SlideShare a Scribd company logo
(cc) 2011 Michael M. Grant | Image from beccaxsos at Flickr.com




eLearning	
  project	
  management	
  
WBS	
  




                             Scheduling	
  




                                                                    Gantt	
  Chart	
  
      Identify	
                              Identify	
  and	
                      Display	
  and	
  
      project	
  tasks	
                      level	
                                communicate	
  
                                              resources	
                            tasks	
  and	
  
                                                                                     scheduling	
  of	
  
                                                                                     resources	
  
¡    Very	
  similar	
  to	
  task	
     1.    Begin	
  at	
  the	
  top	
  
      analysis/content	
                  2.    Name	
  all	
  the	
  tasks	
  
      analysis,	
  particularly	
         3.    Organize	
  the	
  WBS	
  
      Dick,	
  Carey	
  &	
  Carey	
  
¡  By	
  top,	
  we	
  mean	
  a	
  top-­‐down	
  process	
  
¡  Begin	
  by	
  listing	
  all	
  the	
  deliverables	
  




                                                        Image from Trip Deezil at Flickr.com
¡  This	
  is	
  all	
  the	
  tasks	
  and	
  sub-­‐tasks	
  
¡  Convert	
  each	
  deliverable	
  and	
  tasks	
  into	
      real	
  
    tasks 	
  
¡  Recognize	
  the	
  summary	
  tasks	
  and	
  the	
  work	
  
    packages.	
  


              Verb	
  +	
  product	
  =	
  Task	
  
¡    Once	
  all	
  the	
  work	
       ¡    How	
  do	
  you	
  choose?	
  
      packages	
  have	
  been	
               It	
  depends	
  on	
  what	
  you	
  
      identified,	
  arrange	
                  want	
  to	
  communicate.	
  
      them,	
  and	
  there	
  are	
           §  One	
  may	
  emphasize	
  
      multiple	
  ways	
  to	
  do	
               features.	
  
      that.	
                                  §  One	
  may	
  emphasize	
  
                                                   phases	
  of	
  a	
  project	
  
ü    The	
  WBS	
  must	
  be	
  broken	
  down	
  starting	
  at	
  
      the	
  top.	
  
ü    Work	
  packages	
  must	
  add	
  up	
  to	
  the	
  
      summary	
  task.	
  
ü    Each	
  task	
  must	
  be	
  named	
  as	
  an	
  activity	
  that	
  
      produces	
  a	
  product	
  

                Verb	
  +	
  product	
  =	
  Task	
  
¡    perform	
  analysis 	
  
¡    research 	
  
¡    database 	
  




                                 Image from _boris at Flickr.com
¡  No	
  work	
  packages	
  should	
  be	
  
   smaller	
  than	
  8	
  hours	
  (1	
  day)	
  
¡  No	
  task	
  should	
  be	
  longer	
  than	
  the	
  
   time	
  between	
  2	
  status	
  points/
   reporting	
  periods	
  
¡  (No	
  task	
  should	
  be	
  at	
  50%	
  for	
  
   more	
  than	
  2	
  status	
  meetings.)	
  
¡    Granularity	
  
      §  If	
  it s	
  easier	
  to	
  estimate,	
  break	
  it	
  
          down.	
  
      §  If	
  it s	
  easier	
  to	
  assign,	
  break	
  it	
  down.	
  
      §  If	
  it s	
  easier	
  to	
  track,	
  break	
  it	
  down.	
  

¡    If	
  it s	
  not	
  one	
  of	
  these,	
  don t	
  
      break	
  it	
  down.	
  
¡    Don t	
  forget	
  to	
  put	
  PM	
  into	
  the	
  
      WBS,	
  maybe	
  under	
   Manage	
  
      project. 	
  

                                                                              Image from bcostin at Flickr.com
¡    Consider	
  quality	
  for	
  each	
             ¡    Types	
  of	
  quality	
  checks:	
  
      work	
  package:	
                                     §  Reviews—SME	
  review,	
  
      §  What	
  does	
  it	
  mean	
  to	
  be	
               design	
  team	
  review,	
  alpha	
  
          complete	
  with	
  this	
  task?	
                    prototype,	
  storyboard,	
  
      §  How	
  do	
  we	
  know	
  it	
  was	
  
                                                                 expert	
  review	
  
          done	
  correctly/well?	
                          §  Standards—industry	
  
                                                                 standards,	
  internal	
  
                                                                 checklist	
  
                                                             §  Testing—user	
  testing,	
  beta	
  
                                                                 testing,	
  1-­‐on-­‐1,	
  small	
  
                                                                 group,	
  field	
  trial	
  
A	
  realistic	
  schedule…	
  
¡  Includes	
  detailed	
  knowledge	
  of	
  the	
  work	
  to	
  be	
  done.	
  
¡  Has	
  tasks	
  sequenced	
  in	
  the	
  correct	
  order.	
  
¡  Accounts	
  for	
  external	
  constraints.	
  
¡  Can	
  be	
  accomplished	
  on	
  time,	
  given	
  the	
  availability	
  
     of	
  skilled	
  people	
  &	
  enough	
  equipment.	
  
Step	
  3	
  
Step	
  1	
  




                                       Step	
  2	
  
                Identify	
  task	
                     Estimate	
                             Assign	
  &	
  
                relationships	
                        durations	
  for	
                     level	
  
                                                       tasks	
                                resources	
  
¡    Sequence	
  constraints—when	
  one	
  task/work	
  package	
  
      must	
  be	
  performed	
  before	
  another	
  because	
  of	
  
      dependency	
  
¡    Indicate	
  the	
  predecessors	
  for	
  each	
  activity	
  
 Activity	
   Description	
                      Duration	
         Immediate	
  
                                                                   Predecessors	
  
 1.1	
       Analyze	
  learners	
                                          -­‐-­‐	
  
 1.2	
       Analyze	
  context	
                                          1.1	
  
 2.1	
       Define	
  performance	
  gap	
                             1.1,	
  1.2	
  
¡  Display	
  your	
  thinking	
  with	
  a	
  network	
  diagram	
  




             Image from http://press.teleinteractive.net/yackity/2005/10/06/critical_path_in_schedule_management
¡    Network	
  diagram	
  
¡    Relationships	
  
      §  Finish	
  to	
  start	
  

                                                      Task B cannot begin until Task A is finished.




                                      Image from Microsoft at http://office.microsoft.com/en-us/project/HA101130671033.aspx
¡    Network	
  diagrams	
  
      help	
  present	
  
      relationships	
  among	
  
      tasks	
  
                                                      Task B cannot begin until Task A begins.
      §  Finish	
  to	
  start	
  
      §  Start	
  to	
  start	
  




                                      Image from Microsoft at http://office.microsoft.com/en-us/project/HA101130671033.aspx
¡    Network	
  diagram	
  
¡    Relationships	
  
      §  Finish	
  to	
  start	
  
      §  Start	
  to	
  start	
  
                                                      Task B cannot finish until Task A finishes.
      §  Finish	
  to	
  finish	
  




                                      Image from Microsoft at http://office.microsoft.com/en-us/project/HA101130671033.aspx
Activity	
   Description	
                                     Duration	
                 Immediate	
  
                                                               (in	
  days)	
            Predecessors	
  
1.1	
       Analyze	
  learners	
                                   14	
                           -­‐-­‐	
  
1.2	
       Analyze	
  context	
                                    14	
                          1.1	
  
2.1	
       Define	
  performance	
  gap	
                            2	
                      1.1,	
  1.2	
  




                     Image from http://press.teleinteractive.net/yackity/2005/10/06/critical_path_in_schedule_management
¡    Identify	
  resources	
  (i.e.,	
     ¡    Labor:	
  in	
  hours	
  
      labor,	
  equipment,	
                ¡    Equipment:	
  in	
  hours	
  
      materials)	
                          ¡    Materials:	
  amount,	
  
¡    Determine	
  when	
  each	
                 when	
  needed	
  (task	
  
      resource	
  is	
  needed	
  and	
           relationship)	
  
      for	
  how	
  long.	
  




                                                                 Image from Truthout at Flickr.com
¡  Assign	
  resources,	
  primarily	
  labor	
  and	
  
    equipment	
  to	
  tasks	
  
¡  Determine	
  resources	
  for	
  each	
  day	
  and	
  
    compare	
  schedule	
  
¡  Some	
  tasks	
  may	
  not	
  be	
  completed	
  
    concurrently	
  because	
  of	
  resource	
  pool	
  or	
  
    additional	
  resources	
  may	
  be	
  needed	
  
¡    Critical	
  path	
  
      §  The	
  critical	
  path	
  is	
  the	
  longest	
  path	
  through	
  the	
  network,	
  
         but	
  represents	
  the	
  minimum	
  amount	
  of	
  time	
  a	
  project	
  will	
  
         take.	
  




                     Image from http://press.teleinteractive.net/yackity/2005/10/06/critical_path_in_schedule_management
¡    Gantt	
  
      §  Henry	
  Gantt,	
  early	
  1900s	
  
      §  Horizontal	
  axis	
  shows	
  
         schedule,	
  vertical	
  axis	
  
         shows	
  WBS	
  




                                                  Image from http://commons.wikimedia.org/wiki/File:Henri_Gannt.jpg
Image from Gary Booker at http://commons.wikimedia.org/wiki/File:GanttChartAnatomy.png
¡    Booker,	
  G.	
  (2007).	
  Ganttchartanatomy.png	
  [image].	
  Retrieved	
  January	
  27,	
  2010	
  
      from	
  http://commons.wikimedia.org/wiki/File:GanttChartAnatomy.png	
  
¡    dmdk12.	
  (2007).	
  Development	
  of	
  the	
  network	
  diagram	
  and	
  critical	
  path.	
  
      Retrieved	
  January	
  27,	
  2010	
  from	
  http://www.slideshare.net/dmdk12/the-­‐network-­‐
      diagram-­‐and-­‐critical-­‐path	
  
¡    Doval	
  Santos,	
  C.V.	
  (2005).	
  Critical	
  path	
  in	
  schedule	
  management	
  [image].	
  
      Retrieved	
  January	
  27,	
  2010	
  from	
  http://press.teleinteractive.net/yackity/
      2005/10/06/critical_path_in_schedule_management	
  
¡    Lynch,	
  M.M.	
  &	
  Roecker,	
  J.	
  (2007).	
  Project	
  managing	
  e-­‐learning:	
  A	
  handbook	
  for	
  
      successful	
  design,	
  delivery	
  and	
  management.	
  New	
  York:	
  Routledge.	
  
¡    Schwalbe,	
  K.	
  (2010).	
  Information	
  technology	
  project	
  management	
  (6th	
  ed.).	
  
      Boston,	
  MA:	
  Cengage	
  Course	
  Technology.	
  
¡    Verzuh,	
  E.	
  (2008).	
  The	
  fast	
  forward	
  MBA	
  in	
  project	
  management	
  (3rd	
  ed.).	
  
      Hoboken,	
  NJ:	
  Wiley.	
  
(cc) 2011 Michael M. Grant

More Related Content

What's hot

E Commerce Project Charter
E Commerce Project CharterE Commerce Project Charter
E Commerce Project Charter
brianbish10795
 
ERP/SAP Project Charter
ERP/SAP Project CharterERP/SAP Project Charter
ERP/SAP Project Charter
Bogdan Gorka
 
Software Project Management: Project Charter
Software Project Management: Project CharterSoftware Project Management: Project Charter
Software Project Management: Project Charter
Minhas Kamal
 
Project Governance Framework PowerPoint Presentation Slides
Project Governance Framework PowerPoint Presentation SlidesProject Governance Framework PowerPoint Presentation Slides
Project Governance Framework PowerPoint Presentation Slides
SlideTeam
 
Portfolio, Project and Programme Management
Portfolio, Project and Programme ManagementPortfolio, Project and Programme Management
Portfolio, Project and Programme ManagementBruce Levitan
 
Project Management Control
Project Management ControlProject Management Control
Project Management Control
ahmad bassiouny
 
Project Status Report With Highlights And Key Takeaways Printable Presentatio...
Project Status Report With Highlights And Key Takeaways Printable Presentatio...Project Status Report With Highlights And Key Takeaways Printable Presentatio...
Project Status Report With Highlights And Key Takeaways Printable Presentatio...
SlideTeam
 
Startup Leadership Program Curriculum 2021
Startup Leadership Program Curriculum 2021Startup Leadership Program Curriculum 2021
Startup Leadership Program Curriculum 2021
Startup Leadership Program
 
Project Charter in SPM
Project Charter in SPMProject Charter in SPM
Project Charter in SPM
MuhammadUsman1700
 
Project Business Requirements Document
Project Business Requirements DocumentProject Business Requirements Document
Project Business Requirements Document
Joshua Flewelling
 
Srs template
Srs templateSrs template
Srs templatemuqeet19
 
PMI knowledge areas and processes
PMI knowledge areas and processesPMI knowledge areas and processes
PMI knowledge areas and processesWiktor Kabatc
 
Healthcare Tracker App: Full Report
Healthcare Tracker App: Full ReportHealthcare Tracker App: Full Report
Healthcare Tracker App: Full Report
Dave Siegel
 
Sabaruddin de AB_S_Six Step ERP Project Management_FINAL
Sabaruddin de AB_S_Six Step ERP Project Management_FINALSabaruddin de AB_S_Six Step ERP Project Management_FINAL
Sabaruddin de AB_S_Six Step ERP Project Management_FINAL
sabaruddin de AB
 
Mobile Marketing Project Charter
Mobile Marketing Project CharterMobile Marketing Project Charter
Mobile Marketing Project Charter
Demand Metric
 
Business requirement document
Business requirement document Business requirement document
Business requirement document
Not yet
 
Project Management
Project ManagementProject Management
Project Management
Prarthan P
 
Critical Chain Basics
Critical Chain BasicsCritical Chain Basics
Critical Chain Basics
Jakub Linhart
 
Introduction to MS project
Introduction to MS projectIntroduction to MS project
Introduction to MS project
Samir Paralikar
 
Project Charter Template
Project Charter TemplateProject Charter Template
Project Charter Template
dmdk12
 

What's hot (20)

E Commerce Project Charter
E Commerce Project CharterE Commerce Project Charter
E Commerce Project Charter
 
ERP/SAP Project Charter
ERP/SAP Project CharterERP/SAP Project Charter
ERP/SAP Project Charter
 
Software Project Management: Project Charter
Software Project Management: Project CharterSoftware Project Management: Project Charter
Software Project Management: Project Charter
 
Project Governance Framework PowerPoint Presentation Slides
Project Governance Framework PowerPoint Presentation SlidesProject Governance Framework PowerPoint Presentation Slides
Project Governance Framework PowerPoint Presentation Slides
 
Portfolio, Project and Programme Management
Portfolio, Project and Programme ManagementPortfolio, Project and Programme Management
Portfolio, Project and Programme Management
 
Project Management Control
Project Management ControlProject Management Control
Project Management Control
 
Project Status Report With Highlights And Key Takeaways Printable Presentatio...
Project Status Report With Highlights And Key Takeaways Printable Presentatio...Project Status Report With Highlights And Key Takeaways Printable Presentatio...
Project Status Report With Highlights And Key Takeaways Printable Presentatio...
 
Startup Leadership Program Curriculum 2021
Startup Leadership Program Curriculum 2021Startup Leadership Program Curriculum 2021
Startup Leadership Program Curriculum 2021
 
Project Charter in SPM
Project Charter in SPMProject Charter in SPM
Project Charter in SPM
 
Project Business Requirements Document
Project Business Requirements DocumentProject Business Requirements Document
Project Business Requirements Document
 
Srs template
Srs templateSrs template
Srs template
 
PMI knowledge areas and processes
PMI knowledge areas and processesPMI knowledge areas and processes
PMI knowledge areas and processes
 
Healthcare Tracker App: Full Report
Healthcare Tracker App: Full ReportHealthcare Tracker App: Full Report
Healthcare Tracker App: Full Report
 
Sabaruddin de AB_S_Six Step ERP Project Management_FINAL
Sabaruddin de AB_S_Six Step ERP Project Management_FINALSabaruddin de AB_S_Six Step ERP Project Management_FINAL
Sabaruddin de AB_S_Six Step ERP Project Management_FINAL
 
Mobile Marketing Project Charter
Mobile Marketing Project CharterMobile Marketing Project Charter
Mobile Marketing Project Charter
 
Business requirement document
Business requirement document Business requirement document
Business requirement document
 
Project Management
Project ManagementProject Management
Project Management
 
Critical Chain Basics
Critical Chain BasicsCritical Chain Basics
Critical Chain Basics
 
Introduction to MS project
Introduction to MS projectIntroduction to MS project
Introduction to MS project
 
Project Charter Template
Project Charter TemplateProject Charter Template
Project Charter Template
 

Viewers also liked

E Learning Project Development
E Learning Project DevelopmentE Learning Project Development
E Learning Project Development
Kelly Smith
 
Top 7 WBS Mistakes Project Managers Make
Top 7 WBS Mistakes Project Managers MakeTop 7 WBS Mistakes Project Managers Make
Top 7 WBS Mistakes Project Managers Make
joshnankivel
 
e-Learning project initiation template
e-Learning project initiation templatee-Learning project initiation template
e-Learning project initiation template
Saffron Interactive
 
Saari, Hyvinvointia tukeva innovaatiojohtaminen
Saari, Hyvinvointia tukeva innovaatiojohtaminenSaari, Hyvinvointia tukeva innovaatiojohtaminen
Saari, Hyvinvointia tukeva innovaatiojohtaminen
Työterveyslaitos
 
10 CharacteristicS of a perfoming Project Manager
10 CharacteristicS of a perfoming Project Manager10 CharacteristicS of a perfoming Project Manager
10 CharacteristicS of a perfoming Project Manager
Lorenzo Leonelli (ITIL©, 6σ)
 
10+7 Characteristics Of A Successful Project Manager
10+7 Characteristics Of A Successful Project Manager10+7 Characteristics Of A Successful Project Manager
10+7 Characteristics Of A Successful Project Manager
lindabelflower
 
Tm E Learning Project Workflow
Tm E Learning Project WorkflowTm E Learning Project Workflow
Tm E Learning Project Workflowdevleenabasu
 
Guidelines for e-learning project
Guidelines for e-learning projectGuidelines for e-learning project
Guidelines for e-learning project
Daria Bogdanova
 
Innovointi
InnovointiInnovointi
Innovointi
Jari Jussila
 
Similarities and differences between PMBOK® Guide and PRINCE2® method
Similarities and differences between PMBOK® Guide and PRINCE2® methodSimilarities and differences between PMBOK® Guide and PRINCE2® method
Similarities and differences between PMBOK® Guide and PRINCE2® method
Svetlana Sidenko
 
Pmp session 1
Pmp session 1Pmp session 1
Pmp session 1
Wendy Feryanto
 
Skills and Characteristics of a Project Manager
Skills and Characteristics of a Project ManagerSkills and Characteristics of a Project Manager
Skills and Characteristics of a Project Manager
Ricardo Viana Vargas
 
Inse 62301 Project Management Development Plan Presentation Group#20
Inse 62301   Project Management Development Plan Presentation   Group#20Inse 62301   Project Management Development Plan Presentation   Group#20
Inse 62301 Project Management Development Plan Presentation Group#20
Sherif Hafez
 
WBS Principles
WBS PrinciplesWBS Principles
WBS Principles
dmdk12
 
Agile Project Management for elearning development
Agile Project Management for elearning developmentAgile Project Management for elearning development
Agile Project Management for elearning development
Don Bolen
 
Pmp integration chapter 4
Pmp integration chapter 4Pmp integration chapter 4
Pmp integration chapter 4
Ahmed Elshaboury,PMP,LEED GA
 
Project Management
Project ManagementProject Management
Project Management
Mark Roman
 
6 Characteristics of a Project
6 Characteristics of a Project6 Characteristics of a Project
6 Characteristics of a Project
BrightWork
 
Managing eLearning Projects
Managing eLearning ProjectsManaging eLearning Projects
Managing eLearning Projects
Gus Prestera
 
Agile Project Management for Elearning Instructional Design (mLearnCon 2015)
Agile Project Management for Elearning Instructional Design (mLearnCon 2015)Agile Project Management for Elearning Instructional Design (mLearnCon 2015)
Agile Project Management for Elearning Instructional Design (mLearnCon 2015)
TorranceLearning
 

Viewers also liked (20)

E Learning Project Development
E Learning Project DevelopmentE Learning Project Development
E Learning Project Development
 
Top 7 WBS Mistakes Project Managers Make
Top 7 WBS Mistakes Project Managers MakeTop 7 WBS Mistakes Project Managers Make
Top 7 WBS Mistakes Project Managers Make
 
e-Learning project initiation template
e-Learning project initiation templatee-Learning project initiation template
e-Learning project initiation template
 
Saari, Hyvinvointia tukeva innovaatiojohtaminen
Saari, Hyvinvointia tukeva innovaatiojohtaminenSaari, Hyvinvointia tukeva innovaatiojohtaminen
Saari, Hyvinvointia tukeva innovaatiojohtaminen
 
10 CharacteristicS of a perfoming Project Manager
10 CharacteristicS of a perfoming Project Manager10 CharacteristicS of a perfoming Project Manager
10 CharacteristicS of a perfoming Project Manager
 
10+7 Characteristics Of A Successful Project Manager
10+7 Characteristics Of A Successful Project Manager10+7 Characteristics Of A Successful Project Manager
10+7 Characteristics Of A Successful Project Manager
 
Tm E Learning Project Workflow
Tm E Learning Project WorkflowTm E Learning Project Workflow
Tm E Learning Project Workflow
 
Guidelines for e-learning project
Guidelines for e-learning projectGuidelines for e-learning project
Guidelines for e-learning project
 
Innovointi
InnovointiInnovointi
Innovointi
 
Similarities and differences between PMBOK® Guide and PRINCE2® method
Similarities and differences between PMBOK® Guide and PRINCE2® methodSimilarities and differences between PMBOK® Guide and PRINCE2® method
Similarities and differences between PMBOK® Guide and PRINCE2® method
 
Pmp session 1
Pmp session 1Pmp session 1
Pmp session 1
 
Skills and Characteristics of a Project Manager
Skills and Characteristics of a Project ManagerSkills and Characteristics of a Project Manager
Skills and Characteristics of a Project Manager
 
Inse 62301 Project Management Development Plan Presentation Group#20
Inse 62301   Project Management Development Plan Presentation   Group#20Inse 62301   Project Management Development Plan Presentation   Group#20
Inse 62301 Project Management Development Plan Presentation Group#20
 
WBS Principles
WBS PrinciplesWBS Principles
WBS Principles
 
Agile Project Management for elearning development
Agile Project Management for elearning developmentAgile Project Management for elearning development
Agile Project Management for elearning development
 
Pmp integration chapter 4
Pmp integration chapter 4Pmp integration chapter 4
Pmp integration chapter 4
 
Project Management
Project ManagementProject Management
Project Management
 
6 Characteristics of a Project
6 Characteristics of a Project6 Characteristics of a Project
6 Characteristics of a Project
 
Managing eLearning Projects
Managing eLearning ProjectsManaging eLearning Projects
Managing eLearning Projects
 
Agile Project Management for Elearning Instructional Design (mLearnCon 2015)
Agile Project Management for Elearning Instructional Design (mLearnCon 2015)Agile Project Management for Elearning Instructional Design (mLearnCon 2015)
Agile Project Management for Elearning Instructional Design (mLearnCon 2015)
 

Similar to WBS And Scheduling for eLearning Project Managament

Ms Project Workshop
Ms Project WorkshopMs Project Workshop
Ms Project Workshop
Eder Alves
 
Barbayanni results and approach 2013
Barbayanni results and approach 2013Barbayanni results and approach 2013
Barbayanni results and approach 2013Matilda Barbayanni
 
Barbayanni -results and approach
Barbayanni -results and approach Barbayanni -results and approach
Barbayanni -results and approach Matilda Barbayanni
 
Barbayanni -Results and Approach
Barbayanni -Results and Approach Barbayanni -Results and Approach
Barbayanni -Results and Approach Matilda Barbayanni
 
Barbayanni results and approach 2013
Barbayanni results and approach 2013Barbayanni results and approach 2013
Barbayanni results and approach 2013Matilda Barbayanni
 
Work Breakdown Structure
Work Breakdown StructureWork Breakdown Structure
Work Breakdown Structure
Emanuele Della Valle
 
Project Planning
Project PlanningProject Planning
Project Planning
megat zainurul anuar
 
Introduction project management
Introduction  project managementIntroduction  project management
Introduction project managementHager Aamer
 
Lesson 6 - Collaborate And Approve Content
Lesson 6 - Collaborate And Approve ContentLesson 6 - Collaborate And Approve Content
Lesson 6 - Collaborate And Approve Content
Informatica
 
PMICOS Webinar: Building a Sound Schedule in an Enterprise Environment
PMICOS Webinar: Building a Sound Schedule in an Enterprise EnvironmentPMICOS Webinar: Building a Sound Schedule in an Enterprise Environment
PMICOS Webinar: Building a Sound Schedule in an Enterprise Environment
Acumen
 
6 Work Breakdown Structure and SchedulingCavan ImagesSto.docx
6 Work Breakdown Structure  and SchedulingCavan ImagesSto.docx6 Work Breakdown Structure  and SchedulingCavan ImagesSto.docx
6 Work Breakdown Structure and SchedulingCavan ImagesSto.docx
evonnehoggarth79783
 
WBS-final-1.Project Management and Ethics.pptx
WBS-final-1.Project Management and Ethics.pptxWBS-final-1.Project Management and Ethics.pptx
WBS-final-1.Project Management and Ethics.pptx
FillHackjack
 
Work breakdown structure in project management ppt by kiran j
Work breakdown structure in project management ppt by kiran jWork breakdown structure in project management ppt by kiran j
Work breakdown structure in project management ppt by kiran j
IIT delhi
 
PMP Training - 06 project time management2
PMP Training - 06 project time management2PMP Training - 06 project time management2
PMP Training - 06 project time management2ejlp12
 
Project Management
Project ManagementProject Management
Project Management
Mr A
 
LAFS PREPRO Session 5 - Project Schedule
LAFS PREPRO Session 5 - Project ScheduleLAFS PREPRO Session 5 - Project Schedule
LAFS PREPRO Session 5 - Project Schedule
David Mullich
 
Agile Project Management with Scrum (Jack Davis)
Agile Project Management with Scrum (Jack Davis)Agile Project Management with Scrum (Jack Davis)
Agile Project Management with Scrum (Jack Davis)
Jack Davis
 

Similar to WBS And Scheduling for eLearning Project Managament (20)

Ms Project Workshop
Ms Project WorkshopMs Project Workshop
Ms Project Workshop
 
Barbayanni results and approach 2013
Barbayanni results and approach 2013Barbayanni results and approach 2013
Barbayanni results and approach 2013
 
Barbayanni -results and approach
Barbayanni -results and approach Barbayanni -results and approach
Barbayanni -results and approach
 
Barbayanni -Results and Approach
Barbayanni -Results and Approach Barbayanni -Results and Approach
Barbayanni -Results and Approach
 
Barbayanni results and approach 2013
Barbayanni results and approach 2013Barbayanni results and approach 2013
Barbayanni results and approach 2013
 
P&msp2010 04 wbs-and-estimation
P&msp2010 04 wbs-and-estimationP&msp2010 04 wbs-and-estimation
P&msp2010 04 wbs-and-estimation
 
Work Breakdown Structure
Work Breakdown StructureWork Breakdown Structure
Work Breakdown Structure
 
Project Planning
Project PlanningProject Planning
Project Planning
 
Introduction project management
Introduction  project managementIntroduction  project management
Introduction project management
 
Lesson 6 - Collaborate And Approve Content
Lesson 6 - Collaborate And Approve ContentLesson 6 - Collaborate And Approve Content
Lesson 6 - Collaborate And Approve Content
 
PMICOS Webinar: Building a Sound Schedule in an Enterprise Environment
PMICOS Webinar: Building a Sound Schedule in an Enterprise EnvironmentPMICOS Webinar: Building a Sound Schedule in an Enterprise Environment
PMICOS Webinar: Building a Sound Schedule in an Enterprise Environment
 
6 Work Breakdown Structure and SchedulingCavan ImagesSto.docx
6 Work Breakdown Structure  and SchedulingCavan ImagesSto.docx6 Work Breakdown Structure  and SchedulingCavan ImagesSto.docx
6 Work Breakdown Structure and SchedulingCavan ImagesSto.docx
 
WBS PROJECT
WBS PROJECTWBS PROJECT
WBS PROJECT
 
WBS-final-1.Project Management and Ethics.pptx
WBS-final-1.Project Management and Ethics.pptxWBS-final-1.Project Management and Ethics.pptx
WBS-final-1.Project Management and Ethics.pptx
 
Work breakdown structure in project management ppt by kiran j
Work breakdown structure in project management ppt by kiran jWork breakdown structure in project management ppt by kiran j
Work breakdown structure in project management ppt by kiran j
 
PMP Training - 06 project time management2
PMP Training - 06 project time management2PMP Training - 06 project time management2
PMP Training - 06 project time management2
 
Project Management
Project ManagementProject Management
Project Management
 
Assign9
Assign9Assign9
Assign9
 
LAFS PREPRO Session 5 - Project Schedule
LAFS PREPRO Session 5 - Project ScheduleLAFS PREPRO Session 5 - Project Schedule
LAFS PREPRO Session 5 - Project Schedule
 
Agile Project Management with Scrum (Jack Davis)
Agile Project Management with Scrum (Jack Davis)Agile Project Management with Scrum (Jack Davis)
Agile Project Management with Scrum (Jack Davis)
 

More from Michael M Grant

Level up! Integrating Games and Gamification to Support Teaching & Learning
Level up! Integrating Games and Gamification to Support Teaching & LearningLevel up! Integrating Games and Gamification to Support Teaching & Learning
Level up! Integrating Games and Gamification to Support Teaching & Learning
Michael M Grant
 
Engaging students with inquiry: Project-based learning and problem-based lear...
Engaging students with inquiry: Project-based learning and problem-based lear...Engaging students with inquiry: Project-based learning and problem-based lear...
Engaging students with inquiry: Project-based learning and problem-based lear...
Michael M Grant
 
Level Up! Games & Gamification for Teaching and Learning
Level Up! Games & Gamification for Teaching and LearningLevel Up! Games & Gamification for Teaching and Learning
Level Up! Games & Gamification for Teaching and Learning
Michael M Grant
 
Arrogance or Apathy: The Need for Formative Evaluation + Current & Emerging S...
Arrogance or Apathy: The Need for Formative Evaluation + Current & Emerging S...Arrogance or Apathy: The Need for Formative Evaluation + Current & Emerging S...
Arrogance or Apathy: The Need for Formative Evaluation + Current & Emerging S...
Michael M Grant
 
Tried & Tested More Grounded Pedagogies for Online & Blended Courses
Tried & TestedMore Grounded Pedagogies for Online & Blended CoursesTried & TestedMore Grounded Pedagogies for Online & Blended Courses
Tried & Tested More Grounded Pedagogies for Online & Blended Courses
Michael M Grant
 
Sound Pedagogies Online in Blended, Synchronous & Asynchronous Courses
Sound Pedagogies Online in Blended, Synchronous & Asynchronous Courses Sound Pedagogies Online in Blended, Synchronous & Asynchronous Courses
Sound Pedagogies Online in Blended, Synchronous & Asynchronous Courses
Michael M Grant
 
Classroom Slide Templates
Classroom Slide TemplatesClassroom Slide Templates
Classroom Slide TemplatesMichael M Grant
 
Using Mobile Devices & Apps to Drive Engagement
Using Mobile Devices & Apps to Drive EngagementUsing Mobile Devices & Apps to Drive Engagement
Using Mobile Devices & Apps to Drive Engagement
Michael M Grant
 
Information Session: Submitting a proposal to the Research & Theory Division
Information Session: Submitting a proposal to the Research & Theory DivisionInformation Session: Submitting a proposal to the Research & Theory Division
Information Session: Submitting a proposal to the Research & Theory DivisionMichael M Grant
 
You gotta see this! QR codes & augmented reality
You gotta see this! QR codes & augmented realityYou gotta see this! QR codes & augmented reality
You gotta see this! QR codes & augmented reality
Michael M Grant
 
Engaging Students On ground & Online
Engaging Students On ground & OnlineEngaging Students On ground & Online
Engaging Students On ground & Online
Michael M Grant
 
Engaging Students with Inquiry
Engaging Students with InquiryEngaging Students with Inquiry
Engaging Students with Inquiry
Michael M Grant
 
Learning on the move: Considerations for formal, informal, and semiformal lea...
Learning on the move: Considerations for formal, informal, and semiformal lea...Learning on the move: Considerations for formal, informal, and semiformal lea...
Learning on the move: Considerations for formal, informal, and semiformal lea...
Michael M Grant
 
How are schools using technology? A survey of the landscape & emerging practices
How are schools using technology? A survey of the landscape & emerging practicesHow are schools using technology? A survey of the landscape & emerging practices
How are schools using technology? A survey of the landscape & emerging practices
Michael M Grant
 
Panel on Mobile Computing Devices and Applications for Teaching & Learning
Panel on Mobile Computing Devices and Applications for Teaching & LearningPanel on Mobile Computing Devices and Applications for Teaching & Learning
Panel on Mobile Computing Devices and Applications for Teaching & Learning
Michael M Grant
 
Secrets of PBL for STEM
Secrets of PBL for STEMSecrets of PBL for STEM
Secrets of PBL for STEM
Michael M Grant
 
It's a phone! It's a computer! No, it's mobile learning!
It's a phone! It's a computer! No, it's mobile learning!It's a phone! It's a computer! No, it's mobile learning!
It's a phone! It's a computer! No, it's mobile learning!Michael M Grant
 
FREEways to Making Teaching & Learning Mobile
FREEways to Making Teaching & Learning MobileFREEways to Making Teaching & Learning Mobile
FREEways to Making Teaching & Learning MobileMichael M Grant
 
How Are Schools Doing Mobile?
How Are Schools Doing Mobile?How Are Schools Doing Mobile?
How Are Schools Doing Mobile?Michael M Grant
 

More from Michael M Grant (20)

Level up! Integrating Games and Gamification to Support Teaching & Learning
Level up! Integrating Games and Gamification to Support Teaching & LearningLevel up! Integrating Games and Gamification to Support Teaching & Learning
Level up! Integrating Games and Gamification to Support Teaching & Learning
 
Engaging students with inquiry: Project-based learning and problem-based lear...
Engaging students with inquiry: Project-based learning and problem-based lear...Engaging students with inquiry: Project-based learning and problem-based lear...
Engaging students with inquiry: Project-based learning and problem-based lear...
 
Level Up! Games & Gamification for Teaching and Learning
Level Up! Games & Gamification for Teaching and LearningLevel Up! Games & Gamification for Teaching and Learning
Level Up! Games & Gamification for Teaching and Learning
 
Arrogance or Apathy: The Need for Formative Evaluation + Current & Emerging S...
Arrogance or Apathy: The Need for Formative Evaluation + Current & Emerging S...Arrogance or Apathy: The Need for Formative Evaluation + Current & Emerging S...
Arrogance or Apathy: The Need for Formative Evaluation + Current & Emerging S...
 
Tried & Tested More Grounded Pedagogies for Online & Blended Courses
Tried & TestedMore Grounded Pedagogies for Online & Blended CoursesTried & TestedMore Grounded Pedagogies for Online & Blended Courses
Tried & Tested More Grounded Pedagogies for Online & Blended Courses
 
Sound Pedagogies Online in Blended, Synchronous & Asynchronous Courses
Sound Pedagogies Online in Blended, Synchronous & Asynchronous Courses Sound Pedagogies Online in Blended, Synchronous & Asynchronous Courses
Sound Pedagogies Online in Blended, Synchronous & Asynchronous Courses
 
Classroom Slide Templates
Classroom Slide TemplatesClassroom Slide Templates
Classroom Slide Templates
 
Using Mobile Devices & Apps to Drive Engagement
Using Mobile Devices & Apps to Drive EngagementUsing Mobile Devices & Apps to Drive Engagement
Using Mobile Devices & Apps to Drive Engagement
 
Information Session: Submitting a proposal to the Research & Theory Division
Information Session: Submitting a proposal to the Research & Theory DivisionInformation Session: Submitting a proposal to the Research & Theory Division
Information Session: Submitting a proposal to the Research & Theory Division
 
You gotta see this! QR codes & augmented reality
You gotta see this! QR codes & augmented realityYou gotta see this! QR codes & augmented reality
You gotta see this! QR codes & augmented reality
 
Engaging Students On ground & Online
Engaging Students On ground & OnlineEngaging Students On ground & Online
Engaging Students On ground & Online
 
Engaging Students with Inquiry
Engaging Students with InquiryEngaging Students with Inquiry
Engaging Students with Inquiry
 
Learning on the move: Considerations for formal, informal, and semiformal lea...
Learning on the move: Considerations for formal, informal, and semiformal lea...Learning on the move: Considerations for formal, informal, and semiformal lea...
Learning on the move: Considerations for formal, informal, and semiformal lea...
 
How are schools using technology? A survey of the landscape & emerging practices
How are schools using technology? A survey of the landscape & emerging practicesHow are schools using technology? A survey of the landscape & emerging practices
How are schools using technology? A survey of the landscape & emerging practices
 
Panel on Mobile Computing Devices and Applications for Teaching & Learning
Panel on Mobile Computing Devices and Applications for Teaching & LearningPanel on Mobile Computing Devices and Applications for Teaching & Learning
Panel on Mobile Computing Devices and Applications for Teaching & Learning
 
Secrets of PBL for STEM
Secrets of PBL for STEMSecrets of PBL for STEM
Secrets of PBL for STEM
 
QR codes are qrazy
QR codes are qrazyQR codes are qrazy
QR codes are qrazy
 
It's a phone! It's a computer! No, it's mobile learning!
It's a phone! It's a computer! No, it's mobile learning!It's a phone! It's a computer! No, it's mobile learning!
It's a phone! It's a computer! No, it's mobile learning!
 
FREEways to Making Teaching & Learning Mobile
FREEways to Making Teaching & Learning MobileFREEways to Making Teaching & Learning Mobile
FREEways to Making Teaching & Learning Mobile
 
How Are Schools Doing Mobile?
How Are Schools Doing Mobile?How Are Schools Doing Mobile?
How Are Schools Doing Mobile?
 

Recently uploaded

Unit 2- Research Aptitude (UGC NET Paper I).pdf
Unit 2- Research Aptitude (UGC NET Paper I).pdfUnit 2- Research Aptitude (UGC NET Paper I).pdf
Unit 2- Research Aptitude (UGC NET Paper I).pdf
Thiyagu K
 
Additional Benefits for Employee Website.pdf
Additional Benefits for Employee Website.pdfAdditional Benefits for Employee Website.pdf
Additional Benefits for Employee Website.pdf
joachimlavalley1
 
Polish students' mobility in the Czech Republic
Polish students' mobility in the Czech RepublicPolish students' mobility in the Czech Republic
Polish students' mobility in the Czech Republic
Anna Sz.
 
Palestine last event orientationfvgnh .pptx
Palestine last event orientationfvgnh .pptxPalestine last event orientationfvgnh .pptx
Palestine last event orientationfvgnh .pptx
RaedMohamed3
 
Sectors of the Indian Economy - Class 10 Study Notes pdf
Sectors of the Indian Economy - Class 10 Study Notes pdfSectors of the Indian Economy - Class 10 Study Notes pdf
Sectors of the Indian Economy - Class 10 Study Notes pdf
Vivekanand Anglo Vedic Academy
 
1.4 modern child centered education - mahatma gandhi-2.pptx
1.4 modern child centered education - mahatma gandhi-2.pptx1.4 modern child centered education - mahatma gandhi-2.pptx
1.4 modern child centered education - mahatma gandhi-2.pptx
JosvitaDsouza2
 
Chapter 3 - Islamic Banking Products and Services.pptx
Chapter 3 - Islamic Banking Products and Services.pptxChapter 3 - Islamic Banking Products and Services.pptx
Chapter 3 - Islamic Banking Products and Services.pptx
Mohd Adib Abd Muin, Senior Lecturer at Universiti Utara Malaysia
 
Synthetic Fiber Construction in lab .pptx
Synthetic Fiber Construction in lab .pptxSynthetic Fiber Construction in lab .pptx
Synthetic Fiber Construction in lab .pptx
Pavel ( NSTU)
 
Template Jadual Bertugas Kelas (Boleh Edit)
Template Jadual Bertugas Kelas (Boleh Edit)Template Jadual Bertugas Kelas (Boleh Edit)
Template Jadual Bertugas Kelas (Boleh Edit)
rosedainty
 
Overview on Edible Vaccine: Pros & Cons with Mechanism
Overview on Edible Vaccine: Pros & Cons with MechanismOverview on Edible Vaccine: Pros & Cons with Mechanism
Overview on Edible Vaccine: Pros & Cons with Mechanism
DeeptiGupta154
 
Cambridge International AS A Level Biology Coursebook - EBook (MaryFosbery J...
Cambridge International AS  A Level Biology Coursebook - EBook (MaryFosbery J...Cambridge International AS  A Level Biology Coursebook - EBook (MaryFosbery J...
Cambridge International AS A Level Biology Coursebook - EBook (MaryFosbery J...
AzmatAli747758
 
The Roman Empire A Historical Colossus.pdf
The Roman Empire A Historical Colossus.pdfThe Roman Empire A Historical Colossus.pdf
The Roman Empire A Historical Colossus.pdf
kaushalkr1407
 
ESC Beyond Borders _From EU to You_ InfoPack general.pdf
ESC Beyond Borders _From EU to You_ InfoPack general.pdfESC Beyond Borders _From EU to You_ InfoPack general.pdf
ESC Beyond Borders _From EU to You_ InfoPack general.pdf
Fundacja Rozwoju Społeczeństwa Przedsiębiorczego
 
GIÁO ÁN DẠY THÊM (KẾ HOẠCH BÀI BUỔI 2) - TIẾNG ANH 8 GLOBAL SUCCESS (2 CỘT) N...
GIÁO ÁN DẠY THÊM (KẾ HOẠCH BÀI BUỔI 2) - TIẾNG ANH 8 GLOBAL SUCCESS (2 CỘT) N...GIÁO ÁN DẠY THÊM (KẾ HOẠCH BÀI BUỔI 2) - TIẾNG ANH 8 GLOBAL SUCCESS (2 CỘT) N...
GIÁO ÁN DẠY THÊM (KẾ HOẠCH BÀI BUỔI 2) - TIẾNG ANH 8 GLOBAL SUCCESS (2 CỘT) N...
Nguyen Thanh Tu Collection
 
TESDA TM1 REVIEWER FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...
TESDA TM1 REVIEWER  FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...TESDA TM1 REVIEWER  FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...
TESDA TM1 REVIEWER FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...
EugeneSaldivar
 
Unit 8 - Information and Communication Technology (Paper I).pdf
Unit 8 - Information and Communication Technology (Paper I).pdfUnit 8 - Information and Communication Technology (Paper I).pdf
Unit 8 - Information and Communication Technology (Paper I).pdf
Thiyagu K
 
MARUTI SUZUKI- A Successful Joint Venture in India.pptx
MARUTI SUZUKI- A Successful Joint Venture in India.pptxMARUTI SUZUKI- A Successful Joint Venture in India.pptx
MARUTI SUZUKI- A Successful Joint Venture in India.pptx
bennyroshan06
 
Mule 4.6 & Java 17 Upgrade | MuleSoft Mysore Meetup #46
Mule 4.6 & Java 17 Upgrade | MuleSoft Mysore Meetup #46Mule 4.6 & Java 17 Upgrade | MuleSoft Mysore Meetup #46
Mule 4.6 & Java 17 Upgrade | MuleSoft Mysore Meetup #46
MysoreMuleSoftMeetup
 
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
siemaillard
 
Students, digital devices and success - Andreas Schleicher - 27 May 2024..pptx
Students, digital devices and success - Andreas Schleicher - 27 May 2024..pptxStudents, digital devices and success - Andreas Schleicher - 27 May 2024..pptx
Students, digital devices and success - Andreas Schleicher - 27 May 2024..pptx
EduSkills OECD
 

Recently uploaded (20)

Unit 2- Research Aptitude (UGC NET Paper I).pdf
Unit 2- Research Aptitude (UGC NET Paper I).pdfUnit 2- Research Aptitude (UGC NET Paper I).pdf
Unit 2- Research Aptitude (UGC NET Paper I).pdf
 
Additional Benefits for Employee Website.pdf
Additional Benefits for Employee Website.pdfAdditional Benefits for Employee Website.pdf
Additional Benefits for Employee Website.pdf
 
Polish students' mobility in the Czech Republic
Polish students' mobility in the Czech RepublicPolish students' mobility in the Czech Republic
Polish students' mobility in the Czech Republic
 
Palestine last event orientationfvgnh .pptx
Palestine last event orientationfvgnh .pptxPalestine last event orientationfvgnh .pptx
Palestine last event orientationfvgnh .pptx
 
Sectors of the Indian Economy - Class 10 Study Notes pdf
Sectors of the Indian Economy - Class 10 Study Notes pdfSectors of the Indian Economy - Class 10 Study Notes pdf
Sectors of the Indian Economy - Class 10 Study Notes pdf
 
1.4 modern child centered education - mahatma gandhi-2.pptx
1.4 modern child centered education - mahatma gandhi-2.pptx1.4 modern child centered education - mahatma gandhi-2.pptx
1.4 modern child centered education - mahatma gandhi-2.pptx
 
Chapter 3 - Islamic Banking Products and Services.pptx
Chapter 3 - Islamic Banking Products and Services.pptxChapter 3 - Islamic Banking Products and Services.pptx
Chapter 3 - Islamic Banking Products and Services.pptx
 
Synthetic Fiber Construction in lab .pptx
Synthetic Fiber Construction in lab .pptxSynthetic Fiber Construction in lab .pptx
Synthetic Fiber Construction in lab .pptx
 
Template Jadual Bertugas Kelas (Boleh Edit)
Template Jadual Bertugas Kelas (Boleh Edit)Template Jadual Bertugas Kelas (Boleh Edit)
Template Jadual Bertugas Kelas (Boleh Edit)
 
Overview on Edible Vaccine: Pros & Cons with Mechanism
Overview on Edible Vaccine: Pros & Cons with MechanismOverview on Edible Vaccine: Pros & Cons with Mechanism
Overview on Edible Vaccine: Pros & Cons with Mechanism
 
Cambridge International AS A Level Biology Coursebook - EBook (MaryFosbery J...
Cambridge International AS  A Level Biology Coursebook - EBook (MaryFosbery J...Cambridge International AS  A Level Biology Coursebook - EBook (MaryFosbery J...
Cambridge International AS A Level Biology Coursebook - EBook (MaryFosbery J...
 
The Roman Empire A Historical Colossus.pdf
The Roman Empire A Historical Colossus.pdfThe Roman Empire A Historical Colossus.pdf
The Roman Empire A Historical Colossus.pdf
 
ESC Beyond Borders _From EU to You_ InfoPack general.pdf
ESC Beyond Borders _From EU to You_ InfoPack general.pdfESC Beyond Borders _From EU to You_ InfoPack general.pdf
ESC Beyond Borders _From EU to You_ InfoPack general.pdf
 
GIÁO ÁN DẠY THÊM (KẾ HOẠCH BÀI BUỔI 2) - TIẾNG ANH 8 GLOBAL SUCCESS (2 CỘT) N...
GIÁO ÁN DẠY THÊM (KẾ HOẠCH BÀI BUỔI 2) - TIẾNG ANH 8 GLOBAL SUCCESS (2 CỘT) N...GIÁO ÁN DẠY THÊM (KẾ HOẠCH BÀI BUỔI 2) - TIẾNG ANH 8 GLOBAL SUCCESS (2 CỘT) N...
GIÁO ÁN DẠY THÊM (KẾ HOẠCH BÀI BUỔI 2) - TIẾNG ANH 8 GLOBAL SUCCESS (2 CỘT) N...
 
TESDA TM1 REVIEWER FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...
TESDA TM1 REVIEWER  FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...TESDA TM1 REVIEWER  FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...
TESDA TM1 REVIEWER FOR NATIONAL ASSESSMENT WRITTEN AND ORAL QUESTIONS WITH A...
 
Unit 8 - Information and Communication Technology (Paper I).pdf
Unit 8 - Information and Communication Technology (Paper I).pdfUnit 8 - Information and Communication Technology (Paper I).pdf
Unit 8 - Information and Communication Technology (Paper I).pdf
 
MARUTI SUZUKI- A Successful Joint Venture in India.pptx
MARUTI SUZUKI- A Successful Joint Venture in India.pptxMARUTI SUZUKI- A Successful Joint Venture in India.pptx
MARUTI SUZUKI- A Successful Joint Venture in India.pptx
 
Mule 4.6 & Java 17 Upgrade | MuleSoft Mysore Meetup #46
Mule 4.6 & Java 17 Upgrade | MuleSoft Mysore Meetup #46Mule 4.6 & Java 17 Upgrade | MuleSoft Mysore Meetup #46
Mule 4.6 & Java 17 Upgrade | MuleSoft Mysore Meetup #46
 
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
aaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaaa
 
Students, digital devices and success - Andreas Schleicher - 27 May 2024..pptx
Students, digital devices and success - Andreas Schleicher - 27 May 2024..pptxStudents, digital devices and success - Andreas Schleicher - 27 May 2024..pptx
Students, digital devices and success - Andreas Schleicher - 27 May 2024..pptx
 

WBS And Scheduling for eLearning Project Managament

  • 1. (cc) 2011 Michael M. Grant | Image from beccaxsos at Flickr.com eLearning  project  management  
  • 2. WBS   Scheduling   Gantt  Chart   Identify   Identify  and   Display  and   project  tasks   level   communicate   resources   tasks  and   scheduling  of   resources  
  • 3. ¡  Very  similar  to  task   1.  Begin  at  the  top   analysis/content   2.  Name  all  the  tasks   analysis,  particularly   3.  Organize  the  WBS   Dick,  Carey  &  Carey  
  • 4. ¡  By  top,  we  mean  a  top-­‐down  process   ¡  Begin  by  listing  all  the  deliverables   Image from Trip Deezil at Flickr.com
  • 5. ¡  This  is  all  the  tasks  and  sub-­‐tasks   ¡  Convert  each  deliverable  and  tasks  into   real   tasks   ¡  Recognize  the  summary  tasks  and  the  work   packages.   Verb  +  product  =  Task  
  • 6. ¡  Once  all  the  work   ¡  How  do  you  choose?   packages  have  been   It  depends  on  what  you   identified,  arrange   want  to  communicate.   them,  and  there  are   §  One  may  emphasize   multiple  ways  to  do   features.   that.   §  One  may  emphasize   phases  of  a  project  
  • 7. ü  The  WBS  must  be  broken  down  starting  at   the  top.   ü  Work  packages  must  add  up  to  the   summary  task.   ü  Each  task  must  be  named  as  an  activity  that   produces  a  product   Verb  +  product  =  Task  
  • 8. ¡  perform  analysis   ¡  research   ¡  database   Image from _boris at Flickr.com
  • 9. ¡  No  work  packages  should  be   smaller  than  8  hours  (1  day)   ¡  No  task  should  be  longer  than  the   time  between  2  status  points/ reporting  periods   ¡  (No  task  should  be  at  50%  for   more  than  2  status  meetings.)  
  • 10. ¡  Granularity   §  If  it s  easier  to  estimate,  break  it   down.   §  If  it s  easier  to  assign,  break  it  down.   §  If  it s  easier  to  track,  break  it  down.   ¡  If  it s  not  one  of  these,  don t   break  it  down.   ¡  Don t  forget  to  put  PM  into  the   WBS,  maybe  under   Manage   project.   Image from bcostin at Flickr.com
  • 11. ¡  Consider  quality  for  each   ¡  Types  of  quality  checks:   work  package:   §  Reviews—SME  review,   §  What  does  it  mean  to  be   design  team  review,  alpha   complete  with  this  task?   prototype,  storyboard,   §  How  do  we  know  it  was   expert  review   done  correctly/well?   §  Standards—industry   standards,  internal   checklist   §  Testing—user  testing,  beta   testing,  1-­‐on-­‐1,  small   group,  field  trial  
  • 12. A  realistic  schedule…   ¡  Includes  detailed  knowledge  of  the  work  to  be  done.   ¡  Has  tasks  sequenced  in  the  correct  order.   ¡  Accounts  for  external  constraints.   ¡  Can  be  accomplished  on  time,  given  the  availability   of  skilled  people  &  enough  equipment.  
  • 13. Step  3   Step  1   Step  2   Identify  task   Estimate   Assign  &   relationships   durations  for   level   tasks   resources  
  • 14. ¡  Sequence  constraints—when  one  task/work  package   must  be  performed  before  another  because  of   dependency   ¡  Indicate  the  predecessors  for  each  activity   Activity   Description   Duration   Immediate   Predecessors   1.1   Analyze  learners   -­‐-­‐   1.2   Analyze  context   1.1   2.1   Define  performance  gap   1.1,  1.2  
  • 15. ¡  Display  your  thinking  with  a  network  diagram   Image from http://press.teleinteractive.net/yackity/2005/10/06/critical_path_in_schedule_management
  • 16. ¡  Network  diagram   ¡  Relationships   §  Finish  to  start   Task B cannot begin until Task A is finished. Image from Microsoft at http://office.microsoft.com/en-us/project/HA101130671033.aspx
  • 17. ¡  Network  diagrams   help  present   relationships  among   tasks   Task B cannot begin until Task A begins. §  Finish  to  start   §  Start  to  start   Image from Microsoft at http://office.microsoft.com/en-us/project/HA101130671033.aspx
  • 18. ¡  Network  diagram   ¡  Relationships   §  Finish  to  start   §  Start  to  start   Task B cannot finish until Task A finishes. §  Finish  to  finish   Image from Microsoft at http://office.microsoft.com/en-us/project/HA101130671033.aspx
  • 19. Activity   Description   Duration   Immediate   (in  days)   Predecessors   1.1   Analyze  learners   14   -­‐-­‐   1.2   Analyze  context   14   1.1   2.1   Define  performance  gap   2   1.1,  1.2   Image from http://press.teleinteractive.net/yackity/2005/10/06/critical_path_in_schedule_management
  • 20. ¡  Identify  resources  (i.e.,   ¡  Labor:  in  hours   labor,  equipment,   ¡  Equipment:  in  hours   materials)   ¡  Materials:  amount,   ¡  Determine  when  each   when  needed  (task   resource  is  needed  and   relationship)   for  how  long.   Image from Truthout at Flickr.com
  • 21. ¡  Assign  resources,  primarily  labor  and   equipment  to  tasks   ¡  Determine  resources  for  each  day  and   compare  schedule   ¡  Some  tasks  may  not  be  completed   concurrently  because  of  resource  pool  or   additional  resources  may  be  needed  
  • 22. ¡  Critical  path   §  The  critical  path  is  the  longest  path  through  the  network,   but  represents  the  minimum  amount  of  time  a  project  will   take.   Image from http://press.teleinteractive.net/yackity/2005/10/06/critical_path_in_schedule_management
  • 23. ¡  Gantt   §  Henry  Gantt,  early  1900s   §  Horizontal  axis  shows   schedule,  vertical  axis   shows  WBS   Image from http://commons.wikimedia.org/wiki/File:Henri_Gannt.jpg
  • 24. Image from Gary Booker at http://commons.wikimedia.org/wiki/File:GanttChartAnatomy.png
  • 25. ¡  Booker,  G.  (2007).  Ganttchartanatomy.png  [image].  Retrieved  January  27,  2010   from  http://commons.wikimedia.org/wiki/File:GanttChartAnatomy.png   ¡  dmdk12.  (2007).  Development  of  the  network  diagram  and  critical  path.   Retrieved  January  27,  2010  from  http://www.slideshare.net/dmdk12/the-­‐network-­‐ diagram-­‐and-­‐critical-­‐path   ¡  Doval  Santos,  C.V.  (2005).  Critical  path  in  schedule  management  [image].   Retrieved  January  27,  2010  from  http://press.teleinteractive.net/yackity/ 2005/10/06/critical_path_in_schedule_management   ¡  Lynch,  M.M.  &  Roecker,  J.  (2007).  Project  managing  e-­‐learning:  A  handbook  for   successful  design,  delivery  and  management.  New  York:  Routledge.   ¡  Schwalbe,  K.  (2010).  Information  technology  project  management  (6th  ed.).   Boston,  MA:  Cengage  Course  Technology.   ¡  Verzuh,  E.  (2008).  The  fast  forward  MBA  in  project  management  (3rd  ed.).   Hoboken,  NJ:  Wiley.  
  • 26. (cc) 2011 Michael M. Grant