Progress Of Slab
- 1. CLIENT: Zabeel
Investement L.I.C
Planning Departement
Package No. : D0469
Early Start Early Finish Early Start Early Finish Actual Start Actual Finish
Planned
Cycle
Rev.0A
Planned
Cycle
Rev.B
Actual
Concrete
Cycle
Tower N4
Floor Slab - Basement 1 13-Dec-06 20-Dec-06 21-Feb-07 08-Mar-07 04-Feb-07 26-Mar-07 -96 -18 100% 100% Finished
Floor Slab - Ground 30-Dec-06 6-Jan-07 18-Mar-07 02-Apr-07 29-Mar-07 09-Apr-07 17 25 14 -93 -7 100% 100% Finished
Floor Slab - Level 01 15-Jan-07 21-Jan-07 11-Apr-07 24-Apr-07 15-Apr-07 01-May-07 15 22 22 -100 -7 100% 100% Finished
Floor Slab - Level 02 29-Jan-07 04-Feb-07 02-May-07 13-May-07 06-May-07 10-May-07 14 19 9 -95 3 100% 100% Finished
Floor Slab - Level 03 12-Feb-07 17-Feb-07 21-May-07 31-May-07 17-May-07 21-May-07 13 18 11 -93 10 100% 100% Finished
Floor Slab - Level 04 25-Feb-07 01-Mar-07 09-Jun-07 18-Jun-07 23-May-07 28-May-07 12 18 7 -88 21 100% 100% Finished
Floor Slab - Level 05 08-Mar-07 13-Mar-07 25-Jun-07 03-Jul-07 02-Jun-07 07-Jun-07 12 15 10 -86 26 100% 100% Finished
Floor Slab - Level 06 20-Mar-07 25-Mar-07 10-Jul-07 18-Jul-07 14-Jun-07 20-Jun-07 12 15 13 -87 28 100% 100% Finished
Floor Slab - Level 07 01-Apr-07 05-Apr-07 25-Jul-07 02-Aug-07 24-Jun-07 29-Jun-07 11 15 9 -85 34 100% 100% Finished
Floor Slab - Level 08 12-Apr-07 17-Apr-07 09-Aug-07 18-Aug-07 08-Jul-07 18-Jul-07 12 16 19 -92 31 100% 100% Finished
Floor Slab - Level 09 24-Apr-07 29-Apr-07 25-Aug-07 02-Sep-07 25-Jul-07 31-Jul-07 12 15 13 -93 33 100% 100% Finished
Floor Slab - Level 10 06-May-07 10-May-07 09-Sep-07 17-Sep-07 04-Aug-07 13-Aug-07 11 15 13 -95 35 100% 100% Finished
Floor Slab - Level 11 17-May-07 22-May-07 24-Sep-07 02-Oct-07 21-Aug-07 26-Aug-07 12 15 13 -96 37 100% 100% Finished
Floor Slab - Level 12 29-May-07 03-Jun-07 09-Oct-07 17-Oct-07 02-Sep-07 06-Sep-07 12 15 11 -95 41 100% 100% Finished
Floor Slab - Level 13 10-Jun-07 14-Jun-07 24-Oct-07 01-Nov-07 14-Sep-07 19-Sep-07 11 15 13 -97 43 100% 100% Finished
Floor Slab - Level 14 21-Jun-07 26-Jun-07 08-Nov-07 17-Nov-07 01-Oct-07 18-Oct-07 12 16 29 -114 30 100% 100% Finished
Floor Slab - Level 15 03-Jul-07 08-Jul-07 24-Nov-07 02-Dec-07 07-Nov-07 19-Nov-07 12 15 32 -134 13 100% 100% Finished
Floor Slab - Roof Level 15-Jul-07 19-Jul-07 09-Dec-07 17-Dec-07 01-Dec-07 04-Dec-07 11 15 15 -138 13 100% 100% Finished
Delays
Anantara Palm Jumeirah and Tiara Residences
Planned
Progress Of
Concrete
Works
Progress Status
Rev.B
Actual Dates Concrete Cycles
Planned Dates
Progress Of Slabs (N4)
Actual
Progress Of
Concrete
Works
Data Date :
26January 08
Rev.0A Rev.B
Rev.0A
- 2. CLIENT: Zabeel
Investement L.I.C
Planning Departement
Package No. : D0469
Early Start Early Finish Early Start Early Finish Actual Start Actual Finish
Planned
Cycle
Rev.0A
Planned
Cycle
Rev.B
Actual
Concrete
Cycle
Tower N3
Floor Slab - Basement 1 23-dec-06 31-dec-06 08-Apr-07 24-Apr-07 13-Feb-07 29-mar-07 -88 26 100% 100% Finished
Floor Slab - Ground 08-jan-07 16-jan-07 02-May-07 19-May-07 05-Apr-07 12-apr-07 16 25 14 -86 37 100% 100% Finished
Floor Slab - Level 01 24-jan-07 31-jan-07 27-May-07 10-Jun-07 19-Apr-07 1-may-07 15 22 19 -90 40 100% 100% Finished
Floor Slab - Level 02 07-Feb-07 14-Feb-07 17-Jun-07 01-Jul-07 05-May-07 09-May-07 14 21 8 -84 53 100% 100% Finished
Floor Slab - Level 03 21-Feb-07 27-Feb-07 08-Jul-07 17-Jul-07 13-May-07 18-May-07 13 16 9 -80 60 100% 100% Finished
Floor Slab - Level 04 05-Mar-07 11-Mar-07 23-Jul-07 01-Aug-07 27-May-07 04-Jun-07 12 15 17 -85 58 100% 100% Finished
Floor Slab - Level 05 17-Mar-07 22-Mar-07 07-Aug-07 13-Aug-07 09-Jun-07 13-Jun-07 11 12 9 -83 61 100% 100% Finished
Floor Slab - Level 06 28-Mar-07 03-Apr-07 19-Aug-07 25-Aug-07 19-Jun-07 27-Jun-07 12 12 14 -85 59 100% 100% Finished
Floor Slab - Level 07 09-Apr-07 15-Apr-07 30-Aug-07 05-Sep-07 05-Jul-07 10-Jul-07 12 11 13 -86 57 100% 100% Finished
Floor Slab - Level 08 21-Apr-07 26-Apr-07 11-Sep-07 17-Sep-07 19-Jul-07 25-Jul-07 11 12 15 -90 54 100% 100% Finished
Floor Slab - Level 09 02-May-07 08-May-07 23-Sep-07 29-Sep-07 02-Aug-07 07-Aug-07 12 12 13 -91 53 100% 100% Finished
Floor Slab - Level 10 14-May-07 20-May-07 04-Oct-07 10-Oct-07 18-Aug-07 21-Aug-07 12 11 14 -93 50 100% 100% Finished
Floor Slab - Level 11 26-May-07 31-May-07 16-Oct-07 22-Oct-07 31-Aug-07 05-Sep-07 11 12 15 -97 47 100% 100% Finished
Floor Slab - Level 12 06-Jun-07 12-Jun-07 28-Oct-07 03-Nov-07 19-Sep-07 24-Sep-07 12 12 19 -104 40 100% 100% Finished
Floor Slab - Level 13 18-Jun-07 24-Jun-07 08-Nov-07 14-Nov-07 01-Oct-07 04-Oct-07 12 11 10 -102 41 100% 100% Finished
Floor Slab - Level 14 30-Jun-07 05-Jul-07 20-Nov-07 26-Nov-07 17-Oct-07 27-Oct-07 11 12 23 -114 30 100% 100% Finished
Floor Slab - Level 15 11-Jul-07 17-Jul-07 02-Dec-07 08-Dec-07 13-Nov-07 22-Nov-07 12 12 26 -128 16 100% 100% Finished
Floor Slab - Roof Level 23-Jul-07 29-Jul-07 13-Dec-07 19-Dec-07 04-Dec-07 06-Dec-07 12 11 14 -130 13 100% 100% Finished
Planned
Progress Of
Concrete
Works
Actual
Progress Of
Concrete
Works
Planned Dates
Actual Dates Concrete Cycles
Progress Of Slabs (N3)
Data Date :
26January 08
Anantara Palm Jumeirah and Tiara Residences
Progress Status
Delays
Rev.0A Rev.B
Rev.0A Rev.B
- 3. CLIENT: Zabeel
Investement L.I.C
Planning Departement
Package No. : D0469
Early Start Early Finish Early Start Early Finish Actual Start Actual Finish
Planned
Cycle
Rev.0A
Planned
Cycle
Rev.B
Actual
Concrete
Cycle
Tower N2
Floor Slab - Basement 1 07-jan-07 14-jan-07 12-May-07 19-May-07 26-Feb-07 03-Apr-07 -79 46 100% 100% Finished
Floor Slab - Ground 23-jan-07 30-jan-07 28-May-07 04-Jun-07 08-Apr-07 16-Apr-07 16 16 13 -76 49 100% 100% Finished
Floor Slab - Level 01 8-feb-07 14-feb-07 13-Jun-07 19-Jun-07 23-Apr-07 02-May-07 15 15 16 -77 48 100% 100% Finished
Floor Slab - Level 02 22-Feb-07 28-Feb-07 27-Jun-07 03-Jul-07 07-May-07 13-May-07 14 14 11 -74 51 100% 100% Finished
Floor Slab - Level 03 08-Mar-07 14-Mar-07 11-Jul-07 17-Jul-07 27-May-07 31-May-07 14 14 18 -78 47 100% 100% Finished
Floor Slab - Level 04 22-Mar-07 28-Mar-07 25-Jul-07 31-Jul-07 10-Jun-07 14-Jun-07 14 14 14 -78 47 100% 100% Finished
Floor Slab - Level 05 05-Apr-07 10-Apr-07 08-Aug-07 13-Aug-07 23-Jun-07 27-Jun-07 13 13 13 -78 47 100% 100% Finished
Floor Slab - Level 06 18-Apr-07 23-Apr-07 21-Aug-07 26-Aug-07 30-Jun-07 08-Jul-07 13 13 11 -76 49 100% 100% Finished
Floor Slab - Level 07 30-Apr-07 05-May-07 02-Sep-07 06-Sep-07 17-Jul-07 23-Jul-07 12 11 15 -79 45 100% 100% Finished
Floor Slab - Level 08 17-May-07 22-May-07 19-Sep-07 24-Sep-07 31-Jul-07 06-Aug-07 17 18 14 -76 49 100% 100% Finished
Floor Slab - Level 09 29-May-07 03-Jun-07 01-Oct-07 06-Oct-07 12-Aug-07 16-Aug-07 12 12 10 -74 51 100% 100% Finished
Floor Slab - Level 10 10-Jun-07 14-Jun-07 13-Oct-07 17-Oct-07 25-Aug-07 29-Aug-07 11 11 13 -76 49 100% 100% Finished
Floor Slab - Level 11 21-Jun-07 26-Jun-07 24-Oct-07 29-Oct-07 11-Sep-07 17-Sep-07 12 12 19 -83 42 100% 100% Finished
Floor Slab - Level 12 03-Jul-07 08-Jul-07 05-Nov-07 10-Nov-07 25-Sep-07 30-Sep-07 12 12 13 -84 41 100% 100% Finished
Floor Slab - Level 13 15-Jul-07 19-Jul-07 17-Nov-07 21-Nov-07 07-Oct-07 16-Oct-07 11 11 16 -89 36 100% 100% Finished
Floor Slab - Level 14 26-Jul-07 31-Jul-07 28-Nov-07 03-Dec-07 27-Oct-07 31-Oct-07 12 12 15 -92 33 100% 100% Finished
Floor Slab - Level 15 07-Aug-07 12-Aug-07 10-Dec-07 15-Dec-07 18-Nov-07 26-Nov-07 12 12 26 -106 19 100% 100% Finished
Floor Slab - Roof Level 19-Aug-07 23-Aug-07 22-Dec-07 26-Dec-07 06-Dec-07 09-Dec-07 11 11 13 -108 17 100% 100% Finished
Planned Dates Delays
Rev.0A Rev.B
Rev.0A Rev.B
Actual Dates Concrete Cycles
Progress Of Slabs (N2)
Data Date :
26January 08
Anantara Palm Jumeirah and Tiara Residences
Progress Status
Planned
Progress Of
Concrete
Works
Actual
Progress Of
Concrete
Works
- 4. CLIENT: Zabeel
Investement L.I.C
Planning Departement
Package No. : D0469
Early Start Early Finish Early Start Early Finish Actual Start Actual Finish
Planned
Cycle
Rev.0A
Planned
Cycle
Rev.B
Actual
Concrete
Cycle
Tower N1
Floor Slab - Basement 1 10-jan-07 18-jan-07 03-Jun-07 11-Jun-07 10-Mar-07 07-apr-07 -79 65 100% 100% Finished
Floor Slab - Ground 27-jan-07 4-Feb-07 19-Jun-07 27-Jun-07 14-Apr-07 19-apr-07 17 16 12 -74 69 100% 100% Finished
Floor Slab - Level 01 12-feb-07 20-feb-07 05-Jul-07 14-Jul-07 26-Apr-07 3-may-07 16 17 14 -72 72 100% 100% Finished
Floor Slab - Level 02 27-Feb-07 06-Mar-07 21-Jul-07 28-Jul-07 12-May-07 20-May-07 14 14 17 -75 69 100% 100% Finished
Floor Slab - Level 03 13-Mar-07 20-Mar-07 04-Aug-07 11-Aug-07 23-May-07 28-May-07 14 14 8 -69 75 100% 100% Finished
Floor Slab - Level 04 27-Mar-07 03-Apr-07 18-Aug-07 25-Aug-07 02-Jun-07 09-Jun-07 14 14 12 -67 77 100% 100% Finished
Floor Slab - Level 05 10-Apr-07 17-Apr-07 01-Sep-07 08-Sep-07 13-Jun-07 19-Jun-07 14 14 10 -63 81 100% 100% Finished
Floor Slab - Level 06 23-Apr-07 29-Apr-07 13-Sep-07 19-Sep-07 25-Jun-07 02-Jul-07 12 11 13 -64 79 100% 100% Finished
Floor Slab - Level 07 05-May-07 10-May-07 25-Sep-07 01-Oct-07 09-Jul-07 18-Jul-07 11 12 16 -69 75 100% 100% Finished
Floor Slab - Level 08 16-May-07 22-May-07 07-Oct-07 13-Oct-07 25-Jul-07 30-Jul-07 12 12 12 -69 75 100% 100% Finished
Floor Slab - Level 09 28-May-07 03-Jun-07 18-Oct-07 24-Oct-07 04-Aug-07 09-Aug-07 12 11 10 -67 76 100% 100% Finished
Floor Slab - Level 10 09-Jun-07 14-Jun-07 30-Oct-07 05-Nov-07 15-Aug-07 23-Aug-07 11 12 14 -70 74 100% 100% Finished
Floor Slab - Level 11 20-Jun-07 26-Jun-07 11-Nov-07 17-Nov-07 29-Aug-07 03-Sep-07 12 12 11 -69 75 100% 100% Finished
Floor Slab - Level 12 02-Jul-07 08-Jul-07 22-Nov-07 28-Nov-07 12-Sep-07 17-Sep-07 12 11 14 -71 72 100% 100% Finished
Floor Slab - Level 13 14-Jul-07 19-Jul-07 04-Dec-07 10-Dec-07 23-Sep-07 27-Sep-07 11 12 10 -70 74 100% 100% Finished
Floor Slab - Level 14 25-Jul-07 31-Jul-07 16-Dec-07 22-Dec-07 16-Oct-07 21-Oct-07 12 12 24 -82 62 100% 100% Finished
Floor Slab - Level 15 06-Aug-07 12-Aug-07 27-Dec-07 02-Jan-08 21-Nov-07 30-Nov-07 12 11 40 -110 33 29% 100% Finished
Floor Slab - Roof Level 18-Aug-07 23-Aug-07 08-Jan-08 14-Jan-08 07-Dec-07 11-Dec-07 11 12 11 -110 34 0% 100% Finished
Rev.B
Rev.0A Rev.B
Planned Dates
Actual Dates Concrete Cycles
Progress Of Slabs (N1)
Data Date :
26January 08
Anantara Palm Jumeirah and Tiara Residences
Progress Status
Planned
Progress Of
Concrete
Works
Actual
Progress Of
Concrete
Works
Delays
Rev.0A
- 5. CLIENT: Zabeel
Investement L.I.C
Planning Departement
Package No. : D0469
Early Start Early Finish Early Start Early Finish Actual Start Actual Finish
Planned
Cycle
Rev.0A
Planned
Cycle
Rev.B
Actual
Concrete
Cycle
Tower S1
Floor Slab - Basement 1 24-jan-07 31-jan-07 12-Apr-07 19-Apr-07 05-Feb-07 26-Mar-07 -54 24 100% 100% Finished
Floor Slab - Ground 10-feb-07 17-feb-07 29-Apr-07 06-May-07 29-Mar-07 08-Apr-07 17 17 13 -50 28 100% 100% Finished
Floor Slab - Level 01 26-feb-07 5-mar-07 15-May-07 22-May-07 12-Apr-07 01-May-07 16 16 23 -57 21 100% 100% Finished
Floor Slab - Level 02 14-Mar-07 21-Mar-07 31-May-07 07-Jun-07 07-May-07 14-May-07 16 16 13 -54 24 100% 100% Finished
Floor Slab - Level 03 29-Mar-07 04-Apr-07 16-Jun-07 21-Jun-07 17-May-07 21-May-07 14 14 7 -47 31 100% 100% Finished
Floor Slab - Level 04 12-Apr-07 18-Apr-07 30-Jun-07 05-Jul-07 26-May-07 30-May-07 14 14 9 -42 36 100% 100% Finished
Floor Slab - Level 05 26-Apr-07 02-May-07 14-Jul-07 19-Jul-07 09-Jun-07 18-Jun-07 14 14 19 -47 31 100% 100% Finished
Floor Slab - Level 06 09-May-07 14-May-07 26-Jul-07 31-Jul-07 24-Jun-07 02-Jul-07 12 12 14 -49 29 100% 100% Finished
Floor Slab - Level 07 21-May-07 26-May-07 07-Aug-07 12-Aug-07 08-Jul-07 16-Jul-07 12 12 14 -51 27 100% 100% Finished
Floor Slab - Level 08 02-Jun-07 06-Jun-07 19-Aug-07 23-Aug-07 21-Jul-07 29-Jul-07 11 11 13 -53 25 100% 100% Finished
Floor Slab - Level 09 13-Jun-07 18-Jun-07 30-Aug-07 04-Sep-07 04-Aug-07 08-Aug-07 12 12 10 -51 27 100% 100% Finished
Floor Slab - Level 10 25-Jun-07 30-Jun-07 11-Sep-07 16-Sep-07 19-Aug-07 22-Aug-07 12 12 14 -53 25 100% 100% Finished
Floor Slab - Level 11 07-Jul-07 11-Jul-07 23-Sep-07 27-Sep-07 28-Aug-07 02-Sep-07 11 11 11 -53 25 100% 100% Finished
Floor Slab - Level 12 18-Jul-07 23-Jul-07 04-Oct-07 09-Oct-07 11-Sep-07 16-Sep-07 12 12 14 -55 23 100% 100% Finished
Floor Slab - Level 13 30-Jul-07 04-Aug-07 16-Oct-07 21-Oct-07 24-Sep-07 30-Sep-07 12 12 14 -57 21 100% 100% Finished
Floor Slab - Level 14 11-Aug-07 15-Aug-07 28-Oct-07 01-Nov-07 14-Oct-07 25-Oct-07 11 11 25 -71 7 100% 100% Finished
Floor Slab - Level 15 22-Aug-07 27-Aug-07 08-Nov-07 13-Nov-07 13-Nov-07 25-Nov-07 12 12 31 -90 -12 100% 100% Finished
Floor Slab - Roof Level 03-Sep-07 08-Sep-07 20-Nov-07 25-Nov-07 16-Dec-07 16-Dec-07 12 12 21 -99 -21 100% 100% Finished
Planned Dates Delays
Rev.0A Rev.B
Rev.0A Rev.B
Actual Dates Concrete Cycles
Anantara Palm Jumeirah and Tiara Residences
Progress Of Slabs (S1)
Data Date :
26January 08
Progress Status
Planned
Progress Of
Concrete
Works
Actual
Progress Of
Concrete
Works
- 6. CLIENT: Zabeel
Investement L.I.C
Planning Departement
Package No. : D0469
Early Start Early Finish Early Start Early Finish Actual Start Actual Finish
Planned
Cycle
Rev.0A
Planned
Cycle
Rev.B
Actual
Concrete
Cycle
Tower S2
Floor Slab - Basement 1 31-jan-07 08-Feb-07 08-May-07 16-May-07 12-Feb-07 29-Mar-07 -49 48 100% 100% Finished
Floor Slab - Ground 17-Feb-07 25-Feb-07 24-May-07 02-Jun-07 04-Apr-07 12-apr-07 17 17 14 -46 51 100% 100% Finished
Floor Slab - Level 01 05-Mar-07 12-Mar-07 10-Jun-07 17-Jun-07 18-Apr-07 30-apr-07 15 15 18 -49 48 100% 100% Finished
Floor Slab - Level 02 19-Mar-07 26-Mar-07 24-Jun-07 01-Jul-07 03-May-07 09-May-07 14 14 9 -44 53 100% 100% Finished
Floor Slab - Level 03 02-Apr-07 09-Apr-07 08-Jul-07 15-Jul-07 14-May-07 17-May-07 14 14 8 -38 59 100% 100% Finished
Floor Slab - Level 04 16-Apr-07 23-Apr-07 22-Jul-07 29-Jul-07 22-May-07 27-May-07 14 14 10 -34 63 100% 100% Finished
Floor Slab - Level 05 30-Apr-07 07-May-07 05-Aug-07 12-Aug-07 31-May-07 07-Jun-07 14 14 11 -31 66 100% 100% Finished
Floor Slab - Level 06 14-May-07 21-May-07 19-Aug-07 26-Aug-07 14-Jun-07 26-Jun-07 14 14 19 -36 61 100% 100% Finished
Floor Slab - Level 07 27-May-07 02-Jun-07 01-Sep-07 06-Sep-07 02-Jul-07 08-Jul-07 12 11 12 -36 60 100% 100% Finished
Floor Slab - Level 08 07-Jun-07 13-Jun-07 12-Sep-07 18-Sep-07 14-Jul-07 19-Jul-07 11 12 11 -36 61 100% 100% Finished
Floor Slab - Level 09 19-Jun-07 25-Jun-07 24-Sep-07 30-Sep-07 26-Jul-07 01-Aug-07 12 12 13 -37 60 100% 100% Finished
Floor Slab - Level 10 01-Jul-07 07-Jul-07 06-Oct-07 11-Oct-07 04-Aug-07 13-Aug-07 12 11 12 -37 59 100% 100% Finished
Floor Slab - Level 11 12-Jul-07 18-Jul-07 17-Oct-07 23-Oct-07 21-Aug-07 26-Aug-07 11 12 13 -39 58 100% 100% Finished
Floor Slab - Level 12 24-Jul-07 30-Jul-07 29-Oct-07 04-Nov-07 02-Sep-07 06-Sep-07 12 12 11 -38 59 100% 100% Finished
Floor Slab - Level 13 05-Aug-07 11-Aug-07 10-Nov-07 15-Nov-07 14-Sep-07 20-Sep-07 12 11 14 -40 56 100% 100% Finished
Floor Slab - Level 14 16-Aug-07 22-Aug-07 21-Nov-07 27-Nov-07 30-Sep-07 18-Oct-07 11 12 28 -57 40 100% 100% Finished
Floor Slab - Level 15 28-Aug-07 03-Sep-07 03-Dec-07 09-Dec-07 12-Nov-07 20-Nov-07 12 12 33 -78 19 100% 100% Finished
Floor Slab - Roof Level 09-Sep-07 15-Sep-07 15-Dec-07 20-Dec-07 08-Dec-07 10-Dec-07 12 11 20 -86 10 100% 100% Finished
Planned Dates
Actual Dates Concrete Cycles
Rev.B
Rev.0A Rev.B
Anantara Palm Jumeirah and Tiara Residences
Progress Of Slabs (S2)
Data Date :
26January 08
Progress Status
Planned
Progress Of
Concrete
Works
Actual
Progress Of
Concrete
Works
Delays
Rev.0A
- 7. CLIENT: Zabeel
Investement L.I.C
Planning Departement
Package No. : D0469
Early Start Early Finish Early Start Early Finish Actual Start Actual Finish
Planned
Cycle
Rev.0A
Planned
Cycle
Rev.B
Actual
Concrete
Cycle
Tower S3
Floor Slab - Basement 1 15-jan-07 22-jan-07 24-Feb-07 11-Mar-07 17-Feb-07 03-apr-07 -71 -23 100% 100% Finished
Floor Slab - Ground 31-jan-07 7-Feb-07 20-Mar-07 02-Apr-07 07-Apr-07 18-apr-07 16 22 15 -70 -16 100% 100% Finished
Floor Slab - Level 01 17-feb-07 24-feb-07 11-Apr-07 22-Apr-07 21-Apr-07 2-may-07 17 20 14 -67 -10 100% 100% Finished
Floor Slab - Level 02 04-Mar-07 10-Mar-07 30-Apr-07 08-May-07 07-May-07 13-May-07 14 16 11 -64 -5 100% 100% Finished
Floor Slab - Level 03 18-Mar-07 24-Mar-07 16-May-07 24-May-07 17-May-07 22-May-07 14 16 9 -59 2 100% 100% Finished
Floor Slab - Level 04 01-Apr-07 07-Apr-07 02-Jun-07 10-Jun-07 26-May-07 03-Jun-07 14 17 12 -57 7 100% 100% Finished
Floor Slab - Level 05 15-Apr-07 21-Apr-07 18-Jun-07 26-Jun-07 09-Jun-07 17-Jun-07 14 16 14 -57 9 100% 100% Finished
Floor Slab - Level 06 29-Apr-07 05-May-07 04-Jul-07 12-Jul-07 23-Jun-07 28-Jun-07 14 16 11 -54 14 100% 100% Finished
Floor Slab - Level 07 13-May-07 19-May-07 21-Jul-07 26-Jul-07 05-Jul-07 10-Jul-07 14 14 12 -52 16 100% 100% Finished
Floor Slab - Level 08 27-May-07 02-Jun-07 04-Aug-07 09-Aug-07 15-Jul-07 22-Jul-07 14 14 12 -50 18 100% 100% Finished
Floor Slab - Level 09 10-Jun-07 16-Jun-07 18-Aug-07 23-Aug-07 29-Jul-07 06-Aug-07 14 14 15 -51 17 100% 100% Finished
Floor Slab - Level 10 23-Jun-07 27-Jun-07 30-Aug-07 05-Sep-07 12-Aug-07 16-Aug-07 11 13 10 -50 20 100% 100% Finished
Floor Slab - Level 11 04-Jul-07 09-Jul-07 12-Sep-07 18-Sep-07 23-Aug-07 29-Aug-07 12 13 13 -51 20 100% 100% Finished
Floor Slab - Level 12 16-Jul-07 21-Jul-07 25-Sep-07 01-Oct-07 06-Sep-07 11-Sep-07 12 13 13 -52 20 100% 100% Finished
Floor Slab - Level 13 28-Jul-07 01-Aug-07 08-Oct-07 14-Oct-07 19-Sep-07 24-Sep-07 11 13 13 -54 20 100% 100% Finished
Floor Slab - Level 14 08-Aug-07 13-Aug-07 21-Oct-07 27-Oct-07 04-Oct-07 22-Oct-07 12 13 28 -70 5 100% 100% Finished
Floor Slab - Level 15 20-Aug-07 25-Aug-07 03-Nov-07 08-Nov-07 18-Nov-07 30-Nov-07 12 12 39 -97 -22 100% 100% Finished
Floor Slab - Roof Level 01-Sep-07 05-Sep-07 15-Nov-07 21-Nov-07 14-Dec-07 17-Dec-07 11 13 17 -103 -26 100% 100% Finished
Planned Dates Delays
Rev.0A Rev.B
Rev.0A Rev.B
Actual Dates Concrete Cycles
Anantara Palm Jumeirah and Tiara Residences
Progress Of Slabs (S3)
Data Date :
26January 08
Actual
Progress Of
Concrete
Works
Progress Status
Planned
Progress Of
Concrete
Works
- 8. CLIENT: Zabeel
Investement L.I.C
Planning Departement
Package No. : D0469
Early Start Early Finish Early Start Early Finish Actual Start Actual Finish
Planned
Cycle
Rev.0A
Planned
Cycle
Rev.B
Actual
Concrete
Cycle
Tower H1
Floor Slab - Basement 2 19-dec-06 31-dec-06 11-Feb-07 22-Feb-07 05-Feb-07 05-Apr-07 -95 -42 100% 100% Finished
Floor Slab - Basement 1 20-Jan-07 31-Jan-07 14-Mar-07 26-Mar-07 18-Apr-07 29-Apr-07 31 32 24 -88 -34 100% 100% Finished
Floor Slab - Ground 12-Feb-07 24-Feb-07 07-Apr-07 18-Apr-07 30-Apr-07 21-May-07 24 23 22 -86 -33 100% 100% Finished
Floor Slab - Mezzanine 05-Mar-07 14-Mar-07 28-Apr-07 07-May-07 22-May-07 30-May-07 18 19 9 -77 -23 100% 100% Finished
Floor Slab - Level 01 22-Mar-07 31-Mar-07 15-May-07 23-May-07 01-Jun-07 30-Jun-07 17 16 31 -91 -38 100% 100% Finished
Floor Slab - Level 02 08-Apr-07 16-Apr-07 31-May-07 09-Jun-07 01-Jul-07 17-Jul-07 16 17 17 -92 -38 100% 100% Finished
Floor Slab - Level 03 23-Apr-07 30-Apr-07 16-Jun-07 23-Jun-07 19-Jul-07 02-Aug-07 14 14 16 -94 -40 100% 100% Finished
Floor Slab - Level 04 07-May-07 13-May-07 30-Jun-07 05-Jul-07 08-Aug-07 18-Aug-07 13 12 16 -97 -44 100% 100% Finished
Floor Slab - Level 05 19-May-07 24-May-07 11-Jul-07 17-Jul-07 21-Aug-07 27-Aug-07 11 12 9 -95 -41 100% 100% Finished
Floor Slab - Level 06 30-May-07 05-Jun-07 23-Jul-07 29-Jul-07 30-Aug-07 04-Sep-07 12 12 8 -91 -37 100% 100% Finished
Floor Slab - Level 07 11-Jun-07 17-Jun-07 04-Aug-07 09-Aug-07 07-Sep-07 13-Sep-07 12 11 9 -88 -35 100% 100% Finished
Floor Slab - Level 08 23-Jun-07 28-Jun-07 15-Aug-07 21-Aug-07 15-Sep-07 19-Sep-07 11 12 6 -83 -29 100% 100% Finished
Floor Slab - Level 09 04-Jul-07 10-Jul-07 27-Aug-07 02-Sep-07 21-Sep-07 26-Sep-07 12 12 7 -78 -24 100% 100% Finished
Floor Slab - Level 10 16-Jul-07 22-Jul-07 08-Sep-07 13-Sep-07 28-Sep-07 03-Oct-07 12 11 7 -73 -20 100% 100% Finished
Floor Slab - Level 11 28-Jul-07 02-Aug-07 19-Sep-07 25-Sep-07 05-Oct-07 10-Oct-07 11 12 7 -69 -15 100% 100% Finished
Floor Slab - Level 12 08-Aug-07 14-Aug-07 01-Oct-07 07-Oct-07 14-Oct-07 11-Nov-07 12 12 32 -89 -35 100% 100% Finished
Floor Slab - Level 13 20-Aug-07 26-Aug-07 13-Oct-07 18-Oct-07 15-Nov-07 21-Nov-07 12 11 10 -87 -34 100% 100% Finished
Floor Slab - Level 14 01-Sep-07 06-Sep-07 24-Oct-07 30-Oct-07 24-Nov-07 04-Dec-07 11 12 13 -89 -35 100% 100% Finished
Floor Slab - Level 15 12-Sep-07 18-Sep-07 05-Nov-07 11-Nov-07 07-Dec-08 27-Dec-07 12 12 23 -100 -46 100% 100% Finished
Floor Slab - Roof Level 24-Sep-07 30-Sep-07 17-Nov-07 22-Nov-07 100% 0% Behind
Rev.B
Planned
Progress Of
Concrete
Works
Actual
Progress Of
Concrete
Works
Planned Dates
Actual Dates Concrete Cycles
Delays
Rev.0A Rev.B
Rev.0A
Data Date :
26January 08
Anantara Palm Jumeirah and Tiara Residences
Progress Of Slabs (H1)
Progress Status
- 9. CLIENT: Zabeel
Investement L.I.C
Planning Departement
Package No. : D0469
Early Start Early Finish Early Start Early Finish Actual Start Actual Finish
Planned
Cycle
Rev.0A
Planned
Cycle
Rev.B
Actual
Concrete
Cycle
Tower H2
Floor Slab - Basement 2 19-dec-06 31-dec-06 11-Feb-07 22-Feb-07 04-Feb-07 03-Apr-07 -93 -40 100% 100% Finished
Floor Slab - Basement 1 20-jan-07 31-jan-07 14-Mar-07 26-Mar-07 08-Apr-07 26-Apr-07 31 32 23 -85 -31 100% 100% Finished
Floor Slab - Ground 12-Feb-07 24-Feb-07 07-Apr-07 18-Apr-07 30-Apr-07 24-May-07 24 23 28 -89 -36 100% 100% Finished
Floor Slab - Mezzanine 05-Mar-07 14-Mar-07 28-Apr-07 07-May-07 22-May-07 30-May-07 18 19 6 -77 -23 100% 100% Finished
Floor Slab - Level 01 22-Mar-07 31-Mar-07 15-May-07 23-May-07 01-Jun-07 30-Jun-07 17 16 31 -91 -38 100% 100% Finished
Floor Slab - Level 02 08-Apr-07 16-Apr-07 31-May-07 09-Jun-07 03-Jul-07 17-Jul-07 16 17 17 -92 -38 100% 100% Finished
Floor Slab - Level 03 23-Apr-07 30-Apr-07 16-Jun-07 23-Jun-07 21-Jul-07 03-Aug-07 14 14 17 -95 -41 100% 100% Finished
Floor Slab - Level 04 07-May-07 13-May-07 30-Jun-07 05-Jul-07 04-Aug-07 13-Aug-07 13 12 10 -92 -39 100% 100% Finished
Floor Slab - Level 05 19-May-07 24-May-07 11-Jul-07 17-Jul-07 19-Aug-07 23-Aug-07 11 12 10 -91 -37 100% 100% Finished
Floor Slab - Level 06 30-May-07 05-Jun-07 23-Jul-07 29-Jul-07 27-Aug-07 31-Aug-07 12 12 8 -87 -33 100% 100% Finished
Floor Slab - Level 07 17-Jun-07 24-Jun-07 09-Aug-07 16-Aug-07 03-Sep-07 07-Sep-07 19 18 7 -75 -22 100% 100% Finished
Floor Slab - Level 08 30-Jun-07 05-Jul-07 22-Aug-07 28-Aug-07 10-Sep-07 16-Sep-07 11 12 9 -73 -19 100% 100% Finished
Floor Slab - Level 09 11-Jul-07 17-Jul-07 03-Sep-07 09-Sep-07 18-Sep-07 23-Sep-07 12 12 7 -68 -14 100% 100% Finished
Floor Slab - Level 10 23-Jul-07 29-Jul-07 15-Sep-07 20-Sep-07 25-Sep-07 30-Sep-07 12 11 7 -63 -10 100% 100% Finished
Floor Slab - Level 11 04-Aug-07 09-Aug-07 26-Sep-07 02-Oct-07 03-Oct-07 07-Oct-07 11 12 7 -59 -5 100% 100% Finished
Floor Slab - Level 12 15-Aug-07 21-Aug-07 08-Oct-07 14-Oct-07 09-Oct-07 15-Nov-07 12 12 39 -86 -32 100% 100% Finished
Floor Slab - Level 13 27-Aug-07 02-Sep-07 20-Oct-07 25-Oct-07 18-Nov-07 25-Nov-07 12 11 10 -84 -31 100% 100% Finished
Floor Slab - Level 14 08-Sep-07 13-Sep-07 31-Oct-07 06-Nov-07 29-Nov-07 06-Dec-07 11 12 11 -84 -30 100% 100% Finished
Floor Slab - Level 15 19-Sep-07 25-Sep-07 12-Nov-07 18-Nov-07 11-Dec-07 29-Dec-07 12 12 23 -95 -41 100% 100% Finished
Floor Slab - Roof Level 07-Oct-07 13-Oct-07 29-Nov-07 05-Dec-07 100% 0% Behind
Planned Dates
Actual Dates Concrete Cycles
Delays
Rev.0A Rev.B
Rev.0A Rev.B
Data Date :
26January 08
Planned
Progress Of
Concrete
Works
Actual
Progress Of
Concrete
Works
Progress Status
Anantara Palm Jumeirah and Tiara Residences
Progress Of Slabs (H2)