CLIENT: Zabeel Investement L.I.C
Planning Departement
Package No. : D0469
Early Planned Start Early Planned Finish
Tower N4
Basement 2 09-Jan-08 20-Feb-08 22.06% 0.00% Behind
Basement 1 26-Dec-07 06-Feb-08 54.41% 0% Behind
Ground 12-Dec-07 23-Jan-08 100.00% 1% Behind
Level 1 13-Aug-07 24-Sep-07 100% 1% Behind
Level 2 05-Sep-07 17-Oct-07 100% 0% Behind
Level 3 17-Sep-07 29-Oct-07 100% 0% Behind
Level 4 29-Sep-07 10-Nov-07 100% 0% Behind
Level 5 13-Oct-07 24-Nov-07 100% 0% Behind
Level 6 28-Oct-07 09-Dec-07 100% 0% Behind
Level 7 12-Nov-07 24-Dec-07 100% 0% Behind
Level 8 27-Nov-07 08-Jan-08 100% 0% Behind
Level 9 12-Dec-07 23-Jan-08 100.00% 0% Behind
Level 10 27-Dec-07 07-Feb-08 51.49% 0% Behind
Level 11 12-Jan-08 23-Feb-08 12% 0% Behind
Level 12 27-Jan-08 09-Mar-08 0% 0% On Scedule
Level 13 06-Feb-08 19-Mar-08 0% 0% On Scedule
Level 14 17-Feb-08 30-Mar-08 0% 0% On Scedule
Level 15 27-Feb-08 09-Apr-08 0% 0% On Scedule
Early Planned Dates Of Ceiling Works
Month : 26 January 2008
Early Planned Progress Of Ceiling Works Actual Progress Of CeilingWorks
Ceiling Performance
Progress Status
Anantara Palm Jumeirah and Tiara Residences
Progress Of Ceiling Works
CLIENT: Zabeel Investement L.I.C
Planning Departement
Package No. : D0469
Early Planned Start Early Planned Finish
Tower N3
Basement 2 22-Jan-08 03-Mar-08 6% 0% Behind
Basement 1 08-Jan-08 18-Feb-08 24.63% 0% Behind
Ground 25-Dec-07 04-Feb-08 61.94% 0% Behind
Level 1 23-Sep-07 03-Nov-07 100% 3% Behind
Level 2 04-Oct-07 14-Nov-07 100% 0% Behind
Level 3 16-Oct-07 26-Nov-07 100% 0% Behind
Level 4 28-Oct-07 08-Dec-07 100% 0% Behind
Level 5 08-Nov-07 19-Dec-07 100% 0% Behind
Level 6 20-Nov-07 31-Dec-07 100% 0% Behind
Level 7 02-Dec-07 12-Jan-08 100.00% 0% Behind
Level 8 13-Dec-07 23-Jan-08 100.00% 0% Behind
Level 9 25-Dec-07 04-Feb-08 62.12% 0% Behind
Level 10 06-Jan-08 16-Feb-08 30.30% 0% Behind
Level 11 17-Jan-08 27-Feb-08 6% 0% Behind
Level 12 29-Jan-08 10-Mar-08 0% 0% On Scedule
Level 13 09-Feb-08 20-Mar-08 0% 0% On Scedule
Level 14 19-Feb-08 31-Mar-08 0% 0% On Scedule
Level 15 01-Mar-08 13-Apr-08 0% 0% On Scedule
Early Planned Progress Of Ceiling Works Actual Progress Of CeilingWorks
Early Planned Dates Of Ceiling Works
Progress Status
Month : 26 January 2008
Ceiling Performance
Anantara Palm Jumeirah and Tiara Residences
Progress Of Ceiling Works
CLIENT: Zabeel Investement L.I.C
Planning Departement
Package No. : D0469
Early Planned Start Early Planned Finish
Tower N2
Basement 2 29-Jan-08 11-Mar-08 0% 0% On Scedule
Basement 1 15-Jan-08 26-Feb-08 6% 0% Behind
Ground 01-Jan-08 12-Feb-08 41% 0% Behind
Level 1 23-Sep-07 04-Nov-07 100% 1% Behind
Level 2 07-Oct-07 18-Nov-07 100% 0% Behind
Level 3 18-Oct-07 29-Nov-07 100% 0% Behind
Level 4 04-Nov-07 16-Dec-07 100% 0% Behind
Level 5 15-Nov-07 27-Dec-07 100% 0% Behind
Level 6 27-Nov-07 08-Jan-08 100% 0% Behind
Level 7 09-Dec-07 20-Jan-08 100.00% 0% Behind
Level 8 20-Dec-07 31-Jan-08 83.46% 0% Behind
Level 9 01-Jan-08 12-Feb-08 41.35% 0% Behind
Level 10 13-Jan-08 24-Feb-08 6% 0% Behind
Level 11 24-Jan-08 06-Mar-08 2% 0% Behind
Level 12 05-Feb-08 18-Mar-08 0% 0% On Scedule
Level 13 17-Feb-08 30-Mar-08 0% 0% On Scedule
Level 14 28-Feb-08 10-Apr-08 0% 0% On Scedule
Level 15 15-Mar-08 26-Apr-08 0% 0% On Scedule
Early Planned Dates Of Ceiling Works
Month : 26 January 2008
Ceiling Performance
Early Planned Progress Of Ceiling Works Actual Progress Of CeilingWorks Progress Status
Anantara Palm Jumeirah and Tiara Residences
Progress Of Ceiling Works
CLIENT: Zabeel Investement L.I.C
Planning Departement
Package No. : D0469
Early Planned Start Early Planned Finish
Tower N1
Basement 2 02-Feb-08 15-Mar-08 0% 0% On Scedule
Basement 1 19-Jan-08 01-Mar-08 6% 0% Behind
Ground 05-Jan-08 16-Feb-08 33.08% 0% Behind
Level 1 29-Sep-07 10-Nov-07 100% 0% Behind
Level 2 15-Oct-07 26-Nov-07 100% 0% Behind
Level 3 27-Oct-07 08-Dec-07 100% 0% Behind
Level 4 07-Nov-07 19-Dec-07 100% 0% Behind
Level 5 19-Nov-07 31-Dec-07 100% 0% Behind
Level 6 01-Dec-07 12-Jan-08 100.00% 0% Behind
Level 7 12-Dec-07 23-Jan-08 100.00% 0% Behind
Level 8 24-Dec-07 04-Feb-08 66.92% 0% Behind
Level 9 05-Jan-08 16-Feb-08 33.08% 0% Behind
Level 10 16-Jan-08 27-Feb-08 6% 0% Behind
Level 11 28-Jan-08 10-Mar-08 0% 0% On Scedule
Level 12 09-Feb-08 22-Mar-08 0% 0% On Scedule
Level 13 19-Feb-08 01-Apr-08 0% 0% On Scedule
Level 14 01-Mar-08 12-Apr-08 0% 0% On Scedule
Level 15 11-Mar-08 22-Apr-08 0% 0% On Scedule
Early Planned Dates Of Ceiling Works
Ceiling Performance
Month : 26 January 2008
Progress StatusEarly Planned Progress Of Ceiling Works Actual Progress Of CeilingWorks
Anantara Palm Jumeirah and Tiara Residences
Progress Of Ceiling Works
CLIENT: Zabeel Investement L.I.C
Planning Departement
Package No. : D0469
Early Planned Start Early Planned Finish
Tower S1
Basement 2 02-Jan-08 13-Feb-08 38% 0% Behind
Basement 1 19-Dec-07 30-Jan-08 86.47% 0% Behind
Ground 05-Dec-07 16-Jan-08 100.00% 0% Behind
Level 1 29-Aug-07 10-Oct-07 100% 8% Behind
Level 2 12-Sep-07 24-Oct-07 100% 2% Behind
Level 3 26-Sep-07 07-Nov-07 100% 4% Behind
Level 4 08-Oct-07 19-Nov-07 100% 2% Behind
Level 5 20-Oct-07 01-Dec-07 100% 2% Behind
Level 6 31-Oct-07 12-Dec-07 100% 0% Behind
Level 7 12-Nov-07 24-Dec-07 100% 0% Behind
Level 8 24-Nov-07 05-Jan-08 100% 0% Behind
Level 9 05-Dec-07 16-Jan-08 100.00% 0% Behind
Level 10 17-Dec-07 28-Jan-08 92.48% 0% Behind
Level 11 29-Dec-07 09-Feb-08 48.87% 0% Behind
Level 12 09-Jan-08 20-Feb-08 21.80% 0% Behind
Level 13 21-Jan-08 03-Mar-08 6% 0% Behind
Level 14 02-Feb-08 15-Mar-08 0% 0% On Scedule
Level 15 13-Feb-08 26-Mar-08 0% 0% On Scedule
Month : 26 January 2008
Ceiling Performance
Early Planned Dates Of Ceiling Works
Progress StatusEarly Planned Progress Of Ceiling Works Actual Progress Of CeilingWorks
Anantara Palm Jumeirah and Tiara Residences
Progress Of Ceiling Works
CLIENT: Zabeel Investement L.I.C
Planning Departement
Package No. : D0469
Early Planned Start Early Planned Finish
Tower S2
Basement 2 01-Jan-08 11-Feb-08 42.86% 0% Behind
Basement 1 18-Dec-07 28-Jan-08 90.98% 0% Behind
Ground 04-Dec-07 14-Jan-08 100.00% 0% Behind
Level 1 02-Sep-07 13-Oct-07 100% 7% Behind
Level 2 13-Sep-07 24-Oct-07 100% 7% Behind
Level 3 25-Sep-07 05-Nov-07 100% 3% Behind
Level 4 07-Oct-07 17-Nov-07 100% 2% Behind
Level 5 18-Oct-07 28-Nov-07 100% 2% Behind
Level 6 30-Oct-07 10-Dec-07 100% 2% Behind
Level 7 11-Nov-07 22-Dec-07 100% 0% Behind
Level 8 22-Nov-07 02-Jan-08 100% 0% Behind
Level 9 04-Dec-07 14-Jan-08 100.00% 0% Behind
Level 10 16-Dec-07 26-Jan-08 96.99% 0% Behind
Level 11 27-Dec-07 06-Feb-08 53.38% 0% Behind
Level 12 08-Jan-08 18-Feb-08 24.81% 0% Behind
Level 13 20-Jan-08 01-Mar-08 6% 0% Behind
Level 14 31-Jan-08 12-Mar-08 0% 0% On Scedule
Level 15 12-Feb-08 24-Mar-08 0% 0% On Scedule
Early Planned Dates Of Ceiling Works
Month : 26 January 2008
Early Planned Progress Of Ceiling Works Actual Progress Of CeilingWorks Progress Status
Ceiling Performance
Anantara Palm Jumeirah and Tiara Residences
Progress Of Ceiling Works
CLIENT: Zabeel Investement L.I.C
Planning Departement
Package No. : D0469
Early Planned Start Early Planned Finish
Tower S3
Basement 2 26-Dec-07 06-Feb-08 55% 0% Behind
Basement 1 12-Dec-07 23-Jan-08 100.00% 0% Behind
Ground 28-Nov-07 09-Jan-08 100% 0% Behind
Level 1 06-Aug-07 17-Sep-07 100% 7% Behind
Level 2 22-Aug-07 03-Oct-07 100% 8% Behind
Level 3 05-Sep-07 17-Oct-07 100% 0% Behind
Level 4 19-Sep-07 31-Oct-07 100% 0% Behind
Level 5 03-Oct-07 14-Nov-07 100% 0% Behind
Level 6 17-Oct-07 28-Nov-07 100% 0% Behind
Level 7 31-Oct-07 12-Dec-07 100% 0% Behind
Level 8 14-Nov-07 26-Dec-07 100% 0% Behind
Level 9 28-Nov-07 09-Jan-08 100% 0% Behind
Level 10 12-Dec-07 23-Jan-08 100.00% 0% Behind
Level 11 26-Dec-07 06-Feb-08 54.89% 0% Behind
Level 12 07-Jan-08 18-Feb-08 26.32% 0% Behind
Level 13 21-Jan-08 03-Mar-08 6% 0% Behind
Level 14 04-Feb-08 17-Mar-08 0% 0% On Scedule
Level 15 18-Feb-08 31-Mar-08 0% 0% On Scedule
Month : 26 January 2008
Ceiling Performance
Progress Of Ceiling Works
Early Planned Dates Of Ceiling Works
Progress Status
Anantara Palm Jumeirah and Tiara Residences
Early Planned Progress Of Ceiling Works Actual Progress Of CeilingWorks
CLIENT: Zabeel Investement L.I.C
Planning Departement
Package No. : D0469
Early Planned Start Early Planned Finish
Tower H1
Basement 3 29-Jan-08 10-Mar-08 0% 0% On Scedule
Basement 2 17-Jan-08 27-Feb-08 4% 0% Behind
Basement 1 03-Jan-08 13-Feb-08 27.37% 0% Behind
Ground 20-Dec-07 30-Jan-08 85.39% 0% Behind
Mezzanine 06-Dec-07 16-Jan-08 100.00% 0% Behind
Level 1 23-Aug-07 03-Oct-07 100% 0% Behind
Level 2 06-Sep-07 17-Oct-07 100% 0% Behind
Level 3 20-Sep-07 31-Oct-07 100% 0% Behind
Level 4 04-Oct-07 14-Nov-07 100% 0% Behind
Level 5 18-Oct-07 28-Nov-07 100% 0% Behind
Level 6 01-Nov-07 12-Dec-07 100% 0% Behind
Level 7 13-Nov-07 24-Dec-07 100% 0% Behind
Level 8 25-Nov-07 05-Jan-08 100% 0% Behind
Level 9 06-Dec-07 16-Jan-08 100.00% 0% Behind
Level 10 20-Dec-07 30-Jan-08 86.03% 0% Behind
Level 11 03-Jan-08 13-Feb-08 26.82% 0% Behind
Level 12 17-Jan-08 27-Feb-08 4% 0% Behind
Level 13 31-Jan-08 12-Mar-08 0% 0% On Scedule
Level 14 14-Feb-08 26-Mar-08 0% 0% On Scedule
Level 15 26-Feb-08 07-Apr-08 0% 0% On Scedule
Early Planned Progress Of Ceiling Works Actual Progress Of CeilingWorks Progress Status
Month : 26 January 2008
Early Planned Dates Of Ceiling Works
Ceiling Performance
Progress Of Ceiling Works
Anantara Palm Jumeirah and Tiara Residences
CLIENT: Zabeel Investement L.I.C
Planning Departement
Package No. : D0469
Early Planned Start Early Planned Finish
Tower H2
Basement 3 28-Jan-08 09-Mar-08 0% 0% On Scedule
Basement 2 16-Jan-08 26-Feb-08 7% 0% Behind
Basement 1 05-Jan-08 14-Feb-08 25.14% 0% Behind
Ground 24-Dec-07 03-Feb-08 72.78% 0% Behind
Mezzanine 12-Dec-07 22-Jan-08 100.00% 0% Behind
Level 1 04-Sep-07 15-Oct-07 100% 0% Behind
Level 2 18-Sep-07 29-Oct-07 100% 0% Behind
Level 3 04-Oct-07 14-Nov-07 100% 0% Behind
Level 4 17-Oct-07 27-Nov-07 100% 0% Behind
Level 5 31-Oct-07 11-Dec-07 100% 0% Behind
Level 6 14-Nov-07 25-Dec-07 100% 0% Behind
Level 7 28-Nov-07 08-Jan-08 100% 0% Behind
Level 8 12-Dec-07 22-Jan-08 100.00% 0% Behind
Level 9 26-Dec-07 05-Feb-08 60.00% 0% Behind
Level 10 07-Jan-08 17-Feb-08 20.67% 0% Behind
Level 11 19-Jan-08 28-Feb-08 4% 0% Behind
Level 12 30-Jan-08 11-Mar-08 0% 0% On Scedule
Level 13 11-Feb-08 23-Mar-08 0% 0% On Scedule
Level 14 23-Feb-08 03-Apr-08 0% 0% On Scedule
Level 15 05-Mar-08 15-Apr-08 0% 0% On Scedule
Progress StatusEarly Planned Progress Of Ceiling Works Actual Progress Of CeilingWorks
Month : 26 January 2008
Ceiling Performance
Early Planned Dates Of Ceiling Works
Anantara Palm Jumeirah and Tiara Residences
Progress Of Ceiling Works

More Related Content

More from Sam Kendall, MSc, BSc Civil Eng., PMP®, MIEAust

More from Sam Kendall, MSc, BSc Civil Eng., PMP®, MIEAust (20)

Kandil Mohammed Ibrahim_Sameh_Dissertation
Kandil Mohammed Ibrahim_Sameh_DissertationKandil Mohammed Ibrahim_Sameh_Dissertation
Kandil Mohammed Ibrahim_Sameh_Dissertation
 
Summary Progress Of Facade Works
Summary Progress Of Facade WorksSummary Progress Of Facade Works
Summary Progress Of Facade Works
 
Summary Progress Of Concrete Works
Summary Progress Of Concrete WorksSummary Progress Of Concrete Works
Summary Progress Of Concrete Works
 
N1
N1N1
N1
 
Overall Progress S-Curve For Ceiling
Overall Progress S-Curve For CeilingOverall Progress S-Curve For Ceiling
Overall Progress S-Curve For Ceiling
 
Overall Progress S-Curve For Facades
Overall Progress S-Curve For FacadesOverall Progress S-Curve For Facades
Overall Progress S-Curve For Facades
 
Overall Progress S-Curve For Elevators
Overall Progress S-Curve For ElevatorsOverall Progress S-Curve For Elevators
Overall Progress S-Curve For Elevators
 
Overall Progres S-Curve For Concrete Works
Overall Progres S-Curve For Concrete WorksOverall Progres S-Curve For Concrete Works
Overall Progres S-Curve For Concrete Works
 
Window Analysis @ 30-June-2012
Window Analysis @ 30-June-2012Window Analysis @ 30-June-2012
Window Analysis @ 30-June-2012
 
01. P269 - Project Implementation Programme - Rev 00
01. P269 - Project Implementation Programme -  Rev 0001. P269 - Project Implementation Programme -  Rev 00
01. P269 - Project Implementation Programme - Rev 00
 
13. Overall S-Curve
13. Overall S-Curve13. Overall S-Curve
13. Overall S-Curve
 
10. Overall Implementation Programme
10. Overall Implementation Programme10. Overall Implementation Programme
10. Overall Implementation Programme
 
Building-Structure Planning Model
Building-Structure Planning ModelBuilding-Structure Planning Model
Building-Structure Planning Model
 
AWI20202 commercial
AWI20202 commercialAWI20202 commercial
AWI20202 commercial
 
Rihan Height Project Execution Plan-Rev00
Rihan Height Project Execution Plan-Rev00Rihan Height Project Execution Plan-Rev00
Rihan Height Project Execution Plan-Rev00
 
Monthly Progress Report No.13 - September 2011
Monthly Progress Report No.13 - September 2011Monthly Progress Report No.13 - September 2011
Monthly Progress Report No.13 - September 2011
 
Final Submission EOT 1
Final Submission EOT 1Final Submission EOT 1
Final Submission EOT 1
 
Cash Flow Portfolio
Cash Flow PortfolioCash Flow Portfolio
Cash Flow Portfolio
 
Resources Histograms
Resources HistogramsResources Histograms
Resources Histograms
 
Resources Calculations for Bldg. A
Resources Calculations for Bldg. AResources Calculations for Bldg. A
Resources Calculations for Bldg. A
 

Progress Of Ceiling Per Floors

  • 1. CLIENT: Zabeel Investement L.I.C Planning Departement Package No. : D0469 Early Planned Start Early Planned Finish Tower N4 Basement 2 09-Jan-08 20-Feb-08 22.06% 0.00% Behind Basement 1 26-Dec-07 06-Feb-08 54.41% 0% Behind Ground 12-Dec-07 23-Jan-08 100.00% 1% Behind Level 1 13-Aug-07 24-Sep-07 100% 1% Behind Level 2 05-Sep-07 17-Oct-07 100% 0% Behind Level 3 17-Sep-07 29-Oct-07 100% 0% Behind Level 4 29-Sep-07 10-Nov-07 100% 0% Behind Level 5 13-Oct-07 24-Nov-07 100% 0% Behind Level 6 28-Oct-07 09-Dec-07 100% 0% Behind Level 7 12-Nov-07 24-Dec-07 100% 0% Behind Level 8 27-Nov-07 08-Jan-08 100% 0% Behind Level 9 12-Dec-07 23-Jan-08 100.00% 0% Behind Level 10 27-Dec-07 07-Feb-08 51.49% 0% Behind Level 11 12-Jan-08 23-Feb-08 12% 0% Behind Level 12 27-Jan-08 09-Mar-08 0% 0% On Scedule Level 13 06-Feb-08 19-Mar-08 0% 0% On Scedule Level 14 17-Feb-08 30-Mar-08 0% 0% On Scedule Level 15 27-Feb-08 09-Apr-08 0% 0% On Scedule Early Planned Dates Of Ceiling Works Month : 26 January 2008 Early Planned Progress Of Ceiling Works Actual Progress Of CeilingWorks Ceiling Performance Progress Status Anantara Palm Jumeirah and Tiara Residences Progress Of Ceiling Works
  • 2. CLIENT: Zabeel Investement L.I.C Planning Departement Package No. : D0469 Early Planned Start Early Planned Finish Tower N3 Basement 2 22-Jan-08 03-Mar-08 6% 0% Behind Basement 1 08-Jan-08 18-Feb-08 24.63% 0% Behind Ground 25-Dec-07 04-Feb-08 61.94% 0% Behind Level 1 23-Sep-07 03-Nov-07 100% 3% Behind Level 2 04-Oct-07 14-Nov-07 100% 0% Behind Level 3 16-Oct-07 26-Nov-07 100% 0% Behind Level 4 28-Oct-07 08-Dec-07 100% 0% Behind Level 5 08-Nov-07 19-Dec-07 100% 0% Behind Level 6 20-Nov-07 31-Dec-07 100% 0% Behind Level 7 02-Dec-07 12-Jan-08 100.00% 0% Behind Level 8 13-Dec-07 23-Jan-08 100.00% 0% Behind Level 9 25-Dec-07 04-Feb-08 62.12% 0% Behind Level 10 06-Jan-08 16-Feb-08 30.30% 0% Behind Level 11 17-Jan-08 27-Feb-08 6% 0% Behind Level 12 29-Jan-08 10-Mar-08 0% 0% On Scedule Level 13 09-Feb-08 20-Mar-08 0% 0% On Scedule Level 14 19-Feb-08 31-Mar-08 0% 0% On Scedule Level 15 01-Mar-08 13-Apr-08 0% 0% On Scedule Early Planned Progress Of Ceiling Works Actual Progress Of CeilingWorks Early Planned Dates Of Ceiling Works Progress Status Month : 26 January 2008 Ceiling Performance Anantara Palm Jumeirah and Tiara Residences Progress Of Ceiling Works
  • 3. CLIENT: Zabeel Investement L.I.C Planning Departement Package No. : D0469 Early Planned Start Early Planned Finish Tower N2 Basement 2 29-Jan-08 11-Mar-08 0% 0% On Scedule Basement 1 15-Jan-08 26-Feb-08 6% 0% Behind Ground 01-Jan-08 12-Feb-08 41% 0% Behind Level 1 23-Sep-07 04-Nov-07 100% 1% Behind Level 2 07-Oct-07 18-Nov-07 100% 0% Behind Level 3 18-Oct-07 29-Nov-07 100% 0% Behind Level 4 04-Nov-07 16-Dec-07 100% 0% Behind Level 5 15-Nov-07 27-Dec-07 100% 0% Behind Level 6 27-Nov-07 08-Jan-08 100% 0% Behind Level 7 09-Dec-07 20-Jan-08 100.00% 0% Behind Level 8 20-Dec-07 31-Jan-08 83.46% 0% Behind Level 9 01-Jan-08 12-Feb-08 41.35% 0% Behind Level 10 13-Jan-08 24-Feb-08 6% 0% Behind Level 11 24-Jan-08 06-Mar-08 2% 0% Behind Level 12 05-Feb-08 18-Mar-08 0% 0% On Scedule Level 13 17-Feb-08 30-Mar-08 0% 0% On Scedule Level 14 28-Feb-08 10-Apr-08 0% 0% On Scedule Level 15 15-Mar-08 26-Apr-08 0% 0% On Scedule Early Planned Dates Of Ceiling Works Month : 26 January 2008 Ceiling Performance Early Planned Progress Of Ceiling Works Actual Progress Of CeilingWorks Progress Status Anantara Palm Jumeirah and Tiara Residences Progress Of Ceiling Works
  • 4. CLIENT: Zabeel Investement L.I.C Planning Departement Package No. : D0469 Early Planned Start Early Planned Finish Tower N1 Basement 2 02-Feb-08 15-Mar-08 0% 0% On Scedule Basement 1 19-Jan-08 01-Mar-08 6% 0% Behind Ground 05-Jan-08 16-Feb-08 33.08% 0% Behind Level 1 29-Sep-07 10-Nov-07 100% 0% Behind Level 2 15-Oct-07 26-Nov-07 100% 0% Behind Level 3 27-Oct-07 08-Dec-07 100% 0% Behind Level 4 07-Nov-07 19-Dec-07 100% 0% Behind Level 5 19-Nov-07 31-Dec-07 100% 0% Behind Level 6 01-Dec-07 12-Jan-08 100.00% 0% Behind Level 7 12-Dec-07 23-Jan-08 100.00% 0% Behind Level 8 24-Dec-07 04-Feb-08 66.92% 0% Behind Level 9 05-Jan-08 16-Feb-08 33.08% 0% Behind Level 10 16-Jan-08 27-Feb-08 6% 0% Behind Level 11 28-Jan-08 10-Mar-08 0% 0% On Scedule Level 12 09-Feb-08 22-Mar-08 0% 0% On Scedule Level 13 19-Feb-08 01-Apr-08 0% 0% On Scedule Level 14 01-Mar-08 12-Apr-08 0% 0% On Scedule Level 15 11-Mar-08 22-Apr-08 0% 0% On Scedule Early Planned Dates Of Ceiling Works Ceiling Performance Month : 26 January 2008 Progress StatusEarly Planned Progress Of Ceiling Works Actual Progress Of CeilingWorks Anantara Palm Jumeirah and Tiara Residences Progress Of Ceiling Works
  • 5. CLIENT: Zabeel Investement L.I.C Planning Departement Package No. : D0469 Early Planned Start Early Planned Finish Tower S1 Basement 2 02-Jan-08 13-Feb-08 38% 0% Behind Basement 1 19-Dec-07 30-Jan-08 86.47% 0% Behind Ground 05-Dec-07 16-Jan-08 100.00% 0% Behind Level 1 29-Aug-07 10-Oct-07 100% 8% Behind Level 2 12-Sep-07 24-Oct-07 100% 2% Behind Level 3 26-Sep-07 07-Nov-07 100% 4% Behind Level 4 08-Oct-07 19-Nov-07 100% 2% Behind Level 5 20-Oct-07 01-Dec-07 100% 2% Behind Level 6 31-Oct-07 12-Dec-07 100% 0% Behind Level 7 12-Nov-07 24-Dec-07 100% 0% Behind Level 8 24-Nov-07 05-Jan-08 100% 0% Behind Level 9 05-Dec-07 16-Jan-08 100.00% 0% Behind Level 10 17-Dec-07 28-Jan-08 92.48% 0% Behind Level 11 29-Dec-07 09-Feb-08 48.87% 0% Behind Level 12 09-Jan-08 20-Feb-08 21.80% 0% Behind Level 13 21-Jan-08 03-Mar-08 6% 0% Behind Level 14 02-Feb-08 15-Mar-08 0% 0% On Scedule Level 15 13-Feb-08 26-Mar-08 0% 0% On Scedule Month : 26 January 2008 Ceiling Performance Early Planned Dates Of Ceiling Works Progress StatusEarly Planned Progress Of Ceiling Works Actual Progress Of CeilingWorks Anantara Palm Jumeirah and Tiara Residences Progress Of Ceiling Works
  • 6. CLIENT: Zabeel Investement L.I.C Planning Departement Package No. : D0469 Early Planned Start Early Planned Finish Tower S2 Basement 2 01-Jan-08 11-Feb-08 42.86% 0% Behind Basement 1 18-Dec-07 28-Jan-08 90.98% 0% Behind Ground 04-Dec-07 14-Jan-08 100.00% 0% Behind Level 1 02-Sep-07 13-Oct-07 100% 7% Behind Level 2 13-Sep-07 24-Oct-07 100% 7% Behind Level 3 25-Sep-07 05-Nov-07 100% 3% Behind Level 4 07-Oct-07 17-Nov-07 100% 2% Behind Level 5 18-Oct-07 28-Nov-07 100% 2% Behind Level 6 30-Oct-07 10-Dec-07 100% 2% Behind Level 7 11-Nov-07 22-Dec-07 100% 0% Behind Level 8 22-Nov-07 02-Jan-08 100% 0% Behind Level 9 04-Dec-07 14-Jan-08 100.00% 0% Behind Level 10 16-Dec-07 26-Jan-08 96.99% 0% Behind Level 11 27-Dec-07 06-Feb-08 53.38% 0% Behind Level 12 08-Jan-08 18-Feb-08 24.81% 0% Behind Level 13 20-Jan-08 01-Mar-08 6% 0% Behind Level 14 31-Jan-08 12-Mar-08 0% 0% On Scedule Level 15 12-Feb-08 24-Mar-08 0% 0% On Scedule Early Planned Dates Of Ceiling Works Month : 26 January 2008 Early Planned Progress Of Ceiling Works Actual Progress Of CeilingWorks Progress Status Ceiling Performance Anantara Palm Jumeirah and Tiara Residences Progress Of Ceiling Works
  • 7. CLIENT: Zabeel Investement L.I.C Planning Departement Package No. : D0469 Early Planned Start Early Planned Finish Tower S3 Basement 2 26-Dec-07 06-Feb-08 55% 0% Behind Basement 1 12-Dec-07 23-Jan-08 100.00% 0% Behind Ground 28-Nov-07 09-Jan-08 100% 0% Behind Level 1 06-Aug-07 17-Sep-07 100% 7% Behind Level 2 22-Aug-07 03-Oct-07 100% 8% Behind Level 3 05-Sep-07 17-Oct-07 100% 0% Behind Level 4 19-Sep-07 31-Oct-07 100% 0% Behind Level 5 03-Oct-07 14-Nov-07 100% 0% Behind Level 6 17-Oct-07 28-Nov-07 100% 0% Behind Level 7 31-Oct-07 12-Dec-07 100% 0% Behind Level 8 14-Nov-07 26-Dec-07 100% 0% Behind Level 9 28-Nov-07 09-Jan-08 100% 0% Behind Level 10 12-Dec-07 23-Jan-08 100.00% 0% Behind Level 11 26-Dec-07 06-Feb-08 54.89% 0% Behind Level 12 07-Jan-08 18-Feb-08 26.32% 0% Behind Level 13 21-Jan-08 03-Mar-08 6% 0% Behind Level 14 04-Feb-08 17-Mar-08 0% 0% On Scedule Level 15 18-Feb-08 31-Mar-08 0% 0% On Scedule Month : 26 January 2008 Ceiling Performance Progress Of Ceiling Works Early Planned Dates Of Ceiling Works Progress Status Anantara Palm Jumeirah and Tiara Residences Early Planned Progress Of Ceiling Works Actual Progress Of CeilingWorks
  • 8. CLIENT: Zabeel Investement L.I.C Planning Departement Package No. : D0469 Early Planned Start Early Planned Finish Tower H1 Basement 3 29-Jan-08 10-Mar-08 0% 0% On Scedule Basement 2 17-Jan-08 27-Feb-08 4% 0% Behind Basement 1 03-Jan-08 13-Feb-08 27.37% 0% Behind Ground 20-Dec-07 30-Jan-08 85.39% 0% Behind Mezzanine 06-Dec-07 16-Jan-08 100.00% 0% Behind Level 1 23-Aug-07 03-Oct-07 100% 0% Behind Level 2 06-Sep-07 17-Oct-07 100% 0% Behind Level 3 20-Sep-07 31-Oct-07 100% 0% Behind Level 4 04-Oct-07 14-Nov-07 100% 0% Behind Level 5 18-Oct-07 28-Nov-07 100% 0% Behind Level 6 01-Nov-07 12-Dec-07 100% 0% Behind Level 7 13-Nov-07 24-Dec-07 100% 0% Behind Level 8 25-Nov-07 05-Jan-08 100% 0% Behind Level 9 06-Dec-07 16-Jan-08 100.00% 0% Behind Level 10 20-Dec-07 30-Jan-08 86.03% 0% Behind Level 11 03-Jan-08 13-Feb-08 26.82% 0% Behind Level 12 17-Jan-08 27-Feb-08 4% 0% Behind Level 13 31-Jan-08 12-Mar-08 0% 0% On Scedule Level 14 14-Feb-08 26-Mar-08 0% 0% On Scedule Level 15 26-Feb-08 07-Apr-08 0% 0% On Scedule Early Planned Progress Of Ceiling Works Actual Progress Of CeilingWorks Progress Status Month : 26 January 2008 Early Planned Dates Of Ceiling Works Ceiling Performance Progress Of Ceiling Works Anantara Palm Jumeirah and Tiara Residences
  • 9. CLIENT: Zabeel Investement L.I.C Planning Departement Package No. : D0469 Early Planned Start Early Planned Finish Tower H2 Basement 3 28-Jan-08 09-Mar-08 0% 0% On Scedule Basement 2 16-Jan-08 26-Feb-08 7% 0% Behind Basement 1 05-Jan-08 14-Feb-08 25.14% 0% Behind Ground 24-Dec-07 03-Feb-08 72.78% 0% Behind Mezzanine 12-Dec-07 22-Jan-08 100.00% 0% Behind Level 1 04-Sep-07 15-Oct-07 100% 0% Behind Level 2 18-Sep-07 29-Oct-07 100% 0% Behind Level 3 04-Oct-07 14-Nov-07 100% 0% Behind Level 4 17-Oct-07 27-Nov-07 100% 0% Behind Level 5 31-Oct-07 11-Dec-07 100% 0% Behind Level 6 14-Nov-07 25-Dec-07 100% 0% Behind Level 7 28-Nov-07 08-Jan-08 100% 0% Behind Level 8 12-Dec-07 22-Jan-08 100.00% 0% Behind Level 9 26-Dec-07 05-Feb-08 60.00% 0% Behind Level 10 07-Jan-08 17-Feb-08 20.67% 0% Behind Level 11 19-Jan-08 28-Feb-08 4% 0% Behind Level 12 30-Jan-08 11-Mar-08 0% 0% On Scedule Level 13 11-Feb-08 23-Mar-08 0% 0% On Scedule Level 14 23-Feb-08 03-Apr-08 0% 0% On Scedule Level 15 05-Mar-08 15-Apr-08 0% 0% On Scedule Progress StatusEarly Planned Progress Of Ceiling Works Actual Progress Of CeilingWorks Month : 26 January 2008 Ceiling Performance Early Planned Dates Of Ceiling Works Anantara Palm Jumeirah and Tiara Residences Progress Of Ceiling Works