SlideShare a Scribd company logo
Integration of solar generation for reduction
of Auxiliary Power Consumption (APC) in
Thermal Power plant
M. G. Morshad , ADGM / Electrical
TPS II ( 7 x 210MW) NLC India Ltd
Auxiliary Power Consumption (APC)
Auxiliary Power Consumption
(APC)
The MW power required to operate
the auxiliary equipment of the plant
Unit Auxiliary Consumption
(UAC)
The power drawn from own
generation for operating its
own loads (the auxiliary
equipment of Boiler , Turbine ,
Generator)
Station Auxiliary Consumption
(SAC)
The power drawn from Grid
for operating the common and
emergency loads of the plant
(Lighting, AC & Vent, Coal
Handling Plant etc.
Auxiliary Power Consumption
(Station consumption + Unit Consumption )
% Auxiliary consumption = x 100
(Total Generation )
Export in
MU/day
Import in
MU / Day
Unit Auxiliary
Consumption
in MU / Day
Parameters Formula MW Percentage
Total Generation G 1370 100.00 %
Unit Auxiliary consumption UAC 112 8.18%
Station Auxilary Consumption SAC 17 1.24%
Auxiliary Power Consumption APC = UAC + SAC 129 9.42%
Typical Auxiliary Power Consumption in any
thermal power plant
91%
8%
1%
Genertion & APC
Generation
UAC
SAC
Impact of APC on thermal power plant
 APC of any Coal & Lignite base thermal power plant varies
from 5 % to 10% depending upon capacity of the plant ,
Technology used and Fuel quality .
 APC gets further increased for complying with statuary
environmental norms for handling dry ash, emission of SOx,
NOx, SPM and effluent .
 As tariff increases with APC, selling out of energy to grid
through power treading becomes highly competitive with
higher APC.
 Energy feed to the bus (Total Generation – APC) decreases
with higher APC causing revenue loss.
Parameters Station Solar
Load MW 17 10
Capacity Utilization Factor (CUF) 100% 18%
Average load (MW) 17.00 1.80
Reduced load with solar generation (MW) 15.20 ***
Existing
With solar
generation
Parameters Formula MW Percentage MW Percentage
Generation MW 1370 100% 1370 100%
Unit Auxiliary consumption UAPC 112 8.18% 112 8.18%
Station Auxilary Consumption ASAPC 17 1.24% 15.2 1.11%
Total Auxilary consumption
APC = (UAPC +
SAPC)
129 9.42% 127.2 9.28%
Impact of integration of solar generation
Investment for solar plant as per CERC guideline
Investment required = Rs 5.01 Crore / MW
Capital cost Parameters Cr/MW 10 MW
PV Modules 3.10 31.019
Land Cost 0.25 0
Civil and General Works 0.35 0
Mounting Structures 0.35 1
Power Conditioning Unit 0.30 3
Evacuation Cost up to Interconnection Point (Cables and
Transformers)
0.40 4
Preliminary and Pre-Operative Expenses including Contingency 0.26 1
Total capital cost 5.01 40.02
Annual interest @ 10% *** 4.00
Annual depriciation @ 5.58% *** 2.23
Total Project cost *** 46.25
Annual cost @ 15 Years life *** 3.08
Investment for setting up 10 MW solar plant
inside thermal power plant
Parameters Formula Existing With solar
Gross Heat rate (Kcal/Kwhr) GHR 2845 2845
% APC %APC 9.42% 9.28%
Net Heat rate (Kcal/Kwhr) NHR = GHR /(1-% APC) 3140.73 3136.18
Annual generation (MU) MU = 1470X24x365x0.85 10945.62 10945.62
GCV Lignite Kcal/Kg) GCV 2650 2650
Lignite consumption (Ton) LC = HR x MUX1000/GCV 12972555.85 12953767.15
Lignite purchse cost (Rs/Ton) CP 2350 2350
Lignite consumption cost (Crore) LCC = LC x CP / 10000000 3,048.55 3,044.14
Annual Lignite Cost saving (Crore) LCC (Before - After) *** 4.42
Annual fuel saving due to integration of solar
generation
Annual generation (MU) MU = 1470X24x365x0.85 10945.62
Net Heat rate Before (Kcal/Kwhr) NHR 1 3140.73
Net Heat rate After (Kcal/Kwhr) NHR 2 3136.18
Energy Saving Certificate (Nos) ESC = (NHR 1-NHR2)X MU/10 4980.26
Cost per certificate (Rs) C 10000
Total cost (Crore) TC 4.98
Annual incentive (Crore) TC/3 1.66
Annual incentive in the form of Energy saving
certificate under PAT scheme
Parameters
Measuring
Units
Formula Norms Present
With Solar
Generation
Gross station heat rate Kcal/Kwhr GHR 2900 2845 2845
Specific fuel oil consumption ml/Kwhr SFC 2 2 2
Calorific value - Secondary fuel Kcal / ml CVSF 10 10 10
Landed price - Primary fuel Rs / Kg LPPF 2.35 2.35 2.35
Calorific value - Promary fuel Kcal / kg CVPF 2950 2950 2950
Auxiliary Power Consumption % AUX 10 9.42 9.28
Energy Charge rate (EC) Rs / Kwhr
EC = [(GHR - SFC X CVSF) X
LPPF/CVPF]X 100/(100-AUX)
2.563 2.499 2.495
Capacity Charges Rs / Kwhr CC 0.852 0.852 0.852
Energy Charges Rs / Kwhr EC 2.56 2.50 2.49
Tariff Rs / Kwhr CC + EC 3.415 3.351 3.347
Tariff reduction due to integration of solar
generation
Land availability for erection of solar panels
Thermal Solar Unit
Specific land requirement 0.3 7 Acre / MW
Plant Capacity 1470 10 MW
Total land requirement 441 70 Acre
Availability of land in thermal power plant Percentage Acre
Water reservoir 10% 44.1
Building area 2% 8.82
Coal handling area 8% 35.28
Total area available for erection of solar panel 88.2
1. Roof top solar panels are to be mounted over all the
building available inside the plant premises
 Advantages –
 Reduce room temperature that lead to reduce power
consumption for AC & Ventilation system.
2. Floating type solar panels are to be arranged for water
reservoir.
 Advantages –
 Reduce evaporation loss of circulating water from lake that
leads to reduction in water consumption.
 Reduce CW temp during summer which can avoid load
reduction due high CW temp .
Mounting of solar panels
TG Hall
(Roof Top)
CW Pump
House
(Roof
Top)
Lake ( Floating Type)
AO Building
(Roof Top)
Canteen
(Roof Top)
ADPH
Stage I
(Roof
Top)
ADPH
Stage II
(Roof
Top)
Inverter
Arrangement of panels and evacuation of power
Energy
Meter
To
Township
Inverter
11KV Ring main Grid
Solar panels
String
combined Box
DC to AC
Inverter
Solar panels
String
combined Box
DC to AC
Inverter
HT Switcher
Gear
380/11KV
11KV Ring main Grid
System Arrangement
Advantages
1. Fuel cost saving
2. Pumping of more energy to grid due to lower APC which can
fetch additional revenue
3. Earning Energy saving certificate under PAT scheme due to
reduction in Net Heat rate
4. Evacuation of excess generation through power treading
becomes less competitive due to lower tariff
5. No erection of separate switchyard .
6. No additional establishment cost
7. Excess solar generation can be pumped to Township grid
8. Floating panels over lake will reduce the CW temp during
summer and therefore load reduction due to poor condenser
vacuum can be avoided.
9. Roof top panels will reduce the room temperature that lead to
reduce AC & Ventilation consumption.
Points to be taken into consideration for implement
this project.
1. Water sprinkler system to be installed to keep the panels free
from dry ash deposition and increasing efficiency of the PV
cell due to cooling
2. About 200KW is required to operate water sprinkler system
3. Raw water consumption will be increased
4. Investment should be under the head of energy conservation
not as capital investment for asset
Thank You

More Related Content

What's hot

Study Of LANCO 2*600 MW Udupi Thermal Power Plant
Study Of LANCO 2*600 MW Udupi Thermal Power PlantStudy Of LANCO 2*600 MW Udupi Thermal Power Plant
Study Of LANCO 2*600 MW Udupi Thermal Power Plant
SUDHEER KUMAR KALYANAM
 
Heat rate of thermal power plant
Heat rate of thermal power plantHeat rate of thermal power plant
Heat rate of thermal power plant
Manohar Tatwawadi
 
Unit lightup synchronisation & shutdown
Unit lightup synchronisation & shutdownUnit lightup synchronisation & shutdown
Unit lightup synchronisation & shutdown
Nitin Mahalle
 
Thermal Power plant familarisation & its Auxillaries
Thermal Power plant familarisation & its AuxillariesThermal Power plant familarisation & its Auxillaries
Thermal Power plant familarisation & its Auxillaries
Vaibhav Paydelwar
 
Heat rate audit in thermal power plant
Heat rate audit in thermal power plantHeat rate audit in thermal power plant
Heat rate audit in thermal power plant
SHIVAJI CHOUDHURY
 
Auxiliary power consumption reduction
Auxiliary power consumption reductionAuxiliary power consumption reduction
Auxiliary power consumption reduction
Amit jangra
 
THERMAL POWER PLANT EFFICIENCY AND HEAT RATE
THERMAL POWER PLANT EFFICIENCY AND HEAT RATETHERMAL POWER PLANT EFFICIENCY AND HEAT RATE
THERMAL POWER PLANT EFFICIENCY AND HEAT RATE
Manohar Tatwawadi
 
Super Critical Technology-Fundamental Concepts about Super Critical Technolog...
Super Critical Technology-Fundamental Concepts about Super Critical Technolog...Super Critical Technology-Fundamental Concepts about Super Critical Technolog...
Super Critical Technology-Fundamental Concepts about Super Critical Technolog...
Raghab Gorain
 
Basics of Diesel Generator System
Basics of Diesel Generator SystemBasics of Diesel Generator System
Basics of Diesel Generator System
prabakaran G
 
Cmc philosophy
Cmc philosophyCmc philosophy
Cmc philosophy
vikash kumar upadhyay
 
Pulverized coal fired boiler startup procedure
Pulverized coal fired boiler startup procedurePulverized coal fired boiler startup procedure
Pulverized coal fired boiler startup procedure
Ashvani Shukla
 
electrical system
electrical system electrical system
electrical system
Molla Morshad
 
super critical power plant
super critical power plantsuper critical power plant
super critical power plant
sridurga88
 
Unit protection scheme
Unit protection schemeUnit protection scheme
Unit protection scheme
SHIVAJI CHOUDHURY
 
Thermal plant instrumentation and control
Thermal plant instrumentation and controlThermal plant instrumentation and control
Thermal plant instrumentation and control
Shilpa Shukla
 
Coal mill pulverizer in thermal power plants
Coal mill pulverizer in thermal power plantsCoal mill pulverizer in thermal power plants
Coal mill pulverizer in thermal power plants
SHIVAJI CHOUDHURY
 
220 KV Switchyard general overview
220 KV Switchyard general overview220 KV Switchyard general overview
220 KV Switchyard general overview
Thien Huynh
 
Electrohydraulic governing system
Electrohydraulic governing systemElectrohydraulic governing system
Electrohydraulic governing system
Ashvani Shukla
 
Heat rate of coal fired power plant
Heat rate of coal fired power plantHeat rate of coal fired power plant
Heat rate of coal fired power plant
Dr. Koteswara Rao Pothala MBA, PMP,FIE
 
EMERSON Power plant applications
EMERSON Power plant applicationsEMERSON Power plant applications
EMERSON Power plant applications
mirfanm
 

What's hot (20)

Study Of LANCO 2*600 MW Udupi Thermal Power Plant
Study Of LANCO 2*600 MW Udupi Thermal Power PlantStudy Of LANCO 2*600 MW Udupi Thermal Power Plant
Study Of LANCO 2*600 MW Udupi Thermal Power Plant
 
Heat rate of thermal power plant
Heat rate of thermal power plantHeat rate of thermal power plant
Heat rate of thermal power plant
 
Unit lightup synchronisation & shutdown
Unit lightup synchronisation & shutdownUnit lightup synchronisation & shutdown
Unit lightup synchronisation & shutdown
 
Thermal Power plant familarisation & its Auxillaries
Thermal Power plant familarisation & its AuxillariesThermal Power plant familarisation & its Auxillaries
Thermal Power plant familarisation & its Auxillaries
 
Heat rate audit in thermal power plant
Heat rate audit in thermal power plantHeat rate audit in thermal power plant
Heat rate audit in thermal power plant
 
Auxiliary power consumption reduction
Auxiliary power consumption reductionAuxiliary power consumption reduction
Auxiliary power consumption reduction
 
THERMAL POWER PLANT EFFICIENCY AND HEAT RATE
THERMAL POWER PLANT EFFICIENCY AND HEAT RATETHERMAL POWER PLANT EFFICIENCY AND HEAT RATE
THERMAL POWER PLANT EFFICIENCY AND HEAT RATE
 
Super Critical Technology-Fundamental Concepts about Super Critical Technolog...
Super Critical Technology-Fundamental Concepts about Super Critical Technolog...Super Critical Technology-Fundamental Concepts about Super Critical Technolog...
Super Critical Technology-Fundamental Concepts about Super Critical Technolog...
 
Basics of Diesel Generator System
Basics of Diesel Generator SystemBasics of Diesel Generator System
Basics of Diesel Generator System
 
Cmc philosophy
Cmc philosophyCmc philosophy
Cmc philosophy
 
Pulverized coal fired boiler startup procedure
Pulverized coal fired boiler startup procedurePulverized coal fired boiler startup procedure
Pulverized coal fired boiler startup procedure
 
electrical system
electrical system electrical system
electrical system
 
super critical power plant
super critical power plantsuper critical power plant
super critical power plant
 
Unit protection scheme
Unit protection schemeUnit protection scheme
Unit protection scheme
 
Thermal plant instrumentation and control
Thermal plant instrumentation and controlThermal plant instrumentation and control
Thermal plant instrumentation and control
 
Coal mill pulverizer in thermal power plants
Coal mill pulverizer in thermal power plantsCoal mill pulverizer in thermal power plants
Coal mill pulverizer in thermal power plants
 
220 KV Switchyard general overview
220 KV Switchyard general overview220 KV Switchyard general overview
220 KV Switchyard general overview
 
Electrohydraulic governing system
Electrohydraulic governing systemElectrohydraulic governing system
Electrohydraulic governing system
 
Heat rate of coal fired power plant
Heat rate of coal fired power plantHeat rate of coal fired power plant
Heat rate of coal fired power plant
 
EMERSON Power plant applications
EMERSON Power plant applicationsEMERSON Power plant applications
EMERSON Power plant applications
 

Similar to Solar generation for APC

DG
DGDG
Sutherland.Malad Audit Results Electrical (Second Floor).Final.18 Mar 08
Sutherland.Malad Audit Results    Electrical (Second Floor).Final.18 Mar 08Sutherland.Malad Audit Results    Electrical (Second Floor).Final.18 Mar 08
Sutherland.Malad Audit Results Electrical (Second Floor).Final.18 Mar 08
pavang
 
Gas turbine advisors review of a 9 e.03 ccgt power plant
Gas turbine advisors review of a 9 e.03 ccgt power plant Gas turbine advisors review of a 9 e.03 ccgt power plant
Gas turbine advisors review of a 9 e.03 ccgt power plant
Gasturbineconsultants
 
Photovoltaics Case Study
Photovoltaics Case StudyPhotovoltaics Case Study
Photovoltaics Case Study
Leonardo ENERGY
 
A stand-alone, solar powered commercial bank with EV for public transport
A stand-alone, solar powered commercial bank with EV for public transportA stand-alone, solar powered commercial bank with EV for public transport
A stand-alone, solar powered commercial bank with EV for public transport
alatop007
 
17 mse014 pv syst
17 mse014 pv syst17 mse014 pv syst
17 mse014 pv syst
paneliya sagar
 
Solar Barge
Solar BargeSolar Barge
Solar Barge
lgthucabee
 
Pv Solar Grid Connect Solar Design
Pv Solar Grid Connect Solar DesignPv Solar Grid Connect Solar Design
Pv Solar Grid Connect Solar Design
Optimus Energy Philippines
 
الدكتور / علي المراكبي استشاري الهندسة الميكانيكية وخبير ترشيد الطاقة بعنوان...
 الدكتور / علي المراكبي استشاري الهندسة الميكانيكية وخبير ترشيد الطاقة بعنوان... الدكتور / علي المراكبي استشاري الهندسة الميكانيكية وخبير ترشيد الطاقة بعنوان...
الدكتور / علي المراكبي استشاري الهندسة الميكانيكية وخبير ترشيد الطاقة بعنوان...
Egyptian Engineers Association
 
EXERGOECONOMIC ANALYSIS
EXERGOECONOMIC ANALYSISEXERGOECONOMIC ANALYSIS
EXERGOECONOMIC ANALYSIS
Zin Eddine Dadach
 
Electricity Demand Side Management and End-use efficiency
Electricity Demand Side Management and End-use efficiencyElectricity Demand Side Management and End-use efficiency
Electricity Demand Side Management and End-use efficiency
eecfncci
 
Electricity Demand Side Management (DSM) and End-use Efficiency
Electricity Demand Side Management (DSM) and End-use EfficiencyElectricity Demand Side Management (DSM) and End-use Efficiency
Electricity Demand Side Management (DSM) and End-use Efficiency
eecfncci
 
EUREC-NTUA Projects - Carlos Silva
EUREC-NTUA Projects - Carlos SilvaEUREC-NTUA Projects - Carlos Silva
EUREC-NTUA Projects - Carlos Silva
Carlos Silva
 
FYP
FYPFYP
Slide 1_Arpita
Slide 1_ArpitaSlide 1_Arpita
Slide 1_Arpita
Arpita Ghosh
 
HR.pptx
HR.pptxHR.pptx
HR.pptx
vishal laddha
 
17 mse013 performance of power plant
17 mse013 performance of power plant17 mse013 performance of power plant
17 mse013 performance of power plant
paneliya sagar
 
PROPOSAL
PROPOSALPROPOSAL
Ds 090823
Ds 090823Ds 090823
Ds 090823
edozar
 
Research Internship Report
Research Internship ReportResearch Internship Report
Research Internship Report
ArpitSuthar7
 

Similar to Solar generation for APC (20)

DG
DGDG
DG
 
Sutherland.Malad Audit Results Electrical (Second Floor).Final.18 Mar 08
Sutherland.Malad Audit Results    Electrical (Second Floor).Final.18 Mar 08Sutherland.Malad Audit Results    Electrical (Second Floor).Final.18 Mar 08
Sutherland.Malad Audit Results Electrical (Second Floor).Final.18 Mar 08
 
Gas turbine advisors review of a 9 e.03 ccgt power plant
Gas turbine advisors review of a 9 e.03 ccgt power plant Gas turbine advisors review of a 9 e.03 ccgt power plant
Gas turbine advisors review of a 9 e.03 ccgt power plant
 
Photovoltaics Case Study
Photovoltaics Case StudyPhotovoltaics Case Study
Photovoltaics Case Study
 
A stand-alone, solar powered commercial bank with EV for public transport
A stand-alone, solar powered commercial bank with EV for public transportA stand-alone, solar powered commercial bank with EV for public transport
A stand-alone, solar powered commercial bank with EV for public transport
 
17 mse014 pv syst
17 mse014 pv syst17 mse014 pv syst
17 mse014 pv syst
 
Solar Barge
Solar BargeSolar Barge
Solar Barge
 
Pv Solar Grid Connect Solar Design
Pv Solar Grid Connect Solar DesignPv Solar Grid Connect Solar Design
Pv Solar Grid Connect Solar Design
 
الدكتور / علي المراكبي استشاري الهندسة الميكانيكية وخبير ترشيد الطاقة بعنوان...
 الدكتور / علي المراكبي استشاري الهندسة الميكانيكية وخبير ترشيد الطاقة بعنوان... الدكتور / علي المراكبي استشاري الهندسة الميكانيكية وخبير ترشيد الطاقة بعنوان...
الدكتور / علي المراكبي استشاري الهندسة الميكانيكية وخبير ترشيد الطاقة بعنوان...
 
EXERGOECONOMIC ANALYSIS
EXERGOECONOMIC ANALYSISEXERGOECONOMIC ANALYSIS
EXERGOECONOMIC ANALYSIS
 
Electricity Demand Side Management and End-use efficiency
Electricity Demand Side Management and End-use efficiencyElectricity Demand Side Management and End-use efficiency
Electricity Demand Side Management and End-use efficiency
 
Electricity Demand Side Management (DSM) and End-use Efficiency
Electricity Demand Side Management (DSM) and End-use EfficiencyElectricity Demand Side Management (DSM) and End-use Efficiency
Electricity Demand Side Management (DSM) and End-use Efficiency
 
EUREC-NTUA Projects - Carlos Silva
EUREC-NTUA Projects - Carlos SilvaEUREC-NTUA Projects - Carlos Silva
EUREC-NTUA Projects - Carlos Silva
 
FYP
FYPFYP
FYP
 
Slide 1_Arpita
Slide 1_ArpitaSlide 1_Arpita
Slide 1_Arpita
 
HR.pptx
HR.pptxHR.pptx
HR.pptx
 
17 mse013 performance of power plant
17 mse013 performance of power plant17 mse013 performance of power plant
17 mse013 performance of power plant
 
PROPOSAL
PROPOSALPROPOSAL
PROPOSAL
 
Ds 090823
Ds 090823Ds 090823
Ds 090823
 
Research Internship Report
Research Internship ReportResearch Internship Report
Research Internship Report
 

More from Molla Morshad

Circulating water treatment project
Circulating water treatment projectCirculating water treatment project
Circulating water treatment project
Molla Morshad
 
Condition Monitoring of electrical machine
Condition Monitoring of electrical machine Condition Monitoring of electrical machine
Condition Monitoring of electrical machine
Molla Morshad
 
Condition Monitoring of electrical machine
Condition Monitoring of electrical machine Condition Monitoring of electrical machine
Condition Monitoring of electrical machine
Molla Morshad
 
Design turbo generator
Design turbo generatorDesign turbo generator
Design turbo generator
Molla Morshad
 
Turbo generator
Turbo generator Turbo generator
Turbo generator
Molla Morshad
 
insulation monitoring in electrical machine
insulation monitoring in electrical machine insulation monitoring in electrical machine
insulation monitoring in electrical machine
Molla Morshad
 
smart grid
smart grid smart grid
smart grid
Molla Morshad
 
southern grid
southern grid southern grid
southern grid
Molla Morshad
 
Motor Bearings
Motor Bearings Motor Bearings
Motor Bearings
Molla Morshad
 
Electrical Motor
Electrical Motor Electrical Motor
Electrical Motor
Molla Morshad
 
Transformer oil analysis
Transformer oil analysisTransformer oil analysis
Transformer oil analysis
Molla Morshad
 
Transformer maintenance
Transformer maintenance Transformer maintenance
Transformer maintenance
Molla Morshad
 
ESP Rectifier transformer
ESP Rectifier transformerESP Rectifier transformer
ESP Rectifier transformer
Molla Morshad
 
Transformer Maintenance
Transformer Maintenance Transformer Maintenance
Transformer Maintenance
Molla Morshad
 
Resource
ResourceResource
Resource
Molla Morshad
 
Islamic prayer namaz
Islamic prayer namazIslamic prayer namaz
Islamic prayer namaz
Molla Morshad
 
Swachh bharat
Swachh bharatSwachh bharat
Swachh bharat
Molla Morshad
 
Basic concept of inventory management
Basic concept of inventory management Basic concept of inventory management
Basic concept of inventory management
Molla Morshad
 
Reactors
ReactorsReactors
Reactors
Molla Morshad
 
Transformer oil-specifications new
Transformer oil-specifications newTransformer oil-specifications new
Transformer oil-specifications new
Molla Morshad
 

More from Molla Morshad (20)

Circulating water treatment project
Circulating water treatment projectCirculating water treatment project
Circulating water treatment project
 
Condition Monitoring of electrical machine
Condition Monitoring of electrical machine Condition Monitoring of electrical machine
Condition Monitoring of electrical machine
 
Condition Monitoring of electrical machine
Condition Monitoring of electrical machine Condition Monitoring of electrical machine
Condition Monitoring of electrical machine
 
Design turbo generator
Design turbo generatorDesign turbo generator
Design turbo generator
 
Turbo generator
Turbo generator Turbo generator
Turbo generator
 
insulation monitoring in electrical machine
insulation monitoring in electrical machine insulation monitoring in electrical machine
insulation monitoring in electrical machine
 
smart grid
smart grid smart grid
smart grid
 
southern grid
southern grid southern grid
southern grid
 
Motor Bearings
Motor Bearings Motor Bearings
Motor Bearings
 
Electrical Motor
Electrical Motor Electrical Motor
Electrical Motor
 
Transformer oil analysis
Transformer oil analysisTransformer oil analysis
Transformer oil analysis
 
Transformer maintenance
Transformer maintenance Transformer maintenance
Transformer maintenance
 
ESP Rectifier transformer
ESP Rectifier transformerESP Rectifier transformer
ESP Rectifier transformer
 
Transformer Maintenance
Transformer Maintenance Transformer Maintenance
Transformer Maintenance
 
Resource
ResourceResource
Resource
 
Islamic prayer namaz
Islamic prayer namazIslamic prayer namaz
Islamic prayer namaz
 
Swachh bharat
Swachh bharatSwachh bharat
Swachh bharat
 
Basic concept of inventory management
Basic concept of inventory management Basic concept of inventory management
Basic concept of inventory management
 
Reactors
ReactorsReactors
Reactors
 
Transformer oil-specifications new
Transformer oil-specifications newTransformer oil-specifications new
Transformer oil-specifications new
 

Recently uploaded

Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
IJECEIAES
 
Comparative analysis between traditional aquaponics and reconstructed aquapon...
Comparative analysis between traditional aquaponics and reconstructed aquapon...Comparative analysis between traditional aquaponics and reconstructed aquapon...
Comparative analysis between traditional aquaponics and reconstructed aquapon...
bijceesjournal
 
Hematology Analyzer Machine - Complete Blood Count
Hematology Analyzer Machine - Complete Blood CountHematology Analyzer Machine - Complete Blood Count
Hematology Analyzer Machine - Complete Blood Count
shahdabdulbaset
 
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressionsKuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
Victor Morales
 
Mechanical Engineering on AAI Summer Training Report-003.pdf
Mechanical Engineering on AAI Summer Training Report-003.pdfMechanical Engineering on AAI Summer Training Report-003.pdf
Mechanical Engineering on AAI Summer Training Report-003.pdf
21UME003TUSHARDEB
 
Engineering Drawings Lecture Detail Drawings 2014.pdf
Engineering Drawings Lecture Detail Drawings 2014.pdfEngineering Drawings Lecture Detail Drawings 2014.pdf
Engineering Drawings Lecture Detail Drawings 2014.pdf
abbyasa1014
 
132/33KV substation case study Presentation
132/33KV substation case study Presentation132/33KV substation case study Presentation
132/33KV substation case study Presentation
kandramariana6
 
Welding Metallurgy Ferrous Materials.pdf
Welding Metallurgy Ferrous Materials.pdfWelding Metallurgy Ferrous Materials.pdf
Welding Metallurgy Ferrous Materials.pdf
AjmalKhan50578
 
Transformers design and coooling methods
Transformers design and coooling methodsTransformers design and coooling methods
Transformers design and coooling methods
Roger Rozario
 
CEC 352 - SATELLITE COMMUNICATION UNIT 1
CEC 352 - SATELLITE COMMUNICATION UNIT 1CEC 352 - SATELLITE COMMUNICATION UNIT 1
CEC 352 - SATELLITE COMMUNICATION UNIT 1
PKavitha10
 
The Python for beginners. This is an advance computer language.
The Python for beginners. This is an advance computer language.The Python for beginners. This is an advance computer language.
The Python for beginners. This is an advance computer language.
sachin chaurasia
 
学校原版美国波士顿大学毕业证学历学位证书原版一模一样
学校原版美国波士顿大学毕业证学历学位证书原版一模一样学校原版美国波士顿大学毕业证学历学位证书原版一模一样
学校原版美国波士顿大学毕业证学历学位证书原版一模一样
171ticu
 
ISPM 15 Heat Treated Wood Stamps and why your shipping must have one
ISPM 15 Heat Treated Wood Stamps and why your shipping must have oneISPM 15 Heat Treated Wood Stamps and why your shipping must have one
ISPM 15 Heat Treated Wood Stamps and why your shipping must have one
Las Vegas Warehouse
 
AI assisted telemedicine KIOSK for Rural India.pptx
AI assisted telemedicine KIOSK for Rural India.pptxAI assisted telemedicine KIOSK for Rural India.pptx
AI assisted telemedicine KIOSK for Rural India.pptx
architagupta876
 
Use PyCharm for remote debugging of WSL on a Windo cf5c162d672e4e58b4dde5d797...
Use PyCharm for remote debugging of WSL on a Windo cf5c162d672e4e58b4dde5d797...Use PyCharm for remote debugging of WSL on a Windo cf5c162d672e4e58b4dde5d797...
Use PyCharm for remote debugging of WSL on a Windo cf5c162d672e4e58b4dde5d797...
shadow0702a
 
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECTCHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
jpsjournal1
 
官方认证美国密歇根州立大学毕业证学位证书原版一模一样
官方认证美国密歇根州立大学毕业证学位证书原版一模一样官方认证美国密歇根州立大学毕业证学位证书原版一模一样
官方认证美国密歇根州立大学毕业证学位证书原版一模一样
171ticu
 
Software Quality Assurance-se412-v11.ppt
Software Quality Assurance-se412-v11.pptSoftware Quality Assurance-se412-v11.ppt
Software Quality Assurance-se412-v11.ppt
TaghreedAltamimi
 
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
ecqow
 
Optimizing Gradle Builds - Gradle DPE Tour Berlin 2024
Optimizing Gradle Builds - Gradle DPE Tour Berlin 2024Optimizing Gradle Builds - Gradle DPE Tour Berlin 2024
Optimizing Gradle Builds - Gradle DPE Tour Berlin 2024
Sinan KOZAK
 

Recently uploaded (20)

Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
Electric vehicle and photovoltaic advanced roles in enhancing the financial p...
 
Comparative analysis between traditional aquaponics and reconstructed aquapon...
Comparative analysis between traditional aquaponics and reconstructed aquapon...Comparative analysis between traditional aquaponics and reconstructed aquapon...
Comparative analysis between traditional aquaponics and reconstructed aquapon...
 
Hematology Analyzer Machine - Complete Blood Count
Hematology Analyzer Machine - Complete Blood CountHematology Analyzer Machine - Complete Blood Count
Hematology Analyzer Machine - Complete Blood Count
 
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressionsKuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
KuberTENes Birthday Bash Guadalajara - K8sGPT first impressions
 
Mechanical Engineering on AAI Summer Training Report-003.pdf
Mechanical Engineering on AAI Summer Training Report-003.pdfMechanical Engineering on AAI Summer Training Report-003.pdf
Mechanical Engineering on AAI Summer Training Report-003.pdf
 
Engineering Drawings Lecture Detail Drawings 2014.pdf
Engineering Drawings Lecture Detail Drawings 2014.pdfEngineering Drawings Lecture Detail Drawings 2014.pdf
Engineering Drawings Lecture Detail Drawings 2014.pdf
 
132/33KV substation case study Presentation
132/33KV substation case study Presentation132/33KV substation case study Presentation
132/33KV substation case study Presentation
 
Welding Metallurgy Ferrous Materials.pdf
Welding Metallurgy Ferrous Materials.pdfWelding Metallurgy Ferrous Materials.pdf
Welding Metallurgy Ferrous Materials.pdf
 
Transformers design and coooling methods
Transformers design and coooling methodsTransformers design and coooling methods
Transformers design and coooling methods
 
CEC 352 - SATELLITE COMMUNICATION UNIT 1
CEC 352 - SATELLITE COMMUNICATION UNIT 1CEC 352 - SATELLITE COMMUNICATION UNIT 1
CEC 352 - SATELLITE COMMUNICATION UNIT 1
 
The Python for beginners. This is an advance computer language.
The Python for beginners. This is an advance computer language.The Python for beginners. This is an advance computer language.
The Python for beginners. This is an advance computer language.
 
学校原版美国波士顿大学毕业证学历学位证书原版一模一样
学校原版美国波士顿大学毕业证学历学位证书原版一模一样学校原版美国波士顿大学毕业证学历学位证书原版一模一样
学校原版美国波士顿大学毕业证学历学位证书原版一模一样
 
ISPM 15 Heat Treated Wood Stamps and why your shipping must have one
ISPM 15 Heat Treated Wood Stamps and why your shipping must have oneISPM 15 Heat Treated Wood Stamps and why your shipping must have one
ISPM 15 Heat Treated Wood Stamps and why your shipping must have one
 
AI assisted telemedicine KIOSK for Rural India.pptx
AI assisted telemedicine KIOSK for Rural India.pptxAI assisted telemedicine KIOSK for Rural India.pptx
AI assisted telemedicine KIOSK for Rural India.pptx
 
Use PyCharm for remote debugging of WSL on a Windo cf5c162d672e4e58b4dde5d797...
Use PyCharm for remote debugging of WSL on a Windo cf5c162d672e4e58b4dde5d797...Use PyCharm for remote debugging of WSL on a Windo cf5c162d672e4e58b4dde5d797...
Use PyCharm for remote debugging of WSL on a Windo cf5c162d672e4e58b4dde5d797...
 
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECTCHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
 
官方认证美国密歇根州立大学毕业证学位证书原版一模一样
官方认证美国密歇根州立大学毕业证学位证书原版一模一样官方认证美国密歇根州立大学毕业证学位证书原版一模一样
官方认证美国密歇根州立大学毕业证学位证书原版一模一样
 
Software Quality Assurance-se412-v11.ppt
Software Quality Assurance-se412-v11.pptSoftware Quality Assurance-se412-v11.ppt
Software Quality Assurance-se412-v11.ppt
 
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
一比一原版(CalArts毕业证)加利福尼亚艺术学院毕业证如何办理
 
Optimizing Gradle Builds - Gradle DPE Tour Berlin 2024
Optimizing Gradle Builds - Gradle DPE Tour Berlin 2024Optimizing Gradle Builds - Gradle DPE Tour Berlin 2024
Optimizing Gradle Builds - Gradle DPE Tour Berlin 2024
 

Solar generation for APC

  • 1. Integration of solar generation for reduction of Auxiliary Power Consumption (APC) in Thermal Power plant M. G. Morshad , ADGM / Electrical TPS II ( 7 x 210MW) NLC India Ltd
  • 2. Auxiliary Power Consumption (APC) Auxiliary Power Consumption (APC) The MW power required to operate the auxiliary equipment of the plant Unit Auxiliary Consumption (UAC) The power drawn from own generation for operating its own loads (the auxiliary equipment of Boiler , Turbine , Generator) Station Auxiliary Consumption (SAC) The power drawn from Grid for operating the common and emergency loads of the plant (Lighting, AC & Vent, Coal Handling Plant etc.
  • 3. Auxiliary Power Consumption (Station consumption + Unit Consumption ) % Auxiliary consumption = x 100 (Total Generation ) Export in MU/day Import in MU / Day Unit Auxiliary Consumption in MU / Day
  • 4. Parameters Formula MW Percentage Total Generation G 1370 100.00 % Unit Auxiliary consumption UAC 112 8.18% Station Auxilary Consumption SAC 17 1.24% Auxiliary Power Consumption APC = UAC + SAC 129 9.42% Typical Auxiliary Power Consumption in any thermal power plant 91% 8% 1% Genertion & APC Generation UAC SAC
  • 5. Impact of APC on thermal power plant  APC of any Coal & Lignite base thermal power plant varies from 5 % to 10% depending upon capacity of the plant , Technology used and Fuel quality .  APC gets further increased for complying with statuary environmental norms for handling dry ash, emission of SOx, NOx, SPM and effluent .  As tariff increases with APC, selling out of energy to grid through power treading becomes highly competitive with higher APC.  Energy feed to the bus (Total Generation – APC) decreases with higher APC causing revenue loss.
  • 6. Parameters Station Solar Load MW 17 10 Capacity Utilization Factor (CUF) 100% 18% Average load (MW) 17.00 1.80 Reduced load with solar generation (MW) 15.20 *** Existing With solar generation Parameters Formula MW Percentage MW Percentage Generation MW 1370 100% 1370 100% Unit Auxiliary consumption UAPC 112 8.18% 112 8.18% Station Auxilary Consumption ASAPC 17 1.24% 15.2 1.11% Total Auxilary consumption APC = (UAPC + SAPC) 129 9.42% 127.2 9.28% Impact of integration of solar generation
  • 7. Investment for solar plant as per CERC guideline Investment required = Rs 5.01 Crore / MW
  • 8. Capital cost Parameters Cr/MW 10 MW PV Modules 3.10 31.019 Land Cost 0.25 0 Civil and General Works 0.35 0 Mounting Structures 0.35 1 Power Conditioning Unit 0.30 3 Evacuation Cost up to Interconnection Point (Cables and Transformers) 0.40 4 Preliminary and Pre-Operative Expenses including Contingency 0.26 1 Total capital cost 5.01 40.02 Annual interest @ 10% *** 4.00 Annual depriciation @ 5.58% *** 2.23 Total Project cost *** 46.25 Annual cost @ 15 Years life *** 3.08 Investment for setting up 10 MW solar plant inside thermal power plant
  • 9. Parameters Formula Existing With solar Gross Heat rate (Kcal/Kwhr) GHR 2845 2845 % APC %APC 9.42% 9.28% Net Heat rate (Kcal/Kwhr) NHR = GHR /(1-% APC) 3140.73 3136.18 Annual generation (MU) MU = 1470X24x365x0.85 10945.62 10945.62 GCV Lignite Kcal/Kg) GCV 2650 2650 Lignite consumption (Ton) LC = HR x MUX1000/GCV 12972555.85 12953767.15 Lignite purchse cost (Rs/Ton) CP 2350 2350 Lignite consumption cost (Crore) LCC = LC x CP / 10000000 3,048.55 3,044.14 Annual Lignite Cost saving (Crore) LCC (Before - After) *** 4.42 Annual fuel saving due to integration of solar generation
  • 10. Annual generation (MU) MU = 1470X24x365x0.85 10945.62 Net Heat rate Before (Kcal/Kwhr) NHR 1 3140.73 Net Heat rate After (Kcal/Kwhr) NHR 2 3136.18 Energy Saving Certificate (Nos) ESC = (NHR 1-NHR2)X MU/10 4980.26 Cost per certificate (Rs) C 10000 Total cost (Crore) TC 4.98 Annual incentive (Crore) TC/3 1.66 Annual incentive in the form of Energy saving certificate under PAT scheme
  • 11. Parameters Measuring Units Formula Norms Present With Solar Generation Gross station heat rate Kcal/Kwhr GHR 2900 2845 2845 Specific fuel oil consumption ml/Kwhr SFC 2 2 2 Calorific value - Secondary fuel Kcal / ml CVSF 10 10 10 Landed price - Primary fuel Rs / Kg LPPF 2.35 2.35 2.35 Calorific value - Promary fuel Kcal / kg CVPF 2950 2950 2950 Auxiliary Power Consumption % AUX 10 9.42 9.28 Energy Charge rate (EC) Rs / Kwhr EC = [(GHR - SFC X CVSF) X LPPF/CVPF]X 100/(100-AUX) 2.563 2.499 2.495 Capacity Charges Rs / Kwhr CC 0.852 0.852 0.852 Energy Charges Rs / Kwhr EC 2.56 2.50 2.49 Tariff Rs / Kwhr CC + EC 3.415 3.351 3.347 Tariff reduction due to integration of solar generation
  • 12. Land availability for erection of solar panels Thermal Solar Unit Specific land requirement 0.3 7 Acre / MW Plant Capacity 1470 10 MW Total land requirement 441 70 Acre Availability of land in thermal power plant Percentage Acre Water reservoir 10% 44.1 Building area 2% 8.82 Coal handling area 8% 35.28 Total area available for erection of solar panel 88.2
  • 13. 1. Roof top solar panels are to be mounted over all the building available inside the plant premises  Advantages –  Reduce room temperature that lead to reduce power consumption for AC & Ventilation system. 2. Floating type solar panels are to be arranged for water reservoir.  Advantages –  Reduce evaporation loss of circulating water from lake that leads to reduction in water consumption.  Reduce CW temp during summer which can avoid load reduction due high CW temp . Mounting of solar panels
  • 14. TG Hall (Roof Top) CW Pump House (Roof Top) Lake ( Floating Type) AO Building (Roof Top) Canteen (Roof Top) ADPH Stage I (Roof Top) ADPH Stage II (Roof Top) Inverter Arrangement of panels and evacuation of power Energy Meter To Township Inverter 11KV Ring main Grid
  • 15. Solar panels String combined Box DC to AC Inverter Solar panels String combined Box DC to AC Inverter HT Switcher Gear 380/11KV 11KV Ring main Grid System Arrangement
  • 16. Advantages 1. Fuel cost saving 2. Pumping of more energy to grid due to lower APC which can fetch additional revenue 3. Earning Energy saving certificate under PAT scheme due to reduction in Net Heat rate 4. Evacuation of excess generation through power treading becomes less competitive due to lower tariff 5. No erection of separate switchyard . 6. No additional establishment cost 7. Excess solar generation can be pumped to Township grid 8. Floating panels over lake will reduce the CW temp during summer and therefore load reduction due to poor condenser vacuum can be avoided. 9. Roof top panels will reduce the room temperature that lead to reduce AC & Ventilation consumption.
  • 17. Points to be taken into consideration for implement this project. 1. Water sprinkler system to be installed to keep the panels free from dry ash deposition and increasing efficiency of the PV cell due to cooling 2. About 200KW is required to operate water sprinkler system 3. Raw water consumption will be increased 4. Investment should be under the head of energy conservation not as capital investment for asset Thank You