SlideShare a Scribd company logo
Dr Mohamed Elfarran
Project Management
Day (5)
Dr Mohamed Elfarran
Course Outline
Day 1: Introduction + Project Integration Management.
Day 2: Project Scope Management.
Day 3: Project Schedule Management.
Day 4: Project Cost Management.
Day 5: Project Risk Management.
Day 6: Scrum.
Day 7: Final Presentation Day!
Dr Mohamed Elfarran
Project Risk Management
Rev.221102
3
Dr Mohamed Elfarran
The Importance of Project Risk Management
Project risk management is the art and science of identifying, analyzing, and
responding to risk throughout the life of a project and in the best interests of
meeting project objectives
5
Information
Technology
Dr Mohamed Elfarran
Project Risk Management
Project Risk Management includes the process of conducting risk management plan,
identification, analysis, response planning, response implementation, and monitoring
risk on the project. The objectives of project risk management:
○ Increase the probability and/or impact of positive (opportunities) risks and
decrease the probability and/or impact of negative risks (threats), in order
to optimize the chance of Project success.
6
Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) –
Sixth Edition, Project Management Institute, Inc., 2017, Page 395.
Dr Mohamed Elfarran
Project Risk Management
7
Dr Mohamed Elfarran
Integrating Risk with other project management functions
8
Project Risk
Scope
Communication
Time Procurement
Quality
Recourses
Cost
Integration
Life cycle
Enviro. Variables
Cost
Objectives
Availability
Productivity
Requirements
Standards
Time
Objectives
Services
Performance
Expectation Data
Exchange
Accuracy
Dr Mohamed Elfarran
Risk
● An uncertain event or condition that, if it occurs, has a Positive or
Negative effect on a project objective.
○ The severity of any risk can be defined in terms of two quantities:
■ Likelihood: The extent to which the risk effects are likely to
occur.
■ Impact (Consequence): The effect that a risk will have on
the project if it occurs.
9
Dr Mohamed Elfarran
Risk Types
10
Dr Mohamed Elfarran
Risk Levels
Risk exists at two levels within every project.
Each project contains individual risks that can affect the achievement of
project objectives.
It is also important to consider the riskiness of the overall project, which arises
from the combination of individual project risks and other sources of
uncertainty.
○ Individual Project Risk
○ Overall Project Risk
11
Dr Mohamed Elfarran
Risk Levels
● Individual Project Risk
○ Is an uncertain event or condition that, if it occurs, has a Positive or
Negative effect on one or more a project objective.
● Overall Project Risk
○ Is the effect of uncertainty on the project as a whole, arising from all
sources of uncertainty including individual risks, representing the
exposure of stakeholders to the implications of variations in project
outcome, both positive and negative.
12
Dr Mohamed Elfarran
Negative Risk
● A dictionary definition of risk is “the possibility of loss or
injury”
● Negative risk involves understanding potential problems
that might occur in the project and how they might impede
project success
13
Information
Technology
Negative risk Positive risk
Dr Mohamed Elfarran
Risk Can Be Positive
● Positive risks are risks that result in good things
happening; sometimes called opportunities
● A general definition of project risk is an uncertainty that
can have a negative or positive effect on meeting project
objectives
● The goal of project risk management is to minimize
potential negative risks while maximizing potential
positive risks
14
Information
Technology
Dr Mohamed Elfarran
Trends and emerging practices
● Project resilience (Flexibility)
○ Right level of budget and schedule contingency
○ Flexible project process
○ Empowered project team that has clear objective
○ Frequent review of early warning sign
○ Clear input from stakeholders
○ Integrated risk management
○ Program and portfolio
15
Dr Mohamed Elfarran
Plan Risk Management
Rev.221102
16
Dr Mohamed Elfarran 17
Rev.221102
Dr Mohamed Elfarran
Plan Risk Management
Plan Risk Management
is the process of defining how to conduct risk management
activities for the project.
The key benefit of this process is that it ensures that the degree, type, and
visibility of risk management are proportionate to both risks and the
importance of the project to the organization and other stakeholders.
18
Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) –
Sixth Edition, Project Management Institute, Inc., 2017, Page 401.
Dr Mohamed Elfarran
Plan Risk Management, Outputs
● Risk Management Plan
Describes how risk management activities will be structured and
performed, and it may include the following elements:
■ Risk strategy
Describes the general approached to mange the risk
■ Methodology
Defines the specific approaches, tools, and data sources that will be
used to perform risk management on the project. 19
Dr Mohamed Elfarran
Plan Risk Management, Outputs
■ Roles & Responsibilities
Defines the lead, support, and risk management team member for
each type of activities described in the risk management plan, and
clarifies their responsibility.
■ Funding
Identifies the funds needed to perform activities related to the project
risk management. Establishes protocols for the application of
contingency and management reserves. 20
Dr Mohamed Elfarran
Plan Risk Management, Outputs
■ Timing
Defines when and how often the risk management process will be
performed throughout the project life cycle
■ Risk categories
Provides a means for grouping individual project risk. A common way to
structure risk categories is a risk breakdown structure (RBS)
21
Dr Mohamed Elfarran
Plan Risk Management, Outputs
◼ Risk categories
Risks that may affect the project for better or worse can be identified and
organized into categories
22
Macro
Financial
Political
Market
Environment Target
Managerial
Project
Job Site
Procurement
Design
Act of God
Social
Technical
Funding
Control
Team
Contractual
Dr Mohamed Elfarran
Identify Risk
Rev.221102
23
Dr Mohamed Elfarran
Identify Risk
Identify Risk Is The Process of identifying individual project risks as well
as sources of overall project risk, and documenting their characteristics.
The key benefit of this process is the documentation of existing individual
project risks and the sources of overall project risk. It also bring
information so the project team can appropriately to identified risk.
24
Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) –
Sixth Edition, Project Management Institute, Inc., 2017, Page 409.
Dr Mohamed Elfarran
Identify Risk
● Risk is doing business
25
External
Environment
project
Organization
Environment Significant
Factors
Location
of the
site Client Wars
Dr Mohamed Elfarran
Identify Risk, Tools & Tech
● Brainstorming is a technique by which a group attempts to generate ideas or
find a solution for a specific problem by amassing ideas spontaneously and
without judgment
● An experienced facilitator should run the brainstorming session
● Be careful not to overuse or misuse brainstorming.
○ Psychology literature shows that individuals produce a greater number of ideas working alone
than they do through brainstorming in small, face-to-face groups
○ Group effects often inhibit idea generation
26
Information
Technology
Dr Mohamed Elfarran
Risk Breakdown Structure
● A risk breakdown structure is a hierarchy of potential risk categories for a
project
● Similar to a work breakdown structure but used to identify and categorize
risks
27
Dr Mohamed Elfarran
Figure 11-4. Sample Risk Breakdown Structure
28
Information Technology Project Management, Sixth Edition
Dr Mohamed Elfarran
Figure 11-4. Sample Risk Breakdown Structure
29
Information Technology Project Management, Sixth Edition
Dr Mohamed Elfarran
Table 11-4. Potential Negative Risk Conditions Associated with Each Knowledge
Area
30
Dr Mohamed Elfarran
Identify Risk, Tools & Tech.
SWOT Analysis
○ This technique examines the project from each of the strengths,
weaknesses, opportunities, and threats.
31
Dr Mohamed Elfarran
Identify Risk, Tools & Tech.
● Delphi Technique
○ The Delphi Technique is used to derive a consensus among a panel of experts who make
predictions about future developments
○ Provides independent and anonymous input regarding future events
○ Uses repeated rounds of questioning and written responses and avoids the biasing effects
possible in oral methods, such as brainstorming
32
Dr Mohamed Elfarran
Identify Risk, Tools & Tech.
● Prompt Risk
○ A prompt risk is a predetermined list of risk that might give rise
to individual risk and that could also act as sources of overall risk.
The risk categories in the lowest level of the risk breakdown
structure can be used as a prompt list for individual project risk.
● Meetings
○ Often call a risk workshop
33
Dr Mohamed Elfarran
Identify Risk, Output
34
● The main output of the risk identification process is a list of identified
risks and other information needed to begin creating a risk register
● A risk register is:
○ A document that contains the results of various risk management processes
and that is often displayed in a table or spreadsheet format
○ A tool for documenting potential risk events and related information
● Risk events refer to specific, uncertain events that may occur to the
detriment or enhancement of the project
Dr Mohamed Elfarran
Risk Register Contents
● An identification number for each risk event
● A rank for each risk event
● The name of each risk event
● A description of each risk event
● The category under which each risk event falls
● The root cause of each risk
● Triggers for each risk; triggers are indicators or symptoms of actual risk events
● Potential responses to each risk
● The risk owner or person who will own or take responsibility for each risk
● The probability and impact of each risk occurring.
● The status of each risk
35
Information
Technology
Dr Mohamed Elfarran
Table 11-5. Sample Risk Register
36
Information Technology Project Management, Seventh Edition
• No.: R44
• Rank: 1
• Risk: New customer
• Description: We have never done a project for this organization
before and don’t know too much about them. One of our company’s
strengths is building good customer relationships, which often leads
to further projects with that customer. We might have trouble working
with this customer because they are new to us.
• Category: People risk
• Etc.
Dr Mohamed Elfarran
Identify Risk, Output
37
Dr Mohamed Elfarran
● Risk Breakdown
Structure
● Build Your Risk
Registers
38
Dr Mohamed Elfarran
Dr Mohamed Elfarran
Risk Analysis
Rev.221102
39
Dr Mohamed Elfarran
Perform Qualitative Risk Analysis
Perform Qualitative Risk Analysis Is the process of prioritizing
individual project risk for further analysis or actions by assessing the
probability of occurrence and impact and as well as other characteristics.
The key benefit of this process is that it focuses efforts on high priority
risks.
40
Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) –
Sixth Edition, Project Management Institute, Inc., 2017, Page 419.
Dr Mohamed Elfarran
Plotting Risk Events on the Matrix
Risk Probability
Risk Impact
L M H
L
H
M
Dr Mohamed Elfarran
Output
● Top Ten Risk Item Tracking is a qualitative risk analysis tool that helps to
identify risks and maintain an awareness of risks throughout the life of a
project
● Establish a periodic review of the top ten project risk items
● List the current ranking, previous ranking, number of times the risk appears
on the list over a period of time, and a summary of progress made in
resolving the risk item
42
Information
Technology
Dr Mohamed Elfarran
Table 11-6. Example of Top Ten Risk Item Tracking
43
Information
Technology
Dr Mohamed Elfarran
Output
● A watch list is a list of risks that are low priority, but are still identified as
potential risks
● Qualitative analysis can also identify risks that should be evaluated on a
quantitative basis
44
Information
Technology
Dr Mohamed Elfarran
Perform Quantitative Risk Analysis
Perform Quantitative Risk Analysis is the process of numerically
analyzing the combined effect of identified individual project risks and
other sources of uncertainty on overall project objective. The key benefit
of this process is that it quantifies overall project risk exposure, and it can
also provide additional quantitative risk information to support risk
response planning.
45
Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) –
Sixth Edition, Project Management Institute, Inc., 2017, Page 428.
Dr Mohamed Elfarran
Perform Quantitative Risk Analysis
This Process used technique such as Monte Carlo Simulation and Decision
Tree Analysis to:
○ Quantify the possible outcomes for the project and their probabilities.
○ Assess the probability of achieving specific project objectives.
○ Identify risks requiring the most attention by quantifying their relative
contribution to overall project risk.
○ Identify realistic and achievable cost, schedule or scope targets, given
the project risks.
○ Determine the best project management decision when some
conditions or outcomes are uncertain.
46
Dr Mohamed Elfarran
Quantitative Risk Analysis
 Probability and Impact Matrix
47
Dr Mohamed Elfarran
Quantitative Risk Analysis
 Probability and Impact Matrix
48
Dr Mohamed Elfarran
Perform Quantitative Risk Analysis, Tools & Tech.
● Decision Tree Analysis
49
Dr Mohamed Elfarran
Perform Quantitative Risk Analysis, Tools & Tech.
● Expected Monetary Value (EMV)
● Expected Payoff for good market = 80,000*0.15 + 50,000*0.45 = LE 34,500
● Expected Payoff for good quality = 80,000*0.15 + 20,000*0.25 = LE 17,000
● EMV = 80,000*0.15 + 50,000*0.45 +20,000*0.25 + (-20,000)*0.15 = LE 36,500
50
Probability %
Payoff
Status
15
80,000
Good Market – Good Quality
45
50,000
Good Market – Poor Quality
25
20,000
Poor Market – Good Quality
15
-20,000
Poor Market – Poor Quality
Dr Mohamed Elfarran
Perform Quantitative Risk Analysis, Tools & Tech.
● Simulation uses a representation or model of a system to analyze the
expected behavior or performance of the system
● Monte Carlo analysis simulates a model’s outcome many times to provide a
statistical distribution of the calculated results
● To use a Monte Carlo simulation, you must have three estimates (most likely,
pessimistic, and optimistic) plus an estimate of the likelihood of the estimate
being between the most likely and optimistic values
51
Information
Technology
Dr Mohamed Elfarran
Perform Quantitative Risk Analysis
Monte Carlo Simulation
52
Dr Mohamed Elfarran
Perform Quantitative Risk Analysis, Tools & Tech.
● Sensitivity analysis is a technique used to show the effects of changing one
or more variables on an outcome
● For example, many people use it to determine what the monthly payments for
a loan will be given different interest rates or periods of the loan, or for
determining break-even points based on different assumptions
● Spreadsheet software, such as Excel, is a common tool for performing
sensitivity analysis
53
Information
Technology
Dr Mohamed Elfarran
Perform Quantitative Risk Analysis, Tools & Tech.
● Sensitivity Analysis
■ Helps to determine which individual project risks or other
sources of uncertainty have the most potential impact on the
project outcomes
■ Involve making all risk variables at their baseline and study
impact on the project objectives when on variable is changed
54
Dr Mohamed Elfarran
Perform Quantitative Risk Analysis, Tools & Tech.
● Sensitivity Analysis
55
Dr Mohamed Elfarran
● Qualitative Risk
Analysis
● Quantitative Risk
Analysis
56
Dr Mohamed Elfarran
Dr Mohamed Elfarran
Plan Risk Responses
57
Rev.221102
Dr Mohamed Elfarran
Plan Risk Responses
The process of developing options selecting strategies, and agreeing on
actions to address overall project risk exposure, as well as to treat
individual project risk. The key benefit of this process is that it identifies
appropriate way to address overall project risk and individual project risk.
58
Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) –
Sixth Edition, Project Management Institute, Inc., 2017, Page 437.
Dr Mohamed Elfarran
Plan Risk Responses
● Risk response should be:
○ Appropriate to the significance of the risk
○ Cost effective in meeting the challenge
○ Realistic within the project context
○ Agreed upon by all parties involved
○ Owned by a responsible person
59
Dr Mohamed Elfarran
Plan Risk Responses
60
Information
Technology
Dr Mohamed Elfarran
Plan Risk Responses, Tools & Tech.
● Strategies for Threats
○ Avoid
○ Transfer
○ Mitigate
○ Accept
○ Escalate
61
● Strategies for Opportunities
○ Exploit
○ Enhance
○ Share
○ Accept
○ Escalate
Dr Mohamed Elfarran
Plan Risk Responses, Tools & Tech.
● Strategies for Overall Project Risk
○ Avoid
○ Exploit
○ Transfer/Share
○ Mitigate/Enhance
○ Accept
62
Dr Mohamed Elfarran
Risk Response Strategies
Mitigation
(Corrective action)
Avoidance
(Prevention)
Acceptance
(Accept consequences)
Transference
(Shift Responsibility)
Dr Mohamed Elfarran
Plan Risk Responses
● Residual Risk
The risks that remain after risk responses have been implemented.
● Secondary Risk
The risks that arise as a direct result of implementing a risk response.
64
Dr Mohamed Elfarran
Implement Risk Responses
65
Rev.221102
Dr Mohamed Elfarran
Implement Risk Responses
Implement Risk Responses is the process of implementing agreed upon
risk response plans. The key benefit of this process is that it ensures that
the agreed upon risk responses are executed as planned in order to
address overall project risk exposure, minimize individual project threats,
and maximize individual project opportunities.
66
Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) –
Sixth Edition, Project Management Institute, Inc., 2017, Page 449.
Dr Mohamed Elfarran
Monitor Risk
67
Rev.221102
Dr Mohamed Elfarran
Monitor Risk
Monitor risk is the process of monitoring the implementation of agreed upon
response plan, tracking identified risks, identifying and analyzing new risks,
and evaluating risk process effectiveness throughout the project.
The key benefit of this process is that it enable project decisions to be based
on current information about overall project risk exposure and individual
project risk.
68
*This definition is taken from the Glossary of the Project Management Institute, A Guide to the Project Management
Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project Management Institute, Inc., 2017.
Dr Mohamed Elfarran
Monitor Risk
The Monitor Risk processes uses performance information generated
during project execution to determine if:
○ Implemented risk responses are effective
○ Level of overall project risk has changed
○ Status of identified individual project risk has changes
○ New individual project risk have arisen
○ Risk management approach is still appropriate
69
Dr Mohamed Elfarran
Monitor Risk
○ Project assumptions are still valid
○ Risk management policies and procedures are being followed
○ Contingency reserves for cost or schedule require modified
○ Project strategy is still valid
70
Dr Mohamed Elfarran
Risk Assessment
71
ID Event % EGP Plan % EGP Risk Value
1
2
3
4
5
‫التصاريح‬ ‫تأخر‬
‫أسبوعين‬
‫أسبوع‬ ‫التصميم‬ ‫تأخر‬
‫العمالت‬ ‫سعر‬ ‫تغير‬
‫بنسبة‬
10
%
‫ئن‬ْ‫ا‬‫الزب‬ ‫عدد‬ ‫قلة‬
‫بنسبة‬
50
%
‫في‬ ‫التيار‬ ‫انقطاع‬
‫االفتتاح‬
40
50
60
30
50
‫المتوقع‬ ‫الربح‬
70
‫األسبوع‬ ‫في‬ ‫مصرى‬ ‫جنية‬ ‫ألف‬
‫المستوردة‬ ‫التوريدات‬
10
‫دوالر‬ ‫ألف‬
10
20
60
10
140,000
70,000
1,000$
35,000
210,000
40,000
20,000
$ 1,000
15,000
4,000
4,000
600$
1,500
‫محامى‬ ‫مع‬ ‫التعاقد‬
‫التكلفة‬
5
‫جنية‬ ‫الف‬
(
‫تخفيف‬
)
‫استشاري‬ ‫مكتب‬ ‫مع‬ ‫التعاقد‬
‫التكلفة‬
10
‫جنية‬ ‫الف‬
(
‫تخفيف‬
)
‫قبول‬
‫بتكلفة‬ ‫بالدعاية‬ ‫االهتمام‬
2,000
‫جنية‬
‫بتكلفة‬ ‫كهرباء‬ ‫مولد‬ ‫تأجير‬
5,000
‫جنية‬
(
‫تفادي‬
)
Dr Mohamed Elfarran
Dr Mohamed Elfarran 73

More Related Content

Similar to Project Management Day 5 Risk R02.pdf

Software IT risk-management
Software IT risk-managementSoftware IT risk-management
Software IT risk-management
gufranresearcher
 
Project Risk
Project RiskProject Risk
Project Risk
Rohit Kumar
 
Information Technology Project Management - part 11
Information Technology Project Management - part 11Information Technology Project Management - part 11
Information Technology Project Management - part 11
Rizwan Khurram
 
Software Project Risk Management Practice in Oman
Software Project Risk Management Practice in OmanSoftware Project Risk Management Practice in Oman
Software Project Risk Management Practice in Oman
EECJOURNAL
 
المحاضرة الخامسة: إدارة المخاطر
المحاضرة الخامسة: إدارة المخاطرالمحاضرة الخامسة: إدارة المخاطر
المحاضرة الخامسة: إدارة المخاطر
Egypt Scholars Inc.
 
Pmi 19 26
Pmi 19 26Pmi 19 26
Pmi 19 26
Nawzad Bilal
 
CT1553_Slides_441_9.pptx
CT1553_Slides_441_9.pptxCT1553_Slides_441_9.pptx
CT1553_Slides_441_9.pptx
AyidAlmgati
 
Episode 25 : Project Risk Management
Episode 25 :  Project Risk ManagementEpisode 25 :  Project Risk Management
Episode 25 : Project Risk Management
SAJJAD KHUDHUR ABBAS
 
Webinar - Building Team Efficiency and Effectiveness
Webinar - Building Team Efficiency and EffectivenessWebinar - Building Team Efficiency and Effectiveness
Webinar - Building Team Efficiency and Effectiveness
Invensis Learning
 
ITPM_11.ppt
ITPM_11.pptITPM_11.ppt
ITPM_11.ppt
AhmedHusseinElmi
 
Risk Management Presentation.pptx
Risk Management Presentation.pptxRisk Management Presentation.pptx
Risk Management Presentation.pptx
PMIUKChapter
 
Project Risk Management
Project  Risk ManagementProject  Risk Management
Project Risk Management
Kelvin Fredson
 
Project risk management notes bagamoyo 12.10.2017 final v1
Project risk management  notes bagamoyo 12.10.2017 final v1Project risk management  notes bagamoyo 12.10.2017 final v1
Project risk management notes bagamoyo 12.10.2017 final v1
EMAC Consulting Group
 
MBA 6941, Managing Project Teams 1 Course Learning Ou.docx
 MBA 6941, Managing Project Teams 1 Course Learning Ou.docx MBA 6941, Managing Project Teams 1 Course Learning Ou.docx
MBA 6941, Managing Project Teams 1 Course Learning Ou.docx
aryan532920
 
Risk assesment template
Risk assesment templateRisk assesment template
Risk assesment template
Glen Alleman
 
Risk management Phase 1-5 Individual Project.docx
Risk management Phase 1-5 Individual Project.docxRisk management Phase 1-5 Individual Project.docx
Risk management Phase 1-5 Individual Project.docx
joellemurphey
 
RISK MANAGEMENT: ISSUES, CHALLENGES AND OPPORTUNITY
RISK MANAGEMENT: ISSUES, CHALLENGES AND OPPORTUNITYRISK MANAGEMENT: ISSUES, CHALLENGES AND OPPORTUNITY
RISK MANAGEMENT: ISSUES, CHALLENGES AND OPPORTUNITY
Ashim Sharma
 
Risk strategies presentation
Risk strategies presentationRisk strategies presentation
Risk strategies presentation
Raven Morgan
 
Final Class Presentation on Determining Project Stakeholders & Risks.pptx
Final Class Presentation on Determining Project Stakeholders & Risks.pptxFinal Class Presentation on Determining Project Stakeholders & Risks.pptx
Final Class Presentation on Determining Project Stakeholders & Risks.pptx
GeorgeKabongah2
 
8. project risk management
8. project risk management8. project risk management
8. project risk management
Mohamed Salah Eldien Mohamed Ali
 

Similar to Project Management Day 5 Risk R02.pdf (20)

Software IT risk-management
Software IT risk-managementSoftware IT risk-management
Software IT risk-management
 
Project Risk
Project RiskProject Risk
Project Risk
 
Information Technology Project Management - part 11
Information Technology Project Management - part 11Information Technology Project Management - part 11
Information Technology Project Management - part 11
 
Software Project Risk Management Practice in Oman
Software Project Risk Management Practice in OmanSoftware Project Risk Management Practice in Oman
Software Project Risk Management Practice in Oman
 
المحاضرة الخامسة: إدارة المخاطر
المحاضرة الخامسة: إدارة المخاطرالمحاضرة الخامسة: إدارة المخاطر
المحاضرة الخامسة: إدارة المخاطر
 
Pmi 19 26
Pmi 19 26Pmi 19 26
Pmi 19 26
 
CT1553_Slides_441_9.pptx
CT1553_Slides_441_9.pptxCT1553_Slides_441_9.pptx
CT1553_Slides_441_9.pptx
 
Episode 25 : Project Risk Management
Episode 25 :  Project Risk ManagementEpisode 25 :  Project Risk Management
Episode 25 : Project Risk Management
 
Webinar - Building Team Efficiency and Effectiveness
Webinar - Building Team Efficiency and EffectivenessWebinar - Building Team Efficiency and Effectiveness
Webinar - Building Team Efficiency and Effectiveness
 
ITPM_11.ppt
ITPM_11.pptITPM_11.ppt
ITPM_11.ppt
 
Risk Management Presentation.pptx
Risk Management Presentation.pptxRisk Management Presentation.pptx
Risk Management Presentation.pptx
 
Project Risk Management
Project  Risk ManagementProject  Risk Management
Project Risk Management
 
Project risk management notes bagamoyo 12.10.2017 final v1
Project risk management  notes bagamoyo 12.10.2017 final v1Project risk management  notes bagamoyo 12.10.2017 final v1
Project risk management notes bagamoyo 12.10.2017 final v1
 
MBA 6941, Managing Project Teams 1 Course Learning Ou.docx
 MBA 6941, Managing Project Teams 1 Course Learning Ou.docx MBA 6941, Managing Project Teams 1 Course Learning Ou.docx
MBA 6941, Managing Project Teams 1 Course Learning Ou.docx
 
Risk assesment template
Risk assesment templateRisk assesment template
Risk assesment template
 
Risk management Phase 1-5 Individual Project.docx
Risk management Phase 1-5 Individual Project.docxRisk management Phase 1-5 Individual Project.docx
Risk management Phase 1-5 Individual Project.docx
 
RISK MANAGEMENT: ISSUES, CHALLENGES AND OPPORTUNITY
RISK MANAGEMENT: ISSUES, CHALLENGES AND OPPORTUNITYRISK MANAGEMENT: ISSUES, CHALLENGES AND OPPORTUNITY
RISK MANAGEMENT: ISSUES, CHALLENGES AND OPPORTUNITY
 
Risk strategies presentation
Risk strategies presentationRisk strategies presentation
Risk strategies presentation
 
Final Class Presentation on Determining Project Stakeholders & Risks.pptx
Final Class Presentation on Determining Project Stakeholders & Risks.pptxFinal Class Presentation on Determining Project Stakeholders & Risks.pptx
Final Class Presentation on Determining Project Stakeholders & Risks.pptx
 
8. project risk management
8. project risk management8. project risk management
8. project risk management
 

More from Dr Mohamed Elfarran

SCRUM Day 1 Rev03.pdf
SCRUM Day 1 Rev03.pdfSCRUM Day 1 Rev03.pdf
SCRUM Day 1 Rev03.pdf
Dr Mohamed Elfarran
 
Project Management Day 4 Cost ٌ R02.pdf
Project Management Day 4 Cost ٌ R02.pdfProject Management Day 4 Cost ٌ R02.pdf
Project Management Day 4 Cost ٌ R02.pdf
Dr Mohamed Elfarran
 
Day 3 Schedule R02.pdf
Day 3 Schedule R02.pdfDay 3 Schedule R02.pdf
Day 3 Schedule R02.pdf
Dr Mohamed Elfarran
 
Day 1 Framework R03.pdf
Day 1 Framework R03.pdfDay 1 Framework R03.pdf
Day 1 Framework R03.pdf
Dr Mohamed Elfarran
 
Day 2 Scope R02.pdf
Day 2 Scope R02.pdfDay 2 Scope R02.pdf
Day 2 Scope R02.pdf
Dr Mohamed Elfarran
 
how to write a business plan
how to write a business planhow to write a business plan
how to write a business plan
Dr Mohamed Elfarran
 
Industry 4.0 and Cyber physical systems Intro
Industry 4.0 and Cyber physical systems IntroIndustry 4.0 and Cyber physical systems Intro
Industry 4.0 and Cyber physical systems Intro
Dr Mohamed Elfarran
 
Ace 402 lec 12 fueslage shear flow
Ace 402 lec 12 fueslage shear flowAce 402 lec 12 fueslage shear flow
Ace 402 lec 12 fueslage shear flow
Dr Mohamed Elfarran
 
Ace 402 lec 7 unsymmetrical
Ace 402 lec 7 unsymmetrical Ace 402 lec 7 unsymmetrical
Ace 402 lec 7 unsymmetrical
Dr Mohamed Elfarran
 
Ace 402 lec 8 max stress
Ace 402 lec 8 max stressAce 402 lec 8 max stress
Ace 402 lec 8 max stress
Dr Mohamed Elfarran
 
Ace 402 lec 12 fueslage shear flow2
Ace 402 lec 12 fueslage shear flow2Ace 402 lec 12 fueslage shear flow2
Ace 402 lec 12 fueslage shear flow2
Dr Mohamed Elfarran
 
Ace 402 lec 13 max stress unsymetric
Ace 402 lec 13 max stress unsymetricAce 402 lec 13 max stress unsymetric
Ace 402 lec 13 max stress unsymetric
Dr Mohamed Elfarran
 
Ace 402 lec 3 bending
Ace 402 lec 3  bendingAce 402 lec 3  bending
Ace 402 lec 3 bending
Dr Mohamed Elfarran
 
Ace 402 lec 1&2
Ace 402 lec 1&2Ace 402 lec 1&2
Ace 402 lec 1&2
Dr Mohamed Elfarran
 
Ace 402 lec 5 effective
Ace 402 lec 5 effectiveAce 402 lec 5 effective
Ace 402 lec 5 effective
Dr Mohamed Elfarran
 
Ace 402 lec 6 ultimate bending
Ace 402 lec 6 ultimate bending Ace 402 lec 6 ultimate bending
Ace 402 lec 6 ultimate bending
Dr Mohamed Elfarran
 
Ace 402 lec 4 buckling
Ace 402 lec 4 buckling Ace 402 lec 4 buckling
Ace 402 lec 4 buckling
Dr Mohamed Elfarran
 
Mpe 209 lec 9 Pressized Vessels
Mpe 209 lec 9 Pressized Vessels Mpe 209 lec 9 Pressized Vessels
Mpe 209 lec 9 Pressized Vessels
Dr Mohamed Elfarran
 
Mpe 209 lec gear Design
Mpe 209 lec gear DesignMpe 209 lec gear Design
Mpe 209 lec gear Design
Dr Mohamed Elfarran
 
Mpe 209 lec 11 springs
Mpe 209 lec 11 springs Mpe 209 lec 11 springs
Mpe 209 lec 11 springs
Dr Mohamed Elfarran
 

More from Dr Mohamed Elfarran (20)

SCRUM Day 1 Rev03.pdf
SCRUM Day 1 Rev03.pdfSCRUM Day 1 Rev03.pdf
SCRUM Day 1 Rev03.pdf
 
Project Management Day 4 Cost ٌ R02.pdf
Project Management Day 4 Cost ٌ R02.pdfProject Management Day 4 Cost ٌ R02.pdf
Project Management Day 4 Cost ٌ R02.pdf
 
Day 3 Schedule R02.pdf
Day 3 Schedule R02.pdfDay 3 Schedule R02.pdf
Day 3 Schedule R02.pdf
 
Day 1 Framework R03.pdf
Day 1 Framework R03.pdfDay 1 Framework R03.pdf
Day 1 Framework R03.pdf
 
Day 2 Scope R02.pdf
Day 2 Scope R02.pdfDay 2 Scope R02.pdf
Day 2 Scope R02.pdf
 
how to write a business plan
how to write a business planhow to write a business plan
how to write a business plan
 
Industry 4.0 and Cyber physical systems Intro
Industry 4.0 and Cyber physical systems IntroIndustry 4.0 and Cyber physical systems Intro
Industry 4.0 and Cyber physical systems Intro
 
Ace 402 lec 12 fueslage shear flow
Ace 402 lec 12 fueslage shear flowAce 402 lec 12 fueslage shear flow
Ace 402 lec 12 fueslage shear flow
 
Ace 402 lec 7 unsymmetrical
Ace 402 lec 7 unsymmetrical Ace 402 lec 7 unsymmetrical
Ace 402 lec 7 unsymmetrical
 
Ace 402 lec 8 max stress
Ace 402 lec 8 max stressAce 402 lec 8 max stress
Ace 402 lec 8 max stress
 
Ace 402 lec 12 fueslage shear flow2
Ace 402 lec 12 fueslage shear flow2Ace 402 lec 12 fueslage shear flow2
Ace 402 lec 12 fueslage shear flow2
 
Ace 402 lec 13 max stress unsymetric
Ace 402 lec 13 max stress unsymetricAce 402 lec 13 max stress unsymetric
Ace 402 lec 13 max stress unsymetric
 
Ace 402 lec 3 bending
Ace 402 lec 3  bendingAce 402 lec 3  bending
Ace 402 lec 3 bending
 
Ace 402 lec 1&2
Ace 402 lec 1&2Ace 402 lec 1&2
Ace 402 lec 1&2
 
Ace 402 lec 5 effective
Ace 402 lec 5 effectiveAce 402 lec 5 effective
Ace 402 lec 5 effective
 
Ace 402 lec 6 ultimate bending
Ace 402 lec 6 ultimate bending Ace 402 lec 6 ultimate bending
Ace 402 lec 6 ultimate bending
 
Ace 402 lec 4 buckling
Ace 402 lec 4 buckling Ace 402 lec 4 buckling
Ace 402 lec 4 buckling
 
Mpe 209 lec 9 Pressized Vessels
Mpe 209 lec 9 Pressized Vessels Mpe 209 lec 9 Pressized Vessels
Mpe 209 lec 9 Pressized Vessels
 
Mpe 209 lec gear Design
Mpe 209 lec gear DesignMpe 209 lec gear Design
Mpe 209 lec gear Design
 
Mpe 209 lec 11 springs
Mpe 209 lec 11 springs Mpe 209 lec 11 springs
Mpe 209 lec 11 springs
 

Recently uploaded

CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECTCHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
jpsjournal1
 
Textile Chemical Processing and Dyeing.pdf
Textile Chemical Processing and Dyeing.pdfTextile Chemical Processing and Dyeing.pdf
Textile Chemical Processing and Dyeing.pdf
NazakatAliKhoso2
 
2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf
2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf
2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf
Yasser Mahgoub
 
Properties Railway Sleepers and Test.pptx
Properties Railway Sleepers and Test.pptxProperties Railway Sleepers and Test.pptx
Properties Railway Sleepers and Test.pptx
MDSABBIROJJAMANPAYEL
 
TIME DIVISION MULTIPLEXING TECHNIQUE FOR COMMUNICATION SYSTEM
TIME DIVISION MULTIPLEXING TECHNIQUE FOR COMMUNICATION SYSTEMTIME DIVISION MULTIPLEXING TECHNIQUE FOR COMMUNICATION SYSTEM
TIME DIVISION MULTIPLEXING TECHNIQUE FOR COMMUNICATION SYSTEM
HODECEDSIET
 
Computational Engineering IITH Presentation
Computational Engineering IITH PresentationComputational Engineering IITH Presentation
Computational Engineering IITH Presentation
co23btech11018
 
ISPM 15 Heat Treated Wood Stamps and why your shipping must have one
ISPM 15 Heat Treated Wood Stamps and why your shipping must have oneISPM 15 Heat Treated Wood Stamps and why your shipping must have one
ISPM 15 Heat Treated Wood Stamps and why your shipping must have one
Las Vegas Warehouse
 
spirit beverages ppt without graphics.pptx
spirit beverages ppt without graphics.pptxspirit beverages ppt without graphics.pptx
spirit beverages ppt without graphics.pptx
Madan Karki
 
Optimizing Gradle Builds - Gradle DPE Tour Berlin 2024
Optimizing Gradle Builds - Gradle DPE Tour Berlin 2024Optimizing Gradle Builds - Gradle DPE Tour Berlin 2024
Optimizing Gradle Builds - Gradle DPE Tour Berlin 2024
Sinan KOZAK
 
Eric Nizeyimana's document 2006 from gicumbi to ttc nyamata handball play
Eric Nizeyimana's document 2006 from gicumbi to ttc nyamata handball playEric Nizeyimana's document 2006 from gicumbi to ttc nyamata handball play
Eric Nizeyimana's document 2006 from gicumbi to ttc nyamata handball play
enizeyimana36
 
Understanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine LearningUnderstanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine Learning
SUTEJAS
 
A review on techniques and modelling methodologies used for checking electrom...
A review on techniques and modelling methodologies used for checking electrom...A review on techniques and modelling methodologies used for checking electrom...
A review on techniques and modelling methodologies used for checking electrom...
nooriasukmaningtyas
 
Recycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part IIIRecycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part III
Aditya Rajan Patra
 
The Python for beginners. This is an advance computer language.
The Python for beginners. This is an advance computer language.The Python for beginners. This is an advance computer language.
The Python for beginners. This is an advance computer language.
sachin chaurasia
 
22CYT12-Unit-V-E Waste and its Management.ppt
22CYT12-Unit-V-E Waste and its Management.ppt22CYT12-Unit-V-E Waste and its Management.ppt
22CYT12-Unit-V-E Waste and its Management.ppt
KrishnaveniKrishnara1
 
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdfBPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
MIGUELANGEL966976
 
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
IJECEIAES
 
New techniques for characterising damage in rock slopes.pdf
New techniques for characterising damage in rock slopes.pdfNew techniques for characterising damage in rock slopes.pdf
New techniques for characterising damage in rock slopes.pdf
wisnuprabawa3
 
学校原版美国波士顿大学毕业证学历学位证书原版一模一样
学校原版美国波士顿大学毕业证学历学位证书原版一模一样学校原版美国波士顿大学毕业证学历学位证书原版一模一样
学校原版美国波士顿大学毕业证学历学位证书原版一模一样
171ticu
 
International Conference on NLP, Artificial Intelligence, Machine Learning an...
International Conference on NLP, Artificial Intelligence, Machine Learning an...International Conference on NLP, Artificial Intelligence, Machine Learning an...
International Conference on NLP, Artificial Intelligence, Machine Learning an...
gerogepatton
 

Recently uploaded (20)

CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECTCHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
CHINA’S GEO-ECONOMIC OUTREACH IN CENTRAL ASIAN COUNTRIES AND FUTURE PROSPECT
 
Textile Chemical Processing and Dyeing.pdf
Textile Chemical Processing and Dyeing.pdfTextile Chemical Processing and Dyeing.pdf
Textile Chemical Processing and Dyeing.pdf
 
2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf
2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf
2008 BUILDING CONSTRUCTION Illustrated - Ching Chapter 02 The Building.pdf
 
Properties Railway Sleepers and Test.pptx
Properties Railway Sleepers and Test.pptxProperties Railway Sleepers and Test.pptx
Properties Railway Sleepers and Test.pptx
 
TIME DIVISION MULTIPLEXING TECHNIQUE FOR COMMUNICATION SYSTEM
TIME DIVISION MULTIPLEXING TECHNIQUE FOR COMMUNICATION SYSTEMTIME DIVISION MULTIPLEXING TECHNIQUE FOR COMMUNICATION SYSTEM
TIME DIVISION MULTIPLEXING TECHNIQUE FOR COMMUNICATION SYSTEM
 
Computational Engineering IITH Presentation
Computational Engineering IITH PresentationComputational Engineering IITH Presentation
Computational Engineering IITH Presentation
 
ISPM 15 Heat Treated Wood Stamps and why your shipping must have one
ISPM 15 Heat Treated Wood Stamps and why your shipping must have oneISPM 15 Heat Treated Wood Stamps and why your shipping must have one
ISPM 15 Heat Treated Wood Stamps and why your shipping must have one
 
spirit beverages ppt without graphics.pptx
spirit beverages ppt without graphics.pptxspirit beverages ppt without graphics.pptx
spirit beverages ppt without graphics.pptx
 
Optimizing Gradle Builds - Gradle DPE Tour Berlin 2024
Optimizing Gradle Builds - Gradle DPE Tour Berlin 2024Optimizing Gradle Builds - Gradle DPE Tour Berlin 2024
Optimizing Gradle Builds - Gradle DPE Tour Berlin 2024
 
Eric Nizeyimana's document 2006 from gicumbi to ttc nyamata handball play
Eric Nizeyimana's document 2006 from gicumbi to ttc nyamata handball playEric Nizeyimana's document 2006 from gicumbi to ttc nyamata handball play
Eric Nizeyimana's document 2006 from gicumbi to ttc nyamata handball play
 
Understanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine LearningUnderstanding Inductive Bias in Machine Learning
Understanding Inductive Bias in Machine Learning
 
A review on techniques and modelling methodologies used for checking electrom...
A review on techniques and modelling methodologies used for checking electrom...A review on techniques and modelling methodologies used for checking electrom...
A review on techniques and modelling methodologies used for checking electrom...
 
Recycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part IIIRecycled Concrete Aggregate in Construction Part III
Recycled Concrete Aggregate in Construction Part III
 
The Python for beginners. This is an advance computer language.
The Python for beginners. This is an advance computer language.The Python for beginners. This is an advance computer language.
The Python for beginners. This is an advance computer language.
 
22CYT12-Unit-V-E Waste and its Management.ppt
22CYT12-Unit-V-E Waste and its Management.ppt22CYT12-Unit-V-E Waste and its Management.ppt
22CYT12-Unit-V-E Waste and its Management.ppt
 
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdfBPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
BPV-GUI-01-Guide-for-ASME-Review-Teams-(General)-10-10-2023.pdf
 
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
Redefining brain tumor segmentation: a cutting-edge convolutional neural netw...
 
New techniques for characterising damage in rock slopes.pdf
New techniques for characterising damage in rock slopes.pdfNew techniques for characterising damage in rock slopes.pdf
New techniques for characterising damage in rock slopes.pdf
 
学校原版美国波士顿大学毕业证学历学位证书原版一模一样
学校原版美国波士顿大学毕业证学历学位证书原版一模一样学校原版美国波士顿大学毕业证学历学位证书原版一模一样
学校原版美国波士顿大学毕业证学历学位证书原版一模一样
 
International Conference on NLP, Artificial Intelligence, Machine Learning an...
International Conference on NLP, Artificial Intelligence, Machine Learning an...International Conference on NLP, Artificial Intelligence, Machine Learning an...
International Conference on NLP, Artificial Intelligence, Machine Learning an...
 

Project Management Day 5 Risk R02.pdf

  • 1. Dr Mohamed Elfarran Project Management Day (5)
  • 2. Dr Mohamed Elfarran Course Outline Day 1: Introduction + Project Integration Management. Day 2: Project Scope Management. Day 3: Project Schedule Management. Day 4: Project Cost Management. Day 5: Project Risk Management. Day 6: Scrum. Day 7: Final Presentation Day!
  • 3. Dr Mohamed Elfarran Project Risk Management Rev.221102 3
  • 4. Dr Mohamed Elfarran The Importance of Project Risk Management Project risk management is the art and science of identifying, analyzing, and responding to risk throughout the life of a project and in the best interests of meeting project objectives 5 Information Technology
  • 5. Dr Mohamed Elfarran Project Risk Management Project Risk Management includes the process of conducting risk management plan, identification, analysis, response planning, response implementation, and monitoring risk on the project. The objectives of project risk management: ○ Increase the probability and/or impact of positive (opportunities) risks and decrease the probability and/or impact of negative risks (threats), in order to optimize the chance of Project success. 6 Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project Management Institute, Inc., 2017, Page 395.
  • 6. Dr Mohamed Elfarran Project Risk Management 7
  • 7. Dr Mohamed Elfarran Integrating Risk with other project management functions 8 Project Risk Scope Communication Time Procurement Quality Recourses Cost Integration Life cycle Enviro. Variables Cost Objectives Availability Productivity Requirements Standards Time Objectives Services Performance Expectation Data Exchange Accuracy
  • 8. Dr Mohamed Elfarran Risk ● An uncertain event or condition that, if it occurs, has a Positive or Negative effect on a project objective. ○ The severity of any risk can be defined in terms of two quantities: ■ Likelihood: The extent to which the risk effects are likely to occur. ■ Impact (Consequence): The effect that a risk will have on the project if it occurs. 9
  • 10. Dr Mohamed Elfarran Risk Levels Risk exists at two levels within every project. Each project contains individual risks that can affect the achievement of project objectives. It is also important to consider the riskiness of the overall project, which arises from the combination of individual project risks and other sources of uncertainty. ○ Individual Project Risk ○ Overall Project Risk 11
  • 11. Dr Mohamed Elfarran Risk Levels ● Individual Project Risk ○ Is an uncertain event or condition that, if it occurs, has a Positive or Negative effect on one or more a project objective. ● Overall Project Risk ○ Is the effect of uncertainty on the project as a whole, arising from all sources of uncertainty including individual risks, representing the exposure of stakeholders to the implications of variations in project outcome, both positive and negative. 12
  • 12. Dr Mohamed Elfarran Negative Risk ● A dictionary definition of risk is “the possibility of loss or injury” ● Negative risk involves understanding potential problems that might occur in the project and how they might impede project success 13 Information Technology Negative risk Positive risk
  • 13. Dr Mohamed Elfarran Risk Can Be Positive ● Positive risks are risks that result in good things happening; sometimes called opportunities ● A general definition of project risk is an uncertainty that can have a negative or positive effect on meeting project objectives ● The goal of project risk management is to minimize potential negative risks while maximizing potential positive risks 14 Information Technology
  • 14. Dr Mohamed Elfarran Trends and emerging practices ● Project resilience (Flexibility) ○ Right level of budget and schedule contingency ○ Flexible project process ○ Empowered project team that has clear objective ○ Frequent review of early warning sign ○ Clear input from stakeholders ○ Integrated risk management ○ Program and portfolio 15
  • 15. Dr Mohamed Elfarran Plan Risk Management Rev.221102 16
  • 16. Dr Mohamed Elfarran 17 Rev.221102
  • 17. Dr Mohamed Elfarran Plan Risk Management Plan Risk Management is the process of defining how to conduct risk management activities for the project. The key benefit of this process is that it ensures that the degree, type, and visibility of risk management are proportionate to both risks and the importance of the project to the organization and other stakeholders. 18 Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project Management Institute, Inc., 2017, Page 401.
  • 18. Dr Mohamed Elfarran Plan Risk Management, Outputs ● Risk Management Plan Describes how risk management activities will be structured and performed, and it may include the following elements: ■ Risk strategy Describes the general approached to mange the risk ■ Methodology Defines the specific approaches, tools, and data sources that will be used to perform risk management on the project. 19
  • 19. Dr Mohamed Elfarran Plan Risk Management, Outputs ■ Roles & Responsibilities Defines the lead, support, and risk management team member for each type of activities described in the risk management plan, and clarifies their responsibility. ■ Funding Identifies the funds needed to perform activities related to the project risk management. Establishes protocols for the application of contingency and management reserves. 20
  • 20. Dr Mohamed Elfarran Plan Risk Management, Outputs ■ Timing Defines when and how often the risk management process will be performed throughout the project life cycle ■ Risk categories Provides a means for grouping individual project risk. A common way to structure risk categories is a risk breakdown structure (RBS) 21
  • 21. Dr Mohamed Elfarran Plan Risk Management, Outputs ◼ Risk categories Risks that may affect the project for better or worse can be identified and organized into categories 22 Macro Financial Political Market Environment Target Managerial Project Job Site Procurement Design Act of God Social Technical Funding Control Team Contractual
  • 22. Dr Mohamed Elfarran Identify Risk Rev.221102 23
  • 23. Dr Mohamed Elfarran Identify Risk Identify Risk Is The Process of identifying individual project risks as well as sources of overall project risk, and documenting their characteristics. The key benefit of this process is the documentation of existing individual project risks and the sources of overall project risk. It also bring information so the project team can appropriately to identified risk. 24 Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project Management Institute, Inc., 2017, Page 409.
  • 24. Dr Mohamed Elfarran Identify Risk ● Risk is doing business 25 External Environment project Organization Environment Significant Factors Location of the site Client Wars
  • 25. Dr Mohamed Elfarran Identify Risk, Tools & Tech ● Brainstorming is a technique by which a group attempts to generate ideas or find a solution for a specific problem by amassing ideas spontaneously and without judgment ● An experienced facilitator should run the brainstorming session ● Be careful not to overuse or misuse brainstorming. ○ Psychology literature shows that individuals produce a greater number of ideas working alone than they do through brainstorming in small, face-to-face groups ○ Group effects often inhibit idea generation 26 Information Technology
  • 26. Dr Mohamed Elfarran Risk Breakdown Structure ● A risk breakdown structure is a hierarchy of potential risk categories for a project ● Similar to a work breakdown structure but used to identify and categorize risks 27
  • 27. Dr Mohamed Elfarran Figure 11-4. Sample Risk Breakdown Structure 28 Information Technology Project Management, Sixth Edition
  • 28. Dr Mohamed Elfarran Figure 11-4. Sample Risk Breakdown Structure 29 Information Technology Project Management, Sixth Edition
  • 29. Dr Mohamed Elfarran Table 11-4. Potential Negative Risk Conditions Associated with Each Knowledge Area 30
  • 30. Dr Mohamed Elfarran Identify Risk, Tools & Tech. SWOT Analysis ○ This technique examines the project from each of the strengths, weaknesses, opportunities, and threats. 31
  • 31. Dr Mohamed Elfarran Identify Risk, Tools & Tech. ● Delphi Technique ○ The Delphi Technique is used to derive a consensus among a panel of experts who make predictions about future developments ○ Provides independent and anonymous input regarding future events ○ Uses repeated rounds of questioning and written responses and avoids the biasing effects possible in oral methods, such as brainstorming 32
  • 32. Dr Mohamed Elfarran Identify Risk, Tools & Tech. ● Prompt Risk ○ A prompt risk is a predetermined list of risk that might give rise to individual risk and that could also act as sources of overall risk. The risk categories in the lowest level of the risk breakdown structure can be used as a prompt list for individual project risk. ● Meetings ○ Often call a risk workshop 33
  • 33. Dr Mohamed Elfarran Identify Risk, Output 34 ● The main output of the risk identification process is a list of identified risks and other information needed to begin creating a risk register ● A risk register is: ○ A document that contains the results of various risk management processes and that is often displayed in a table or spreadsheet format ○ A tool for documenting potential risk events and related information ● Risk events refer to specific, uncertain events that may occur to the detriment or enhancement of the project
  • 34. Dr Mohamed Elfarran Risk Register Contents ● An identification number for each risk event ● A rank for each risk event ● The name of each risk event ● A description of each risk event ● The category under which each risk event falls ● The root cause of each risk ● Triggers for each risk; triggers are indicators or symptoms of actual risk events ● Potential responses to each risk ● The risk owner or person who will own or take responsibility for each risk ● The probability and impact of each risk occurring. ● The status of each risk 35 Information Technology
  • 35. Dr Mohamed Elfarran Table 11-5. Sample Risk Register 36 Information Technology Project Management, Seventh Edition • No.: R44 • Rank: 1 • Risk: New customer • Description: We have never done a project for this organization before and don’t know too much about them. One of our company’s strengths is building good customer relationships, which often leads to further projects with that customer. We might have trouble working with this customer because they are new to us. • Category: People risk • Etc.
  • 36. Dr Mohamed Elfarran Identify Risk, Output 37
  • 37. Dr Mohamed Elfarran ● Risk Breakdown Structure ● Build Your Risk Registers 38 Dr Mohamed Elfarran
  • 38. Dr Mohamed Elfarran Risk Analysis Rev.221102 39
  • 39. Dr Mohamed Elfarran Perform Qualitative Risk Analysis Perform Qualitative Risk Analysis Is the process of prioritizing individual project risk for further analysis or actions by assessing the probability of occurrence and impact and as well as other characteristics. The key benefit of this process is that it focuses efforts on high priority risks. 40 Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project Management Institute, Inc., 2017, Page 419.
  • 40. Dr Mohamed Elfarran Plotting Risk Events on the Matrix Risk Probability Risk Impact L M H L H M
  • 41. Dr Mohamed Elfarran Output ● Top Ten Risk Item Tracking is a qualitative risk analysis tool that helps to identify risks and maintain an awareness of risks throughout the life of a project ● Establish a periodic review of the top ten project risk items ● List the current ranking, previous ranking, number of times the risk appears on the list over a period of time, and a summary of progress made in resolving the risk item 42 Information Technology
  • 42. Dr Mohamed Elfarran Table 11-6. Example of Top Ten Risk Item Tracking 43 Information Technology
  • 43. Dr Mohamed Elfarran Output ● A watch list is a list of risks that are low priority, but are still identified as potential risks ● Qualitative analysis can also identify risks that should be evaluated on a quantitative basis 44 Information Technology
  • 44. Dr Mohamed Elfarran Perform Quantitative Risk Analysis Perform Quantitative Risk Analysis is the process of numerically analyzing the combined effect of identified individual project risks and other sources of uncertainty on overall project objective. The key benefit of this process is that it quantifies overall project risk exposure, and it can also provide additional quantitative risk information to support risk response planning. 45 Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project Management Institute, Inc., 2017, Page 428.
  • 45. Dr Mohamed Elfarran Perform Quantitative Risk Analysis This Process used technique such as Monte Carlo Simulation and Decision Tree Analysis to: ○ Quantify the possible outcomes for the project and their probabilities. ○ Assess the probability of achieving specific project objectives. ○ Identify risks requiring the most attention by quantifying their relative contribution to overall project risk. ○ Identify realistic and achievable cost, schedule or scope targets, given the project risks. ○ Determine the best project management decision when some conditions or outcomes are uncertain. 46
  • 46. Dr Mohamed Elfarran Quantitative Risk Analysis  Probability and Impact Matrix 47
  • 47. Dr Mohamed Elfarran Quantitative Risk Analysis  Probability and Impact Matrix 48
  • 48. Dr Mohamed Elfarran Perform Quantitative Risk Analysis, Tools & Tech. ● Decision Tree Analysis 49
  • 49. Dr Mohamed Elfarran Perform Quantitative Risk Analysis, Tools & Tech. ● Expected Monetary Value (EMV) ● Expected Payoff for good market = 80,000*0.15 + 50,000*0.45 = LE 34,500 ● Expected Payoff for good quality = 80,000*0.15 + 20,000*0.25 = LE 17,000 ● EMV = 80,000*0.15 + 50,000*0.45 +20,000*0.25 + (-20,000)*0.15 = LE 36,500 50 Probability % Payoff Status 15 80,000 Good Market – Good Quality 45 50,000 Good Market – Poor Quality 25 20,000 Poor Market – Good Quality 15 -20,000 Poor Market – Poor Quality
  • 50. Dr Mohamed Elfarran Perform Quantitative Risk Analysis, Tools & Tech. ● Simulation uses a representation or model of a system to analyze the expected behavior or performance of the system ● Monte Carlo analysis simulates a model’s outcome many times to provide a statistical distribution of the calculated results ● To use a Monte Carlo simulation, you must have three estimates (most likely, pessimistic, and optimistic) plus an estimate of the likelihood of the estimate being between the most likely and optimistic values 51 Information Technology
  • 51. Dr Mohamed Elfarran Perform Quantitative Risk Analysis Monte Carlo Simulation 52
  • 52. Dr Mohamed Elfarran Perform Quantitative Risk Analysis, Tools & Tech. ● Sensitivity analysis is a technique used to show the effects of changing one or more variables on an outcome ● For example, many people use it to determine what the monthly payments for a loan will be given different interest rates or periods of the loan, or for determining break-even points based on different assumptions ● Spreadsheet software, such as Excel, is a common tool for performing sensitivity analysis 53 Information Technology
  • 53. Dr Mohamed Elfarran Perform Quantitative Risk Analysis, Tools & Tech. ● Sensitivity Analysis ■ Helps to determine which individual project risks or other sources of uncertainty have the most potential impact on the project outcomes ■ Involve making all risk variables at their baseline and study impact on the project objectives when on variable is changed 54
  • 54. Dr Mohamed Elfarran Perform Quantitative Risk Analysis, Tools & Tech. ● Sensitivity Analysis 55
  • 55. Dr Mohamed Elfarran ● Qualitative Risk Analysis ● Quantitative Risk Analysis 56 Dr Mohamed Elfarran
  • 56. Dr Mohamed Elfarran Plan Risk Responses 57 Rev.221102
  • 57. Dr Mohamed Elfarran Plan Risk Responses The process of developing options selecting strategies, and agreeing on actions to address overall project risk exposure, as well as to treat individual project risk. The key benefit of this process is that it identifies appropriate way to address overall project risk and individual project risk. 58 Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project Management Institute, Inc., 2017, Page 437.
  • 58. Dr Mohamed Elfarran Plan Risk Responses ● Risk response should be: ○ Appropriate to the significance of the risk ○ Cost effective in meeting the challenge ○ Realistic within the project context ○ Agreed upon by all parties involved ○ Owned by a responsible person 59
  • 59. Dr Mohamed Elfarran Plan Risk Responses 60 Information Technology
  • 60. Dr Mohamed Elfarran Plan Risk Responses, Tools & Tech. ● Strategies for Threats ○ Avoid ○ Transfer ○ Mitigate ○ Accept ○ Escalate 61 ● Strategies for Opportunities ○ Exploit ○ Enhance ○ Share ○ Accept ○ Escalate
  • 61. Dr Mohamed Elfarran Plan Risk Responses, Tools & Tech. ● Strategies for Overall Project Risk ○ Avoid ○ Exploit ○ Transfer/Share ○ Mitigate/Enhance ○ Accept 62
  • 62. Dr Mohamed Elfarran Risk Response Strategies Mitigation (Corrective action) Avoidance (Prevention) Acceptance (Accept consequences) Transference (Shift Responsibility)
  • 63. Dr Mohamed Elfarran Plan Risk Responses ● Residual Risk The risks that remain after risk responses have been implemented. ● Secondary Risk The risks that arise as a direct result of implementing a risk response. 64
  • 64. Dr Mohamed Elfarran Implement Risk Responses 65 Rev.221102
  • 65. Dr Mohamed Elfarran Implement Risk Responses Implement Risk Responses is the process of implementing agreed upon risk response plans. The key benefit of this process is that it ensures that the agreed upon risk responses are executed as planned in order to address overall project risk exposure, minimize individual project threats, and maximize individual project opportunities. 66 Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project Management Institute, Inc., 2017, Page 449.
  • 66. Dr Mohamed Elfarran Monitor Risk 67 Rev.221102
  • 67. Dr Mohamed Elfarran Monitor Risk Monitor risk is the process of monitoring the implementation of agreed upon response plan, tracking identified risks, identifying and analyzing new risks, and evaluating risk process effectiveness throughout the project. The key benefit of this process is that it enable project decisions to be based on current information about overall project risk exposure and individual project risk. 68 *This definition is taken from the Glossary of the Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project Management Institute, Inc., 2017.
  • 68. Dr Mohamed Elfarran Monitor Risk The Monitor Risk processes uses performance information generated during project execution to determine if: ○ Implemented risk responses are effective ○ Level of overall project risk has changed ○ Status of identified individual project risk has changes ○ New individual project risk have arisen ○ Risk management approach is still appropriate 69
  • 69. Dr Mohamed Elfarran Monitor Risk ○ Project assumptions are still valid ○ Risk management policies and procedures are being followed ○ Contingency reserves for cost or schedule require modified ○ Project strategy is still valid 70
  • 70. Dr Mohamed Elfarran Risk Assessment 71 ID Event % EGP Plan % EGP Risk Value 1 2 3 4 5 ‫التصاريح‬ ‫تأخر‬ ‫أسبوعين‬ ‫أسبوع‬ ‫التصميم‬ ‫تأخر‬ ‫العمالت‬ ‫سعر‬ ‫تغير‬ ‫بنسبة‬ 10 % ‫ئن‬ْ‫ا‬‫الزب‬ ‫عدد‬ ‫قلة‬ ‫بنسبة‬ 50 % ‫في‬ ‫التيار‬ ‫انقطاع‬ ‫االفتتاح‬ 40 50 60 30 50 ‫المتوقع‬ ‫الربح‬ 70 ‫األسبوع‬ ‫في‬ ‫مصرى‬ ‫جنية‬ ‫ألف‬ ‫المستوردة‬ ‫التوريدات‬ 10 ‫دوالر‬ ‫ألف‬ 10 20 60 10 140,000 70,000 1,000$ 35,000 210,000 40,000 20,000 $ 1,000 15,000 4,000 4,000 600$ 1,500 ‫محامى‬ ‫مع‬ ‫التعاقد‬ ‫التكلفة‬ 5 ‫جنية‬ ‫الف‬ ( ‫تخفيف‬ ) ‫استشاري‬ ‫مكتب‬ ‫مع‬ ‫التعاقد‬ ‫التكلفة‬ 10 ‫جنية‬ ‫الف‬ ( ‫تخفيف‬ ) ‫قبول‬ ‫بتكلفة‬ ‫بالدعاية‬ ‫االهتمام‬ 2,000 ‫جنية‬ ‫بتكلفة‬ ‫كهرباء‬ ‫مولد‬ ‫تأجير‬ 5,000 ‫جنية‬ ( ‫تفادي‬ )