Aislamiento Synthesia para cubiertasCertificado BBA - Aislamiento Synthesia para cubiertas
Certificado BBA - Aislamiento Synthesia para cubiertas
 
National BIM Conference 2015 - JHunt
National BIM Conference 2015 - JHuntNational BIM Conference 2015 - JHunt
National BIM Conference 2015 - JHunt
 
WPC Door Manufacturing Plant Project Report.pptx
WPC Door Manufacturing Plant Project Report.pptxWPC Door Manufacturing Plant Project Report.pptx
WPC Door Manufacturing Plant Project Report.pptx
 
Areca Nut Processing Plant Project Report.pptx
Areca Nut Processing Plant Project Report.pptxAreca Nut Processing Plant Project Report.pptx
Areca Nut Processing Plant Project Report.pptx
 

More from SANJEEV Wazir

Use of bim in project management
Use of bim in project managementUse of bim in project management
Use of bim in project managementSANJEEV Wazir
 
Common causes of cost overruns in construction projects
Common causes of cost overruns in construction projectsCommon causes of cost overruns in construction projects
Common causes of cost overruns in construction projectsSANJEEV Wazir
 
Periodical meeting report and progress report
Periodical meeting report and progress reportPeriodical meeting report and progress report
Periodical meeting report and progress reportSANJEEV Wazir
 
What is Manpower Planning Organizing Staffing Important objectives of staffin...
What is Manpower Planning Organizing Staffing Important objectives of staffin...What is Manpower Planning Organizing Staffing Important objectives of staffin...
What is Manpower Planning Organizing Staffing Important objectives of staffin...SANJEEV Wazir
 
CONSTRUCTION METHODS BASICS BTCE-503-18
CONSTRUCTION METHODS BASICSBTCE-503-18CONSTRUCTION METHODS BASICSBTCE-503-18
CONSTRUCTION METHODS BASICS BTCE-503-18SANJEEV Wazir
 
Canal Regulation Works
Canal Regulation WorksCanal Regulation Works
Canal Regulation WorksSANJEEV Wazir
 
impact field work report
 impact field work report impact field work report
impact field work reportSANJEEV Wazir
 
construction project planing
 construction project planing construction project planing
construction project planingSANJEEV Wazir
 
Unit 1 basics of construction
Unit 1 basics of constructionUnit 1 basics of construction
Unit 1 basics of constructionSANJEEV Wazir
 
.BOUSSINESQ’S THEORY FOR VERTICAL STRESSES UNDER A CIRCULAR AREA.pdf
.BOUSSINESQ’S THEORY FOR VERTICAL STRESSES UNDER A CIRCULAR AREA.pdf.BOUSSINESQ’S THEORY FOR VERTICAL STRESSES UNDER A CIRCULAR AREA.pdf
.BOUSSINESQ’S THEORY FOR VERTICAL STRESSES UNDER A CIRCULAR AREA.pdfSANJEEV Wazir
 
How to calculate quantity of steel in slab
How to calculate quantity of steel in slabHow to calculate quantity of steel in slab
How to calculate quantity of steel in slabSANJEEV Wazir
 
HOW TO CALCULATE THE QUANTITY FOR CEMENT,SAND, AND AGGREGATES
HOW TO CALCULATE THE QUANTITY FOR CEMENT,SAND, AND AGGREGATESHOW TO CALCULATE THE QUANTITY FOR CEMENT,SAND, AND AGGREGATES
HOW TO CALCULATE THE QUANTITY FOR CEMENT,SAND, AND AGGREGATESSANJEEV Wazir
 

More from SANJEEV Wazir (20)

Use of bim in project management
Use of bim in project managementUse of bim in project management
Use of bim in project management
 
Lean costruction
Lean costructionLean costruction
Lean costruction
 
Common causes of cost overruns in construction projects
Common causes of cost overruns in construction projectsCommon causes of cost overruns in construction projects
Common causes of cost overruns in construction projects
 
Periodical meeting report and progress report
Periodical meeting report and progress reportPeriodical meeting report and progress report
Periodical meeting report and progress report
 
RECORD KEEPING
RECORD KEEPINGRECORD KEEPING
RECORD KEEPING
 
What is Manpower Planning Organizing Staffing Important objectives of staffin...
What is Manpower Planning Organizing Staffing Important objectives of staffin...What is Manpower Planning Organizing Staffing Important objectives of staffin...
What is Manpower Planning Organizing Staffing Important objectives of staffin...
 
CONSTRUCTION METHODS BASICS BTCE-503-18
CONSTRUCTION METHODS BASICSBTCE-503-18CONSTRUCTION METHODS BASICSBTCE-503-18
CONSTRUCTION METHODS BASICS BTCE-503-18
 
Canal Regulation Works
Canal Regulation WorksCanal Regulation Works
Canal Regulation Works
 
impact field work report
 impact field work report impact field work report
impact field work report
 
canal regulators
 canal regulators canal regulators
canal regulators
 
construction project planing
 construction project planing construction project planing
construction project planing
 
energy dissipators
energy dissipatorsenergy dissipators
energy dissipators
 
energy dissipators
energy dissipatorsenergy dissipators
energy dissipators
 
Unit 1 basics of construction
Unit 1 basics of constructionUnit 1 basics of construction
Unit 1 basics of construction
 
design of weirs
design of weirsdesign of weirs
design of weirs
 
theory of seepage
theory of seepagetheory of seepage
theory of seepage
 
DIVERSION HEAD WORK
DIVERSION HEAD WORKDIVERSION HEAD WORK
DIVERSION HEAD WORK
 
.BOUSSINESQ’S THEORY FOR VERTICAL STRESSES UNDER A CIRCULAR AREA.pdf
.BOUSSINESQ’S THEORY FOR VERTICAL STRESSES UNDER A CIRCULAR AREA.pdf.BOUSSINESQ’S THEORY FOR VERTICAL STRESSES UNDER A CIRCULAR AREA.pdf
.BOUSSINESQ’S THEORY FOR VERTICAL STRESSES UNDER A CIRCULAR AREA.pdf
 
How to calculate quantity of steel in slab
How to calculate quantity of steel in slabHow to calculate quantity of steel in slab
How to calculate quantity of steel in slab
 
HOW TO CALCULATE THE QUANTITY FOR CEMENT,SAND, AND AGGREGATES
HOW TO CALCULATE THE QUANTITY FOR CEMENT,SAND, AND AGGREGATESHOW TO CALCULATE THE QUANTITY FOR CEMENT,SAND, AND AGGREGATES
HOW TO CALCULATE THE QUANTITY FOR CEMENT,SAND, AND AGGREGATES
 

Recently uploaded

Crayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon ACrayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon AUnboundStockton
 
Roles & Responsibilities in Pharmacovigilance
Roles & Responsibilities in PharmacovigilanceRoles & Responsibilities in Pharmacovigilance
Roles & Responsibilities in PharmacovigilanceSamikshaHamane
 
Pharmacognosy Flower 3. Compositae 2023.pdf
Pharmacognosy Flower 3. Compositae 2023.pdfPharmacognosy Flower 3. Compositae 2023.pdf
Pharmacognosy Flower 3. Compositae 2023.pdfMahmoud M. Sallam
 
MARGINALIZATION (Different learners in Marginalized Group
MARGINALIZATION (Different learners in Marginalized GroupMARGINALIZATION (Different learners in Marginalized Group
MARGINALIZATION (Different learners in Marginalized GroupJonathanParaisoCruz
 
Employee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxEmployee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxNirmalaLoungPoorunde1
 
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdf
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdfEnzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdf
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdfSumit Tiwari
 
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdfssuser54595a
 
Introduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher EducationIntroduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher Educationpboyjonauth
 
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTiammrhaywood
 
Meghan Sutherland In Media Res Media Component
Meghan Sutherland In Media Res Media ComponentMeghan Sutherland In Media Res Media Component
Meghan Sutherland In Media Res Media ComponentInMediaRes1
 
Capitol Tech U Doctoral Presentation - April 2024.pptx
Capitol Tech U Doctoral Presentation - April 2024.pptxCapitol Tech U Doctoral Presentation - April 2024.pptx
Capitol Tech U Doctoral Presentation - April 2024.pptxCapitolTechU
 
MICROBIOLOGY biochemical test detailed.pptx
MICROBIOLOGY biochemical test detailed.pptxMICROBIOLOGY biochemical test detailed.pptx
MICROBIOLOGY biochemical test detailed.pptxabhijeetpadhi001
 
Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17Celine George
 
Difference Between Search & Browse Methods in Odoo 17
Difference Between Search & Browse Methods in Odoo 17Difference Between Search & Browse Methods in Odoo 17
Difference Between Search & Browse Methods in Odoo 17Celine George
 
DATA STRUCTURE AND ALGORITHM for beginners
DATA STRUCTURE AND ALGORITHM for beginnersDATA STRUCTURE AND ALGORITHM for beginners
DATA STRUCTURE AND ALGORITHM for beginnersSabitha Banu
 
Alper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentAlper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentInMediaRes1
 
Like-prefer-love -hate+verb+ing & silent letters & citizenship text.pdf
Like-prefer-love -hate+verb+ing & silent letters & citizenship text.pdfLike-prefer-love -hate+verb+ing & silent letters & citizenship text.pdf
Like-prefer-love -hate+verb+ing & silent letters & citizenship text.pdfMr Bounab Samir
 
Presiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha electionsPresiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha electionsanshu789521
 

Recently uploaded (20)

Crayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon ACrayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon A
 
Roles & Responsibilities in Pharmacovigilance
Roles & Responsibilities in PharmacovigilanceRoles & Responsibilities in Pharmacovigilance
Roles & Responsibilities in Pharmacovigilance
 
Pharmacognosy Flower 3. Compositae 2023.pdf
Pharmacognosy Flower 3. Compositae 2023.pdfPharmacognosy Flower 3. Compositae 2023.pdf
Pharmacognosy Flower 3. Compositae 2023.pdf
 
MARGINALIZATION (Different learners in Marginalized Group
MARGINALIZATION (Different learners in Marginalized GroupMARGINALIZATION (Different learners in Marginalized Group
MARGINALIZATION (Different learners in Marginalized Group
 
Employee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxEmployee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptx
 
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdf
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdfEnzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdf
Enzyme, Pharmaceutical Aids, Miscellaneous Last Part of Chapter no 5th.pdf
 
OS-operating systems- ch04 (Threads) ...
OS-operating systems- ch04 (Threads) ...OS-operating systems- ch04 (Threads) ...
OS-operating systems- ch04 (Threads) ...
 
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
18-04-UA_REPORT_MEDIALITERAСY_INDEX-DM_23-1-final-eng.pdf
 
Introduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher EducationIntroduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher Education
 
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
 
Meghan Sutherland In Media Res Media Component
Meghan Sutherland In Media Res Media ComponentMeghan Sutherland In Media Res Media Component
Meghan Sutherland In Media Res Media Component
 
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
 
Capitol Tech U Doctoral Presentation - April 2024.pptx
Capitol Tech U Doctoral Presentation - April 2024.pptxCapitol Tech U Doctoral Presentation - April 2024.pptx
Capitol Tech U Doctoral Presentation - April 2024.pptx
 
MICROBIOLOGY biochemical test detailed.pptx
MICROBIOLOGY biochemical test detailed.pptxMICROBIOLOGY biochemical test detailed.pptx
MICROBIOLOGY biochemical test detailed.pptx
 
Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17Computed Fields and api Depends in the Odoo 17
Computed Fields and api Depends in the Odoo 17
 
Difference Between Search & Browse Methods in Odoo 17
Difference Between Search & Browse Methods in Odoo 17Difference Between Search & Browse Methods in Odoo 17
Difference Between Search & Browse Methods in Odoo 17
 
DATA STRUCTURE AND ALGORITHM for beginners
DATA STRUCTURE AND ALGORITHM for beginnersDATA STRUCTURE AND ALGORITHM for beginners
DATA STRUCTURE AND ALGORITHM for beginners
 
Alper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentAlper Gobel In Media Res Media Component
Alper Gobel In Media Res Media Component
 
Like-prefer-love -hate+verb+ing & silent letters & citizenship text.pdf
Like-prefer-love -hate+verb+ing & silent letters & citizenship text.pdfLike-prefer-love -hate+verb+ing & silent letters & citizenship text.pdf
Like-prefer-love -hate+verb+ing & silent letters & citizenship text.pdf
 
Presiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha electionsPresiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha elections
 

Quality control IN CONSTRUCTION

  • 2. QUALITY CONTROL • The designer(s), manufacture and contractors must ensure that minimum quality standards are met and maintained. • They must make sure that the building will perform as required and expected by its owners and occupiers. 12/15/2020SNJV432@GMAIL.COM 2
  • 6. ISO 9001 & QUALITY ASSURANCE 1. process approach to system. 2. process measurement. 3. Process management. 4. customer satisfaction monitoring. 5. continual improvement. 12/15/2020SNJV432@GMAIL.COM 6
  • 7. ISO 9001 & QUALITY ASSURANCE ISO 9001: 2000 also puts a stronger emphasis on the quality management function of the organization as distinct from: 1. quality assurance 2. quality control activities 3. five requirements. 12/15/2020SNJV432@GMAIL.COM 7
  • 8. ISO 14000 & QUALITY ASSURANCE ❑ The ISO 14000 series consist of five standards: 1.Environmental management systems 2.Environmental auditing 3.Environmental labelling 4.Environmental performance evaluation 5. Life cycle assessment 12/15/2020SNJV432@GMAIL.COM 8
  • 9. QUALITY CONTROL Construction Quality and Construction Quality Control (QC)Inspectors 1. All construction processes, procedures, and workmanship must be inspected Quality Inspectors. 2. Inspection should include the observations, measurements, and documentation specified in contractor’s Method Statement and the Contract Documents. 12/15/2020SNJV432@GMAIL.COM 9
  • 10. QUALITY CONTROL Quality Control (QC) Testing Staff Sampling and testing of field-tested Materials in accordance with the contract documents. Certified Testing Laboratory Independent Referee Laboratory Materials Quality Management Contractor is responsible for providing Quality Control (QC) sampling and testing, and carrying out Quality Level Analysis during production to submit when required by the client or client representative. 12/15/2020SNJV432@GMAIL.COM 10
  • 11. QUALITY CONTROL Quality Assurance Client’s QA Program defines the responsibilities and roles of both contractor and it’s sub- contractors. The QA Program is contained in the contract document. The contractor is responsible for providing QC sampling and testing of all the Materials specified in the contract document. 12/15/2020SNJV432@GMAIL.COM 11
  • 12. QUALITY CONTROL In practice Building Control Officers (BCOs)and inspectors are prepared to provide some advice where they can and if they visit. Large Private Developments –Sites where main contractor is client These sites are often those being developed by a large private house builder. The house builder/developer will often have a project manager and site manager. Larger sites-assistant site managers who have responsibility for quality control. 12/15/2020SNJV432@GMAIL.COM 12
  • 13. QUALITY CONTROL •BCOs and inspectors from the Local Authorities are prepared to provide some advice where they can and if they visit. • However, it is not their role. • Often, the emphasis, on sites of this nature, is on getting the work done as quickly as possible to the minimum standard required to satisfy the warranty provider and possibly the BCO. • This emphasis has developed as a result of commercial pressures on time and finance and the lack of skilled tradesmen. 12/15/2020SNJV432@GMAIL.COM 13
  • 14. QUALITY CONTROL Large Private Developments (where main contractor is not client) 1. The project manager/site manager for the contractor have to satisfy the client or their agents that the work done meets the standard required. 2. The standard required will normally have been agreed as part of the original contract and the specification. 12/15/2020SNJV432@GMAIL.COM 14
  • 15. QUALITY CONTROL It is the responsibility of the: 1. project manager 2. site manager/ 3. assistant site managers 4. foremen to ensure that the quality of work carried out meets the requirement of the specification. 12/15/2020SNJV432@GMAIL.COM 15
  • 16. QUALITY CONTROL Under Design & Build contracts: • Most of the responsibility for quality control of design, specification and construction rests with the main contractor. • Under many forms of Design & Build contract the client is able to check build quality through the use of: 1. their own Clerk ofWorks 2. third-party inspection service providers. 12/15/2020SNJV432@GMAIL.COM 16
  • 17. QUALITY CONTROL Quality Assurance Schemes The National Standards Authority of Ireland (NSAI) is Ireland’s Standards body. They facilitate the development of voluntary standard documents. NSAI is a leading supplier of product and system certification services, both domestically and internationally. The NSAI represent Irish interests in European and international Standards bodies. 12/15/2020SNJV432@GMAIL.COM 17
  • 18. QUALITY CONTROL The NSAI are responsible for the Timber Frame Manufacturers’ Quality Approval Scheme. The scheme does not apply to timber frame buildings, which are fabricated on site (stick buildings). It is based on the requirements of the Irish Building Regulations, TGDs and relevant Irish and British Standards.12/15/2020SNJV432@GMAIL.COM 18
  • 19. QUALITY CONTROL It considers: Design QA procedures related to design and manufacture Material specifications Manufacturing process Manufacturing information and documentation Production facilities 12/15/2020SNJV432@GMAIL.COM 19
  • 20. QUALITY CONTROL Site information and documentation Quality records Personnel Training 12/15/2020SNJV432@GMAIL.COM 20
  • 21. QUALITY CONTROL HomeBond is a private company set up by the Construction Industry Federation (CIF). It operates independently of the CIF HomeBond is a warrantor and inspects constructions to determine: ‘good practice’ and/or HomeBond requirements are being met. HomeBond does not underwrite developments but provides cover in the event that the developments are not soundly constructed with the appropriate materials. 12/15/2020SNJV432@GMAIL.COM 21
  • 22. QUALITY CONTROL HomeBond covers the dwelling against: Major structural defects such as: 1. major defect in the foundations of a dwelling 2. the load-bearing part of its floors 3. walls and roof or retaining walls necessary for its support which affectsthe structural stability of the dwelling’. 12/15/2020SNJV432@GMAIL.COM 22
  • 23. QUALITY CONTROL Major non-structural defects which might lead to problems such as: 1.Smoke 2.Water penetration from an adjacent building into the completed home. 12/15/2020SNJV432@GMAIL.COM 23
  • 24. QUALITY CONTROL A variety of sources of technical information exists for those involved in the design, manufacture and construction of timber frame buildings in Ireland. The principal sources of technical information for each of the disciplines involved is set out below: Architects Guidance is given in the Technical Guidance Documents on how to meet the requirements of the National Building Regulations. 12/15/2020SNJV432@GMAIL.COM 24
  • 25. QUALITY CONTROL The requirements of HomeBond are published in their House Building Manual. Appendix B of the House Building Manual publication relates to timber frame construction. Additional guidance, relating specifically to on-site practice is given in their Right On Site leaflets. 12/15/2020SNJV432@GMAIL.COM 25
  • 26. QUALITY CONTROL The TRADA Technology publication (Timber Frame Construction) provides a source of standard details and advice on issues such as: 1. good practice guide 2 . a site supervisor checklist 3. guidance on appropriate material specifications. In-company standard details or standard details issued by the timber frame manufacturer. WOODSPEC TRADA/BRE Design Guide for Multi Storey Timber Frame Buildings – Timber Stairs.12/15/2020SNJV432@GMAIL.COM 26
  • 27. QUALITY CONTROL Engineers Guidance is given in the Technical Guidance Documents on how to meet the requirements of the National Building Regulations. BS 5268: Part 2: 1996: Structural use of timber – Code of practice for permissible stress design, materials and workmanship. 12/15/2020SNJV432@GMAIL.COM 27
  • 28. QUALITY CONTROL IS 193: 1996: Timber trussed rafters for roofs. IS 444: 1998: Use ofstructural timber in buildings. BS 5268: Part 4: 1978: Structural use of timber – Fire resistance of timber structures. Section 4.1. Recommendations for calculating the fire resistance of timber members. 12/15/2020SNJV432@GMAIL.COM 28
  • 29. QUALITY CONTROL BS 5268: Part 4: 1978: Structural use of timber – Fire resistance of timber structures. Section 4.2. Recommendations for calculating the fire resistance of timber stud walls and joisted floor constructions. BS 5268: Part 6: 1996: Structural use of timber – Code of practice for timber framed walls. Section 6.1. Dwellings not exceeding four storeys. 12/15/2020SNJV432@GMAIL.COM 29
  • 30. QUALITY CONTROL Site Managers In-company documentation. The requirements of HomeBond are published in their House Building Manual. Appendix B of the House Building Manual publication relates to timber frame construction. Additional guidance, relating specifically to on- site practice is given in their Right On Site leaflets. 12/15/2020SNJV432@GMAIL.COM 30
  • 31. QUALITY CONTROL The TRADA Technology publication, Timber Frame Construction, provides a source of standard details and advice on good practice including a site supervisors’ checklist and guidance on appropriate material specifications. Guidance is given in the Technical Guidance Documents on how to meet the requirements of the National Building Regulations. TRADA/BRE Design Guide for Multi Storey Timber Frame Buildings – Timber Stairs. 12/15/2020SNJV432@GMAIL.COM 31
  • 32. QUALITY CONTROL Clerk of Works In-company documentation. The requirements of HomeBond are published in their House Building Manual. Appendix B of the House Building Manual publication relates to timber frame construction. Additional guidance, relating specifically to on- site practice is given in their Right On Site leaflets. 12/15/2020SNJV432@GMAIL.COM 32
  • 33. QUALITY CONTROL The TRADA Technology publication, Timber Frame Construction, provides a source of standard details and advice on good practice including a site supervisors’ checklist and guidance on appropriate material specifications. 12/15/2020SNJV432@GMAIL.COM 33
  • 34. QUALITY CONTROL Guidance is given in the Technical Guidance Documents on how to meet the requirements of the National Building Regulations. TRADA/BRE Design Guide for Multi Storey Timber Frame Buildings – Timber Stairs. 12/15/2020SNJV432@GMAIL.COM 34