CLIENT: Zabeel InvestementCLIENT: Zabeel InvestementCLIENT: Zabeel InvestementCLIENT: Zabeel Investement
L.I.CL.I.CL.I.CL.I.C
Planning Departement
Package No. : D0469
Planned Preogress % Actual Progress % Variance % Ahead/Behind
External Facades 76.37% 37.80% -38.57% Behind
Residential Tower N4 84.55% 47.57% -37% Behind
Residential Tower N3 83.32% 50.22% -33% Behind
Residential Tower N2 67.42% 47.27% -20% Behind
Residential Tower N1 66.06% 43.17% -23% Behind
Residential Tower S3 79.67% 49.91% -30% Behind
Residential Tower S2 81.62% 52.10% -30% Behind
Residential Tower S1 80.68% 50.55% -30% Behind
Hotel Tower H1 74.38% 0.00% -74% Behind
Hotel Tower H2 69.39% 0.00% -69% Behind
Planned Progress % Actual Progress % Variance % Ahead/Behind
External Facades 76.37% 37.80% -38.57% Behind
Residentials 77.66% 48.68% -29% Behind
Hotel 71.88% 0.00% -72% Behind
Anantara Palm Jumeirah and Tiara Residences
Progress Of Facades Works Month : 26January2008
Type Of Work
Current Month (Up to 26January08)
Type Of Work
Current Month (Up to 26January08)

More Related Content

What's hot

Anchor Stand Schematic for CS Unitec Core Drills: BST 300 V
Anchor Stand Schematic for CS Unitec Core Drills: BST 300 VAnchor Stand Schematic for CS Unitec Core Drills: BST 300 V
Anchor Stand Schematic for CS Unitec Core Drills: BST 300 VCS Unitec
 
Istana Bandar Jugrah Sections
Istana Bandar Jugrah SectionsIstana Bandar Jugrah Sections
Istana Bandar Jugrah SectionsClaire Zhuangg
 
WDT December 2014 London Salary Guide
WDT December 2014 London Salary GuideWDT December 2014 London Salary Guide
WDT December 2014 London Salary GuideMartin Dendle
 
Tihomir Dovramadjiev PhD BLENDER TUTORIAL. CREATING DOOR HANDLE WITH USING 90...
Tihomir Dovramadjiev PhD BLENDER TUTORIAL. CREATING DOOR HANDLE WITH USING 90...Tihomir Dovramadjiev PhD BLENDER TUTORIAL. CREATING DOOR HANDLE WITH USING 90...
Tihomir Dovramadjiev PhD BLENDER TUTORIAL. CREATING DOOR HANDLE WITH USING 90...FIDE Master Tihomir Dovramadjiev PhD
 
WDT September 2015 London Salary Guide
WDT September 2015 London Salary GuideWDT September 2015 London Salary Guide
WDT September 2015 London Salary GuideMartin Dendle
 
WDT December 2015 London Salary Guide
WDT December 2015 London Salary GuideWDT December 2015 London Salary Guide
WDT December 2015 London Salary GuideMartin Dendle
 
Anchor Stand Schematic for CS Unitec Core Drills: BST 300 U
Anchor Stand Schematic for CS Unitec Core Drills: BST 300 UAnchor Stand Schematic for CS Unitec Core Drills: BST 300 U
Anchor Stand Schematic for CS Unitec Core Drills: BST 300 UCS Unitec
 

What's hot (7)

Anchor Stand Schematic for CS Unitec Core Drills: BST 300 V
Anchor Stand Schematic for CS Unitec Core Drills: BST 300 VAnchor Stand Schematic for CS Unitec Core Drills: BST 300 V
Anchor Stand Schematic for CS Unitec Core Drills: BST 300 V
 
Istana Bandar Jugrah Sections
Istana Bandar Jugrah SectionsIstana Bandar Jugrah Sections
Istana Bandar Jugrah Sections
 
WDT December 2014 London Salary Guide
WDT December 2014 London Salary GuideWDT December 2014 London Salary Guide
WDT December 2014 London Salary Guide
 
Tihomir Dovramadjiev PhD BLENDER TUTORIAL. CREATING DOOR HANDLE WITH USING 90...
Tihomir Dovramadjiev PhD BLENDER TUTORIAL. CREATING DOOR HANDLE WITH USING 90...Tihomir Dovramadjiev PhD BLENDER TUTORIAL. CREATING DOOR HANDLE WITH USING 90...
Tihomir Dovramadjiev PhD BLENDER TUTORIAL. CREATING DOOR HANDLE WITH USING 90...
 
WDT September 2015 London Salary Guide
WDT September 2015 London Salary GuideWDT September 2015 London Salary Guide
WDT September 2015 London Salary Guide
 
WDT December 2015 London Salary Guide
WDT December 2015 London Salary GuideWDT December 2015 London Salary Guide
WDT December 2015 London Salary Guide
 
Anchor Stand Schematic for CS Unitec Core Drills: BST 300 U
Anchor Stand Schematic for CS Unitec Core Drills: BST 300 UAnchor Stand Schematic for CS Unitec Core Drills: BST 300 U
Anchor Stand Schematic for CS Unitec Core Drills: BST 300 U
 

Viewers also liked (14)

Women's group5 2
Women's group5 2Women's group5 2
Women's group5 2
 
13. Overall S-Curve
13. Overall S-Curve13. Overall S-Curve
13. Overall S-Curve
 
Monthly Progress Report No.05 - June-2012
Monthly Progress Report No.05 - June-2012Monthly Progress Report No.05 - June-2012
Monthly Progress Report No.05 - June-2012
 
Overall Progress S-Curve For Ceiling
Overall Progress S-Curve For CeilingOverall Progress S-Curve For Ceiling
Overall Progress S-Curve For Ceiling
 
Resources Calculations for Bldg. A
Resources Calculations for Bldg. AResources Calculations for Bldg. A
Resources Calculations for Bldg. A
 
Method123 ebook
Method123 ebookMethod123 ebook
Method123 ebook
 
01. P269 - Project Implementation Programme - Rev 00
01. P269 - Project Implementation Programme -  Rev 0001. P269 - Project Implementation Programme -  Rev 00
01. P269 - Project Implementation Programme - Rev 00
 
Overall Progress S-Curve For Facades
Overall Progress S-Curve For FacadesOverall Progress S-Curve For Facades
Overall Progress S-Curve For Facades
 
Monthly Progress Report - September 2014
Monthly Progress Report - September 2014Monthly Progress Report - September 2014
Monthly Progress Report - September 2014
 
Contract 2 - Project Progress Status. Oct-13
Contract 2 - Project Progress Status. Oct-13Contract 2 - Project Progress Status. Oct-13
Contract 2 - Project Progress Status. Oct-13
 
Building-Structure Planning Model
Building-Structure Planning ModelBuilding-Structure Planning Model
Building-Structure Planning Model
 
Marijuana tourism
Marijuana tourismMarijuana tourism
Marijuana tourism
 
Monitoring Programme Review
Monitoring Programme ReviewMonitoring Programme Review
Monitoring Programme Review
 
Construction Monthly Progress Report - June 2011
Construction Monthly Progress Report - June 2011Construction Monthly Progress Report - June 2011
Construction Monthly Progress Report - June 2011
 

Similar to Zabeel Investement construction progress report

Similar to Zabeel Investement construction progress report (7)

Effective Contingency Management - Contractor Management Forum - PD July 2013
Effective Contingency Management - Contractor Management Forum - PD July 2013Effective Contingency Management - Contractor Management Forum - PD July 2013
Effective Contingency Management - Contractor Management Forum - PD July 2013
 
JTP - EV Presentation
JTP - EV PresentationJTP - EV Presentation
JTP - EV Presentation
 
Nigerian Oil & Gas Salary Survey 2015
Nigerian  Oil & Gas Salary Survey 2015Nigerian  Oil & Gas Salary Survey 2015
Nigerian Oil & Gas Salary Survey 2015
 
De assignment
De assignmentDe assignment
De assignment
 
Wind Power Project Appraisal.pptx
Wind Power Project Appraisal.pptxWind Power Project Appraisal.pptx
Wind Power Project Appraisal.pptx
 
eugene technology 084370 Algorithm Investment Report
eugene technology 084370 Algorithm Investment Reporteugene technology 084370 Algorithm Investment Report
eugene technology 084370 Algorithm Investment Report
 
HYUNDAI E&C 000720 Algorithm Investment Report
HYUNDAI E&C 000720 Algorithm Investment ReportHYUNDAI E&C 000720 Algorithm Investment Report
HYUNDAI E&C 000720 Algorithm Investment Report
 

More from Sam Kendall, MSc, BSc Civil Eng., PMP®, MIEAust

More from Sam Kendall, MSc, BSc Civil Eng., PMP®, MIEAust (20)

Kandil Mohammed Ibrahim_Sameh_Dissertation
Kandil Mohammed Ibrahim_Sameh_DissertationKandil Mohammed Ibrahim_Sameh_Dissertation
Kandil Mohammed Ibrahim_Sameh_Dissertation
 
Progress Of Ceiling Per Floors
Progress Of Ceiling Per FloorsProgress Of Ceiling Per Floors
Progress Of Ceiling Per Floors
 
N1
N1N1
N1
 
Progress Of Slab
Progress Of SlabProgress Of Slab
Progress Of Slab
 
Overall Progress S-Curve For Elevators
Overall Progress S-Curve For ElevatorsOverall Progress S-Curve For Elevators
Overall Progress S-Curve For Elevators
 
Overall Progres S-Curve For Concrete Works
Overall Progres S-Curve For Concrete WorksOverall Progres S-Curve For Concrete Works
Overall Progres S-Curve For Concrete Works
 
Window Analysis @ 30-June-2012
Window Analysis @ 30-June-2012Window Analysis @ 30-June-2012
Window Analysis @ 30-June-2012
 
10. Overall Implementation Programme
10. Overall Implementation Programme10. Overall Implementation Programme
10. Overall Implementation Programme
 
AWI20202 commercial
AWI20202 commercialAWI20202 commercial
AWI20202 commercial
 
Rihan Height Project Execution Plan-Rev00
Rihan Height Project Execution Plan-Rev00Rihan Height Project Execution Plan-Rev00
Rihan Height Project Execution Plan-Rev00
 
Monthly Progress Report No.13 - September 2011
Monthly Progress Report No.13 - September 2011Monthly Progress Report No.13 - September 2011
Monthly Progress Report No.13 - September 2011
 
Final Submission EOT 1
Final Submission EOT 1Final Submission EOT 1
Final Submission EOT 1
 
Cash Flow Portfolio
Cash Flow PortfolioCash Flow Portfolio
Cash Flow Portfolio
 
Resources Histograms
Resources HistogramsResources Histograms
Resources Histograms
 
Kandil_Sameh_AR50123
Kandil_Sameh_AR50123Kandil_Sameh_AR50123
Kandil_Sameh_AR50123
 
Kandil_Sameh_CPMPart 3 _b
Kandil_Sameh_CPMPart 3 _bKandil_Sameh_CPMPart 3 _b
Kandil_Sameh_CPMPart 3 _b
 
Kandil_Sameh_CPMPart 5 _b
Kandil_Sameh_CPMPart 5 _bKandil_Sameh_CPMPart 5 _b
Kandil_Sameh_CPMPart 5 _b
 
Kandil_Sameh_CPMPart 4 _b
Kandil_Sameh_CPMPart 4 _bKandil_Sameh_CPMPart 4 _b
Kandil_Sameh_CPMPart 4 _b
 
Kandil_Sameh_CPMPart 1 _b
Kandil_Sameh_CPMPart 1 _bKandil_Sameh_CPMPart 1 _b
Kandil_Sameh_CPMPart 1 _b
 
Kandil_Sameh_AR50411_Part 1 to 5
Kandil_Sameh_AR50411_Part 1 to 5Kandil_Sameh_AR50411_Part 1 to 5
Kandil_Sameh_AR50411_Part 1 to 5
 

Zabeel Investement construction progress report

  • 1. CLIENT: Zabeel InvestementCLIENT: Zabeel InvestementCLIENT: Zabeel InvestementCLIENT: Zabeel Investement L.I.CL.I.CL.I.CL.I.C Planning Departement Package No. : D0469 Planned Preogress % Actual Progress % Variance % Ahead/Behind External Facades 76.37% 37.80% -38.57% Behind Residential Tower N4 84.55% 47.57% -37% Behind Residential Tower N3 83.32% 50.22% -33% Behind Residential Tower N2 67.42% 47.27% -20% Behind Residential Tower N1 66.06% 43.17% -23% Behind Residential Tower S3 79.67% 49.91% -30% Behind Residential Tower S2 81.62% 52.10% -30% Behind Residential Tower S1 80.68% 50.55% -30% Behind Hotel Tower H1 74.38% 0.00% -74% Behind Hotel Tower H2 69.39% 0.00% -69% Behind Planned Progress % Actual Progress % Variance % Ahead/Behind External Facades 76.37% 37.80% -38.57% Behind Residentials 77.66% 48.68% -29% Behind Hotel 71.88% 0.00% -72% Behind Anantara Palm Jumeirah and Tiara Residences Progress Of Facades Works Month : 26January2008 Type Of Work Current Month (Up to 26January08) Type Of Work Current Month (Up to 26January08)