CONTRACT CONDITIONS - II:
VARIATIONS/DEVIATIONS
Dr K M Soni, ADG(Retd.), CPWD,
New Delhi
Variations/Deviations
• Variations or Deviations are the changes from
the scope of work of a contract resulting during
execution of work except duration of the
contract.
• Mostly, Variations or Deviations are considered
the changes from the quantities or items of the
bill of quantities (Schedule of quantities) of a
contract resulting during execution of work as
changes in design, quantity or conditions
ultimately lead to affect BOQ/SOQ.
Variations/Deviations
• Variation/Deviation in quantities of items
• Extra items
• Substituted items
Deviation in Quantities
• These are the deviations or variations from
the quantities taken in Bill of Quantities or
Schedule of Quantities
• These are the items for which rates are
available in the contract
• The deviations/variations may be +ve or –ve
i.e. Quantities may increase or decrease from
the quantities available in BOQ/SOQ
Reasons of Deviations in Quantities
• Wrong assessment or mistake during preparation of detailed
estimate/BOQ/tender documents
• Assessment of quantities without availability of
architectural, structural or MEP drawings.
• Revision of drawings/design
• Revision due to local bye laws or local body agencies
• Revision due to non availability of materials at a particular
time
• Revisions due to client, architect, or engineer and contractor
Rates of Deviations in Quantities
• Rates of such items are available in the contract
• Deviations are +ve or –ve
• Rates can be based on;
• Available in contract for all deviations
• Rates available in the contract upto additional quantities
as mentioned in the contract (deviation limit, described in
percentage) and beyond it, market rates, Schedule rates
+/- quoted percentage, Schedule rates or cost plus basis or
any other method as mentioned in the contract or agreed
upon by the parties.
Extra or Additional items
• Items that are completely new and in addition
to the items contained in the contract
• These are the items other than those available
in BOQ and not covered in the conditions of
contract
• In some contracts, these are the items which are
not available in contract and not taken up in
substitution of items available in BOQ
Reasons of Extra/Additional items
• Left or mistake during preparation of detailed estimate/BOQ/tender
documents
• Specifications not available during preparation of detailed estimate/BOQ
• Non availability of architectural, structural or MEP drawings during
preparation of detailed estimate/tender document
• Revision of drawings/design
• Revision due to local bye laws or local body agencies
• Revision due to non availability of materials at a particular time
• Items not anticipated during preparation of tender documents i.e.
Contingent items
• Revisions due to client, architect, or engineer and contractor
Rates of Extra or Additional Items
• Market rates
• Schedule rates +/- quoted percentage
• Schedule rates
• Cost plus basis or
• Any other method as mentioned in the
contract or agreed upon by the parties.
Substituted item
• Items taken up as partial substitution or in
lieu of items of work available in the contract
• Therefore, the items are basically due to
change of specifications during execution
from those considered during preparation of
detailed estimate/BOQ/tender documents
Reasons of Substituted items
• Specifications/drawings not available during preparation of
detailed estimate/BOQ i.e. Non availability of architectural,
structural or MEP drawings
• Revision of drawings/design/specifications
• Revision due to local bye laws or local body agencies
• Revision due to non availability of materials or non
feasibility of the execution of the item at a particular time
• Revisions due to client, architect, or engineer and contractor
Rates of Substituted Items
• Agreement rates increased or decreased by the
difference in market rates of item substituted
compared to market rates of agreement item
• Market rates
• Schedule rates +/- quoted percentage
• Schedule rates
• Cost plus basis or
• Any other method as mentioned in the contract
or agreed upon by the parties.
Implications of Variations/ Deviations
• Extension of time
• Possible justification of regularisation of delay caused
by the contractor
• Chances of non compatibility of such items with
respect to other services
• Source of Disputes about the rates, time extension,
loss of profit, idle establishment and thus arbitration
• Delayed decisions
• Non approval of items and rates of variations
• Time overrun and cost overrun
Thanks for attending
Dr K M Soni, ADG (Retd.), CPWD, New Delhi
Also available on Youtube: KRISHNA MURARI Soni at
https://www.youtube.com/channel/UC_pPYxk0jI1ayqA5rO6fBOw

More Related Content

What's hot

Tendering Bidding & Award of Contract Final Draft
Tendering Bidding & Award of Contract Final DraftTendering Bidding & Award of Contract Final Draft
Tendering Bidding & Award of Contract Final DraftMuneesh Methwani
 
Contract & Tender Management
Contract & Tender ManagementContract & Tender Management
Contract & Tender ManagementAnand Subramaniam
 
Construction Claims Explained
Construction Claims ExplainedConstruction Claims Explained
Construction Claims Explainedclaimsconsultancy
 
Tenders and procedure of tendering
Tenders and procedure of tenderingTenders and procedure of tendering
Tenders and procedure of tenderingvvsasane
 
Clause 4.2 Performance Security-Understanding Clauses in FIDIC ‘Conditions of...
Clause 4.2 Performance Security-Understanding Clauses in FIDIC ‘Conditions of...Clause 4.2 Performance Security-Understanding Clauses in FIDIC ‘Conditions of...
Clause 4.2 Performance Security-Understanding Clauses in FIDIC ‘Conditions of...Divyanshu Dayal
 
Lecture 4 - selection of contract forms
Lecture 4 - selection of contract formsLecture 4 - selection of contract forms
Lecture 4 - selection of contract formskohwenqi
 
Time management in fidic red book 2017(prmg080 project)
Time management in fidic red book 2017(prmg080 project)Time management in fidic red book 2017(prmg080 project)
Time management in fidic red book 2017(prmg080 project)mohamed Ismail
 
Fidic conditions of contract presentation
Fidic conditions of contract presentationFidic conditions of contract presentation
Fidic conditions of contract presentationJeff B
 
Construction Contracts: Basics of Contracts and Contract Administration
Construction Contracts:  Basics of Contracts and Contract AdministrationConstruction Contracts:  Basics of Contracts and Contract Administration
Construction Contracts: Basics of Contracts and Contract AdministrationGerald R. (Jerry) Genge
 
CONTRACT ADMINISTRATION- Presentation dated 22.11.16
CONTRACT ADMINISTRATION- Presentation dated 22.11.16CONTRACT ADMINISTRATION- Presentation dated 22.11.16
CONTRACT ADMINISTRATION- Presentation dated 22.11.16Arvind Solanki
 
Training fidic moustafa ismail 2017 _ lec 4
Training fidic moustafa ismail  2017 _  lec 4Training fidic moustafa ismail  2017 _  lec 4
Training fidic moustafa ismail 2017 _ lec 4Moustafa Ismail Abu Dief
 
Construction contract
Construction contract Construction contract
Construction contract Rakshith Reddy
 
Fidic yellow vs silver
Fidic yellow vs silverFidic yellow vs silver
Fidic yellow vs silverWeero Koster
 
Construction claims, disputes and project closure
Construction claims, disputes and project closureConstruction claims, disputes and project closure
Construction claims, disputes and project closuresrinivas2036
 

What's hot (20)

Tendering Bidding & Award of Contract Final Draft
Tendering Bidding & Award of Contract Final DraftTendering Bidding & Award of Contract Final Draft
Tendering Bidding & Award of Contract Final Draft
 
Contract & Tender Management
Contract & Tender ManagementContract & Tender Management
Contract & Tender Management
 
Construction Claims Explained
Construction Claims ExplainedConstruction Claims Explained
Construction Claims Explained
 
Fidic
FidicFidic
Fidic
 
Tenders and procedure of tendering
Tenders and procedure of tenderingTenders and procedure of tendering
Tenders and procedure of tendering
 
TENDER DOCUMENT
TENDER DOCUMENTTENDER DOCUMENT
TENDER DOCUMENT
 
Clause 4.2 Performance Security-Understanding Clauses in FIDIC ‘Conditions of...
Clause 4.2 Performance Security-Understanding Clauses in FIDIC ‘Conditions of...Clause 4.2 Performance Security-Understanding Clauses in FIDIC ‘Conditions of...
Clause 4.2 Performance Security-Understanding Clauses in FIDIC ‘Conditions of...
 
Lecture 4 - selection of contract forms
Lecture 4 - selection of contract formsLecture 4 - selection of contract forms
Lecture 4 - selection of contract forms
 
Time management in fidic red book 2017(prmg080 project)
Time management in fidic red book 2017(prmg080 project)Time management in fidic red book 2017(prmg080 project)
Time management in fidic red book 2017(prmg080 project)
 
Fidic conditions of contract presentation
Fidic conditions of contract presentationFidic conditions of contract presentation
Fidic conditions of contract presentation
 
Gcc vs scc
Gcc vs sccGcc vs scc
Gcc vs scc
 
Construction Claims
Construction ClaimsConstruction Claims
Construction Claims
 
Construction Contracts: Basics of Contracts and Contract Administration
Construction Contracts:  Basics of Contracts and Contract AdministrationConstruction Contracts:  Basics of Contracts and Contract Administration
Construction Contracts: Basics of Contracts and Contract Administration
 
Lump Sum Contract
Lump Sum ContractLump Sum Contract
Lump Sum Contract
 
CONTRACT ADMINISTRATION- Presentation dated 22.11.16
CONTRACT ADMINISTRATION- Presentation dated 22.11.16CONTRACT ADMINISTRATION- Presentation dated 22.11.16
CONTRACT ADMINISTRATION- Presentation dated 22.11.16
 
Training fidic moustafa ismail 2017 _ lec 4
Training fidic moustafa ismail  2017 _  lec 4Training fidic moustafa ismail  2017 _  lec 4
Training fidic moustafa ismail 2017 _ lec 4
 
Construction contract
Construction contract Construction contract
Construction contract
 
Contracts
ContractsContracts
Contracts
 
Fidic yellow vs silver
Fidic yellow vs silverFidic yellow vs silver
Fidic yellow vs silver
 
Construction claims, disputes and project closure
Construction claims, disputes and project closureConstruction claims, disputes and project closure
Construction claims, disputes and project closure
 

Similar to Variations in works contracts

CONTRACT ADMINISTRATION Updated.pptx
CONTRACT ADMINISTRATION Updated.pptxCONTRACT ADMINISTRATION Updated.pptx
CONTRACT ADMINISTRATION Updated.pptxAditya Mane
 
Classification of contracts
Classification of contractsClassification of contracts
Classification of contractsAnil Kumar(6)
 
Extensions of Time - Contract Management
Extensions of Time - Contract ManagementExtensions of Time - Contract Management
Extensions of Time - Contract Managementbrainquisitive
 
Legal issues associated with project management and consulting
Legal issues associated with project management and consultingLegal issues associated with project management and consulting
Legal issues associated with project management and consultingThis account is closed
 
Common Interest Repair Issues
Common Interest Repair IssuesCommon Interest Repair Issues
Common Interest Repair IssuesTRIslides
 
Measure And Pay Contract
Measure And Pay Contract Measure And Pay Contract
Measure And Pay Contract Venuri Lakshani
 
Bid Evaluation
Bid EvaluationBid Evaluation
Bid EvaluationVj NiroSh
 
Procurement Strategies: A Seminar
Procurement Strategies: A SeminarProcurement Strategies: A Seminar
Procurement Strategies: A SeminarPang Khai Shuen
 
Key Components of Cost Estimation in construction
Key Components of Cost Estimation in constructionKey Components of Cost Estimation in construction
Key Components of Cost Estimation in constructionWaleed Liaqat
 
Professional practice-1-presentation
Professional practice-1-presentationProfessional practice-1-presentation
Professional practice-1-presentationTimun Loh
 
Turnkey implementation of distribution projects
Turnkey implementation of distribution projectsTurnkey implementation of distribution projects
Turnkey implementation of distribution projectsD.Pawan Kumar
 
Construction Documents
Construction DocumentsConstruction Documents
Construction DocumentsAllan Berry
 
Change management and dispute resolution
Change management and dispute resolutionChange management and dispute resolution
Change management and dispute resolutionAlex Iskandar
 
CCDC2 - A Focus on 3 Topics Using Case Studies
CCDC2 - A Focus on 3 Topics Using Case StudiesCCDC2 - A Focus on 3 Topics Using Case Studies
CCDC2 - A Focus on 3 Topics Using Case StudiesSamantha Ip
 
Contract Conditions
Contract ConditionsContract Conditions
Contract ConditionsDr K M SONI
 

Similar to Variations in works contracts (20)

CONTRACT ADMINISTRATION Updated.pptx
CONTRACT ADMINISTRATION Updated.pptxCONTRACT ADMINISTRATION Updated.pptx
CONTRACT ADMINISTRATION Updated.pptx
 
Classification of contracts
Classification of contractsClassification of contracts
Classification of contracts
 
Extensions of Time - Contract Management
Extensions of Time - Contract ManagementExtensions of Time - Contract Management
Extensions of Time - Contract Management
 
Common Interest Repair Issues
Common Interest Repair IssuesCommon Interest Repair Issues
Common Interest Repair Issues
 
Legal issues associated with project management and consulting
Legal issues associated with project management and consultingLegal issues associated with project management and consulting
Legal issues associated with project management and consulting
 
Common Interest Repair Issues
Common Interest Repair IssuesCommon Interest Repair Issues
Common Interest Repair Issues
 
Measure And Pay Contract
Measure And Pay Contract Measure And Pay Contract
Measure And Pay Contract
 
Bid Evaluation
Bid EvaluationBid Evaluation
Bid Evaluation
 
TOPIC7.pdf
TOPIC7.pdfTOPIC7.pdf
TOPIC7.pdf
 
Procurement Strategies: A Seminar
Procurement Strategies: A SeminarProcurement Strategies: A Seminar
Procurement Strategies: A Seminar
 
Key Components of Cost Estimation in construction
Key Components of Cost Estimation in constructionKey Components of Cost Estimation in construction
Key Components of Cost Estimation in construction
 
Professional practice-1-presentation
Professional practice-1-presentationProfessional practice-1-presentation
Professional practice-1-presentation
 
Turnkey implementation of distribution projects
Turnkey implementation of distribution projectsTurnkey implementation of distribution projects
Turnkey implementation of distribution projects
 
Construction Documents
Construction DocumentsConstruction Documents
Construction Documents
 
Preparation of boq
Preparation of boqPreparation of boq
Preparation of boq
 
Change management and dispute resolution
Change management and dispute resolutionChange management and dispute resolution
Change management and dispute resolution
 
CCDC2 - A Focus on 3 Topics Using Case Studies
CCDC2 - A Focus on 3 Topics Using Case StudiesCCDC2 - A Focus on 3 Topics Using Case Studies
CCDC2 - A Focus on 3 Topics Using Case Studies
 
Contract Conditions
Contract ConditionsContract Conditions
Contract Conditions
 
ACH 216 Lecture 04b (Bidding) Part 1
ACH 216 Lecture 04b (Bidding) Part 1ACH 216 Lecture 04b (Bidding) Part 1
ACH 216 Lecture 04b (Bidding) Part 1
 
Chapter 5- Contract Management
Chapter 5- Contract ManagementChapter 5- Contract Management
Chapter 5- Contract Management
 

More from Dr K M SONI

Heritage Conservation
Heritage ConservationHeritage Conservation
Heritage ConservationDr K M SONI
 
Project Management
Project ManagementProject Management
Project ManagementDr K M SONI
 
You are also a leader
You are also a leaderYou are also a leader
You are also a leaderDr K M SONI
 
Contract Management
Contract Management Contract Management
Contract Management Dr K M SONI
 
Contract and agreements
Contract and agreementsContract and agreements
Contract and agreementsDr K M SONI
 
Price variation in works contracts
Price variation in works contractsPrice variation in works contracts
Price variation in works contractsDr K M SONI
 
Anchors in civil engineering works
Anchors in civil engineering worksAnchors in civil engineering works
Anchors in civil engineering worksDr K M SONI
 
Advance Payments in Works
Advance Payments in WorksAdvance Payments in Works
Advance Payments in WorksDr K M SONI
 
Net zero energy building
Net zero energy buildingNet zero energy building
Net zero energy buildingDr K M SONI
 
C & D Waste Management
C & D Waste ManagementC & D Waste Management
C & D Waste ManagementDr K M SONI
 
EPC and other types of contracts
EPC and other types of contractsEPC and other types of contracts
EPC and other types of contractsDr K M SONI
 
Contract Management
Contract Management Contract Management
Contract Management Dr K M SONI
 
EPS Geofoam Blocks
EPS Geofoam BlocksEPS Geofoam Blocks
EPS Geofoam BlocksDr K M SONI
 
Aesthetics and Functionality through Glass
Aesthetics and Functionality through GlassAesthetics and Functionality through Glass
Aesthetics and Functionality through GlassDr K M SONI
 
Maintenance Aspects and Services in Architectural Planning
Maintenance Aspects and Services in Architectural PlanningMaintenance Aspects and Services in Architectural Planning
Maintenance Aspects and Services in Architectural PlanningDr K M SONI
 
Safety in Public Works
Safety in Public WorksSafety in Public Works
Safety in Public WorksDr K M SONI
 

More from Dr K M SONI (20)

Heritage Conservation
Heritage ConservationHeritage Conservation
Heritage Conservation
 
Project Management
Project ManagementProject Management
Project Management
 
You are also a leader
You are also a leaderYou are also a leader
You are also a leader
 
Contract Management
Contract Management Contract Management
Contract Management
 
Contract and agreements
Contract and agreementsContract and agreements
Contract and agreements
 
Price variation in works contracts
Price variation in works contractsPrice variation in works contracts
Price variation in works contracts
 
Anchors in civil engineering works
Anchors in civil engineering worksAnchors in civil engineering works
Anchors in civil engineering works
 
Advance Payments in Works
Advance Payments in WorksAdvance Payments in Works
Advance Payments in Works
 
Earnest Money
Earnest MoneyEarnest Money
Earnest Money
 
Deconstruction
DeconstructionDeconstruction
Deconstruction
 
Geosynthetics
GeosyntheticsGeosynthetics
Geosynthetics
 
Net zero energy building
Net zero energy buildingNet zero energy building
Net zero energy building
 
C & D Waste Management
C & D Waste ManagementC & D Waste Management
C & D Waste Management
 
EPC and other types of contracts
EPC and other types of contractsEPC and other types of contracts
EPC and other types of contracts
 
Contract Management
Contract Management Contract Management
Contract Management
 
EPS Geofoam Blocks
EPS Geofoam BlocksEPS Geofoam Blocks
EPS Geofoam Blocks
 
Aesthetics and Functionality through Glass
Aesthetics and Functionality through GlassAesthetics and Functionality through Glass
Aesthetics and Functionality through Glass
 
EPC Contracts
EPC Contracts EPC Contracts
EPC Contracts
 
Maintenance Aspects and Services in Architectural Planning
Maintenance Aspects and Services in Architectural PlanningMaintenance Aspects and Services in Architectural Planning
Maintenance Aspects and Services in Architectural Planning
 
Safety in Public Works
Safety in Public WorksSafety in Public Works
Safety in Public Works
 

Recently uploaded

INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEINFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEroselinkalist12
 
Electronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfElectronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfme23b1001
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.eptoze12
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learningmisbanausheenparvam
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...srsj9000
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionDr.Costas Sachpazis
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...asadnawaz62
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
power system scada applications and uses
power system scada applications and usespower system scada applications and uses
power system scada applications and usesDevarapalliHaritha
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidNikhilNagaraju
 
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2RajaP95
 
Introduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxIntroduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxk795866
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AIabhishek36461
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSCAESB
 
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxKartikeyaDwivedi3
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineeringmalavadedarshan25
 

Recently uploaded (20)

INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETEINFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
INFLUENCE OF NANOSILICA ON THE PROPERTIES OF CONCRETE
 
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
 
Electronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfElectronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdf
 
young call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Serviceyoung call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Service
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learning
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
power system scada applications and uses
power system scada applications and usespower system scada applications and uses
power system scada applications and uses
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfid
 
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
Introduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxIntroduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptx
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AI
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentation
 
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptx
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineering
 

Variations in works contracts

  • 1. CONTRACT CONDITIONS - II: VARIATIONS/DEVIATIONS Dr K M Soni, ADG(Retd.), CPWD, New Delhi
  • 2. Variations/Deviations • Variations or Deviations are the changes from the scope of work of a contract resulting during execution of work except duration of the contract. • Mostly, Variations or Deviations are considered the changes from the quantities or items of the bill of quantities (Schedule of quantities) of a contract resulting during execution of work as changes in design, quantity or conditions ultimately lead to affect BOQ/SOQ.
  • 3. Variations/Deviations • Variation/Deviation in quantities of items • Extra items • Substituted items
  • 4. Deviation in Quantities • These are the deviations or variations from the quantities taken in Bill of Quantities or Schedule of Quantities • These are the items for which rates are available in the contract • The deviations/variations may be +ve or –ve i.e. Quantities may increase or decrease from the quantities available in BOQ/SOQ
  • 5. Reasons of Deviations in Quantities • Wrong assessment or mistake during preparation of detailed estimate/BOQ/tender documents • Assessment of quantities without availability of architectural, structural or MEP drawings. • Revision of drawings/design • Revision due to local bye laws or local body agencies • Revision due to non availability of materials at a particular time • Revisions due to client, architect, or engineer and contractor
  • 6. Rates of Deviations in Quantities • Rates of such items are available in the contract • Deviations are +ve or –ve • Rates can be based on; • Available in contract for all deviations • Rates available in the contract upto additional quantities as mentioned in the contract (deviation limit, described in percentage) and beyond it, market rates, Schedule rates +/- quoted percentage, Schedule rates or cost plus basis or any other method as mentioned in the contract or agreed upon by the parties.
  • 7. Extra or Additional items • Items that are completely new and in addition to the items contained in the contract • These are the items other than those available in BOQ and not covered in the conditions of contract • In some contracts, these are the items which are not available in contract and not taken up in substitution of items available in BOQ
  • 8. Reasons of Extra/Additional items • Left or mistake during preparation of detailed estimate/BOQ/tender documents • Specifications not available during preparation of detailed estimate/BOQ • Non availability of architectural, structural or MEP drawings during preparation of detailed estimate/tender document • Revision of drawings/design • Revision due to local bye laws or local body agencies • Revision due to non availability of materials at a particular time • Items not anticipated during preparation of tender documents i.e. Contingent items • Revisions due to client, architect, or engineer and contractor
  • 9. Rates of Extra or Additional Items • Market rates • Schedule rates +/- quoted percentage • Schedule rates • Cost plus basis or • Any other method as mentioned in the contract or agreed upon by the parties.
  • 10. Substituted item • Items taken up as partial substitution or in lieu of items of work available in the contract • Therefore, the items are basically due to change of specifications during execution from those considered during preparation of detailed estimate/BOQ/tender documents
  • 11. Reasons of Substituted items • Specifications/drawings not available during preparation of detailed estimate/BOQ i.e. Non availability of architectural, structural or MEP drawings • Revision of drawings/design/specifications • Revision due to local bye laws or local body agencies • Revision due to non availability of materials or non feasibility of the execution of the item at a particular time • Revisions due to client, architect, or engineer and contractor
  • 12. Rates of Substituted Items • Agreement rates increased or decreased by the difference in market rates of item substituted compared to market rates of agreement item • Market rates • Schedule rates +/- quoted percentage • Schedule rates • Cost plus basis or • Any other method as mentioned in the contract or agreed upon by the parties.
  • 13. Implications of Variations/ Deviations • Extension of time • Possible justification of regularisation of delay caused by the contractor • Chances of non compatibility of such items with respect to other services • Source of Disputes about the rates, time extension, loss of profit, idle establishment and thus arbitration • Delayed decisions • Non approval of items and rates of variations • Time overrun and cost overrun
  • 14. Thanks for attending Dr K M Soni, ADG (Retd.), CPWD, New Delhi Also available on Youtube: KRISHNA MURARI Soni at https://www.youtube.com/channel/UC_pPYxk0jI1ayqA5rO6fBOw