1. Revamps for Ageing Hydrogen Plants
By
Gerard B. Hawkins
Managing Director, CEO
2. Introduction
This presentation highlights some of
the retrofits that can be applied to
• Improve efficiency
• Increase production
Safety
Efficiency
Reliability
Throughput
Environment
3. Introduction
For older hydrogen plants, efficiency
is worse than for a modern plant
To maximize profit must improve
either
• Plant efficiency
• Plant production rate
4. Site Circumstances
Hydrogen plants have a wide range of
site circumstances
Is there value for steam on the site ?
What are the downstream users ?
What is the contract basis for the H2
supply
When conducting a revamp these need
to be carefully considered
GBHE is in a unique position to fully
understand these issues and design
revamps accordingly
5. Plant Limitations
Need to address plant limitations,
such as
• Process side pressure drop
• Maximum tube wall temperature
• Coil design temperatures in duct
• Steam balance
• Fan capacity
6. Basis for Study
Old style plant with
• Top Fired SMR - 500 tubes
• Steam to carbon of 3.9
• Duct heat recovery is feed preheat and
steam raising
• HTS
• LTS
• Wet CO2 system
• Methanation
9. Plant Limitations
Three areas that can limit plant
performance
SMR
Convection Section
Cooling, Shifts
and CO2 Removal
10. Change Catalyst Shape and Size
By optimizing catalyst size can
• Reduce pressure drop by up to 27%
• Reduce carbon formation potential
By changing to VULCAN Series VSG-Z101
can
• Reduce CH4 slip and increase production by
5%
• Reduce Tube Wall Temperatures by 10°C
• Reduce carbon formation potential
• Reduce pressure drop by 29%
11. Reduce Steam to Carbon Ratio
By reducing SC ratio by 0.6 can
• Reduce steam addition by 19 mtphr
• Increase steam export by 9 mtphr
• Reduce pressure drop by 23%
• Reduce TWT by 14°C
• Gain 5.3 GJ/mmSCF
12. Reduce Steam to Carbon Ratio
Or increase plant rate
• Reduced DP
• Gain 1.8 GJ/mmSCF
• In some cases can increase rate above
base case
But must be aware of
• Metal dusting of WHB
• Increased potential for carbon
formation
13. Raise Outlet Reformer Temperature
Many operators run to a false tube
wall or outlet header temperature
By analysis of reformer operation,
this limitation can be eliminated
Improves production by 2-5%
At margin loss of efficiency
Some of this efficiency can be
recouped by other revamps
14. Rebalancing Firing
One Terraced Wall or Side Fired reformers,
the firing can be rebalanced
Either improves efficiency or steam raising
capacity on in some cases can increase rate
Parameter Units Case A Case B Case C
Firing at Top % 50 40 60
Firing at Bottom % 50 60 40
Steam Export Mt/hr 0 -15 +11
Efficiency GJ/mmSCF 452 443 463
15. Reformer Re-tubes
The reformer tubes do have to be
replaced and therefore have to be
considered as a consumable
By replacing with an improve
metallurgy, a thinner wall tube can
be used
This provides a wide range of
process and operability benefits
16. Reformer Re-tubes
Parameter Units Case A
Base
Case B
New Tubes
Case C
Uprate
Tube material N/A HK40 HP Mod HP Mod
Tube OD mm 114 114 114
Tube ID mm 84 96.4 96.4
Catalyst “P”
“P”
“P” “P”
H2 Production mmSCF 100 101 109
Efficiency GJ/mmSCF 430 428 433
17. Addition of a Pre-Reformer
MP Steam
Existing
Reformer
Natural Gas
Synthesis Gas
Pre-reformer
New Reheat
Coil
18. Addition of a Pre-Reformer
To obtain maximum benefit requires
• Reheat of effluent - an achieve very high
preheat and reheat temperature with latest
generation of pre-reforming catalyst can
recover more heat from duct and reduce
furnace duty significantly
• Must model effect on duct to ensure that
existing demands for heat are fulfilled (HP
Steam Raising)
Can allow for efficiency improvements of
up to 24 GJ/mmSCF
Or rate increases of up to 9%
19. Addition of an ATR
Existing
Reformer
NG Preheater NG/Steam
Preheater
MUG Cooler
Oxygen Preheater
Steam Drum
MP Boiler
Natural Gas Make Up Gas
Condensate
20. Addition of an ATR or Secondary
Either in parallel (ATR) or in series
(secondary)
• Parallel ATR has less impact on the main
plant
• Main plant can run when ATR off line
Can increase production rate by 22%
• More can be achieved depending on plant
design
Require an oxygen plant (9 mt/hr)
Energy efficiency improved by 13
GJ/mmSCF
21. Addition of an AGHRPR
Can add a AGHR as a post reformer
Reduces steam export capacity significantly
Depending on plant design allows for plant
rate increases of between 20-40%
Also potential energy efficiency gains
Steam
Hydrocarbon
Feed HDS
Fuel
Steam
Generation
and
Superheating
Steam
Generation
and
Superheating
Combustion
Air
Pre-heat
Reformed
Gas
Process
Additional gas + steam feed
Gas
Heated
Post-
Reformer
Waste
Heat
Boiler
HDS
Preheat
Mixed
Feed
Preheat
22. Addition of Saturator
Recovers low grade heat into the process
Maximizes quality and quantity
Up to 13 mt/hr of export steam can be
generated
Link with CO2 solution change
23. Addition of a Saturator
MP Steam
Existing
Reformer
Natural Gas
Synthesis Gas
Heater
Saturator
24. Combustion Air Preheat
Allows for improvement in heat recovery
from the duct
Most suitable for top fired furnaces but can
be applied to side fired furnaces
• Cost is higher due to complexity of
ducting
Will reduce fluegas flow and therefore heat
available in the duct - must model this
carefully
Improve plant efficiency by 30 GJ/mmSCF
Can allow for rate increase
25. VULCAN SG Delta Retrofit for Shift
Vessels
By installing a specialized support
system can reduce pressure drop
significantly
GBHE can offer the VULCAN SG Delta
which can reduce pressure drop by
around 50%
Allows plant rate increases of up to 3%
26. Other Options
Use ROG or other streams as a feed
Use low methanol LTS catalyst
Preheat fuel
Change CO2 solution
Install quench upstream of LTS
Reduction in excess air in reformer
27. Hydrogen Plant Revamp Capacity
Increases
What capacity
increase is required ?
>15%
Front End
Catalyst size
change
VULCAN SG Delta
SC Reduction
LTS Quench
<5%
Front End
Catalyst shape and
size change
Pre-reformer
Re-tube
Change reformer
exit temperature
5-15%
Front End
ATR
AGHRPR
28. Hydrogen Plant Revamp Efficiency
Improvements
What efficiency improvement
is required ?
>15 GJ/mmSCF<5 GJ/mmSCF
Front End
ATR
SC ratio change
Fuel preheat
Excess air
optimisation
5-15 GJ/mmSCF
Front End
Pre-reformer
Saturator
CA preheat
Front End
Optimised reformer
catalyst loading
Re-tube
VULCAN SG Delta
29. Problems and Pitfalls
Contractor and Contract
Must carefully select partners
• Must have domain knowledge
Design and operations
• Must have correct tools
• Must be able to supply correct level of detail
for study
Must select appropriate contract type
• LSTK or Reimbursable
• Both have advantages and disadvantages
30. Problems and Pitfalls
Modelling Capability
Must use correct tools
Model the whole plant using a
flowsheeting package
• Must include all unit operations
• Must develop a robust base case
• Must validate against plant data
• Must understand deviations
• Then develop the retrofit case
31. Problems and Pitfalls
Retrofit Details
The customer and engineering contractor
must determine
• Precise scope for retrofit
• Responsibilities
• Key deliverables
• A detailed and consistent design basis
• Time scale and milestones
• Review schedules
Summarize as Good Project Management
32. Problems and Pitfalls
Design Basis
Engineering contractor must conduct on
site visit
• Must work with client
• Collect representative plant data
• Model and understand plant data
• Discuss discrepancies and eliminate
• Identify bottlenecks
• Identify opportunities for improvement
These form the core of the design basis
33. Problems and Pitfalls
HAZOPs and Commissioning
Must use systematic review method to
highlight potential problems with retrofit
• HAZOPs are a well proven system
• Requires time and buy in from all parties
• Results as good as quality of people !
Retrofit will change plant parameters
• Must update PFDs and P&IDs
• Must update operating instructions
• Must take additional care during start up
34. What Can GBHE Catalysts Offer?
Detail catalyst unit operation models
such as the world leading VULCAN
REFORMER SIMULATION program
• Also models for other catalyst unit
operations
Detail non-catalyst unit operation
models such as
• Heat exchange programs
• Finite Element Analysis
• CFD modelling
One stop shop
35. What Can GBHE Catalysts Offer?
Domain Knowledge
• Operations
Many staff have operations
background
Troubleshooting clients plants
• Design
Many staff have detailed
engineering background
Engineers work on design daily
Work with leading contractors
on front end and detailed
design issues
Catalysts
Consulting
Services
Domain
Knowledge
36. What Can GBHE Catalysts Offer?
Can supply any level of detail for
retrofit
Scoping studies
• Front End
• What are the best options
Front End Engineering
• Flowsheets and design of key components
Detailed Engineering
• Design of all components of retrofit
A one stop shop for your revamp
requirements
37. One Stop Shop Case Study
Re-tube – Present Model
Plant
Operator
Concept
Engineer
Tube
Supplier
Catalyst
Vendor
Tube
Installer
Catalyst
Handler
No Communication
Detailed
Engineer
38. One Stop Shop Case Study
Re-tube – “One Stop Shop” Model
Plant
Operator
GBHE
Concept Engineer
Tube
Supplier
Tube
Installer
Catalyst
Handler
Detailed
Engineer
Seamless
Minimum Cost
Maximum Benefit
39. Case Study
How GBHE Catalysts Works
Strong position due to credibility from previous
work
Uprate projects
• Feasibility Process Uprate study on Naphtha 115%,
130% or 150% cases
• FEEP (Front End Engineering Package, what would be
needed?)
115% FEEP adopted
• Option evaluations and natural gas feed conversion
Followed by full Engineering Detail Design
Also additional design work on Desulfurization
Design Study
40. Conclusions
A number of retrofits have been
presented that are suitable for
application to hydrogen plants
They address all the key limitations that
hydrogen plants typically suffer from
To take full benefit from some of these
retrofits, others may also be required
GBHE Catalysts has all the right
expertise and knowledge to develop and
design retrofits