SlideShare a Scribd company logo
INTRODUCTION TO:
PROJECT MANAGEMENT
      PROJECT EXECUTION
     MODULE 2: Day 2 / S2

       by: DREAMSOFT (M)SDN BHD
       http://www.thedreamsoft.com
           admin@thedreamsoft.com
Work Breakdown Structure (WBS)

• A detailed, hierarchical (from
  general to specific) tree structure
  of deliverables and tasks that
  need to be performed to
  complete a project.
purpose or WBS


• to identify actual tasks to be done
  in a project. Serves as basis for
  project planning.

• An extension to PERT.
Standard Work Breakdown Structure
                              Standard Work Breakdown
                                   Structure (WBS)




     1.0           2.0          3.0                 4.0             5.0           6.0
   Mission     Investment     Solution        Implementation    In-Service    Disposition
   Analysis      Analysis   Development                        Management




 Activity A   Activity B    Activity C       Activity D        Activity E    Activity F




  Pre-Project Activities                  Project Specific Activities

                                                                                            LEGEND



                                                     Decomposes to lower level WBS elements
Project Management
          Day 1 / S2
Overview on Planning

             Who Will   By When Must
             Do It?     It Be Done?

                                       How Much Will
How Should                             It Cost?
It Be Done


What Must
Be Done                                 How Good Does
                                        It Has To Be?
Project Planning


Definition
• A Project Plan sets out the phases,
  activities and tasks needed to deliver
  a project.
• The timeframes required to deliver the
  project, along with the resources and
  milestones are also shown in the
  Project Plan.
Main Output From Project Planning



        PROJECT
        PLANNING



        Project       PERT Diagram   Gantt Chart
        Predecessor
        Table
History

• PERT is a network model that allows for
  randomness in activity completion
  times.
• PERT was developed in the late 1950's
  for the U.S. Navy's Polaris project
  having thousands of contractors.
  – It has the potential to reduce both the
    time and cost required to complete a
    project.
Methods

Main methods used in project planning:

3. Project Schedule
4. PERT
5. Gantt Chart
1. Project Schedule

Definition

  • An organized method of presenting in-
    formation on when activities need to be
    started, how long activities are planned
    to take, and when activities are planned
    to be completed.
  • A schedule should also reflect the logical
    relationships between activities.
2. PERT (Project Evaluation Review
Technique)
Definition

• A diagram that shows tasks and their
  relationships. Limited because it shows
  only task relationships. Strength: easy
  to read task relationships.
  – Also known as Network Diagram
Tasks

 Duration of Tasks          Durations
                     PERT   (months)
Precedors of Tasks
3. Gantt Chart

Definition

• A bar chart. While visually appealing
  on a task/duration basis, it is limited
  because it does not show task or
  resource relationships well.
  – Strength: easy to maintain and read.
An Example of a Gantt Chart
Task Name        Predecessor   Task ID Estimated   1 2 3 4 5 6 7 8 9 10
                                          Time


Mark Utilities       B           A         3
Dig Holes            C           B         2
Buy Trees            D           C         1
Buy Flowers           E          D         1
Plant Trees           F          E         2
Plant Flowers       G,H          F         1
Buy Cover             -          G         1
Install Cover         -          H         1

                                          12
Steps in the PERT Planning Process

PERT planning involves the following steps:

• Identify the specific activities and milestones
• Determine the proper sequence of the activities
• Construct a network diagram
• Estimate the time required for each activity
---------------------------
• Determine the Critical Path
• Update the PERT Chart as the project progresses
1. Identify Activities and Milestones


• The activities are the tasks required to
  complete the project.
• The milestones are the events marking
  the beginning and end of one or more
  activities.
  – It is helpful to list the tasks in a table that in
    later steps can be expanded to include
    information on sequence and duration.
2. Determine Activity Sequence

• This step may be combined with the
  activity identification step since the
  activity sequence is evident for some
  tasks.
  – Other tasks may require more analysis to
    determine the exact order in which they
    must be performed.
3. Construct the Network Diagram

• Using the activity sequence
  information, a network diagram can
  be drawn showing the sequence of
  the serial and parallel activities.
  – For the original activity-on-arc model, the
    activities are depicted by arrowed lines
    and milestones are depicted by circles or
    "bubbles".
4. Estimate Activity Times (ET)
For each activity, the model usually includes three
  time estimates:

• Optimistic time - generally the shortest time in which
  the activity can be completed.

• Most likely time - the completion time having the
  highest probability. Note that this time is different
  from the expected time.

• Pessimistic time - the longest time that an activity
  might require. Three standard deviations from the
  mean is commonly used for the pessimistic time.
Expected Time



               Expected time =
  ( Optimistic + 4 x Most likely + Pessimistic ) / 6
Standard Work Breakdown Structure
                                             Standard Work Breakdown
                                                  Structure (WBS)




     1.0            2.0            3.0           4.0             5.0            6.0            7.0            8.0
  ET:3 days      ET:2 days     ET: 1 day     ET: 1 day        ET2 days       ET:1 day       ET:1 day       ET:1 day




    A                B           C              D                 E              F             G               H
Mark Utilities   Dig Holes    Buy Trees    Buy Flowers       Plant Trees   Plant Flowers   Buy Edging   Install Edging




Project Specific Activities

                                                                                             LEGEND



                                                         Decomposes to lower level WBS elements
An Example of a Logical Sequence
Predecessor Table

Task Name /               Estimated Time   Activity   Predecessor
Description

Mark Utilities                                           B,C,D
Dig Holes                                                  E
Buy Trees                                                G,E
Buy Flowers                                                F
Plant Trees                                                F
Plant Flowers                                             E,D
Buy Edging                                                C
Install Edging                                            F,G
                 TOTALS

      Card Activities****
From PERT to GANTT Chart
An Example of a Gantt Chart
Task Name /      Predecessor Activity   Estimated    1 2 3 4 5 6 7 8 9 10
Description                              Time (ET)


Mark Utilities        B         A           3
Dig Holes            C           B          2
Buy Trees             D         C           1
Buy Flowers           E         D           1
Plant Trees           F          E          2
Plant Flowers       G,H          F          1
Buy Cover             -         G           1
Install Cover         -         H           1

                                           12
Exercise:
‘PROJECT LANDSCAPE DARUL AMAN’
Refer to Template:

• Predecessor Table
• PERT
• GANTT Chart
lesson learned

•   __________________________________   •   __________________________________
•   __________________________________   •   __________________________________
•   __________________________________   •   __________________________________
•   __________________________________   •   __________________________________
•   __________________________________   •   __________________________________
•   __________________________________   •   __________________________________
•   __________________________________   •   __________________________________
•   __________________________________   •   __________________________________
•   __________________________________   •   __________________________________
•   __________________________________   •   __________________________________
•   __________________________________   •   __________________________________
•   __________________________________   •   __________________________________
•   __________________________________   •   __________________________________
•   __________________________________   •   __________________________________
•   __________________________________   •   __________________________________

More Related Content

What's hot

Project management planning
Project management planningProject management planning
Project management planning
Alvin Niere
 
An Introduction To Project Management
An Introduction To Project ManagementAn Introduction To Project Management
An Introduction To Project ManagementAshish Mittal
 
Project Planning
Project PlanningProject Planning
Project Planning
Srinivasan Rengasamy
 
Project Scope Management -
Project Scope Management - Project Scope Management -
Project Scope Management -
dyaksa hanindito
 
Project planning and planning process
Project planning and planning processProject planning and planning process
Project planning and planning process
Shamim Hossain
 
Project life cycle
Project life cycleProject life cycle
Project life cycle
Abhishek Raj
 
4 steps to perfect project planning
4 steps to perfect project planning4 steps to perfect project planning
4 steps to perfect project planning
josephb987
 
Lec 03 project life cycle
Lec 03 project life cycleLec 03 project life cycle
Lec 03 project life cycle
SAJID ALI RUK
 
Project planning and scheduling techniques
Project planning and scheduling techniquesProject planning and scheduling techniques
Project planning and scheduling techniques
Shivangi Saini
 
Project Time Management
Project Time Management Project Time Management
Project Time Management
Waqar Ali
 
00 Introduction of project scheduling
00 Introduction of project scheduling00 Introduction of project scheduling
00 Introduction of project scheduling
Soe Naing Win
 
Project time management
Project time managementProject time management
Project time management
Imran Jamil
 
Work breakdown structures
Work breakdown structures Work breakdown structures
Work breakdown structures
Ian Cammack
 
Introduction To Primavera (P6)
Introduction To Primavera (P6)Introduction To Primavera (P6)
Introduction To Primavera (P6)
Sandip Kumar Verma
 
Project planning and scheduling
Project planning and schedulingProject planning and scheduling
Project planning and scheduling
adeel hamid
 
Project Management Tools and Techniques
Project Management Tools and TechniquesProject Management Tools and Techniques
Project Management Tools and Techniques
MaRS Discovery District
 
Primavara
PrimavaraPrimavara
Primavara
danabl
 
Primavera - Tutorial
Primavera - TutorialPrimavera - Tutorial
Primavera - Tutorial
Rajeev Sharma
 
Project management
Project managementProject management
Project management
Jay Raval
 
Ms project 2016 overview
Ms project 2016 overviewMs project 2016 overview
Ms project 2016 overview
Maher Almohamad
 

What's hot (20)

Project management planning
Project management planningProject management planning
Project management planning
 
An Introduction To Project Management
An Introduction To Project ManagementAn Introduction To Project Management
An Introduction To Project Management
 
Project Planning
Project PlanningProject Planning
Project Planning
 
Project Scope Management -
Project Scope Management - Project Scope Management -
Project Scope Management -
 
Project planning and planning process
Project planning and planning processProject planning and planning process
Project planning and planning process
 
Project life cycle
Project life cycleProject life cycle
Project life cycle
 
4 steps to perfect project planning
4 steps to perfect project planning4 steps to perfect project planning
4 steps to perfect project planning
 
Lec 03 project life cycle
Lec 03 project life cycleLec 03 project life cycle
Lec 03 project life cycle
 
Project planning and scheduling techniques
Project planning and scheduling techniquesProject planning and scheduling techniques
Project planning and scheduling techniques
 
Project Time Management
Project Time Management Project Time Management
Project Time Management
 
00 Introduction of project scheduling
00 Introduction of project scheduling00 Introduction of project scheduling
00 Introduction of project scheduling
 
Project time management
Project time managementProject time management
Project time management
 
Work breakdown structures
Work breakdown structures Work breakdown structures
Work breakdown structures
 
Introduction To Primavera (P6)
Introduction To Primavera (P6)Introduction To Primavera (P6)
Introduction To Primavera (P6)
 
Project planning and scheduling
Project planning and schedulingProject planning and scheduling
Project planning and scheduling
 
Project Management Tools and Techniques
Project Management Tools and TechniquesProject Management Tools and Techniques
Project Management Tools and Techniques
 
Primavara
PrimavaraPrimavara
Primavara
 
Primavera - Tutorial
Primavera - TutorialPrimavera - Tutorial
Primavera - Tutorial
 
Project management
Project managementProject management
Project management
 
Ms project 2016 overview
Ms project 2016 overviewMs project 2016 overview
Ms project 2016 overview
 

Viewers also liked

Project planning
Project planning Project planning
Project planning
Dipnarayan Thakur
 
Planning and Resourcing a Project
Planning and Resourcing a ProjectPlanning and Resourcing a Project
Planning and Resourcing a Project
Nishant Munjal
 
Project Planning Basics - Everything you need to start managing a project
Project Planning Basics - Everything you need to start managing a projectProject Planning Basics - Everything you need to start managing a project
Project Planning Basics - Everything you need to start managing a project
Keely Killpack, PhD
 
4 Project Pre-Planning & Stakeholder Analysis
4 Project Pre-Planning & Stakeholder Analysis4 Project Pre-Planning & Stakeholder Analysis
4 Project Pre-Planning & Stakeholder Analysis
Tony
 
3 Project Cycle and Planning (4-6 hours)
3 Project Cycle and Planning (4-6 hours)3 Project Cycle and Planning (4-6 hours)
3 Project Cycle and Planning (4-6 hours)
Tony
 
Managing Project Resources
Managing Project ResourcesManaging Project Resources
Managing Project ResourcesToyin Osunlaja
 
Project planning and project work plan
Project planning and project work planProject planning and project work plan
Project planning and project work plan
Ferdinand Importado, CPA, MBA
 
Planning And Controlling
Planning And ControllingPlanning And Controlling
Planning And Controlling
Manuel Ardales
 
Project planning and control
Project planning and controlProject planning and control
Project planning and control
Venugopal Venkatachalapathy
 
5 The Logical Framework - a short course for NGOs
5 The Logical Framework - a short course for NGOs5 The Logical Framework - a short course for NGOs
5 The Logical Framework - a short course for NGOs
Tony
 
Importance of Ethics
Importance of EthicsImportance of Ethics
Importance of Ethics
Sayak Sarkar
 
Introduction to Agile Project Planning and Project Management
Introduction to Agile Project Planning and Project ManagementIntroduction to Agile Project Planning and Project Management
Introduction to Agile Project Planning and Project Management
Mike Cottmeyer
 
Fundamentals of Project Management
Fundamentals of Project ManagementFundamentals of Project Management
Fundamentals of Project Management
Rodolfo Siles
 

Viewers also liked (15)

Project planning
Project planning Project planning
Project planning
 
Planning and Resourcing a Project
Planning and Resourcing a ProjectPlanning and Resourcing a Project
Planning and Resourcing a Project
 
Project Planning Basics - Everything you need to start managing a project
Project Planning Basics - Everything you need to start managing a projectProject Planning Basics - Everything you need to start managing a project
Project Planning Basics - Everything you need to start managing a project
 
4 Project Pre-Planning & Stakeholder Analysis
4 Project Pre-Planning & Stakeholder Analysis4 Project Pre-Planning & Stakeholder Analysis
4 Project Pre-Planning & Stakeholder Analysis
 
3 Project Cycle and Planning (4-6 hours)
3 Project Cycle and Planning (4-6 hours)3 Project Cycle and Planning (4-6 hours)
3 Project Cycle and Planning (4-6 hours)
 
Managing Project Resources
Managing Project ResourcesManaging Project Resources
Managing Project Resources
 
Project planning and project work plan
Project planning and project work planProject planning and project work plan
Project planning and project work plan
 
Project organization
Project organizationProject organization
Project organization
 
Planning And Controlling
Planning And ControllingPlanning And Controlling
Planning And Controlling
 
Project planning and control
Project planning and controlProject planning and control
Project planning and control
 
5 The Logical Framework - a short course for NGOs
5 The Logical Framework - a short course for NGOs5 The Logical Framework - a short course for NGOs
5 The Logical Framework - a short course for NGOs
 
Importance of Ethics
Importance of EthicsImportance of Ethics
Importance of Ethics
 
Introduction to Agile Project Planning and Project Management
Introduction to Agile Project Planning and Project ManagementIntroduction to Agile Project Planning and Project Management
Introduction to Agile Project Planning and Project Management
 
Ethics
EthicsEthics
Ethics
 
Fundamentals of Project Management
Fundamentals of Project ManagementFundamentals of Project Management
Fundamentals of Project Management
 

Similar to Project Planning

Chapter 2
Chapter 2Chapter 2
Chapter 2Mr SMAK
 
Chapter 2 ASE
Chapter 2 ASEChapter 2 ASE
Chapter 2 ASEMr SMAK
 
Software project-scheduling
Software project-schedulingSoftware project-scheduling
Software project-schedulingsaurabhshertukde
 
WBS And Scheduling for eLearning Project Managament
WBS And Scheduling for eLearning Project ManagamentWBS And Scheduling for eLearning Project Managament
WBS And Scheduling for eLearning Project Managament
Michael M Grant
 
Ms Project Workshop
Ms Project WorkshopMs Project Workshop
Ms Project Workshop
Eder Alves
 
Slides 2015 for contact 1
Slides 2015 for contact 1Slides 2015 for contact 1
Slides 2015 for contact 1
YourhighnessJordaan
 
Project Management Through Gantt & Pert Chart
Project Management Through Gantt & Pert ChartProject Management Through Gantt & Pert Chart
Project Management Through Gantt & Pert Chart
Vinay Prajapati
 
Project mgt
Project mgtProject mgt
Project mgtNgoc Dep
 
Barbayanni results and approach 2013
Barbayanni results and approach 2013Barbayanni results and approach 2013
Barbayanni results and approach 2013Matilda Barbayanni
 
Barbayanni -results and approach
Barbayanni -results and approach Barbayanni -results and approach
Barbayanni -results and approach Matilda Barbayanni
 
Barbayanni -Results and Approach
Barbayanni -Results and Approach Barbayanni -Results and Approach
Barbayanni -Results and Approach Matilda Barbayanni
 
Barbayanni results and approach 2013
Barbayanni results and approach 2013Barbayanni results and approach 2013
Barbayanni results and approach 2013Matilda Barbayanni
 
CPM-PERT.ppt
CPM-PERT.pptCPM-PERT.ppt
CPM-PERT.ppt
AhmadAbdullah626071
 
Eggert.joe
Eggert.joeEggert.joe
Eggert.joeNASAPMC
 
Software engineering ppt on pert and gantt charts
Software engineering ppt on pert and gantt chartsSoftware engineering ppt on pert and gantt charts
Software engineering ppt on pert and gantt charts
GovadaDhana
 

Similar to Project Planning (20)

Chapter 2
Chapter 2Chapter 2
Chapter 2
 
Chapter 2 ASE
Chapter 2 ASEChapter 2 ASE
Chapter 2 ASE
 
Software project-scheduling
Software project-schedulingSoftware project-scheduling
Software project-scheduling
 
WBS And Scheduling for eLearning Project Managament
WBS And Scheduling for eLearning Project ManagamentWBS And Scheduling for eLearning Project Managament
WBS And Scheduling for eLearning Project Managament
 
Ms Project Workshop
Ms Project WorkshopMs Project Workshop
Ms Project Workshop
 
Chap003
Chap003Chap003
Chap003
 
Ch3 proj.mgt
Ch3 proj.mgtCh3 proj.mgt
Ch3 proj.mgt
 
Project admin lu3
Project admin   lu3Project admin   lu3
Project admin lu3
 
Ch3 proj.mgt
Ch3 proj.mgtCh3 proj.mgt
Ch3 proj.mgt
 
Slides 2015 for contact 1
Slides 2015 for contact 1Slides 2015 for contact 1
Slides 2015 for contact 1
 
Project Management Through Gantt & Pert Chart
Project Management Through Gantt & Pert ChartProject Management Through Gantt & Pert Chart
Project Management Through Gantt & Pert Chart
 
Project mgt
Project mgtProject mgt
Project mgt
 
Barbayanni results and approach 2013
Barbayanni results and approach 2013Barbayanni results and approach 2013
Barbayanni results and approach 2013
 
Barbayanni -results and approach
Barbayanni -results and approach Barbayanni -results and approach
Barbayanni -results and approach
 
Barbayanni -Results and Approach
Barbayanni -Results and Approach Barbayanni -Results and Approach
Barbayanni -Results and Approach
 
Barbayanni results and approach 2013
Barbayanni results and approach 2013Barbayanni results and approach 2013
Barbayanni results and approach 2013
 
CPM-PERT.ppt
CPM-PERT.pptCPM-PERT.ppt
CPM-PERT.ppt
 
Eggert.joe
Eggert.joeEggert.joe
Eggert.joe
 
D07 Project Charter
D07 Project CharterD07 Project Charter
D07 Project Charter
 
Software engineering ppt on pert and gantt charts
Software engineering ppt on pert and gantt chartsSoftware engineering ppt on pert and gantt charts
Software engineering ppt on pert and gantt charts
 

More from megat zainurul anuar

Final Project Closing
Final Project ClosingFinal Project Closing
Final Project Closing
megat zainurul anuar
 
Project Execution
Project ExecutionProject Execution
Project Execution
megat zainurul anuar
 
Project Scope Managemen Final Megat
Project Scope Managemen Final MegatProject Scope Managemen Final Megat
Project Scope Managemen Final Megat
megat zainurul anuar
 
Introduction To Project Management Megat
Introduction To Project Management MegatIntroduction To Project Management Megat
Introduction To Project Management Megat
megat zainurul anuar
 
Information And Decision Support System
Information And Decision Support SystemInformation And Decision Support System
Information And Decision Support System
megat zainurul anuar
 
Information System and Information Technology
Information System and Information TechnologyInformation System and Information Technology
Information System and Information Technology
megat zainurul anuar
 

More from megat zainurul anuar (7)

Final Project Closing
Final Project ClosingFinal Project Closing
Final Project Closing
 
Project Execution
Project ExecutionProject Execution
Project Execution
 
Project Scope Managemen Final Megat
Project Scope Managemen Final MegatProject Scope Managemen Final Megat
Project Scope Managemen Final Megat
 
Introduction To Project Management Megat
Introduction To Project Management MegatIntroduction To Project Management Megat
Introduction To Project Management Megat
 
Information And Decision Support System
Information And Decision Support SystemInformation And Decision Support System
Information And Decision Support System
 
Information System and Information Technology
Information System and Information TechnologyInformation System and Information Technology
Information System and Information Technology
 
Knowledge Management Megat
Knowledge Management MegatKnowledge Management Megat
Knowledge Management Megat
 

Recently uploaded

Knowledge engineering: from people to machines and back
Knowledge engineering: from people to machines and backKnowledge engineering: from people to machines and back
Knowledge engineering: from people to machines and back
Elena Simperl
 
Empowering NextGen Mobility via Large Action Model Infrastructure (LAMI): pav...
Empowering NextGen Mobility via Large Action Model Infrastructure (LAMI): pav...Empowering NextGen Mobility via Large Action Model Infrastructure (LAMI): pav...
Empowering NextGen Mobility via Large Action Model Infrastructure (LAMI): pav...
Thierry Lestable
 
Slack (or Teams) Automation for Bonterra Impact Management (fka Social Soluti...
Slack (or Teams) Automation for Bonterra Impact Management (fka Social Soluti...Slack (or Teams) Automation for Bonterra Impact Management (fka Social Soluti...
Slack (or Teams) Automation for Bonterra Impact Management (fka Social Soluti...
Jeffrey Haguewood
 
Leading Change strategies and insights for effective change management pdf 1.pdf
Leading Change strategies and insights for effective change management pdf 1.pdfLeading Change strategies and insights for effective change management pdf 1.pdf
Leading Change strategies and insights for effective change management pdf 1.pdf
OnBoard
 
From Siloed Products to Connected Ecosystem: Building a Sustainable and Scala...
From Siloed Products to Connected Ecosystem: Building a Sustainable and Scala...From Siloed Products to Connected Ecosystem: Building a Sustainable and Scala...
From Siloed Products to Connected Ecosystem: Building a Sustainable and Scala...
Product School
 
FIDO Alliance Osaka Seminar: FIDO Security Aspects.pdf
FIDO Alliance Osaka Seminar: FIDO Security Aspects.pdfFIDO Alliance Osaka Seminar: FIDO Security Aspects.pdf
FIDO Alliance Osaka Seminar: FIDO Security Aspects.pdf
FIDO Alliance
 
Connector Corner: Automate dynamic content and events by pushing a button
Connector Corner: Automate dynamic content and events by pushing a buttonConnector Corner: Automate dynamic content and events by pushing a button
Connector Corner: Automate dynamic content and events by pushing a button
DianaGray10
 
AI for Every Business: Unlocking Your Product's Universal Potential by VP of ...
AI for Every Business: Unlocking Your Product's Universal Potential by VP of ...AI for Every Business: Unlocking Your Product's Universal Potential by VP of ...
AI for Every Business: Unlocking Your Product's Universal Potential by VP of ...
Product School
 
Software Delivery At the Speed of AI: Inflectra Invests In AI-Powered Quality
Software Delivery At the Speed of AI: Inflectra Invests In AI-Powered QualitySoftware Delivery At the Speed of AI: Inflectra Invests In AI-Powered Quality
Software Delivery At the Speed of AI: Inflectra Invests In AI-Powered Quality
Inflectra
 
Kubernetes & AI - Beauty and the Beast !?! @KCD Istanbul 2024
Kubernetes & AI - Beauty and the Beast !?! @KCD Istanbul 2024Kubernetes & AI - Beauty and the Beast !?! @KCD Istanbul 2024
Kubernetes & AI - Beauty and the Beast !?! @KCD Istanbul 2024
Tobias Schneck
 
Smart TV Buyer Insights Survey 2024 by 91mobiles.pdf
Smart TV Buyer Insights Survey 2024 by 91mobiles.pdfSmart TV Buyer Insights Survey 2024 by 91mobiles.pdf
Smart TV Buyer Insights Survey 2024 by 91mobiles.pdf
91mobiles
 
Generating a custom Ruby SDK for your web service or Rails API using Smithy
Generating a custom Ruby SDK for your web service or Rails API using SmithyGenerating a custom Ruby SDK for your web service or Rails API using Smithy
Generating a custom Ruby SDK for your web service or Rails API using Smithy
g2nightmarescribd
 
DevOps and Testing slides at DASA Connect
DevOps and Testing slides at DASA ConnectDevOps and Testing slides at DASA Connect
DevOps and Testing slides at DASA Connect
Kari Kakkonen
 
FIDO Alliance Osaka Seminar: Overview.pdf
FIDO Alliance Osaka Seminar: Overview.pdfFIDO Alliance Osaka Seminar: Overview.pdf
FIDO Alliance Osaka Seminar: Overview.pdf
FIDO Alliance
 
GDG Cloud Southlake #33: Boule & Rebala: Effective AppSec in SDLC using Deplo...
GDG Cloud Southlake #33: Boule & Rebala: Effective AppSec in SDLC using Deplo...GDG Cloud Southlake #33: Boule & Rebala: Effective AppSec in SDLC using Deplo...
GDG Cloud Southlake #33: Boule & Rebala: Effective AppSec in SDLC using Deplo...
James Anderson
 
Mission to Decommission: Importance of Decommissioning Products to Increase E...
Mission to Decommission: Importance of Decommissioning Products to Increase E...Mission to Decommission: Importance of Decommissioning Products to Increase E...
Mission to Decommission: Importance of Decommissioning Products to Increase E...
Product School
 
When stars align: studies in data quality, knowledge graphs, and machine lear...
When stars align: studies in data quality, knowledge graphs, and machine lear...When stars align: studies in data quality, knowledge graphs, and machine lear...
When stars align: studies in data quality, knowledge graphs, and machine lear...
Elena Simperl
 
Accelerate your Kubernetes clusters with Varnish Caching
Accelerate your Kubernetes clusters with Varnish CachingAccelerate your Kubernetes clusters with Varnish Caching
Accelerate your Kubernetes clusters with Varnish Caching
Thijs Feryn
 
Epistemic Interaction - tuning interfaces to provide information for AI support
Epistemic Interaction - tuning interfaces to provide information for AI supportEpistemic Interaction - tuning interfaces to provide information for AI support
Epistemic Interaction - tuning interfaces to provide information for AI support
Alan Dix
 
State of ICS and IoT Cyber Threat Landscape Report 2024 preview
State of ICS and IoT Cyber Threat Landscape Report 2024 previewState of ICS and IoT Cyber Threat Landscape Report 2024 preview
State of ICS and IoT Cyber Threat Landscape Report 2024 preview
Prayukth K V
 

Recently uploaded (20)

Knowledge engineering: from people to machines and back
Knowledge engineering: from people to machines and backKnowledge engineering: from people to machines and back
Knowledge engineering: from people to machines and back
 
Empowering NextGen Mobility via Large Action Model Infrastructure (LAMI): pav...
Empowering NextGen Mobility via Large Action Model Infrastructure (LAMI): pav...Empowering NextGen Mobility via Large Action Model Infrastructure (LAMI): pav...
Empowering NextGen Mobility via Large Action Model Infrastructure (LAMI): pav...
 
Slack (or Teams) Automation for Bonterra Impact Management (fka Social Soluti...
Slack (or Teams) Automation for Bonterra Impact Management (fka Social Soluti...Slack (or Teams) Automation for Bonterra Impact Management (fka Social Soluti...
Slack (or Teams) Automation for Bonterra Impact Management (fka Social Soluti...
 
Leading Change strategies and insights for effective change management pdf 1.pdf
Leading Change strategies and insights for effective change management pdf 1.pdfLeading Change strategies and insights for effective change management pdf 1.pdf
Leading Change strategies and insights for effective change management pdf 1.pdf
 
From Siloed Products to Connected Ecosystem: Building a Sustainable and Scala...
From Siloed Products to Connected Ecosystem: Building a Sustainable and Scala...From Siloed Products to Connected Ecosystem: Building a Sustainable and Scala...
From Siloed Products to Connected Ecosystem: Building a Sustainable and Scala...
 
FIDO Alliance Osaka Seminar: FIDO Security Aspects.pdf
FIDO Alliance Osaka Seminar: FIDO Security Aspects.pdfFIDO Alliance Osaka Seminar: FIDO Security Aspects.pdf
FIDO Alliance Osaka Seminar: FIDO Security Aspects.pdf
 
Connector Corner: Automate dynamic content and events by pushing a button
Connector Corner: Automate dynamic content and events by pushing a buttonConnector Corner: Automate dynamic content and events by pushing a button
Connector Corner: Automate dynamic content and events by pushing a button
 
AI for Every Business: Unlocking Your Product's Universal Potential by VP of ...
AI for Every Business: Unlocking Your Product's Universal Potential by VP of ...AI for Every Business: Unlocking Your Product's Universal Potential by VP of ...
AI for Every Business: Unlocking Your Product's Universal Potential by VP of ...
 
Software Delivery At the Speed of AI: Inflectra Invests In AI-Powered Quality
Software Delivery At the Speed of AI: Inflectra Invests In AI-Powered QualitySoftware Delivery At the Speed of AI: Inflectra Invests In AI-Powered Quality
Software Delivery At the Speed of AI: Inflectra Invests In AI-Powered Quality
 
Kubernetes & AI - Beauty and the Beast !?! @KCD Istanbul 2024
Kubernetes & AI - Beauty and the Beast !?! @KCD Istanbul 2024Kubernetes & AI - Beauty and the Beast !?! @KCD Istanbul 2024
Kubernetes & AI - Beauty and the Beast !?! @KCD Istanbul 2024
 
Smart TV Buyer Insights Survey 2024 by 91mobiles.pdf
Smart TV Buyer Insights Survey 2024 by 91mobiles.pdfSmart TV Buyer Insights Survey 2024 by 91mobiles.pdf
Smart TV Buyer Insights Survey 2024 by 91mobiles.pdf
 
Generating a custom Ruby SDK for your web service or Rails API using Smithy
Generating a custom Ruby SDK for your web service or Rails API using SmithyGenerating a custom Ruby SDK for your web service or Rails API using Smithy
Generating a custom Ruby SDK for your web service or Rails API using Smithy
 
DevOps and Testing slides at DASA Connect
DevOps and Testing slides at DASA ConnectDevOps and Testing slides at DASA Connect
DevOps and Testing slides at DASA Connect
 
FIDO Alliance Osaka Seminar: Overview.pdf
FIDO Alliance Osaka Seminar: Overview.pdfFIDO Alliance Osaka Seminar: Overview.pdf
FIDO Alliance Osaka Seminar: Overview.pdf
 
GDG Cloud Southlake #33: Boule & Rebala: Effective AppSec in SDLC using Deplo...
GDG Cloud Southlake #33: Boule & Rebala: Effective AppSec in SDLC using Deplo...GDG Cloud Southlake #33: Boule & Rebala: Effective AppSec in SDLC using Deplo...
GDG Cloud Southlake #33: Boule & Rebala: Effective AppSec in SDLC using Deplo...
 
Mission to Decommission: Importance of Decommissioning Products to Increase E...
Mission to Decommission: Importance of Decommissioning Products to Increase E...Mission to Decommission: Importance of Decommissioning Products to Increase E...
Mission to Decommission: Importance of Decommissioning Products to Increase E...
 
When stars align: studies in data quality, knowledge graphs, and machine lear...
When stars align: studies in data quality, knowledge graphs, and machine lear...When stars align: studies in data quality, knowledge graphs, and machine lear...
When stars align: studies in data quality, knowledge graphs, and machine lear...
 
Accelerate your Kubernetes clusters with Varnish Caching
Accelerate your Kubernetes clusters with Varnish CachingAccelerate your Kubernetes clusters with Varnish Caching
Accelerate your Kubernetes clusters with Varnish Caching
 
Epistemic Interaction - tuning interfaces to provide information for AI support
Epistemic Interaction - tuning interfaces to provide information for AI supportEpistemic Interaction - tuning interfaces to provide information for AI support
Epistemic Interaction - tuning interfaces to provide information for AI support
 
State of ICS and IoT Cyber Threat Landscape Report 2024 preview
State of ICS and IoT Cyber Threat Landscape Report 2024 previewState of ICS and IoT Cyber Threat Landscape Report 2024 preview
State of ICS and IoT Cyber Threat Landscape Report 2024 preview
 

Project Planning

  • 1. INTRODUCTION TO: PROJECT MANAGEMENT PROJECT EXECUTION MODULE 2: Day 2 / S2 by: DREAMSOFT (M)SDN BHD http://www.thedreamsoft.com admin@thedreamsoft.com
  • 2. Work Breakdown Structure (WBS) • A detailed, hierarchical (from general to specific) tree structure of deliverables and tasks that need to be performed to complete a project.
  • 3. purpose or WBS • to identify actual tasks to be done in a project. Serves as basis for project planning. • An extension to PERT.
  • 4. Standard Work Breakdown Structure Standard Work Breakdown Structure (WBS) 1.0 2.0 3.0 4.0 5.0 6.0 Mission Investment Solution Implementation In-Service Disposition Analysis Analysis Development Management Activity A Activity B Activity C Activity D Activity E Activity F Pre-Project Activities Project Specific Activities LEGEND Decomposes to lower level WBS elements
  • 5. Project Management Day 1 / S2
  • 6. Overview on Planning Who Will By When Must Do It? It Be Done? How Much Will How Should It Cost? It Be Done What Must Be Done How Good Does It Has To Be?
  • 7. Project Planning Definition • A Project Plan sets out the phases, activities and tasks needed to deliver a project. • The timeframes required to deliver the project, along with the resources and milestones are also shown in the Project Plan.
  • 8. Main Output From Project Planning PROJECT PLANNING Project PERT Diagram Gantt Chart Predecessor Table
  • 9. History • PERT is a network model that allows for randomness in activity completion times. • PERT was developed in the late 1950's for the U.S. Navy's Polaris project having thousands of contractors. – It has the potential to reduce both the time and cost required to complete a project.
  • 10. Methods Main methods used in project planning: 3. Project Schedule 4. PERT 5. Gantt Chart
  • 11. 1. Project Schedule Definition • An organized method of presenting in- formation on when activities need to be started, how long activities are planned to take, and when activities are planned to be completed. • A schedule should also reflect the logical relationships between activities.
  • 12. 2. PERT (Project Evaluation Review Technique) Definition • A diagram that shows tasks and their relationships. Limited because it shows only task relationships. Strength: easy to read task relationships. – Also known as Network Diagram
  • 13. Tasks Duration of Tasks Durations PERT (months) Precedors of Tasks
  • 14. 3. Gantt Chart Definition • A bar chart. While visually appealing on a task/duration basis, it is limited because it does not show task or resource relationships well. – Strength: easy to maintain and read.
  • 15. An Example of a Gantt Chart Task Name Predecessor Task ID Estimated 1 2 3 4 5 6 7 8 9 10 Time Mark Utilities B A 3 Dig Holes C B 2 Buy Trees D C 1 Buy Flowers E D 1 Plant Trees F E 2 Plant Flowers G,H F 1 Buy Cover - G 1 Install Cover - H 1 12
  • 16. Steps in the PERT Planning Process PERT planning involves the following steps: • Identify the specific activities and milestones • Determine the proper sequence of the activities • Construct a network diagram • Estimate the time required for each activity --------------------------- • Determine the Critical Path • Update the PERT Chart as the project progresses
  • 17. 1. Identify Activities and Milestones • The activities are the tasks required to complete the project. • The milestones are the events marking the beginning and end of one or more activities. – It is helpful to list the tasks in a table that in later steps can be expanded to include information on sequence and duration.
  • 18. 2. Determine Activity Sequence • This step may be combined with the activity identification step since the activity sequence is evident for some tasks. – Other tasks may require more analysis to determine the exact order in which they must be performed.
  • 19. 3. Construct the Network Diagram • Using the activity sequence information, a network diagram can be drawn showing the sequence of the serial and parallel activities. – For the original activity-on-arc model, the activities are depicted by arrowed lines and milestones are depicted by circles or "bubbles".
  • 20. 4. Estimate Activity Times (ET) For each activity, the model usually includes three time estimates: • Optimistic time - generally the shortest time in which the activity can be completed. • Most likely time - the completion time having the highest probability. Note that this time is different from the expected time. • Pessimistic time - the longest time that an activity might require. Three standard deviations from the mean is commonly used for the pessimistic time.
  • 21. Expected Time Expected time = ( Optimistic + 4 x Most likely + Pessimistic ) / 6
  • 22. Standard Work Breakdown Structure Standard Work Breakdown Structure (WBS) 1.0 2.0 3.0 4.0 5.0 6.0 7.0 8.0 ET:3 days ET:2 days ET: 1 day ET: 1 day ET2 days ET:1 day ET:1 day ET:1 day A B C D E F G H Mark Utilities Dig Holes Buy Trees Buy Flowers Plant Trees Plant Flowers Buy Edging Install Edging Project Specific Activities LEGEND Decomposes to lower level WBS elements
  • 23. An Example of a Logical Sequence Predecessor Table Task Name / Estimated Time Activity Predecessor Description Mark Utilities B,C,D Dig Holes E Buy Trees G,E Buy Flowers F Plant Trees F Plant Flowers E,D Buy Edging C Install Edging F,G TOTALS Card Activities****
  • 24. From PERT to GANTT Chart
  • 25. An Example of a Gantt Chart Task Name / Predecessor Activity Estimated 1 2 3 4 5 6 7 8 9 10 Description Time (ET) Mark Utilities B A 3 Dig Holes C B 2 Buy Trees D C 1 Buy Flowers E D 1 Plant Trees F E 2 Plant Flowers G,H F 1 Buy Cover - G 1 Install Cover - H 1 12
  • 26. Exercise: ‘PROJECT LANDSCAPE DARUL AMAN’ Refer to Template: • Predecessor Table • PERT • GANTT Chart
  • 27. lesson learned • __________________________________ • __________________________________ • __________________________________ • __________________________________ • __________________________________ • __________________________________ • __________________________________ • __________________________________ • __________________________________ • __________________________________ • __________________________________ • __________________________________ • __________________________________ • __________________________________ • __________________________________ • __________________________________ • __________________________________ • __________________________________ • __________________________________ • __________________________________ • __________________________________ • __________________________________ • __________________________________ • __________________________________ • __________________________________ • __________________________________ • __________________________________ • __________________________________ • __________________________________ • __________________________________