The document outlines the planned and actual progress of facade works for Tower N1 of the Anantara Palm Jumeirah and Tiara Residences project. It provides start and finish dates for each level, from the basement to level 15, for four construction phases (1st fix, 2nd fix, 3rd fix, 4th fix). Performance is reported as ahead, on schedule, or behind for each level and phase. Some levels were up to 100% behind schedule on certain phases.