SlideShare a Scribd company logo
1 of 34
A PROPOSAL FOR
INSTALLTION OF 1 MW
SOLAR THERMAL
POWER PLANT
Submitted to the
Ministry of power
Govt. Of
Uttarakhand INDIA
1 | P a g e
SUBMITTED TO
Mrs Jyoti laxmi Kashyap
Assistant professor
Department of centre for professional communication
TEAM MEMBERS
S.no Name Sap id Roll no.
1. Sashikant Tiwari 500041217 66
2. Ragiv Rehmani 500041170 70
3. Shivank Omar 500041143 72
S. No. Content Page No.
1. Statement of request 3
2. Introduction 6
3. Background 7
4. Statement of problem 8
5. Scope 8
6. Limitation 8
7. Aim 9
8. Objective 9
9. Research question 10
10. Gaps 11
11. Risk probability 12
12. Methodology 13
13. Data gathering 13
14. Data analysis 14
15. Installation 16
16. Budget 18 , 19
17. Phase plan 20 , 21
18. Cash plan 22
19. Output 27
20. Exit plans 28
21. Benefits 29 , 30
22. Drawbacks 31
23. Conclusion 32
24. References 33
3 | P a g e
STATEMENT OF REQUEST
10th
October 2015
Sashikant Tiwari
Project Manager
Future Energy Inc.
To,
The Ministry of Power
Govt. of Uttarakhand, India
Subject: Proposal for the installation of 1MW Solar Thermal
Power Plant.
Sir,
Thank you for the opportunity to conduct business with Future
Energy Inc. We have a great idea for opening a new business on
power generation through solar energy and please submit our
proposal for more efficient , low cost solar energy generation .
Our proposal is built on proven success based methodologies for
generation of electricity by solar energy. Based on the application
of parabolic reflectors to collect solar energy and convert it into
electricity.
The following individuals together or individually, are authorize
as signatures and to negotiate on behalf of Future Energy Inc.
relating to terms, condition, pricing and concession percentage:
1.Shivank Omar , Future Energy Inc. President
preFEI@gmail.com
2.Ragiv Rehmani , Future Energy Inc. Vice-president
vicepreFEI@gmail.com
We intend to offer 22% for this business. Future Energy Inc.
is ready to begin operation within 30 days of contract
assigned.
I shall be thankful to you if you will kindly let me know the
status the status of the proposal at the earliest.
Yours faithfully
Sashikant Tiwari
Project Manager
Future Energy Inc.
Contact no.+917536036009
prmagFEI@gmail.com
According to the increasing demand of different Renewable
sources of energy . This project is about the installation of a 1MW
solar thermal energy power plant especially in the hilly areas of
the Uttrakhand to generate electricity. This will not only fulfill the
requirement of electricity in those areas but also more cost
efficient, and also generate more electricity as compared to a
normal PV solar cell. This plant is installed in such a way to
without interrupting peoples livelihood and no environmental
damage.
5 | P a g e
 Project Title:
Installation of 1MW solar power plant .
 Proposer:
1. Shivank Omar
2. Ragiv Rehmani
3. Sashikant Tiwari
 Venue of Work:
Hilly areas as per assigned by the Govt. Of Uttrakhand.
 Time Needed:
6 Months.
 PeopleInvolved:
3 Power System Engineers, 2 Designers, 30 Workers.
Approximate Budget:
INR. 645 lakhs.
The power generation service available with the Future Energy
Inc. provides an efficient and low cost method to generate power
by a completely safe mechanism designed and developed by
industry renowned the Future Energy Inc. Industry provides a
way to harness the easily available renewable source of energy to
give power without creating any hazard to environment and
native peoples. For the assurance of saving of our renewable
sources Solar Thermal Power Plant is installed.
Solar Energy Can Be Used for Heat
and Electricity:
•When converted to thermal (or heat) energy, solar energy can be
used to:
•Heat water —for use in homes, buildings, or swimming pools
•Heat spaces —inside homes, greenhouses, and other buildings
•Heat fluids —to high temperatures to operate a turbine to
generate electricity
7 | P a g e
BACKGROUND:
 Solar Thermal/Electric Power Plants generate electricity by
concentrating solar energy to heat a fluid and produce
steam that is used to power a generator. In 2009, there were
13 solar thermal-power generating units operating in the
United States, 11 in California, 1 in Arizona, and 1 in
Nevada.
 Solar thermal power currently leads the way as the most
cost-effective solar technology on a large scale. It currently
beats other PV systems, and it also can beat the cost of
electricity from fossil fuels such as natural gas. In terms of
low-cost and high negative environmental impact, nothing
competes with coal.
STATEMENT OF PROBLEM
Installation of 1MW of Solar Thermal Power Plant in a place
Which will be covering an area of around 18,210.87 -20,234.3
square meter.
SCOPE
 The provisions of this proposal shall specify the use of
energy sources other then our conventional sources which is
almost on the verge of becoming extinct. So, this kind of
energy generation methods will act like replacement for the
conventional sources.
LIMITATIONS
•The amount of sunlight that arrives at the Earth's surface is not
constant. It varies depending on location, time of day, time of
year, and weather conditions.
•Because the sun doesn't deliver that much energy to any one
place at any one time, a large surface area is required to collect
the energy at a useful rate.
AIM
Installation of 1MW Solar Thermal Power Plant .
9 | P a g e
OBJECTIVES
 To control environmental pollution
 Preserve the Non Renewable source of energy like petrol,
diesel etc.
 Develop Ultra Mega and Large scale Solar plants including
Solar Parks.
 Own, operate , develop & manage both grid connected
& off grid solar installations including rooftops.
 To take up energy access programs for rural and remote
areas through solar energy.
 To promote integrated power generation projects of solar
with conventional & renewable sources.
Research Questions
1. How can you make the system efficient?
2. How can you manage the system?
3. How can you reduce the overall cost?
4. What are the hazards presents in the industry?
5. Why are you choosing this method of energy production?
6. How you can reach rural areas by this method?
GAPS
To make the system more efficient we need to install after
performing proper audit .
Reduce the cost of the total system setup by using proper
durable items.
Proper, systematic, trained and skilled management of
the systems is required.
Health, Safety and environmental hazard analysis is
required.
Monthly audits should be conducted.
Backup should always be there in case of failure.
Risk Probability
 OPERATIONAL:
- Risk due to casual handle of Power Plant.
11 | P a g e
-Care should be taken during installation.
 BUDGET:
Some failure in system or any defect is there in system
will sell these products and replace them with new to
overcome loss.
 IMPLEMENTATIONS
 Malfunctioning of the level transmitter on the Deaerator
led to dry running of boiler feedwater pump
 COMMUNICATION PROBLEM
Data Gathering:
 Before installing the Power Plant there be initial
inspection of the whole Area of different parameters like:-
 Total area to be covered- 18,210.87 -20,234.3 square
meter
 Total people living nearby.
 Equipment and tool are in use.
 Geographical overview of that selected area.
 Transportation system.
 Power backups.
13 | P a g e
Data Analysis:
Diagram to show a circuital overview.
Fig. 1
Fig. 2 shows how it going to look after installation.
15 | P a g e
Installation of solar Thermal
 Parabolic Through
 A parabolic trough collector has a long parabolic-shaped
reflector that focuses the sun's rays on a receiver pipe
located at the focus of the parabola.The collector tilts with
 the sun as the sun moves from east to west during the day
to ensure that the sun is continuously focused on the
receiver.
 Because of its parabolic shape, a trough can focus the sun
at 30 to 100 times its normal intensity (concentration
ratio) on the receiver pipe located along the focal line of
the trough, achieving operating temperatures over 750°F.
Fig.3
BUDGET
ITEM Rs.(in lakh)
1. Supply, Installation, Erection &
Commissioning of Modules
2. Module mounting structure and
associated civil works
3. Installation , Erection &
Commissioning of Inverters
4. Cables and associated Civil works
5. Testing & Commissioning of
Transformer
6. H.T. Panel and associated civil works
7. Meters with C.T. & P.T. ,Isolators
four pole structure
8. SCADA , Weather station ,Earth and
lightening protection
9. ACDB,DCDB, Batteries with chargers
ect.
330
90
55
35
18
10
18
15
08
17 | P a g e
Total 645Lakhs(6.45 Crores )
10.String Combiner Box
11.Inverter and control Room
12.Inscurence
13.Engineering & Men power & Out
Of pocket expenses
12
30
09
15
CASH PLAN
SL
N
O.
ITEM MATERIAL MAN
POWER
DAYS
REQUIR
ED
NO. OF
ITEMS
COST
1. FOR
MATERIAL
TESTING
LABORATOR
Y
SILICON AND
GERMANIUM
1
POWER
ENGINE
ER & 1
WORKE
R
2 0 5000RS
2. FOR METAL
TESTING
IRON&COPPER
STAINLESS
STEEL
3
POWER
ENGINE
ERS
10 0 75000RS
3. PURCHASE
FOR SOLAR
PANEL
SOLAR Mirror
& SOLAR
PANEL BODY
1
SKILLED
1 100SOL
AR
PANEL
PER
10KW
200LAKH
SRS
4. TRANSPORTA
TION
SOLAR PANEL 2 NON
SKILLED
10 100 15000
5. ASSMEBLING SOLAR PANEL 30
WORKE
RS 3
POWER
ENGINE
ERS 2
DESIGN
ERS
30 100 5.95LAKH
S
6. ORDER GIVEN
FOR A
THERMAL
STORAGE
TANK
2 M HEIGHT
COPPER &
STEEL MIX
2
SKILLED
25-30 4 6 LAKHS
7. TRANSPORTA
TION
STORAGE
TANK
4 NON
SKILLED
10 4 20000 RS
8. ORDER FOR
STEAM
CONDENSER
2
SKILLED
& NON
SKILLED
25 4 5 LAKHS
9. TRANSPORTA
TION
FOR STEAM
CONDENSER
4 NON
SKILLED
10 4 25000RS
10. PURCHASE
FOR TURBINE
&
GENERATOR
4 MW HEAT
GENERATED
AND 1 MW
ELECTRICITY
GENERATED
3
SKILLED
POWER
ENGINE
ERS & 2
DESIGN
ERS
60 1 100
LAKHS
19 | P a g e
11. ASSEMBLING TURBINE &
GENERATOR&
TANK
&CONDENSER
30 NON
SKILLED
& 3
POWER
ENGINE
ER 2
DESIGN
ER
30 10 5.95
LAKHS
12. TRANSFORME
R PURCHASE
1 MW STEP UP
TRANSFORME
R
2
POWER
ENGINE
ERS
10 1 5 LAKHS
13. COST FOR
DAILY USE
ITEM
FOOD , HOTEL 35 180 0 16.2
LAKHS
14. TRANSPORTA
TION OF
TRANSFORME
R
1 MW
TRANSFORME
R
2 NON
SKILLED
2 1 4000RS
TECHNICAL PLAN
SL
NO.
ITEM DAYS
REQ
UIRE
D
1. FOR MATERIAL
TESTING LABORATORY
2
2. FOR METAL TESTING 10
3. PURCHASE FOR SOLAR
PANEL
1
4. TRANSPORTATION 10
5. ASSMEBLING 30
6. ORDER GIVEN FOR A
THERMAL ORDER FOR
STEAM CONDENSER
25
STORAGE TANK
7. TRANSPORTATION 10
8. PURCHASE FOR
TURBINE &
GENERATOR
40
9. ASSEMBLING 30
10. TRANSFORMER
PURCHASE
10
11. TRANSPORTATION OF
TRANSFORMER
2
Installation of Solar Power Plant
 Mirrors
 Receiver Tubes
 Structure
 Tracking Mechanism
 Heat Transfer Fluid
 Pressure Vessels
 Piping
21 | P a g e
Process Flow Diagram
Raw WaterTank
Cooling WaterPumps
BoilerFeed Pumps
23 | P a g e
Steam Ejector
Electrical Panels
WeatherStation
25 | P a g e
HT and LT Panels
Output
1) No Fuel Cost – Solar Thermal Energy does not require any
fuel like most other sources of renewable energy. This is a
huge advantage over other fossil fuels whose costs are
increasing at a drastic rate every year. Electricity prices are
increasingly rapidly in most parts of the world much faster
than general inflation. Price shocks due to high fuel costs are
a big risk with fossil fuel energy these days.
2) Predictable, 24/7 Power-Solar Thermal Energy can generate
power 24 hours a day. This is made possible as solar thermal
power plants store the energy in the form of molten salts etc.
Other forms of Renewable Energy like Solar PV and Wind
Energy are intermittent in nature. The electricity supply is
much more uniform and reliable.
3) No Pollution and Global Warming Effects – Solar Thermal
Energy does not cause pollution which is one of the biggest
advantages. Note there are costs associated with the
equipment used to build and transport Solar Thermal
Energy Equipment.
27 | P a g e
Exit Plan
If our company is not finding the profit in installing of Solar
Thermal Power Plant of 1MW we will be sell our project to
another company who are willing to take on this project
And ready to give us reasonable price that may come over our
loss.
Benefits
 Inexpensive Water Heating
Using the sun’s thermal energy to heat water can dramatically
reduce your electricity bill. Instead of using an electric hot water
heater, many homes have solar hot water heaters that not only
heat water but pump it through the house. According to the
government’s Energy Savers website, solar hot water heaters
work in any climate and the fuel is always free. They note that
passive water heating systems—those without pumps—require
very little maintenance, as infrequently as every 3 to 5 years.
 Inexpensive Home Heating
Passive solar heating uses a structure’s location and building
materials to collect and store the sun’s energy. According to the
Whole Building Design Guide website, features like south-facing
windows, building materials with heat storage capacities, natural
convection vents and glazed windows can all reduce the need for
electrical heating and cooling. In fact, the website reports that
even modest usage of passive solar design can reduce heating
needs between five and 25 percent, at little or no cost. Buildings
designed entirely on these principles can reduce heating needs
between 25 and 75 percent, making them cost-effective over the
life of the building.
Unlimited Source of Energy
Unlike fossil fuels, the sun’s thermal energy is in no short supply.
According to BP’s 2007 Statistical Review of World Energy, the
earth’s known oil reserves will last approximately 40 years;
however, Britain’s Oil Depletion Analysis Centre criticizes that
estimate, predicting a sharp decline in oil availability as soon as
2011. Alternative energy sources such as coal and natural gas
exist, but both are considered “dirty” sources that will pollute the
environment and the atmosphere. The sun, in contrast, offers a
limitless supply of free energy.
 Cost-Effectiveness of Solar Thermal Power Plants
Although many solar applications are small-scale and exist in
individual homes or offices, the potential exists to build solar
thermal power plants to replace traditional oil- or gas-powered
plants. According to Ferrostaal, a German solar contractor, solar
power plants are already competitive in terms of cost with their
fossil-fuel-powered competitors. They claim that solar thermal
plants remain competitive when oil costs $70 per barrel. Should
that price rise as high as $130 per barrel, solar thermal plants will
be more economical than plants fueled by oil or natural gas.
29 | P a g e
 Environmental Friendliness of Solar Thermal Power
Plants
Solar thermal power plants have several other advantages over
their fossil-fuel competitors. According to Ferrostaal, solar
thermal plants don’t require a great deal of space and can make
use of undeveloped, unproductive land. They’re built using
recyclable materials such as glass, steel and concrete. Best of all,
no fossil fuels need be consumed during the power production
process, resulting in zero harmful carbon dioxide emissions
Drawbacks
1) Future Technology has a high probability of making CSP
Obsolete – Solar Energy has become a Hotbed of Innovation with
daily news of some new breakthrough in materials and process in
PV Technology. Oerlikon has come out with a radial new a-Si
Technology while CIGs player are touting increased efficiencies.
Chinese Solar Companies have captured large chunks of the Solar
Market through low cost leadership while number of Global
Heavyweights like Posco, Samsung, Hyundai, Sharp, GE, TSMC
promise to further decrease these costs.
2) Water Issue – Solar Thermal Plants use lots of Water which is
Major Problem in Desert Areas. Using non-water cooling raises
the cost of CSP projects too much. While using Sea Water has
been proposed it remains to be seen if it possible to implement
this solution as this would imply building Plants very near the
Coastline.
3)Ecological and Cultural Issues – The Usage of Massive Arrays
of Mirrors is noted to heavily impact the Desert Wildlife
endangering the endangered species. California has already seen
a massive fight on this issue with Project Developers curtailing
the size of their Plants and spending money to move the wildlife.
4) Limited Locations and Size Limitations – Solar
Thermal Energy can only be built in places which have the high
amount of solar radiation. They can be built in deserts mostly and
require a large land area. This means its not possible to build
them in populated areas. Solar Thermal Energy also can only be
built in large sizes which are at least 50 MW in size to be
economical. This contrasts to Solar PV which is sold in sizes as
low as 5 Watts.
5)Long Gestation Time Leading to Cost Overruns – The
Gestation Time for permitting, financing, drilling etc. can easily
take 5-7 years to develop a concentrated solar thermal power
31 | P a g e
plant. Compare this to 6 months for a small wind farm or 3
months for a Solar PV plant.
6) Financing – is the biggest problem in developing projects
particularly for small solar thermal developers in this industry.
Conclusion
The solar Thermal Power Plant System installed are fully tested
and standardized based system that can help in generation of
electricity from solar energy acts as a replacements for non-
renewable sources of energy which very much cost efficient and in
abundance. It is ecofriendly and can be made easily available to
rural areas.
References
 http://www.greenworldinvestor.com
 Design, Approach ,Experience and results of 1MW solar
thermal energy. www.ese.iitb.ac.in
 HANS MÜLLER-STEINHAGEN
FREZ AND FRANZ TRIEB
INSTITUTE OF TECHNICAL
THERMODYNAMICS, GERMAN
AEROSPACE CENTRE (DLR),
STUTTGART, GERMANY
 http://www.livestrong.com/article/225606-the-advantages-
of-solar-thermal-energy/
 Solar thermal energy from Wikipedia free encyclopedia
 Fiz Karlsruhe’s Utilising concentrated Sunlight.
 “CSP Facts & Figures”.csp-world.com.June 2012.Retrived
22 April 2013.
APPENDICES
1. MW – Mega Watt
2. PV-Photovoltaic
3. CSP-Concentrated Solar Power
4. INC.-Incorporation
33 | P a g e
Qualification
Three Power System Engineers, Two Designers and 30 Workers;
 Sashikant Tiwari , Bachelor Of Technology in Power System
Engineering , University of Petroleum and Energy Studies,
Dehradun , Uttarakhand, India, Power management ,
University of Petroleum and Energy Studies, Dehradun ,
Uttarakhand , India.
 Ragiv Rehmani , Bachelor Of Technology in Power System
Engineering , University of Petroleum and Energy Studies,
Dehradun , Uttarakhand, India, M.B.A (Power System ) ,
National Power Training Institute, New Delhi
 Shivank Omar Bachelor Of Technology in Power System
Engineering , University of Petroleum and Energy Studies,
Dehradun , Uttarakhand, India, Purdue University - West
Lafayette
 Two Designers, Bachelor Of Technology in Civil
Engineering, University of Petroleum and Energy Studies,
Dehradun , Uttarakhand, India
 Workers, 20 are diploma holders, 10 workers with their
respective work experiences.

More Related Content

What's hot

Solar energy in india
Solar energy in indiaSolar energy in india
Solar energy in indiadevesh soni
 
Solar energy power point presentation
Solar energy power point presentation Solar energy power point presentation
Solar energy power point presentation Shrijeet Modi
 
Hybrid Solar-Wind Power System
Hybrid Solar-Wind Power SystemHybrid Solar-Wind Power System
Hybrid Solar-Wind Power SystemSwapnil Nakate
 
Photovoltaic Training - Session 4 - Plant Maintenance
Photovoltaic Training - Session 4 - Plant MaintenancePhotovoltaic Training - Session 4 - Plant Maintenance
Photovoltaic Training - Session 4 - Plant MaintenanceLeonardo ENERGY
 
Solar to energy presentation geofrey yator
Solar to energy presentation geofrey yatorSolar to energy presentation geofrey yator
Solar to energy presentation geofrey yatorGeofrey Yator
 
2. Solar Power Plant- O&M Issues
2. Solar Power Plant- O&M Issues2. Solar Power Plant- O&M Issues
2. Solar Power Plant- O&M IssuesNageswar Rao
 
Solar Power Presentation
Solar Power PresentationSolar Power Presentation
Solar Power Presentationthatpho
 
Lobel proposal for 1 mw crystalline pv solar power plant
Lobel proposal for 1 mw crystalline pv solar power plantLobel proposal for 1 mw crystalline pv solar power plant
Lobel proposal for 1 mw crystalline pv solar power plantL'Obel Solar Power System
 
Hybrid power generation system
Hybrid power generation systemHybrid power generation system
Hybrid power generation systemAlok Kumar Singh
 
Energy Storage Solutions - Technology Deployment Analysis
Energy Storage Solutions - Technology Deployment AnalysisEnergy Storage Solutions - Technology Deployment Analysis
Energy Storage Solutions - Technology Deployment AnalysisGensol Engineering Limited
 
Photovoltaic Power Conversion systems
Photovoltaic Power Conversion systems	Photovoltaic Power Conversion systems
Photovoltaic Power Conversion systems Niraj Solanki
 
1.introduction to Solar Energy
1.introduction to Solar Energy1.introduction to Solar Energy
1.introduction to Solar EnergyPrateek Yadav
 
Solar System proposal
Solar System proposalSolar System proposal
Solar System proposalSohail Azeem
 
Renewable Energy Power Point
Renewable Energy Power PointRenewable Energy Power Point
Renewable Energy Power Pointwallbren
 
Rooftop Solar Systems
Rooftop Solar SystemsRooftop Solar Systems
Rooftop Solar SystemsJay Ranvir
 
Mini grid and Solar home system
Mini grid and Solar home systemMini grid and Solar home system
Mini grid and Solar home systemTuong Do
 

What's hot (20)

Solar photo voltaics
Solar photo voltaics Solar photo voltaics
Solar photo voltaics
 
Solar energy in india
Solar energy in indiaSolar energy in india
Solar energy in india
 
Solar energy power point presentation
Solar energy power point presentation Solar energy power point presentation
Solar energy power point presentation
 
Hybrid Solar-Wind Power System
Hybrid Solar-Wind Power SystemHybrid Solar-Wind Power System
Hybrid Solar-Wind Power System
 
Photovoltaic Training - Session 4 - Plant Maintenance
Photovoltaic Training - Session 4 - Plant MaintenancePhotovoltaic Training - Session 4 - Plant Maintenance
Photovoltaic Training - Session 4 - Plant Maintenance
 
Solar to energy presentation geofrey yator
Solar to energy presentation geofrey yatorSolar to energy presentation geofrey yator
Solar to energy presentation geofrey yator
 
roof top solar
roof top solarroof top solar
roof top solar
 
2. Solar Power Plant- O&M Issues
2. Solar Power Plant- O&M Issues2. Solar Power Plant- O&M Issues
2. Solar Power Plant- O&M Issues
 
Solar Power Presentation
Solar Power PresentationSolar Power Presentation
Solar Power Presentation
 
Lobel proposal for 1 mw crystalline pv solar power plant
Lobel proposal for 1 mw crystalline pv solar power plantLobel proposal for 1 mw crystalline pv solar power plant
Lobel proposal for 1 mw crystalline pv solar power plant
 
Hybrid power generation system
Hybrid power generation systemHybrid power generation system
Hybrid power generation system
 
Energy Storage Solutions - Technology Deployment Analysis
Energy Storage Solutions - Technology Deployment AnalysisEnergy Storage Solutions - Technology Deployment Analysis
Energy Storage Solutions - Technology Deployment Analysis
 
Solar pv systems
Solar pv systemsSolar pv systems
Solar pv systems
 
Photovoltaic Power Conversion systems
Photovoltaic Power Conversion systems	Photovoltaic Power Conversion systems
Photovoltaic Power Conversion systems
 
1.introduction to Solar Energy
1.introduction to Solar Energy1.introduction to Solar Energy
1.introduction to Solar Energy
 
Solar System proposal
Solar System proposalSolar System proposal
Solar System proposal
 
Renewable Energy Power Point
Renewable Energy Power PointRenewable Energy Power Point
Renewable Energy Power Point
 
Rooftop Solar Systems
Rooftop Solar SystemsRooftop Solar Systems
Rooftop Solar Systems
 
Phases of Construction - Solar Project
Phases of Construction - Solar ProjectPhases of Construction - Solar Project
Phases of Construction - Solar Project
 
Mini grid and Solar home system
Mini grid and Solar home systemMini grid and Solar home system
Mini grid and Solar home system
 

Viewers also liked

Grid+connect+pv+install+and+supervise+guidelines+cec+issue+9Grid-Connected So...
Grid+connect+pv+install+and+supervise+guidelines+cec+issue+9Grid-Connected So...Grid+connect+pv+install+and+supervise+guidelines+cec+issue+9Grid-Connected So...
Grid+connect+pv+install+and+supervise+guidelines+cec+issue+9Grid-Connected So...JLanka Technologies (Pvt) Limited
 
Design Aspect of Standalone PV system
Design Aspect of Standalone PV systemDesign Aspect of Standalone PV system
Design Aspect of Standalone PV systemMalik Sameeullah
 
Standalone Solar PV system design Example
Standalone Solar PV system design ExampleStandalone Solar PV system design Example
Standalone Solar PV system design ExampleDr Naim R Kidwai
 
2.24 MW Solar Project Proposal
2.24 MW Solar Project Proposal2.24 MW Solar Project Proposal
2.24 MW Solar Project ProposalBrandon McNulty
 
Grid connected Solar Rooftop
Grid connected Solar Rooftop Grid connected Solar Rooftop
Grid connected Solar Rooftop medors
 
Solar mango corporate presentation
Solar mango   corporate presentationSolar mango   corporate presentation
Solar mango corporate presentationAnjali Khandelwal
 
Solar Thermal Power Plant Pure Solar 12 hrs 1 MW
Solar Thermal Power Plant Pure Solar 12 hrs 1 MWSolar Thermal Power Plant Pure Solar 12 hrs 1 MW
Solar Thermal Power Plant Pure Solar 12 hrs 1 MWJack Wong
 
TECHNOLOGY IN EDUCATION TIMELINE
TECHNOLOGY IN EDUCATION TIMELINETECHNOLOGY IN EDUCATION TIMELINE
TECHNOLOGY IN EDUCATION TIMELINEedna goff
 
Proposal for Installation of Solar PV system and Steam Cooking System.
Proposal for Installation of Solar PV system and Steam Cooking System.Proposal for Installation of Solar PV system and Steam Cooking System.
Proposal for Installation of Solar PV system and Steam Cooking System.Sridhar Sibi
 
Ahmendabd presentation 28th nov workshop
Ahmendabd presentation 28th nov workshopAhmendabd presentation 28th nov workshop
Ahmendabd presentation 28th nov workshopAbhinav Jain
 
SOLAR DESIGN -PREMKUMAR-1
SOLAR DESIGN -PREMKUMAR-1SOLAR DESIGN -PREMKUMAR-1
SOLAR DESIGN -PREMKUMAR-1Murugappa Group
 
Photovoltaics Case Study
Photovoltaics Case StudyPhotovoltaics Case Study
Photovoltaics Case StudyLeonardo ENERGY
 
Mojave Solar: clean and sustainable power in California
Mojave Solar: clean and sustainable power in CaliforniaMojave Solar: clean and sustainable power in California
Mojave Solar: clean and sustainable power in CaliforniaAbengoa
 
Handbook for solar_pv_systems
Handbook for solar_pv_systemsHandbook for solar_pv_systems
Handbook for solar_pv_systemsWei Chiao Kuo
 
Presentation by A. K. Bohra on Issues & Challenges in Net Metering
Presentation by A. K. Bohra on Issues & Challenges in Net MeteringPresentation by A. K. Bohra on Issues & Challenges in Net Metering
Presentation by A. K. Bohra on Issues & Challenges in Net MeteringAnil Kumar Bohra
 
Design & estimation of rooftop grid tied solar pv system
Design & estimation of rooftop grid tied solar pv systemDesign & estimation of rooftop grid tied solar pv system
Design & estimation of rooftop grid tied solar pv systemSabrina Chowdhury
 

Viewers also liked (20)

Grid+connect+pv+install+and+supervise+guidelines+cec+issue+9Grid-Connected So...
Grid+connect+pv+install+and+supervise+guidelines+cec+issue+9Grid-Connected So...Grid+connect+pv+install+and+supervise+guidelines+cec+issue+9Grid-Connected So...
Grid+connect+pv+install+and+supervise+guidelines+cec+issue+9Grid-Connected So...
 
Design Aspect of Standalone PV system
Design Aspect of Standalone PV systemDesign Aspect of Standalone PV system
Design Aspect of Standalone PV system
 
Standalone Solar PV system design Example
Standalone Solar PV system design ExampleStandalone Solar PV system design Example
Standalone Solar PV system design Example
 
2.24 MW Solar Project Proposal
2.24 MW Solar Project Proposal2.24 MW Solar Project Proposal
2.24 MW Solar Project Proposal
 
Grid connected Solar Rooftop
Grid connected Solar Rooftop Grid connected Solar Rooftop
Grid connected Solar Rooftop
 
Solar Power Plant Design and PV Syst
Solar Power Plant Design and PV SystSolar Power Plant Design and PV Syst
Solar Power Plant Design and PV Syst
 
Solar mango corporate presentation
Solar mango   corporate presentationSolar mango   corporate presentation
Solar mango corporate presentation
 
Solar Thermal Power Plant Pure Solar 12 hrs 1 MW
Solar Thermal Power Plant Pure Solar 12 hrs 1 MWSolar Thermal Power Plant Pure Solar 12 hrs 1 MW
Solar Thermal Power Plant Pure Solar 12 hrs 1 MW
 
TECHNOLOGY IN EDUCATION TIMELINE
TECHNOLOGY IN EDUCATION TIMELINETECHNOLOGY IN EDUCATION TIMELINE
TECHNOLOGY IN EDUCATION TIMELINE
 
Proposal for Installation of Solar PV system and Steam Cooking System.
Proposal for Installation of Solar PV system and Steam Cooking System.Proposal for Installation of Solar PV system and Steam Cooking System.
Proposal for Installation of Solar PV system and Steam Cooking System.
 
Solar petrol pump proposal
Solar petrol pump proposalSolar petrol pump proposal
Solar petrol pump proposal
 
Jakson_report_Final
Jakson_report_FinalJakson_report_Final
Jakson_report_Final
 
Ahmendabd presentation 28th nov workshop
Ahmendabd presentation 28th nov workshopAhmendabd presentation 28th nov workshop
Ahmendabd presentation 28th nov workshop
 
SOLAR DESIGN -PREMKUMAR-1
SOLAR DESIGN -PREMKUMAR-1SOLAR DESIGN -PREMKUMAR-1
SOLAR DESIGN -PREMKUMAR-1
 
Photovoltaics Case Study
Photovoltaics Case StudyPhotovoltaics Case Study
Photovoltaics Case Study
 
Mojave Solar: clean and sustainable power in California
Mojave Solar: clean and sustainable power in CaliforniaMojave Solar: clean and sustainable power in California
Mojave Solar: clean and sustainable power in California
 
Handbook for solar_pv_systems
Handbook for solar_pv_systemsHandbook for solar_pv_systems
Handbook for solar_pv_systems
 
BESCOM Solar Rooftop Project Guidelines
BESCOM Solar Rooftop Project GuidelinesBESCOM Solar Rooftop Project Guidelines
BESCOM Solar Rooftop Project Guidelines
 
Presentation by A. K. Bohra on Issues & Challenges in Net Metering
Presentation by A. K. Bohra on Issues & Challenges in Net MeteringPresentation by A. K. Bohra on Issues & Challenges in Net Metering
Presentation by A. K. Bohra on Issues & Challenges in Net Metering
 
Design & estimation of rooftop grid tied solar pv system
Design & estimation of rooftop grid tied solar pv systemDesign & estimation of rooftop grid tied solar pv system
Design & estimation of rooftop grid tied solar pv system
 

Similar to 1MW Solar Thermal Plant Proposal

technical paper
technical papertechnical paper
technical paperJ K Shree
 
A Praposal For Installation of 10 mw solar thermal power plant.
A Praposal For Installation of 10 mw solar thermal power plant.A Praposal For Installation of 10 mw solar thermal power plant.
A Praposal For Installation of 10 mw solar thermal power plant.Saurabh Biswas
 
Feasibility of alternating energy(solar) at IUBAT University
Feasibility of alternating energy(solar) at IUBAT University Feasibility of alternating energy(solar) at IUBAT University
Feasibility of alternating energy(solar) at IUBAT University Md. Tarekul Islam
 
IRJET- Design of Solar Rooftop Plant for JSSATEN
IRJET- Design of Solar Rooftop Plant for JSSATENIRJET- Design of Solar Rooftop Plant for JSSATEN
IRJET- Design of Solar Rooftop Plant for JSSATENIRJET Journal
 
FUNDAMENTALS OF POWER PLANT ENGINEERING LAB.docx
FUNDAMENTALS OF POWER PLANT ENGINEERING LAB.docxFUNDAMENTALS OF POWER PLANT ENGINEERING LAB.docx
FUNDAMENTALS OF POWER PLANT ENGINEERING LAB.docxAzouzAbdullah
 
Synopsis of 6 months industrial
Synopsis of 6 months industrialSynopsis of 6 months industrial
Synopsis of 6 months industrialLahsan Haque
 
Solarcentury Africa Hybrid Brochure 0216
Solarcentury Africa Hybrid Brochure 0216Solarcentury Africa Hybrid Brochure 0216
Solarcentury Africa Hybrid Brochure 0216Daniel Davies
 
IRJET- Intelligent Microgrid Connected Rooftop Solar Power Plant 2KWP
IRJET- Intelligent Microgrid Connected Rooftop Solar Power Plant 2KWPIRJET- Intelligent Microgrid Connected Rooftop Solar Power Plant 2KWP
IRJET- Intelligent Microgrid Connected Rooftop Solar Power Plant 2KWPIRJET Journal
 
IRJET- Intelligent Microgrid Connected Rooftop Solar Power Plant 2KWP
IRJET- Intelligent Microgrid Connected Rooftop Solar Power Plant 2KWPIRJET- Intelligent Microgrid Connected Rooftop Solar Power Plant 2KWP
IRJET- Intelligent Microgrid Connected Rooftop Solar Power Plant 2KWPIRJET Journal
 
Manipur solar policy 2014
Manipur solar policy 2014Manipur solar policy 2014
Manipur solar policy 2014Headway Solar
 
Optimization of PV Cell through MPPT Algorithm
Optimization of PV Cell through MPPT AlgorithmOptimization of PV Cell through MPPT Algorithm
Optimization of PV Cell through MPPT AlgorithmIRJET Journal
 
solar-ups_compress.pptx
solar-ups_compress.pptxsolar-ups_compress.pptx
solar-ups_compress.pptxAkhilKanyal1
 
IRJET- Development of Solar Palm Tree for Rural Street Lights
IRJET-  	  Development of Solar Palm Tree for Rural Street LightsIRJET-  	  Development of Solar Palm Tree for Rural Street Lights
IRJET- Development of Solar Palm Tree for Rural Street LightsIRJET Journal
 
Vertex Engineering - Presentation
Vertex Engineering -  PresentationVertex Engineering -  Presentation
Vertex Engineering - PresentationIrfan Ali Chougle
 
ISES 2013 - Day 3 - Stephen Roosa (Association of Energy Engineers) - The Tr...
ISES 2013  - Day 3 - Stephen Roosa (Association of Energy Engineers) - The Tr...ISES 2013  - Day 3 - Stephen Roosa (Association of Energy Engineers) - The Tr...
ISES 2013 - Day 3 - Stephen Roosa (Association of Energy Engineers) - The Tr...Student Energy
 
Enhancement of power generated by solar panels using reflected sunlight
Enhancement of power generated by solar panels using reflected sunlightEnhancement of power generated by solar panels using reflected sunlight
Enhancement of power generated by solar panels using reflected sunlightIRJET Journal
 
Implementation of Solar Distribution Grid for Agriculture Resources through M...
Implementation of Solar Distribution Grid for Agriculture Resources through M...Implementation of Solar Distribution Grid for Agriculture Resources through M...
Implementation of Solar Distribution Grid for Agriculture Resources through M...IRJET Journal
 

Similar to 1MW Solar Thermal Plant Proposal (20)

technical paper
technical papertechnical paper
technical paper
 
A Praposal For Installation of 10 mw solar thermal power plant.
A Praposal For Installation of 10 mw solar thermal power plant.A Praposal For Installation of 10 mw solar thermal power plant.
A Praposal For Installation of 10 mw solar thermal power plant.
 
Feasibility of alternating energy(solar) at IUBAT University
Feasibility of alternating energy(solar) at IUBAT University Feasibility of alternating energy(solar) at IUBAT University
Feasibility of alternating energy(solar) at IUBAT University
 
IRJET- Design of Solar Rooftop Plant for JSSATEN
IRJET- Design of Solar Rooftop Plant for JSSATENIRJET- Design of Solar Rooftop Plant for JSSATEN
IRJET- Design of Solar Rooftop Plant for JSSATEN
 
FUNDAMENTALS OF POWER PLANT ENGINEERING LAB.docx
FUNDAMENTALS OF POWER PLANT ENGINEERING LAB.docxFUNDAMENTALS OF POWER PLANT ENGINEERING LAB.docx
FUNDAMENTALS OF POWER PLANT ENGINEERING LAB.docx
 
Synopsis of 6 months industrial
Synopsis of 6 months industrialSynopsis of 6 months industrial
Synopsis of 6 months industrial
 
Final Report
Final ReportFinal Report
Final Report
 
Project solar
Project solar Project solar
Project solar
 
Solarcentury Africa Hybrid Brochure 0216
Solarcentury Africa Hybrid Brochure 0216Solarcentury Africa Hybrid Brochure 0216
Solarcentury Africa Hybrid Brochure 0216
 
IRJET- Intelligent Microgrid Connected Rooftop Solar Power Plant 2KWP
IRJET- Intelligent Microgrid Connected Rooftop Solar Power Plant 2KWPIRJET- Intelligent Microgrid Connected Rooftop Solar Power Plant 2KWP
IRJET- Intelligent Microgrid Connected Rooftop Solar Power Plant 2KWP
 
IRJET- Intelligent Microgrid Connected Rooftop Solar Power Plant 2KWP
IRJET- Intelligent Microgrid Connected Rooftop Solar Power Plant 2KWPIRJET- Intelligent Microgrid Connected Rooftop Solar Power Plant 2KWP
IRJET- Intelligent Microgrid Connected Rooftop Solar Power Plant 2KWP
 
Manipur solar policy 2014
Manipur solar policy 2014Manipur solar policy 2014
Manipur solar policy 2014
 
Optimization of PV Cell through MPPT Algorithm
Optimization of PV Cell through MPPT AlgorithmOptimization of PV Cell through MPPT Algorithm
Optimization of PV Cell through MPPT Algorithm
 
H00140717_Energy_Dissertation.
H00140717_Energy_Dissertation.H00140717_Energy_Dissertation.
H00140717_Energy_Dissertation.
 
solar-ups_compress.pptx
solar-ups_compress.pptxsolar-ups_compress.pptx
solar-ups_compress.pptx
 
IRJET- Development of Solar Palm Tree for Rural Street Lights
IRJET-  	  Development of Solar Palm Tree for Rural Street LightsIRJET-  	  Development of Solar Palm Tree for Rural Street Lights
IRJET- Development of Solar Palm Tree for Rural Street Lights
 
Vertex Engineering - Presentation
Vertex Engineering -  PresentationVertex Engineering -  Presentation
Vertex Engineering - Presentation
 
ISES 2013 - Day 3 - Stephen Roosa (Association of Energy Engineers) - The Tr...
ISES 2013  - Day 3 - Stephen Roosa (Association of Energy Engineers) - The Tr...ISES 2013  - Day 3 - Stephen Roosa (Association of Energy Engineers) - The Tr...
ISES 2013 - Day 3 - Stephen Roosa (Association of Energy Engineers) - The Tr...
 
Enhancement of power generated by solar panels using reflected sunlight
Enhancement of power generated by solar panels using reflected sunlightEnhancement of power generated by solar panels using reflected sunlight
Enhancement of power generated by solar panels using reflected sunlight
 
Implementation of Solar Distribution Grid for Agriculture Resources through M...
Implementation of Solar Distribution Grid for Agriculture Resources through M...Implementation of Solar Distribution Grid for Agriculture Resources through M...
Implementation of Solar Distribution Grid for Agriculture Resources through M...
 

More from Sashikant Tiwari

Summer Internship Presentation
Summer Internship PresentationSummer Internship Presentation
Summer Internship PresentationSashikant Tiwari
 
Industrial training presentation
Industrial training presentation Industrial training presentation
Industrial training presentation Sashikant Tiwari
 
Industrail training report by -Sashikant Tiwari
Industrail training report by -Sashikant TiwariIndustrail training report by -Sashikant Tiwari
Industrail training report by -Sashikant TiwariSashikant Tiwari
 
Child labour ppt made by-sashikant tiwari
Child labour ppt made by-sashikant tiwariChild labour ppt made by-sashikant tiwari
Child labour ppt made by-sashikant tiwariSashikant Tiwari
 
find the dielectric constant of a given material. made by sashikant tiwari.
 find the dielectric constant of a given material. made by sashikant tiwari. find the dielectric constant of a given material. made by sashikant tiwari.
find the dielectric constant of a given material. made by sashikant tiwari.Sashikant Tiwari
 

More from Sashikant Tiwari (6)

Summer Internship Reprot
Summer Internship ReprotSummer Internship Reprot
Summer Internship Reprot
 
Summer Internship Presentation
Summer Internship PresentationSummer Internship Presentation
Summer Internship Presentation
 
Industrial training presentation
Industrial training presentation Industrial training presentation
Industrial training presentation
 
Industrail training report by -Sashikant Tiwari
Industrail training report by -Sashikant TiwariIndustrail training report by -Sashikant Tiwari
Industrail training report by -Sashikant Tiwari
 
Child labour ppt made by-sashikant tiwari
Child labour ppt made by-sashikant tiwariChild labour ppt made by-sashikant tiwari
Child labour ppt made by-sashikant tiwari
 
find the dielectric constant of a given material. made by sashikant tiwari.
 find the dielectric constant of a given material. made by sashikant tiwari. find the dielectric constant of a given material. made by sashikant tiwari.
find the dielectric constant of a given material. made by sashikant tiwari.
 

Recently uploaded

Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSCAESB
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
Analog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAnalog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAbhinavSharma374939
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingrakeshbaidya232001
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxupamatechverse
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxupamatechverse
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSSIVASHANKAR N
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...ranjana rawat
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations120cr0395
 

Recently uploaded (20)

Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
Call Girls in Nagpur Suman Call 7001035870 Meet With Nagpur Escorts
 
Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and RoutesRoadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
 
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(PRIYA) Rajgurunagar Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentation
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
Analog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog ConverterAnalog to Digital and Digital to Analog Converter
Analog to Digital and Digital to Analog Converter
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writing
 
Introduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptxIntroduction and different types of Ethernet.pptx
Introduction and different types of Ethernet.pptx
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
 
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
The Most Attractive Pune Call Girls Budhwar Peth 8250192130 Will You Miss Thi...
 
Extrusion Processes and Their Limitations
Extrusion Processes and Their LimitationsExtrusion Processes and Their Limitations
Extrusion Processes and Their Limitations
 

1MW Solar Thermal Plant Proposal

  • 1. A PROPOSAL FOR INSTALLTION OF 1 MW SOLAR THERMAL POWER PLANT Submitted to the Ministry of power Govt. Of Uttarakhand INDIA
  • 2. 1 | P a g e SUBMITTED TO Mrs Jyoti laxmi Kashyap Assistant professor Department of centre for professional communication TEAM MEMBERS S.no Name Sap id Roll no. 1. Sashikant Tiwari 500041217 66 2. Ragiv Rehmani 500041170 70 3. Shivank Omar 500041143 72
  • 3. S. No. Content Page No. 1. Statement of request 3 2. Introduction 6 3. Background 7 4. Statement of problem 8 5. Scope 8 6. Limitation 8 7. Aim 9 8. Objective 9 9. Research question 10 10. Gaps 11 11. Risk probability 12 12. Methodology 13 13. Data gathering 13 14. Data analysis 14 15. Installation 16 16. Budget 18 , 19 17. Phase plan 20 , 21 18. Cash plan 22 19. Output 27 20. Exit plans 28 21. Benefits 29 , 30 22. Drawbacks 31 23. Conclusion 32 24. References 33
  • 4. 3 | P a g e STATEMENT OF REQUEST 10th October 2015 Sashikant Tiwari Project Manager Future Energy Inc. To, The Ministry of Power Govt. of Uttarakhand, India Subject: Proposal for the installation of 1MW Solar Thermal Power Plant. Sir, Thank you for the opportunity to conduct business with Future Energy Inc. We have a great idea for opening a new business on power generation through solar energy and please submit our proposal for more efficient , low cost solar energy generation . Our proposal is built on proven success based methodologies for generation of electricity by solar energy. Based on the application of parabolic reflectors to collect solar energy and convert it into electricity. The following individuals together or individually, are authorize as signatures and to negotiate on behalf of Future Energy Inc. relating to terms, condition, pricing and concession percentage:
  • 5. 1.Shivank Omar , Future Energy Inc. President preFEI@gmail.com 2.Ragiv Rehmani , Future Energy Inc. Vice-president vicepreFEI@gmail.com We intend to offer 22% for this business. Future Energy Inc. is ready to begin operation within 30 days of contract assigned. I shall be thankful to you if you will kindly let me know the status the status of the proposal at the earliest. Yours faithfully Sashikant Tiwari Project Manager Future Energy Inc. Contact no.+917536036009 prmagFEI@gmail.com According to the increasing demand of different Renewable sources of energy . This project is about the installation of a 1MW solar thermal energy power plant especially in the hilly areas of the Uttrakhand to generate electricity. This will not only fulfill the requirement of electricity in those areas but also more cost efficient, and also generate more electricity as compared to a normal PV solar cell. This plant is installed in such a way to without interrupting peoples livelihood and no environmental damage.
  • 6. 5 | P a g e  Project Title: Installation of 1MW solar power plant .  Proposer: 1. Shivank Omar 2. Ragiv Rehmani 3. Sashikant Tiwari  Venue of Work: Hilly areas as per assigned by the Govt. Of Uttrakhand.  Time Needed: 6 Months.  PeopleInvolved: 3 Power System Engineers, 2 Designers, 30 Workers. Approximate Budget: INR. 645 lakhs.
  • 7. The power generation service available with the Future Energy Inc. provides an efficient and low cost method to generate power by a completely safe mechanism designed and developed by industry renowned the Future Energy Inc. Industry provides a way to harness the easily available renewable source of energy to give power without creating any hazard to environment and native peoples. For the assurance of saving of our renewable sources Solar Thermal Power Plant is installed. Solar Energy Can Be Used for Heat and Electricity: •When converted to thermal (or heat) energy, solar energy can be used to: •Heat water —for use in homes, buildings, or swimming pools •Heat spaces —inside homes, greenhouses, and other buildings •Heat fluids —to high temperatures to operate a turbine to generate electricity
  • 8. 7 | P a g e BACKGROUND:  Solar Thermal/Electric Power Plants generate electricity by concentrating solar energy to heat a fluid and produce steam that is used to power a generator. In 2009, there were 13 solar thermal-power generating units operating in the United States, 11 in California, 1 in Arizona, and 1 in Nevada.  Solar thermal power currently leads the way as the most cost-effective solar technology on a large scale. It currently beats other PV systems, and it also can beat the cost of electricity from fossil fuels such as natural gas. In terms of low-cost and high negative environmental impact, nothing competes with coal. STATEMENT OF PROBLEM Installation of 1MW of Solar Thermal Power Plant in a place Which will be covering an area of around 18,210.87 -20,234.3 square meter. SCOPE
  • 9.  The provisions of this proposal shall specify the use of energy sources other then our conventional sources which is almost on the verge of becoming extinct. So, this kind of energy generation methods will act like replacement for the conventional sources. LIMITATIONS •The amount of sunlight that arrives at the Earth's surface is not constant. It varies depending on location, time of day, time of year, and weather conditions. •Because the sun doesn't deliver that much energy to any one place at any one time, a large surface area is required to collect the energy at a useful rate. AIM Installation of 1MW Solar Thermal Power Plant .
  • 10. 9 | P a g e OBJECTIVES  To control environmental pollution  Preserve the Non Renewable source of energy like petrol, diesel etc.  Develop Ultra Mega and Large scale Solar plants including Solar Parks.  Own, operate , develop & manage both grid connected & off grid solar installations including rooftops.  To take up energy access programs for rural and remote areas through solar energy.  To promote integrated power generation projects of solar with conventional & renewable sources. Research Questions 1. How can you make the system efficient? 2. How can you manage the system? 3. How can you reduce the overall cost? 4. What are the hazards presents in the industry? 5. Why are you choosing this method of energy production? 6. How you can reach rural areas by this method?
  • 11. GAPS To make the system more efficient we need to install after performing proper audit . Reduce the cost of the total system setup by using proper durable items. Proper, systematic, trained and skilled management of the systems is required. Health, Safety and environmental hazard analysis is required. Monthly audits should be conducted. Backup should always be there in case of failure. Risk Probability  OPERATIONAL: - Risk due to casual handle of Power Plant.
  • 12. 11 | P a g e -Care should be taken during installation.  BUDGET: Some failure in system or any defect is there in system will sell these products and replace them with new to overcome loss.  IMPLEMENTATIONS  Malfunctioning of the level transmitter on the Deaerator led to dry running of boiler feedwater pump  COMMUNICATION PROBLEM
  • 13. Data Gathering:  Before installing the Power Plant there be initial inspection of the whole Area of different parameters like:-  Total area to be covered- 18,210.87 -20,234.3 square meter  Total people living nearby.  Equipment and tool are in use.  Geographical overview of that selected area.  Transportation system.  Power backups.
  • 14. 13 | P a g e Data Analysis: Diagram to show a circuital overview. Fig. 1
  • 15. Fig. 2 shows how it going to look after installation.
  • 16. 15 | P a g e Installation of solar Thermal  Parabolic Through  A parabolic trough collector has a long parabolic-shaped reflector that focuses the sun's rays on a receiver pipe located at the focus of the parabola.The collector tilts with  the sun as the sun moves from east to west during the day to ensure that the sun is continuously focused on the receiver.  Because of its parabolic shape, a trough can focus the sun at 30 to 100 times its normal intensity (concentration ratio) on the receiver pipe located along the focal line of the trough, achieving operating temperatures over 750°F. Fig.3
  • 17. BUDGET ITEM Rs.(in lakh) 1. Supply, Installation, Erection & Commissioning of Modules 2. Module mounting structure and associated civil works 3. Installation , Erection & Commissioning of Inverters 4. Cables and associated Civil works 5. Testing & Commissioning of Transformer 6. H.T. Panel and associated civil works 7. Meters with C.T. & P.T. ,Isolators four pole structure 8. SCADA , Weather station ,Earth and lightening protection 9. ACDB,DCDB, Batteries with chargers ect. 330 90 55 35 18 10 18 15 08
  • 18. 17 | P a g e Total 645Lakhs(6.45 Crores ) 10.String Combiner Box 11.Inverter and control Room 12.Inscurence 13.Engineering & Men power & Out Of pocket expenses 12 30 09 15
  • 19. CASH PLAN SL N O. ITEM MATERIAL MAN POWER DAYS REQUIR ED NO. OF ITEMS COST 1. FOR MATERIAL TESTING LABORATOR Y SILICON AND GERMANIUM 1 POWER ENGINE ER & 1 WORKE R 2 0 5000RS 2. FOR METAL TESTING IRON&COPPER STAINLESS STEEL 3 POWER ENGINE ERS 10 0 75000RS 3. PURCHASE FOR SOLAR PANEL SOLAR Mirror & SOLAR PANEL BODY 1 SKILLED 1 100SOL AR PANEL PER 10KW 200LAKH SRS 4. TRANSPORTA TION SOLAR PANEL 2 NON SKILLED 10 100 15000 5. ASSMEBLING SOLAR PANEL 30 WORKE RS 3 POWER ENGINE ERS 2 DESIGN ERS 30 100 5.95LAKH S 6. ORDER GIVEN FOR A THERMAL STORAGE TANK 2 M HEIGHT COPPER & STEEL MIX 2 SKILLED 25-30 4 6 LAKHS 7. TRANSPORTA TION STORAGE TANK 4 NON SKILLED 10 4 20000 RS 8. ORDER FOR STEAM CONDENSER 2 SKILLED & NON SKILLED 25 4 5 LAKHS 9. TRANSPORTA TION FOR STEAM CONDENSER 4 NON SKILLED 10 4 25000RS 10. PURCHASE FOR TURBINE & GENERATOR 4 MW HEAT GENERATED AND 1 MW ELECTRICITY GENERATED 3 SKILLED POWER ENGINE ERS & 2 DESIGN ERS 60 1 100 LAKHS
  • 20. 19 | P a g e 11. ASSEMBLING TURBINE & GENERATOR& TANK &CONDENSER 30 NON SKILLED & 3 POWER ENGINE ER 2 DESIGN ER 30 10 5.95 LAKHS 12. TRANSFORME R PURCHASE 1 MW STEP UP TRANSFORME R 2 POWER ENGINE ERS 10 1 5 LAKHS 13. COST FOR DAILY USE ITEM FOOD , HOTEL 35 180 0 16.2 LAKHS 14. TRANSPORTA TION OF TRANSFORME R 1 MW TRANSFORME R 2 NON SKILLED 2 1 4000RS TECHNICAL PLAN SL NO. ITEM DAYS REQ UIRE D 1. FOR MATERIAL TESTING LABORATORY 2 2. FOR METAL TESTING 10 3. PURCHASE FOR SOLAR PANEL 1 4. TRANSPORTATION 10 5. ASSMEBLING 30 6. ORDER GIVEN FOR A THERMAL ORDER FOR STEAM CONDENSER 25
  • 21. STORAGE TANK 7. TRANSPORTATION 10 8. PURCHASE FOR TURBINE & GENERATOR 40 9. ASSEMBLING 30 10. TRANSFORMER PURCHASE 10 11. TRANSPORTATION OF TRANSFORMER 2 Installation of Solar Power Plant  Mirrors  Receiver Tubes  Structure  Tracking Mechanism  Heat Transfer Fluid  Pressure Vessels  Piping
  • 22. 21 | P a g e Process Flow Diagram Raw WaterTank
  • 24. 23 | P a g e Steam Ejector Electrical Panels
  • 26. 25 | P a g e HT and LT Panels
  • 27. Output 1) No Fuel Cost – Solar Thermal Energy does not require any fuel like most other sources of renewable energy. This is a huge advantage over other fossil fuels whose costs are increasing at a drastic rate every year. Electricity prices are increasingly rapidly in most parts of the world much faster than general inflation. Price shocks due to high fuel costs are a big risk with fossil fuel energy these days. 2) Predictable, 24/7 Power-Solar Thermal Energy can generate power 24 hours a day. This is made possible as solar thermal power plants store the energy in the form of molten salts etc. Other forms of Renewable Energy like Solar PV and Wind Energy are intermittent in nature. The electricity supply is much more uniform and reliable. 3) No Pollution and Global Warming Effects – Solar Thermal Energy does not cause pollution which is one of the biggest advantages. Note there are costs associated with the equipment used to build and transport Solar Thermal Energy Equipment.
  • 28. 27 | P a g e Exit Plan If our company is not finding the profit in installing of Solar Thermal Power Plant of 1MW we will be sell our project to another company who are willing to take on this project And ready to give us reasonable price that may come over our loss. Benefits  Inexpensive Water Heating Using the sun’s thermal energy to heat water can dramatically reduce your electricity bill. Instead of using an electric hot water heater, many homes have solar hot water heaters that not only heat water but pump it through the house. According to the government’s Energy Savers website, solar hot water heaters work in any climate and the fuel is always free. They note that passive water heating systems—those without pumps—require very little maintenance, as infrequently as every 3 to 5 years.  Inexpensive Home Heating Passive solar heating uses a structure’s location and building materials to collect and store the sun’s energy. According to the Whole Building Design Guide website, features like south-facing windows, building materials with heat storage capacities, natural
  • 29. convection vents and glazed windows can all reduce the need for electrical heating and cooling. In fact, the website reports that even modest usage of passive solar design can reduce heating needs between five and 25 percent, at little or no cost. Buildings designed entirely on these principles can reduce heating needs between 25 and 75 percent, making them cost-effective over the life of the building. Unlimited Source of Energy Unlike fossil fuels, the sun’s thermal energy is in no short supply. According to BP’s 2007 Statistical Review of World Energy, the earth’s known oil reserves will last approximately 40 years; however, Britain’s Oil Depletion Analysis Centre criticizes that estimate, predicting a sharp decline in oil availability as soon as 2011. Alternative energy sources such as coal and natural gas exist, but both are considered “dirty” sources that will pollute the environment and the atmosphere. The sun, in contrast, offers a limitless supply of free energy.  Cost-Effectiveness of Solar Thermal Power Plants Although many solar applications are small-scale and exist in individual homes or offices, the potential exists to build solar thermal power plants to replace traditional oil- or gas-powered plants. According to Ferrostaal, a German solar contractor, solar power plants are already competitive in terms of cost with their fossil-fuel-powered competitors. They claim that solar thermal plants remain competitive when oil costs $70 per barrel. Should that price rise as high as $130 per barrel, solar thermal plants will be more economical than plants fueled by oil or natural gas.
  • 30. 29 | P a g e  Environmental Friendliness of Solar Thermal Power Plants Solar thermal power plants have several other advantages over their fossil-fuel competitors. According to Ferrostaal, solar thermal plants don’t require a great deal of space and can make use of undeveloped, unproductive land. They’re built using recyclable materials such as glass, steel and concrete. Best of all, no fossil fuels need be consumed during the power production process, resulting in zero harmful carbon dioxide emissions
  • 31. Drawbacks 1) Future Technology has a high probability of making CSP Obsolete – Solar Energy has become a Hotbed of Innovation with daily news of some new breakthrough in materials and process in PV Technology. Oerlikon has come out with a radial new a-Si Technology while CIGs player are touting increased efficiencies. Chinese Solar Companies have captured large chunks of the Solar Market through low cost leadership while number of Global Heavyweights like Posco, Samsung, Hyundai, Sharp, GE, TSMC promise to further decrease these costs. 2) Water Issue – Solar Thermal Plants use lots of Water which is Major Problem in Desert Areas. Using non-water cooling raises the cost of CSP projects too much. While using Sea Water has been proposed it remains to be seen if it possible to implement this solution as this would imply building Plants very near the Coastline. 3)Ecological and Cultural Issues – The Usage of Massive Arrays of Mirrors is noted to heavily impact the Desert Wildlife endangering the endangered species. California has already seen a massive fight on this issue with Project Developers curtailing the size of their Plants and spending money to move the wildlife. 4) Limited Locations and Size Limitations – Solar Thermal Energy can only be built in places which have the high amount of solar radiation. They can be built in deserts mostly and require a large land area. This means its not possible to build them in populated areas. Solar Thermal Energy also can only be built in large sizes which are at least 50 MW in size to be economical. This contrasts to Solar PV which is sold in sizes as low as 5 Watts. 5)Long Gestation Time Leading to Cost Overruns – The Gestation Time for permitting, financing, drilling etc. can easily take 5-7 years to develop a concentrated solar thermal power
  • 32. 31 | P a g e plant. Compare this to 6 months for a small wind farm or 3 months for a Solar PV plant. 6) Financing – is the biggest problem in developing projects particularly for small solar thermal developers in this industry. Conclusion The solar Thermal Power Plant System installed are fully tested and standardized based system that can help in generation of electricity from solar energy acts as a replacements for non- renewable sources of energy which very much cost efficient and in abundance. It is ecofriendly and can be made easily available to rural areas.
  • 33. References  http://www.greenworldinvestor.com  Design, Approach ,Experience and results of 1MW solar thermal energy. www.ese.iitb.ac.in  HANS MÜLLER-STEINHAGEN FREZ AND FRANZ TRIEB INSTITUTE OF TECHNICAL THERMODYNAMICS, GERMAN AEROSPACE CENTRE (DLR), STUTTGART, GERMANY  http://www.livestrong.com/article/225606-the-advantages- of-solar-thermal-energy/  Solar thermal energy from Wikipedia free encyclopedia  Fiz Karlsruhe’s Utilising concentrated Sunlight.  “CSP Facts & Figures”.csp-world.com.June 2012.Retrived 22 April 2013. APPENDICES 1. MW – Mega Watt 2. PV-Photovoltaic 3. CSP-Concentrated Solar Power 4. INC.-Incorporation
  • 34. 33 | P a g e Qualification Three Power System Engineers, Two Designers and 30 Workers;  Sashikant Tiwari , Bachelor Of Technology in Power System Engineering , University of Petroleum and Energy Studies, Dehradun , Uttarakhand, India, Power management , University of Petroleum and Energy Studies, Dehradun , Uttarakhand , India.  Ragiv Rehmani , Bachelor Of Technology in Power System Engineering , University of Petroleum and Energy Studies, Dehradun , Uttarakhand, India, M.B.A (Power System ) , National Power Training Institute, New Delhi  Shivank Omar Bachelor Of Technology in Power System Engineering , University of Petroleum and Energy Studies, Dehradun , Uttarakhand, India, Purdue University - West Lafayette  Two Designers, Bachelor Of Technology in Civil Engineering, University of Petroleum and Energy Studies, Dehradun , Uttarakhand, India  Workers, 20 are diploma holders, 10 workers with their respective work experiences.