SlideShare a Scribd company logo
1 of 1
Download to read offline
Basement 1 27-Feb-08 03-Mar-08 03-Mar-08 09-Mar-08 09-Mar-08 15-Mar-08 15-Mar-08 18-Mar-08 0% 0% On Schedule 0% 0% On Schedule 0% 0% On Schedule 0% 0% On Schedule
Ground 03-Mar-08 09-Mar-08 27-Feb-08 04-Mar-08 04-Mar-08 10-Mar-08 10-Mar-08 13-Mar-08 0% 52.98% Ahead 0% 48.02% Ahead 0% 25.58% Ahead 0% 0.00% On Schedule
Level 1 09-Mar-08 15-Mar-08 12-Sep-07 17-Sep-07 18-Sep-07 23-Sep-07 24-Sep-07 27-Sep-07 100% 100% On Schedule 100% 88% Behind 100% 74% Behind 100% 0% Behind
Level 2 15-Mar-08 18-Mar-08 29-Sep-07 04-Oct-07 04-Oct-07 09-Oct-07 10-Oct-07 14-Oct-07 100% 100% On Schedule 100% 88% Behind 100% 74% Behind 100% 0% Behind
Level 3 06-Oct-07 10-Oct-07 10-Oct-07 16-Oct-07 16-Oct-07 21-Oct-07 22-Oct-07 25-Oct-07 100% 100% On Schedule 100% 88% Behind 100% 74% Behind 100% 0% Behind
Level 4 17-Oct-07 22-Oct-07 22-Oct-07 28-Oct-07 28-Oct-07 01-Nov-07 03-Nov-07 06-Nov-07 100% 100% On Schedule 100% 88% Behind 100% 79% Behind 100% 0% Behind
Level 5 29-Oct-07 03-Nov-07 03-Nov-07 08-Nov-07 08-Nov-07 13-Nov-07 14-Nov-07 18-Nov-07 100% 100% On Schedule 100% 88% Behind 100% 79% Behind 100% 0% Behind
Level 6 10-Nov-07 14-Nov-07 14-Nov-07 20-Nov-07 20-Nov-07 25-Nov-07 26-Nov-07 29-Nov-07 100% 100% On Schedule 100% 84% Behind 100% 63% Behind 100% 0% Behind
Level 7 21-Nov-07 26-Nov-07 26-Nov-07 02-Dec-07 02-Dec-07 06-Dec-07 08-Dec-07 11-Dec-07 100% 100% On Schedule 100% 84% Behind 100% 61% Behind 100% 0% Behind
Level 8 03-Dec-07 08-Dec-07 08-Dec-07 13-Dec-07 13-Dec-07 18-Dec-07 19-Dec-07 23-Dec-07 100% 82.50% Behind 100% 82.50% Behind 100% 54.99% Behind 100% 0.00% Behind
Level 9 15-Dec-07 19-Dec-07 19-Dec-07 25-Dec-07 25-Dec-07 30-Dec-07 31-Dec-07 03-Jan-08 100% 82.49% Behind 100% 82.50% Behind 100% 53.99% Behind 100% 0.00% Behind
Level 10 26-Dec-07 31-Dec-07 31-Dec-07 06-Jan-08 06-Jan-08 10-Jan-08 12-Jan-08 15-Jan-08 100% 73.02% Behind 100% 63.00% Behind 100% 38.99% Behind 100% 0.00% Behind
Level 11 07-Jan-08 12-Jan-08 12-Jan-08 17-Jan-08 17-Jan-08 22-Jan-08 23-Jan-08 27-Jan-08 100% 62.98% Behind 100% 63.00% Behind 100% 22.02% Behind 57% 0.00% Behind
Level 12 19-Jan-08 23-Jan-08 23-Jan-08 29-Jan-08 29-Jan-08 03-Feb-08 04-Feb-08 07-Feb-08 100% 63.01% Behind 35% 63.01% Ahead 0% 17.98% Ahead 0% 0.00% On Schedule
Level 13 29-Jan-08 03-Feb-08 03-Feb-08 09-Feb-08 09-Feb-08 13-Feb-08 14-Feb-08 18-Feb-08 0% 0% On Schedule 0% 0% On Schedule 0% 0% On Schedule 0% 0% On Schedule
Level 14 09-Feb-08 13-Feb-08 13-Feb-08 19-Feb-08 19-Feb-08 24-Feb-08 25-Feb-08 28-Feb-08 0% 0% On Schedule 0% 0% On Schedule 0% 0% On Schedule 0% 0% On Schedule
Level 15 19-Feb-08 24-Feb-08 24-Feb-08 01-Mar-08 01-Mar-08 05-Mar-08 06-Mar-08 10-Mar-08 0% 0% On Schedule 0% 0% On Schedule 0% 0% On Schedule 0% 0% On Schedule
CLIENT: ZabeelCLIENT: ZabeelCLIENT: ZabeelCLIENT: Zabeel
Investement L.I.CInvestement L.I.CInvestement L.I.CInvestement L.I.C
Month
:26January2008
Anantara Palm Jumeirah and Tiara Residences
Progress Of Facades Works For Tower N1
Performace Of 3rd Fix
Ahead/
Behind
Performace Of 4th Fix
Planned
Progress Of
Facades Works
Actual Progress
Of facades
Works
Ahead/
Behind
Ahead/
Behind
Planned
Progress Of
Facades Works
Actual Progress
Of facades
Works
Planned
Progress Of
Facades Works
Actual Progress
Of facades
Works
Planned
Progress Of
Facades Works
Actual Progress
Of facades
Works
Planning Departement
Package No. : D0469
Planned FinishPlanned StartPlanned FinishPlanned Start Planned FinishPlanned StartPlanned Finish
Planned Dates Of 1st Fix Planned Dates Of 2nd Fix Planned Dates Of 3rd Fix Planned Dates Of 4th Fix
Planned Start
Ahead/
Behind
Performace Of 1st Fix Performace Of 2nd Fix

More Related Content

Viewers also liked (12)

Monthly Progress Report No.13 - September 2011
Monthly Progress Report No.13 - September 2011Monthly Progress Report No.13 - September 2011
Monthly Progress Report No.13 - September 2011
 
WO5A CS1A Construction Progress Status Report Week #25
WO5A CS1A Construction Progress Status Report Week #25WO5A CS1A Construction Progress Status Report Week #25
WO5A CS1A Construction Progress Status Report Week #25
 
Summary Progress Of Concrete Works
Summary Progress Of Concrete WorksSummary Progress Of Concrete Works
Summary Progress Of Concrete Works
 
Final Submission EOT 1
Final Submission EOT 1Final Submission EOT 1
Final Submission EOT 1
 
Project Progress Report
Project Progress ReportProject Progress Report
Project Progress Report
 
GRP Monthly Report February 2012
GRP Monthly Report February 2012GRP Monthly Report February 2012
GRP Monthly Report February 2012
 
Progress Report
Progress Report Progress Report
Progress Report
 
Dr. amjad bangash bechtel
Dr. amjad bangash   bechtelDr. amjad bangash   bechtel
Dr. amjad bangash bechtel
 
Saudi Railway Company Presentation - Railways Projects 2014
Saudi Railway Company Presentation - Railways Projects 2014Saudi Railway Company Presentation - Railways Projects 2014
Saudi Railway Company Presentation - Railways Projects 2014
 
Riyadh metro project presentation 06052015 Final
Riyadh metro project presentation 06052015 FinalRiyadh metro project presentation 06052015 Final
Riyadh metro project presentation 06052015 Final
 
Riyadh Metro Presentation ADA
Riyadh Metro Presentation ADARiyadh Metro Presentation ADA
Riyadh Metro Presentation ADA
 
Progress report
Progress reportProgress report
Progress report
 

Similar to N1 (10)

Progress Of Ceiling Per Floors
Progress Of Ceiling Per FloorsProgress Of Ceiling Per Floors
Progress Of Ceiling Per Floors
 
Progress Of Slab
Progress Of SlabProgress Of Slab
Progress Of Slab
 
Historical Trail of Repo Rate, Reverse Repo, WPI and CPI
Historical Trail of Repo Rate, Reverse Repo, WPI and CPIHistorical Trail of Repo Rate, Reverse Repo, WPI and CPI
Historical Trail of Repo Rate, Reverse Repo, WPI and CPI
 
Book2.pdf
Book2.pdfBook2.pdf
Book2.pdf
 
Book2.pdf
Book2.pdfBook2.pdf
Book2.pdf
 
Book2.pdf
Book2.pdfBook2.pdf
Book2.pdf
 
Book2.pdf
Book2.pdfBook2.pdf
Book2.pdf
 
SEO Reports
SEO ReportsSEO Reports
SEO Reports
 
Clase tambo
Clase tamboClase tambo
Clase tambo
 
Mortgage Brokers Association Data
Mortgage Brokers Association DataMortgage Brokers Association Data
Mortgage Brokers Association Data
 

More from Sam Kendall, MSc, BSc Civil Eng., PMP®, MIEAust

More from Sam Kendall, MSc, BSc Civil Eng., PMP®, MIEAust (20)

Kandil Mohammed Ibrahim_Sameh_Dissertation
Kandil Mohammed Ibrahim_Sameh_DissertationKandil Mohammed Ibrahim_Sameh_Dissertation
Kandil Mohammed Ibrahim_Sameh_Dissertation
 
Summary Progress Of Facade Works
Summary Progress Of Facade WorksSummary Progress Of Facade Works
Summary Progress Of Facade Works
 
Overall Progress S-Curve For Ceiling
Overall Progress S-Curve For CeilingOverall Progress S-Curve For Ceiling
Overall Progress S-Curve For Ceiling
 
Overall Progress S-Curve For Facades
Overall Progress S-Curve For FacadesOverall Progress S-Curve For Facades
Overall Progress S-Curve For Facades
 
Overall Progress S-Curve For Elevators
Overall Progress S-Curve For ElevatorsOverall Progress S-Curve For Elevators
Overall Progress S-Curve For Elevators
 
Overall Progres S-Curve For Concrete Works
Overall Progres S-Curve For Concrete WorksOverall Progres S-Curve For Concrete Works
Overall Progres S-Curve For Concrete Works
 
Window Analysis @ 30-June-2012
Window Analysis @ 30-June-2012Window Analysis @ 30-June-2012
Window Analysis @ 30-June-2012
 
01. P269 - Project Implementation Programme - Rev 00
01. P269 - Project Implementation Programme -  Rev 0001. P269 - Project Implementation Programme -  Rev 00
01. P269 - Project Implementation Programme - Rev 00
 
13. Overall S-Curve
13. Overall S-Curve13. Overall S-Curve
13. Overall S-Curve
 
10. Overall Implementation Programme
10. Overall Implementation Programme10. Overall Implementation Programme
10. Overall Implementation Programme
 
Building-Structure Planning Model
Building-Structure Planning ModelBuilding-Structure Planning Model
Building-Structure Planning Model
 
AWI20202 commercial
AWI20202 commercialAWI20202 commercial
AWI20202 commercial
 
Rihan Height Project Execution Plan-Rev00
Rihan Height Project Execution Plan-Rev00Rihan Height Project Execution Plan-Rev00
Rihan Height Project Execution Plan-Rev00
 
Cash Flow Portfolio
Cash Flow PortfolioCash Flow Portfolio
Cash Flow Portfolio
 
Resources Histograms
Resources HistogramsResources Histograms
Resources Histograms
 
Resources Calculations for Bldg. A
Resources Calculations for Bldg. AResources Calculations for Bldg. A
Resources Calculations for Bldg. A
 
Monthly Progress Report No.05 - June-2012
Monthly Progress Report No.05 - June-2012Monthly Progress Report No.05 - June-2012
Monthly Progress Report No.05 - June-2012
 
Contract 2 - Project Progress Status. Oct-13
Contract 2 - Project Progress Status. Oct-13Contract 2 - Project Progress Status. Oct-13
Contract 2 - Project Progress Status. Oct-13
 
Kandil_Sameh_CPMPart 3 _b
Kandil_Sameh_CPMPart 3 _bKandil_Sameh_CPMPart 3 _b
Kandil_Sameh_CPMPart 3 _b
 
Kandil_Sameh_CPMPart 5 _b
Kandil_Sameh_CPMPart 5 _bKandil_Sameh_CPMPart 5 _b
Kandil_Sameh_CPMPart 5 _b
 

N1

  • 1. Basement 1 27-Feb-08 03-Mar-08 03-Mar-08 09-Mar-08 09-Mar-08 15-Mar-08 15-Mar-08 18-Mar-08 0% 0% On Schedule 0% 0% On Schedule 0% 0% On Schedule 0% 0% On Schedule Ground 03-Mar-08 09-Mar-08 27-Feb-08 04-Mar-08 04-Mar-08 10-Mar-08 10-Mar-08 13-Mar-08 0% 52.98% Ahead 0% 48.02% Ahead 0% 25.58% Ahead 0% 0.00% On Schedule Level 1 09-Mar-08 15-Mar-08 12-Sep-07 17-Sep-07 18-Sep-07 23-Sep-07 24-Sep-07 27-Sep-07 100% 100% On Schedule 100% 88% Behind 100% 74% Behind 100% 0% Behind Level 2 15-Mar-08 18-Mar-08 29-Sep-07 04-Oct-07 04-Oct-07 09-Oct-07 10-Oct-07 14-Oct-07 100% 100% On Schedule 100% 88% Behind 100% 74% Behind 100% 0% Behind Level 3 06-Oct-07 10-Oct-07 10-Oct-07 16-Oct-07 16-Oct-07 21-Oct-07 22-Oct-07 25-Oct-07 100% 100% On Schedule 100% 88% Behind 100% 74% Behind 100% 0% Behind Level 4 17-Oct-07 22-Oct-07 22-Oct-07 28-Oct-07 28-Oct-07 01-Nov-07 03-Nov-07 06-Nov-07 100% 100% On Schedule 100% 88% Behind 100% 79% Behind 100% 0% Behind Level 5 29-Oct-07 03-Nov-07 03-Nov-07 08-Nov-07 08-Nov-07 13-Nov-07 14-Nov-07 18-Nov-07 100% 100% On Schedule 100% 88% Behind 100% 79% Behind 100% 0% Behind Level 6 10-Nov-07 14-Nov-07 14-Nov-07 20-Nov-07 20-Nov-07 25-Nov-07 26-Nov-07 29-Nov-07 100% 100% On Schedule 100% 84% Behind 100% 63% Behind 100% 0% Behind Level 7 21-Nov-07 26-Nov-07 26-Nov-07 02-Dec-07 02-Dec-07 06-Dec-07 08-Dec-07 11-Dec-07 100% 100% On Schedule 100% 84% Behind 100% 61% Behind 100% 0% Behind Level 8 03-Dec-07 08-Dec-07 08-Dec-07 13-Dec-07 13-Dec-07 18-Dec-07 19-Dec-07 23-Dec-07 100% 82.50% Behind 100% 82.50% Behind 100% 54.99% Behind 100% 0.00% Behind Level 9 15-Dec-07 19-Dec-07 19-Dec-07 25-Dec-07 25-Dec-07 30-Dec-07 31-Dec-07 03-Jan-08 100% 82.49% Behind 100% 82.50% Behind 100% 53.99% Behind 100% 0.00% Behind Level 10 26-Dec-07 31-Dec-07 31-Dec-07 06-Jan-08 06-Jan-08 10-Jan-08 12-Jan-08 15-Jan-08 100% 73.02% Behind 100% 63.00% Behind 100% 38.99% Behind 100% 0.00% Behind Level 11 07-Jan-08 12-Jan-08 12-Jan-08 17-Jan-08 17-Jan-08 22-Jan-08 23-Jan-08 27-Jan-08 100% 62.98% Behind 100% 63.00% Behind 100% 22.02% Behind 57% 0.00% Behind Level 12 19-Jan-08 23-Jan-08 23-Jan-08 29-Jan-08 29-Jan-08 03-Feb-08 04-Feb-08 07-Feb-08 100% 63.01% Behind 35% 63.01% Ahead 0% 17.98% Ahead 0% 0.00% On Schedule Level 13 29-Jan-08 03-Feb-08 03-Feb-08 09-Feb-08 09-Feb-08 13-Feb-08 14-Feb-08 18-Feb-08 0% 0% On Schedule 0% 0% On Schedule 0% 0% On Schedule 0% 0% On Schedule Level 14 09-Feb-08 13-Feb-08 13-Feb-08 19-Feb-08 19-Feb-08 24-Feb-08 25-Feb-08 28-Feb-08 0% 0% On Schedule 0% 0% On Schedule 0% 0% On Schedule 0% 0% On Schedule Level 15 19-Feb-08 24-Feb-08 24-Feb-08 01-Mar-08 01-Mar-08 05-Mar-08 06-Mar-08 10-Mar-08 0% 0% On Schedule 0% 0% On Schedule 0% 0% On Schedule 0% 0% On Schedule CLIENT: ZabeelCLIENT: ZabeelCLIENT: ZabeelCLIENT: Zabeel Investement L.I.CInvestement L.I.CInvestement L.I.CInvestement L.I.C Month :26January2008 Anantara Palm Jumeirah and Tiara Residences Progress Of Facades Works For Tower N1 Performace Of 3rd Fix Ahead/ Behind Performace Of 4th Fix Planned Progress Of Facades Works Actual Progress Of facades Works Ahead/ Behind Ahead/ Behind Planned Progress Of Facades Works Actual Progress Of facades Works Planned Progress Of Facades Works Actual Progress Of facades Works Planned Progress Of Facades Works Actual Progress Of facades Works Planning Departement Package No. : D0469 Planned FinishPlanned StartPlanned FinishPlanned Start Planned FinishPlanned StartPlanned Finish Planned Dates Of 1st Fix Planned Dates Of 2nd Fix Planned Dates Of 3rd Fix Planned Dates Of 4th Fix Planned Start Ahead/ Behind Performace Of 1st Fix Performace Of 2nd Fix