• MARBELLA-114
• MONACO-38
• CAPRI STREET-44
• TOWNHOUSE-36
• TOWNHOUSE-38`
• TCC to prepare a method statement explaining to ANTARA’s
Helpdesk the next work steps and how to get access.
• TCC to provide a list of the required materials.
• TCC is to submit a schedule for investigation for all units
• TCC to submit an FIR to the tenant(s) and then get their approval for
the commencement of works.
*For details regarding ALL risks, refer to Risk Register – to
submitted by TCC
• JLL will be responsible to issue a Dashboard on a weekly basis
• TCC requested access for investigation only witnessed by AECOM.
• TAR will explain to the tenant(s) that access is needed for all areas
RISK ACTION STATUS COMMENTS
Reports
requires leaks
To be
documentation
in Minutes of
Meeting
On going
Additional work
that is not
explained in the
reports requires
more time than
anticipated.
Permit issue
JLL will arrange
a meeting with
all parties
involved to
address and
resolve the
matter.
High Risk
Final handover
may be delayed
due to delays in
the issuance of
permits by the
ANTARA and
maintenance
ENGIN
Eid Holiday TAR will handle
process
tenant(s) that
access is
needed
On going
The upcoming
Eid holiday may
create delay,
and this is an
inevitable risk
of hindering the
project timeline
Client name ANTARA
Project Name ANTARA Project
Project Location King Khalid Br Rd, Ar Rihab, Diriyah - Kingdom of
Saudi Arabia
Building Name
Mixed used Villas and other structures
Level:
Size
Approved Budget 628.782.44 SAR
Contract Type Emergency repair works
Contractor Triangle construction contract (TCC)
Designer Omrania consulting
Commencement Date 13th April 2023
Contract Handover
Date
17th Aug 2023
Project Status
Project Overview:
Emergency repair works
TCC have Works in several locations. The upcoming Eid
holiday may cause delays the project timeline. TAR will
explain to tenants that access is needed for all areas to
proceed, TCC must prepare a method statement and list of
materials, submit an investigation schedule and FIR to
tenants, and request access for investigation with AECOM.
Dashboard 11.05.23
Weekly Dashboard No. 01
1. Executive Summary 2. Client and Consultant Actions
3. Designer Actions
5. Weekly Look Ahead
6. Milestones
DELIVERABLE START FINISH STATUS
BOQ / Proposal April April Completed
Contract signature 13th Apr 23 13th Apr
23
Completed
Construction 14th Apr 23 17th Aug
23
On going
advance payment ( Down
payment 10% ) 5 working
days of the Effective
30th Apr
23
4th May
23
Completed
Contractor Payment
application 80% (Monthly)
4th May 23 4th Jun 23 On going
First payment after 62 Unit
delivery
TBC TBC On going
Second payment after 57
Unit delivery
TBC TBC On going
Third payment after 34 Unit
delivery
TBC TBC On going
Release payment of 5% of
the reserved amount.
TBC TBC On going
Remaining batch retention.
5%
TBC TBC On going
Project handover TBC TBC On going
7. Commercial Update & Overview (To be Determined)
8. Project Plan
Ref Description Cost
Approved Project Budget 628.782.44 SAR
1 Contract B.O.Q Sum (Emergency
repair works)
628.782.44 SAR
2 advance payment ( Down
payment ) 10%
62.878.24 SAR - Paid
3 Contractor Payment application
80%
503.025.95 SAR - To
be scheduled
4 Release payment of 5% of the
reserved amount.
31.439.122 SAR
5 Remaining batch retention. 5% 31.439.122 SAR
4. Contractor Actions
The design is already finished by Omrania Consulting
Project details:
Achievements:
Achievements:
TCC closed five villas until now
Look Ahead:
• MARBELLA-114
• MONACO-38
• CAPRI STREET-44
• TOWNHOUSE-36
• TOWNHOUSE-38`
Item SAR Percentage
Construction value 628.782.44 100%
Down payment 62.878.24 100%
Approved V.O. by
P.M.
Paid to date
Other Costs - -
TOTAL OF
CONTRACT VAL
62.878.24 10%
Type of
Risk/Issue
Description
Severity
of Impact
Planned Mitigation
Action
required/who
Risks
Permit
Final handover may be delayed due to delays in the issuance of
permits by the ANTARA and maintenance (Engie) co.
Meeting must be set up with the client and maintenance to clarify
procedure TCC
Reports
Additional work that is not explained in the reports requires more time
than anticipated.
This will be documented in the MOM
JLL
Eid
Holiday
The upcoming Eid holiday may create delay, and this is an inevitable
risk of hindering the project timeline
TAR will handle process tenant(s) that access is needed
TAR
Issues
No Major issues recorded N/A N/A
No Major issues recorded N/A N/A
Schedule S E Apr May Jun Jul Aug
Construction 13-4
17-
8
Works on Balconies and Terraces 27-4
Rectification Works for Damages In &
Out of the Bldgs
27-4
Roof works 27-4
Sealant Roof Works 27-4
Rectification Electrical Works 27-4
Project Close Out TBC
Opening
COST
SUMMARY
PROJECT
TIMELINE
PROJECT
OVERVIEW
KEY
ACTIVITY
FORECAST
Location: King Khalid Br Rd, Ar Rihab, Diriyah -
Kingdom of Saudi Arabia
Project Type: Emergency repair works
Total project value: 628.782.44
Construction planed end date: April 13, 2023 – August
17, 2023
Estimated opening date: August
Project Size (sqm):
Project Manager: JLL
Contractor: Triangle construction contract (TCC)
Consultant: AECOM
Designer: Omrania consulting
PERMIT
STAGES
RISKS
&
ISSUES
Overall Project Status At Risk On track Complete
Behind
Not started
On track
Validation
of
V.O.
Santorini-40 
Townhouse-13 
Antara drive-14 
Marbella-114
Monaco-38
Dashboard 11.05.23
Weekly Dashboard No. 01
Time now
Sun Mon Tue Wed Thu Fri Sat
01 02 03 04 05 06
07 08
Weekly call 15:00
KSA Time
09
Site visit 9:30
Site Meeting
14:00 KSA Time
10 11 12 13
14 15
Weekly call 15:00
KSA Time
16
Site visit 9:30
Site Meeting
14:00 KSA Time
17 18 19 20
21 22
Weekly call 15:00
KSA Time
23
Site visit 9:30
Site Meeting
14:00 KSA Time
24 25 26 27
28 29
Weekly call 15:00
KSA Time
30
Site visit 9:30
Site Meeting
14:00 KSA Time
31
May 2023
Dashboard 11.05.23
Calendar
MILESTONES DUE
Milestones that are coming soon.
Project Update
Payment Track
Current and Future Payments.
Cost Update
Achievement
Tasks and Milestones been completed.
% Complete
4.9%Construction
% Complete
10%
# Variation Due Date Amount Status
1 VO1
2 VO2
3 VO3
Grand Total
Variation Track
Current and Future Variations.
# Payment Due Date % Amount Status
1
Contractor – 1st
invoice (10%)
Down payment
10 62.878.24 SAR Paid
2
Contractor – 2nd
invoice (80%)
Contractor Payment application
80 503.025.95 SAR
To be
schedule
3
Contractor – 3rd
invoice (5%)
Release payment of 5% of the
reserved amount.
5 31.439.122 SAR
4
Contractor – 4th
invoice (5%)
Remaining batch retention.
5 31.439.122 SAR
Project Budget 628 K 100%
Task Name
Task
SN-35 -- 100%
TH-13 -- 100%
AD-14 -- 100%
TH-30 – 100%
M.T-114 – 100%
SN-40 – 50%
TH-38 -- 50%
M-48 -- 50%
M-114 -- 50%
MC-38 -- 50%
CT-44 -- 50%
TH-36 -- 50%
Total of villas – 160
TCC, Will provide a tacker for tasks & achievement
Dashboard 11.05.23
ProjectOverview
Dashboard 11.05.23
Project Programme
Dashboard 11.05.23
Project Programme
Dashboard 11.05.23
Weekly Report
S.No Location Description of Work Start date Permit no. Status REMARK Photos
Verifying defects of water leakage
Defects found in roof ducting
Water leakage in bathroom ceiling
Duct Joint sealant done
Inspection submitted
Balcony floor existing tiles works ongoing.
Floor Screed to maintain slope.
Water slope test done
Installation of polythene sheet & Thermal insulation
Sand filling in balcony area
Sealant filling for electrical box
Floor drain coring & installation of new pipes in external walls
Water slope test done
Screed work in progress
1
More defects were found in the kitchen ceiling & master bedroom
Bathroom gypsum board works ongoing
Bedroom,& hall area ceiling gypsum works ongoing
HVAC gravel removal and drain pipe repair.
Tiles replacement work in progress
Water Slope Test Done & Skirting Water Proof Membrane Repair ongoing
Staircase wall leakage area paint putty work in progress
Core In Wall & Install New Drain
Verified the defect
Kitchen ceiling paint work in progress
Roof hatch joint filling work in progress
duct joint sealant work in progress
Verified the defects of water leak
water coming in bedroom wall near light switch
water leak in Roof drain pipe
water leak in Roof duct
Duct Joint sealant work completed
Verified the defects of water leak
Water leak from roof duct
water coming inside maid room
joint sealant work in progress
SANTORINI -35
TOWNHOUSE -30
ANTARA DRIV -14
TOWNHOUSE -13
SANTORINI -40
8 TOWNHOUSE-30 ANT-RWL-PER-015 DONE
9
SANTORINI -35
TOWNHOUSE -30
ANTARA DRIV-14
TOWNHOUSE -13
SANTORINI -40
DONE
ANT-RWL-PER-010 DONE
MONACO-38
5 TOWNHOUSE-38 ANT-RWL-PER-014 OPEN
6 SANTORINI-40 ANT-RWL-PER-012 OPEN
7 ANTARA DRIVE-14
3 ANT-RWL-PER-019 OPEN
4 TOWNHOUSE-36 OPEN
CAPRI STREET -44
1 MARBELLA-114 ANT-RWL-PER-001 DONE
2 ANT-RWL-PER-009 OPEN
S.No Location Description of Work Start date Permit no. Status REMARK Photos
Verifying defects of water leakage
Defects found in roof ducting
Water leakage in bathroom ceiling
Duct Joint sealant done
Inspection submitted
Balcony floor existing tiles works ongoing.
Floor Screed to maintain slope.
Water slope test done
Installation of polythene sheet & Thermal insulation
Sand filling in balcony area
Sealant filling for electrical box
Floor drain coring & installation of new pipes in external walls
Water slope test done
Screed work in progress
1
More defects were found in the kitchen ceiling & master bedroom
Bathroom gypsum board works ongoing
Bedroom,& hall area ceiling gypsum works ongoing
HVAC gravel removal and drain pipe repair.
Tiles replacement work in progress
Water Slope Test Done & Skirting Water Proof Membrane Repair ongoing
Staircase wall leakage area paint putty work in progress
Core In Wall & Install New Drain
Verified the defect
Kitchen ceiling paint work in progress
Roof hatch joint filling work in progress
duct joint sealant work in progress
Verified the defects of water leak
water coming in bedroom wall near light switch
water leak in Roof drain pipe
water leak in Roof duct
Duct Joint sealant work completed
Verified the defects of water leak
Water leak from roof duct
water coming inside maid room
joint sealant work in progress
SANTORINI -35
TOWNHOUSE -30
ANTARA DRIV -14
TOWNHOUSE -13
SANTORINI -40
8 TOWNHOUSE-30 ANT-RWL-PER-015 DONE
9
SANTORINI -35
TOWNHOUSE -30
ANTARA DRIV-14
TOWNHOUSE -13
SANTORINI -40
DONE
ANT-RWL-PER-010 DONE
MONACO-38
5 TOWNHOUSE-38 ANT-RWL-PER-014 OPEN
6 SANTORINI-40 ANT-RWL-PER-012 OPEN
7 ANTARA DRIVE-14
3 ANT-RWL-PER-019 OPEN
4 TOWNHOUSE-36 OPEN
CAPRI STREET -44
1 MARBELLA-114 ANT-RWL-PER-001 DONE
2 ANT-RWL-PER-009 OPEN

More Related Content

Similar to Antara Dashboard-002.pptx

Buildings so r 14 15
Buildings so r 14 15Buildings so r 14 15
Buildings so r 14 15Ptpg Stuc
 
Project management report of stadium
Project management report of stadiumProject management report of stadium
Project management report of stadiumSLIIT, Sri Lanka
 
Rajgir Sports Complex_Project Kick Off Presentation.pptx
Rajgir Sports Complex_Project Kick Off Presentation.pptxRajgir Sports Complex_Project Kick Off Presentation.pptx
Rajgir Sports Complex_Project Kick Off Presentation.pptxsyedaliabl2023
 
PMI Scheduling Conference 2016 Bruce Stephan
PMI Scheduling Conference 2016 Bruce StephanPMI Scheduling Conference 2016 Bruce Stephan
PMI Scheduling Conference 2016 Bruce StephanBruce Stephan
 
AIWSP presentation SCM 3 11.09.2018 (1).ppt
AIWSP presentation SCM 3  11.09.2018 (1).pptAIWSP presentation SCM 3  11.09.2018 (1).ppt
AIWSP presentation SCM 3 11.09.2018 (1).pptRajabdeen Amjath
 
Building Economics:Tender Report
Building Economics:Tender ReportBuilding Economics:Tender Report
Building Economics:Tender Report마 이환
 
Case study 1 effective and efficient communication
Case study 1 effective and efficient communicationCase study 1 effective and efficient communication
Case study 1 effective and efficient communicationMustafa Ozgoren
 
KEE_RESUME_New_CV16 - Copy (8)
KEE_RESUME_New_CV16 - Copy (8)KEE_RESUME_New_CV16 - Copy (8)
KEE_RESUME_New_CV16 - Copy (8)Kee M
 
QAQC Presentation for project startup .pptx
QAQC Presentation for project startup .pptxQAQC Presentation for project startup .pptx
QAQC Presentation for project startup .pptxAliIrfan66
 
Attachement 3 61T01411 - Construction Execution Plan
Attachement 3 61T01411 - Construction Execution PlanAttachement 3 61T01411 - Construction Execution Plan
Attachement 3 61T01411 - Construction Execution PlanJames Zhang (Chi, Zhang)
 
Construction Administration Seminar
Construction Administration Seminar Construction Administration Seminar
Construction Administration Seminar jenkinswilliamc
 
Quality Management Plan
Quality Management PlanQuality Management Plan
Quality Management PlanAnuragBhat7
 
altaf resume work preparation
altaf resume work preparationaltaf resume work preparation
altaf resume work preparationAltaf Tanwar
 

Similar to Antara Dashboard-002.pptx (20)

Project assign 2
Project assign 2Project assign 2
Project assign 2
 
Buildings so r 14 15
Buildings so r 14 15Buildings so r 14 15
Buildings so r 14 15
 
Project management report of stadium
Project management report of stadiumProject management report of stadium
Project management report of stadium
 
Kandil_Sameh_CPMPart 4 _b
Kandil_Sameh_CPMPart 4 _bKandil_Sameh_CPMPart 4 _b
Kandil_Sameh_CPMPart 4 _b
 
Rajgir Sports Complex_Project Kick Off Presentation.pptx
Rajgir Sports Complex_Project Kick Off Presentation.pptxRajgir Sports Complex_Project Kick Off Presentation.pptx
Rajgir Sports Complex_Project Kick Off Presentation.pptx
 
PMI Scheduling Conference 2016 Bruce Stephan
PMI Scheduling Conference 2016 Bruce StephanPMI Scheduling Conference 2016 Bruce Stephan
PMI Scheduling Conference 2016 Bruce Stephan
 
AIWSP presentation SCM 3 11.09.2018 (1).ppt
AIWSP presentation SCM 3  11.09.2018 (1).pptAIWSP presentation SCM 3  11.09.2018 (1).ppt
AIWSP presentation SCM 3 11.09.2018 (1).ppt
 
Building Economics:Tender Report
Building Economics:Tender ReportBuilding Economics:Tender Report
Building Economics:Tender Report
 
RSR LATEST TRESUME
RSR LATEST TRESUMERSR LATEST TRESUME
RSR LATEST TRESUME
 
Case study 1 effective and efficient communication
Case study 1 effective and efficient communicationCase study 1 effective and efficient communication
Case study 1 effective and efficient communication
 
KEE_RESUME_New_CV16 - Copy (8)
KEE_RESUME_New_CV16 - Copy (8)KEE_RESUME_New_CV16 - Copy (8)
KEE_RESUME_New_CV16 - Copy (8)
 
QAQC Presentation for project startup .pptx
QAQC Presentation for project startup .pptxQAQC Presentation for project startup .pptx
QAQC Presentation for project startup .pptx
 
DAMAC Heights Project
DAMAC Heights ProjectDAMAC Heights Project
DAMAC Heights Project
 
Attachement 3 61T01411 - Construction Execution Plan
Attachement 3 61T01411 - Construction Execution PlanAttachement 3 61T01411 - Construction Execution Plan
Attachement 3 61T01411 - Construction Execution Plan
 
Construction Administration Seminar
Construction Administration Seminar Construction Administration Seminar
Construction Administration Seminar
 
Quality Management Plan
Quality Management PlanQuality Management Plan
Quality Management Plan
 
Hossam CV-FEB2016
Hossam CV-FEB2016Hossam CV-FEB2016
Hossam CV-FEB2016
 
Mitigtion Plan Presentation
Mitigtion Plan PresentationMitigtion Plan Presentation
Mitigtion Plan Presentation
 
10. Overall Implementation Programme
10. Overall Implementation Programme10. Overall Implementation Programme
10. Overall Implementation Programme
 
altaf resume work preparation
altaf resume work preparationaltaf resume work preparation
altaf resume work preparation
 

Recently uploaded

RA-11058_IRR-COMPRESS Do 198 series of 1998
RA-11058_IRR-COMPRESS Do 198 series of 1998RA-11058_IRR-COMPRESS Do 198 series of 1998
RA-11058_IRR-COMPRESS Do 198 series of 1998YohFuh
 
Call Us ➥97111√47426🤳Call Girls in Aerocity (Delhi NCR)
Call Us ➥97111√47426🤳Call Girls in Aerocity (Delhi NCR)Call Us ➥97111√47426🤳Call Girls in Aerocity (Delhi NCR)
Call Us ➥97111√47426🤳Call Girls in Aerocity (Delhi NCR)jennyeacort
 
Schema on read is obsolete. Welcome metaprogramming..pdf
Schema on read is obsolete. Welcome metaprogramming..pdfSchema on read is obsolete. Welcome metaprogramming..pdf
Schema on read is obsolete. Welcome metaprogramming..pdfLars Albertsson
 
Call Girls In Mahipalpur O9654467111 Escorts Service
Call Girls In Mahipalpur O9654467111  Escorts ServiceCall Girls In Mahipalpur O9654467111  Escorts Service
Call Girls In Mahipalpur O9654467111 Escorts ServiceSapana Sha
 
VIP High Class Call Girls Jamshedpur Anushka 8250192130 Independent Escort Se...
VIP High Class Call Girls Jamshedpur Anushka 8250192130 Independent Escort Se...VIP High Class Call Girls Jamshedpur Anushka 8250192130 Independent Escort Se...
VIP High Class Call Girls Jamshedpur Anushka 8250192130 Independent Escort Se...Suhani Kapoor
 
Industrialised data - the key to AI success.pdf
Industrialised data - the key to AI success.pdfIndustrialised data - the key to AI success.pdf
Industrialised data - the key to AI success.pdfLars Albertsson
 
VIP Call Girls Service Miyapur Hyderabad Call +91-8250192130
VIP Call Girls Service Miyapur Hyderabad Call +91-8250192130VIP Call Girls Service Miyapur Hyderabad Call +91-8250192130
VIP Call Girls Service Miyapur Hyderabad Call +91-8250192130Suhani Kapoor
 
Dubai Call Girls Wifey O52&786472 Call Girls Dubai
Dubai Call Girls Wifey O52&786472 Call Girls DubaiDubai Call Girls Wifey O52&786472 Call Girls Dubai
Dubai Call Girls Wifey O52&786472 Call Girls Dubaihf8803863
 
From idea to production in a day – Leveraging Azure ML and Streamlit to build...
From idea to production in a day – Leveraging Azure ML and Streamlit to build...From idea to production in a day – Leveraging Azure ML and Streamlit to build...
From idea to production in a day – Leveraging Azure ML and Streamlit to build...Florian Roscheck
 
DBA Basics: Getting Started with Performance Tuning.pdf
DBA Basics: Getting Started with Performance Tuning.pdfDBA Basics: Getting Started with Performance Tuning.pdf
DBA Basics: Getting Started with Performance Tuning.pdfJohn Sterrett
 
Saket, (-DELHI )+91-9654467111-(=)CHEAP Call Girls in Escorts Service Saket C...
Saket, (-DELHI )+91-9654467111-(=)CHEAP Call Girls in Escorts Service Saket C...Saket, (-DELHI )+91-9654467111-(=)CHEAP Call Girls in Escorts Service Saket C...
Saket, (-DELHI )+91-9654467111-(=)CHEAP Call Girls in Escorts Service Saket C...Sapana Sha
 
Beautiful Sapna Vip Call Girls Hauz Khas 9711199012 Call /Whatsapps
Beautiful Sapna Vip  Call Girls Hauz Khas 9711199012 Call /WhatsappsBeautiful Sapna Vip  Call Girls Hauz Khas 9711199012 Call /Whatsapps
Beautiful Sapna Vip Call Girls Hauz Khas 9711199012 Call /Whatsappssapnasaifi408
 
Customer Service Analytics - Make Sense of All Your Data.pptx
Customer Service Analytics - Make Sense of All Your Data.pptxCustomer Service Analytics - Make Sense of All Your Data.pptx
Customer Service Analytics - Make Sense of All Your Data.pptxEmmanuel Dauda
 
Call Girls in Defence Colony Delhi 💯Call Us 🔝8264348440🔝
Call Girls in Defence Colony Delhi 💯Call Us 🔝8264348440🔝Call Girls in Defence Colony Delhi 💯Call Us 🔝8264348440🔝
Call Girls in Defence Colony Delhi 💯Call Us 🔝8264348440🔝soniya singh
 
Indian Call Girls in Abu Dhabi O5286O24O8 Call Girls in Abu Dhabi By Independ...
Indian Call Girls in Abu Dhabi O5286O24O8 Call Girls in Abu Dhabi By Independ...Indian Call Girls in Abu Dhabi O5286O24O8 Call Girls in Abu Dhabi By Independ...
Indian Call Girls in Abu Dhabi O5286O24O8 Call Girls in Abu Dhabi By Independ...dajasot375
 
办理学位证中佛罗里达大学毕业证,UCF成绩单原版一比一
办理学位证中佛罗里达大学毕业证,UCF成绩单原版一比一办理学位证中佛罗里达大学毕业证,UCF成绩单原版一比一
办理学位证中佛罗里达大学毕业证,UCF成绩单原版一比一F sss
 
Predictive Analysis - Using Insight-informed Data to Determine Factors Drivin...
Predictive Analysis - Using Insight-informed Data to Determine Factors Drivin...Predictive Analysis - Using Insight-informed Data to Determine Factors Drivin...
Predictive Analysis - Using Insight-informed Data to Determine Factors Drivin...ThinkInnovation
 

Recently uploaded (20)

RA-11058_IRR-COMPRESS Do 198 series of 1998
RA-11058_IRR-COMPRESS Do 198 series of 1998RA-11058_IRR-COMPRESS Do 198 series of 1998
RA-11058_IRR-COMPRESS Do 198 series of 1998
 
Call Us ➥97111√47426🤳Call Girls in Aerocity (Delhi NCR)
Call Us ➥97111√47426🤳Call Girls in Aerocity (Delhi NCR)Call Us ➥97111√47426🤳Call Girls in Aerocity (Delhi NCR)
Call Us ➥97111√47426🤳Call Girls in Aerocity (Delhi NCR)
 
Deep Generative Learning for All - The Gen AI Hype (Spring 2024)
Deep Generative Learning for All - The Gen AI Hype (Spring 2024)Deep Generative Learning for All - The Gen AI Hype (Spring 2024)
Deep Generative Learning for All - The Gen AI Hype (Spring 2024)
 
Schema on read is obsolete. Welcome metaprogramming..pdf
Schema on read is obsolete. Welcome metaprogramming..pdfSchema on read is obsolete. Welcome metaprogramming..pdf
Schema on read is obsolete. Welcome metaprogramming..pdf
 
Call Girls In Mahipalpur O9654467111 Escorts Service
Call Girls In Mahipalpur O9654467111  Escorts ServiceCall Girls In Mahipalpur O9654467111  Escorts Service
Call Girls In Mahipalpur O9654467111 Escorts Service
 
VIP High Class Call Girls Jamshedpur Anushka 8250192130 Independent Escort Se...
VIP High Class Call Girls Jamshedpur Anushka 8250192130 Independent Escort Se...VIP High Class Call Girls Jamshedpur Anushka 8250192130 Independent Escort Se...
VIP High Class Call Girls Jamshedpur Anushka 8250192130 Independent Escort Se...
 
Industrialised data - the key to AI success.pdf
Industrialised data - the key to AI success.pdfIndustrialised data - the key to AI success.pdf
Industrialised data - the key to AI success.pdf
 
VIP Call Girls Service Miyapur Hyderabad Call +91-8250192130
VIP Call Girls Service Miyapur Hyderabad Call +91-8250192130VIP Call Girls Service Miyapur Hyderabad Call +91-8250192130
VIP Call Girls Service Miyapur Hyderabad Call +91-8250192130
 
Dubai Call Girls Wifey O52&786472 Call Girls Dubai
Dubai Call Girls Wifey O52&786472 Call Girls DubaiDubai Call Girls Wifey O52&786472 Call Girls Dubai
Dubai Call Girls Wifey O52&786472 Call Girls Dubai
 
From idea to production in a day – Leveraging Azure ML and Streamlit to build...
From idea to production in a day – Leveraging Azure ML and Streamlit to build...From idea to production in a day – Leveraging Azure ML and Streamlit to build...
From idea to production in a day – Leveraging Azure ML and Streamlit to build...
 
DBA Basics: Getting Started with Performance Tuning.pdf
DBA Basics: Getting Started with Performance Tuning.pdfDBA Basics: Getting Started with Performance Tuning.pdf
DBA Basics: Getting Started with Performance Tuning.pdf
 
Saket, (-DELHI )+91-9654467111-(=)CHEAP Call Girls in Escorts Service Saket C...
Saket, (-DELHI )+91-9654467111-(=)CHEAP Call Girls in Escorts Service Saket C...Saket, (-DELHI )+91-9654467111-(=)CHEAP Call Girls in Escorts Service Saket C...
Saket, (-DELHI )+91-9654467111-(=)CHEAP Call Girls in Escorts Service Saket C...
 
Beautiful Sapna Vip Call Girls Hauz Khas 9711199012 Call /Whatsapps
Beautiful Sapna Vip  Call Girls Hauz Khas 9711199012 Call /WhatsappsBeautiful Sapna Vip  Call Girls Hauz Khas 9711199012 Call /Whatsapps
Beautiful Sapna Vip Call Girls Hauz Khas 9711199012 Call /Whatsapps
 
Customer Service Analytics - Make Sense of All Your Data.pptx
Customer Service Analytics - Make Sense of All Your Data.pptxCustomer Service Analytics - Make Sense of All Your Data.pptx
Customer Service Analytics - Make Sense of All Your Data.pptx
 
VIP Call Girls Service Charbagh { Lucknow Call Girls Service 9548273370 } Boo...
VIP Call Girls Service Charbagh { Lucknow Call Girls Service 9548273370 } Boo...VIP Call Girls Service Charbagh { Lucknow Call Girls Service 9548273370 } Boo...
VIP Call Girls Service Charbagh { Lucknow Call Girls Service 9548273370 } Boo...
 
Call Girls in Defence Colony Delhi 💯Call Us 🔝8264348440🔝
Call Girls in Defence Colony Delhi 💯Call Us 🔝8264348440🔝Call Girls in Defence Colony Delhi 💯Call Us 🔝8264348440🔝
Call Girls in Defence Colony Delhi 💯Call Us 🔝8264348440🔝
 
Indian Call Girls in Abu Dhabi O5286O24O8 Call Girls in Abu Dhabi By Independ...
Indian Call Girls in Abu Dhabi O5286O24O8 Call Girls in Abu Dhabi By Independ...Indian Call Girls in Abu Dhabi O5286O24O8 Call Girls in Abu Dhabi By Independ...
Indian Call Girls in Abu Dhabi O5286O24O8 Call Girls in Abu Dhabi By Independ...
 
办理学位证中佛罗里达大学毕业证,UCF成绩单原版一比一
办理学位证中佛罗里达大学毕业证,UCF成绩单原版一比一办理学位证中佛罗里达大学毕业证,UCF成绩单原版一比一
办理学位证中佛罗里达大学毕业证,UCF成绩单原版一比一
 
Predictive Analysis - Using Insight-informed Data to Determine Factors Drivin...
Predictive Analysis - Using Insight-informed Data to Determine Factors Drivin...Predictive Analysis - Using Insight-informed Data to Determine Factors Drivin...
Predictive Analysis - Using Insight-informed Data to Determine Factors Drivin...
 
E-Commerce Order PredictionShraddha Kamble.pptx
E-Commerce Order PredictionShraddha Kamble.pptxE-Commerce Order PredictionShraddha Kamble.pptx
E-Commerce Order PredictionShraddha Kamble.pptx
 

Antara Dashboard-002.pptx

  • 1. • MARBELLA-114 • MONACO-38 • CAPRI STREET-44 • TOWNHOUSE-36 • TOWNHOUSE-38` • TCC to prepare a method statement explaining to ANTARA’s Helpdesk the next work steps and how to get access. • TCC to provide a list of the required materials. • TCC is to submit a schedule for investigation for all units • TCC to submit an FIR to the tenant(s) and then get their approval for the commencement of works. *For details regarding ALL risks, refer to Risk Register – to submitted by TCC • JLL will be responsible to issue a Dashboard on a weekly basis • TCC requested access for investigation only witnessed by AECOM. • TAR will explain to the tenant(s) that access is needed for all areas RISK ACTION STATUS COMMENTS Reports requires leaks To be documentation in Minutes of Meeting On going Additional work that is not explained in the reports requires more time than anticipated. Permit issue JLL will arrange a meeting with all parties involved to address and resolve the matter. High Risk Final handover may be delayed due to delays in the issuance of permits by the ANTARA and maintenance ENGIN Eid Holiday TAR will handle process tenant(s) that access is needed On going The upcoming Eid holiday may create delay, and this is an inevitable risk of hindering the project timeline Client name ANTARA Project Name ANTARA Project Project Location King Khalid Br Rd, Ar Rihab, Diriyah - Kingdom of Saudi Arabia Building Name Mixed used Villas and other structures Level: Size Approved Budget 628.782.44 SAR Contract Type Emergency repair works Contractor Triangle construction contract (TCC) Designer Omrania consulting Commencement Date 13th April 2023 Contract Handover Date 17th Aug 2023 Project Status Project Overview: Emergency repair works TCC have Works in several locations. The upcoming Eid holiday may cause delays the project timeline. TAR will explain to tenants that access is needed for all areas to proceed, TCC must prepare a method statement and list of materials, submit an investigation schedule and FIR to tenants, and request access for investigation with AECOM. Dashboard 11.05.23 Weekly Dashboard No. 01 1. Executive Summary 2. Client and Consultant Actions 3. Designer Actions 5. Weekly Look Ahead 6. Milestones DELIVERABLE START FINISH STATUS BOQ / Proposal April April Completed Contract signature 13th Apr 23 13th Apr 23 Completed Construction 14th Apr 23 17th Aug 23 On going advance payment ( Down payment 10% ) 5 working days of the Effective 30th Apr 23 4th May 23 Completed Contractor Payment application 80% (Monthly) 4th May 23 4th Jun 23 On going First payment after 62 Unit delivery TBC TBC On going Second payment after 57 Unit delivery TBC TBC On going Third payment after 34 Unit delivery TBC TBC On going Release payment of 5% of the reserved amount. TBC TBC On going Remaining batch retention. 5% TBC TBC On going Project handover TBC TBC On going 7. Commercial Update & Overview (To be Determined) 8. Project Plan Ref Description Cost Approved Project Budget 628.782.44 SAR 1 Contract B.O.Q Sum (Emergency repair works) 628.782.44 SAR 2 advance payment ( Down payment ) 10% 62.878.24 SAR - Paid 3 Contractor Payment application 80% 503.025.95 SAR - To be scheduled 4 Release payment of 5% of the reserved amount. 31.439.122 SAR 5 Remaining batch retention. 5% 31.439.122 SAR 4. Contractor Actions The design is already finished by Omrania Consulting Project details:
  • 2. Achievements: Achievements: TCC closed five villas until now Look Ahead: • MARBELLA-114 • MONACO-38 • CAPRI STREET-44 • TOWNHOUSE-36 • TOWNHOUSE-38` Item SAR Percentage Construction value 628.782.44 100% Down payment 62.878.24 100% Approved V.O. by P.M. Paid to date Other Costs - - TOTAL OF CONTRACT VAL 62.878.24 10% Type of Risk/Issue Description Severity of Impact Planned Mitigation Action required/who Risks Permit Final handover may be delayed due to delays in the issuance of permits by the ANTARA and maintenance (Engie) co. Meeting must be set up with the client and maintenance to clarify procedure TCC Reports Additional work that is not explained in the reports requires more time than anticipated. This will be documented in the MOM JLL Eid Holiday The upcoming Eid holiday may create delay, and this is an inevitable risk of hindering the project timeline TAR will handle process tenant(s) that access is needed TAR Issues No Major issues recorded N/A N/A No Major issues recorded N/A N/A Schedule S E Apr May Jun Jul Aug Construction 13-4 17- 8 Works on Balconies and Terraces 27-4 Rectification Works for Damages In & Out of the Bldgs 27-4 Roof works 27-4 Sealant Roof Works 27-4 Rectification Electrical Works 27-4 Project Close Out TBC Opening COST SUMMARY PROJECT TIMELINE PROJECT OVERVIEW KEY ACTIVITY FORECAST Location: King Khalid Br Rd, Ar Rihab, Diriyah - Kingdom of Saudi Arabia Project Type: Emergency repair works Total project value: 628.782.44 Construction planed end date: April 13, 2023 – August 17, 2023 Estimated opening date: August Project Size (sqm): Project Manager: JLL Contractor: Triangle construction contract (TCC) Consultant: AECOM Designer: Omrania consulting PERMIT STAGES RISKS & ISSUES Overall Project Status At Risk On track Complete Behind Not started On track Validation of V.O. Santorini-40  Townhouse-13  Antara drive-14  Marbella-114 Monaco-38 Dashboard 11.05.23 Weekly Dashboard No. 01 Time now
  • 3. Sun Mon Tue Wed Thu Fri Sat 01 02 03 04 05 06 07 08 Weekly call 15:00 KSA Time 09 Site visit 9:30 Site Meeting 14:00 KSA Time 10 11 12 13 14 15 Weekly call 15:00 KSA Time 16 Site visit 9:30 Site Meeting 14:00 KSA Time 17 18 19 20 21 22 Weekly call 15:00 KSA Time 23 Site visit 9:30 Site Meeting 14:00 KSA Time 24 25 26 27 28 29 Weekly call 15:00 KSA Time 30 Site visit 9:30 Site Meeting 14:00 KSA Time 31 May 2023 Dashboard 11.05.23 Calendar
  • 4. MILESTONES DUE Milestones that are coming soon. Project Update Payment Track Current and Future Payments. Cost Update Achievement Tasks and Milestones been completed. % Complete 4.9%Construction % Complete 10% # Variation Due Date Amount Status 1 VO1 2 VO2 3 VO3 Grand Total Variation Track Current and Future Variations. # Payment Due Date % Amount Status 1 Contractor – 1st invoice (10%) Down payment 10 62.878.24 SAR Paid 2 Contractor – 2nd invoice (80%) Contractor Payment application 80 503.025.95 SAR To be schedule 3 Contractor – 3rd invoice (5%) Release payment of 5% of the reserved amount. 5 31.439.122 SAR 4 Contractor – 4th invoice (5%) Remaining batch retention. 5 31.439.122 SAR Project Budget 628 K 100% Task Name Task SN-35 -- 100% TH-13 -- 100% AD-14 -- 100% TH-30 – 100% M.T-114 – 100% SN-40 – 50% TH-38 -- 50% M-48 -- 50% M-114 -- 50% MC-38 -- 50% CT-44 -- 50% TH-36 -- 50% Total of villas – 160 TCC, Will provide a tacker for tasks & achievement Dashboard 11.05.23 ProjectOverview
  • 7. Dashboard 11.05.23 Weekly Report S.No Location Description of Work Start date Permit no. Status REMARK Photos Verifying defects of water leakage Defects found in roof ducting Water leakage in bathroom ceiling Duct Joint sealant done Inspection submitted Balcony floor existing tiles works ongoing. Floor Screed to maintain slope. Water slope test done Installation of polythene sheet & Thermal insulation Sand filling in balcony area Sealant filling for electrical box Floor drain coring & installation of new pipes in external walls Water slope test done Screed work in progress 1 More defects were found in the kitchen ceiling & master bedroom Bathroom gypsum board works ongoing Bedroom,& hall area ceiling gypsum works ongoing HVAC gravel removal and drain pipe repair. Tiles replacement work in progress Water Slope Test Done & Skirting Water Proof Membrane Repair ongoing Staircase wall leakage area paint putty work in progress Core In Wall & Install New Drain Verified the defect Kitchen ceiling paint work in progress Roof hatch joint filling work in progress duct joint sealant work in progress Verified the defects of water leak water coming in bedroom wall near light switch water leak in Roof drain pipe water leak in Roof duct Duct Joint sealant work completed Verified the defects of water leak Water leak from roof duct water coming inside maid room joint sealant work in progress SANTORINI -35 TOWNHOUSE -30 ANTARA DRIV -14 TOWNHOUSE -13 SANTORINI -40 8 TOWNHOUSE-30 ANT-RWL-PER-015 DONE 9 SANTORINI -35 TOWNHOUSE -30 ANTARA DRIV-14 TOWNHOUSE -13 SANTORINI -40 DONE ANT-RWL-PER-010 DONE MONACO-38 5 TOWNHOUSE-38 ANT-RWL-PER-014 OPEN 6 SANTORINI-40 ANT-RWL-PER-012 OPEN 7 ANTARA DRIVE-14 3 ANT-RWL-PER-019 OPEN 4 TOWNHOUSE-36 OPEN CAPRI STREET -44 1 MARBELLA-114 ANT-RWL-PER-001 DONE 2 ANT-RWL-PER-009 OPEN S.No Location Description of Work Start date Permit no. Status REMARK Photos Verifying defects of water leakage Defects found in roof ducting Water leakage in bathroom ceiling Duct Joint sealant done Inspection submitted Balcony floor existing tiles works ongoing. Floor Screed to maintain slope. Water slope test done Installation of polythene sheet & Thermal insulation Sand filling in balcony area Sealant filling for electrical box Floor drain coring & installation of new pipes in external walls Water slope test done Screed work in progress 1 More defects were found in the kitchen ceiling & master bedroom Bathroom gypsum board works ongoing Bedroom,& hall area ceiling gypsum works ongoing HVAC gravel removal and drain pipe repair. Tiles replacement work in progress Water Slope Test Done & Skirting Water Proof Membrane Repair ongoing Staircase wall leakage area paint putty work in progress Core In Wall & Install New Drain Verified the defect Kitchen ceiling paint work in progress Roof hatch joint filling work in progress duct joint sealant work in progress Verified the defects of water leak water coming in bedroom wall near light switch water leak in Roof drain pipe water leak in Roof duct Duct Joint sealant work completed Verified the defects of water leak Water leak from roof duct water coming inside maid room joint sealant work in progress SANTORINI -35 TOWNHOUSE -30 ANTARA DRIV -14 TOWNHOUSE -13 SANTORINI -40 8 TOWNHOUSE-30 ANT-RWL-PER-015 DONE 9 SANTORINI -35 TOWNHOUSE -30 ANTARA DRIV-14 TOWNHOUSE -13 SANTORINI -40 DONE ANT-RWL-PER-010 DONE MONACO-38 5 TOWNHOUSE-38 ANT-RWL-PER-014 OPEN 6 SANTORINI-40 ANT-RWL-PER-012 OPEN 7 ANTARA DRIVE-14 3 ANT-RWL-PER-019 OPEN 4 TOWNHOUSE-36 OPEN CAPRI STREET -44 1 MARBELLA-114 ANT-RWL-PER-001 DONE 2 ANT-RWL-PER-009 OPEN