SlideShare a Scribd company logo
A Framework for Schedule Design
     Planning for Schedule Development




   Chris Carson, PSP                                       Patrick Kelly, PSP
Corporate Director of Project Controls                       Project Controls Manager

  Chris.Carson@alphacorporation.com                      Patrick.Kelly@alphacorporation.com
 (O) 757-533-9368   (M) 757-342-5524                    (O) 757-533-9368    (M) 757-217-6820
                AACE International’s 52nd Annual Meeting
                   and ICEC’s 6th World Congress
                 on Cost Engineering, Project Management, and Quantity Surveying
AACE International’s 52nd Annual Meeting & ICEC’s 6th World Congress


Schedule Design - Introduction


• A proper schedule addresses the needs of
  project management in balance with the
  requirements of the specifications, providing
  accurate predictive capabilities with an
  appropriate level of detail that ensures a
  nimble yet accurate management tool.
• Such schedules are not put together
  mindlessly; they must be intentionally
  designed to achieve this purpose.
                                                                              2
AACE International’s 52nd Annual Meeting & ICEC’s 6th World Congress


Schedule Design - Introduction


• Schedules are rarely Designed; rather,
  Schedulers tend to move directly into
  Schedule Planning and Development.
   – The focus is generally on the mechanics of
     Development, not the reason for the schedule.
   – Decisions such as level of detail, reporting needs,
     end user needs, abilities of the input user, and
     others, are allowed to develop as an offshoot of
     Schedule Planning and Development.


                                                                              3
AACE International’s 52nd Annual Meeting & ICEC’s 6th World Congress


Schedule Design - Introduction

• Following a Framework for Schedule Design will ensure that
  project schedules will meet all participant’s needs, from
  Project Superintendents to the Project’s End User.
   – Building a schedule is a project in itself, and Design is planning for a
     Schedule Planning and Development.
   – Good Design will yield significant benefits by achieving project team
     buy-in at the Design phase.
• Purpose: to provide a detailed and structured approach to
  designing a schedule, with a checklist and question and
  answer approach that allows the scheduler / planner to
  leverage their planning time into a good layout for the full
  Schedule Planning and Development process.


                                                                                4
AACE International’s 52nd Annual Meeting & ICEC’s 6th World Congress


Schedule Design - Background

• Why design a schedule?
   – A schedule meets the criteria for a “project” in itself.
   – A schedule is a guideline or plan for a project.
   – A schedule provides a a methodical approach for a project.
   – Keeps the Schedule Planning and Development on track.
   – Prevents rework due to late understanding of needs.
   – Allows buy-in from end users prior to Development.
   – Makes the Schedule Planning and Development session much more
     meaningful.
   – Documents the assumptions and intention of the schedule.
       •   For reviewer and approver.
       •   For future reference.
       •   To facilitate changes in schedulers.
       •   Place to capture Lessons Learned.


                                                                                  5
AACE International’s 52nd Annual Meeting & ICEC’s 6th World Congress


Schedule Design - Background


• What is Schedule Design, and how does it differ
  from Schedule Planning and Development?
• What is the uniform taxonomy of these terms, and
  what is their relationship to one another?
• Total Cost Management Framework provides good
  definitions of the differences.




                                                                              6
AACE International’s 52nd Annual Meeting & ICEC’s 6th World Congress


Schedule Design - Background


• Design vs. Development.
   – Schedule Design exists primarily in 7.1 Project Scope
     and Execution Strategy Development.
   – Planning and Development exist in 7.2 Schedule
     Planning and Development.




                                                                              7
AACE International’s 52nd Annual Meeting & ICEC’s 6th World Congress


Schedule Design - Background

• 7.1 Project Scope and Execution Strategy
  Development.
   – “The project scope and execution strategy development
     process translates the project implementation basis (i.e.,
     asset scope, objectives, constraints, and assumptions)
     into controllable project scope definition and an execution
     strategy.
   – The project scope defines what the work is (i.e., the work
     that must be performed to deliver a product, service, or
     result with the specified features and functions).
   – The execution strategy establishes criteria for how the
     work will be implemented (i.e., the general approach
     through which the work will be performed.)”

                                                                              8
AACE International’s 52nd Annual Meeting & ICEC’s 6th World Congress


Schedule Design - Background


• TCM 7.1 Process Map.




                                                                              9
AACE International’s 52nd Annual Meeting & ICEC’s 6th World Congress


Schedule Design - Background


• 7.2 Schedule Planning and Development.
   – “Schedule planning and development are the processes
     for the planning of work over time in consideration of the
     costs and resources for that work. Schedule planning and
     schedule development are separate, but related, sub-
     processes that call for different skills and knowledge
     emphasis.
      • Schedule planning consists of breaking work package scope into
        activities, and logically ordering those activities into the sequence
        in which they will be best performed. Result is a detailed, but
        conceptual, non-resource driven, schedule.
      • Schedule development consists of enhancing the model created
        in planning and allocating available resources, to iteratively
        generate the as-planned schedule model that becomes the
        schedule control baseline.
                                                                              10
AACE International’s 52nd Annual Meeting & ICEC’s 6th World Congress


Schedule Design - Background


• TCM 7.2 Process Map.

                           Schedule Design is a prerequisite
                           to Schedule Planning




                                                                              11
AACE International’s 52nd Annual Meeting & ICEC’s 6th World Congress


Schedule Design - Background


• Summary of Process Maps.
                                                                  RP 23R-02
                                                                  Identification of
                                                                  Activities establishes
        Schedule
                                                                  the start of this
         Design
                                                                  phase.


        TCM 7.1                        Schedule
                                       Planning
Defines the work that
must be performed to
deliver the Project, the
                                                                    Schedule
general approach
                                                                   Development
through which the work
will be performed, and
the schedule architecture
                                                      TCM 7.2
needed to support.
                                                                                       12
AACE International’s 52nd Annual Meeting & ICEC’s 6th World Congress


Schedule Design - Background


• Note on PSP Scope of Knowledge RP
  14R-90.
   – “Schedule Development” is defined to encompass
     what TCM refers to as Design and Development.
   – RP 14R-90 also uses the terms “Planning” and
     “Scheduling” to define some of these functions.
   – TCM and the PSP Scope of Knowledge have
     unresolved overlap in terminology.
      • Clearly, both Design and Development are part of the
        Skills and Knowledge of a Planning and Scheduling
        Professional.
      • This presentation uses TCM framework to drive
        definitions and delineate the Design process.
                                                                              13
AACE International’s 52nd Annual Meeting & ICEC’s 6th World Congress


Schedule Design - Background

• Design vs. Development – How PMI & PMBOK handles it?
   – PMBOK identifies six Project Time Management processes, usually
     defined as part of the project lifecycle, Section 2.1 of PMBOK.
      •    Activity Definition.
      •    Activity Sequencing.
      •    Activity Resource Estimating.
      •    Activity Duration Estimating.
      •    Schedule Development.
      •    Schedule Control.
   – These processes are preceded by a planning effort by the project
     management team, which is part of PMBOK’s “Develop Project
     Management Plan”, PMBOK Section 4.3 (which sets the format and
     establishes criteria for developing the project schedule).
   – These processes are documented in what PMBOK calls a Schedule
     Management Plan, which is contained in the project management
     plan, in the introduction to Section 4.3, Project Integration
     Management.

                                                                                 14
AACE International’s 52nd Annual Meeting & ICEC’s 6th World Congress


Schedule Design - Background

• PMBOK Process Inputs.
   – The inputs for the different Time Management Processes are listed
     as:
       •    Activity list.
       •    Product description.
       •    Mandatory dependencies.
       •    Discretionary dependencies.
       •    External dependencies.
       •    Resource requirements.
       •    Resource capabilities.
       •    Historical information.
       •    Identified risks.
       •    Constraints.
       •    Assumptions.
   – All of these items, along with the Schedule Management Plan, are
     part of Schedule Design, but PMBOK does not offer clear definition
     and delineation of Schedule Design.
   – The Time Management Processes do not include Schedule Design.

                                                                                  15
AACE International’s 52nd Annual Meeting & ICEC’s 6th World Congress


Schedule Design - Background


• Design vs. Development – why
  emphasize the distinction?
   – Design tends to be ignored in favor of jumping
     right into development.
      • Many schedulers elect to begin creating activities
        instead of Designing.
      • Work is subsequently repetitive, with lots of potential for
        rework.
      • Results tend to be disorganized.
• Avoid planning mistakes and problems.
                                                                              16
AACE International’s 52nd Annual Meeting & ICEC’s 6th World Congress


Schedule Design - Background


• Poorly designed Activity Coding:




 Repetitive
 Activity Coding
 and Grouping
 Levels due to
 lack of
 forethought in
 structure

                                                                                17
AACE International’s 52nd Annual Meeting & ICEC’s 6th World Congress


Schedule Design - Background


• Activities driving the Work Breakdown Structure:




Inconsistent
levels of detail
due to
unorganized
activity entry.
Hinders
grouping and
comparison.


                                                                                  18
AACE International’s 52nd Annual Meeting & ICEC’s 6th World Congress


Schedule Design - Background

• Lack of Good Area Definition preventing activity
  closeout:
Areas are so
broadly defined
that activities
sit at nearly
complete for
large parts of
the project.
Hinders
productivity
analysis, good
cost loading,
accurate as-
built dates.

                                                                                 19
AACE International’s 52nd Annual Meeting & ICEC’s 6th World Congress


Schedule Design - Background


• Inconsistency in level of detail throughout trades:
Some trades
are heavily
developed
while others
are left with
summary-level
activities only.




                                                                                 20
AACE International’s 52nd Annual Meeting & ICEC’s 6th World Congress


Schedule Design – Components of the Design Process


  Scope of Design vs. Development.
    Design – Conceptualizing the schedule.
       Planning the Schedule.
            Starting with the end in mind.
            Providing concept of final product.
       Creating organizational structure to fulfill the concept.
  Timing.
    Must be done prior to Schedule Planning and
    Development.




                                                                              21
AACE International’s 52nd Annual Meeting & ICEC’s 6th World Congress


Schedule Design – Components of the Design Process


  Documentation and use of Schedule Design.
    Create a book or binder.
    Use the highest level of checklist outline items as tabs.
    Use the book as basis for schedule submittal
    documentation.
    Keep the book current during project.
    Use the book for handoff between schedulers.
    Share a copy of the book with superintendent/PM.




                                                                              22
AACE International’s 52nd Annual Meeting & ICEC’s 6th World Congress


Schedule Design – Components of the Design Process


   Schedule Design Process.
      Development of Controllable Project
      Scope Definition.
      Development of Execution Strategy.




                                                                              23
AACE International’s 52nd Annual Meeting & ICEC’s 6th World Congress


Schedule Design Checklist


  Development of Controllable Project Scope
  Definition
     Collection of Inputs
       Project Implementation Basis (or Project Plan) (TCM
       4.1).
       Project Historical Information (TCM 10.4).
       Change Management Plan (TCM 10.3).
       Team Players.
       Other Planning Process Plans (TCM 7.2 to 7.7).
     Develop Work Breakdown Structure

                                                                              24
AACE International’s 52nd Annual Meeting & ICEC’s 6th World Congress

Schedule Design Checklist - Development of Controllable
Project Scope Definition

  Project Implementation Basis (or Project
  Plan) (TCM 4.1).
     Contract (TCM 7.7).
     Notice to Proceed or Release Letter.
     Project Drawings.
        Area Designation Plan.
        Sequencing plan.
     Specifications.
        Scheduling Specification.
        Scope of Work definition.
        Liquidated Damages schedule.
        Owner-provided items & scope.

                                                                              25
AACE International’s 52nd Annual Meeting & ICEC’s 6th World Congress

Schedule Design Checklist - Development of Controllable
Project Scope Definition

Schedule Specification – General Contents.




                                                                              26
AACE International’s 52nd Annual Meeting & ICEC’s 6th World Congress

Schedule Design Checklist - Development of Controllable
Project Scope Definition

  Project Implementation Basis (or Project
  Plan) (TCM 4.1).
     Owner milestones, phases, or master schedules.
     Estimate & quantity surveys/bills of materials. (TCM 7.3).
     Any existing internal WBS.
     Owner separate contracts and scope (coordination
     between this and other external projects).
     Value Analysis and Engineering (TCM 7.5).




                                                                              27
AACE International’s 52nd Annual Meeting & ICEC’s 6th World Congress

Schedule Design Checklist - Development of Controllable
Project Scope Definition

  Project Historical Information (TCM 10.4).
     Collection of data from the Project Historical Database.
     Actual Schedule Data.
     Actual Resource Data.
     Project Lessons Learned.
     Incorporation of this data aids in development of
     Execution Plan.




                                                                              28
AACE International’s 52nd Annual Meeting & ICEC’s 6th World Congress

Schedule Design Checklist - Development of Controllable
Project Scope Definition

  Change Management Plan (TCM 10.3).
     Notification requirements.
     Methodology allowed.
     Quality control process.
     Process flowchart.




                                                                              29
AACE International’s 52nd Annual Meeting & ICEC’s 6th World Congress

Schedule Design Checklist - Development of Controllable
Project Scope Definition

Change Management Plan Control Process.




                                                                              30
AACE International’s 52nd Annual Meeting & ICEC’s 6th World Congress

Schedule Design Checklist - Development of Controllable
Project Scope Definition

Change Management Plan Process Flowchart.
                         Collect Admin                       Verify All
                         Progress Data                         Data
                                                                                                                                         No
                                                                                                                       Critical Path
                                                                                                                         Delay?
         Request for        Collect Field              Status              Update            Compare to
         Update Data        Progress Data             Schedule            Schedule            Baseline
                                                                                                                              Yes

                                         Identify Contract
                                            Changes                                                                  Identify Previous
                                                                                                                          Period
                                                                                                                       Critical Path
                                                                                                                                                    Publish
                         Research                                                                                                                   Updated
                                                Quantify            Identify Causal         Identify Changes
                       Documents For                                                                                                                Schedule
                                                 Delays             Delay Activities         To Critical Path
                       Driving Delays


                                                                                                Is the
                         Assess                 Any                   Perform                  Owner
                                                             Yes                                                Yes
                                                                                                                                          Prepare
                       Responsibility        Concurrent            Concurrent Delay          Responsible
                                                                                                                                         Recovery
                        For Delays            Delays?                 Analysis                For Delay?
                                                                                                                                         Schedule

                                                       No
                                                                                                      No
                                                                                                                                  Resolve
                                                                                                                                Subcontractor
                                                                                                 Is a
                                                                      Is the
                                                                                                                                Contributions
                                                                                       No                       No
                                            Verify Single            Owner                   Subcontractor
                                            Source Delay                                     Responsible
                                                                   Responsible
                                            Responsibility                                    For Delay?
                                                                    For Delay?
                                                                                                                       Discuss Delay &
                                                                                                                        Mitigation with
                                                                                                       Yes
                                                                                                                        Subcontractor
                                                                            Yes
              Proposed Schedule Update
              With Change Management                                                                       Discuss Delay                   Prepare Delay
                                                                                                            & Mitigation                     Analysis
                                                                                                            With Owner                    & Change Order


                                                                                                                                                               31
AACE International’s 52nd Annual Meeting & ICEC’s 6th World Congress

Schedule Design Checklist - Development of Controllable
Project Scope Definition

  Team Players.
     Organizational Chart.
     Identify the Schedule Users.
        Who has Input?
        Who Updates?
        Who Checks for Accuracy?
        Who Reviews?
        Who approves?
     Identify Responsibility Assignment Matrix (RAM).




                                                                              32
AACE International’s 52nd Annual Meeting & ICEC’s 6th World Congress

Schedule Design Checklist - Development of Controllable
Project Scope Definition

RAM Example (based on PMBOK RACI Chart).




                                                                              33
AACE International’s 52nd Annual Meeting & ICEC’s 6th World Congress

Schedule Design Checklist - Development of Controllable
Project Scope Definition

  Other Planning Process Plans (TCM 7.2 to 7.7).
     Many of these processes have been covered in other
     items.
     We recommend reading the publication.




                                                                              34
AACE International’s 52nd Annual Meeting & ICEC’s 6th World Congress

Schedule Design Checklist - Development of Controllable
Project Scope Definition

  Develop Work Breakdown Structure.
     Translate asset scope into component deliverables
     (“decomposition”).
     Ensure consistency in WBS levels, to facilitate
     comparison.




                                                                              35
AACE International’s 52nd Annual Meeting & ICEC’s 6th World Congress


Schedule Design – Components of the Design Process


   Schedule Design Process.
      Development of Controllable Project.
      Scope Definition.
      Development of Execution Strategy.




                                                                              36
AACE International’s 52nd Annual Meeting & ICEC’s 6th World Congress


Schedule Design Checklist

  Development of Controllable Execution
  Strategy.
    Organizational Breakdown Structure.
    Work Package Development.
    Schedule Design Output (Software Driven).
    Outline Schedule.
    Risk Analysis.
    Definition of Processes.
                                                                             37
AACE International’s 52nd Annual Meeting & ICEC’s 6th World Congress

Schedule Design Checklist - Development of Execution
Strategy

  Organizational Breakdown Structure.




                                       From: DOE Training “EVM Tutorial – WBS”
                                       by Booze-Allen-Hamilton




                                                                                 38
AACE International’s 52nd Annual Meeting & ICEC’s 6th World Congress

Schedule Design Checklist - Development of Execution
Strategy

  Work Package Development.
       By Contract.
       As assigned by Client.

   VI. Work Packages
   Division 2 and 5 Specifications require the following Work Packages:
   –   Superstructure Waterproofing
   –   Corrosion Protection of Structural Steelwork
   –   Movements and Tolerances Specification for Structural Steel
   –   Structural Steel Superstructure
   –   Cast in Place Concrete


                                                                                 39
AACE International’s 52nd Annual Meeting & ICEC’s 6th World Congress

Schedule Design Checklist - Development of Execution
Strategy

  Schedule Design Output (Software Driven)
     Software Identification.
        Specific software.
        Required minimum and versions allowed.
        Enterprise specific issues.
            Users identified.
            Schedules used for import or data source.
            Levels of access.
            Validation process.
            For master schedules, establish data dates.

                                                                              40
AACE International’s 52nd Annual Meeting & ICEC’s 6th World Congress

Schedule Design Checklist - Development of Execution
Strategy

  Schedule Design Output (Software Driven).
     Purpose of Work Product.
       What the Schedule can be used for (purpose).
            Superintendent work schedule.
            Buyout schedule.
            Justification of time requests.
            Claims/Dispute Resolution.
     Reports Generated from the Schedule.
       Who receives reports.
       List of reports.
       Samples of reports.
     Glossary/Lexicon of ambiguous terms.

                                                                              41
AACE International’s 52nd Annual Meeting & ICEC’s 6th World Congress

Schedule Design Checklist - Development of Execution
Strategy – Example of Lexicon

General Notes Regarding this Report:
• “Program,” “Programme,” and “Baseline CPM,” and “Schedule” all have
  the same definition and are used interchangeably.
• “Snagging” and “Punch-out” have the same definition and are used
  interchangeably.
• “Fixed” and “Rough-in” have roughly the same definition. For clarification
  purposes, “Fixed” has been used in this Program.
• “Conventional concrete” is defined as post-tension poured-in-place
  concrete.
• “Wild Air” is defined as a stage in construction, for which the building is
  closed in by perimeter walls and ventilation has started. (Ventilation only,
  not complete environmental controls or functioning air conditioning.) This
  term is used in lieu of “environmental controls,” or “drying –in” as wet
  weather is not a real factor in Dubai.
• “Raft” construction consists of the foundation including but not limited to
  piles, grade beams, footers, and slab-on-grade.
                                                                                42
AACE International’s 52nd Annual Meeting & ICEC’s 6th World Congress

Schedule Design Checklist - Development of Execution
Strategy

  Schedule Design Output (Software Driven)
    Level of Detail.
        Determine approach:
            Bottom-up (starting with detailed activities).
            Top-down (starting with summary schedule).
            Both (prepare Top-down, then Bottom-up).
        Identify frequency of updates.
        Establish smallest activity duration range.


                                                                              43
AACE International’s 52nd Annual Meeting & ICEC’s 6th World Congress

Schedule Design Checklist - Development of Execution
Strategy

  Schedule Design Output (Software Driven)
     Codes Dictionary.
       For tracking and monitoring work:
            Work Phase.
            Structure.
            Area.
            Floor or Station.
            Location.
       For Project Management:
            Responsibility.
            Work Shifts.
            Costs.
            Resource.
            Specification.
            Change management.


                                                                              44
AACE International’s 52nd Annual Meeting & ICEC’s 6th World Congress

Schedule Design Checklist - Development of Execution
Strategy

   Schedule Design Output (Software Driven)
     Weather Planning & Calendars.
        Weather planning.
            Expected adverse weather.
            Identify source or specification requirement.
            Identify methodology.
            Identify accounting method for actual weather.
        Establish number of calendars needed.
        Define calendars and application.

                                                                              45
AACE International’s 52nd Annual Meeting & ICEC’s 6th World Congress

Schedule Design Checklist - Development of Execution
Strategy

Example of Calendar Section:

•   Calendars are defined as follows:
    –   Calendar 1 – 24 hours a day, 7 days a week.
    –   Calendar 2 – 24 hours a day, only Fridays off. (This is the Default Calendar.)
    –   Calendar 3 – Night Shift, only Fridays off.
    –   Calendar 4 – Night Shift, 24 hours a day, 7 days a week.
    –   Please note that 01140/1.9.a. requires that the Contractor notify the Client
        regarding multiple shifts, etc. This has been accomplished by using Day
        and Night sift calendars as well as by incorporating multiple crew codes into
        the Program. (For more on Crews, please refer to the Resources section of
        this report.)



                                                                                     46
AACE International’s 52nd Annual Meeting & ICEC’s 6th World Congress

Schedule Design Checklist - Development of Execution
Strategy

  Schedule Design Output (Software Driven)
    Cost & Resources.
         Estimate & correlation to cost loading.
         Bill of Quantities & use in resources.
         Resource Crew descriptions.
         Equipment descriptions.
         How actual production will be monitored.
         Earned Value Management System.
                                                                              47
AACE International’s 52nd Annual Meeting & ICEC’s 6th World Congress

Schedule Design Checklist - Development of Execution
Strategy

  Outline Schedule.
     Outline Schedule.
        Key Activities being tracked.
        Client Milestones.
        Long Lead Items.
        WBS Structure.
        Other Contracts on Project.
     Narrative Basis and Assumptions.
        Procedure Used to create the Schedule.
        Definitions/lexicon.
        Description of sequence of work per structure.

                                                                              48
AACE International’s 52nd Annual Meeting & ICEC’s 6th World Congress

Schedule Design Checklist - Development of Execution
Strategy

Narrative Basis.




                                                                              49
AACE International’s 52nd Annual Meeting & ICEC’s 6th World Congress

Schedule Design Checklist - Development of Execution
Strategy

Example of Schedule Narrative Explanation:


Schedules:
•   01320/1.04 - Tender Works Schedule: A detailed schedule depicting
    construction sequencing and dates at the Tender stage.
•   01320/1.05 – Schedule of Works: This is a detailed Baseline CPM
    schedule. This schedule will be cost loaded, resource loaded with
    manpower and equipment, and incorporate the Bill of Quantities. This
    schedule will not only show construction activities, but will also
    demonstrate procurement and submittal activities. The submission of
    this schedule will include initial project histograms (for manpower,
    definable features of work, and submittal items) and a S-Curves (for
    costs, manpower, and submittal items.) Finally, this package will
    include any support data including but not limited to a Narrative
    explaining calendar usage, estimated average manpower, planned
    procurement of materials and equipment, etc.
                                                                               50
AACE International’s 52nd Annual Meeting & ICEC’s 6th World Congress

Schedule Design Checklist - Development of Execution
Strategy

  Risk Analysis (TCM 7.6).
     Risks and Constructability.
        Brainstorming of issues.
            Known problems & constructability (threats & opportunities).
            Provisional Items.
            Predicted Problems.
            Lessons Learned.
            Outside influences.
            Site condition concerns.
        Develop Risk Management Plan.
            Initial process during baseline schedule development.
            Process for use during updates.


                                                                              51
AACE International’s 52nd Annual Meeting & ICEC’s 6th World Congress

Schedule Design Checklist - Development of Execution
Strategy

Risk Management Plan.
   – Based on PMBOK.




                                                                              52
AACE International’s 52nd Annual Meeting & ICEC’s 6th World Congress

Schedule Design Checklist - Development of Execution
Strategy

  Risk Analysis (TCM 7.6).
    Time Contingencies.
        Amounts.
        Specific trade (from risk management
       plan).
        Specific contractor contingency.
        How carried.
        Use historical data for reference.
                                                                              53
AACE International’s 52nd Annual Meeting & ICEC’s 6th World Congress

Schedule Design Checklist - Development of Execution
Strategy

Specific Trade Contingency Determination – Based on
  Historical Data.
                           Time Performance Ratio

              12.0
              10.0
               8.0
        TPR




               6.0
               4.0
               2.0
               0.0




                            ev s
                                      ry




                                       s
                                      ry




                                      nt




                          E l c al
                                     ws
                                       e




                        / W f ing




                                        l
                       E q hes
                                       s
                                     rk
                                     in




                                    ca
                                     g

                                   or
                                    et



                                    al

                                   nt
                                 on
                                   m




                      Fu me
                                wo




                                  in
                                do




                                ni

                                t ri
                                et




                                at
                                cr




                              pe

                                o
               Ad




                                s



                             ish
                             as




                             ha

                             ec
                             te




                   oo Ro
                             M




                             ni

                              p
                            on




                             in
                           ar




                           ui
                          Fi
                          M
                          Si




                          rn



                         ec
                         El
                          C




                         C




                      M
                     rs
                 D




                                       Type of Work


                                                                              54
AACE International’s 52nd Annual Meeting & ICEC’s 6th World Congress

Schedule Design Checklist - Development of Execution
Strategy

  Definition of Processes.
     Update Process.
        Frequency.
        Data request and transmission.
        Validation.
        Process flowchart.
                            Collect Admin                       Verify All
                            Progress Data                         Data


              Request for     Collect Field               Status              Update    Compare to
              Update Data     Progress Data              Schedule            Schedule    Baseline


                                            Identify Contract
                                               Changes




                                                                                                     55
AACE International’s 52nd Annual Meeting & ICEC’s 6th World Congress

Schedule Design Checklist - Development of Execution
Strategy

Establish Update process.




                                                                              56
AACE International’s 52nd Annual Meeting & ICEC’s 6th World Congress

Schedule Design Checklist - Development of Execution
Strategy

  Definition of Processes.
     Recovery Process.
       Identify what logic changes
       are acceptable without formal
       approval.
       Identify what constitutes a
       Revision requiring approval.
       Provide process description
       or flow chart.



                                                                              57
AACE International’s 52nd Annual Meeting & ICEC’s 6th World Congress

Schedule Design Checklist - Development of Execution
Strategy

  Definition of Processes.
     Dispute Resolution Process.
        Review program for claims avoidance.
            Reinforce planning for claims avoidance.
            Identify specific program for claims avoidance during schedule
            updates and change management.
       Identify steps if change management process fails or
       stalls.
       Follow specifications.
       Provide time frames for stages in process.
       Provide process description or flow chart.

                                                                              58
AACE International’s 52nd Annual Meeting & ICEC’s 6th World Congress

Schedule Design Checklist - Development of Execution
Strategy

  Reporting.
     Define all reports.
     Provide examples.




                                                                              59
AACE International’s 52nd Annual Meeting & ICEC’s 6th World Congress


Schedule Design


•       Conclusion.
    –    At the end of this process, TCM 7.2 should be ready to begin.
    –    Although this requires an initial investment in time, there will be a
         savings during Planning/Development, and a reduction in rework.
    –    For success in Schedule Planning and Development, Schedule
         Design should be a completely different process.
    –    Process must be done prior to Development.
    –    Process and results documented.
    –    Documentation done in formal Schedule Design Book.
    –    Book used to provide continuity between schedulers or project
         managers.




                                                                                 60
AACE International’s 52nd Annual Meeting & ICEC’s 6th World Congress


Schedule Design


• Resources.
  – See Lance Stephenson’s “Schedule Basis Memorandum”
    paper, also addresses schedule levels.
  – See AACEi’s Total Cost Management.
  – See PMBOK for Risk Management process.
• Recommendations.
  – Get involved with AACEi and the Recommended Practices
    development.
  – Get involved with the CoS SEI Project developing Best
    Practices and Guidelines for Scheduling.
  – Get involved with CMAA in the Time Management
    development.
                                                                             61
AACE International’s 52nd Annual Meeting & ICEC’s 6th World Congress


Schedule Design



                   Questions?

      Recommendations?

                                                                             62
A Framework for Schedule Design
     Planning for Schedule Development




   Chris Carson, PSP                                       Patrick Kelly, PSP
Corporate Director of Project Controls                       Project Controls Manager

  Chris.Carson@alphacorporation.com                      Patrick.Kelly@alphacorporation.com
 (O) 757-533-9368   (M) 757-342-5524                    (O) 757-533-9368    (M) 757-217-6820
                AACE International’s 52nd Annual Meeting
                   and ICEC’s 6th World Congress
                 on Cost Engineering, Project Management, and Quantity Surveying
A Framework for Schedule Design
        Planning for Schedule Development




       Chris Carson, PSP                                      Patrick Kelly, PSP
   Corporate Director of Project Controls                       Project Controls Manager
Alpha Construction & Engineering Corporation         Alpha Construction & Engineering Corporation
      Chris.Carson@alphacorporation.com                    Patrick.Kelly@alphacorporation.com
    (O) 757-533-9368    (M) 757-342-5524                 (O) 757-533-9368     (M) 757-217-6820
                   AACE International’s 52nd Annual Meeting
                      and ICEC’s 6th World Congress
                    on Cost Engineering, Project Management, and Quantity Surveying

More Related Content

What's hot

Meeting Project Schedule Compliance Standards
Meeting Project Schedule Compliance StandardsMeeting Project Schedule Compliance Standards
Meeting Project Schedule Compliance Standards
Acumen
 
Forensic schedule analysis acesss
Forensic schedule analysis acesssForensic schedule analysis acesss
Forensic schedule analysis acesss
McLachlan Lister Pty Limited
 
Project Control Handbook
Project Control HandbookProject Control Handbook
Project Control Handbook
haroldtaylor1113
 
Time Impact Analysis
Time Impact AnalysisTime Impact Analysis
Time Impact Analysis
Chris Carson
 
Quantify Construction Damages related to Delay, disruption, and inefficiencies
Quantify Construction Damages related to Delay, disruption, and inefficienciesQuantify Construction Damages related to Delay, disruption, and inefficiencies
Quantify Construction Damages related to Delay, disruption, and inefficiencies
Michael Pink
 
Fiatech 2016 - Advanced Work Packaging: from Theory to Practice
Fiatech 2016 - Advanced Work Packaging: from Theory to PracticeFiatech 2016 - Advanced Work Packaging: from Theory to Practice
Fiatech 2016 - Advanced Work Packaging: from Theory to Practice
CCT International
 
Construction Delay Analysis, Simplified
Construction Delay Analysis, SimplifiedConstruction Delay Analysis, Simplified
Construction Delay Analysis, Simplified
Michael Pink
 
Delay Analysis and Concurrent Delay
Delay Analysis and Concurrent DelayDelay Analysis and Concurrent Delay
Delay Analysis and Concurrent Delay
M Maged Hegazy, LLM, MBA, CCP, P3O
 
Update Delay Analysis
Update Delay AnalysisUpdate Delay Analysis
Update Delay Analysis
Chris Carson
 
Earned value management
Earned value managementEarned value management
Earned value management
Ashif AR
 
Promo_Epc project rule of credit and progress measurement
Promo_Epc project rule of credit and progress measurement Promo_Epc project rule of credit and progress measurement
Promo_Epc project rule of credit and progress measurement
ignitetribes
 
Performing against the wall - SPI after completion
Performing against the wall - SPI after completionPerforming against the wall - SPI after completion
Performing against the wall - SPI after completion
M Maged Hegazy, LLM, MBA, CCP, P3O
 
Design & Development Of A Schedule Management Plan Presentation
Design & Development Of A Schedule Management Plan PresentationDesign & Development Of A Schedule Management Plan Presentation
Design & Development Of A Schedule Management Plan Presentation
Chris Carson
 
Earned Value Management
Earned Value ManagementEarned Value Management
Earned Value Management
Anand Subramaniam
 
Project control plan_draft
Project control plan_draftProject control plan_draft
Project control plan_draft
ignitetribes
 
Avoiding unrealistic schedules
Avoiding unrealistic schedulesAvoiding unrealistic schedules
Avoiding unrealistic schedules
Hatem Hegazi
 
Schedule Updates
Schedule UpdatesSchedule Updates
Schedule Updates
Chris Carson
 
Loading cost in primavera schedule using resources and expenses r01
Loading cost in primavera schedule using resources and expenses r01Loading cost in primavera schedule using resources and expenses r01
Loading cost in primavera schedule using resources and expenses r01
Muhammad Mujahid PMP®, PSP®, SP®, APMC®
 
Delay analysis ... wise after the event.
Delay analysis ... wise after the event.Delay analysis ... wise after the event.
Delay analysis ... wise after the event.
Tim Lloyd
 
Primavera P6 Tips and Tricks
Primavera P6 Tips and TricksPrimavera P6 Tips and Tricks
Primavera P6 Tips and Tricks
p6academy
 

What's hot (20)

Meeting Project Schedule Compliance Standards
Meeting Project Schedule Compliance StandardsMeeting Project Schedule Compliance Standards
Meeting Project Schedule Compliance Standards
 
Forensic schedule analysis acesss
Forensic schedule analysis acesssForensic schedule analysis acesss
Forensic schedule analysis acesss
 
Project Control Handbook
Project Control HandbookProject Control Handbook
Project Control Handbook
 
Time Impact Analysis
Time Impact AnalysisTime Impact Analysis
Time Impact Analysis
 
Quantify Construction Damages related to Delay, disruption, and inefficiencies
Quantify Construction Damages related to Delay, disruption, and inefficienciesQuantify Construction Damages related to Delay, disruption, and inefficiencies
Quantify Construction Damages related to Delay, disruption, and inefficiencies
 
Fiatech 2016 - Advanced Work Packaging: from Theory to Practice
Fiatech 2016 - Advanced Work Packaging: from Theory to PracticeFiatech 2016 - Advanced Work Packaging: from Theory to Practice
Fiatech 2016 - Advanced Work Packaging: from Theory to Practice
 
Construction Delay Analysis, Simplified
Construction Delay Analysis, SimplifiedConstruction Delay Analysis, Simplified
Construction Delay Analysis, Simplified
 
Delay Analysis and Concurrent Delay
Delay Analysis and Concurrent DelayDelay Analysis and Concurrent Delay
Delay Analysis and Concurrent Delay
 
Update Delay Analysis
Update Delay AnalysisUpdate Delay Analysis
Update Delay Analysis
 
Earned value management
Earned value managementEarned value management
Earned value management
 
Promo_Epc project rule of credit and progress measurement
Promo_Epc project rule of credit and progress measurement Promo_Epc project rule of credit and progress measurement
Promo_Epc project rule of credit and progress measurement
 
Performing against the wall - SPI after completion
Performing against the wall - SPI after completionPerforming against the wall - SPI after completion
Performing against the wall - SPI after completion
 
Design & Development Of A Schedule Management Plan Presentation
Design & Development Of A Schedule Management Plan PresentationDesign & Development Of A Schedule Management Plan Presentation
Design & Development Of A Schedule Management Plan Presentation
 
Earned Value Management
Earned Value ManagementEarned Value Management
Earned Value Management
 
Project control plan_draft
Project control plan_draftProject control plan_draft
Project control plan_draft
 
Avoiding unrealistic schedules
Avoiding unrealistic schedulesAvoiding unrealistic schedules
Avoiding unrealistic schedules
 
Schedule Updates
Schedule UpdatesSchedule Updates
Schedule Updates
 
Loading cost in primavera schedule using resources and expenses r01
Loading cost in primavera schedule using resources and expenses r01Loading cost in primavera schedule using resources and expenses r01
Loading cost in primavera schedule using resources and expenses r01
 
Delay analysis ... wise after the event.
Delay analysis ... wise after the event.Delay analysis ... wise after the event.
Delay analysis ... wise after the event.
 
Primavera P6 Tips and Tricks
Primavera P6 Tips and TricksPrimavera P6 Tips and Tricks
Primavera P6 Tips and Tricks
 

Similar to Schedule Design AACE

61r 10
61r 1061r 10
Schedule Development
Schedule DevelopmentSchedule Development
Schedule Development
Chris Carson
 
GAFM Academy - THE ESSENTIALS OF PLANNING AND SCOPING A PROJECT
GAFM Academy - THE ESSENTIALS OF PLANNING AND SCOPING A PROJECTGAFM Academy - THE ESSENTIALS OF PLANNING AND SCOPING A PROJECT
GAFM Academy - THE ESSENTIALS OF PLANNING AND SCOPING A PROJECT
GAFM Academy of Project Management ® - ISO 29990 Certified International Board of Standards
 
Pm chapter 5
Pm chapter 5Pm chapter 5
Pm chapter 5
Golam Bitonsir
 
Pm chapter 5
Pm chapter 5Pm chapter 5
Pm chapter 5
Golam Bitonsir
 
Project Management Presentation material
Project Management Presentation material Project Management Presentation material
Project Management Presentation material
Abdel Rahman okasha
 
Pm chapter 5...
Pm chapter 5...Pm chapter 5...
Pm chapter 5...
Golam Bitonsir
 
PROJECT PLANNING METHODOLOGIES.pdf
PROJECT  PLANNING METHODOLOGIES.pdfPROJECT  PLANNING METHODOLOGIES.pdf
PROJECT PLANNING METHODOLOGIES.pdf
Surashmie Kaalmegh
 
Project Time Management
Project Time ManagementProject Time Management
Project Time Management
Andersson Lujan Ojeda
 
Project Life Cycle.pptx
Project Life Cycle.pptxProject Life Cycle.pptx
Project Life Cycle.pptx
FawadAfridi6
 
Project Management.pptx
 Project  Management.pptx Project  Management.pptx
Project Management.pptx
HafixFarhan
 
Define the Project
Define the ProjectDefine the Project
Define the Project
pmSPECFramework
 
File 2 extra slide 1
File 2 extra slide 1File 2 extra slide 1
File 2 extra slide 1
test prod1
 
Project Management (Comprehensive) PowerPoint Presentation 228 slides with 21...
Project Management (Comprehensive) PowerPoint Presentation 228 slides with 21...Project Management (Comprehensive) PowerPoint Presentation 228 slides with 21...
Project Management (Comprehensive) PowerPoint Presentation 228 slides with 21...
Andrew Schwartz
 
File 2 removed 1 slide 1
File 2 removed 1 slide 1File 2 removed 1 slide 1
File 2 removed 1 slide 1
test prod1
 
File 2 extra slide 2
File 2 extra slide 2File 2 extra slide 2
File 2 extra slide 2
test prod1
 
File 2 four extra slides 2
File 2 four extra slides 2File 2 four extra slides 2
File 2 four extra slides 2
test prod1
 
File 2 original
File 2 originalFile 2 original
File 2 original
test prod1
 
File 2 removed 1 slide 2
File 2 removed 1 slide 2File 2 removed 1 slide 2
File 2 removed 1 slide 2
test prod1
 
File 2 removed 5 words 2
File 2 removed 5 words 2File 2 removed 5 words 2
File 2 removed 5 words 2
test prod1
 

Similar to Schedule Design AACE (20)

61r 10
61r 1061r 10
61r 10
 
Schedule Development
Schedule DevelopmentSchedule Development
Schedule Development
 
GAFM Academy - THE ESSENTIALS OF PLANNING AND SCOPING A PROJECT
GAFM Academy - THE ESSENTIALS OF PLANNING AND SCOPING A PROJECTGAFM Academy - THE ESSENTIALS OF PLANNING AND SCOPING A PROJECT
GAFM Academy - THE ESSENTIALS OF PLANNING AND SCOPING A PROJECT
 
Pm chapter 5
Pm chapter 5Pm chapter 5
Pm chapter 5
 
Pm chapter 5
Pm chapter 5Pm chapter 5
Pm chapter 5
 
Project Management Presentation material
Project Management Presentation material Project Management Presentation material
Project Management Presentation material
 
Pm chapter 5...
Pm chapter 5...Pm chapter 5...
Pm chapter 5...
 
PROJECT PLANNING METHODOLOGIES.pdf
PROJECT  PLANNING METHODOLOGIES.pdfPROJECT  PLANNING METHODOLOGIES.pdf
PROJECT PLANNING METHODOLOGIES.pdf
 
Project Time Management
Project Time ManagementProject Time Management
Project Time Management
 
Project Life Cycle.pptx
Project Life Cycle.pptxProject Life Cycle.pptx
Project Life Cycle.pptx
 
Project Management.pptx
 Project  Management.pptx Project  Management.pptx
Project Management.pptx
 
Define the Project
Define the ProjectDefine the Project
Define the Project
 
File 2 extra slide 1
File 2 extra slide 1File 2 extra slide 1
File 2 extra slide 1
 
Project Management (Comprehensive) PowerPoint Presentation 228 slides with 21...
Project Management (Comprehensive) PowerPoint Presentation 228 slides with 21...Project Management (Comprehensive) PowerPoint Presentation 228 slides with 21...
Project Management (Comprehensive) PowerPoint Presentation 228 slides with 21...
 
File 2 removed 1 slide 1
File 2 removed 1 slide 1File 2 removed 1 slide 1
File 2 removed 1 slide 1
 
File 2 extra slide 2
File 2 extra slide 2File 2 extra slide 2
File 2 extra slide 2
 
File 2 four extra slides 2
File 2 four extra slides 2File 2 four extra slides 2
File 2 four extra slides 2
 
File 2 original
File 2 originalFile 2 original
File 2 original
 
File 2 removed 1 slide 2
File 2 removed 1 slide 2File 2 removed 1 slide 2
File 2 removed 1 slide 2
 
File 2 removed 5 words 2
File 2 removed 5 words 2File 2 removed 5 words 2
File 2 removed 5 words 2
 

More from Chris Carson

Favorite Delay Analysis Methodologies Town Hall SEI
Favorite Delay Analysis Methodologies Town Hall SEIFavorite Delay Analysis Methodologies Town Hall SEI
Favorite Delay Analysis Methodologies Town Hall SEI
Chris Carson
 
Use Of Schedule Logs 2012 Pmi Scop Conference
Use Of Schedule Logs   2012 Pmi Scop ConferenceUse Of Schedule Logs   2012 Pmi Scop Conference
Use Of Schedule Logs 2012 Pmi Scop Conference
Chris Carson
 
Pmicos 2011 Review And Analysis Of Mitigation Schedules
Pmicos 2011 Review And Analysis Of Mitigation SchedulesPmicos 2011 Review And Analysis Of Mitigation Schedules
Pmicos 2011 Review And Analysis Of Mitigation Schedules
Chris Carson
 
Mitigation And Performance Recovery Using Earned Value
Mitigation And Performance Recovery Using Earned ValueMitigation And Performance Recovery Using Earned Value
Mitigation And Performance Recovery Using Earned Value
Chris Carson
 
Roadmap To World Class Project Controls Pp
Roadmap To World Class Project Controls PpRoadmap To World Class Project Controls Pp
Roadmap To World Class Project Controls Pp
Chris Carson
 
Types Of Industry Scheduling
Types Of Industry SchedulingTypes Of Industry Scheduling
Types Of Industry Scheduling
Chris Carson
 
Use Of A Claims Triage Workshop To Choose An Analysis Method
Use Of A Claims Triage Workshop To Choose An Analysis MethodUse Of A Claims Triage Workshop To Choose An Analysis Method
Use Of A Claims Triage Workshop To Choose An Analysis Method
Chris Carson
 
Early Completion Schedules
Early Completion SchedulesEarly Completion Schedules
Early Completion Schedules
Chris Carson
 
Can A Subcontractor Have CP Delay When The Gc Does Not
Can A Subcontractor Have CP Delay When The Gc Does NotCan A Subcontractor Have CP Delay When The Gc Does Not
Can A Subcontractor Have CP Delay When The Gc Does Not
Chris Carson
 
Schedule-Centric View Of Contract Admin
Schedule-Centric View Of Contract AdminSchedule-Centric View Of Contract Admin
Schedule-Centric View Of Contract Admin
Chris Carson
 
Presentation Classification Of Schedule Types
Presentation Classification Of Schedule TypesPresentation Classification Of Schedule Types
Presentation Classification Of Schedule Types
Chris Carson
 
Claims Triage
Claims TriageClaims Triage
Claims Triage
Chris Carson
 
Using Symptoms To Develop Appropriate Claims Avoidance Documentation Wpl We...
Using Symptoms To Develop Appropriate Claims Avoidance Documentation   Wpl We...Using Symptoms To Develop Appropriate Claims Avoidance Documentation   Wpl We...
Using Symptoms To Develop Appropriate Claims Avoidance Documentation Wpl We...
Chris Carson
 
Mitigation Of Risks In Using Parallel Schedules
Mitigation Of Risks In Using Parallel SchedulesMitigation Of Risks In Using Parallel Schedules
Mitigation Of Risks In Using Parallel Schedules
Chris Carson
 
How To Structure A Successful Mediation
How To Structure A Successful MediationHow To Structure A Successful Mediation
How To Structure A Successful Mediation
Chris Carson
 
2010 AACEi Great Debate - Approval of Schedule Revisions
2010 AACEi Great Debate - Approval of Schedule Revisions2010 AACEi Great Debate - Approval of Schedule Revisions
2010 AACEi Great Debate - Approval of Schedule Revisions
Chris Carson
 
Planning A Complex Project
Planning A Complex ProjectPlanning A Complex Project
Planning A Complex Project
Chris Carson
 
Mitigation of Risk in Dual Schedules
Mitigation of Risk in Dual SchedulesMitigation of Risk in Dual Schedules
Mitigation of Risk in Dual Schedules
Chris Carson
 
Innovative Program Delivery - Airport
Innovative Program Delivery - AirportInnovative Program Delivery - Airport
Innovative Program Delivery - Airport
Chris Carson
 
Planning For Adverse Weather
Planning For Adverse WeatherPlanning For Adverse Weather
Planning For Adverse Weather
Chris Carson
 

More from Chris Carson (20)

Favorite Delay Analysis Methodologies Town Hall SEI
Favorite Delay Analysis Methodologies Town Hall SEIFavorite Delay Analysis Methodologies Town Hall SEI
Favorite Delay Analysis Methodologies Town Hall SEI
 
Use Of Schedule Logs 2012 Pmi Scop Conference
Use Of Schedule Logs   2012 Pmi Scop ConferenceUse Of Schedule Logs   2012 Pmi Scop Conference
Use Of Schedule Logs 2012 Pmi Scop Conference
 
Pmicos 2011 Review And Analysis Of Mitigation Schedules
Pmicos 2011 Review And Analysis Of Mitigation SchedulesPmicos 2011 Review And Analysis Of Mitigation Schedules
Pmicos 2011 Review And Analysis Of Mitigation Schedules
 
Mitigation And Performance Recovery Using Earned Value
Mitigation And Performance Recovery Using Earned ValueMitigation And Performance Recovery Using Earned Value
Mitigation And Performance Recovery Using Earned Value
 
Roadmap To World Class Project Controls Pp
Roadmap To World Class Project Controls PpRoadmap To World Class Project Controls Pp
Roadmap To World Class Project Controls Pp
 
Types Of Industry Scheduling
Types Of Industry SchedulingTypes Of Industry Scheduling
Types Of Industry Scheduling
 
Use Of A Claims Triage Workshop To Choose An Analysis Method
Use Of A Claims Triage Workshop To Choose An Analysis MethodUse Of A Claims Triage Workshop To Choose An Analysis Method
Use Of A Claims Triage Workshop To Choose An Analysis Method
 
Early Completion Schedules
Early Completion SchedulesEarly Completion Schedules
Early Completion Schedules
 
Can A Subcontractor Have CP Delay When The Gc Does Not
Can A Subcontractor Have CP Delay When The Gc Does NotCan A Subcontractor Have CP Delay When The Gc Does Not
Can A Subcontractor Have CP Delay When The Gc Does Not
 
Schedule-Centric View Of Contract Admin
Schedule-Centric View Of Contract AdminSchedule-Centric View Of Contract Admin
Schedule-Centric View Of Contract Admin
 
Presentation Classification Of Schedule Types
Presentation Classification Of Schedule TypesPresentation Classification Of Schedule Types
Presentation Classification Of Schedule Types
 
Claims Triage
Claims TriageClaims Triage
Claims Triage
 
Using Symptoms To Develop Appropriate Claims Avoidance Documentation Wpl We...
Using Symptoms To Develop Appropriate Claims Avoidance Documentation   Wpl We...Using Symptoms To Develop Appropriate Claims Avoidance Documentation   Wpl We...
Using Symptoms To Develop Appropriate Claims Avoidance Documentation Wpl We...
 
Mitigation Of Risks In Using Parallel Schedules
Mitigation Of Risks In Using Parallel SchedulesMitigation Of Risks In Using Parallel Schedules
Mitigation Of Risks In Using Parallel Schedules
 
How To Structure A Successful Mediation
How To Structure A Successful MediationHow To Structure A Successful Mediation
How To Structure A Successful Mediation
 
2010 AACEi Great Debate - Approval of Schedule Revisions
2010 AACEi Great Debate - Approval of Schedule Revisions2010 AACEi Great Debate - Approval of Schedule Revisions
2010 AACEi Great Debate - Approval of Schedule Revisions
 
Planning A Complex Project
Planning A Complex ProjectPlanning A Complex Project
Planning A Complex Project
 
Mitigation of Risk in Dual Schedules
Mitigation of Risk in Dual SchedulesMitigation of Risk in Dual Schedules
Mitigation of Risk in Dual Schedules
 
Innovative Program Delivery - Airport
Innovative Program Delivery - AirportInnovative Program Delivery - Airport
Innovative Program Delivery - Airport
 
Planning For Adverse Weather
Planning For Adverse WeatherPlanning For Adverse Weather
Planning For Adverse Weather
 

Recently uploaded

Unveiling the Dynamic Personalities, Key Dates, and Horoscope Insights: Gemin...
Unveiling the Dynamic Personalities, Key Dates, and Horoscope Insights: Gemin...Unveiling the Dynamic Personalities, Key Dates, and Horoscope Insights: Gemin...
Unveiling the Dynamic Personalities, Key Dates, and Horoscope Insights: Gemin...
my Pandit
 
Zodiac Signs and Food Preferences_ What Your Sign Says About Your Taste
Zodiac Signs and Food Preferences_ What Your Sign Says About Your TasteZodiac Signs and Food Preferences_ What Your Sign Says About Your Taste
Zodiac Signs and Food Preferences_ What Your Sign Says About Your Taste
my Pandit
 
Maksym Vyshnivetskyi: PMO KPIs (UA) (#12)
Maksym Vyshnivetskyi: PMO KPIs (UA) (#12)Maksym Vyshnivetskyi: PMO KPIs (UA) (#12)
Maksym Vyshnivetskyi: PMO KPIs (UA) (#12)
Lviv Startup Club
 
Best Forex Brokers Comparison in INDIA 2024
Best Forex Brokers Comparison in INDIA 2024Best Forex Brokers Comparison in INDIA 2024
Best Forex Brokers Comparison in INDIA 2024
Top Forex Brokers Review
 
GKohler - Retail Scavenger Hunt Presentation
GKohler - Retail Scavenger Hunt PresentationGKohler - Retail Scavenger Hunt Presentation
GKohler - Retail Scavenger Hunt Presentation
GraceKohler1
 
Digital Transformation Frameworks: Driving Digital Excellence
Digital Transformation Frameworks: Driving Digital ExcellenceDigital Transformation Frameworks: Driving Digital Excellence
Digital Transformation Frameworks: Driving Digital Excellence
Operational Excellence Consulting
 
一比一原版新西兰奥塔哥大学毕业证(otago毕业证)如何办理
一比一原版新西兰奥塔哥大学毕业证(otago毕业证)如何办理一比一原版新西兰奥塔哥大学毕业证(otago毕业证)如何办理
一比一原版新西兰奥塔哥大学毕业证(otago毕业证)如何办理
taqyea
 
Satta Matka Dpboss Matka Guessing Kalyan Chart Indian Matka Kalyan panel Chart
Satta Matka Dpboss Matka Guessing Kalyan Chart Indian Matka Kalyan panel ChartSatta Matka Dpboss Matka Guessing Kalyan Chart Indian Matka Kalyan panel Chart
Satta Matka Dpboss Matka Guessing Kalyan Chart Indian Matka Kalyan panel Chart
➒➌➎➏➑➐➋➑➐➐Dpboss Matka Guessing Satta Matka Kalyan Chart Indian Matka
 
Industrial Tech SW: Category Renewal and Creation
Industrial Tech SW:  Category Renewal and CreationIndustrial Tech SW:  Category Renewal and Creation
Industrial Tech SW: Category Renewal and Creation
Christian Dahlen
 
Chapter 7 Final business management sciences .ppt
Chapter 7 Final business management sciences .pptChapter 7 Final business management sciences .ppt
Chapter 7 Final business management sciences .ppt
ssuser567e2d
 
The Genesis of BriansClub.cm Famous Dark WEb Platform
The Genesis of BriansClub.cm Famous Dark WEb PlatformThe Genesis of BriansClub.cm Famous Dark WEb Platform
The Genesis of BriansClub.cm Famous Dark WEb Platform
SabaaSudozai
 
How are Lilac French Bulldogs Beauty Charming the World and Capturing Hearts....
How are Lilac French Bulldogs Beauty Charming the World and Capturing Hearts....How are Lilac French Bulldogs Beauty Charming the World and Capturing Hearts....
How are Lilac French Bulldogs Beauty Charming the World and Capturing Hearts....
Lacey Max
 
DearbornMusic-KatherineJasperFullSailUni
DearbornMusic-KatherineJasperFullSailUniDearbornMusic-KatherineJasperFullSailUni
DearbornMusic-KatherineJasperFullSailUni
katiejasper96
 
The APCO Geopolitical Radar - Q3 2024 The Global Operating Environment for Bu...
The APCO Geopolitical Radar - Q3 2024 The Global Operating Environment for Bu...The APCO Geopolitical Radar - Q3 2024 The Global Operating Environment for Bu...
The APCO Geopolitical Radar - Q3 2024 The Global Operating Environment for Bu...
APCO
 
Brian Fitzsimmons on the Business Strategy and Content Flywheel of Barstool S...
Brian Fitzsimmons on the Business Strategy and Content Flywheel of Barstool S...Brian Fitzsimmons on the Business Strategy and Content Flywheel of Barstool S...
Brian Fitzsimmons on the Business Strategy and Content Flywheel of Barstool S...
Neil Horowitz
 
Lundin Gold Corporate Presentation - June 2024
Lundin Gold Corporate Presentation - June 2024Lundin Gold Corporate Presentation - June 2024
Lundin Gold Corporate Presentation - June 2024
Adnet Communications
 
Creative Web Design Company in Singapore
Creative Web Design Company in SingaporeCreative Web Design Company in Singapore
Creative Web Design Company in Singapore
techboxsqauremedia
 
Anny Serafina Love - Letter of Recommendation by Kellen Harkins, MS.
Anny Serafina Love - Letter of Recommendation by Kellen Harkins, MS.Anny Serafina Love - Letter of Recommendation by Kellen Harkins, MS.
Anny Serafina Love - Letter of Recommendation by Kellen Harkins, MS.
AnnySerafinaLove
 
Business storytelling: key ingredients to a story
Business storytelling: key ingredients to a storyBusiness storytelling: key ingredients to a story
Business storytelling: key ingredients to a story
Alexandra Fulford
 
Pitch Deck Teardown: Kinnect's $250k Angel deck
Pitch Deck Teardown: Kinnect's $250k Angel deckPitch Deck Teardown: Kinnect's $250k Angel deck
Pitch Deck Teardown: Kinnect's $250k Angel deck
HajeJanKamps
 

Recently uploaded (20)

Unveiling the Dynamic Personalities, Key Dates, and Horoscope Insights: Gemin...
Unveiling the Dynamic Personalities, Key Dates, and Horoscope Insights: Gemin...Unveiling the Dynamic Personalities, Key Dates, and Horoscope Insights: Gemin...
Unveiling the Dynamic Personalities, Key Dates, and Horoscope Insights: Gemin...
 
Zodiac Signs and Food Preferences_ What Your Sign Says About Your Taste
Zodiac Signs and Food Preferences_ What Your Sign Says About Your TasteZodiac Signs and Food Preferences_ What Your Sign Says About Your Taste
Zodiac Signs and Food Preferences_ What Your Sign Says About Your Taste
 
Maksym Vyshnivetskyi: PMO KPIs (UA) (#12)
Maksym Vyshnivetskyi: PMO KPIs (UA) (#12)Maksym Vyshnivetskyi: PMO KPIs (UA) (#12)
Maksym Vyshnivetskyi: PMO KPIs (UA) (#12)
 
Best Forex Brokers Comparison in INDIA 2024
Best Forex Brokers Comparison in INDIA 2024Best Forex Brokers Comparison in INDIA 2024
Best Forex Brokers Comparison in INDIA 2024
 
GKohler - Retail Scavenger Hunt Presentation
GKohler - Retail Scavenger Hunt PresentationGKohler - Retail Scavenger Hunt Presentation
GKohler - Retail Scavenger Hunt Presentation
 
Digital Transformation Frameworks: Driving Digital Excellence
Digital Transformation Frameworks: Driving Digital ExcellenceDigital Transformation Frameworks: Driving Digital Excellence
Digital Transformation Frameworks: Driving Digital Excellence
 
一比一原版新西兰奥塔哥大学毕业证(otago毕业证)如何办理
一比一原版新西兰奥塔哥大学毕业证(otago毕业证)如何办理一比一原版新西兰奥塔哥大学毕业证(otago毕业证)如何办理
一比一原版新西兰奥塔哥大学毕业证(otago毕业证)如何办理
 
Satta Matka Dpboss Matka Guessing Kalyan Chart Indian Matka Kalyan panel Chart
Satta Matka Dpboss Matka Guessing Kalyan Chart Indian Matka Kalyan panel ChartSatta Matka Dpboss Matka Guessing Kalyan Chart Indian Matka Kalyan panel Chart
Satta Matka Dpboss Matka Guessing Kalyan Chart Indian Matka Kalyan panel Chart
 
Industrial Tech SW: Category Renewal and Creation
Industrial Tech SW:  Category Renewal and CreationIndustrial Tech SW:  Category Renewal and Creation
Industrial Tech SW: Category Renewal and Creation
 
Chapter 7 Final business management sciences .ppt
Chapter 7 Final business management sciences .pptChapter 7 Final business management sciences .ppt
Chapter 7 Final business management sciences .ppt
 
The Genesis of BriansClub.cm Famous Dark WEb Platform
The Genesis of BriansClub.cm Famous Dark WEb PlatformThe Genesis of BriansClub.cm Famous Dark WEb Platform
The Genesis of BriansClub.cm Famous Dark WEb Platform
 
How are Lilac French Bulldogs Beauty Charming the World and Capturing Hearts....
How are Lilac French Bulldogs Beauty Charming the World and Capturing Hearts....How are Lilac French Bulldogs Beauty Charming the World and Capturing Hearts....
How are Lilac French Bulldogs Beauty Charming the World and Capturing Hearts....
 
DearbornMusic-KatherineJasperFullSailUni
DearbornMusic-KatherineJasperFullSailUniDearbornMusic-KatherineJasperFullSailUni
DearbornMusic-KatherineJasperFullSailUni
 
The APCO Geopolitical Radar - Q3 2024 The Global Operating Environment for Bu...
The APCO Geopolitical Radar - Q3 2024 The Global Operating Environment for Bu...The APCO Geopolitical Radar - Q3 2024 The Global Operating Environment for Bu...
The APCO Geopolitical Radar - Q3 2024 The Global Operating Environment for Bu...
 
Brian Fitzsimmons on the Business Strategy and Content Flywheel of Barstool S...
Brian Fitzsimmons on the Business Strategy and Content Flywheel of Barstool S...Brian Fitzsimmons on the Business Strategy and Content Flywheel of Barstool S...
Brian Fitzsimmons on the Business Strategy and Content Flywheel of Barstool S...
 
Lundin Gold Corporate Presentation - June 2024
Lundin Gold Corporate Presentation - June 2024Lundin Gold Corporate Presentation - June 2024
Lundin Gold Corporate Presentation - June 2024
 
Creative Web Design Company in Singapore
Creative Web Design Company in SingaporeCreative Web Design Company in Singapore
Creative Web Design Company in Singapore
 
Anny Serafina Love - Letter of Recommendation by Kellen Harkins, MS.
Anny Serafina Love - Letter of Recommendation by Kellen Harkins, MS.Anny Serafina Love - Letter of Recommendation by Kellen Harkins, MS.
Anny Serafina Love - Letter of Recommendation by Kellen Harkins, MS.
 
Business storytelling: key ingredients to a story
Business storytelling: key ingredients to a storyBusiness storytelling: key ingredients to a story
Business storytelling: key ingredients to a story
 
Pitch Deck Teardown: Kinnect's $250k Angel deck
Pitch Deck Teardown: Kinnect's $250k Angel deckPitch Deck Teardown: Kinnect's $250k Angel deck
Pitch Deck Teardown: Kinnect's $250k Angel deck
 

Schedule Design AACE

  • 1. A Framework for Schedule Design Planning for Schedule Development Chris Carson, PSP Patrick Kelly, PSP Corporate Director of Project Controls Project Controls Manager Chris.Carson@alphacorporation.com Patrick.Kelly@alphacorporation.com (O) 757-533-9368 (M) 757-342-5524 (O) 757-533-9368 (M) 757-217-6820 AACE International’s 52nd Annual Meeting and ICEC’s 6th World Congress on Cost Engineering, Project Management, and Quantity Surveying
  • 2. AACE International’s 52nd Annual Meeting & ICEC’s 6th World Congress Schedule Design - Introduction • A proper schedule addresses the needs of project management in balance with the requirements of the specifications, providing accurate predictive capabilities with an appropriate level of detail that ensures a nimble yet accurate management tool. • Such schedules are not put together mindlessly; they must be intentionally designed to achieve this purpose. 2
  • 3. AACE International’s 52nd Annual Meeting & ICEC’s 6th World Congress Schedule Design - Introduction • Schedules are rarely Designed; rather, Schedulers tend to move directly into Schedule Planning and Development. – The focus is generally on the mechanics of Development, not the reason for the schedule. – Decisions such as level of detail, reporting needs, end user needs, abilities of the input user, and others, are allowed to develop as an offshoot of Schedule Planning and Development. 3
  • 4. AACE International’s 52nd Annual Meeting & ICEC’s 6th World Congress Schedule Design - Introduction • Following a Framework for Schedule Design will ensure that project schedules will meet all participant’s needs, from Project Superintendents to the Project’s End User. – Building a schedule is a project in itself, and Design is planning for a Schedule Planning and Development. – Good Design will yield significant benefits by achieving project team buy-in at the Design phase. • Purpose: to provide a detailed and structured approach to designing a schedule, with a checklist and question and answer approach that allows the scheduler / planner to leverage their planning time into a good layout for the full Schedule Planning and Development process. 4
  • 5. AACE International’s 52nd Annual Meeting & ICEC’s 6th World Congress Schedule Design - Background • Why design a schedule? – A schedule meets the criteria for a “project” in itself. – A schedule is a guideline or plan for a project. – A schedule provides a a methodical approach for a project. – Keeps the Schedule Planning and Development on track. – Prevents rework due to late understanding of needs. – Allows buy-in from end users prior to Development. – Makes the Schedule Planning and Development session much more meaningful. – Documents the assumptions and intention of the schedule. • For reviewer and approver. • For future reference. • To facilitate changes in schedulers. • Place to capture Lessons Learned. 5
  • 6. AACE International’s 52nd Annual Meeting & ICEC’s 6th World Congress Schedule Design - Background • What is Schedule Design, and how does it differ from Schedule Planning and Development? • What is the uniform taxonomy of these terms, and what is their relationship to one another? • Total Cost Management Framework provides good definitions of the differences. 6
  • 7. AACE International’s 52nd Annual Meeting & ICEC’s 6th World Congress Schedule Design - Background • Design vs. Development. – Schedule Design exists primarily in 7.1 Project Scope and Execution Strategy Development. – Planning and Development exist in 7.2 Schedule Planning and Development. 7
  • 8. AACE International’s 52nd Annual Meeting & ICEC’s 6th World Congress Schedule Design - Background • 7.1 Project Scope and Execution Strategy Development. – “The project scope and execution strategy development process translates the project implementation basis (i.e., asset scope, objectives, constraints, and assumptions) into controllable project scope definition and an execution strategy. – The project scope defines what the work is (i.e., the work that must be performed to deliver a product, service, or result with the specified features and functions). – The execution strategy establishes criteria for how the work will be implemented (i.e., the general approach through which the work will be performed.)” 8
  • 9. AACE International’s 52nd Annual Meeting & ICEC’s 6th World Congress Schedule Design - Background • TCM 7.1 Process Map. 9
  • 10. AACE International’s 52nd Annual Meeting & ICEC’s 6th World Congress Schedule Design - Background • 7.2 Schedule Planning and Development. – “Schedule planning and development are the processes for the planning of work over time in consideration of the costs and resources for that work. Schedule planning and schedule development are separate, but related, sub- processes that call for different skills and knowledge emphasis. • Schedule planning consists of breaking work package scope into activities, and logically ordering those activities into the sequence in which they will be best performed. Result is a detailed, but conceptual, non-resource driven, schedule. • Schedule development consists of enhancing the model created in planning and allocating available resources, to iteratively generate the as-planned schedule model that becomes the schedule control baseline. 10
  • 11. AACE International’s 52nd Annual Meeting & ICEC’s 6th World Congress Schedule Design - Background • TCM 7.2 Process Map. Schedule Design is a prerequisite to Schedule Planning 11
  • 12. AACE International’s 52nd Annual Meeting & ICEC’s 6th World Congress Schedule Design - Background • Summary of Process Maps. RP 23R-02 Identification of Activities establishes Schedule the start of this Design phase. TCM 7.1 Schedule Planning Defines the work that must be performed to deliver the Project, the Schedule general approach Development through which the work will be performed, and the schedule architecture TCM 7.2 needed to support. 12
  • 13. AACE International’s 52nd Annual Meeting & ICEC’s 6th World Congress Schedule Design - Background • Note on PSP Scope of Knowledge RP 14R-90. – “Schedule Development” is defined to encompass what TCM refers to as Design and Development. – RP 14R-90 also uses the terms “Planning” and “Scheduling” to define some of these functions. – TCM and the PSP Scope of Knowledge have unresolved overlap in terminology. • Clearly, both Design and Development are part of the Skills and Knowledge of a Planning and Scheduling Professional. • This presentation uses TCM framework to drive definitions and delineate the Design process. 13
  • 14. AACE International’s 52nd Annual Meeting & ICEC’s 6th World Congress Schedule Design - Background • Design vs. Development – How PMI & PMBOK handles it? – PMBOK identifies six Project Time Management processes, usually defined as part of the project lifecycle, Section 2.1 of PMBOK. • Activity Definition. • Activity Sequencing. • Activity Resource Estimating. • Activity Duration Estimating. • Schedule Development. • Schedule Control. – These processes are preceded by a planning effort by the project management team, which is part of PMBOK’s “Develop Project Management Plan”, PMBOK Section 4.3 (which sets the format and establishes criteria for developing the project schedule). – These processes are documented in what PMBOK calls a Schedule Management Plan, which is contained in the project management plan, in the introduction to Section 4.3, Project Integration Management. 14
  • 15. AACE International’s 52nd Annual Meeting & ICEC’s 6th World Congress Schedule Design - Background • PMBOK Process Inputs. – The inputs for the different Time Management Processes are listed as: • Activity list. • Product description. • Mandatory dependencies. • Discretionary dependencies. • External dependencies. • Resource requirements. • Resource capabilities. • Historical information. • Identified risks. • Constraints. • Assumptions. – All of these items, along with the Schedule Management Plan, are part of Schedule Design, but PMBOK does not offer clear definition and delineation of Schedule Design. – The Time Management Processes do not include Schedule Design. 15
  • 16. AACE International’s 52nd Annual Meeting & ICEC’s 6th World Congress Schedule Design - Background • Design vs. Development – why emphasize the distinction? – Design tends to be ignored in favor of jumping right into development. • Many schedulers elect to begin creating activities instead of Designing. • Work is subsequently repetitive, with lots of potential for rework. • Results tend to be disorganized. • Avoid planning mistakes and problems. 16
  • 17. AACE International’s 52nd Annual Meeting & ICEC’s 6th World Congress Schedule Design - Background • Poorly designed Activity Coding: Repetitive Activity Coding and Grouping Levels due to lack of forethought in structure 17
  • 18. AACE International’s 52nd Annual Meeting & ICEC’s 6th World Congress Schedule Design - Background • Activities driving the Work Breakdown Structure: Inconsistent levels of detail due to unorganized activity entry. Hinders grouping and comparison. 18
  • 19. AACE International’s 52nd Annual Meeting & ICEC’s 6th World Congress Schedule Design - Background • Lack of Good Area Definition preventing activity closeout: Areas are so broadly defined that activities sit at nearly complete for large parts of the project. Hinders productivity analysis, good cost loading, accurate as- built dates. 19
  • 20. AACE International’s 52nd Annual Meeting & ICEC’s 6th World Congress Schedule Design - Background • Inconsistency in level of detail throughout trades: Some trades are heavily developed while others are left with summary-level activities only. 20
  • 21. AACE International’s 52nd Annual Meeting & ICEC’s 6th World Congress Schedule Design – Components of the Design Process Scope of Design vs. Development. Design – Conceptualizing the schedule. Planning the Schedule. Starting with the end in mind. Providing concept of final product. Creating organizational structure to fulfill the concept. Timing. Must be done prior to Schedule Planning and Development. 21
  • 22. AACE International’s 52nd Annual Meeting & ICEC’s 6th World Congress Schedule Design – Components of the Design Process Documentation and use of Schedule Design. Create a book or binder. Use the highest level of checklist outline items as tabs. Use the book as basis for schedule submittal documentation. Keep the book current during project. Use the book for handoff between schedulers. Share a copy of the book with superintendent/PM. 22
  • 23. AACE International’s 52nd Annual Meeting & ICEC’s 6th World Congress Schedule Design – Components of the Design Process Schedule Design Process. Development of Controllable Project Scope Definition. Development of Execution Strategy. 23
  • 24. AACE International’s 52nd Annual Meeting & ICEC’s 6th World Congress Schedule Design Checklist Development of Controllable Project Scope Definition Collection of Inputs Project Implementation Basis (or Project Plan) (TCM 4.1). Project Historical Information (TCM 10.4). Change Management Plan (TCM 10.3). Team Players. Other Planning Process Plans (TCM 7.2 to 7.7). Develop Work Breakdown Structure 24
  • 25. AACE International’s 52nd Annual Meeting & ICEC’s 6th World Congress Schedule Design Checklist - Development of Controllable Project Scope Definition Project Implementation Basis (or Project Plan) (TCM 4.1). Contract (TCM 7.7). Notice to Proceed or Release Letter. Project Drawings. Area Designation Plan. Sequencing plan. Specifications. Scheduling Specification. Scope of Work definition. Liquidated Damages schedule. Owner-provided items & scope. 25
  • 26. AACE International’s 52nd Annual Meeting & ICEC’s 6th World Congress Schedule Design Checklist - Development of Controllable Project Scope Definition Schedule Specification – General Contents. 26
  • 27. AACE International’s 52nd Annual Meeting & ICEC’s 6th World Congress Schedule Design Checklist - Development of Controllable Project Scope Definition Project Implementation Basis (or Project Plan) (TCM 4.1). Owner milestones, phases, or master schedules. Estimate & quantity surveys/bills of materials. (TCM 7.3). Any existing internal WBS. Owner separate contracts and scope (coordination between this and other external projects). Value Analysis and Engineering (TCM 7.5). 27
  • 28. AACE International’s 52nd Annual Meeting & ICEC’s 6th World Congress Schedule Design Checklist - Development of Controllable Project Scope Definition Project Historical Information (TCM 10.4). Collection of data from the Project Historical Database. Actual Schedule Data. Actual Resource Data. Project Lessons Learned. Incorporation of this data aids in development of Execution Plan. 28
  • 29. AACE International’s 52nd Annual Meeting & ICEC’s 6th World Congress Schedule Design Checklist - Development of Controllable Project Scope Definition Change Management Plan (TCM 10.3). Notification requirements. Methodology allowed. Quality control process. Process flowchart. 29
  • 30. AACE International’s 52nd Annual Meeting & ICEC’s 6th World Congress Schedule Design Checklist - Development of Controllable Project Scope Definition Change Management Plan Control Process. 30
  • 31. AACE International’s 52nd Annual Meeting & ICEC’s 6th World Congress Schedule Design Checklist - Development of Controllable Project Scope Definition Change Management Plan Process Flowchart. Collect Admin Verify All Progress Data Data No Critical Path Delay? Request for Collect Field Status Update Compare to Update Data Progress Data Schedule Schedule Baseline Yes Identify Contract Changes Identify Previous Period Critical Path Publish Research Updated Quantify Identify Causal Identify Changes Documents For Schedule Delays Delay Activities To Critical Path Driving Delays Is the Assess Any Perform Owner Yes Yes Prepare Responsibility Concurrent Concurrent Delay Responsible Recovery For Delays Delays? Analysis For Delay? Schedule No No Resolve Subcontractor Is a Is the Contributions No No Verify Single Owner Subcontractor Source Delay Responsible Responsible Responsibility For Delay? For Delay? Discuss Delay & Mitigation with Yes Subcontractor Yes Proposed Schedule Update With Change Management Discuss Delay Prepare Delay & Mitigation Analysis With Owner & Change Order 31
  • 32. AACE International’s 52nd Annual Meeting & ICEC’s 6th World Congress Schedule Design Checklist - Development of Controllable Project Scope Definition Team Players. Organizational Chart. Identify the Schedule Users. Who has Input? Who Updates? Who Checks for Accuracy? Who Reviews? Who approves? Identify Responsibility Assignment Matrix (RAM). 32
  • 33. AACE International’s 52nd Annual Meeting & ICEC’s 6th World Congress Schedule Design Checklist - Development of Controllable Project Scope Definition RAM Example (based on PMBOK RACI Chart). 33
  • 34. AACE International’s 52nd Annual Meeting & ICEC’s 6th World Congress Schedule Design Checklist - Development of Controllable Project Scope Definition Other Planning Process Plans (TCM 7.2 to 7.7). Many of these processes have been covered in other items. We recommend reading the publication. 34
  • 35. AACE International’s 52nd Annual Meeting & ICEC’s 6th World Congress Schedule Design Checklist - Development of Controllable Project Scope Definition Develop Work Breakdown Structure. Translate asset scope into component deliverables (“decomposition”). Ensure consistency in WBS levels, to facilitate comparison. 35
  • 36. AACE International’s 52nd Annual Meeting & ICEC’s 6th World Congress Schedule Design – Components of the Design Process Schedule Design Process. Development of Controllable Project. Scope Definition. Development of Execution Strategy. 36
  • 37. AACE International’s 52nd Annual Meeting & ICEC’s 6th World Congress Schedule Design Checklist Development of Controllable Execution Strategy. Organizational Breakdown Structure. Work Package Development. Schedule Design Output (Software Driven). Outline Schedule. Risk Analysis. Definition of Processes. 37
  • 38. AACE International’s 52nd Annual Meeting & ICEC’s 6th World Congress Schedule Design Checklist - Development of Execution Strategy Organizational Breakdown Structure. From: DOE Training “EVM Tutorial – WBS” by Booze-Allen-Hamilton 38
  • 39. AACE International’s 52nd Annual Meeting & ICEC’s 6th World Congress Schedule Design Checklist - Development of Execution Strategy Work Package Development. By Contract. As assigned by Client. VI. Work Packages Division 2 and 5 Specifications require the following Work Packages: – Superstructure Waterproofing – Corrosion Protection of Structural Steelwork – Movements and Tolerances Specification for Structural Steel – Structural Steel Superstructure – Cast in Place Concrete 39
  • 40. AACE International’s 52nd Annual Meeting & ICEC’s 6th World Congress Schedule Design Checklist - Development of Execution Strategy Schedule Design Output (Software Driven) Software Identification. Specific software. Required minimum and versions allowed. Enterprise specific issues. Users identified. Schedules used for import or data source. Levels of access. Validation process. For master schedules, establish data dates. 40
  • 41. AACE International’s 52nd Annual Meeting & ICEC’s 6th World Congress Schedule Design Checklist - Development of Execution Strategy Schedule Design Output (Software Driven). Purpose of Work Product. What the Schedule can be used for (purpose). Superintendent work schedule. Buyout schedule. Justification of time requests. Claims/Dispute Resolution. Reports Generated from the Schedule. Who receives reports. List of reports. Samples of reports. Glossary/Lexicon of ambiguous terms. 41
  • 42. AACE International’s 52nd Annual Meeting & ICEC’s 6th World Congress Schedule Design Checklist - Development of Execution Strategy – Example of Lexicon General Notes Regarding this Report: • “Program,” “Programme,” and “Baseline CPM,” and “Schedule” all have the same definition and are used interchangeably. • “Snagging” and “Punch-out” have the same definition and are used interchangeably. • “Fixed” and “Rough-in” have roughly the same definition. For clarification purposes, “Fixed” has been used in this Program. • “Conventional concrete” is defined as post-tension poured-in-place concrete. • “Wild Air” is defined as a stage in construction, for which the building is closed in by perimeter walls and ventilation has started. (Ventilation only, not complete environmental controls or functioning air conditioning.) This term is used in lieu of “environmental controls,” or “drying –in” as wet weather is not a real factor in Dubai. • “Raft” construction consists of the foundation including but not limited to piles, grade beams, footers, and slab-on-grade. 42
  • 43. AACE International’s 52nd Annual Meeting & ICEC’s 6th World Congress Schedule Design Checklist - Development of Execution Strategy Schedule Design Output (Software Driven) Level of Detail. Determine approach: Bottom-up (starting with detailed activities). Top-down (starting with summary schedule). Both (prepare Top-down, then Bottom-up). Identify frequency of updates. Establish smallest activity duration range. 43
  • 44. AACE International’s 52nd Annual Meeting & ICEC’s 6th World Congress Schedule Design Checklist - Development of Execution Strategy Schedule Design Output (Software Driven) Codes Dictionary. For tracking and monitoring work: Work Phase. Structure. Area. Floor or Station. Location. For Project Management: Responsibility. Work Shifts. Costs. Resource. Specification. Change management. 44
  • 45. AACE International’s 52nd Annual Meeting & ICEC’s 6th World Congress Schedule Design Checklist - Development of Execution Strategy Schedule Design Output (Software Driven) Weather Planning & Calendars. Weather planning. Expected adverse weather. Identify source or specification requirement. Identify methodology. Identify accounting method for actual weather. Establish number of calendars needed. Define calendars and application. 45
  • 46. AACE International’s 52nd Annual Meeting & ICEC’s 6th World Congress Schedule Design Checklist - Development of Execution Strategy Example of Calendar Section: • Calendars are defined as follows: – Calendar 1 – 24 hours a day, 7 days a week. – Calendar 2 – 24 hours a day, only Fridays off. (This is the Default Calendar.) – Calendar 3 – Night Shift, only Fridays off. – Calendar 4 – Night Shift, 24 hours a day, 7 days a week. – Please note that 01140/1.9.a. requires that the Contractor notify the Client regarding multiple shifts, etc. This has been accomplished by using Day and Night sift calendars as well as by incorporating multiple crew codes into the Program. (For more on Crews, please refer to the Resources section of this report.) 46
  • 47. AACE International’s 52nd Annual Meeting & ICEC’s 6th World Congress Schedule Design Checklist - Development of Execution Strategy Schedule Design Output (Software Driven) Cost & Resources. Estimate & correlation to cost loading. Bill of Quantities & use in resources. Resource Crew descriptions. Equipment descriptions. How actual production will be monitored. Earned Value Management System. 47
  • 48. AACE International’s 52nd Annual Meeting & ICEC’s 6th World Congress Schedule Design Checklist - Development of Execution Strategy Outline Schedule. Outline Schedule. Key Activities being tracked. Client Milestones. Long Lead Items. WBS Structure. Other Contracts on Project. Narrative Basis and Assumptions. Procedure Used to create the Schedule. Definitions/lexicon. Description of sequence of work per structure. 48
  • 49. AACE International’s 52nd Annual Meeting & ICEC’s 6th World Congress Schedule Design Checklist - Development of Execution Strategy Narrative Basis. 49
  • 50. AACE International’s 52nd Annual Meeting & ICEC’s 6th World Congress Schedule Design Checklist - Development of Execution Strategy Example of Schedule Narrative Explanation: Schedules: • 01320/1.04 - Tender Works Schedule: A detailed schedule depicting construction sequencing and dates at the Tender stage. • 01320/1.05 – Schedule of Works: This is a detailed Baseline CPM schedule. This schedule will be cost loaded, resource loaded with manpower and equipment, and incorporate the Bill of Quantities. This schedule will not only show construction activities, but will also demonstrate procurement and submittal activities. The submission of this schedule will include initial project histograms (for manpower, definable features of work, and submittal items) and a S-Curves (for costs, manpower, and submittal items.) Finally, this package will include any support data including but not limited to a Narrative explaining calendar usage, estimated average manpower, planned procurement of materials and equipment, etc. 50
  • 51. AACE International’s 52nd Annual Meeting & ICEC’s 6th World Congress Schedule Design Checklist - Development of Execution Strategy Risk Analysis (TCM 7.6). Risks and Constructability. Brainstorming of issues. Known problems & constructability (threats & opportunities). Provisional Items. Predicted Problems. Lessons Learned. Outside influences. Site condition concerns. Develop Risk Management Plan. Initial process during baseline schedule development. Process for use during updates. 51
  • 52. AACE International’s 52nd Annual Meeting & ICEC’s 6th World Congress Schedule Design Checklist - Development of Execution Strategy Risk Management Plan. – Based on PMBOK. 52
  • 53. AACE International’s 52nd Annual Meeting & ICEC’s 6th World Congress Schedule Design Checklist - Development of Execution Strategy Risk Analysis (TCM 7.6). Time Contingencies. Amounts. Specific trade (from risk management plan). Specific contractor contingency. How carried. Use historical data for reference. 53
  • 54. AACE International’s 52nd Annual Meeting & ICEC’s 6th World Congress Schedule Design Checklist - Development of Execution Strategy Specific Trade Contingency Determination – Based on Historical Data. Time Performance Ratio 12.0 10.0 8.0 TPR 6.0 4.0 2.0 0.0 ev s ry s ry nt E l c al ws e / W f ing l E q hes s rk in ca g or et al nt on m Fu me wo in do ni t ri et at cr pe o Ad s ish as ha ec te oo Ro M ni p on in ar ui Fi M Si rn ec El C C M rs D Type of Work 54
  • 55. AACE International’s 52nd Annual Meeting & ICEC’s 6th World Congress Schedule Design Checklist - Development of Execution Strategy Definition of Processes. Update Process. Frequency. Data request and transmission. Validation. Process flowchart. Collect Admin Verify All Progress Data Data Request for Collect Field Status Update Compare to Update Data Progress Data Schedule Schedule Baseline Identify Contract Changes 55
  • 56. AACE International’s 52nd Annual Meeting & ICEC’s 6th World Congress Schedule Design Checklist - Development of Execution Strategy Establish Update process. 56
  • 57. AACE International’s 52nd Annual Meeting & ICEC’s 6th World Congress Schedule Design Checklist - Development of Execution Strategy Definition of Processes. Recovery Process. Identify what logic changes are acceptable without formal approval. Identify what constitutes a Revision requiring approval. Provide process description or flow chart. 57
  • 58. AACE International’s 52nd Annual Meeting & ICEC’s 6th World Congress Schedule Design Checklist - Development of Execution Strategy Definition of Processes. Dispute Resolution Process. Review program for claims avoidance. Reinforce planning for claims avoidance. Identify specific program for claims avoidance during schedule updates and change management. Identify steps if change management process fails or stalls. Follow specifications. Provide time frames for stages in process. Provide process description or flow chart. 58
  • 59. AACE International’s 52nd Annual Meeting & ICEC’s 6th World Congress Schedule Design Checklist - Development of Execution Strategy Reporting. Define all reports. Provide examples. 59
  • 60. AACE International’s 52nd Annual Meeting & ICEC’s 6th World Congress Schedule Design • Conclusion. – At the end of this process, TCM 7.2 should be ready to begin. – Although this requires an initial investment in time, there will be a savings during Planning/Development, and a reduction in rework. – For success in Schedule Planning and Development, Schedule Design should be a completely different process. – Process must be done prior to Development. – Process and results documented. – Documentation done in formal Schedule Design Book. – Book used to provide continuity between schedulers or project managers. 60
  • 61. AACE International’s 52nd Annual Meeting & ICEC’s 6th World Congress Schedule Design • Resources. – See Lance Stephenson’s “Schedule Basis Memorandum” paper, also addresses schedule levels. – See AACEi’s Total Cost Management. – See PMBOK for Risk Management process. • Recommendations. – Get involved with AACEi and the Recommended Practices development. – Get involved with the CoS SEI Project developing Best Practices and Guidelines for Scheduling. – Get involved with CMAA in the Time Management development. 61
  • 62. AACE International’s 52nd Annual Meeting & ICEC’s 6th World Congress Schedule Design Questions? Recommendations? 62
  • 63. A Framework for Schedule Design Planning for Schedule Development Chris Carson, PSP Patrick Kelly, PSP Corporate Director of Project Controls Project Controls Manager Chris.Carson@alphacorporation.com Patrick.Kelly@alphacorporation.com (O) 757-533-9368 (M) 757-342-5524 (O) 757-533-9368 (M) 757-217-6820 AACE International’s 52nd Annual Meeting and ICEC’s 6th World Congress on Cost Engineering, Project Management, and Quantity Surveying
  • 64. A Framework for Schedule Design Planning for Schedule Development Chris Carson, PSP Patrick Kelly, PSP Corporate Director of Project Controls Project Controls Manager Alpha Construction & Engineering Corporation Alpha Construction & Engineering Corporation Chris.Carson@alphacorporation.com Patrick.Kelly@alphacorporation.com (O) 757-533-9368 (M) 757-342-5524 (O) 757-533-9368 (M) 757-217-6820 AACE International’s 52nd Annual Meeting and ICEC’s 6th World Congress on Cost Engineering, Project Management, and Quantity Surveying