SlideShare a Scribd company logo
1 of 24
1
STUDY IN RISK MANAGEMENT
OF STEEL PLANT PROJECTS
PRESENTED BY :-
DILPREET SINGH
NICMAR PEM-9 (2013-15)
2
OVERVIEW
 INTRODUCTION
 REVIEW OF LITERATURE
 RESEARCH METHODOLOGY
METHOD - I (Quantitative Analysis)
METHOD - II (Qualitative Analysis)
 FINDINGS FROM METHOD I & II
 CONCLUSION
 LIMITATIONS
 REFERENCES 3
INTRODUCTION
 The Steel industry is being faced by myriad challenges such as
volatility, shifting demand centers, complex supply chains,
productivity and cost efficiency.
 It incorporates different phases of steel plant projects such as
Development phase, Execution phase and Operation phase.
 The scope of study includes qualitative and quantitative
analysis which helps in consolidating decision making under
uncertainty.
4
5
S.No. Company Location State
Current
approximate
Capacity*
1 Steel Authority of India Limited IISCO, Burnpur West Bengal 0.5
2 Steel Authority of India Limited Bokaro Jharkhand 4.36
3 Steel Authority of India Limited Bhilai Chhattisgarh 3.93
4 Steel Authority of India Limited Rourkela Orissa 1.9
5 Steel Authority of India Limited Durgapur West Bengal 1.8
6 RashtriyaIspat Nigam Limited Visakhapatanam Andhra Aradesh 2.9
7 Tata Steel Limited Jamshedpur Jharkhand 6.8
8 Essar Steel Limited Hazira Gujarat 4.6
9 JSW Steel Limited Vijayanagar Karnataka 6.6
10 Jindal Steel & Power Limited Raigarh Chhattisgarh 2.4
11 Ispat Industries Limited Dolvi Maharastra 3
12 Bhushan Power & Steel Limited Jharsugda Orissa 1.2
13 Bhushan Steel Limited Angul-Dhenkanal Orissa 1.56
NUMBERS OF STEEL PLANT IN INDIA WITH THEIR CAPACITY
SOURCE: http://pib.nic.in/newsite/erelease.aspx?relid=77494
OBJECTIVES
 To study the risks involved in Steel Plant Project and to
identify the benefits of application of the risk management.
 To identify the principles of Risk Management.
 To find the most critical risks which were quantified with the
help of @RISK software and as per the tornedo chart the
results are interpreted. .
 To assess and mitigate the risk involved in Steel Plant Projects
and arriving at a conclusion
7
REVIEW OF LITERATURE
 Steel demand and production outlook for indian steel.
 Steel consumption scenarios.
 Global outlook for Steel.
8
PROJECT RISK MANAGEMENT
PROCESS
9
QUANTITATIVE ANALYSIS
 Questionnaire
 Risk Rating
 Responses
 Tornado Graph
 Interpretation
 Identification of critical risks
 Mitigation Plans
10
VARIABLES
11
  Development Phase
1 Significant swings in the demand for steel.
2
Decline in Profit Margin in downstream
processing.
3 Difficulties in financing project.
4 Unrealistic contract duration.
5 Scarcity of raw materials.
6 Market risk.
7 Political risk.
8 Delay in land acquisition.
9 Delay in obtaining permissions.
10 Energy Scarcity Risks.
11 Risk of Exchange Rate Fluctuations
12 Business Competition Risk.
CONTINUED…..
  Construction Phase
13 Lack of decision making involving all project teams.
14 Unforeseen ground conditions.
15 Change in soil condition.
16 Lack of technical feasibility.
17 Changes in rules & regulations.
18 Severe weather conditions.
19 Safety Risk.
20 Non-availability of utilities on site.
21 Lack of effeicient technology.
22 Inadequate code provision.
23 Delay in payments by owner.
24 Delay in supply of equipments
25 Lack of information available.
26 Non-availability of utilities on site.
27 Failure of construction equipment.
28 Interrupted cash flow.
12
CONTINUED…..
 
Operation Phase
29 Fuel supply risk.
30 Improper estimation for maintenance&operationcost.
31 Overproduction of steel.
32 Incorrect manufacturing processes.
33 Ineffecient quality standards.
34 Inadequate safety measures.
35 Ineffeciency of subcontractor company.
13
WHY @RISK SOFTWARE
 Uses monte carlo simulation
 Shows many possible outcomes for a problem
under consideration
 It tracks many possible future scenarios,
 Its probability
 The risks associated with each different
scenarios.
 Allows the user to judge upon the risks which one
to take or which one to avoid
14
MONTE CARLO SIMULATION
A computerized mathematical technique
For quantitative analysis
For decision making
Generates all the possible outcomes
With their impact of risk
15
@RISK FLOW
CHART
16
TORNADO CHART
 Shows the spread of every parameter.
 Gives the critical parameters carrying the high potential
of uncertainty.
 The tornado spread gives the critical parameter.
17
TORNADO CHART
18
FINDINGS
 Critical parameters:
 Significant swings in the demand of steel
(Development phase)
 Decline in profit margin in the downstream
process(Development phase)
 Unforeseen ground conditions(Construction
Phase)
 Difficulty in financing project(Development
Phase)
 Delay in obtaining permission.(Development
Phase)
19
QUALITATIVE ANALYSIS
Phase Of Project Risk Involved
IISCO,Burnpu
r
JINDAL SAW
LTD,Mundra
SUNFLAG
STEEL
,Bhandara
DEVELOPMENT PHASE
DEFAULT IN MOU      
1.default in mou provisions by
government
Y    
DELAY IN LAND ACQUISITION:      
1. political interference/patronage   Y  
2.policy restriction for change in land
use pattern
Y    
PERMIT/APPROVAL RISK:      
1.delay in contractual clearances Y   Y
2.delay in project specific
orders/approvals
     
3.delay in statutory
clearance(environmental, forest, etc)
Y Y Y
4.improper feasibility report,
documentations
     
MARKET RISKS      
1.Drastic change in market.      
2.Competitors threat.      
FINANCIAL RISK      
1.project cost overrun Y    
2.project not bankable   Y  
3.failure to arrange equity in time     Y
DELAY RISKS      
1. Delay in submission of drawing Y    
2.Delay in handing over the site to
contractors
Y Y  
3. Delay in mobilizing the required
resources in time
  Y  
4. Co-ordination and managerial
     
20
Phase Of Project Risk Involved
IISCO,Burnpu
r
JINDAL SAW
LTD,Mundra
SUNFLAG
STEEL ,Bhandara
CONSTRUCTION PHASE
TECHNOLOGY RISK      
1. lack of technical feasibility.      
2. technology failure   Y  
DESIGN RISK      
1.Design changes Y Y  
2.loss due to faulty design Y    
3. Delays due to submission and
approval of design and drawing
     
4.insufficient design documentation      
DELAYS DUE TO UNBALANCED
CONTRACT
     
1. Risk is unilaterally transferred to
one side.
    Y
2.change in scope of project      
3. Delay in settlement of claim      
4.Delay in arbitration proceedings
during the execution of project.
Y    
5.Delay in settlement of rates for
extra items, additional items and
revision of rates.
     
OTHER RISKS      
1.Co-ordination and managerial
problems of the owner.
     
2.Delay in issue of drawings by the
owner in construction contracts.
Y   Y
3. Health hazards and non-
availability of medical facilities.
     
4.Political problems, riots, agitations Y Y  
5. Inter-state disputes.      
6.Delay in releasing payments leading
to cash-flow problems to the
contractors.
     
7.Local problems, obstruction by local
Y    
21
Phase Of Project Risk Involved
IISCO,Bur
npur
JINDAL SAW
LTD,Mundra
SUNFLAG
STEEL
,Bhandara
OPERATION PHASE
OPERATION RISK:      
1.Transportation risks      
2.improper estimation for
maintenance and operation
cost
Y Y  
3.Poor workmanship      
4.Poor quality      
5.Non availability of man,
material, machinery,
money
     
6.Lack of political will      
7.Breakdown Problems   Y  
 
8.Lack of management
expertise      
 
9.Non sequential supply of
equipments Y    
 
10.Non availability of spares
in stores   Y  
22
CONCLUSION
 Qualitative and Quantitative have given the same
results and hence the methodology can be validated.
 The research methodology can be taken as a
reference for further research work in Steel Plant
project or in similar researches for other
infrastructure projects.
 Most of the risks that are identified and which have
to be mitigated are from development phase .These
risks are to be taken into considerations for future
steel plant projects
23
THANK YOU.
24

More Related Content

What's hot

Risk assessment techniques a critical success factor
Risk assessment techniques a critical success factorRisk assessment techniques a critical success factor
Risk assessment techniques a critical success factorPECB
 
Basic Risk Identification Techniques
Basic Risk Identification TechniquesBasic Risk Identification Techniques
Basic Risk Identification TechniquesRicardo Viana Vargas
 
Safety for Water Treatment Plant Facilities
Safety for Water Treatment Plant FacilitiesSafety for Water Treatment Plant Facilities
Safety for Water Treatment Plant FacilitiesDavid Horowitz
 
Counter Disaster Planning, Response And Recovery
Counter  Disaster  Planning, Response And RecoveryCounter  Disaster  Planning, Response And Recovery
Counter Disaster Planning, Response And RecoveryFe Angela Verzosa
 
Risk Management and Risk Transfer
Risk Management and Risk TransferRisk Management and Risk Transfer
Risk Management and Risk TransferCBIZ, Inc.
 
Risk management
Risk managementRisk management
Risk managementMECandPMV
 
Bow Tie Risk Analysis
Bow Tie Risk AnalysisBow Tie Risk Analysis
Bow Tie Risk AnalysisJohn Kingsley
 
Industrial Safety Training by Author Stream
Industrial Safety Training by Author StreamIndustrial Safety Training by Author Stream
Industrial Safety Training by Author StreamAtlantic Training, LLC.
 
Lecture 03 Software Risk Management
Lecture 03 Software Risk ManagementLecture 03 Software Risk Management
Lecture 03 Software Risk ManagementAchmad Solichin
 
BIA - Example of Business Impact Analysis and Dependencies
BIA - Example of Business Impact Analysis and DependenciesBIA - Example of Business Impact Analysis and Dependencies
BIA - Example of Business Impact Analysis and DependenciesRamiro Cid
 
Fundamentals of Environmental Health and Safety
Fundamentals of Environmental Health and SafetyFundamentals of Environmental Health and Safety
Fundamentals of Environmental Health and SafetyGAURAV. H .TANDON
 
Quantitative Project Risk Analysis
Quantitative Project Risk AnalysisQuantitative Project Risk Analysis
Quantitative Project Risk AnalysisIntaver Insititute
 
Bcm Framework PowerPoint Presentation Slides
Bcm Framework PowerPoint Presentation SlidesBcm Framework PowerPoint Presentation Slides
Bcm Framework PowerPoint Presentation SlidesSlideTeam
 
The business case for process safety final ppt
The business case for process safety final pptThe business case for process safety final ppt
The business case for process safety final pptorosghe
 

What's hot (20)

Risk assessment techniques a critical success factor
Risk assessment techniques a critical success factorRisk assessment techniques a critical success factor
Risk assessment techniques a critical success factor
 
Basic Risk Identification Techniques
Basic Risk Identification TechniquesBasic Risk Identification Techniques
Basic Risk Identification Techniques
 
Natural Hazards - Flood Response Planning
Natural Hazards -  Flood Response PlanningNatural Hazards -  Flood Response Planning
Natural Hazards - Flood Response Planning
 
Safety for Water Treatment Plant Facilities
Safety for Water Treatment Plant FacilitiesSafety for Water Treatment Plant Facilities
Safety for Water Treatment Plant Facilities
 
Risk analysis
Risk analysis  Risk analysis
Risk analysis
 
Counter Disaster Planning, Response And Recovery
Counter  Disaster  Planning, Response And RecoveryCounter  Disaster  Planning, Response And Recovery
Counter Disaster Planning, Response And Recovery
 
How to Develop a Business Case
How to Develop a Business CaseHow to Develop a Business Case
How to Develop a Business Case
 
Resilience and vulnerability
Resilience and vulnerabilityResilience and vulnerability
Resilience and vulnerability
 
Risk Management and Risk Transfer
Risk Management and Risk TransferRisk Management and Risk Transfer
Risk Management and Risk Transfer
 
Risk management
Risk managementRisk management
Risk management
 
Bow Tie Risk Analysis
Bow Tie Risk AnalysisBow Tie Risk Analysis
Bow Tie Risk Analysis
 
Industrial Safety Training by Author Stream
Industrial Safety Training by Author StreamIndustrial Safety Training by Author Stream
Industrial Safety Training by Author Stream
 
Lecture 03 Software Risk Management
Lecture 03 Software Risk ManagementLecture 03 Software Risk Management
Lecture 03 Software Risk Management
 
BIA - Example of Business Impact Analysis and Dependencies
BIA - Example of Business Impact Analysis and DependenciesBIA - Example of Business Impact Analysis and Dependencies
BIA - Example of Business Impact Analysis and Dependencies
 
Fundamentals of Environmental Health and Safety
Fundamentals of Environmental Health and SafetyFundamentals of Environmental Health and Safety
Fundamentals of Environmental Health and Safety
 
FMEA Presentation
FMEA PresentationFMEA Presentation
FMEA Presentation
 
Haad safety in heat program
Haad safety in heat programHaad safety in heat program
Haad safety in heat program
 
Quantitative Project Risk Analysis
Quantitative Project Risk AnalysisQuantitative Project Risk Analysis
Quantitative Project Risk Analysis
 
Bcm Framework PowerPoint Presentation Slides
Bcm Framework PowerPoint Presentation SlidesBcm Framework PowerPoint Presentation Slides
Bcm Framework PowerPoint Presentation Slides
 
The business case for process safety final ppt
The business case for process safety final pptThe business case for process safety final ppt
The business case for process safety final ppt
 

Viewers also liked

Summer Internship Presentation
Summer Internship PresentationSummer Internship Presentation
Summer Internship PresentationPiyush Verma
 
BHP-RISK ASSESSMENT - DALF R1
BHP-RISK ASSESSMENT - DALF R1BHP-RISK ASSESSMENT - DALF R1
BHP-RISK ASSESSMENT - DALF R1Dennis J Morgan
 
Risk Assessment and Method Statement for Installation of Boardwalk in Dublin ...
Risk Assessment and Method Statement for Installation of Boardwalk in Dublin ...Risk Assessment and Method Statement for Installation of Boardwalk in Dublin ...
Risk Assessment and Method Statement for Installation of Boardwalk in Dublin ...pierdole
 
Blast furnace presentation
Blast furnace presentation Blast furnace presentation
Blast furnace presentation Muzzamil Eatoo
 
Fmc close out repot hse dept. rev.000
Fmc close out repot hse dept. rev.000Fmc close out repot hse dept. rev.000
Fmc close out repot hse dept. rev.000Fitri Ifony
 
Operational Risk Management
Operational Risk ManagementOperational Risk Management
Operational Risk Managementarsqureshi
 
Risk assessment for blast furnace using fmea
Risk assessment for blast furnace using fmeaRisk assessment for blast furnace using fmea
Risk assessment for blast furnace using fmeaeSAT Publishing House
 
Manufacturing of steel
Manufacturing of steelManufacturing of steel
Manufacturing of steelCholan PK
 

Viewers also liked (10)

Risk Assessment
Risk Assessment Risk Assessment
Risk Assessment
 
Summer Internship Presentation
Summer Internship PresentationSummer Internship Presentation
Summer Internship Presentation
 
BHP-RISK ASSESSMENT - DALF R1
BHP-RISK ASSESSMENT - DALF R1BHP-RISK ASSESSMENT - DALF R1
BHP-RISK ASSESSMENT - DALF R1
 
Risk Assessment and Method Statement for Installation of Boardwalk in Dublin ...
Risk Assessment and Method Statement for Installation of Boardwalk in Dublin ...Risk Assessment and Method Statement for Installation of Boardwalk in Dublin ...
Risk Assessment and Method Statement for Installation of Boardwalk in Dublin ...
 
Nebosh unit ic questions matrix - ans
Nebosh unit ic questions matrix - ansNebosh unit ic questions matrix - ans
Nebosh unit ic questions matrix - ans
 
Blast furnace presentation
Blast furnace presentation Blast furnace presentation
Blast furnace presentation
 
Fmc close out repot hse dept. rev.000
Fmc close out repot hse dept. rev.000Fmc close out repot hse dept. rev.000
Fmc close out repot hse dept. rev.000
 
Operational Risk Management
Operational Risk ManagementOperational Risk Management
Operational Risk Management
 
Risk assessment for blast furnace using fmea
Risk assessment for blast furnace using fmeaRisk assessment for blast furnace using fmea
Risk assessment for blast furnace using fmea
 
Manufacturing of steel
Manufacturing of steelManufacturing of steel
Manufacturing of steel
 

Similar to “Study in Risk Management of Steel Plant Projects”

Excelsior presentation
Excelsior presentationExcelsior presentation
Excelsior presentationShawn Westcott
 
The significant Causes and effects of delays in Ghadir 2206 residential project
The significant Causes and effects of delays in Ghadir 2206 residential projectThe significant Causes and effects of delays in Ghadir 2206 residential project
The significant Causes and effects of delays in Ghadir 2206 residential projectIOSR Journals
 
Capacity Expansion Banes in Indian Steel Industry
Capacity Expansion Banes in Indian Steel IndustryCapacity Expansion Banes in Indian Steel Industry
Capacity Expansion Banes in Indian Steel IndustryDr. Amarjeet Singh
 
Causes of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge GirdersCauses of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge GirdersIOSR Journals
 
Causes of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge GirdersCauses of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge GirdersIOSR Journals
 
Causes of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge GirdersCauses of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge GirdersIOSR Journals
 
causes and implication of delay in construction
causes and implication of delay in constructioncauses and implication of delay in construction
causes and implication of delay in constructionsudinak
 
CRU World Copper Conference 2017
CRU World Copper Conference 2017CRU World Copper Conference 2017
CRU World Copper Conference 2017TeckResourcesLtd
 
Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...
Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...
Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...iosrjce
 
CSCM Causes of project delay
CSCM Causes of project delayCSCM Causes of project delay
CSCM Causes of project delayEst
 
Factor Affecting Construction Cost and Time in road project
Factor Affecting Construction Cost and Time in road projectFactor Affecting Construction Cost and Time in road project
Factor Affecting Construction Cost and Time in road projectIRJET Journal
 
A Critical Literature Review On Main Cause Of Delay In Construction Projects
A Critical Literature Review On Main Cause Of Delay In Construction ProjectsA Critical Literature Review On Main Cause Of Delay In Construction Projects
A Critical Literature Review On Main Cause Of Delay In Construction ProjectsRick Vogel
 
IRJET-A Critical Literature Review on Main Cause of Delay in Construction Pro...
IRJET-A Critical Literature Review on Main Cause of Delay in Construction Pro...IRJET-A Critical Literature Review on Main Cause of Delay in Construction Pro...
IRJET-A Critical Literature Review on Main Cause of Delay in Construction Pro...IRJET Journal
 
Strategic Resources - Corporate Presentation December 2023
Strategic Resources - Corporate Presentation December 2023Strategic Resources - Corporate Presentation December 2023
Strategic Resources - Corporate Presentation December 2023AdnetNew
 
Strategic Resources - Corporate Presentation October 2023
Strategic Resources - Corporate Presentation October 2023Strategic Resources - Corporate Presentation October 2023
Strategic Resources - Corporate Presentation October 2023Adnet Communications
 
Identification of Project Risks & Risk Breakdown Structure In Manufacture of ...
Identification of Project Risks & Risk Breakdown Structure In Manufacture of ...Identification of Project Risks & Risk Breakdown Structure In Manufacture of ...
Identification of Project Risks & Risk Breakdown Structure In Manufacture of ...IJERA Editor
 

Similar to “Study in Risk Management of Steel Plant Projects” (20)

Excelsior presentation
Excelsior presentationExcelsior presentation
Excelsior presentation
 
The significant Causes and effects of delays in Ghadir 2206 residential project
The significant Causes and effects of delays in Ghadir 2206 residential projectThe significant Causes and effects of delays in Ghadir 2206 residential project
The significant Causes and effects of delays in Ghadir 2206 residential project
 
Capacity Expansion Banes in Indian Steel Industry
Capacity Expansion Banes in Indian Steel IndustryCapacity Expansion Banes in Indian Steel Industry
Capacity Expansion Banes in Indian Steel Industry
 
Causes of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge GirdersCauses of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge Girders
 
Causes of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge GirdersCauses of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge Girders
 
Causes of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge GirdersCauses of Delay in Construction of Bridge Girders
Causes of Delay in Construction of Bridge Girders
 
B012140812
B012140812B012140812
B012140812
 
causes and implication of delay in construction
causes and implication of delay in constructioncauses and implication of delay in construction
causes and implication of delay in construction
 
CRU World Copper Conference 2017
CRU World Copper Conference 2017CRU World Copper Conference 2017
CRU World Copper Conference 2017
 
Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...
Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...
Delay Analysis of Projects and Effects of Delays in the Mining/Manufacturing ...
 
I012646171
I012646171I012646171
I012646171
 
I012646171
I012646171I012646171
I012646171
 
CSCM Causes of project delay
CSCM Causes of project delayCSCM Causes of project delay
CSCM Causes of project delay
 
Factor Affecting Construction Cost and Time in road project
Factor Affecting Construction Cost and Time in road projectFactor Affecting Construction Cost and Time in road project
Factor Affecting Construction Cost and Time in road project
 
A Critical Literature Review On Main Cause Of Delay In Construction Projects
A Critical Literature Review On Main Cause Of Delay In Construction ProjectsA Critical Literature Review On Main Cause Of Delay In Construction Projects
A Critical Literature Review On Main Cause Of Delay In Construction Projects
 
IRJET-A Critical Literature Review on Main Cause of Delay in Construction Pro...
IRJET-A Critical Literature Review on Main Cause of Delay in Construction Pro...IRJET-A Critical Literature Review on Main Cause of Delay in Construction Pro...
IRJET-A Critical Literature Review on Main Cause of Delay in Construction Pro...
 
Strategic Resources - Corporate Presentation December 2023
Strategic Resources - Corporate Presentation December 2023Strategic Resources - Corporate Presentation December 2023
Strategic Resources - Corporate Presentation December 2023
 
Rubicon Minerals 2018 Fact Sheet
Rubicon Minerals 2018 Fact SheetRubicon Minerals 2018 Fact Sheet
Rubicon Minerals 2018 Fact Sheet
 
Strategic Resources - Corporate Presentation October 2023
Strategic Resources - Corporate Presentation October 2023Strategic Resources - Corporate Presentation October 2023
Strategic Resources - Corporate Presentation October 2023
 
Identification of Project Risks & Risk Breakdown Structure In Manufacture of ...
Identification of Project Risks & Risk Breakdown Structure In Manufacture of ...Identification of Project Risks & Risk Breakdown Structure In Manufacture of ...
Identification of Project Risks & Risk Breakdown Structure In Manufacture of ...
 

Recently uploaded

Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxbritheesh05
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx959SahilShah
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...VICTOR MAESTRE RAMIREZ
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learningmisbanausheenparvam
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girlsssuser7cb4ff
 
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2RajaP95
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile servicerehmti665
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineeringmalavadedarshan25
 
Introduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxIntroduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxvipinkmenon1
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLDeelipZope
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxDeepakSakkari2
 

Recently uploaded (20)

Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptx
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learning
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girls
 
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Serviceyoung call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineering
 
Introduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxIntroduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptx
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
Current Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCLCurrent Transformer Drawing and GTP for MSETCL
Current Transformer Drawing and GTP for MSETCL
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptx
 

“Study in Risk Management of Steel Plant Projects”

  • 1. 1
  • 2. STUDY IN RISK MANAGEMENT OF STEEL PLANT PROJECTS PRESENTED BY :- DILPREET SINGH NICMAR PEM-9 (2013-15) 2
  • 3. OVERVIEW  INTRODUCTION  REVIEW OF LITERATURE  RESEARCH METHODOLOGY METHOD - I (Quantitative Analysis) METHOD - II (Qualitative Analysis)  FINDINGS FROM METHOD I & II  CONCLUSION  LIMITATIONS  REFERENCES 3
  • 4. INTRODUCTION  The Steel industry is being faced by myriad challenges such as volatility, shifting demand centers, complex supply chains, productivity and cost efficiency.  It incorporates different phases of steel plant projects such as Development phase, Execution phase and Operation phase.  The scope of study includes qualitative and quantitative analysis which helps in consolidating decision making under uncertainty. 4
  • 5. 5
  • 6. S.No. Company Location State Current approximate Capacity* 1 Steel Authority of India Limited IISCO, Burnpur West Bengal 0.5 2 Steel Authority of India Limited Bokaro Jharkhand 4.36 3 Steel Authority of India Limited Bhilai Chhattisgarh 3.93 4 Steel Authority of India Limited Rourkela Orissa 1.9 5 Steel Authority of India Limited Durgapur West Bengal 1.8 6 RashtriyaIspat Nigam Limited Visakhapatanam Andhra Aradesh 2.9 7 Tata Steel Limited Jamshedpur Jharkhand 6.8 8 Essar Steel Limited Hazira Gujarat 4.6 9 JSW Steel Limited Vijayanagar Karnataka 6.6 10 Jindal Steel & Power Limited Raigarh Chhattisgarh 2.4 11 Ispat Industries Limited Dolvi Maharastra 3 12 Bhushan Power & Steel Limited Jharsugda Orissa 1.2 13 Bhushan Steel Limited Angul-Dhenkanal Orissa 1.56 NUMBERS OF STEEL PLANT IN INDIA WITH THEIR CAPACITY SOURCE: http://pib.nic.in/newsite/erelease.aspx?relid=77494
  • 7. OBJECTIVES  To study the risks involved in Steel Plant Project and to identify the benefits of application of the risk management.  To identify the principles of Risk Management.  To find the most critical risks which were quantified with the help of @RISK software and as per the tornedo chart the results are interpreted. .  To assess and mitigate the risk involved in Steel Plant Projects and arriving at a conclusion 7
  • 8. REVIEW OF LITERATURE  Steel demand and production outlook for indian steel.  Steel consumption scenarios.  Global outlook for Steel. 8
  • 10. QUANTITATIVE ANALYSIS  Questionnaire  Risk Rating  Responses  Tornado Graph  Interpretation  Identification of critical risks  Mitigation Plans 10
  • 11. VARIABLES 11   Development Phase 1 Significant swings in the demand for steel. 2 Decline in Profit Margin in downstream processing. 3 Difficulties in financing project. 4 Unrealistic contract duration. 5 Scarcity of raw materials. 6 Market risk. 7 Political risk. 8 Delay in land acquisition. 9 Delay in obtaining permissions. 10 Energy Scarcity Risks. 11 Risk of Exchange Rate Fluctuations 12 Business Competition Risk.
  • 12. CONTINUED…..   Construction Phase 13 Lack of decision making involving all project teams. 14 Unforeseen ground conditions. 15 Change in soil condition. 16 Lack of technical feasibility. 17 Changes in rules & regulations. 18 Severe weather conditions. 19 Safety Risk. 20 Non-availability of utilities on site. 21 Lack of effeicient technology. 22 Inadequate code provision. 23 Delay in payments by owner. 24 Delay in supply of equipments 25 Lack of information available. 26 Non-availability of utilities on site. 27 Failure of construction equipment. 28 Interrupted cash flow. 12
  • 13. CONTINUED…..   Operation Phase 29 Fuel supply risk. 30 Improper estimation for maintenance&operationcost. 31 Overproduction of steel. 32 Incorrect manufacturing processes. 33 Ineffecient quality standards. 34 Inadequate safety measures. 35 Ineffeciency of subcontractor company. 13
  • 14. WHY @RISK SOFTWARE  Uses monte carlo simulation  Shows many possible outcomes for a problem under consideration  It tracks many possible future scenarios,  Its probability  The risks associated with each different scenarios.  Allows the user to judge upon the risks which one to take or which one to avoid 14
  • 15. MONTE CARLO SIMULATION A computerized mathematical technique For quantitative analysis For decision making Generates all the possible outcomes With their impact of risk 15
  • 17. TORNADO CHART  Shows the spread of every parameter.  Gives the critical parameters carrying the high potential of uncertainty.  The tornado spread gives the critical parameter. 17
  • 19. FINDINGS  Critical parameters:  Significant swings in the demand of steel (Development phase)  Decline in profit margin in the downstream process(Development phase)  Unforeseen ground conditions(Construction Phase)  Difficulty in financing project(Development Phase)  Delay in obtaining permission.(Development Phase) 19
  • 20. QUALITATIVE ANALYSIS Phase Of Project Risk Involved IISCO,Burnpu r JINDAL SAW LTD,Mundra SUNFLAG STEEL ,Bhandara DEVELOPMENT PHASE DEFAULT IN MOU       1.default in mou provisions by government Y     DELAY IN LAND ACQUISITION:       1. political interference/patronage   Y   2.policy restriction for change in land use pattern Y     PERMIT/APPROVAL RISK:       1.delay in contractual clearances Y   Y 2.delay in project specific orders/approvals       3.delay in statutory clearance(environmental, forest, etc) Y Y Y 4.improper feasibility report, documentations       MARKET RISKS       1.Drastic change in market.       2.Competitors threat.       FINANCIAL RISK       1.project cost overrun Y     2.project not bankable   Y   3.failure to arrange equity in time     Y DELAY RISKS       1. Delay in submission of drawing Y     2.Delay in handing over the site to contractors Y Y   3. Delay in mobilizing the required resources in time   Y   4. Co-ordination and managerial       20
  • 21. Phase Of Project Risk Involved IISCO,Burnpu r JINDAL SAW LTD,Mundra SUNFLAG STEEL ,Bhandara CONSTRUCTION PHASE TECHNOLOGY RISK       1. lack of technical feasibility.       2. technology failure   Y   DESIGN RISK       1.Design changes Y Y   2.loss due to faulty design Y     3. Delays due to submission and approval of design and drawing       4.insufficient design documentation       DELAYS DUE TO UNBALANCED CONTRACT       1. Risk is unilaterally transferred to one side.     Y 2.change in scope of project       3. Delay in settlement of claim       4.Delay in arbitration proceedings during the execution of project. Y     5.Delay in settlement of rates for extra items, additional items and revision of rates.       OTHER RISKS       1.Co-ordination and managerial problems of the owner.       2.Delay in issue of drawings by the owner in construction contracts. Y   Y 3. Health hazards and non- availability of medical facilities.       4.Political problems, riots, agitations Y Y   5. Inter-state disputes.       6.Delay in releasing payments leading to cash-flow problems to the contractors.       7.Local problems, obstruction by local Y     21
  • 22. Phase Of Project Risk Involved IISCO,Bur npur JINDAL SAW LTD,Mundra SUNFLAG STEEL ,Bhandara OPERATION PHASE OPERATION RISK:       1.Transportation risks       2.improper estimation for maintenance and operation cost Y Y   3.Poor workmanship       4.Poor quality       5.Non availability of man, material, machinery, money       6.Lack of political will       7.Breakdown Problems   Y     8.Lack of management expertise         9.Non sequential supply of equipments Y       10.Non availability of spares in stores   Y   22
  • 23. CONCLUSION  Qualitative and Quantitative have given the same results and hence the methodology can be validated.  The research methodology can be taken as a reference for further research work in Steel Plant project or in similar researches for other infrastructure projects.  Most of the risks that are identified and which have to be mitigated are from development phase .These risks are to be taken into considerations for future steel plant projects 23