TOWER CRANES
TOPICS INTRODUCTION TYPES OF CRANES DIFFERENT COMPONENTS OF CRANE ERECTION PROCEDURE UTILITY TO PROJECT / SITE DISADVANTAGES  STATISTICAL ANALYSIS CONCLUSION & CONSENSUS
What Are Tower Cranes? A  crane  is a tower or derrick equipped with cables and pulleys that is used to lift and lower materials. Ancient Crane Mobile Crane Telescopic Crane Tower Crane Loader Crane Stacker Crane Gantry Crane Overhead Crane
Tower Cranes Fixed to the ground  Horizontal boom is balanced asymmetrically  Short arm carries a counterweight of concrete blocks  Long arm carries the lifting gear
 
 
 
 
 
 
 
 
 
 
The Base
Mast / Fixed Tower
Swing Ring
Boom Counter Weight
Erection of Boom
The Operator’s Cabin
Load Carried by the Boom  Tower Crane at the Site:   Maximum unsupported height  - 141 feet (43 meters)  Maximum reach  - 164 feet (50 meters)  Maximum lifting power  – 6.61 tons (6 metric tons),  Counterweights  – 17.6 tons (16 metric tons)   Sr. No. Distance from the Mast ( in meters) Load Carrying Capacity  ( in Metric Tonnes) 1 10m 6 2 20m 4 3 30m 3 4 40m 2
 
TIME SAVING MACHINE MULTIPURPOSE IN USE HEAVY DUTY HIGH PERFORMANCE EASE EVEN IN CRITICAL SITUATION CAN BE TRANSFERRED FROM ONE PROJECT TO ANOTHER WHEN IDLE , NO OVERHEADS OPTIMUM UTILISATION OF RESOURCES UTILITY TO PROJECT
DISADVANTAGES CUMBERSOME TO ERECT & DISMANTLE. HIGH INITIAL COST FOR ERECTION AS WELL AS DISMANTLING. SKILLED OPERATORS ARE REQUIRED. IF IN DEFECTIVE SESSION , HAMPERS THE SCHEDULE. MAINTANANCE IS DIFFICULT.  SOMETIMES CREATE SAFETY PROBLEMS. LIMITED TO PROJECTS WITH LARGE AREAS.
STATISTICAL ANALYSIS Sr. No. PARTICULARS WITH CRANE WITH LIFTS 1 CONCRETING @ 7000 Sq.ft  10 Hr 25 Hr 2 LABOURS REQUIRED FOR  15-25 45-60 3 QUANTITY OF CONCRETE  6 Bag 1 Bag 4 R/F SHIFTING WITHIN SITE 1-1.5 Hr 8-10 Hr 5 ERECTION - DISMANTLING COST 1,00,000 25,000 6 ½ YEARLY MAINTAINANCE COST 30,000 5,000 7 WASTAGE OF CONCRETE 0.25 % 3%
Thank You . . .

Tower crane Basics

  • 1.
  • 2.
    TOPICS INTRODUCTION TYPESOF CRANES DIFFERENT COMPONENTS OF CRANE ERECTION PROCEDURE UTILITY TO PROJECT / SITE DISADVANTAGES STATISTICAL ANALYSIS CONCLUSION & CONSENSUS
  • 3.
    What Are TowerCranes? A crane is a tower or derrick equipped with cables and pulleys that is used to lift and lower materials. Ancient Crane Mobile Crane Telescopic Crane Tower Crane Loader Crane Stacker Crane Gantry Crane Overhead Crane
  • 4.
    Tower Cranes Fixedto the ground Horizontal boom is balanced asymmetrically Short arm carries a counterweight of concrete blocks Long arm carries the lifting gear
  • 5.
  • 6.
  • 7.
  • 8.
  • 9.
  • 10.
  • 11.
  • 12.
  • 13.
  • 14.
  • 15.
  • 16.
  • 17.
  • 18.
  • 19.
  • 20.
  • 21.
    Load Carried bythe Boom Tower Crane at the Site: Maximum unsupported height - 141 feet (43 meters) Maximum reach - 164 feet (50 meters) Maximum lifting power – 6.61 tons (6 metric tons), Counterweights – 17.6 tons (16 metric tons) Sr. No. Distance from the Mast ( in meters) Load Carrying Capacity ( in Metric Tonnes) 1 10m 6 2 20m 4 3 30m 3 4 40m 2
  • 22.
  • 23.
    TIME SAVING MACHINEMULTIPURPOSE IN USE HEAVY DUTY HIGH PERFORMANCE EASE EVEN IN CRITICAL SITUATION CAN BE TRANSFERRED FROM ONE PROJECT TO ANOTHER WHEN IDLE , NO OVERHEADS OPTIMUM UTILISATION OF RESOURCES UTILITY TO PROJECT
  • 24.
    DISADVANTAGES CUMBERSOME TOERECT & DISMANTLE. HIGH INITIAL COST FOR ERECTION AS WELL AS DISMANTLING. SKILLED OPERATORS ARE REQUIRED. IF IN DEFECTIVE SESSION , HAMPERS THE SCHEDULE. MAINTANANCE IS DIFFICULT. SOMETIMES CREATE SAFETY PROBLEMS. LIMITED TO PROJECTS WITH LARGE AREAS.
  • 25.
    STATISTICAL ANALYSIS Sr.No. PARTICULARS WITH CRANE WITH LIFTS 1 CONCRETING @ 7000 Sq.ft 10 Hr 25 Hr 2 LABOURS REQUIRED FOR 15-25 45-60 3 QUANTITY OF CONCRETE 6 Bag 1 Bag 4 R/F SHIFTING WITHIN SITE 1-1.5 Hr 8-10 Hr 5 ERECTION - DISMANTLING COST 1,00,000 25,000 6 ½ YEARLY MAINTAINANCE COST 30,000 5,000 7 WASTAGE OF CONCRETE 0.25 % 3%
  • 26.