Progress Of Ceiling Per Floors
- 1. CLIENT: Zabeel Investement L.I.C
Planning Departement
Package No. : D0469
Early Planned Start Early Planned Finish
Tower N4
Basement 2 09-Jan-08 20-Feb-08 22.06% 0.00% Behind
Basement 1 26-Dec-07 06-Feb-08 54.41% 0% Behind
Ground 12-Dec-07 23-Jan-08 100.00% 1% Behind
Level 1 13-Aug-07 24-Sep-07 100% 1% Behind
Level 2 05-Sep-07 17-Oct-07 100% 0% Behind
Level 3 17-Sep-07 29-Oct-07 100% 0% Behind
Level 4 29-Sep-07 10-Nov-07 100% 0% Behind
Level 5 13-Oct-07 24-Nov-07 100% 0% Behind
Level 6 28-Oct-07 09-Dec-07 100% 0% Behind
Level 7 12-Nov-07 24-Dec-07 100% 0% Behind
Level 8 27-Nov-07 08-Jan-08 100% 0% Behind
Level 9 12-Dec-07 23-Jan-08 100.00% 0% Behind
Level 10 27-Dec-07 07-Feb-08 51.49% 0% Behind
Level 11 12-Jan-08 23-Feb-08 12% 0% Behind
Level 12 27-Jan-08 09-Mar-08 0% 0% On Scedule
Level 13 06-Feb-08 19-Mar-08 0% 0% On Scedule
Level 14 17-Feb-08 30-Mar-08 0% 0% On Scedule
Level 15 27-Feb-08 09-Apr-08 0% 0% On Scedule
Early Planned Dates Of Ceiling Works
Month : 26 January 2008
Early Planned Progress Of Ceiling Works Actual Progress Of CeilingWorks
Ceiling Performance
Progress Status
Anantara Palm Jumeirah and Tiara Residences
Progress Of Ceiling Works
- 2. CLIENT: Zabeel Investement L.I.C
Planning Departement
Package No. : D0469
Early Planned Start Early Planned Finish
Tower N3
Basement 2 22-Jan-08 03-Mar-08 6% 0% Behind
Basement 1 08-Jan-08 18-Feb-08 24.63% 0% Behind
Ground 25-Dec-07 04-Feb-08 61.94% 0% Behind
Level 1 23-Sep-07 03-Nov-07 100% 3% Behind
Level 2 04-Oct-07 14-Nov-07 100% 0% Behind
Level 3 16-Oct-07 26-Nov-07 100% 0% Behind
Level 4 28-Oct-07 08-Dec-07 100% 0% Behind
Level 5 08-Nov-07 19-Dec-07 100% 0% Behind
Level 6 20-Nov-07 31-Dec-07 100% 0% Behind
Level 7 02-Dec-07 12-Jan-08 100.00% 0% Behind
Level 8 13-Dec-07 23-Jan-08 100.00% 0% Behind
Level 9 25-Dec-07 04-Feb-08 62.12% 0% Behind
Level 10 06-Jan-08 16-Feb-08 30.30% 0% Behind
Level 11 17-Jan-08 27-Feb-08 6% 0% Behind
Level 12 29-Jan-08 10-Mar-08 0% 0% On Scedule
Level 13 09-Feb-08 20-Mar-08 0% 0% On Scedule
Level 14 19-Feb-08 31-Mar-08 0% 0% On Scedule
Level 15 01-Mar-08 13-Apr-08 0% 0% On Scedule
Early Planned Progress Of Ceiling Works Actual Progress Of CeilingWorks
Early Planned Dates Of Ceiling Works
Progress Status
Month : 26 January 2008
Ceiling Performance
Anantara Palm Jumeirah and Tiara Residences
Progress Of Ceiling Works
- 3. CLIENT: Zabeel Investement L.I.C
Planning Departement
Package No. : D0469
Early Planned Start Early Planned Finish
Tower N2
Basement 2 29-Jan-08 11-Mar-08 0% 0% On Scedule
Basement 1 15-Jan-08 26-Feb-08 6% 0% Behind
Ground 01-Jan-08 12-Feb-08 41% 0% Behind
Level 1 23-Sep-07 04-Nov-07 100% 1% Behind
Level 2 07-Oct-07 18-Nov-07 100% 0% Behind
Level 3 18-Oct-07 29-Nov-07 100% 0% Behind
Level 4 04-Nov-07 16-Dec-07 100% 0% Behind
Level 5 15-Nov-07 27-Dec-07 100% 0% Behind
Level 6 27-Nov-07 08-Jan-08 100% 0% Behind
Level 7 09-Dec-07 20-Jan-08 100.00% 0% Behind
Level 8 20-Dec-07 31-Jan-08 83.46% 0% Behind
Level 9 01-Jan-08 12-Feb-08 41.35% 0% Behind
Level 10 13-Jan-08 24-Feb-08 6% 0% Behind
Level 11 24-Jan-08 06-Mar-08 2% 0% Behind
Level 12 05-Feb-08 18-Mar-08 0% 0% On Scedule
Level 13 17-Feb-08 30-Mar-08 0% 0% On Scedule
Level 14 28-Feb-08 10-Apr-08 0% 0% On Scedule
Level 15 15-Mar-08 26-Apr-08 0% 0% On Scedule
Early Planned Dates Of Ceiling Works
Month : 26 January 2008
Ceiling Performance
Early Planned Progress Of Ceiling Works Actual Progress Of CeilingWorks Progress Status
Anantara Palm Jumeirah and Tiara Residences
Progress Of Ceiling Works
- 4. CLIENT: Zabeel Investement L.I.C
Planning Departement
Package No. : D0469
Early Planned Start Early Planned Finish
Tower N1
Basement 2 02-Feb-08 15-Mar-08 0% 0% On Scedule
Basement 1 19-Jan-08 01-Mar-08 6% 0% Behind
Ground 05-Jan-08 16-Feb-08 33.08% 0% Behind
Level 1 29-Sep-07 10-Nov-07 100% 0% Behind
Level 2 15-Oct-07 26-Nov-07 100% 0% Behind
Level 3 27-Oct-07 08-Dec-07 100% 0% Behind
Level 4 07-Nov-07 19-Dec-07 100% 0% Behind
Level 5 19-Nov-07 31-Dec-07 100% 0% Behind
Level 6 01-Dec-07 12-Jan-08 100.00% 0% Behind
Level 7 12-Dec-07 23-Jan-08 100.00% 0% Behind
Level 8 24-Dec-07 04-Feb-08 66.92% 0% Behind
Level 9 05-Jan-08 16-Feb-08 33.08% 0% Behind
Level 10 16-Jan-08 27-Feb-08 6% 0% Behind
Level 11 28-Jan-08 10-Mar-08 0% 0% On Scedule
Level 12 09-Feb-08 22-Mar-08 0% 0% On Scedule
Level 13 19-Feb-08 01-Apr-08 0% 0% On Scedule
Level 14 01-Mar-08 12-Apr-08 0% 0% On Scedule
Level 15 11-Mar-08 22-Apr-08 0% 0% On Scedule
Early Planned Dates Of Ceiling Works
Ceiling Performance
Month : 26 January 2008
Progress StatusEarly Planned Progress Of Ceiling Works Actual Progress Of CeilingWorks
Anantara Palm Jumeirah and Tiara Residences
Progress Of Ceiling Works
- 5. CLIENT: Zabeel Investement L.I.C
Planning Departement
Package No. : D0469
Early Planned Start Early Planned Finish
Tower S1
Basement 2 02-Jan-08 13-Feb-08 38% 0% Behind
Basement 1 19-Dec-07 30-Jan-08 86.47% 0% Behind
Ground 05-Dec-07 16-Jan-08 100.00% 0% Behind
Level 1 29-Aug-07 10-Oct-07 100% 8% Behind
Level 2 12-Sep-07 24-Oct-07 100% 2% Behind
Level 3 26-Sep-07 07-Nov-07 100% 4% Behind
Level 4 08-Oct-07 19-Nov-07 100% 2% Behind
Level 5 20-Oct-07 01-Dec-07 100% 2% Behind
Level 6 31-Oct-07 12-Dec-07 100% 0% Behind
Level 7 12-Nov-07 24-Dec-07 100% 0% Behind
Level 8 24-Nov-07 05-Jan-08 100% 0% Behind
Level 9 05-Dec-07 16-Jan-08 100.00% 0% Behind
Level 10 17-Dec-07 28-Jan-08 92.48% 0% Behind
Level 11 29-Dec-07 09-Feb-08 48.87% 0% Behind
Level 12 09-Jan-08 20-Feb-08 21.80% 0% Behind
Level 13 21-Jan-08 03-Mar-08 6% 0% Behind
Level 14 02-Feb-08 15-Mar-08 0% 0% On Scedule
Level 15 13-Feb-08 26-Mar-08 0% 0% On Scedule
Month : 26 January 2008
Ceiling Performance
Early Planned Dates Of Ceiling Works
Progress StatusEarly Planned Progress Of Ceiling Works Actual Progress Of CeilingWorks
Anantara Palm Jumeirah and Tiara Residences
Progress Of Ceiling Works
- 6. CLIENT: Zabeel Investement L.I.C
Planning Departement
Package No. : D0469
Early Planned Start Early Planned Finish
Tower S2
Basement 2 01-Jan-08 11-Feb-08 42.86% 0% Behind
Basement 1 18-Dec-07 28-Jan-08 90.98% 0% Behind
Ground 04-Dec-07 14-Jan-08 100.00% 0% Behind
Level 1 02-Sep-07 13-Oct-07 100% 7% Behind
Level 2 13-Sep-07 24-Oct-07 100% 7% Behind
Level 3 25-Sep-07 05-Nov-07 100% 3% Behind
Level 4 07-Oct-07 17-Nov-07 100% 2% Behind
Level 5 18-Oct-07 28-Nov-07 100% 2% Behind
Level 6 30-Oct-07 10-Dec-07 100% 2% Behind
Level 7 11-Nov-07 22-Dec-07 100% 0% Behind
Level 8 22-Nov-07 02-Jan-08 100% 0% Behind
Level 9 04-Dec-07 14-Jan-08 100.00% 0% Behind
Level 10 16-Dec-07 26-Jan-08 96.99% 0% Behind
Level 11 27-Dec-07 06-Feb-08 53.38% 0% Behind
Level 12 08-Jan-08 18-Feb-08 24.81% 0% Behind
Level 13 20-Jan-08 01-Mar-08 6% 0% Behind
Level 14 31-Jan-08 12-Mar-08 0% 0% On Scedule
Level 15 12-Feb-08 24-Mar-08 0% 0% On Scedule
Early Planned Dates Of Ceiling Works
Month : 26 January 2008
Early Planned Progress Of Ceiling Works Actual Progress Of CeilingWorks Progress Status
Ceiling Performance
Anantara Palm Jumeirah and Tiara Residences
Progress Of Ceiling Works
- 7. CLIENT: Zabeel Investement L.I.C
Planning Departement
Package No. : D0469
Early Planned Start Early Planned Finish
Tower S3
Basement 2 26-Dec-07 06-Feb-08 55% 0% Behind
Basement 1 12-Dec-07 23-Jan-08 100.00% 0% Behind
Ground 28-Nov-07 09-Jan-08 100% 0% Behind
Level 1 06-Aug-07 17-Sep-07 100% 7% Behind
Level 2 22-Aug-07 03-Oct-07 100% 8% Behind
Level 3 05-Sep-07 17-Oct-07 100% 0% Behind
Level 4 19-Sep-07 31-Oct-07 100% 0% Behind
Level 5 03-Oct-07 14-Nov-07 100% 0% Behind
Level 6 17-Oct-07 28-Nov-07 100% 0% Behind
Level 7 31-Oct-07 12-Dec-07 100% 0% Behind
Level 8 14-Nov-07 26-Dec-07 100% 0% Behind
Level 9 28-Nov-07 09-Jan-08 100% 0% Behind
Level 10 12-Dec-07 23-Jan-08 100.00% 0% Behind
Level 11 26-Dec-07 06-Feb-08 54.89% 0% Behind
Level 12 07-Jan-08 18-Feb-08 26.32% 0% Behind
Level 13 21-Jan-08 03-Mar-08 6% 0% Behind
Level 14 04-Feb-08 17-Mar-08 0% 0% On Scedule
Level 15 18-Feb-08 31-Mar-08 0% 0% On Scedule
Month : 26 January 2008
Ceiling Performance
Progress Of Ceiling Works
Early Planned Dates Of Ceiling Works
Progress Status
Anantara Palm Jumeirah and Tiara Residences
Early Planned Progress Of Ceiling Works Actual Progress Of CeilingWorks
- 8. CLIENT: Zabeel Investement L.I.C
Planning Departement
Package No. : D0469
Early Planned Start Early Planned Finish
Tower H1
Basement 3 29-Jan-08 10-Mar-08 0% 0% On Scedule
Basement 2 17-Jan-08 27-Feb-08 4% 0% Behind
Basement 1 03-Jan-08 13-Feb-08 27.37% 0% Behind
Ground 20-Dec-07 30-Jan-08 85.39% 0% Behind
Mezzanine 06-Dec-07 16-Jan-08 100.00% 0% Behind
Level 1 23-Aug-07 03-Oct-07 100% 0% Behind
Level 2 06-Sep-07 17-Oct-07 100% 0% Behind
Level 3 20-Sep-07 31-Oct-07 100% 0% Behind
Level 4 04-Oct-07 14-Nov-07 100% 0% Behind
Level 5 18-Oct-07 28-Nov-07 100% 0% Behind
Level 6 01-Nov-07 12-Dec-07 100% 0% Behind
Level 7 13-Nov-07 24-Dec-07 100% 0% Behind
Level 8 25-Nov-07 05-Jan-08 100% 0% Behind
Level 9 06-Dec-07 16-Jan-08 100.00% 0% Behind
Level 10 20-Dec-07 30-Jan-08 86.03% 0% Behind
Level 11 03-Jan-08 13-Feb-08 26.82% 0% Behind
Level 12 17-Jan-08 27-Feb-08 4% 0% Behind
Level 13 31-Jan-08 12-Mar-08 0% 0% On Scedule
Level 14 14-Feb-08 26-Mar-08 0% 0% On Scedule
Level 15 26-Feb-08 07-Apr-08 0% 0% On Scedule
Early Planned Progress Of Ceiling Works Actual Progress Of CeilingWorks Progress Status
Month : 26 January 2008
Early Planned Dates Of Ceiling Works
Ceiling Performance
Progress Of Ceiling Works
Anantara Palm Jumeirah and Tiara Residences
- 9. CLIENT: Zabeel Investement L.I.C
Planning Departement
Package No. : D0469
Early Planned Start Early Planned Finish
Tower H2
Basement 3 28-Jan-08 09-Mar-08 0% 0% On Scedule
Basement 2 16-Jan-08 26-Feb-08 7% 0% Behind
Basement 1 05-Jan-08 14-Feb-08 25.14% 0% Behind
Ground 24-Dec-07 03-Feb-08 72.78% 0% Behind
Mezzanine 12-Dec-07 22-Jan-08 100.00% 0% Behind
Level 1 04-Sep-07 15-Oct-07 100% 0% Behind
Level 2 18-Sep-07 29-Oct-07 100% 0% Behind
Level 3 04-Oct-07 14-Nov-07 100% 0% Behind
Level 4 17-Oct-07 27-Nov-07 100% 0% Behind
Level 5 31-Oct-07 11-Dec-07 100% 0% Behind
Level 6 14-Nov-07 25-Dec-07 100% 0% Behind
Level 7 28-Nov-07 08-Jan-08 100% 0% Behind
Level 8 12-Dec-07 22-Jan-08 100.00% 0% Behind
Level 9 26-Dec-07 05-Feb-08 60.00% 0% Behind
Level 10 07-Jan-08 17-Feb-08 20.67% 0% Behind
Level 11 19-Jan-08 28-Feb-08 4% 0% Behind
Level 12 30-Jan-08 11-Mar-08 0% 0% On Scedule
Level 13 11-Feb-08 23-Mar-08 0% 0% On Scedule
Level 14 23-Feb-08 03-Apr-08 0% 0% On Scedule
Level 15 05-Mar-08 15-Apr-08 0% 0% On Scedule
Progress StatusEarly Planned Progress Of Ceiling Works Actual Progress Of CeilingWorks
Month : 26 January 2008
Ceiling Performance
Early Planned Dates Of Ceiling Works
Anantara Palm Jumeirah and Tiara Residences
Progress Of Ceiling Works