SlideShare a Scribd company logo
1 of 21
Schedule Assessment and
       Risk Analysis
                         Richard M. Greathouse
               Lead Programmatic Analysis Group
                Heidemarie S. Borchardt, PMP
                            Lead Schedule Analyst
Contributors: Kelley Cyr, Michele King, Kelly Moses,
                                        Robin Smith
 Independent Program Assessment Office (IPAO)
Overview

•   The schedule is a powerful tool for project
    management. Schedule risk analysis:
       Identifies potential risks
       Identifies impacts of risks to project schedule
•   IPAO has the opportunity to meet with many
    programs and projects:
       Lessons Learned
       Future Plans




                                                          2
IPAO Forensics Analysis
                      Excerpt
Strengths:
•   Risk management, budget, and schedule tend to gravitate to very few
    (typically one) overall strengths for each program.
•    Resources Other Than Budget received the fewest strengths.
Issues:
•   Schedule issues were the most frequent issues identified and may be an
    opportunity for improvement.
     – Schedule issues may be caused by poor planning, poor schedule
       (duration) estimates, or an overall lack of emphasis on good schedule
       practices.
     – Insufficient time may have been allowed to achieve Level I milestones,
       perhaps complicated by insufficient funding.



                                                      IPAO Forensics Analysis performed by
                                                      Keith Burleson, 2008-2009; 2009-2010


                                                                                       3
IPAO Schedule Analysis Results

•   IPAO schedule analysts typically have to amend the schedules in order to
    be able to assess the schedule.
•   Schedules received for assessment are typically not of good quality due to
    poor scheduling practices.
      Missing predecessors and successors
      Containing constrained data
      Risks are not mapped to the schedule
      Lack of a true critical path
      Inappropriate use of lags/leads hides actual work being done which
        does not allow the schedule to be properly loaded with resources
•   NASA Schedule Management Handbook and NPR 7120.5D (NID), NM
    7120-81, and NPR 7123.1
•   Schedule management may be the area that presents the best
    opportunity for improvement -- There are immediate actions we can
    take to improve!

                                                                                 4
Improving Schedule
                Management

•   Schedule Health/Quality Check

•   Schedule Analysis vs. Reporting

•   Schedule Risk Analysis
Schedule Health/Quality Check
 DCMA 14 Point Assessment
                            An Integrated
                            Baseline
                            Review (IBR)
                            will assess the
                            metrics outlined
                            in the DCMA 14
                            point
                            assessment.
                            The biggest
                            areas for
                            improvement
                            are in logic
                            and
                            constraints.
GAO Criteria

  Government Accounting Office (GAO) Scheduling Best                                             GAO audits many of
                      Practices                                                                  the programs and
              Metric                                     Definition                              projects that IPAO
Scope of Work                    Capturing all Activities - WBS
                                                                                                 assesses. It is
Logic Network                    Sequencing all activities – All activities have a predecessor
                                                                                                 important to
                                 and successor excepting the start and finish activity.          understand and
Resource Loaded Schedule         Assigning resources to all activities – labor, material, and    adhere to their
                                 overhead                                                        criteria.
Durations                        Establishing the duration of all activities – Basis of
                                 Estimate to include resources
Schedule Integration             Integrating schedule activities horizontally and vertically
                                                                                                 GAO is in the process
Critical Path Method             Establishing the critical path for all activities – Project
                                                                                                 of developing a
                                 master schedule and critical path are defined                   Schedule Estimating
Float/Slack                      Identifying reasonable float between activities – calculated    Best
                                 by schedule analysis                                            Practices Guidebook –
Schedule Risk                    Conducting a schedule risk analysis                             Draft Release March
Statusing                        Updating the schedule using logic and durations to              2011
                                 determine the dates – not constraints; Schedule analyzed
                                 continuously to determine changes in critical path and          GAO Cost Estimating and
                                 variances                                                       Assessment Guide,
                                                                                                 GAO-09-3SP
Baseline Schedule (new metric)   Creating and managing a baseline schedule
                                                                                                                       7
Schedule Health/Quality Check
     NASA STAT Tool
                        STAT is a NASA-developed
                        schedule integrity check tool
                        for MS Project-based
                        schedules that aids in the
                        development, assessment,
                        analysis and reporting of
                        project schedules.

                        Many NASA schedulers do
                        not seem to be aware of the
                        STAT tool. This analysis
                        should be performed as
                        part of the update cycle.

                        To get your copy of the STAT
                        software and a registration
                        form, please contact Ken
                        Poole, MSFC, at
                        Kenneth.W.Poole@nasa.gov
                        256.544.2419
                                               8
Schedule Analysis

The schedule is an informative management tool. It
should be used for analysis as well as reporting actual
status.
•   Critical Path Analysis
•   Schedule Performance Trend Analysis
•   Baseline vs. Current Comparison Analysis – Variance
•   Resource Analysis
•   What-if Analysis
•   Earned Value Management (EVM) Analysis
•   Schedule Margin Assessment
•   Schedule Risk Analysis
•   Joint Confidence Level (JCL) Analysis
                                                Reference: NASA/SP-2010-33403
                                                NASA Schedule Management Handbook


                                                                             9
Critical Path Analysis

Many projects will report what the critical path is; however,
the reported path is not reflected in the project and in some
cases is a misrepresentation of the true critical path. It is
imperative that the critical path come from the IMS and that
it and the other merging paths are properly managed.
•   Critical Path – “the sequence of schedule activities that determines the
    duration of the project.” PMI
•   Importance of C/P Analysis – helps determine which activities can impact
    the project completion date (excludes LOE tasks). Understand schedule
    drivers.
•   The critical path needs to be monitored as it can change. Monitoring the
    critical path will show the project manager where resources are required to
    prevent schedule delays. Activities with higher slack values can be
    postponed in order to work activities that must be completed.


                                                                                  10
Schedule Performance Trend
                    Analysis
Types of Analysis:
• Schedule Performance Work-off – compares baseline
  dates against actual and forecasted dates
• Schedule Baseline vs. Actual Finish
• Schedule Performance Efficiency (Baseline Execution
  Index)
• Projection of Actuals Based upon Schedule Performance
• Total Slack Trends
• Baseline vs. Current Comparison Analysis
       Schedule Milestones
                                    Studies show that once a
       Schedule Variance Reports   schedule slips more than 15%,
•   Earned Value Management         it cannot get back on track.
                                                               11
Resource Analysis

Resource loading of schedules is a tool to manage
resources effectively.
•   Are the right people, material, and facilities available to do the
    job when needed?
•   Workforce planning is dependent on the project’s schedule -
    Brooks’s Law.
•   Most NASA schedules are resource and time constrained.
•   Cost and schedule analysts review how the resources are
    loaded or allocated in the IMS that supports the JCL
      Time dependent/variable (i.e. program management
       staffing)
      Time independent/fixed (i.e. material costs, resources)


                                                                     12
What-if Analysis

The schedule is a powerful management tool,
as well as, a reporting vehicle.
•   Tool for assessing potential schedule problems and
    mitigations.
•   Used to plan for corrective actions.




                                                         13
Schedule Margin Assessment

Margin needs to be applied to critical path and high
  risk activities.
•   Margin – “a provision in the project management plan to mitigate
    cost and/or schedule risk.” PMI
•   Margin is not float/slack. Float/slack only appears on non-critical
    paths; critical paths for NASA projects tend have 0; cost reserves
    can be applied to both float/slack on a given path as well as
    schedule margin on the critical path and it is important to know the
    difference.
•   Margin can be moved around the schedule as needed for high risk
    activities – if this is not the case, for instance, if the time is allocated
    to working a specific task/risk mitigation, it is no longer considered
    margin.
•   A probabilistic risk assessment is recommended as a basis for
    determining required margins.
                                                                               14
Schedule Risk Analysis

The schedule is a powerful tool for assessing
and mitigating risks. Project Manager, Risk
Manager and Scheduler work together to closely
monitor risks and schedule impacts.
•   Map risk ID to schedule task that is affected by the risk.
•   Determine if mitigation is required (mitigation tasks,
    additional resources, use of schedule margin if on the
    critical path)




                                                                 15
Schedule Risk Analysis (SRA)
              and Simulation - GAO
1.    Does the schedule reflect all work to be completed?
2.    Are the P/p critical dates used to plan the schedule?
3.    Are the activities sequenced logically?
4.    Are activity interdependencies identified and logical?
5.    If there are constraints, lags, and lead times, are they required, and is
      documentation available to justify the amounts?
6.    How realistic are the schedule duration estimates?
7.    How were resource estimates developed for each activity and will be the resources
      be available when needed?
8.    How accurate is the critical path and was it developed with scheduling software?
9.    How reasonable are float estimates?
10.   Can the schedule determine current status and provide reasonable completion date
      forecasts?
11.   What level of confidence is associated with the P/p schedule completion
      date? Does it reflect a schedule risk analysis and the organization’s or
      stakeholder’s risk tolerance?

                                                                    GAO-09-3SP Appendix X
Project Inputs

Projects deliver products at SR-100. SRB members understand that
programmatic documents are works in progress.
•   Documents (Requested of Project):
      Project Management Plan, Risk Management Plan, Schedule Management Plan
      Work Breakdown Structure (WBS) and WBS Dictionary
      Resources Plan (staffing, workforce, facilities)
      Project management status reports and EVM Data
•   Best Practice Master Schedule / Integrated Master Schedule (IMS)
      Project runs NASA STAT health check and schedule should be green for delivery
      Identification of Critical Path and Schedule Margin/Reserve with basis
      Removal of constraints from schedule for purposes of performing SRA
      Provide basis for any constraints not removed from schedule
      Identification of risk mitigation activities in the schedule
      Qualitative uncertainty ratings by WBS (Ref. schedule risk consequence chart)
•   Risk List
      Likelihood and Consequence Probabilities for Risks
      Mapping of Risks to Specific Schedule Activities
•   Joint Confidence Level (JCL) and assumptions (if required)
Kickoff                          Initial
                                                                                                                                           PAG                        Site
                                                                     Meeting                         Review
                                                                                                                                           Peer                      Review
                                                                      with                             with
                                                                                                                                          Review                      (SR)
                                                                      SRB                             PAG



                         Receive Initial                                                                                                            Receive
                      Programmatic Data        Receive Updated Data                                       Receive Final JCL                        Final Risk
                         Drop from P/p          Drop form P/p (Final                                        Model* and                             Updates
                      (Master Schedule &      IMS Delivery and Initial                                     Programmatic                            from P/p
                       Integrated Master        JCL Model Delivery*)                                      Updates from P/p
                        Schedule (IMS))
                        Due at SR-100 days       Due at SR-60 days                                         Due at SR-20 days                       Due at SR

                                                                          Collect Initial SRB Risk       Collect Updated SRB                                     Collect Final SRB Risk
                                                                             and Uncertainty             Risk and Uncertainty                                      and Uncertainty
                                                                               Assessment                     Assessment                                              Assessment

                                                                                                                                   Apply           Update       Brief SRB on Updated
                       Draft IPA Plan and     Perform Cost/Schedule       Create Cost/Schedule            Brief SRB on Initial
                                                                                                                                  Updated          Analysis            Analysis
                     Methodology; Review      Analysis and Work with           Risk Model                       Analysis
                                                                                                                                  SRB Risks        per Peer
                      with PAG Lead; Get        Project to Resolve
                                                                                                                                    and            Review        Run Final SRB Risk
                     signatures from IPAO         Issues, Identify       Apply P/p Risks & Initial        Begin Drafting IPA     Uncertainty                    Updates and P/p Risk
                        Director, Review       Uncertainty, and Map          SRB Risks and                     Report             Values to                     Updates in Model and
                       Manager, and PAG                 Risks             Uncertainty Values to                                                  Continue
                                                                                                                                   Model                         Provide Chair with
                              Lead                                               Model                                                           Updating
                                                                                                                                                                      Results
                                                                                                                                                IPA Report
                    Communicate with the                                                                                         Create SRB
                      P/p Regarding IPA                                                                                              /IPA                       Inform PAG Lead of Any
                           Process             The project timeline provides an                                                  Briefing and                    Updates to the Model
                     Review Programmatic                                                                                           Internal                             Results
                          Documents            opportunity for the project to deliver                                            Peer Review
                                                                                                                                    Charts
                                               a best-practices schedule to be                                                                                   Present Updated IPA
                    Review IMS and Work                                                                                           Continue                        Findings to the SRB
                    with P/P to resolve any    used in performing the schedule                                                    Updating
                         quality issues                                                                                          IPA Report                      Complete IPA Report
                                               risk assessment.
  * Required if the P/p has a Joint
Confidence Level (JCL) Requirement
Schedule Risk Assessment
                     Output
The schedule risk assessment is a tool to mitigate
project risks:
      Schedule Health/Quality Assessment
      Critical Path Analysis
      Tornado chart depicting the impact of risks occurring
      S-Curve depicting the impact of risks on the schedule confidence level
      Risk Assessed Stochastic Critical Path
      Frontier Curve showing the schedule or schedule and cost confidence level (or
       JCL if required)*
      Sensitivity Analysis (if needed) implemented to analyze the various risks to the
       project by looking at all their potential impact on the overall goal
Future Plans

•   Schedule Analysis Working Group
•   Connect and Discover the NASA Planning & Scheduling
    Community of Practice: To obtain access to the NASA P&S
    CoP contact:
    Jennifer Poston, Jennifer.L.Poston@nasa.gov (301) 286-7492
•   Continuous improvement of IPAO Standard Operating
    Procedure Instruction (SOPI) which contains cost, schedule,
    and risk analysis processes.
•   Supporting the development of 7120.5E
•   Visiting NASA centers and providing overview of
    programmatic assessment process.
       Ames – November 2010
•   Consistency between reviews and across centers
                                                                  20
References


•   NASA Schedule Management Handbook, NASA/SP-
    2010-3403, January 2010

•   DOD Integrated Master Plan and Integrated Master
    Schedule Preparation and Use Guide Version 0.9,
    October 21, 2005

•   GAO Cost Estimating and Assessment Guide, GAO-09-
    3SP


                                                        21

More Related Content

What's hot

Harvey.tony
Harvey.tonyHarvey.tony
Harvey.tonyNASAPMC
 
C armstrong tbyers
C armstrong tbyersC armstrong tbyers
C armstrong tbyersNASAPMC
 
Backup darren elliott
Backup darren elliottBackup darren elliott
Backup darren elliottNASAPMC
 
K.pagel.beene
K.pagel.beeneK.pagel.beene
K.pagel.beeneNASAPMC
 
Claunch.cathy
Claunch.cathyClaunch.cathy
Claunch.cathyNASAPMC
 
Sandra smalley
Sandra smalleySandra smalley
Sandra smalleyNASAPMC
 
Thomas.coonce
Thomas.coonceThomas.coonce
Thomas.coonceNASAPMC
 
Backup jim cassidy
Backup jim cassidyBackup jim cassidy
Backup jim cassidyNASAPMC
 
Gonzales.matthew
Gonzales.matthewGonzales.matthew
Gonzales.matthewNASAPMC
 
Louis.cioletti
Louis.ciolettiLouis.cioletti
Louis.ciolettiNASAPMC
 
Nichols.david
Nichols.davidNichols.david
Nichols.davidNASAPMC
 
Mahmood porter
Mahmood porterMahmood porter
Mahmood porterNASAPMC
 
Bauer.frank
Bauer.frankBauer.frank
Bauer.frankNASAPMC
 
Matt.gonzales
Matt.gonzalesMatt.gonzales
Matt.gonzalesNASAPMC
 
Ed mangopanelpm challengefinal
Ed mangopanelpm challengefinalEd mangopanelpm challengefinal
Ed mangopanelpm challengefinalNASAPMC
 
Healy edward
Healy edwardHealy edward
Healy edwardNASAPMC
 
Dean.david
Dean.davidDean.david
Dean.davidNASAPMC
 
Brian muirhead v1-27-12
Brian muirhead v1-27-12Brian muirhead v1-27-12
Brian muirhead v1-27-12NASAPMC
 
Simon.dekker.vance kotrla
Simon.dekker.vance kotrlaSimon.dekker.vance kotrla
Simon.dekker.vance kotrlaNASAPMC
 

What's hot (20)

Harvey.tony
Harvey.tonyHarvey.tony
Harvey.tony
 
C armstrong tbyers
C armstrong tbyersC armstrong tbyers
C armstrong tbyers
 
Backup darren elliott
Backup darren elliottBackup darren elliott
Backup darren elliott
 
K.pagel.beene
K.pagel.beeneK.pagel.beene
K.pagel.beene
 
Claunch.cathy
Claunch.cathyClaunch.cathy
Claunch.cathy
 
Symons
SymonsSymons
Symons
 
Sandra smalley
Sandra smalleySandra smalley
Sandra smalley
 
Thomas.coonce
Thomas.coonceThomas.coonce
Thomas.coonce
 
Backup jim cassidy
Backup jim cassidyBackup jim cassidy
Backup jim cassidy
 
Gonzales.matthew
Gonzales.matthewGonzales.matthew
Gonzales.matthew
 
Louis.cioletti
Louis.ciolettiLouis.cioletti
Louis.cioletti
 
Nichols.david
Nichols.davidNichols.david
Nichols.david
 
Mahmood porter
Mahmood porterMahmood porter
Mahmood porter
 
Bauer.frank
Bauer.frankBauer.frank
Bauer.frank
 
Matt.gonzales
Matt.gonzalesMatt.gonzales
Matt.gonzales
 
Ed mangopanelpm challengefinal
Ed mangopanelpm challengefinalEd mangopanelpm challengefinal
Ed mangopanelpm challengefinal
 
Healy edward
Healy edwardHealy edward
Healy edward
 
Dean.david
Dean.davidDean.david
Dean.david
 
Brian muirhead v1-27-12
Brian muirhead v1-27-12Brian muirhead v1-27-12
Brian muirhead v1-27-12
 
Simon.dekker.vance kotrla
Simon.dekker.vance kotrlaSimon.dekker.vance kotrla
Simon.dekker.vance kotrla
 

Similar to Borchardt.heidemarie

Ipao great houseetc-programmatic analysis ll
Ipao great houseetc-programmatic analysis llIpao great houseetc-programmatic analysis ll
Ipao great houseetc-programmatic analysis llNASAPMC
 
Ortiz.james
Ortiz.jamesOrtiz.james
Ortiz.jamesNASAPMC
 
Integrating Risk With Earned Value
Integrating Risk With Earned ValueIntegrating Risk With Earned Value
Integrating Risk With Earned ValueGlen Alleman
 
CCI Project Prioritization Project
CCI Project Prioritization ProjectCCI Project Prioritization Project
CCI Project Prioritization Projectjcvpve
 
Humphreys.gary
Humphreys.garyHumphreys.gary
Humphreys.garyNASAPMC
 
Humphreys.gary
Humphreys.garyHumphreys.gary
Humphreys.garyNASAPMC
 
Week 9-performance-management-1222266539427090-9
Week 9-performance-management-1222266539427090-9Week 9-performance-management-1222266539427090-9
Week 9-performance-management-1222266539427090-9Tu Nguyen, PMP®,PMI-RMP®
 
Project management best practices
Project management best practicesProject management best practices
Project management best practiceswalkerswu
 
3 programming and tools swot & lfa
3 programming and tools swot & lfa3 programming and tools swot & lfa
3 programming and tools swot & lfaDagný Gísladóttir
 
Program Review for Integrated Planning
Program Review for Integrated PlanningProgram Review for Integrated Planning
Program Review for Integrated PlanningWASC Senior
 
1844final 100811113357 Phpapp01
1844final 100811113357 Phpapp011844final 100811113357 Phpapp01
1844final 100811113357 Phpapp01pmfigliola
 
1844final 100811113357 Phpapp01
1844final 100811113357 Phpapp011844final 100811113357 Phpapp01
1844final 100811113357 Phpapp01pmfigliola
 
2.2 programming and tools swot & lfa
2.2 programming and tools swot & lfa2.2 programming and tools swot & lfa
2.2 programming and tools swot & lfaDagný Gísladóttir
 
Framework for Analyzing Public Investment Management
Framework for Analyzing Public Investment ManagementFramework for Analyzing Public Investment Management
Framework for Analyzing Public Investment Managementicgfmconference
 
PROJECT PLANNING METHODOLOGIES.pdf
PROJECT  PLANNING METHODOLOGIES.pdfPROJECT  PLANNING METHODOLOGIES.pdf
PROJECT PLANNING METHODOLOGIES.pdfSurashmie Kaalmegh
 

Similar to Borchardt.heidemarie (20)

Ipao great houseetc-programmatic analysis ll
Ipao great houseetc-programmatic analysis llIpao great houseetc-programmatic analysis ll
Ipao great houseetc-programmatic analysis ll
 
Capm time mgmt matching exercise
Capm time mgmt matching exerciseCapm time mgmt matching exercise
Capm time mgmt matching exercise
 
Ortiz.james
Ortiz.jamesOrtiz.james
Ortiz.james
 
Integrating Risk With Earned Value
Integrating Risk With Earned ValueIntegrating Risk With Earned Value
Integrating Risk With Earned Value
 
WBS PROJECT
WBS PROJECTWBS PROJECT
WBS PROJECT
 
CCI Project Prioritization Project
CCI Project Prioritization ProjectCCI Project Prioritization Project
CCI Project Prioritization Project
 
Pmt 06
Pmt 06Pmt 06
Pmt 06
 
Humphreys.gary
Humphreys.garyHumphreys.gary
Humphreys.gary
 
Humphreys.gary
Humphreys.garyHumphreys.gary
Humphreys.gary
 
Week 9-performance-management-1222266539427090-9
Week 9-performance-management-1222266539427090-9Week 9-performance-management-1222266539427090-9
Week 9-performance-management-1222266539427090-9
 
Project management best practices
Project management best practicesProject management best practices
Project management best practices
 
3 programming and tools swot & lfa
3 programming and tools swot & lfa3 programming and tools swot & lfa
3 programming and tools swot & lfa
 
Controlling
ControllingControlling
Controlling
 
Program Review for Integrated Planning
Program Review for Integrated PlanningProgram Review for Integrated Planning
Program Review for Integrated Planning
 
1844final 100811113357 Phpapp01
1844final 100811113357 Phpapp011844final 100811113357 Phpapp01
1844final 100811113357 Phpapp01
 
1844final 100811113357 Phpapp01
1844final 100811113357 Phpapp011844final 100811113357 Phpapp01
1844final 100811113357 Phpapp01
 
2.2 programming and tools swot & lfa
2.2 programming and tools swot & lfa2.2 programming and tools swot & lfa
2.2 programming and tools swot & lfa
 
Framework for Analyzing Public Investment Management
Framework for Analyzing Public Investment ManagementFramework for Analyzing Public Investment Management
Framework for Analyzing Public Investment Management
 
Project scheduling
Project schedulingProject scheduling
Project scheduling
 
PROJECT PLANNING METHODOLOGIES.pdf
PROJECT  PLANNING METHODOLOGIES.pdfPROJECT  PLANNING METHODOLOGIES.pdf
PROJECT PLANNING METHODOLOGIES.pdf
 

More from NASAPMC

Bejmuk bo
Bejmuk boBejmuk bo
Bejmuk boNASAPMC
 
Baniszewski john
Baniszewski johnBaniszewski john
Baniszewski johnNASAPMC
 
Yew manson
Yew mansonYew manson
Yew mansonNASAPMC
 
Wood frank
Wood frankWood frank
Wood frankNASAPMC
 
Wood frank
Wood frankWood frank
Wood frankNASAPMC
 
Wessen randi (cd)
Wessen randi (cd)Wessen randi (cd)
Wessen randi (cd)NASAPMC
 
Vellinga joe
Vellinga joeVellinga joe
Vellinga joeNASAPMC
 
Trahan stuart
Trahan stuartTrahan stuart
Trahan stuartNASAPMC
 
Stock gahm
Stock gahmStock gahm
Stock gahmNASAPMC
 
Snow lee
Snow leeSnow lee
Snow leeNASAPMC
 
Smalley sandra
Smalley sandraSmalley sandra
Smalley sandraNASAPMC
 
Seftas krage
Seftas krageSeftas krage
Seftas krageNASAPMC
 
Sampietro marco
Sampietro marcoSampietro marco
Sampietro marcoNASAPMC
 
Rudolphi mike
Rudolphi mikeRudolphi mike
Rudolphi mikeNASAPMC
 
Roberts karlene
Roberts karleneRoberts karlene
Roberts karleneNASAPMC
 
Rackley mike
Rackley mikeRackley mike
Rackley mikeNASAPMC
 
Paradis william
Paradis williamParadis william
Paradis williamNASAPMC
 
O'keefe william
O'keefe williamO'keefe william
O'keefe williamNASAPMC
 
Muller ralf
Muller ralfMuller ralf
Muller ralfNASAPMC
 
Mulenburg jerry
Mulenburg jerryMulenburg jerry
Mulenburg jerryNASAPMC
 

More from NASAPMC (20)

Bejmuk bo
Bejmuk boBejmuk bo
Bejmuk bo
 
Baniszewski john
Baniszewski johnBaniszewski john
Baniszewski john
 
Yew manson
Yew mansonYew manson
Yew manson
 
Wood frank
Wood frankWood frank
Wood frank
 
Wood frank
Wood frankWood frank
Wood frank
 
Wessen randi (cd)
Wessen randi (cd)Wessen randi (cd)
Wessen randi (cd)
 
Vellinga joe
Vellinga joeVellinga joe
Vellinga joe
 
Trahan stuart
Trahan stuartTrahan stuart
Trahan stuart
 
Stock gahm
Stock gahmStock gahm
Stock gahm
 
Snow lee
Snow leeSnow lee
Snow lee
 
Smalley sandra
Smalley sandraSmalley sandra
Smalley sandra
 
Seftas krage
Seftas krageSeftas krage
Seftas krage
 
Sampietro marco
Sampietro marcoSampietro marco
Sampietro marco
 
Rudolphi mike
Rudolphi mikeRudolphi mike
Rudolphi mike
 
Roberts karlene
Roberts karleneRoberts karlene
Roberts karlene
 
Rackley mike
Rackley mikeRackley mike
Rackley mike
 
Paradis william
Paradis williamParadis william
Paradis william
 
O'keefe william
O'keefe williamO'keefe william
O'keefe william
 
Muller ralf
Muller ralfMuller ralf
Muller ralf
 
Mulenburg jerry
Mulenburg jerryMulenburg jerry
Mulenburg jerry
 

Recently uploaded

MAHA Global and IPR: Do Actions Speak Louder Than Words?
MAHA Global and IPR: Do Actions Speak Louder Than Words?MAHA Global and IPR: Do Actions Speak Louder Than Words?
MAHA Global and IPR: Do Actions Speak Louder Than Words?Olivia Kresic
 
Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...
Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...
Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...lizamodels9
 
BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,noida100girls
 
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCRashishs7044
 
Organizational Structure Running A Successful Business
Organizational Structure Running A Successful BusinessOrganizational Structure Running A Successful Business
Organizational Structure Running A Successful BusinessSeta Wicaksana
 
Global Scenario On Sustainable and Resilient Coconut Industry by Dr. Jelfina...
Global Scenario On Sustainable  and Resilient Coconut Industry by Dr. Jelfina...Global Scenario On Sustainable  and Resilient Coconut Industry by Dr. Jelfina...
Global Scenario On Sustainable and Resilient Coconut Industry by Dr. Jelfina...ictsugar
 
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deckPitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deckHajeJanKamps
 
BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,noida100girls
 
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...lizamodels9
 
The CMO Survey - Highlights and Insights Report - Spring 2024
The CMO Survey - Highlights and Insights Report - Spring 2024The CMO Survey - Highlights and Insights Report - Spring 2024
The CMO Survey - Highlights and Insights Report - Spring 2024christinemoorman
 
8447779800, Low rate Call girls in Tughlakabad Delhi NCR
8447779800, Low rate Call girls in Tughlakabad Delhi NCR8447779800, Low rate Call girls in Tughlakabad Delhi NCR
8447779800, Low rate Call girls in Tughlakabad Delhi NCRashishs7044
 
Call Us 📲8800102216📞 Call Girls In DLF City Gurgaon
Call Us 📲8800102216📞 Call Girls In DLF City GurgaonCall Us 📲8800102216📞 Call Girls In DLF City Gurgaon
Call Us 📲8800102216📞 Call Girls In DLF City Gurgaoncallgirls2057
 
Lean: From Theory to Practice — One City’s (and Library’s) Lean Story… Abridged
Lean: From Theory to Practice — One City’s (and Library’s) Lean Story… AbridgedLean: From Theory to Practice — One City’s (and Library’s) Lean Story… Abridged
Lean: From Theory to Practice — One City’s (and Library’s) Lean Story… AbridgedKaiNexus
 
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCRashishs7044
 
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
8447779800, Low rate Call girls in Uttam Nagar Delhi NCRashishs7044
 
Call US-88OO1O2216 Call Girls In Mahipalpur Female Escort Service
Call US-88OO1O2216 Call Girls In Mahipalpur Female Escort ServiceCall US-88OO1O2216 Call Girls In Mahipalpur Female Escort Service
Call US-88OO1O2216 Call Girls In Mahipalpur Female Escort Servicecallgirls2057
 
Flow Your Strategy at Flight Levels Day 2024
Flow Your Strategy at Flight Levels Day 2024Flow Your Strategy at Flight Levels Day 2024
Flow Your Strategy at Flight Levels Day 2024Kirill Klimov
 
Buy gmail accounts.pdf Buy Old Gmail Accounts
Buy gmail accounts.pdf Buy Old Gmail AccountsBuy gmail accounts.pdf Buy Old Gmail Accounts
Buy gmail accounts.pdf Buy Old Gmail AccountsBuy Verified Accounts
 
Independent Call Girls Andheri Nightlaila 9967584737
Independent Call Girls Andheri Nightlaila 9967584737Independent Call Girls Andheri Nightlaila 9967584737
Independent Call Girls Andheri Nightlaila 9967584737Riya Pathan
 
Digital Transformation in the PLM domain - distrib.pdf
Digital Transformation in the PLM domain - distrib.pdfDigital Transformation in the PLM domain - distrib.pdf
Digital Transformation in the PLM domain - distrib.pdfJos Voskuil
 

Recently uploaded (20)

MAHA Global and IPR: Do Actions Speak Louder Than Words?
MAHA Global and IPR: Do Actions Speak Louder Than Words?MAHA Global and IPR: Do Actions Speak Louder Than Words?
MAHA Global and IPR: Do Actions Speak Louder Than Words?
 
Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...
Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...
Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...
 
BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
 
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
8447779800, Low rate Call girls in Kotla Mubarakpur Delhi NCR
 
Organizational Structure Running A Successful Business
Organizational Structure Running A Successful BusinessOrganizational Structure Running A Successful Business
Organizational Structure Running A Successful Business
 
Global Scenario On Sustainable and Resilient Coconut Industry by Dr. Jelfina...
Global Scenario On Sustainable  and Resilient Coconut Industry by Dr. Jelfina...Global Scenario On Sustainable  and Resilient Coconut Industry by Dr. Jelfina...
Global Scenario On Sustainable and Resilient Coconut Industry by Dr. Jelfina...
 
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deckPitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
Pitch Deck Teardown: Geodesic.Life's $500k Pre-seed deck
 
BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
 
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
Call Girls In Sikandarpur Gurgaon ❤️8860477959_Russian 100% Genuine Escorts I...
 
The CMO Survey - Highlights and Insights Report - Spring 2024
The CMO Survey - Highlights and Insights Report - Spring 2024The CMO Survey - Highlights and Insights Report - Spring 2024
The CMO Survey - Highlights and Insights Report - Spring 2024
 
8447779800, Low rate Call girls in Tughlakabad Delhi NCR
8447779800, Low rate Call girls in Tughlakabad Delhi NCR8447779800, Low rate Call girls in Tughlakabad Delhi NCR
8447779800, Low rate Call girls in Tughlakabad Delhi NCR
 
Call Us 📲8800102216📞 Call Girls In DLF City Gurgaon
Call Us 📲8800102216📞 Call Girls In DLF City GurgaonCall Us 📲8800102216📞 Call Girls In DLF City Gurgaon
Call Us 📲8800102216📞 Call Girls In DLF City Gurgaon
 
Lean: From Theory to Practice — One City’s (and Library’s) Lean Story… Abridged
Lean: From Theory to Practice — One City’s (and Library’s) Lean Story… AbridgedLean: From Theory to Practice — One City’s (and Library’s) Lean Story… Abridged
Lean: From Theory to Practice — One City’s (and Library’s) Lean Story… Abridged
 
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR
 
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
 
Call US-88OO1O2216 Call Girls In Mahipalpur Female Escort Service
Call US-88OO1O2216 Call Girls In Mahipalpur Female Escort ServiceCall US-88OO1O2216 Call Girls In Mahipalpur Female Escort Service
Call US-88OO1O2216 Call Girls In Mahipalpur Female Escort Service
 
Flow Your Strategy at Flight Levels Day 2024
Flow Your Strategy at Flight Levels Day 2024Flow Your Strategy at Flight Levels Day 2024
Flow Your Strategy at Flight Levels Day 2024
 
Buy gmail accounts.pdf Buy Old Gmail Accounts
Buy gmail accounts.pdf Buy Old Gmail AccountsBuy gmail accounts.pdf Buy Old Gmail Accounts
Buy gmail accounts.pdf Buy Old Gmail Accounts
 
Independent Call Girls Andheri Nightlaila 9967584737
Independent Call Girls Andheri Nightlaila 9967584737Independent Call Girls Andheri Nightlaila 9967584737
Independent Call Girls Andheri Nightlaila 9967584737
 
Digital Transformation in the PLM domain - distrib.pdf
Digital Transformation in the PLM domain - distrib.pdfDigital Transformation in the PLM domain - distrib.pdf
Digital Transformation in the PLM domain - distrib.pdf
 

Borchardt.heidemarie

  • 1. Schedule Assessment and Risk Analysis Richard M. Greathouse Lead Programmatic Analysis Group Heidemarie S. Borchardt, PMP Lead Schedule Analyst Contributors: Kelley Cyr, Michele King, Kelly Moses, Robin Smith Independent Program Assessment Office (IPAO)
  • 2. Overview • The schedule is a powerful tool for project management. Schedule risk analysis:  Identifies potential risks  Identifies impacts of risks to project schedule • IPAO has the opportunity to meet with many programs and projects:  Lessons Learned  Future Plans 2
  • 3. IPAO Forensics Analysis Excerpt Strengths: • Risk management, budget, and schedule tend to gravitate to very few (typically one) overall strengths for each program. • Resources Other Than Budget received the fewest strengths. Issues: • Schedule issues were the most frequent issues identified and may be an opportunity for improvement. – Schedule issues may be caused by poor planning, poor schedule (duration) estimates, or an overall lack of emphasis on good schedule practices. – Insufficient time may have been allowed to achieve Level I milestones, perhaps complicated by insufficient funding. IPAO Forensics Analysis performed by Keith Burleson, 2008-2009; 2009-2010 3
  • 4. IPAO Schedule Analysis Results • IPAO schedule analysts typically have to amend the schedules in order to be able to assess the schedule. • Schedules received for assessment are typically not of good quality due to poor scheduling practices.  Missing predecessors and successors  Containing constrained data  Risks are not mapped to the schedule  Lack of a true critical path  Inappropriate use of lags/leads hides actual work being done which does not allow the schedule to be properly loaded with resources • NASA Schedule Management Handbook and NPR 7120.5D (NID), NM 7120-81, and NPR 7123.1 • Schedule management may be the area that presents the best opportunity for improvement -- There are immediate actions we can take to improve! 4
  • 5. Improving Schedule Management • Schedule Health/Quality Check • Schedule Analysis vs. Reporting • Schedule Risk Analysis
  • 6. Schedule Health/Quality Check DCMA 14 Point Assessment An Integrated Baseline Review (IBR) will assess the metrics outlined in the DCMA 14 point assessment. The biggest areas for improvement are in logic and constraints.
  • 7. GAO Criteria Government Accounting Office (GAO) Scheduling Best GAO audits many of Practices the programs and Metric Definition projects that IPAO Scope of Work Capturing all Activities - WBS assesses. It is Logic Network Sequencing all activities – All activities have a predecessor important to and successor excepting the start and finish activity. understand and Resource Loaded Schedule Assigning resources to all activities – labor, material, and adhere to their overhead criteria. Durations Establishing the duration of all activities – Basis of Estimate to include resources Schedule Integration Integrating schedule activities horizontally and vertically GAO is in the process Critical Path Method Establishing the critical path for all activities – Project of developing a master schedule and critical path are defined Schedule Estimating Float/Slack Identifying reasonable float between activities – calculated Best by schedule analysis Practices Guidebook – Schedule Risk Conducting a schedule risk analysis Draft Release March Statusing Updating the schedule using logic and durations to 2011 determine the dates – not constraints; Schedule analyzed continuously to determine changes in critical path and GAO Cost Estimating and variances Assessment Guide, GAO-09-3SP Baseline Schedule (new metric) Creating and managing a baseline schedule 7
  • 8. Schedule Health/Quality Check NASA STAT Tool STAT is a NASA-developed schedule integrity check tool for MS Project-based schedules that aids in the development, assessment, analysis and reporting of project schedules. Many NASA schedulers do not seem to be aware of the STAT tool. This analysis should be performed as part of the update cycle. To get your copy of the STAT software and a registration form, please contact Ken Poole, MSFC, at Kenneth.W.Poole@nasa.gov 256.544.2419 8
  • 9. Schedule Analysis The schedule is an informative management tool. It should be used for analysis as well as reporting actual status. • Critical Path Analysis • Schedule Performance Trend Analysis • Baseline vs. Current Comparison Analysis – Variance • Resource Analysis • What-if Analysis • Earned Value Management (EVM) Analysis • Schedule Margin Assessment • Schedule Risk Analysis • Joint Confidence Level (JCL) Analysis Reference: NASA/SP-2010-33403 NASA Schedule Management Handbook 9
  • 10. Critical Path Analysis Many projects will report what the critical path is; however, the reported path is not reflected in the project and in some cases is a misrepresentation of the true critical path. It is imperative that the critical path come from the IMS and that it and the other merging paths are properly managed. • Critical Path – “the sequence of schedule activities that determines the duration of the project.” PMI • Importance of C/P Analysis – helps determine which activities can impact the project completion date (excludes LOE tasks). Understand schedule drivers. • The critical path needs to be monitored as it can change. Monitoring the critical path will show the project manager where resources are required to prevent schedule delays. Activities with higher slack values can be postponed in order to work activities that must be completed. 10
  • 11. Schedule Performance Trend Analysis Types of Analysis: • Schedule Performance Work-off – compares baseline dates against actual and forecasted dates • Schedule Baseline vs. Actual Finish • Schedule Performance Efficiency (Baseline Execution Index) • Projection of Actuals Based upon Schedule Performance • Total Slack Trends • Baseline vs. Current Comparison Analysis  Schedule Milestones Studies show that once a  Schedule Variance Reports schedule slips more than 15%, • Earned Value Management it cannot get back on track. 11
  • 12. Resource Analysis Resource loading of schedules is a tool to manage resources effectively. • Are the right people, material, and facilities available to do the job when needed? • Workforce planning is dependent on the project’s schedule - Brooks’s Law. • Most NASA schedules are resource and time constrained. • Cost and schedule analysts review how the resources are loaded or allocated in the IMS that supports the JCL  Time dependent/variable (i.e. program management staffing)  Time independent/fixed (i.e. material costs, resources) 12
  • 13. What-if Analysis The schedule is a powerful management tool, as well as, a reporting vehicle. • Tool for assessing potential schedule problems and mitigations. • Used to plan for corrective actions. 13
  • 14. Schedule Margin Assessment Margin needs to be applied to critical path and high risk activities. • Margin – “a provision in the project management plan to mitigate cost and/or schedule risk.” PMI • Margin is not float/slack. Float/slack only appears on non-critical paths; critical paths for NASA projects tend have 0; cost reserves can be applied to both float/slack on a given path as well as schedule margin on the critical path and it is important to know the difference. • Margin can be moved around the schedule as needed for high risk activities – if this is not the case, for instance, if the time is allocated to working a specific task/risk mitigation, it is no longer considered margin. • A probabilistic risk assessment is recommended as a basis for determining required margins. 14
  • 15. Schedule Risk Analysis The schedule is a powerful tool for assessing and mitigating risks. Project Manager, Risk Manager and Scheduler work together to closely monitor risks and schedule impacts. • Map risk ID to schedule task that is affected by the risk. • Determine if mitigation is required (mitigation tasks, additional resources, use of schedule margin if on the critical path) 15
  • 16. Schedule Risk Analysis (SRA) and Simulation - GAO 1. Does the schedule reflect all work to be completed? 2. Are the P/p critical dates used to plan the schedule? 3. Are the activities sequenced logically? 4. Are activity interdependencies identified and logical? 5. If there are constraints, lags, and lead times, are they required, and is documentation available to justify the amounts? 6. How realistic are the schedule duration estimates? 7. How were resource estimates developed for each activity and will be the resources be available when needed? 8. How accurate is the critical path and was it developed with scheduling software? 9. How reasonable are float estimates? 10. Can the schedule determine current status and provide reasonable completion date forecasts? 11. What level of confidence is associated with the P/p schedule completion date? Does it reflect a schedule risk analysis and the organization’s or stakeholder’s risk tolerance? GAO-09-3SP Appendix X
  • 17. Project Inputs Projects deliver products at SR-100. SRB members understand that programmatic documents are works in progress. • Documents (Requested of Project):  Project Management Plan, Risk Management Plan, Schedule Management Plan  Work Breakdown Structure (WBS) and WBS Dictionary  Resources Plan (staffing, workforce, facilities)  Project management status reports and EVM Data • Best Practice Master Schedule / Integrated Master Schedule (IMS)  Project runs NASA STAT health check and schedule should be green for delivery  Identification of Critical Path and Schedule Margin/Reserve with basis  Removal of constraints from schedule for purposes of performing SRA  Provide basis for any constraints not removed from schedule  Identification of risk mitigation activities in the schedule  Qualitative uncertainty ratings by WBS (Ref. schedule risk consequence chart) • Risk List  Likelihood and Consequence Probabilities for Risks  Mapping of Risks to Specific Schedule Activities • Joint Confidence Level (JCL) and assumptions (if required)
  • 18. Kickoff Initial PAG Site Meeting Review Peer Review with with Review (SR) SRB PAG Receive Initial Receive Programmatic Data Receive Updated Data Receive Final JCL Final Risk Drop from P/p Drop form P/p (Final Model* and Updates (Master Schedule & IMS Delivery and Initial Programmatic from P/p Integrated Master JCL Model Delivery*) Updates from P/p Schedule (IMS)) Due at SR-100 days Due at SR-60 days Due at SR-20 days Due at SR Collect Initial SRB Risk Collect Updated SRB Collect Final SRB Risk and Uncertainty Risk and Uncertainty and Uncertainty Assessment Assessment Assessment Apply Update Brief SRB on Updated Draft IPA Plan and Perform Cost/Schedule Create Cost/Schedule Brief SRB on Initial Updated Analysis Analysis Methodology; Review Analysis and Work with Risk Model Analysis SRB Risks per Peer with PAG Lead; Get Project to Resolve and Review Run Final SRB Risk signatures from IPAO Issues, Identify Apply P/p Risks & Initial Begin Drafting IPA Uncertainty Updates and P/p Risk Director, Review Uncertainty, and Map SRB Risks and Report Values to Updates in Model and Manager, and PAG Risks Uncertainty Values to Continue Model Provide Chair with Lead Model Updating Results IPA Report Communicate with the Create SRB P/p Regarding IPA /IPA Inform PAG Lead of Any Process The project timeline provides an Briefing and Updates to the Model Review Programmatic Internal Results Documents opportunity for the project to deliver Peer Review Charts a best-practices schedule to be Present Updated IPA Review IMS and Work Continue Findings to the SRB with P/P to resolve any used in performing the schedule Updating quality issues IPA Report Complete IPA Report risk assessment. * Required if the P/p has a Joint Confidence Level (JCL) Requirement
  • 19. Schedule Risk Assessment Output The schedule risk assessment is a tool to mitigate project risks:  Schedule Health/Quality Assessment  Critical Path Analysis  Tornado chart depicting the impact of risks occurring  S-Curve depicting the impact of risks on the schedule confidence level  Risk Assessed Stochastic Critical Path  Frontier Curve showing the schedule or schedule and cost confidence level (or JCL if required)*  Sensitivity Analysis (if needed) implemented to analyze the various risks to the project by looking at all their potential impact on the overall goal
  • 20. Future Plans • Schedule Analysis Working Group • Connect and Discover the NASA Planning & Scheduling Community of Practice: To obtain access to the NASA P&S CoP contact: Jennifer Poston, Jennifer.L.Poston@nasa.gov (301) 286-7492 • Continuous improvement of IPAO Standard Operating Procedure Instruction (SOPI) which contains cost, schedule, and risk analysis processes. • Supporting the development of 7120.5E • Visiting NASA centers and providing overview of programmatic assessment process.  Ames – November 2010 • Consistency between reviews and across centers 20
  • 21. References • NASA Schedule Management Handbook, NASA/SP- 2010-3403, January 2010 • DOD Integrated Master Plan and Integrated Master Schedule Preparation and Use Guide Version 0.9, October 21, 2005 • GAO Cost Estimating and Assessment Guide, GAO-09- 3SP 21

Editor's Notes

  1. Rich
  2. Schedule assessment is used to determine whether the program/project’s planned schedule is adequate to accomplish the proposed technical work. Independent schedule risk analysis helps identify any potential risks not already identified by the project and the potential impact to the baseline schedule. The IPAO Programmatic Analysis Group (PAG) is growing its schedule assessment capability through hiring of dedicated schedule analysts and through evolution of fully integrated cost and schedule assessment approaches. This presentation discusses positive steps taken in IPAO to address the changing climate for programmatic assessment in the Agency. Lessons learned and future plans will be shared.
  3. Documented in forensics analysis based on IPAO schedule analysis results (IPA Reports – schedule health checks)
  4. GAO audits many of the programs and projects that IPAO assesses. It is important to understand and adhere to their criteria.
  5. Brooks's law is a principle in software development which says that "adding manpower to a late software project makes it later".[1] It was coined by Fred Brooks in his 1975 book The Mythical Man-Month. The corollary of Brooks's Law is that there is an incremental person who, when added to a project, makes it take more, not less time. Wikipedia.
  6. Projects do not always understand the timeline and tend to want to shorten it. Having a credible schedule is imperative to performing the risk assessment.
  7. MK: Added a space between each line.